Week No. 33
DAILY ACTIVITY REPORT Date Cut-In 14-Aug-23
14-Aug-23 22024 PM4 Stock Preparation Sewer Effluent 8:00 AM - 5:00 PM Start
15-Aug-23 22024 PM4 Stock Preparation Sewer Effluent - adjustment on route 8:00 AM - 5:00 PM Start
16-Aug-23 22024 PM4 Stock Preparation Updating drawings 8:00 AM - 5:00 PM Start
17-Aug-23 22024 PM4 Stock Preparation Updating drawings 8:00 AM - 5:00 PM Start
18-Aug-23 22024 PM4 Stock Preparation Foundation Civil Guide Layout 8:00 AM - 5:00 PM Start
19-Aug-23 22024 PM4 Stock Preparation Foundation Civil Guide Layout 8:00 AM - 5:00 PM Start