Rate Analysis
Rate Analysis
H1 BLOCK PLOT NO 38
20 DIA BAR 200 MM LONG REBARING WITH HILTI
CHEMICAL RE 500
A 20# 200 mm long NOS
DATA 1 No.
Chemical ml 65 15.27 992.55
( Rs 7635 per pack of 500 ml Hilti RE 500 V 4) Rs 15.27 per
ml
65 ml per no. as per hilti specifications
wastage @ 3% 29.78
1,022.33
1,022.33 A
Labour for Drilling & filling chemical
Labor (including drilling machine) No. 1 110 110.00
Scaffolding L.S. -
110.00 B
B JCB CHARGES
DATA 8 HOURS
JCB ( 8 Hours per day)including operator & diesel DAY 1 8000 8,000.00
8,000.00
8,000.00 A
8,000.00
DATA 20 Sqm
Black Sheet Sqm 20 52.00 1,040.00
wastage & overlaps @ 15% 156.00
Masking tape L.S. 50.00
Labour Sqm 20 15.00 300.00
1,546.00 A
1,546.00
DATA 25 No.s
Gunny Bag No. 25 5.00 125.00
Unskilled Labour for Earth filling Day 1 450.00 450.00
Skilled Labour for stacking Day 0.5 600 300.00
875.00 A
875.00
For P/L
25
GUNNY
962.50 BAGS
Charges for P/F Gunny Bag 38.50 Per No.
GST EXTRA
For
shifting
Charges per Cum 275.00 of Earth
GST EXTRA