3 Month Target Sep-Nov' 23
3 Month Target Sep-Nov' 23
Phase: Phase 1
SUMMARY OF 3 MONTHS WORK TARGET
(All amount in "000")
S
Work Head Sep-23 Oct-23 Nov-23
No.
Unit Qty Qty Amount Qty Amount
Tower 5
1 Foundation
Subtotal 0.00 0.00 0.00
2 Super Structure
Shuttering Work Except Loft , lintel & Chajja
etc. (130' to 140')
Sqm 3,200.00 875.42
Shuttering Work Except Loft , lintel & Chajja
etc. (140' to 150')
Sqm 3,200.00 890.66
Shuttering Work Except Loft , lintel & Chajja
etc. (150' to 160')
Sqm 800 226.46 800 226.46
RMC M-30 (10' to 20') Cum
RMC M-25 (20' to 30') Cum
RMC M-25 (30' to 40') Cum
RMC M-25 (40' to 50') Cum
RMC M-25 (50' to 60') Cum
RMC M-25 (60' to 70') Cum
RMC M-25 (70' to 80') Cum
RMC M-25 (80' to 90') Cum
RMC M-25 (90' to 100') Cum
RMC M-25 (100' to 110') Cum
RMC M-25 (110' to 120') Cum
RMC M-25 (120' to 130') Cum
RMC M-25 (130' to 140') Cum 300.00 1852.92
RMC M-25 (140' to 150') Cum 300.00 1855.90
RMC M-25 (150' to 160') Cum 40.00 247.85 40.00 247.85
Steel Reinforcement work including Cutting,
shifting, bending, binding. (Except Loft , lintel Ton
etc.(10' to 20')
Steel Reinforcement work including Cutting,
shifting, bending, binding. (Except Loft , lintel Ton
etc.(20' to 30')
Steel Reinforcement work including Cutting,
shifting, bending, binding. (Except Loft , lintel Ton
etc.(30' to 40')
Steel Reinforcement work including Cutting,
shifting, bending, binding. (Except Loft , lintel Ton
etc.(40' to 50')
Steel Reinforcement work including Cutting,
shifting, bending, binding. (Except Loft , lintel Ton
etc.(50' to 60')
Steel Reinforcement work including Cutting,
shifting, bending, binding. (Except Loft , lintel Ton
etc.(60' to 70')
Steel Reinforcement work including Cutting,
shifting, bending, binding. (Except Loft , lintel Ton
etc.(70' to 80')
Steel Reinforcement work including Cutting,
shifting, bending, binding. (Except Loft , lintel Ton
etc.(80' to 90')
Steel Reinforcement work including Cutting,
shifting, bending, binding. (Except Loft , lintel Ton
etc.(90' to 100')
Steel Reinforcement work including Cutting,
shifting, bending, binding. (Except Loft , lintel Ton
etc.(100' to 110')
Steel Reinforcement work including Cutting,
shifting, bending, binding. (Except Loft , lintel Ton
etc.(110' to 120')
Steel Reinforcement work including Cutting,
shifting, bending, binding. (Except Loft , lintel Ton
etc.(120' to 130')
Steel Reinforcement work including Cutting,
shifting, bending, binding. (Except Loft , lintel Ton 28.00 2085.29
etc.(130' to 140')
Steel Reinforcement work including Cutting,
shifting, bending, binding. (Except Loft , lintel Ton 28.00 2092.70
etc.(140' to 150')
Steel Reinforcement work including Cutting,
shifting, bending, binding. (Except Loft , lintel Ton 5.00 375.02 5.00 375.02
etc.(150' to 160')
Subtotal 9652.89 849.33 849.33
3 Masonry Work
AAC Blockwork 100 mm (0'-10') sqm
AAC Blockwork 100 mm (10'-20') sqm
AAC Blockwork 100 mm (20'-30') sqm
AAC Blockwork 100 mm (30'-40') sqm
AAC Blockwork 100 mm (40'-50') sqm
AAC Blockwork 100 mm (50'-60') sqm
AAC Blockwork 100 mm (60'-70') sqm
AAC Blockwork 100 mm (70'-80') sqm 300.00 229.86
AAC Blockwork 100 mm (80'-90') sqm 300.00 232.75
AAC Blockwork 100 mm (90'-100') sqm 300.00 235.64
AAC Blockwork 100 mm (100'-110') sqm 300.00 238.54
AAC Blockwork 100 mm (110'-120') sqm 300.00 241.43 300.00 241.43
AAC Blockwork 100 mm (120'-130') sqm 300.00 244.32
AAC Blockwork 100 mm (130'-140') sqm 300.00 247.21
AAC Blockwork 100 mm (140'-150') sqm
AAC Blockwork 100 mm (150'-160') sqm
AAC Blockwork 150 mm (40'-50') cum
AAC Blockwork 150 mm (50'-60') cum
AAC Blockwork 150 mm (60'-70') cum
AAC Blockwork 150 mm (70'-80') cum 9.00 52.35
AAC Blockwork 150 mm (80'-90') cum 9.00 52.73
AAC Blockwork 150 mm (90'-100') cum 9.00 53.11
AAC Blockwork 150 mm (100'-110') cum 9.00 53.49
AAC Blockwork 150 mm (110'-120') cum 9.00 53.87 9.00 53.87
AAC Blockwork 150 mm (120'-130') cum 9.00 54.25
AAC Blockwork 150 mm (130'-140') cum 9.00 54.63
AAC Blockwork 150 mm (140'-150') cum
AAC Blockwork 150 mm (150'-160') cum
Subtotal 567.69 876.08 895.71
4 Electrical Work
Slab material flat 16.00 216.00 16.00 216.00 0.00
Wall material flat 20.00 220.00 20.00 220.00 24.00 264.00
Subtotal 436.00 436.00 264.00
5 MS Work
Medium Weight MS fabrication Work Kg 0.00 0.00 0.00
Subtotal 0.00 0.00 0.00
8 Flooring works
Floor Chipping Work for Flooring sqm 2000.00 43.00 3059.89 65.79 4000.00 86.00
Vitrified tiles Flooring including ponding with
laying and removal of protection sheet sqm 500.00 475.00 1000.00 950.00 1500.00 1425.00
Ceramic Tiles Flooring and skirting work sqm 100.00 78.00 250.00 195.00 500.00 390.00
Ceramic Tiles Dado sqm 260.00 195.00 260.00 195.00 360.00 270.00
Base Plaster for Dado tile sqm 260.00 44.20 260.00 44.20 360.00 61.20
Kadappa/ Dholpur stone below kit counter Sqm 60.00 54.00 120.00 108.00 180.00 162.00
Subtotal 889.20 1557.99 2394.20
10 Internal Painting
POP Work - POP Punning Sqm 3200.00 134.40 3200.00 134.40 4500.00 189.00
Gypsum Plaster Sqm 1100.00 276.10 1100.00 276.10 2500.00 627.50
Internal Painting Sqm 0.00 0.00 500.00 45.00
Enamel Painting over steel structure Sqm
Subtotal 410.50 699.16 1150.16
* 12644 6336 8425
* Add 10% For over head 1264 634 842
* PROJECT TOTAL 13908 6969 9267
* Area (In Sft) 6909 3462 4604
Project: Ashiana Malhar 28-Aug-23
Phase: Phase 1 .
SUMMARY OF 3 MONTHS WORK TARGET
(All amount in "000")
S 1 to 5
Work Head Sep-23 Oct-23 Nov-23
No.
Unit Qty Qty Amount Qty Amount
Tower 4
1 Foundation
Subtotal 0.00 0.00 0.00
2 Super Structure
Shuttering Work Except Loft , lintel &
Chajja etc. (0' to 10') Sqm
Shuttering Work Except Loft , lintel &
Chajja etc. (10' to 20')
Sqm
Shuttering Work Except Loft , lintel &
Chajja etc. (20' to 30')
Sqm
Shuttering Work Except Loft , lintel &
Chajja etc. (30' to 40')
Sqm
Shuttering Work Except Loft , lintel &
Chajja etc. (40' to 50')
Sqm
Shuttering Work Except Loft , lintel &
Chajja etc. (50' to 60') Sqm
Shuttering Work Except Loft , lintel &
Chajja etc. (60' to 70')
Sqm
Shuttering Work Except Loft , lintel &
Chajja etc. (70' to 80') Sqm 1600.00 392.06
Shuttering Work Except Loft , lintel &
Chajja etc. (80' to 90')
Sqm 3200.00 799.36
Shuttering Work Except Loft , lintel &
Chajja etc. (90' to 100')
Sqm 1600.00 407.28 1,600.00 407.28
Shuttering Work Except Loft , lintel &
Chajja etc. (100' to 110')
Sqm 3200.00 829.79
Shuttering Work Except Loft , lintel &
Chajja etc. (110' to 120')
Sqm 3200.00 844.99
Shuttering Work Except Loft , lintel &
Chajja etc. (120' to 130') Sqm 3200 860.22
Shuttering Work Except Loft , lintel &
Chajja etc. (130' to 140')
Sqm 3200.00 875.42
Shuttering Work Except Loft , lintel &
Chajja etc. (140' to 150') Sqm 3200.00 890.66
RMC M-30 (10' to 20') Cum
RMC M-25 (20' to 30') Cum
RMC M-25 (30' to 40') Cum
RMC M-25 (40' to 50') Cum
RMC M-25 (50' to 60') Cum
RMC M-25 (60' to 70') Cum
RMC M-25 (70' to 80') Cum 150.00 917.54
RMC M-25 (80' to 90') Cum 300.00 1838.06
RMC M-25 (90' to 100') Cum 150.00 920.51 150.00 920.51
RMC M-25 (100' to 110') Cum 300.00 1844.00
RMC M-25 (110' to 120') Cum 300.00 1846.98
RMC M-25 (120' to 130') Cum 300.00 1849.95
RMC M-25 (130' to 140') Cum 300.00 1852.92
RMC M-25 (140' to 150') Cum 300.00 1855.90
RMC M-25 (150' to 160') Cum
Steel Reinforcement work including
Cutting, shifting, bending, binding. (Except Ton
Loft , lintel etc.(10' to 20')
Steel Reinforcement work including
Cutting, shifting, bending, binding. (Except Ton
Loft , lintel etc.(20' to 30')
Steel Reinforcement work including
Cutting, shifting, bending, binding. (Except Ton
Loft , lintel etc.(30' to 40')
Steel Reinforcement work including
Cutting, shifting, bending, binding. (Except Ton
Loft , lintel etc.(40' to 50')
Steel Reinforcement work including
Cutting, shifting, bending, binding. (Except Ton
Loft , lintel etc.(50' to 60')
Steel Reinforcement work including
Cutting, shifting, bending, binding. (Except Ton
Loft , lintel etc.(60' to 70')
Steel Reinforcement work including
Cutting, shifting, bending, binding. (Except Ton 14.00 1020.42
Loft , lintel etc.(70' to 80')
Steel Reinforcement work including
Cutting, shifting, bending, binding. (Except Ton 28.00 2048.41
Loft , lintel etc.(80' to 90')
Steel Reinforcement work including
Cutting, shifting, bending, binding. (Except Ton 14.00 1027.83 14.00 1027.83
Loft , lintel etc.(90' to 100')
Steel Reinforcement work including
Cutting, shifting, bending, binding. (Except Ton 28.00 2063.06
Loft , lintel etc.(100' to 110')
Steel Reinforcement work including
Cutting, shifting, bending, binding. (Except Ton 28.00 2070.48
Loft , lintel etc.(110' to 120')
Steel Reinforcement work including
Cutting, shifting, bending, binding. (Except Ton 28 2077.88
Loft , lintel etc.(120' to 130')
Steel Reinforcement work including
Cutting, shifting, bending, binding. (Except 28 2085.29
Loft , lintel etc.(130' to 140')
Steel Reinforcement work including
Cutting, shifting, bending, binding. (Except 28 2092.70
Loft , lintel etc.(140' to 150')
Steel Reinforcement work including
Cutting, shifting, bending, binding. (Except
Loft , lintel etc.(150' to 160')
5 MS Work
Medium Weight MS fabrication Work 0.00 0.00
Subtotal 0.00 0.00
8 Flooring works
Floor Chipping Work for Flooring sqm 0.00 2000.00 43.00 3059.89 65.79
Vitrified tiles Flooring including ponding
with laying and removal of protection sheet sqm 0.00 500.00 475.00 1000.00 950.00
Ceramic Tiles Flooring and skirting work sqm 0.00 100.00 78.00 250.00 195.00
Ceramic Tiles Dado sqm 0.00 260.00 195.00 260.00 195.00
Base Plaster for Dado tile sqm 0.00 260.00 44.20 260.00 44.20
Kadappa/ Dholpur stone below kit counter Sqm 0.00 60.00 54.00 120.00 108.00
Subtotal 0.00 889.20 1557.99
2 Super Structure
Shuttering Work Except Loft , lintel &
Chajja etc. (0' to 10')
Sqm 1159.00 244.55 1500.00 316.50 1000.00 211.00
Shuttering Work Except Loft , lintel &
Chajja etc. (10' to 20')
Sqm 1159.00 254.98 1500 322.5
Shuttering Work Except Loft , lintel &
Chajja etc. (20' to 30')
Sqm 1159.00 253.82
Shuttering Work Except Loft , lintel &
Chajja etc. (30' to 40')
Sqm
RMC M-40 (0' to 10') Cum 75.00 570.00 60.00 456.00 30.00 228.00
RMC M-30 (0' to 10') Cum 100.00 760.00 100.00 760.00 150.00 1140.00
RMC M-40 (10' to 20') Cum 50.00 384.00 40 304.00
RMC M-30 (20' to 30') Cum 100.00 728.00 100.00 728.00
RMC M-30 (30' to 40') Cum
Steel Reinforcement work including
Cutting, shifting, bending, binding. (Except Ton 30.00 1980.00 20.00 1320.00 20.00 1320.00
Loft , lintel etc.(0' to 10')
Steel Reinforcement work including
Cutting, shifting, bending, binding. (Except Ton 20.00 1360.00 20.00 1360.00
Loft , lintel etc.(10' to 20')
Steel Reinforcement work including
Cutting, shifting, bending, binding. (Except Ton 10.00 700.00
Loft , lintel etc.(20' to 30')
Steel Reinforcement work including
Cutting, shifting, bending, binding. (Except Ton
Loft , lintel etc.(30' to 40')
Subtotal 3554.55 5579.48 7639.32 ###
* 4232 5928 7988
* Add 10% For over head 423 593 799
* PROJECT TOTAL 4655 6521 8786
* Area (In Sft) 2313 3239 4365
Project: Ashiana Malhar 28-Aug-23
Phase: Phase 1A .
SUMMARY OF 3 MONTHS WORK TARGET
(All amount in "000")
S
Work Head Sep-23 Oct-23 Nov-23
No.
Unit Qty Amount Qty Amount Qty Amount
1 Foundation
Random Rubble Masonry Cum
RMC M-10 (0' to -10') Cum 75 395.25 150 790.50 75 395.25
Hard Rock Excavation Cum 1000 723.00 500 92.50
PCC - M-15 Cum 0.00 0.00 120 654.60
RMC - M-25 Cum 100 605.70 200 1211.40 200 1211.40###
RMC - M-30 Cum 100 703.50 100 703.50 ###
RMC - M-40 Cum
Shuttering Work Sqm 500 108.00 1500 324.00 1500 324.00
Shuttering Board Making Sqm
Steel MT 15 1069.49 25 1782.48 25 1782.48
ATT Sqm 200 21.05 200 21.05
Back filing Mechenical Cum 500 75.00 2000 300
Subtotal 2901.44 5000.42 5392.27
2 Super Structure
Shuttering Work Except Loft , lintel &
Chajja etc. (0' to 10')
Sqm 0.00 0.00 0.00
Shuttering Work Except Loft , lintel &
Chajja etc. (10' to 20')
Sqm 0.00 0
Shuttering Work Except Loft , lintel &
Chajja etc. (20' to 30')
Sqm 0.00
Shuttering Work Except Loft , lintel &
Chajja etc. (30' to 40')
Sqm
RMC M-40 (0' to 10') Cum 0.00 0.00 0.00
RMC M-30 (0' to 10') Cum 0.00 0.00 0.00
RMC M-40 (10' to 20') Cum 0.00 0.00
RMC M-30 (20' to 30') Cum 0.00 0.00
RMC M-30 (30' to 40') Cum
Steel Reinforcement work including
Cutting, shifting, bending, binding. (Except Ton 0.00 0.00 0.00
Loft , lintel etc.(0' to 10')
Steel Reinforcement work including
Cutting, shifting, bending, binding. (Except Ton 0.00 0.00
Loft , lintel etc.(10' to 20')
Steel Reinforcement work including
Cutting, shifting, bending, binding. (Except Ton 0.00
Loft , lintel etc.(20' to 30')
Steel Reinforcement work including
Cutting, shifting, bending, binding. (Except Ton
Loft , lintel etc.(30' to 40')
Subtotal 0.00 0.00 1072.00 ###
* 2901 5000 6464
* Add 10% For over head 290 500 646
* PROJECT TOTAL 3192 5500 7111
* Area (In Sft) 1585 2732 3532
Phase:Dev SUMMARY OF 3 MONTHS WORK TARGET
All amount in '000" Date
Sep'23 Oct'23 Nov'23
S.No Item
Qty Amount Qty Amount Qty
1 Club House 750 1000
Foundation
PCC M15
RMC M30
2 Podium 1000 750
1953.552 0 2073.77 0
17075 0 17617 0
ARGET
8/28/2023
Nov'23
Amount
1000
750
1000
300
200
3250
3575
1775.95628
8230
1953.55191
18942
Project: Ashiana Malhar
Phase:All SUMMARY OF 3 MONTHS WORK TARGET
All amount in '000'
Sep'23
S.NO. ITEM UNIT
Qty Amount
1 Foundation 3579
2 Super Structure 22579
3 Masonry
Brick/Block Work 1119
Plaster -
Sub Total 1119
4 Flooring Work
Floor Chipping Work for Flooring 43
Vitrified tiles Flooring including ponding with laying an 475
Ceramic Tiles Flooring and skirting work 78
Ceramic Tiles Dado 195
Base Plaster for Dado tile 44
Kadappa/ Dholpur stone below kit counter 54
Sub Total 889
5 Sealing & Water Proofing 0
Sunken Slab treatment Sqm 118.00
PCC 1:2:4 (0' to 10') Cum 96.93
Light Weight Filling in SunkenCum 14.73
Sub Total 230
6 Doors & Windows
Single rebate fixing 124
Double rebate fixing 76
Balcony Railing 209
Door Shutter 0
Sub Total 409
7 Electrical Work
Wall & Slab 828
Wring and Fittings
Panels
Other work
Sub Total 828
8 PHE Work
Int CPVC Work 426
Int PVC Work 105
UPVc External 0
PVC Disposal 0
Sub Total 531
9 Painting Work
POP 411
Internal Paint 0
External Paint
Other work
Sub Total 411
10 Fuel House Keeping etc.
Fire Fighting
LPG
Sub Total
11 Others(MS WORK ) 0
12 Phase-2
BUILDING TOTAL 30574
DEVELOPMENT TOTAL 3250
PROJECT TOTAL 33824
PROJECT TOTAL (Including Over heads) 37207
1583 1772
1583 1772
109 152
1425 2375
273 585
390 465
88 105
162 270
2447 3952
0 0
177.00 177.00
96.93 96.93
14.73 14.73
289 289
231 287
118 138
680 1019
0 61
1028 1585
880 821
880 821
818 818
202 202
408 817
1048 2097
2476 3933
821 1382
0 45
1110 1716
0 0
###
33445 36482
3450 3250
36895 39732
40585 43705
20161 21711
Project: Ashiana Dwarka #REF!
Phase: III & Development
SUMMARY OF 3 MONTHS WORK TARGET
(All amount in "000")
S
Work Head Aug-21 Sep-21 Oct-21
No.
Unit Qty Amount Qty Amount Qty Amount
Phase-III
1 Foundation
Earth work in Excavation - Manual (0' to -10') Cum 0.00 0.00 0.00 0.00 0.00 0.00
Earth work in Excavation - Mechanical (0' to -10') Cum 0.00 0.00 0.00 0.00 0.00 0.00
Sand filling Cum 0.00 0.00 0.00 0.00 0.00 0.00
RMC M-10 (0' to -10') Cum 0.00 0.00 0.00 0.00 0.00 0.00
Back Filling in Excavation- Manual (-0' to -10') Cum 0.00 0.00 0.00 0.00 0.00 0.00
Back Filling in Excavation - Mechanical Cum 0.00 0.00 0.00 0.00 0.00 0.00
Anti-termite treatment Sqm 0.00 0.00 0.00 0.00 0.00 0.00
Flat Bricks soling Sqm 0.00 0.00 0.00 0.00 0.00 0.00
RMC M-15 (0' to -10') Cum 0.00 0.00 0.00 0.00 0.00 0.00
RMC M-25 (0' to -10') Cum 0.00 0.00 0.00 0.00 0.00 0.00
RMC M-35 (0' to -10') Cum 0.00 0.00 0.00 0.00 0.00 0.00
Shuttering Board Making Sqm 0.00 0.00 0.00 0.00 0.00 0.00
Shuttering Work Except Loft , lintel & Chajja etc. (0' to -10') Sqm 0.00 0.00 0.00 0.00 0.00 0.00
Steel Reinforcement work including Cutting, shifting, bending, binding. Ton 0.00 0.00 0.00 0.00 0.00 0.00
(Except Loft , lintel etc.(0' to -10')
Full Brick Work, incl. Layout & Curing (230 mm) (0' to -10') Cum 0.00 0.00 0.00 0.00 0.00 0.00
Neat cement Plaster Sqm 0.00 0.00 0.00 0.00 0.00 0.00
2 Super Structure
Shuttering Work Except Loft , lintel & Chajja etc. (0' to 10') Sqm 0.00 0.00 0.00 0.00 0.00 0.00
Shuttering Work Except Loft , lintel & Chajja etc. (10' to 20') Sqm 0.00 0.00 0.00 0.00 0.00 0.00
RMC M-25 (0' to 10') Cum 0.00 0.00 0.00 0.00 0.00 0.00
RMC M-35 (0' to 10') Cum 0.00 0.00 0.00 0.00 0.00 0.00
RMC M-35 (10' to 20') Cum 0.00 0.00 0.00 0.00 0.00 0.00
Steel Reinforcement work including Cutting, shifting, bending, binding. Ton 0.00 0.00 0.00 0.00 0.00 0.00
(Except Loft , lintel etc.(0' to 10')
Steel Reinforcement work including Cutting, shifting, bending, binding. Ton 0.00 0.00 0.00 0.00 0.00 0.00
(Except Loft , lintel etc.(10' to 20')
Subtotal 0.00 0.00 0.00
3 Masonry
Flat Handing over Nos 0.00 0.00 0.00 0.00 0.00 0.00
Sqm 0.00 0.00 0.00 0.00 0.00 0.00
Subtotal 0.00 0.00 0.00
4 Flooring Work
Flooring work Sqm 0.00 0.00 0.00 0.00 0.00 0.00
DADO work Sqm 0.00 0.00 0.00 0.00 0.00 0.00
Kota Stone work Sqm 0.00 0.00 0.00 0.00 0.00 0.00
Tile Grouting and cleaning work with tile cleaning machine Sqm 0.00 0.00 0.00 0.00 0.00 0.00
Half round Moulding Sqm 0.00 0.00 0.00 0.00 0.00 0.00
Subtotal 0.00 0.00 0.00
8 PHE Work
UPVC Terrace ring (3 & 2 BHK) Block 0.00 0.00 0.00 0.00 0.00 0.00
Solenoid Valve Nos 0.00 0.00 0.00 0.00 0.00 0.00
CP & Vitreous Flat 0.00 0.00 0.00 0.00 0.00 0.00
9 Painting Work
POP work Sqm 0.00 0.00 0.00 0.00 0.00 0.00
Internal Paint work Sqm 0.00 0.00 0.00 0.00 0.00 0.00
Enamel Paint work (Steel Structure) Sqm 0.00 0.00 0.00 0.00 0.00 0.00
External Textured paint Sqm 0.00 0.00 0.00 0.00 0.00 0.00
Terra Cotta Paint Sqm 0.00 0.00 0.00 0.00 0.00 0.00
Terra Cota / Sandtex Mat paint over external Surface Sqm 0.00 0.00 0.00 0.00 0.00 0.00
Subtotal 0.00 0.00 0.00
10 MS Work
Light Weight MS fabrication Work Kg 0.00 0.00 0.00 0.00 0.00 0.00
Duct Cover Poly Carbonate sheet Sqm 0.00 0.00 0.00 0.00 0.00 0.00
Medium Weight MS fabrication Work Sqm 0.00 0.00 0.00 0.00 0.00 0.00
Subtotal 0.00 0.00 0.00
Development
1 Parking
Car Parking-Paver Sqm 0.00 0.00 0.00 0.00 0.00 0.00
Flat Brick Soling Sqm 0.00 0.00 0.00 0.00 0.00 0.00
Kerb Stone Rmt 0.00 0.00 0.00 0.00 0.00 0.00
Subtotal 0.00 0.00 0.00
4 Power Supply
Supervision Charges & Transformer PH-III Rmt 0.00 0.00 0.00 0.00 0.00 0.00
Earthing Pit-Chemical Nos. 0.00 0.00 0.00 0.00 0.00 0.00
GO-DO Set 11 KVA Nos. 0.00 0.00 0.00 0.00 0.00 0.00
Supervision charge to electricity Deptt. Nos. 0.00 0.00 0.00 0.00 0.00 0.00
33 KVA Transformer Nos. 0.00 0.00 0.00 0.00 0.00 0.00
Subtotal 0.00 0.00 0.00
6 Internal Roads
Excavation Cum 0 0.00 0.00 0.00 0 0.00
GSB + WMM Sqm 0 0.00 0.00 0.00 0 0.00
Holland Paver fixing Sqm 0 0.00 0.00 0.00 0 0.00
Subtotal 0.00 0.00 0.00
7 Plantation
Plantation 0 0.00 0.00 0.00 0 0.00
Subtotal 0.00 0.00 0.00
* BUILDING TOTAL 0 0 0
* DEVELOPMENT TOTAL 0 0 0
* Add 10% For over head 0 0 0
* PROJECT TOTAL 0 0 0
* Area (In Sft) 0 0 0
Project: Ashiana Dwarka 5-Sep-23
Phase: IV
SUMMARY OF 3 MONTHS WORK TARGET
(All amount in "000")
2 Super Structure
Shuttering Work Except Loft , lintel & Chajja etc. (0' to 10') Sqm 2200.00 386.10 0.00 0.00 0.00 0.00
Shuttering Work Except Loft , lintel & Chajja etc. (10' to 20') Sqm 0.00 0.00 2010.00 360.16 0.00 0.00
Shuttering Work Except Loft , lintel & Chajja etc. (20' to 30') Sqm 0.00 0.00 2010.00 367.57 0.00 0.00
Shuttering Work Except Loft , lintel & Chajja etc. (30' to 40') Sqm 0.00 0.00 0.00 0.00 2100.00 391.77
Shuttering Work Except Loft , lintel & Chajja etc. (40' to 50') Sqm 0.00 0.00 0.00 0.00 2100.00 399.50
Shuttering Work Except Loft , lintel & Chajja etc. (50' to 60') Sqm 0.00 0.00 0.00 0.00 0.00 0.00
RMC M-25 (0' to 10') Cum 200.00 760.67 0.00 0.00 0.00 0.00
RMC M-25 (10' to 20') Cum 0.00 0.00 202.00 769.82 0.00 0.00
RMC M-25 (20' to 30') Cum 0.00 0.00 202.00 771.37 0.00 0.00
RMC M-25 (30' to 40') Cum 0.00 0.00 0.00 0.00 202.00 772.92
RMC M-25 (40' to 50') Cum 0.00 0.00 0.00 0.00 202.00 774.47
RMC M-30 (30' to 40') Cum 0.00 0.00 0.00 0.00 2.70 12.45
RMC M-30 (40' to 50') Cum 0.00 0.00 0.00 0.00 2.70 12.53
RMC M-35 (0' to 10') Cum 76.00 357.99 0.00 0.00 0.00 0.00
RMC M-35 (10' to 20') Cum 0.00 0.00 42.00 199.22 0.00 0.00
RMC M-35 (20' to 30') Cum 0.00 0.00 42.00 200.61 0.00 0.00
RMC M-35 (30' to 40') Cum 0.00 0.00 0.00 0.00 40.00 192.38
RMC M-35 (40' to 50') Cum 0.00 0.00 0.00 0.00 40.00 193.70
Steel Reinforcement work including Cutting, shifting, bending, binding. Ton 33.50 1464.11 0.00 0.00 0.00 0.00
(Except Loft , lintel etc.(0' to 10')
Steel Reinforcement work including Cutting, shifting, bending, binding. Ton 0.00 0.00 28.00 1229.61 0.00 0.00
(Except Loft , lintel etc.(10' to 20')
Steel Reinforcement work including Cutting, shifting, bending, binding. Ton 0.00 0.00 28.00 1235.48 0.00 0.00
(Except Loft , lintel etc.(20' to 30')
Steel Reinforcement work including Cutting, shifting, bending, binding. Ton 0.00 0.00 0.00 0.00 29.00 1285.68
(Except Loft , lintel etc.(30' to 40')
Steel Reinforcement work including Cutting, shifting, bending, binding. Ton 0.00 0.00 0.00 0.00 29.00 1291.76
(Except Loft , lintel etc.(40' to 50')
Steel Reinforcement work including Cutting, shifting, bending, binding. Ton 0.00 0.00 0.00 0.00 0.00 0.00
(Except Loft , lintel etc.(50' to 60')
Scaffolding work (External) Sqm 0.00 0.00 590.00 11.86 940.00 18.90
Full Brick Work, incl. Layout & Curing (230 mm) (0' to 10') Cum 0.00 0.00 0.00 0.00 35.00 82.42
Half Brick Work, Incl. Layout & curing (115mm) (0' to 10') Sqm 0.00 0.00 0.00 0.00 140.00 53.56
Half Brick Work, Incl. Layout & curing (115mm) (10' to 20') Sqm 0.00 0.00 0.00 0.00 0.00 0.00
Subtotal 0.00 2968.87 0.00 5145.70 0.00 5482.03
7 Electrical Work
Slab Material - 3BHK - 2 Toilet Flat 4.00 24.00 6.00 36.00 8.00 48.00
Slab Material - 2BHK - 2 Toilet Flat 4.00 21.54 6.00 32.30 8.00 43.07
Subtotal 45.54 68.31 91.07
10 MS Work
Light Weight MS fabrication Work Kg 100.00 14.23 200.00 28.46 200.00 28.46
Subtotal 14.23 28.46 28.46