1.0 PURPOSE
To Establish The Procedure To Ensure The Inprocess ,Assembly ,Final
inspection,firewall inspection / pre delivery inspection activities are carried out as
per the quality standard and quality specification.
2.0 SCOPE
All products under production and Finished components.
3.0 RESPONSIBILITY
Quality Head & Quality Engineer
04. MANUAL
4.1.1 Finished products / After assembly product & After the final inspection parts
to be move to Fire wall inspection as agreed with customer and as per the firewall
inspection requirement by Quality – Head .
DONG A INDIA
4.1.4 Necessary Quality firewall standards ,Work instructions & Master part list to be
displayed at fire wall station .
4.1.5 After the firewall inspection if parts found OK ,
- The parts to be moved to FG and send to customer
4.1.5 If parts found defective and /or NG ( even 1 no’s also), To be analyse the
problem / Quality issues along with CFT by Head – QA and necessary action to be
taken and Follow as per customer complaint procedure .
Effectiveness monitoring
Lesson learned
Doc No : DAI/QSP/FWI/01
FIRE WALL INSPECTION Rev .No : 01
PROCEDURE Date : 02.12.2021
DONG A INDIA