Laporan Mngr. Shift P-2B, 25 Agustus 2023 (Night Shift)
Laporan Mngr. Shift P-2B, 25 Agustus 2023 (Night Shift)
Laporan Mngr. Shift P-2B, 25 Agustus 2023 (Night Shift)
Night Shift
Jum’at, 25 Agustus 2023
UREA : Shutdown
23.45 : Start GA-403 ke LPA (make up LPA)
00.00 : Test drain dust chumber FC-301 (OK)
00.30 : Mekanik pasang AV drain EA-101, test dengan SHC 78 Kg/cm² (OK)
01.00 : Open FV-504 (Start Up PCT)
01.30 : C-Shop pasang scafold di BV drain lantai 1 (OK) dan lanjut pembersihan di dust chumber (IP)
01.45 : Start pompa GA-502 B
02.00 : Mekanik buka BV drain dust chumber FC-301 (OK)
Tie-in : - Paralel Vapour NH3 (TP-04A 100 %) - Kirim Demin water ke STG - Kirim Filter water ke P3
- Tie in CO2 MOV-3001 ( 0 %) - Terima Cold NH₃ dari P1B & P4
Edi Suroso
02.0355