Professional Documents
Culture Documents
Risk Assessment - Pull Out Test
Risk Assessment - Pull Out Test
05 2023 Rev 00
Main Contractor:
PROJECT: EXIT 10 – AL HAMRA DEVELOPMENT PROJECT, RIYADH
Shapoorji Pallonji Mideast
LLC
Page 1 of 12
RISK ASSESSMENT FOR Pull out test for Drop In Anchors Date: 02.05 2023 Rev 00
Main Contractor:
PROJECT: EXIT 10 – AL HAMRA DEVELOPMENT PROJECT, RIYADH
Shapoorji Pallonji Mideast
LLC
RISK MATRIX
Page 2 of 12
RISK ASSESSMENT FOR Pull out test for Drop In Anchors Date: 02.05 2023 Rev 00
Main Contractor:
PROJECT: EXIT 10 – AL HAMRA DEVELOPMENT PROJECT, RIYADH
Shapoorji Pallonji Mideast
LLC
Steps Activity Hazards Who Risk Description Risk Risk Control Measures Risk Who is
might be Ranking Ranking Responsible
harmed
L C R L C R
1 Mobilization Vehicular Site Collision of vehicles, 3 5 15 Driver must have valid heavy vehicle 1 5 5 Security personnel,
of: Movement Workers, hit/run-over the site driving license. Logistic
Visitors workers, visitors or Vehicle must have the valid registration, supervisor,
Power tools and Driver structure. insurance and periodic inspection Site Supervisor,
Store Keeper
(Drill certificate.
machine & Vehicle must be equipped with horn,
Pull out test reverse alarm, head light and indicators
Apparatus). etc.
Site Speed Limit to be followed by
Personal Injury,
Hand Tools driver.
Fatality,
(Hacksaw
Property Damage.
Banksman to be deployed with each
Frames and heavy vehicle to guide the driver.
Spanner, Hi-Vi Vest must be worn.
Grip plier & Flash light to be used in night shift.
Hammer). Adequate illumination to be ensured
during night shift.
Designated pedestrian access to be
Subcontracto provided and usage of the same to be
r team ensured.
Un-calibrated/ Site Risk of injury due to 3 3 9 Ensure tools and equipment are tested by 1 3 3 Store Keeper,
Sub-standard/ Workers, use of unsafe, competent person prior to engaging in Site Engineer,
damaged tools Visitors sub-standard, operation and be assured of good Site Foreman.
and equipment damaged tools and condition.
equipment All tools must be properly checked,
inspected and tagged (color-coded)
before issuing to site.
Personal Injury Unsafe, sub-standard, damaged tools
Page 3 of 12
RISK ASSESSMENT FOR Pull out test for Drop In Anchors Date: 02.05 2023 Rev 00
Main Contractor:
PROJECT: EXIT 10 – AL HAMRA DEVELOPMENT PROJECT, RIYADH
Shapoorji Pallonji Mideast
LLC
Obstructed Involved Scattered items in the 2 3 6 Make sure the aisles are free from 1 3 3 Site Engineer
aisles crew and aisles may cause obstruction.
Visitors workers to trip and fall. Good housekeeping practice to be strictly Site Supervisor
Personal injuries.
followed.
Store keeper
Do not leave any material unattended in the
Page 4 of 12
RISK ASSESSMENT FOR Pull out test for Drop In Anchors Date: 02.05 2023 Rev 00
Main Contractor:
PROJECT: EXIT 10 – AL HAMRA DEVELOPMENT PROJECT, RIYADH
Shapoorji Pallonji Mideast
LLC
aisles.
Materials shall be stored according to “First
In-First Out” (FIFO) basis.
Pest (termite and Materials Property loss 2 3 6 Schedule regular pest control inspections in 1 3 3 Store keeper
rodent) attack storage area to identify the entry points and
harborage area of rodents and termites. Logistic
coordinator
Periodic pest control treatments shall be
conducted in coordination with main
Procurement
contractor. Engineer
Keep the storage area dry and free from
moisture or stagnant water.
Maintain cleanliness and good housekeeping
practice in storage area.
Fire Workers Burn, 3 4 12 Do not allow any hot work activity near 1 4 4 Project Manager,
(Combustible Property damage storage area. Construction
materials) Ensure the firefighting system is installed in Manager,
Site engineer,
the storage area. Procurement dept.
Adequate number of suitable fire Store keeper.
extinguishers to be provided.
Training to be provided on Fire fighting.
Make sure monthly inspection of firefighting
equipment are performed by a competent
person.
Materials should not be placed in exit route.
Emergency contact numbers shall be
displayed in storage area.
Page 5 of 12
RISK ASSESSMENT FOR Pull out test for Drop In Anchors Date: 02.05 2023 Rev 00
Main Contractor:
PROJECT: EXIT 10 – AL HAMRA DEVELOPMENT PROJECT, RIYADH
Shapoorji Pallonji Mideast
LLC
3 Pre-testing Unsafe/Blocked Involved Slip, trip and fall 2 3 6 Site supervisor shall pre-check the testing 1 3 3 Site engineer
procedure of access and crew area.
pull out test egress Personal Injuries Safe access and egress shall be provided. Site supervisor
Visible exit and access sign boards to be
placed.
Do not keep any material or tools in the
access.
Access to be free from any obstruction.
Poor Involved Slip, trip and fall 2 3 6 Ensure adequate illumination is provided in 1 3 3 Site engineer
illumination crew, site working area.
worker, Personal Injuries Make sure emergency lights are available in Site supervisor
visitors case of power failure in enclosed areas.
Poor Involved Slip, trip and fall 2 3 6 Always maintain good housekeeping 1 3 3 Site engineer
housekeeping crew, site practice.
worker, Personal Injuries Make sure the access/egress is not blocked by Site supervisor
visitors materials or waste.
Always keep tools in tool box.
4 Use of Drilling Damaged Operative Electric shock 3 4 12 All power tools shall be inspected and 1 4 4 Site Engineer
Machine: tools/cables/plug colour coded.
s Operative and supervisor will inspect the Site Supervisor
To install the tools for any damage or defect.
Drop In Make sure periodic maintenance of tools
Anchor
is carried out.
Double insulated cables shall be used.
Damaged cables should be return to
store.
Cables should be hanged on S shaped
nonconductive hanger.
Page 6 of 12
RISK ASSESSMENT FOR Pull out test for Drop In Anchors Date: 02.05 2023 Rev 00
Main Contractor:
PROJECT: EXIT 10 – AL HAMRA DEVELOPMENT PROJECT, RIYADH
Shapoorji Pallonji Mideast
LLC
Dust (Minor)/ Operative Irritation in respiratory 2 3 6 PPE – Dust Mask according to standards 1 3 3 Site Engineer
tract to be worn by workers. Site Supervisor
Flying debris Operative, Eye injury 2 3 6 PPE-Wear suitable safety glass while 1 3 3 Site Engineer
workers using drilling machine. Site Supervisor
nearby
Hand-arm Operative Muscular sprain/strain 3 3 9 Use suitable low-vibration tools. 1 3 3 Site Engineer
vibration Check tools before use to make sure the
tools are properly maintained and Site Supervisor
repaired to avoid increased vibration
caused by faults.
Reduce the amount of time to use the tool
in one go.
Wear appropriate hand gloves.
Poor Operative, Headache, dizziness & 2 3 6 Ensure adequate illumination is provided in 1 3 3 Site Engineer
illumination & workers eye strain working area.
ventilation nearby & Make sure emergency lights are available in Site Supervisor
visitors case of power failure in enclosed areas.
Ensure proper ventilation system is installed
in the working area.
Slip, Trip and Operative Personal injuries 2 3 6 Maintain good housekeeping practice in 1 3 3 Site Engineer
Fall & workers the area.
nearby Keep the area free of any obstruction. Site Supervisor
Cables shall run in neatly manner and
hang on nonconductive hangers.
Keep all tools and materials in toolbox.
Page 7 of 12
RISK ASSESSMENT FOR Pull out test for Drop In Anchors Date: 02.05 2023 Rev 00
Main Contractor:
PROJECT: EXIT 10 – AL HAMRA DEVELOPMENT PROJECT, RIYADH
Shapoorji Pallonji Mideast
LLC
Page 8 of 12
RISK ASSESSMENT FOR Pull out test for Drop In Anchors Date: 02.05 2023 Rev 00
Main Contractor:
PROJECT: EXIT 10 – AL HAMRA DEVELOPMENT PROJECT, RIYADH
Shapoorji Pallonji Mideast
LLC
Anchors and visitors. Minor to major injuries with approved design. Scaffold inspector
performing the Scaffolding components should be of good
test quality.
Use of loose and weak planks should be
avoided.
Work Permit shall be obtained to carry out
the job.
Training on WORK AT HEIGHT shall be
provided to involved crew prior to start the
activity.
STARRT card shall be filled and
communicated to all involved personnel.
While erecting scaffold, red tag shall be
displayed on height equal to eye level.
Workers should use chin straps, leather
gloves and safety harness full time.
Area to be barricaded and sign boards to be
displayed.
Electrocution Involved Person may fall, 3 5 15 The supervision staff must ensure there is no 1 5 5 Site engineer
crew Serious injuries, overhead electrical services while working on Site supervisor
Fatality scaffold. Scaffold supervisor
Adequate distance shall be maintained
between scaffold structure and electrical
services.
Site coordination must be ensured with
electrical team.
Ensure the availability and correct use of
double lanyard full body safety harness.
Falling object Involved Bruise, Cut, Fracture 3 3 9 Tools and spanners shall be secured by using 1 3 3 Site engineer
crew and etc. tool tethering lanyard and shall be kept in Site supervisor
site toolbox when not in use. Scaffold supervisor
workers Area shall be barricaded (Hard/temporary)
and sign boards to be displayed.
Page 9 of 12
RISK ASSESSMENT FOR Pull out test for Drop In Anchors Date: 02.05 2023 Rev 00
Main Contractor:
PROJECT: EXIT 10 – AL HAMRA DEVELOPMENT PROJECT, RIYADH
Shapoorji Pallonji Mideast
LLC
Page 10 of 12
RISK ASSESSMENT FOR Pull out test for Drop In Anchors Date: 02.05 2023 Rev 00
Main Contractor:
PROJECT: EXIT 10 – AL HAMRA DEVELOPMENT PROJECT, RIYADH
Shapoorji Pallonji Mideast
LLC
Handling Operative, Personal injuries 2 3 6 Make sure the equipment is handled carefully
equipment above Nearby while testing.
shoulder height workers Wear appropriate hand gloves (if possible) to
for longer time. get a good grip on equipment.
Keep all visitors and site workers away from
testing area.
Do not work for longer time in one position.
Ensure the body posture is correct while
testing.
Barricade the area.
Slipping of Operative, Personal injuries 2 3 6 Check the condition of equipment prior 1 3 3 Site engineer
testing Nearby to use.
equipment while workers Equipment to be used only for the Site supervisor
using intended purpose.
Follow the manufacturer’s instructions
while using the equipment.
Ensure the parts of equipment are
properly fitted and is not loosen.
Flying particles Operative, Eye injury 2 3 6 Always wear eye protection (safety 1 3 3 Site engineer
Nearby goggles).
workers Keep nearby workers away from Site supervisor
working area.
8 Housekeeping Dust, Involved Respiratory problems 2 3 6 Use suitable brush for housekeeping. 1 3 3 Site engineer
of work- pieces of wires workers, Always watch your step. Site supervisor
related waste and rods workers Trip & fall Use appropriate PPEs (Dust mask, hand
nearby gloves & safety glass).
Personal injuries Dispose the collected waste in designated
skip bin as per site’s waste management
plan.
Other site related hazards
9 Interface Lack of Site Fall of objects/materials 3 3 9 Prior information to be given to affected 1 3 3 Site Engineer,
Page 11 of 12
RISK ASSESSMENT FOR Pull out test for Drop In Anchors Date: 02.05 2023 Rev 00
Main Contractor:
PROJECT: EXIT 10 – AL HAMRA DEVELOPMENT PROJECT, RIYADH
Shapoorji Pallonji Mideast
LLC
Page 12 of 12