A. API 510.
B. API RP 581.
C. API RP 584.
D. API RP 580.
Question: Details related to NDE of welds that should be reviewed by the Inspector include:
Question: What will provide the safety relief valve with stable lifting characteristics on either compressible
or incompressible media?
A. Car Seal
B. Vented Bonnet
C. Lift Lever
D. Trim
Question: What type of relief device uses a weight or compressed spring to hold the valve seat closed
below the set pressure or vacuum setting of the device?
Question: Pressure test pressure, duration and procedures used should be in accordance with the applicable
construction code requirements and applicable procedures of the:
A. Local jurisdiction.
B. Owner/User.
C. Vessel manufacturer.
D. Inspection agent.
A. Lift lever.
B. Trim.
C. Car Seal.
D. Bellows.
Question: External inspection intervals for vessels in non-continuous service are the same as continuous
service vessels because:
Question: The criteria that constitutes an “as-received” pop test failure is defined as:
A. A facilitator owner-user.
B. Testing contractor.
C. Pressure vessel inspector.
D. Relief device manufacturer.
Question: A competent person who has met the knowledge, skill requirements and expectations of the
owner/user is defined as:
A. A qualified person.
B. An inspector.
C. A certified person.
D. The owner/user’s representative.
Question: Inspection tasks typically associated with hot tapping or welding on in-service equipment should
include:
A. Process solids.
B. Poor seat lapping.
C. Improper blowdown ring setting.
D. Pitting on the valve body.
Question: Prior to weld repairs of a pressure vessel in caustic service, a review of the details of the welding
plan to ensure suitability for service should be performed by a:
A. Material engineer.
B. Authorized inspector.
C. Welding engineer.
D. Corrosion specialist.
Question: Pressure-relief valves in fouling service that have lifted while in service:
A. A response or evidence resulting from the application of a NDE that could be flaws or defects upon
further analysis.
B. An imperfection whose type or size, exceeds the applicable acceptance criteria and is therefore
rejectable.
C. Service conditions that may produce fatigue due to cyclic loading from pressure, thermal, and
mechanical loads.
D. Any type of deterioration that can result in flaws/defects that can affect the integrity of vessels.
Question: An assembly installed in the space between a rupture disk and another relief device to detect or
prevent the accumulation of pressure between the rupture disk and the other device is a:
A. Pin-actuated device.
B. Lifting lever.
C. Telltale indicator.
D. Car seal.
Question: Rupture disks that become dented or otherwise damaged during installation or handling may:
Question: The next planned inspection of a pressure vessel shall include all CMLs that have which of the
following corrosion rate and remaining life descriptions?
Page 4 of 6
API-510 Recertification Quiz - Questions and Answers (2020)
Question: Any repair welding should be performed according to a procedure accepted by the:
A. Inspection agency.
B. Owner/user.
B. Repair organization.
D. Inspector or engineer.
Question: Are non-integrally bonded metallic liners are counted as part of the pressure boundary of a
pressure vessel?
Page 5 of 6
API-510 Recertification Quiz - Questions and Answers (2020)
Question: For valves in acid or caustic service, after pre-pop testing, the pressure-relief valves should be:
A. Blinded.
B. Blocked.
C. Neutralized.
D. Sealed.
Page 6 of 6