SAIC NUMBER ISSUE DATE DISCIPLINE


SAUDI ARAMCO INSPECTION CHECKLIST
BELOW-THE HOOK LIFTING EQUIPMENT
SAIC-U-7002 1-Jan-23 ELEVATING/LIFTING EQUIPMENT
(LIFTING/SPREADER BEAMS)
PROJECT TITLE WBS/BI/JO NUMBER INSPECTION COMPANY

EQUIPMENT ID NUMBER EQUIPMENT DESCRIPTION/TYPE SERIAL NO. REPORT No.:

CAPACITY (SWL) MANUFACTURER FACILITY / LOCATION

REQUESTED INSPECTION DATE RFI No. TASK COMPLETED DATE EQUIPMENT OWNER

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A Remark
No.

1 GENERAL REQUIREMENTS

SAES-B067
1.1 The elevating/lifting equipment is painted safety yellow
Sec:4.4

The elevating/lifting equipment is painted safety yellow-and-black stripes SAES-B067


1.2
on offshore facilities Sec:4.4

Rated capacity of the elevating/lifting equipment is marked (Arabic & SAES-B067


1.3
English) Sec:4.4

A sign is posted warning the operator not to rely solely on any automatic G.I. 7.030
1.4
device as a substitute for safe operating practice Para: 5.6.2

2 STRUCTURAL AND MECHANICAL LIFTING DEVICES

ASME B30.20
2.1 Equipment documentation is available
Sec: 20-1.5

ASME B30.20
2.2 Previous inspection reports are checked
Sec: 20-1.3.6

G.I.7.030
2.3 Preventive Maintenance is established and dated records are maintained
Para: 5.5.2

ASME B30.20
2.4 Rated load is marked on the main structure or tagged
Sec: 20-1.2.1.b.6

Lifting device has marking/tagging of manufacturer name, address, serial ASME B30.20
2.5
no., lifter weight Sec: 20-1.2.1(B)

ASME B30.20
2.6 Values of cold current and rated voltage (when applicable) are correct
Sec: 20-1.2.1.b.5

ASME B30.20
2.7 Product safety labels are attached and legible
Sec: 20-1.2.1(d)

ASME B30.20
2.8 All welds are not showing cracks or corrosion Sec: 20-6.3.7
(m-1)

ASME B30.20
2.9 Guards for moving parts are fitted where required
Sec: 20-1.2.2 (b)

External power supply, electrical equipment and wiring is in place and ASME B30.20
2.10
undamaged (when applicable ) Sec:20-2.2.2

Saudi Aramco: Company General Use Saudi Aramco: Company General Use
#
#

SAIC NUMBER ISSUE DATE DISCIPLINE


SAUDI ARAMCO INSPECTION CHECKLIST
BELOW-THE HOOK LIFTING EQUIPMENT
SAIC-U-7002 1-Jan-23 ELEVATING/LIFTING EQUIPMENT
(LIFTING/SPREADER BEAMS)
PROJECT TITLE WBS/BI/JO NUMBER INSPECTION COMPANY

EQUIPMENT ID NUMBER EQUIPMENT DESCRIPTION/TYPE SERIAL NO. REPORT No.:

CAPACITY (SWL) MANUFACTURER FACILITY / LOCATION

REQUESTED INSPECTION DATE RFI No. TASK COMPLETED DATE EQUIPMENT OWNER

ASME B30.20
2.11 Surface of load is not covered in debris (where applicable )
Sec: 20-1.3.2 (a)

ASME B30.20
2.12 Condition and operation of the controls are correct and functioning well
Sec:20-1.3.2(b)

Condition and operation of the indicators and meters are correct and ASME B30.20
2.13
functioning well (where applicable) Sec:20-1.3.2(c)

ASME B30.20
2.14 Structural members are not deformed, cracked or excessively worn
Sec:20-2.3.3(a)

ASME B30.20
2.15 There are no loose or missing guards, bolts and fasteners
Sec: 20-1.3.3(b)

ASME B30.20
2.16 Covers, stops or nameplates are not missing
Sec: 20-1.3.3(b)

ASME B30.20
2.17 Verify operation of mechanisms (where applicable )
Sec: 20-1.3.3 (c)

Automatic hold-and-release mechanisms are adjusted and not interfering ASME B30.20
2.18
with operation (where appropriate ) Sec: 20-1.3.3 (c)

ASME B30.20
2.19 Gears, pulleys and sheaves are not cracked or worn
Table 20-1.3.3-1

ASME B30.20
2.20 Sprockets, bearings, chains or belts are no cracked or worn
Table 20-1.3.3-1

ASME B30.20
2.21 Linkages and other mechanical parts do not have excessive wear
Table 20-1.3.3-1

Hoist hooking points and load support clevises or pins do not have ASME B30.20
2.22
excessive wear Table 20-1.3.3-1

REMARKS:

REFERENCE DOCUMENTS:
1- ASME B30.20 - 2021 Issue: Below-the-Hook Lifting Devices
2- SAES-B067 - 2020 Issue: Safety Identification and Safety Colors
3- SA GI 7.030 - 2023 Issue: Inspection and Testing Requirements for Elevating/Lifting Equipment

Load Tested By (If Applicable):


Name, Signature, & Date:

Saudi Aramco: Company General Use Saudi Aramco: Company General Use
#
#

SAIC NUMBER ISSUE DATE DISCIPLINE


SAUDI ARAMCO INSPECTION CHECKLIST
BELOW-THE HOOK LIFTING EQUIPMENT
SAIC-U-7002 1-Jan-23 ELEVATING/LIFTING EQUIPMENT
(LIFTING/SPREADER BEAMS)
PROJECT TITLE WBS/BI/JO NUMBER INSPECTION COMPANY

EQUIPMENT ID NUMBER EQUIPMENT DESCRIPTION/TYPE SERIAL NO. REPORT No.:

CAPACITY (SWL) MANUFACTURER FACILITY / LOCATION

REQUESTED INSPECTION DATE RFI No. TASK COMPLETED DATE EQUIPMENT OWNER

□ Inspected □ Witnessed by 3rd Party Certified Inspector:


Name, Signature, Certificate No. & Company:

User Representative:
Name, Signature, & Date: