GOVERNMNENT OF KHYBER PAKHTUNKHWA.

IRRIGATION DEPARTMENT
CONSTRUCTION OF SIRAN RIGHT BANK CANAL DISTRICT MANSEHRA
CONTRACTOR:M/s National RCC (pvt) Ltd CONSULTANT: PES Consultants

"ABSTRACT"

Difference
Revised Detailed Difference
Detailed Estimate Approved BOQ (Revised Detailed
S.No Description Estimate Amount VO-1 Amount (Million) (BOQ - VO-1)
Amount (Million) Amount (Million) Estimate - BOQ)
(Million) (Million)
(Million)

Building Canal and


1 2,245.955 2,130.58 1,937.88 1,934.83 308.07 (3.06)
Allied works
Construction of Siran Right Bank Canal
District Mansehra
ABSTRACT OF COST
Amount
Sr. No. ITEMS / DESCRIPTION
(Rs. Million)
A WORKS
1 Offtake Structure & Head Regulator 207.065

2 Irrigation Canal (Main & Minor) 1,473.049

3 Canal Affiliated Structures 802.515

Building I & II (Sub-Engineer Office cum Residence &


4 12.877
Chowkidar Hut)
Sub Total A 2,495.505
Contractor's Premium at 10% below (249.551)
Total A 2,245.955
B PRELIMINARIES

1 Land Acquisition 220.00

2 Extension of Power Line & Diversion Arrangements 20.00


Total B 240.00
C GENERAL
1 Establishment of Project Directorate Office 212.06

2 Consultancy Charges 249.261

3 Escalation / Price Adjustment 230.10

4 Others / unforseen physical works 10.000


Total C 701.421
Grand Total (A+B+C) 3,187.376

Project Manager
Siran Right Bank Canal Project
Pakistan Engineering Services (Pvt.) Ltd.
in association with: Dynatech Consultants
Construction of Siran Right Bank Canal
District Mansehra
ABSTRACT OF COST
COMPARISION B/W PC-I AND DETAILED ESTIMATE
Amount (Rs. Million)
PC-I Detailed Revised T.S Difference Revised Difference Detailed
Sr. No. ITEMS / DESCRIPTION Estimate T.S & PC 1 Estimate & Revised T.S

A WORKS 2259.42 2129.300 2245.955 -13.465 116.655

B PRELIMINARIES

1 Land Acquisition 200 200.00 220.00 20.000 20.000

Extension of Power Line & Diversion


2 20 20.00 20.00 0.000 0.000
Arrangements

Total B 220.00 220.00 240.00 20.000 20.000

C GENERAL

1 Establishment of Project Directorate Office 154.23 154.230 212.060 57.830 57.830

2 Consultancy Charges 70 155.752 249.261 179.261 93.509

3 Escalation / Price Adjustment 136.86 136.86 230.10 93.240 93.240

4 Others / unforseen physical works 10 10.000 10.000 0.000 0.000

Total C 371.090 456.842 701.421 330.331 244.579

Grand Total (A+B+C) 2,850.510 2,806.142 3,187.376 336.866 381.234

Siran Right Bank Canal Project


Pakistan Engineering Services (Pvt.) Ltd.
in association with: Dynatech Consultants
Construction of Siran Right Bank Canal
District Mansehra
ITEM WISE SUMMARY OF COST (WORKS)

MRS 2016 Revised T.S


Sr. No. Description of Items Unit MRS 2016 Rate Revised T.S Amount Remarks
Item Code Quantity

Providing and fixing stainless steel sink with drain


ATR
1 14-06-b board size 18"x36" including set of brackets, waste Each 4.00 2,585.80 10,343.20
BOQ Item #1
pipe etc
Providing & Fixing Steel manhole cover with frame ATR
2 14-37-d Each 6.00 3,443.75 20,662.50
18"x18" full heavy duty BOQ Item #2
ATR
3 23-11 Soakage pit ( 6' dia x 15' deep ) complete. No 6.00 16,376.25 98,257.50
BOQ Item #3
Providing and installing PVC tees BSS Class ATR
4 24-27-a-02 Each 30.00 500.45 15,013.50
'B'working pressure : 3" i/d BOQ Item #4
Providing and installing PVC bends BSS Class ATR
5 24-26-c-02 Each 22.00 291.54 6,413.88
'D'working pressure : 3" i/d BOQ Item #5
Providing and Laying cut, joint, test, disinfect PVC ATR
6 24-18-c-05 R. M 25.00 699.29 17,482.25
pipe line BSS Class 'D' working pressure : 3" i/d BOQ Item #6
Providing and installing PVC tees BSS Class ATR
7 24-27-a-03 Each 15.00 687.85 10,317.75
'B'working pressure : 4" i/d BOQ Item #7
Providing and installing PVC bends BSS Class ATR
8 24-26-c-03 Each 15.00 438.29 6,574.35
'D'working pressure : 4" i/d BOQ Item #8
Providing and Laying cut, joint, test, disinfect PVC ATR
9 24-18-c-06 R. M 90.00 788.70 70,983.00
pipe line BSS Class 'D' working pressure : 4" i/d BOQ Item #9
Providing and installing PVC sockets BSS Class ATR
10 24-28-a-04 Each 10.00 1,360.30 13,603.00
'B'working pressure : 6" i/d BOQ Item #10
Providing and installing PVC bends BSS Class ATR
11 24-26-a-04 Each 9.00 920.87 8,287.83
'B'working pressure : 6" i/d BOQ Item #11
Providing and Laying cut, joint, test, disinfect PVC ATR
12 24-18-a-03 R. M 160.00 914.20 146,272.00
pipe line BSS Class 'B'working pressure : 6" i/d BOQ Item #12
Providing and Fixing of poly dex high pressure PPR
ATR
13 14-71-b (green including testing ect complete 20 mm(including R. M 185.00 399.64 73,933.40
BOQ Item #13
all special etc)
Providing and Fixing of poly dex high pressure
ATR
14 14-71-a PPR(green including testing ect complete 25 R. M 160.00 427.66 68,425.60
BOQ Item #14
mm(including all special etc)
Supply and Fixing CI manhole cover with frame etc ATR
15 14-37-b Each 10.00 1,909.96 19,099.60
complete 18" dia BOQ Item #15
Providing and fixing CI main hole cover with frame etc ATR
16 14-37-a No 10.00 1,110.86 11,108.60
complete 12" dia BOQ Item #16
Providing and Fixing CI floor trap including CI grating ATR
17 14-31-b Each 6.00 793.80 4,762.80
& concrete chamber all round : 4"x3" BOQ Item #17
ATR
18 14-26-b Providing and fixing CP shower rose : 3/4"x6". No 5.00 665.13 3,325.65
BOQ Item #18
Providing and fixing gun metal peet / gate valve ATR
19 14-28-a No 4.00 1,331.80 5,327.20
(screwed ) 1" dia. BOQ Item #19
Providing and Fixing CP mixing valve for WHB, sink or ATR
20 14-27 No 4.00 2,129.13 8,516.52
shower BOQ Item #20
Providing and Fixing CP or brass oxidized swan-neck ATR
21 14-29-b Each 5.00 2,320.00 11,600.00
cock 1/2" dia : Double way BOQ Item #21
ATR
22 14-25 Providing and Fixing 1/2" CP tee stop cock Each 11.00 567.53 6,242.83
BOQ Item #22
Providing and Fixing glazed earthen ware soap dish ATR
23 14-14-b Each 6.00 421.13 2,526.78
Coloured BOQ Item #23
Providing and fixing best quality 5mm glass mirror ATR
24 14-17 No 5.00 914.81 4,574.05
22"x16" size BOQ Item #24
ATR
25 14-16-a Providing and fixing CP rail :24" long, 3/4" dia. No 5.00 787.13 3,935.65
BOQ Item #25
ATR
26 14-15 Providing and fixing CP tailot paper holder. No 5.00 286.92 1,434.60
BOQ Item #26
ATR
27 14-13 Providing and fixing CP soap dish. No 5.00 537.03 2,685.15
BOQ Item #27
Providing and Fixing glazed earthen ware low down ATR
28 14-10-b Each 5.00 2,781.00 13,905.00
flushing cistern 3 gallons capacity : Coloured BOQ Item #28
Providing and Fixing glazed earthen ware WC
ATR
29 14-01-b European type excluding cost of seat & cover : Each 5.00 5,118.63 25,593.15
BOQ Item #29
Coloured
ATR
30 14-78 Supply and Fixing low level plastic flushing cistern Each 5.00 1,001.20 5,006.00
BOQ Item #30

Providing and Fixing glazed earthen ware WC ATR


31 14-03-b Each 5.00 1,719.75 8,598.75
squatting type with built-in foot rests : Coloured BOQ Item #31

Providing and Fixing angle iron brackets for : WHB


ATR
32 14-46-a and Each 4.00 246.00 984.00
BOQ Item #32
cistern
Providing and Fixing glazed earthen ware WHB ATR
33 14-05-a-02 Each 5.00 3,012.80 15,064.00
complete Size 22"x16" : Coloured with pedestal BOQ Item #33
Energy saver 32 Watts (Phillips or eq) with down
ATR
34 ATR light / simple holder and extra accessories etc as No. 15.00 450.00 6,750.00
BOQ Item #34
specified
ATR
35 ATR Supply and erection plastic box size 7"x4" No. 22.00 600.00 13,200.00
BOQ Item #35
ATR
36 ATR Supply and erection plastic box size 4"x4" No. 22.00 500.00 11,000.00
BOQ Item #36
Supply and Erection gate-light fitting complete with ATR
37 15-63-a Each 12.00 796.65 9,559.80
holder & 160-Watt mercury blended lamp: Small BOQ Item #37
Earthing of iron clad/aluminium switches etc with GI ATR
38 15-41 Job 2.00 5,822.66 11,645.32
wire #8 SWG in GI pipe 0.5" dia BOQ Item #38
Supply and Erection 2'x2'x1/8" copper plate including
ATR
39 15-42 riveting to copper tape & placing in mixture of salt and Each 3.00 9,231.69 27,695.07
BOQ Item #39
charcoal etc
Supply and Erection single phase imported auto circuit ATR
40 15-71-d Each 3.00 624.94 1,874.82
breaker 30 Amp. BOQ Item #40
Supply and Erection single phase imported auto circuit ATR
41 15-71-c Each 8.00 472.44 3,779.52
breaker 20 Amp BOQ Item #41
Supply and Erection single phase imported auto circuit ATR
42 15-71-b Each 10.00 472.44 4,724.40
breaker 15 Amp BOQ Item #42

Supply and Erection transpower auto circuit breaker 3- ATR


43 15-70-a Each 6.00 2,006.25 12,037.50
phase, 400V fungus moisture proofing : 30 Amp. BOQ Item #43

Supply and Erection transpower auto circuit breaker 3- ATR


44 15-70-c Each 3.00 5,238.94 15,716.82
phase, 400V fungus moisture proofing : 100 Amp BOQ Item #44
Construction of Siran Right Bank Canal
District Mansehra
ITEM WISE SUMMARY OF COST (WORKS)

MRS 2016 Revised T.S


Sr. No. Description of Items Unit MRS 2016 Rate Revised T.S Amount Remarks
Item Code Quantity

Supply and Erection single core PVC insulated copper ATR


45 15-05-e R. M 30.00 164.83 4,944.90
conductor 250/440 V grade cable : 7/0.044" BOQ Item #45

Supply and Erection single core PVC insulated copper ATR


46 15-05-c R. M 300.00 69.50 20,850.00
conductor 250/440 V grade cable : 7/0.029" BOQ Item #46

Supply and Erection single core PVC insulated copper ATR


47 15-05-a R. M 350.00 42.14 14,749.00
conductor 250/440 V grade cable : 3/0.029" BOQ Item #47

Supply and Erection white round globe with holder, ATR


48 15-56-c Each 3.00 221.43 664.29
gallery & 100 Watt bulb complete : 10" dia. BOQ Item #48
Supply and Erection PVC pipe for wiring purpose
ATR
49 15-02-b-03 complete Recessed in walls including chase etc : 1" R. M 130.00 275.83 35,857.90
BOQ Item #49
i/d
Supply and Erection PVC pipe for wiring purpose
ATR
50 15-02-b-02 complete Recessed in walls including chase etc : 3/4" R. M 130.00 302.02 39,262.60
BOQ Item #50
i/d

Floor S/E cubical type factory fabricated floor / wall ATR


51 15-75-b No 2.00 38,157.65 76,315.30
mounted main board steel complete recessed. BOQ Item #51

Supply and fixing electric AC exhaust/fresh air


ATR
52 15-77-c circulation(Double way) 220/230 single phase plastic Each 3.00 3,086.07 9,258.21
BOQ Item #52
frame body and blade complete 12"x12"

S/E best quality ceiling fan complete with G-I rod ATR
53 15-68-c No 15.00 3,845.53 57,682.95
canopy blade & regulator 56" sweep. BOQ Item #53
Supply and Erection girder clamp hook, 5/8" dia.for ATR
54 15-25 Each 9.00 318.11 2,862.99
hanging ceiling fans BOQ Item #54
Supply and Erection tube light, including rod, choke
ATR
55 15-24-a etc complete Double rod (2x40 watts) with 2 chokes & Set 14.00 975.58 13,658.12
BOQ Item #55
2 starters
ATR
56 15-24-b S/E tube light rod and choke complete 40 watt. No 14.00 454.14 6,357.96
BOQ Item #56
ATR
57 15-82 Supply and Fixing Asia porcelin power plug 30 Amp Each 30.00 151.88 4,556.40
BOQ Item #57
Wiring of 2/3 pin 5 AMP plug point in 3/029 pvc ATR
58 15-51 No 30.00 368.80 11,064.00
insulated cable in pvc pipe recessed. BOQ Item #58
Wiring of light / fan / call bell point in 3-29 pvc ATR
59 15-50 No 90.00 850.55 76,549.50
insulated cable in pvc pipe recessed. BOQ Item #59
Making and fixing grating in opening, including fixing ATR
60 25-32 M2 60.00 2,344.44 140,666.40
at site with flat iron 2"x3/8" and 3/4" sq. bars BOQ Item #61
Filling, watering and ramming earth under floor with ATR
61 03-16-a M3 99.16 103.30 10,243.12
surplus earth from foundation, etc BOQ Item #62
Shoes, bends or offsets for cast iron rain water down ATR
62 09-21 Each 17.00 1,747.97 29,715.49
pipe, including fixing & painting BOQ Item #63

Heads for cast iron rain water down pipe fixed in place ATR
63 09-20 Each 17.00 1,832.34 31,149.78
including cost of clamp holdfast and painting BOQ Item #64

Cast iron rain water down pipe fixed in position ATR


64 09-19-a R. M 54.88 2,212.05 121,392.99
excluding heads & shoes : 4" dia BOQ Item #65
ATR
Plain Cement Concrete including placing, compacting,
65 06-05-h M3 4,457.29 5,861.65 26,127,052.36 BOQ Item #66 &
finishing & curing (Ratio 1:3:6)
#131
ATR
Preparing surface & painting with snowcem / weather
66 13-38-b M2 416.22 85.56 35,611.57 BOQ Item #60 &
shield paint : 2nd & subsequent coats
#67
Preparing surface & painting with snowcem / weather ATR
67 13-38-a M2 430.83 166.86 71,887.82
shield paint : First coat BOQ Item #68
ATR
68 11-23-a-03 Distemper New surface: three coats. M² 1,987.95 79.31 157,663.97
BOQ Item #69
ATR
69 11-25-a-03 White washing: New surface : Three coats M2 1,987.95 40.16 79,835.90
BOQ Item #70
ATR
70 11-22 Priming coat of chalk under distemper M2 1,987.95 19.34 38,446.87
BOQ Item #71
Providing and Fixing terrace railing of 2" i/d conduit
ATR
71 25-33 pipe 16 SWG welded with 5/8"x5/8" sq bar 2.75' high M2 55.00 3,368.16 185,248.80
BOQ Item #72
complete
MS flat 1/2"x1/8" grill in windows of approved design ATR
72 12-50 M2 48.09 3,073.30 147,809.74
including painting 3 coats, complete BOQ Item #73
ATR
73 13-08-a French polishing complete : on new work . M² 358.12 671.13 240,345.08
BOQ Item #74
Varnishing wood work, including cleaning & preparing ATR
74 13-09-c M2 358.12 53.44 19,137.93
surface : Third coat BOQ Item #75
Varnishing wood work, including cleaning & preparing ATR
75 13-09-b M2 358.12 61.53 22,035.12
surface : Second coat BOQ Item #76
Varnishing wood work, including cleaning & preparing ATR
76 13-09-a M 2
358.12 93.65 33,537.94
surface : First coat BOQ Item #77
ATR
77 12-17-b P/F hydraulic Door Closer (Best Quality) Each 18.00 1,682.50 30,285.00
BOQ Item #78
Providing and fixing sliding bolt to doors Brass sliding ATR
78 12-18-c-01 Each 18.00 1,121.05 20,178.90
bolts : 10" long BOQ Item #79
Providing and fixing sliding bolt to doors Brass sliding ATR
79 12-18-c-02 Each 18.00 1,426.05 25,668.90
bolts : 12" long BOQ Item #80
Provide & fix wooden box type wardrobe 22" deep ATR
80 12-23-b M2 26.02 10,896.40 283,549.44
Deodar wood boxing & deodar shelves etc BOQ Item #81
Supply and Fixing aluminium door/window, Economy ATR
81 12-53-a-01 M2 50.05 7,334.76 367,078.83
model Sliding window BOQ Item #82
Deodar wood framed, braced & battened doors & ATR
82 12-08-b M2 39.36 8,858.29 348,651.10
windows: 1.75" thick, 1" battens & 3/4" planks BOQ Item #83
Provide & fix chowkat for doors, windows & CS ATR
83 12-24-c M2 41.96 2,758.60 115,753.52
windows, including holdfast etc : Deodar wood BOQ Item #84
Providing and fixing glazed tile colour printed border ATR
84 10-26-g R. M 55.20 636.89 35,153.25
3" wide BOQ Item #85
Glazed tile 1/4" thick dado jointed in white cement ATR
85 10-38-c M2 169.80 1,542.43 261,897.73
complete : Printed tiles BOQ Item #86
Cement pointing struck joints, on walls, upto 20' height ATR
86 11-18-b M2 747.54 225.48 168,554.22
: Ratio 1:3 BOQ Item #87
Construction of Siran Right Bank Canal
District Mansehra
ITEM WISE SUMMARY OF COST (WORKS)

MRS 2016 Revised T.S


Sr. No. Description of Items Unit MRS 2016 Rate Revised T.S Amount Remarks
Item Code Quantity

1.375" thick mosaic flooring, including rubbing and ATR


87 10-21-a M2 1,246.64 1,117.03 1,392,538.52
polishing complete : Using grey cement BOQ Item #88

Provide & lay marble fine dressed stone flooring on


ATR
88 10-26-a surface in white cement complete: 3/4" thick (Badel, M2 203.75 1,943.89 396,068.04
BOQ Item #89
Silky black, Sunny white, Sunny Grey or eq)

ATR
89 11-09-b Cement plaster 1:4 upto 20' height 1/2" thick M2 1,562.34 215.00 335,903.39 BOQ Item #90 &
#114
Cement plaster 3/8" thick under soffit of RCC roof ATR
90 11-10-b M2 309.76 253.11 78,402.39
slabs only upto 20' height : (1:3) BOQ Item #91
Pacca brick work in ground floor Cement, sand mortar ATR
91 07-05-a-05 M3 186.29 8,003.98 1,491,042.06
1:6 BOQ Item #92
Damp proof course of cem. conc. 1:2:4 including
ATR
92 06-22-a-03 bitumen coat, 1 layer polythene & 1 coat bitumen (3" M2 4.23 770.95 3,257.38
BOQ Item #93
thick)
Pacca brick work in foundation and plinth in Cement, ATR
93 07-04-a-05 M3 79.61 7,433.74 591,830.93
sand mortar 1:6 BOQ Item #94
Erecting & removing formwork to concrete in any ATR
94 06-38-b M2 176,353.21 515.47 90,904,789.16
shape / position (Vertical) BOQ Item #95
ATR
Supply fabricate M.S reinforcement for cement
95 06-07-c Tonne 2,294.75 103,529.94 237,574,843.91 BOQ Item #96 &
concrete ( hot rolled deformed bars Grade 40)
#127
ATR
RCC in roof slab , beam , column and other structural
96 06-06-a-03 M³ 6,096.85 8,710.19 53,104,756.31 BOQ Item #97 &
member , in sithu or precast. Type C 1:2:4.
#129
ATR
RCC in raft foundation slab, base slab of column & ret.
97 06-06-b-03 M3 15,436.56 7,830.79 120,880,438.90 BOQ Item #98 &
wall etc, not including in 06-06. Type C (1:2:4)
#128
ATR
Plain Cement Concrete including placing, compacting,
98 06-05-i M3 8,281.12 5,090.88 42,158,166.91 BOQ Item #99 &
finishing & curing (Ratio 1:4:8)
#133
Excavation in foundation of building bridges etc ATR
99 03-23-d M³ 254.45 273.34 69,551.24
complete in Shingle gravel. BOQ Item #100

Carriage of surplus materials i/c loading/unloading to ATR


100 ATR Job 0.36 26,054,468.00 9,379,608.48
specified disposal site as per instructions of Engineer BOQ Item #101

ATR
Erection and removal of steel formwork for RCC or
101 ATR M² 70.00 47.98 3,358.60 BOQ
plain concrete vertical (Labor Rate only) (06-39-b)
Item #102
ATR
Supplying and Fixing PVC Water Stopper 8" wide 3/8"
102 24-40 M 9,016.93 440.77 3,974,391.06 BOQ
thick
Item #103
Grouting stone pitching or apron etc, in : Cement, ATR
103 19-31-a M2 696.12 -
sand mortar 1:3 BOQ Item #104
ATR
Providing and Laying stone pitching/filling, dry hand
104 19-25 M3 1,990.491 1,676.39 3,336,840.03 BOQ
packed in pitching & aprons
ATRItem #105
Providing and Laying stone pitching for top layer only :
105 19-28-b M3 815.520 2,655.28 2,165,433.95 BOQ
On level
ATRItem #106
Providing and Laying stone pitching for top layer only :
106 19-28-a M3 3,979.47 3,052.57 12,147,619.10 BOQ
On slope
ATRItem #107
Random rubble masonry in foundn. & plinth Dry
107 08-01-a M³ 28,533.91 2,715.59 77,486,396.53 BOQ
masonry
Item #108
ATR
Supply and Fixing of GI Pipe as per required diameter
108 ATR R. Ft. 1,220.000 1,295.00 1,579,900.00 BOQ
on the direction of Engineer Incharge
Item #109
ATR
Providing and Laying RCC pipe sewers complete as
109 23-03-c-09 M 20.000 12,118.93 242,378.60 BOQ
per ASTM C-76-79, Class IV : 36" i/d, Wall B
Item #110

ATR
Providing and Laying RCC pipe sewers complete as
110 23-03-c-05 M 20.000 5,465.50 109,310.00 BOQ
per ASTM C-76-79, Class IV : 24" i/d, Wall B
Item #111

ATR
Providing and Laying RCC pipe seweres complete as
111 23-03-c-03 M 50.000 3,850.96 192,548.00 BOQ
per ASTM C-76-79, Class IV : 18" i/d, Wall B
Item #112

Dressing & levelling earth to designed section gravel ATR


112 03-19-c work or soft rock not requiring blasting upto cut or fill 6 M3 100.000 40.83 4,083.00 BOQ
inches Item #113
ATR
Structural backfill using Common Material available at
113 03-60-c M3 102,673.13 435.23 44,686,428.37 BOQ
site
ATRItem #115
P/I gates for head regulator & Under Sluice i/c hoisting
114 ATR M 2
23.48 260,000.00 6,105,013.06 BOQ
device complete in all respect.
ATRItem #116
115 16-64 Bailing out water by Mechanical mean. M3 106,468.86 17.90 1,905,792.59 BOQ
ATRItem #117
Erection and removal of steel Form work for RCC or
116 06-39-b M2 14.00 772.27 10,811.78 BOQ
Plain Concrete vertical
ATRItem #118
Providing & Laying precast PCC blocks of ration 1:2:4
117 ATR No. 1,493.00 802.14 1,197,595.02 BOQ
having size 2' x 2' x 1'.
ATRItem #119
PCC 1:3:6 in mass concrete less formwork using 40%
118 06-36-b M3 61,173.18 4,221.30 258,230,357.22 BOQ
boulders
Item #120

Reinforced cement concrete work as in dams,


spillways, weirs, barrages, cross drainage works and
other hydraulic structures using crushed stone
aggregate(screening &
washing) and coarse sand i/c cost of all labour and ATR
119 06-06-d-03 material and all kinds of form works, moulds, M3 8,722.83 10,081.98 87,943,402.49 BOQ
shuttering lifting/pumping, curing, rendering and Item #121
finishing the exposed surface, cast in situ/precast
excluding the cost of steel reinforcement and labour
for bending binding also excludig cost of additives
which have to be paid separately. Type C (1:2:4)

ATR
Supplying stone and stone filling in GI wire crate and
120 19-26 M3 3,491.42 1,716.12 5,991,701.22 BOQ
its sewing, excluding cost of crates
Item #122
Construction of Siran Right Bank Canal
District Mansehra
ITEM WISE SUMMARY OF COST (WORKS)

MRS 2016 Revised T.S


Sr. No. Description of Items Unit MRS 2016 Rate Revised T.S Amount Remarks
Item Code Quantity
ATR
Provide & weave GI wire netting for wire crates 6"x9"
121 19-13-a-03 M2 38,841.34 369.52 14,352,652.90 BOQ
mesh : 8 SWG wire
Item #123
ATR
Providing and fixing MS steel grated trash rack as per
122 ATR M2 116.76 13,000.00 1,517,924.06 BOQ
drawings and instructions of Engineer.
Item #124

Procuring 6 mm steel sheets, cold bending &


fabricating to make 3.08 diameter circular pipe in
suitable lengths including inlets/outlet, cone, horizontal
& verticals bends, manholes & drainage arrangement,
painting on the inner sides all as per drawings &
specifications, ready to be lowered in pipe trenched, ATR
123 ATR supported on temporary or permanently embedded Tonne 0.000 227,530.00 - BOQ
steel/concrete supports. The pipe is to be aligned Item #125
/installed to line & grade field welded, including the
costs of non destructive tests, complete in all
respects. The work shall include the costs of all the
items required for providing complete steel pipe in
place, ready for concrete cladding

ATR
Supply & fabricate M.S. reinforcement for cement
124 06-07-b Tonne 1,702.23 110,254.06 187,677,768.55 BOQ
concrete (Hot rolled deformed bars Grade 60)
Item #126
ATR
4" thick PCC lining. using washed screened & graded
125 17-10-a-01 M³ 6,818.71 - BOQ
stone aggregate : in bed : ratio 1:2:4
Item #130
ATR
Plain Cement Concrete including placing,
126 06-05-f M³ 6,817.97 6,758.12 46,076,689.08 BOQ
compacting,finishing & curing (Ratio 1:2:4)
Item #132
ATR
Structural Excavation in Rock Material requiring
127 03-60-b M3 4,557.29 1,629.01 7,423,872.55 BOQ
blasting
Item #134
ATR
128 03-60-a Structural Excavation in Common Material M³ 30,565.278 315.25 9,635,704.00 BOQ
Item #135
ATR
Rock Excavation, dressing & disposal up to 50m
129 03-11-b M3 7,054.25 643.35 4,538,352.59 BOQ
Medium hard rock, requiring occasional blasting
Item #136

Excavation for core trench of Dam


Embankment/Spillway/Intake & Outlet Structure and ATR
130 03-68-d Irrigation System upto design depth in Hard Rock M3 71,051.28 436.15 30,989,015.82 BOQ
requiring 75% blasting i/c removing of material from Item #137
outside of the structure area

Excavation for core trench of Dam


Embankment/Spillway/Intake & Outlet Structure and ATR
131 03-68-c Irrigation System upto design depth in Medium Hard M3 127,892.30 371.52 47,514,548.85 BOQ
Rock requiring 50% blasting i/c removing of material Item #138
from outside of the structure area

Excavation for core trench of Dam


Embankment/Spillway/Intake & Outlet Structure and ATR
132 03-68-b Irrigation System upto design depth in Soft M3 682,092.29 306.89 209,327,302.57 BOQ
Rock/Shale requiring 20% blasting i/c removing of Item #139
material from outside of the structure area

Excavation for core trench of Dam


Embankment/Spillway/Intake & Outlet Structure and ATR
133 03-68 Irrigation System upto a minimum depth of 35 ft in M3 221,679.99 206.56 45,790,219.55 BOQ
common soil including removing of excavated material Item #140
by machinery in 1 KM radius

Excavation for core trench of Dam Embankment


/Spillway/Intake & Outlet Structure and Irrigation ATR
134 03-68-a System upto a minimum depth of 35 ft in shingle M3 68,394.60 215.37 14,730,145.63 BOQ
gravel including removing of excavated material by Item #141
machinery in 1 KM radius

Single layer of tiles 10"x5"x1.25" laid over 4" earth and Required as per
135 09-05 M2 327.75 1,261.92 413,595.28
1" mud plaster on top of RC roof slab site conditions

Required as per
136 14-69-a-02 P/F Fiber glass Water Tank 400 gallons. No. 1.00 9,379.42 9,379.42
site conditions
Required as per
137 14-69-a-01 P/F Fiber glass Water Tank 300 gallons. No. 1.00 7,884.51 7,884.51
site conditions

Supply and fixing of 2.0 HP Monoblock water pump


Required as per
138 14-80-a 1.5"x1.25" 3 stage model DE-S3 (Deen Pump) single No. 2.00 22,790.62 45,581.24
site conditions
phase for 150 ft head with all accessories.

Making and fixing steel grated doors, complete with Required as per
139 25-30 M2 13.75 8,088.33 111,214.54
locking arrangements & angle iron frame site conditions
Construction of Siran Right Bank Canal
District Mansehra
ITEM WISE SUMMARY OF COST (WORKS)

MRS 2016 Revised T.S


Sr. No. Description of Items Unit MRS 2016 Rate Revised T.S Amount Remarks
Item Code Quantity

Provide , Place & compact shoulder material (sandy /


silty gravel) in Dam Embankment, of specified Required as per
140 03-65 M3 30,391.34 284.77 8,654,541.45
grading, leveling/dressing i/c haulage for obtaining of site conditions
95% modified AASHTHO dry density.

Supply & fill new synthetic fibre/plastic bags 4-5 cft Required as per
141 19-04-a Nos. 16,587.00 218.85 3,630,064.95
capacity with sand or earth,sewing, stacking : in dry site conditions

Supply & fill new synthetic fibre/plastic bags 4-5cft


Required as per
142 19-04-b capacity with sand or earth,sewing, stacking : Under Nos. 16,587.00 263.85 4,376,479.95
site conditions
water

Supplying clean and screened river or pit sand within Required as per
143 03-43 M3 4,696.76 715.12 3,358,750.07
150m including removal of loose earth or overburden. site conditions

Required as per
144 16-14 Providing and fixing GI pipe railing (3 feet high) M 10.65 2,752.93 29,309.77
site conditions
Providing and Laying expansion joint of neoprene strip Required as per
145 16-44 R. M. 1,097.68 643.06 705,876.44
4"x1/4" and plastic bitumen site conditions

Providing and Laying cut, joint, test & disinfect GI pipe Required as per
146 24-16-c-03 R. M. 120.69 392.44 47,363.58
line Using light quality GI Pipe : 1" i/d site conditions

Required as per
147 19-33 Grouting stone filling or pitching with bajri M3 85.93 610.21 52,433.75
site conditions
Levelling and dressing stone filling under blocks and Required as per
148 19-36 M 3
107.04 498.07 53,312.21
grouting with shingle site conditions
Boring for Cast-in-place RCC Piles in Alluvial Soils : Required as per
149 16-27-a R. M. 4,583.97 5,103.35 23,393,594.64
Dia up to 760mm site conditions

Plain woodwork for regulation karries or needles etc. Required as per


150 12-02-a M3 2.76 144,275.56 398,690.88
complete as per specs : Deodar wood site conditions

Required as per
151 03-14-b Rehandling of Earthwork up to a lead of 25 m. M³ 113,682.05 69.53 7,904,312.81
site conditions
Formation of Embankment from Roadway Excavation
Required as per
152 03-61-a in Common Material including compaction by power M³ 29,150.22 321.26 9,364,800.70
site conditions
roller
Required as per
153 16-03-a Granular Sub Base Course using Pit Run Gravel M³ 54,699.89 1,257.96 68,810,269.54
site conditions
Required as per
154 06-21-a Filling expansion joints with bitumen R. M 11,000.71 294.62 3,241,029.42
site conditions
Required as per
155 17-01-a Formation, dressing and preparing sub-grade In bed M² 42,602.80 69.36 2,954,929.88
site conditions
Required as per
156 17-01-b Formation, dressing and preparing sub-grade On slope M² 111,394.77 96.84 10,787,469.59
site conditions

Providing and Laying cut, joint, test, disinfect PVC Required as per
157 24-18-a-01 R. M 18,273.88 375.08 6,854,168.02
pipeline BSS Class 'B' working pressure : 3" i/d site conditions

Filter granular backfill behind retaining wall


Required as per
158 19-47 (stone/boulder filling upto one meter to prevent M³ 525.98 1,257.27 661,294.83
site conditions
choking of weep holes)
Removal of tree:gith 150mm -300mm i/c removal of Required as per
159 03-57-a Nos. 800.00 486.61 389,288.00
stump site conditions
Removal of tree:gith 300mm -600mm i/c removal of Required as per
160 03-57-b Nos. 900.00 973.22 875,898.00
stump site conditions
Required as per
161 NSI Providing and installing air/water relief valves Nos. 13.000 78,185.55 1,016,412.21
site conditions
Extra labour for laying concrete (plain or reinforced) Required as per
162 06-12-a M3 1,022.020 794.58 812,076.65
From 20' upto 40' height site conditions

Extra labour for laying concrete (plain or reinforced) Required as per


163 06-12-a + 06-12-b M 3
681.340 1,589.16 1,082,758.27
For every extra 10' height (upto 60' height) site conditions

Painting two feet wide gauges, reading to 1/10th of a Required as per


164 13-18 M 115.818 422.61 48,945.99
foot. site conditions
Required as per
165 04-19-b Dismantling: Plain cement concrete 1:3:6 M3 226.501 1,727.81 391,349.94
site conditions
Filling and Compacting Soil, Earth and Boulders Required as per
166 03-32 M3 11,350.733 178.78 2,029,284.07
behind retaining walls (Available material) site conditions
Provide and place 4" thick PCC lining in channel
167 NSI M3 Taken in PC-I
(1:2:4)

168 NSI Provide and place1.5" thick Cement sand Mortar M3 Taken in PC-I

169 19-38-g-01 Laying stone or spawl filling M3 Taken in PC-I

Provide, place and compact coarse filter material


170 03-67 M3 Taken in PC-I
under stone pitching on horizontal slope surfaces

171 NSI Provide RCC railing as per drawings. M Taken in PC-I

Plain Cement Concrete including placing compacting


172 06-05-b M3 Taken in PC-I
finishing and curing complete 1:1.5:1.5

Supply & fill bricks in wire crates including sewing Required as per
173 19-18-a M3 7,678.690 1,247.67 9,580,471.15
crates, excl cost of crates: Stone orboulders site conditions

Required as per
176 17-02 Stabilized layer of cement, sand mortar 1:30 2" thick M² 134,974.708 259.42 35,015,138.75
site conditions

4" thick PCC lining, using washed screened & Required as per
177 17-10-a-01
graded/crushed stone aggregate : in bed : Ratio 1:2:4
M³ 3,836.125 6,818.71 26,157,420.64
site conditions
Construction of Siran Right Bank Canal
District Mansehra
ITEM WISE SUMMARY OF COST (WORKS)

MRS 2016 Revised T.S


Sr. No. Description of Items Unit MRS 2016 Rate Revised T.S Amount Remarks
Item Code Quantity

4" thick PCC lining, using washed screened &


Required as per
178 17-10-b-01 graded/crushed stone aggregate : On slope : Ratio M³ 9,055.139 7,106.74 64,352,520.48
site conditions
1:2:4

Cement Concrete (brick/stone ballast, 1.5" to


2"/nullah
Required as per
179 06-03-e shingle well graded and cleaned) in foundation & M³ 7,638.080 3,188.12 24,351,116.91
site conditions
plinth
(Ratio 1:6:18)

Required as per
180 NSI Admixture Chemical Liter 3,406.850 500.00 1,703,425.24
site conditions

Supply and Fixing Neoprene Bearing Pad as per


Required as per
181 16-30-a specs & design cm3 200,000.000 1.61 322,000.00
site conditions

Supplying and filling sand under floor or plugging in Required as per


182 07-30 M3 670.053 1,106.79 741,607.79
wells site conditions

Providing and Laying segments in Precast lining M Required as per


183 17-11-a 4,268.820 2,420.66 10,333,362.99
(Parabola type) Type A site conditions

M Required as per
NSI HDPE Pipe for Syphon-1 975.310 174,862.00 170,544,657.22
site conditions

M Required as per
NSI HDPE Pipe for Syphon-2 76.200 141,861.00 10,809,808.20
site conditions

M Required as per
NSI HDPE Pipe for Syphon-3 914.340 88,450.00 80,873,373.00
site conditions

Total Amount Rs. 2,312,908,046.58

Total Amount (Non Schedule Items) Rs. 22,534,186.67


Add 8% for District Mansehra Area Cost Factor Except in NSI/Market Rate 183,229,908.79

Total Amount Rs. 2,496,137,955.38

Converting into millions 2,496.138


Contractor's Premium at 10% below (249.614)

G. Total Amount Rs. 2,246.524


Construction of Siran Right Bank Canal
District Mansehra
ITEM WISE COMPARISON BETWEEN DETAILED ESTIMATE BOQ & VO-1 QUANTITIES AND COSTS
Revised
Detailed Approved Difference
Sr. MRS 2016 Detailed VO-1 MRS 2016 Revised Detailed Detailed Estimate Approved BOQ Difference
Description of Items Unit Estimate BOQ VO-1 Amount ( Revised Detailed
No. Item Code Estimate Quantity Rate Estimate Amount Amount Amount (BOQ - VO-1)
Quantity Quantity Estimate - BOQ)
Quantity

Providing and fixing stainless steel sink with


1 14-06-b drain board size 18"x36" including set of Each 4.00 4.00 3.00 3.00 2,585.80 10,343.20 10,343.20 7,757.40 7,757.40 2,585.80 -
brackets, waste pipe etc
Providing & Fixing Steel manhole cover with
2 14-37-d Each 6.00 6.00 8.00 8.00 3,443.75 20,662.50 20,662.50 27,550.00 27,550.00 (6,887.50) -
frame 18"x18" full heavy duty

3 23-11 Soakage pit ( 6' dia x 15' deep ) complete. No 6.00 6.00 6.00 6.00 16,376.25 98,257.50 98,257.50 98,257.50 98,257.50 - -
Providing and installing PVC tees BSS Class
4 24-27-a-02 Each 30.00 30.00 25.00 25.00 500.45 15,013.50 15,013.50 12,511.25 12,511.25 2,502.25 -
'B'working pressure : 3" i/d
Providing and installing PVC bends BSS
5 24-26-c-02 Each 22.00 22.00 18.00 18.00 291.54 6,413.88 6,413.88 5,247.72 5,247.72 1,166.16 -
Class 'D'working pressure : 3" i/d
Providing and Laying cut, joint, test, disinfect
6 24-18-c-05 PVC pipe line BSS Class 'D' working R. M 25.00 25.00 18.00 18.00 699.29 17,482.25 17,482.25 12,587.22 12,587.22 4,895.03 -
pressure : 3" i/d
Providing and installing PVC tees BSS Class
7 24-27-a-03 Each 15.00 15.00 10.00 10.00 687.85 10,317.75 10,317.75 6,878.50 6,878.50 3,439.25 -
'B'working pressure : 4" i/d
Providing and installing PVC bends BSS
8 24-26-c-03 Each 15.00 15.00 10.00 10.00 438.29 6,574.35 6,574.35 4,382.90 4,382.90 2,191.45 -
Class 'D'working pressure : 4" i/d
Providing and Laying cut, joint, test, disinfect
9 24-18-c-06 PVC pipe line BSS Class 'D' working R. M 90.00 90.00 55.00 55.00 788.70 70,983.00 70,983.00 43,378.50 43,378.50 27,604.50 -
pressure : 4" i/d
Providing and installing PVC sockets BSS
10 24-28-a-04 Each 10.00 10.00 5.00 5.00 1,360.30 13,603.00 13,603.00 6,801.50 6,801.50 6,801.50 -
Class 'B'working pressure : 6" i/d
Providing and installing PVC bends BSS
11 24-26-a-04 Each 9.00 9.00 4.00 4.00 920.87 8,287.83 8,287.83 3,683.48 3,683.48 4,604.35 -
Class 'B'working pressure : 6" i/d
Providing and Laying cut, joint, test, disinfect
12 24-18-a-03 PVC pipe line BSS Class 'B'working pressure R. M 160.00 160.00 105.00 105.00 914.20 146,272.00 146,272.00 95,991.00 95,991.00 50,281.00 -
: 6" i/d
Providing and Fixing of poly dex high
13 14-71-b pressure PPR (green including testing ect R. M 185.00 185.00 110.00 110.00 399.64 73,933.40 73,933.40 43,960.40 43,960.40 29,973.00 -
complete 20 mm(including all special etc)
Providing and Fixing of poly dex high
14 14-71-a pressure PPR(green including testing ect R. M 160.00 160.00 90.00 90.00 427.66 68,425.60 68,425.60 38,489.40 38,489.40 29,936.20 -
complete 25 mm(including all special etc)
Supply and Fixing CI manhole cover with
15 14-37-b Each 10.00 10.00 12.00 12.00 1,909.96 19,099.60 19,099.60 22,919.52 22,919.52 (3,819.92) -
frame etc complete 18" dia
Providing and fixing CI main hole cover with
16 14-37-a No 10.00 10.00 12.00 12.00 1,110.86 11,108.60 11,108.60 13,330.32 13,330.32 (2,221.72) -
frame etc complete 12" dia

Providing and Fixing CI floor trap including CI


17 14-31-b Each 6.00 6.00 6.00 6.00 793.80 4,762.80 4,762.80 4,762.80 4,762.80 - -
grating & concrete chamber all round : 4"x3"

Providing and fixing CP shower rose :


18 14-26-b No 5.00 5.00 6.00 6.00 665.13 3,325.65 3,325.65 3,990.78 3,990.78 (665.13) -
3/4"x6".
Providing and fixing gun metal peet / gate
19 14-28-a No 4.00 4.00 6.00 6.00 1,331.80 5,327.20 5,327.20 7,990.80 7,990.80 (2,663.60) -
valve (screwed ) 1" dia.
Providing and Fixing CP mixing valve for
20 14-27 No 4.00 4.00 6.00 6.00 2,129.13 8,516.52 8,516.52 12,774.78 12,774.78 (4,258.26) -
WHB, sink or shower

Providing and Fixing CP or brass oxidized


21 14-29-b Each 5.00 5.00 6.00 6.00 2,320.00 11,600.00 11,600.00 13,920.00 13,920.00 (2,320.00) -
swan-neck cock 1/2" dia : Double way

22 14-25 Providing and Fixing 1/2" CP tee stop cock Each 11.00 11.00 12.00 12.00 567.53 6,242.83 6,242.83 6,810.36 6,810.36 (567.53) -

Providing and Fixing glazed earthen ware


23 14-14-b Each 6.00 6.00 12.00 12.00 421.13 2,526.78 2,526.78 5,053.56 5,053.56 (2,526.78) -
soap dish Coloured
Providing and fixing best quality 5mm glass
24 14-17 No 5.00 5.00 6.00 6.00 914.81 4,574.05 4,574.05 5,488.86 5,488.86 (914.81) -
mirror 22"x16" size
Construction of Siran Right Bank Canal
District Mansehra
ITEM WISE COMPARISON BETWEEN DETAILED ESTIMATE BOQ & VO-1 QUANTITIES AND COSTS
Revised
Detailed Approved Difference
Sr. MRS 2016 Detailed VO-1 MRS 2016 Revised Detailed Detailed Estimate Approved BOQ Difference
Description of Items Unit Estimate BOQ VO-1 Amount ( Revised Detailed
No. Item Code Estimate Quantity Rate Estimate Amount Amount Amount (BOQ - VO-1)
Quantity Quantity Estimate - BOQ)
Quantity

Providing and fixing CP rail :24" long, 3/4"


25 14-16-a No 5.00 5.00 6.00 6.00 787.13 3,935.65 3,935.65 4,722.78 4,722.78 (787.13) -
dia.

26 14-15 Providing and fixing CP tailot paper holder. No 5.00 5.00 6.00 6.00 286.92 1,434.60 1,434.60 1,721.52 1,721.52 (286.92) -

27 14-13 Providing and fixing CP soap dish. No 5.00 5.00 6.00 6.00 537.03 2,685.15 2,685.15 3,222.18 3,222.18 (537.03) -

Providing and Fixing glazed earthen ware


28 14-10-b low down flushing cistern 3 gallons capacity : Each 5.00 5.00 6.00 6.00 2,781.00 13,905.00 13,905.00 16,686.00 16,686.00 (2,781.00) -
Coloured

Providing and Fixing glazed earthen ware


29 14-01-b WC European type excluding cost of seat & Each 5.00 5.00 6.00 6.00 5,118.63 25,593.15 25,593.15 30,711.78 30,711.78 (5,118.63) -
cover : Coloured

Supply and Fixing low level plastic flushing


30 14-78 Each 5.00 5.00 6.00 6.00 1,001.20 5,006.00 5,006.00 6,007.20 6,007.20 (1,001.20) -
cistern
Providing and Fixing glazed earthen ware
31 14-03-b WC squatting type with built-in foot rests : Each 5.00 5.00 6.00 6.00 1,719.75 8,598.75 8,598.75 10,318.50 10,318.50 (1,719.75) -
Coloured
Providing and Fixing angle iron brackets for :
32 14-46-a WHB and Each 4.00 4.00 6.00 6.00 246.00 984.00 984.00 1,476.00 1,476.00 (492.00) -
cistern
Providing and Fixing glazed earthen ware
33 14-05-a-02 WHB complete Size 22"x16" : Coloured with Each 5.00 5.00 6.00 6.00 3,012.80 15,064.00 15,064.00 18,076.80 18,076.80 (3,012.80) -
pedestal
Energy saver 32 Watts (Phillips or eq) with
34 ATR down light / simple holder and extra No. 15.00 15.00 20.00 20.00 450.00 6,750.00 6,750.00 9,000.00 9,000.00 (2,250.00) -
accessories etc as specified

35 ATR Supply and erection plastic box size 7"x4" No. 22.00 22.00 30.00 30.00 600.00 13,200.00 13,200.00 18,000.00 18,000.00 (4,800.00) -

36 ATR Supply and erection plastic box size 4"x4" No. 22.00 22.00 8.00 8.00 500.00 11,000.00 11,000.00 4,000.00 4,000.00 7,000.00 -
Supply and Erection gate-light fitting
37 15-63-a complete with holder & 160-Watt mercury Each 12.00 12.00 6.00 6.00 796.65 9,559.80 9,559.80 4,779.90 4,779.90 4,779.90 -
blended lamp: Small

Earthing of iron clad/aluminium switches etc


38 15-41 Job 2.00 2.00 1.00 1.00 5,822.66 11,645.32 11,645.32 5,822.66 5,822.66 5,822.66 -
with GI wire #8 SWG in GI pipe 0.5" dia

Supply and Erection 2'x2'x1/8" copper plate


39 15-42 including rivetting to copper tape & placing in Each 3.00 3.00 3.00 3.00 9,231.69 27,695.07 27,695.07 27,695.07 27,695.07 - -
mixture of salt and charcol etc
Supply and Erection single phase imported
40 15-71-d Each 3.00 3.00 6.00 6.00 624.94 1,874.82 1,874.82 3,749.64 3,749.64 (1,874.82) -
auto circuit breaker 30 Amp.

Supply and Erection single phase imported


41 15-71-c Each 8.00 8.00 8.00 8.00 472.44 3,779.52 3,779.52 3,779.52 3,779.52 - -
auto circuit breaker 20 Amp

Supply and Erection single phase imported


42 15-71-b Each 10.00 10.00 10.00 10.00 472.44 4,724.40 4,724.40 4,724.40 4,724.40 - -
auto circuit breaker 15 Amp
Supply and Erection transpower auto circuit
43 15-70-a breaker 3-phase, 400V fungus moisture Each 6.00 6.00 8.00 8.00 2,006.25 12,037.50 12,037.50 16,050.00 16,050.00 (4,012.50) -
proofing : 30 Amp.

Supply and Erection transpower auto circuit


44 15-70-c breaker 3-phase, 400V fungus moisture Each 3.00 3.00 2.00 2.00 5,238.94 15,716.82 15,716.82 10,477.88 10,477.88 5,238.94 -
proofing : 100 Amp
Construction of Siran Right Bank Canal
District Mansehra
ITEM WISE COMPARISON BETWEEN DETAILED ESTIMATE BOQ & VO-1 QUANTITIES AND COSTS
Revised
Detailed Approved Difference
Sr. MRS 2016 Detailed VO-1 MRS 2016 Revised Detailed Detailed Estimate Approved BOQ Difference
Description of Items Unit Estimate BOQ VO-1 Amount ( Revised Detailed
No. Item Code Estimate Quantity Rate Estimate Amount Amount Amount (BOQ - VO-1)
Quantity Quantity Estimate - BOQ)
Quantity

Supply and Erection single core PVC


45 15-05-e insulated copper conductor 250/440 V grade R. M 30.00 30.00 40.00 40.00 164.83 4,944.90 4,944.90 6,593.20 6,593.20 (1,648.30) -
cable : 7/0.044"

Supply and Erection single core PVC


46 15-05-c insulated copper R. M 300.00 300.00 450.00 450.00 69.50 20,850.00 20,850.00 31,275.00 31,275.00 (10,425.00) -
conductor 250/440 V grade cable : 7/0.029"

Supply and Erection single core PVC


47 15-05-a insulated copper conductor 250/440 V grade R. M 350.00 350.00 450.00 450.00 42.14 14,749.00 14,749.00 18,963.00 18,963.00 (4,214.00) -
cable : 3/0.029"

Supply and Erection white round globe with


48 15-56-c holder, gallery & 100 Watt bulb complete : Each 3.00 3.00 2.00 2.00 221.43 664.29 664.29 442.86 442.86 221.43 -
10" dia.

Supply and Erection PVC pipe for wiring


49 15-02-b-03 purpose complete Recessed in walls R. M 130.00 130.00 180.00 180.00 275.83 35,857.90 35,857.90 49,649.40 49,649.40 (13,791.50) -
including chase etc : 1" i/d
Supply and Erection PVC pipe for wiring
50 15-02-b-02 purpose complete Recessed in walls R. M 130.00 130.00 90.00 90.00 302.02 39,262.60 39,262.60 27,181.80 27,181.80 12,080.80 -
including chase etc : 3/4" i/d

Floor S/E cubical type factory fabricated floor


51 15-75-b / wall mounted main board steel complete No 2.00 2.00 1.00 1.00 38,157.65 76,315.30 76,315.30 38,157.65 38,157.65 38,157.65 -
recessed.

Supply and fixing electric AC exhaust/fresh


air circulation(Double way) 220/230 single
52 15-77-c Each 3.00 3.00 2.00 2.00 3,086.07 9,258.21 9,258.21 6,172.14 6,172.14 3,086.07 -
phase plastic frame body and blade
complete 12"x12"

S/E best quality ceilling fan complete with G-I


53 15-68-c No 15.00 15.00 6.00 6.00 3,845.53 57,682.95 57,682.95 23,073.18 23,073.18 34,609.77 -
rod conopy blade & regulator 56" sweep.

Supply and Erection girder clamp hook, 5/8"


54 15-25 Each 9.00 9.00 6.00 6.00 318.11 2,862.99 2,862.99 1,908.66 1,908.66 954.33 -
dia.for hanging ceiling fans
Supply and Erection tube light, including rod,
55 15-24-a choke etc complete Double rod (2x40 watts) Set 14.00 14.00 6.00 6.00 975.58 13,658.12 13,658.12 5,853.48 5,853.48 7,804.64 -
with 2 chokes & 2 starters
S/E tube light rod and choke complete 40
56 15-24-b No 14.00 14.00 10.00 10.00 454.14 6,357.96 6,357.96 4,541.40 4,541.40 1,816.56 -
watt.

Supply and Fixing Asia porcelin power plug


57 15-82 Each 30.00 30.00 20.00 20.00 151.88 4,556.40 4,556.40 3,037.60 3,037.60 1,518.80 -
30 Amp

Wiring of 2/3 pin 5 AMP plug point in 3/029


58 15-51 No 30.00 30.00 20.00 20.00 368.80 11,064.00 11,064.00 7,376.00 7,376.00 3,688.00 -
pvc insulated cable in pvc pipe recessed.

Wiring of light / fan / call bell point in 3-29 pvc


59 15-50 No 90.00 90.00 60.00 60.00 850.55 76,549.50 76,549.50 51,033.00 51,033.00 25,516.50 -
insulated cable in pvc pipe recessed.

Making and fixing grating in opening,


60 25-32 including fixing at site with flat iron 2"x3/8" M2 60.00 60.00 39.02 39.02 2,344.44 140,666.40 140,666.40 91,480.05 91,480.05 49,186.35 -
and 3/4" sq. bars
Construction of Siran Right Bank Canal
District Mansehra
ITEM WISE COMPARISON BETWEEN DETAILED ESTIMATE BOQ & VO-1 QUANTITIES AND COSTS
Revised
Detailed Approved Difference
Sr. MRS 2016 Detailed VO-1 MRS 2016 Revised Detailed Detailed Estimate Approved BOQ Difference
Description of Items Unit Estimate BOQ VO-1 Amount ( Revised Detailed
No. Item Code Estimate Quantity Rate Estimate Amount Amount Amount (BOQ - VO-1)
Quantity Quantity Estimate - BOQ)
Quantity

Filling, watering and ramming earth under


61 03-16-a M3 99.16 99.16 953.42 953.42 103.30 10,243.12 10,243.12 98,488.29 98,488.29 (88,245.17) -
floor with surplus earth from foundation, etc

Shoes, bends or offsets for cast iron rain


62 09-21 Each 17.00 17.00 9.00 9.00 1,747.97 29,715.49 29,715.49 15,731.73 15,731.73 13,983.76 -
water down pipe, including fixing & painting

Heads for cast iron rain water down pipe


63 09-20 fixed in place Each 17.00 17.00 9.00 9.00 1,832.34 31,149.78 31,149.78 16,491.06 16,491.06 14,658.72 -
including cost of clamp holdfast and painting

Cast iron rain water down pipe fixed in


64 09-19-a R. M 54.88 54.88 68.58 68.58 2,212.05 121,392.99 121,392.99 151,702.39 151,702.39 (30,309.40) -
position excluding heads & shoes : 4" dia

Plain Cement Concrete including placing,


65 06-05-h M3 4,457.29 4,383.38 467.08 467.08 5,861.65 26,127,052.36 25,693,862.70 2,737,859.48 2,737,859.48 23,389,192.88 -
compacting, finishing & curing (Ratio 1:3:6)

Preparing surface & painting with snowcem /


66 13-38-b weathershield paint : 2nd & subsequent M2 416.22 416.22 883.22 883.22 85.56 35,611.57 35,611.57 75,568.30 75,568.30 (39,956.74) -
coats
Preparing surface & painting with snowcem /
67 13-38-a M2 430.83 430.83 441.61 441.61 166.86 71,887.82 71,887.82 73,687.04 73,687.04 (1,799.23) -
weathershield paint : First coat
68 11-23-a-03 Distember New surface: three coats. M² 1,987.95 1,987.95 1,384.89 1,384.89 79.31 157,663.97 157,663.97 109,835.63 109,835.63 47,828.34 -

69 11-25-a-03 White washing: New surface : Three coats M2 1,987.95 1,987.95 1,384.89 1,384.89 40.16 79,835.90 79,835.90 55,617.18 55,617.18 24,218.72 -

70 11-22 Priming coat of chalk under distemper M 2


1,987.95 1,987.95 1,384.89 1,384.89 19.34 38,446.87 38,446.87 26,783.77 26,783.77 11,663.10 -
Providing and Fixing terrace railing of 2" i/d
71 25-33 conduit pipe 16 SWG welded with 5/8"x5/8" M2 55.00 55.00 36.57 36.57 3,368.16 185,248.80 185,248.80 123,173.61 123,173.61 62,075.19 -
sq bar 2.75' high complete

MS flat 1/2"x1/8" grill in windows of approved


72 12-50 M2 48.09 48.09 51.28 51.28 3,073.30 147,809.74 147,809.74 157,598.82 157,598.82 (9,789.09) -
design including painting 3 coats, complete

73 13-08-a French polishing complete : on new work . M² 358.12 358.12 257.52 257.52 671.13 240,345.08 240,345.08 172,829.40 172,829.40 67,515.68 -
Varnishing wood work, including cleaning &
74 13-09-c M2 358.12 358.12 257.52 257.52 53.44 19,137.93 19,137.93 13,761.87 13,761.87 5,376.06 -
preparing surface : Third coat
Varnishing wood work, including cleaning &
75 13-09-b M 2
358.12 358.12 257.52 257.52 61.53 22,035.12 22,035.12 15,845.21 15,845.21 6,189.92 -
preparing surface : Second coat

Varnishing wood work, including cleaning &


76 13-09-a M2 358.12 358.12 257.52 257.52 93.65 33,537.94 33,537.94 24,116.75 24,116.75 9,421.19 -
preparing surface : First coat

77 12-17-b P/F hydraulic Door Closer (Best Quality) Each 18.00 18.00 12.00 12.00 1,682.50 30,285.00 30,285.00 20,190.00 20,190.00 10,095.00 -

Providing and fixing sliding bolt to doors


78 12-18-c-01 Each 18.00 18.00 12.00 12.00 1,121.05 20,178.90 20,178.90 13,452.60 13,452.60 6,726.30 -
Brass sliding bolts : 10" long

Providing and fixing sliding bolt to doors


79 12-18-c-02 Each 18.00 18.00 12.00 12.00 1,426.05 25,668.90 25,668.90 17,112.60 17,112.60 8,556.30 -
Brass sliding bolts : 12" long

Provide & fix wooden box type wardrobe 22"


80 12-23-b deep Deodar wood boxing & deodar shelves M2 26.02 26.02 44.59 44.59 10,896.40 283,549.44 283,549.44 485,870.48 485,870.48 (202,321.03) -
etc
Construction of Siran Right Bank Canal
District Mansehra
ITEM WISE COMPARISON BETWEEN DETAILED ESTIMATE BOQ & VO-1 QUANTITIES AND COSTS
Revised
Detailed Approved Difference
Sr. MRS 2016 Detailed VO-1 MRS 2016 Revised Detailed Detailed Estimate Approved BOQ Difference
Description of Items Unit Estimate BOQ VO-1 Amount ( Revised Detailed
No. Item Code Estimate Quantity Rate Estimate Amount Amount Amount (BOQ - VO-1)
Quantity Quantity Estimate - BOQ)
Quantity

Supply and Fixing aluminium door/window,


81 12-53-a-01 M2 50.05 50.05 51.28 51.28 7,334.76 367,078.83 367,078.83 376,126.49 376,126.49 (9,047.66) -
Economy model Sliding window

Deodar wood framed, braced & battened


82 12-08-b doors & windows: 1.75" thick, 1" battens & M2 39.36 39.36 42.92 42.92 8,858.29 348,651.10 348,651.10 380,197.81 380,197.81 (31,546.71) -
3/4" planks

Provide & fix chowkat for doors, windows &


83 12-24-c CS windows, including holdfast etc : Deodar M2 41.96 41.96 42.92 42.92 2,758.60 115,753.52 115,753.52 118,399.11 118,399.11 (2,645.59) -
wood

Providing and fixing glazed tile colour printed


84 10-26-g R. M 55.20 55.20 39.32 39.32 636.89 35,153.25 35,153.25 25,042.51 25,042.51 10,110.74 -
border 3" wide

Glazed tile 1/4" thick dado jointed in white


85 10-38-c M2 169.80 169.80 138.10 138.10 1,542.43 261,897.73 261,897.73 213,009.58 213,009.58 48,888.15 -
cement complete : Printed tiles
Cement pointing struck joints, on walls, upto
86 11-18-b M2 747.54 747.54 441.61 441.61 225.48 168,554.22 168,554.22 99,574.22 99,574.22 68,980.00 -
20' height : Ratio 1:3
1.375" thick mosaic flooring, including
87 10-21-a rubbing and polishing complete : Using grey M2 1,246.64 1,246.64 443.88 443.88 1,117.03 1,392,538.52 1,392,538.52 495,827.28 495,827.28 896,711.24 -
cement
Provide & lay marble fine dressed stone
flooring on surface in white cement complete:
88 10-26-a M2 203.75 203.75 256.97 256.97 1,943.89 396,068.04 396,068.04 499,521.41 499,521.41 (103,453.37) -
3/4" thick (Badel, Silky black, Sunny white,
Sunny Grey or eq)

89 11-09-b Cement plaster 1:4 upto 20' height 1/2" thick M2 1,562.34 1,562.34 148,081.19 148,081.19 215.00 335,903.39 335,903.39 31,837,455.85 31,837,455.85 (31,501,552.46) -

Cement plaster 3/8" thick under soffit of RCC


90 11-10-b M2 309.76 309.76 228.26 228.26 253.11 78,402.39 78,402.39 57,774.89 57,774.89 20,627.50 -
roof slabs only upto 20' height : (1:3)

Pacca brick work in ground floor Cement,


91 07-05-a-05 M3 186.29 186.29 218.41 218.41 8,003.98 1,491,042.06 1,491,042.06 1,748,149.27 1,748,149.27 (257,107.21) -
sand mortar 1:6

Damp proof course of cem. conc. 1:2:4


92 06-22-a-03 including bitumen coat, 1 layer polythene & 1 M2 4.23 4.23 19.70 19.70 770.95 3,257.38 3,257.38 15,187.72 15,187.72 (11,930.33) -
coat bitumen (3" thick)

Pacca brick work in foundation and plinth in


93 07-04-a-05 M3 79.61 79.61 117.62 117.62 7,433.74 591,830.93 591,830.93 874,356.50 874,356.50 (282,525.57) -
Cement, sand mortar 1:6

Erecting & removing formwork to concrete in


94 06-38-b M2 176,353.21 145.90 145.90 515.47 90,904,789.16 - 75,207.07 75,207.07 90,829,582.09 -
any shape / position (Vertical)

Supply fabricate M.S reinforcement for


95 06-07-c cement concrete ( hot rolled deformed bars Tonne 2,294.75 2,147.12 1,110.72 1,110.72 103,529.94 237,574,843.91 222,291,588.21 114,992,774.96 114,992,774.96 122,582,068.96 -
Grade 40)

RCC in roof slab , beam , column and other


96 06-06-a-03 structural member , in sithu or precast. Type M³ 6,096.85 5,026.84 4,796.42 4,796.42 8,710.19 53,104,756.31 43,784,690.65 41,777,729.52 41,777,729.52 11,327,026.79 -
C 1:2:4.

RCC in raft foundation slab, base slab of


97 06-06-b-03 column & ret. wall etc, not including in 06-06. M3 15,436.56 15,010.96 4,930.08 4,930.08 7,830.79 120,880,438.90 117,547,710.61 38,606,421.16 38,606,421.16 82,274,017.73 -
Type C (1:2:4)

Plain Cement Concrete including placing,


98 06-05-i M3 8,281.12 14,744.68 16,371.81 16,371.81 5,090.88 42,158,166.91 75,063,391.54 83,346,920.09 83,346,920.09 (41,188,753.18) -
compacting, finishing & curing (Ratio 1:4:8)
Construction of Siran Right Bank Canal
District Mansehra
ITEM WISE COMPARISON BETWEEN DETAILED ESTIMATE BOQ & VO-1 QUANTITIES AND COSTS
Revised
Detailed Approved Difference
Sr. MRS 2016 Detailed VO-1 MRS 2016 Revised Detailed Detailed Estimate Approved BOQ Difference
Description of Items Unit Estimate BOQ VO-1 Amount ( Revised Detailed
No. Item Code Estimate Quantity Rate Estimate Amount Amount Amount (BOQ - VO-1)
Quantity Quantity Estimate - BOQ)
Quantity

Excavation in foundation of building bridges


99 03-23-d M³ 254.45 254.45 397.26 397.26 273.34 69,551.24 69,551.24 108,587.05 108,587.05 (39,035.80) -
etc complete in Shingle gravel.

Carriage of surplus materials i/c


100 ATR loading/unloading to specified disposal site Job 0.36 1.00 1.00 26,054,468.00 9,379,608.48 - 26,054,468.00 26,054,468.00 (16,674,859.52) -
as per instructions of Engineer

Erection and removal of steel formwork for


101 ATR RCC or plain concrete vertical (Labor Rate M² 70.00 304,239.68 210,209.55 210,209.55 47.98 3,358.60 14,597,419.65 10,085,854.21 10,085,854.21 (10,082,495.61) -
only) (06-39-b)

Supplying and Fixing PVC Water Stopper 8"


102 24-40 M 9,016.93 9,332.49 5,637.48 5,637.48 440.77 3,974,391.06 4,113,480.44 2,484,832.06 2,484,832.06 1,489,559.00 -
wide 3/8" thick

Grouting stone pitching or apron etc, in :


103 19-31-a M2 55,207.38 55,207.38 696.12 - - 38,430,961.37 38,430,961.37 (38,430,961.37) -
Cement, sand mortar 1:3

Providing and Laying stone pitching/filling,


104 19-25 M3 1,990.491 2,047.040 3,264.60 3,264.600 1,676.39 3,336,840.03 3,431,637.45 5,472,742.79 5,472,742.79 (2,135,902.76) -
dry hand packed in pitching & aprons

Providing and Laying stone pitching for top


105 19-28-b M3 815.520 815.520 7,212.66 7,212.660 2,655.28 2,165,433.95 2,165,433.95 19,151,631.84 19,151,631.84 (16,986,197.90) -
layer only : On level
Providing and Laying stone pitching for top
106 19-28-a M3 3,979.47 3,979.47 9,616.81 9,616.81 3,052.57 12,147,619.10 12,147,619.10 29,355,985.70 29,355,985.70 (17,208,366.60) -
layer only : On slope

Random rubble masonry in foundn. & plinth


107 08-01-a M³ 28,533.91 29,052.78 32,104.86 32,104.86 2,715.59 77,486,396.53 78,895,437.33 87,183,636.77 87,183,636.77 (9,697,240.24) -
Dry masonry

Supply and Fixing of GI Pipe as per required


108 ATR diameter on the direction of Engineer R. Ft. 1,220.000 1,220.000 560.00 560.000 1,295.00 1,579,900.00 1,579,900.00 725,200.00 725,200.00 854,700.00 -
Incharge

Providing and Laying RCC pipe sewers


109 23-03-c-09 complete as per ASTM C-76-79, Class IV : M 20.000 152.42 152.420 12,118.93 242,378.60 - 1,847,167.31 1,847,167.31 (1,604,788.71) -
36" i/d, Wall B

Providing and Laying RCC pipe sewers


110 23-03-c-05 complete as per ASTM C-76-79, Class IV : M 20.000 152.42 152.420 5,465.50 109,310.00 - 833,051.51 833,051.51 (723,741.51) -
24" i/d, Wall B
Providing and Laying RCC pipe seweres
111 23-03-c-03 complete as per ASTM C-76-79, Class IV : M 50.000 266.74 266.740 3,850.96 192,548.00 - 1,027,205.07 1,027,205.07 (834,657.07) -
18" i/d, Wall B

Dressing & levelling earth to designed


112 03-19-c section gravel work or soft rock not requiring M3 100.000 35,644.63 35,644.630 40.83 4,083.00 - 1,455,370.24 1,455,370.24 (1,451,287.24) -
blasting upto cut or fill 6 inches

Structural backfill using Common Material


113 03-60-c M3 102,673.13 117,743.67 56,117.18 56,117.18 435.23 44,686,428.37 51,245,576.27 24,423,880.25 24,423,880.25 20,262,548.11 -
available at site

P/I gates for head regulator & Under Sluice


114 ATR M2 23.48 23.48 3.72 3.72 260,000.00 6,105,013.06 6,105,013.06 967,200.00 967,200.00 5,137,813.06 -
i/c hoisting device complete in all respect.

115 16-64 Bailing out water by Mechanical mean. M3 106,468.86 220,280.39 220,280.40 220,280.40 17.90 1,905,792.59 3,943,018.98 3,943,019.16 3,943,019.16 (2,037,226.57) -

Erection and removal of steel Form work for


116 06-39-b M2 14.00 60,847.93 13,221.35 13,221.35 772.27 10,811.78 46,991,031.87 10,210,451.96 10,210,451.96 (10,199,640.18) -
RCC or Plain Concrete vertical
Construction of Siran Right Bank Canal
District Mansehra
ITEM WISE COMPARISON BETWEEN DETAILED ESTIMATE BOQ & VO-1 QUANTITIES AND COSTS
Revised
Detailed Approved Difference
Sr. MRS 2016 Detailed VO-1 MRS 2016 Revised Detailed Detailed Estimate Approved BOQ Difference
Description of Items Unit Estimate BOQ VO-1 Amount ( Revised Detailed
No. Item Code Estimate Quantity Rate Estimate Amount Amount Amount (BOQ - VO-1)
Quantity Quantity Estimate - BOQ)
Quantity

Providing & Laying precast PCC blocks of


117 ATR No. 1,493.00 1,493.00 1,176.00 1,176.00 802.14 1,197,595.02 1,197,595.02 943,316.64 943,316.64 254,278.38 -
ration 1:2:4 having size 2' x 2' x 1'.

PCC 1:3:6 in mass concrete less formwork


118 06-36-b M3 61,173.18 129,268.57 77,672.74 77,672.74 4,221.30 258,230,357.22 545,681,397.02 327,879,937.36 327,879,937.36 (69,649,580.14) -
using 40% boulders

Reinforced cement concrete work as in


dams, spillways, weirs, barrages, cross
drainage works and other hydrolic structures
using crushed stone aggregate(screening &
washing) and coarse sand i/c cost of all
labour and material and all kinds of form
119 06-06-d-03 works, moulds, shuttering lifting/pumping, M3 8,722.83 8,385.36 25,440.09 25,440.09 10,081.98 87,943,402.49 84,540,999.66 256,486,478.58 256,486,478.58 (168,543,076.09) -
curing, rendering and finishing the exposed
surface, cast in situ/precast excluding the
cost of steel reinforcement and labour for
bending binding also excludig cost of
additives which have to be paid separately.
Type C (1:2:4)

Supplying stone and stone filling in GI wire


120 19-26 M3 3,491.42 11,170.11 6,710.96 - 1,716.12 5,991,701.22 19,169,254.70 11,516,812.68 - (5,525,111.45) (11,516,812.68)
crate and its sewing, excluding cost of crates

Provide & weave GI wire netting for wire


121 19-13-a-03 M2 38,841.34 38,841.34 28,978.19 28,978.19 369.52 14,352,652.90 14,352,652.90 10,708,020.77 10,708,020.77 3,644,632.13 -
crates 6"x9" mesh : 8 SWG wire

Providing and fixing MS steel grated trash


122 ATR rack as per drawings and instructions of M2 116.76 100.86 15.61 15.61 13,000.00 1,517,924.06 1,311,224.06 202,930.00 202,930.00 1,314,994.06 -
Engineer.

Procuring 6 mm steel sheets, cold bending &


fabricating to make 3.08 diameter circular
pipe in suitable lengths including inlets/outlet,
cone, horizontal & verticals bends, manholes
& drainage arrangement, painting on the
inner sides all as per drawings &
specifications, ready to be lowered in pipe
trenched, supported on temporary or
123 ATR Tonne 0.000 270.430 189.52 189.520 227,530.00 - 61,530,937.90 43,121,485.60 43,121,485.60 (43,121,485.60) -
permanently embedded steel/concrete
supports. The pipe is to be aligned /installed
to line & grade field welded, including the
costs of non destructive tests, complete in all
respects. The work shall include the costs of
all the items required for providing complete
steel pipe in place, ready for concrete
cladding

Supply & fabricate M.S. reinforcement for


124 06-07-b cement concrete (Hot rolled deformed bars Tonne 1,702.23 1,950.46 2,715.20 2,715.20 110,254.06 187,677,768.55 215,046,133.87 299,361,823.71 299,361,823.71 (111,684,055.16) -
Grade 60)

4" thick PCC lining. using washed screened


125 17-10-a-01 & graded stone aggregate : in bed : ratio M³ 8,565.84 8,565.84 6,818.71 - - 58,407,978.87 58,407,978.87 (58,407,978.87) -
1:2:4
Construction of Siran Right Bank Canal
District Mansehra
ITEM WISE COMPARISON BETWEEN DETAILED ESTIMATE BOQ & VO-1 QUANTITIES AND COSTS
Revised
Detailed Approved Difference
Sr. MRS 2016 Detailed VO-1 MRS 2016 Revised Detailed Detailed Estimate Approved BOQ Difference
Description of Items Unit Estimate BOQ VO-1 Amount ( Revised Detailed
No. Item Code Estimate Quantity Rate Estimate Amount Amount Amount (BOQ - VO-1)
Quantity Quantity Estimate - BOQ)
Quantity

Plain Cement Concrete including placing,


126 06-05-f M³ 6,817.97 9,174.10 4,905.86 4,905.86 6,758.12 46,076,689.08 61,999,694.18 33,154,390.58 33,154,390.58 12,922,298.50 -
compacting,finishing & curing (Ratio 1:2:4)

Structural Excavation in Rock Material


127 03-60-b M3 4,557.291 604.390 5,310.30 5,310.300 1,629.01 7,423,872.55 984,557.35 8,650,531.80 8,650,531.80 (1,226,659.25) -
requiring blasting

128 03-60-a Structural Excavation in Common Material M³ 30,565.278 27,046.412 62,673.89 62,673.890 315.25 9,635,704.00 8,526,381.49 19,757,943.82 19,757,943.82 (10,122,239.83) -
Construction of Siran Right Bank Canal
District Mansehra
ITEM WISE COMPARISON BETWEEN DETAILED ESTIMATE BOQ & VO-1 QUANTITIES AND COSTS
Revised
Detailed Approved Difference
Sr. MRS 2016 Detailed VO-1 MRS 2016 Revised Detailed Detailed Estimate Approved BOQ Difference
Description of Items Unit Estimate BOQ VO-1 Amount ( Revised Detailed
No. Item Code Estimate Quantity Rate Estimate Amount Amount Amount (BOQ - VO-1)
Quantity Quantity Estimate - BOQ)
Quantity

Rock Excavation, dressing & disposal up to


129 03-11-b 50m Medium hard rock, requiring occasional M3 7,054.25 7,054.25 3,973.04 3,973.04 643.35 4,538,352.59 4,538,352.59 2,556,055.28 2,556,055.28 1,982,297.31 -
blasting

Excavation for core trench of Dam


Embankment/Spillway/Intake & Outlet
Structure and Irrigation System upto design
130 03-68-d M3 71,051.28 104,530.59 271,445.68 271,445.68 436.15 30,989,015.82 45,591,017.74 118,391,033.33 118,391,033.33 (87,402,017.51) -
depth in Hard Rock requiring 75% blasting i/c
removing of material from outside of the
structure area

Excavation for core trench of Dam


Embankment/Spillway/Intake & Outlet
Structure and Irrigation System upto design
131 03-68-c M3 127,892.30 104,530.59 159,804.95 159,804.95 371.52 47,514,548.85 38,835,205.58 59,370,735.02 59,370,735.02 (11,856,186.17) -
depth in Medium Hard Rock requiring 50%
blasting i/c removing of material from outside
of the structure area

Excavation for core trench of Dam


Embankment/Spillway/Intake & Outlet
Structure and Irrigation System upto design
132 03-68-b M3 682,092.29 313,591.78 472,009.85 472,009.85 306.89 209,327,302.57 96,238,180.23 144,855,102.87 144,855,102.87 64,472,199.71 -
depth in Soft Rock/Shale requiring 20%
blasting i/c removing of material from outside
of the structure area

Excavation for core trench of Dam


Embankment/Spillway/Intake & Outlet
Structure and Irrigation System upto a
133 03-68 M3 221,679.99 209,061.18 60,699.90 60,699.90 206.56 45,790,219.55 43,183,678.21 12,538,171.34 12,538,171.34 33,252,048.20 -
minimum depth of 35 ft in common soil
including removing of excavated material by
machinery in 1 KM radius

Excavation for core trench of Dam


Embankment /Spillway/Intake & Outlet
Structure and Irrigation System upto a
134 03-68-a M3 68,394.60 353,565.87 32,997.30 32,997.30 215.37 14,730,145.63 76,147,480.82 7,106,628.50 7,106,628.50 7,623,517.13 -
minimum depth of 35 ft in shingle gravel
including removing of excavated material by
machinery in 1 KM radius

Single layer of tiles 10"x5"x1.25" laid over 4"


135 09-05 earth and 1" mud plaster on top of RC roof M2 327.75 327.75 1,261.92 413,595.28 413,595.28 - 413,595.28 -
slab
136 14-69-a-02 P/F Fiber glass Water Tank 400 gallons. No. 1.00 1.00 9,379.42 9,379.42 9,379.42 - - 9,379.42 -

137 14-69-a-01 P/F Fiber glass Water Tank 300 gallons. No. 1.00 1.00 7,884.51 7,884.51 7,884.51 - - 7,884.51 -

Supply and fixing of 2.0 HP Monoblock water


pump 1.5"x1.25" 3 stage model DE-S3
138 14-80-a No. 2.00 2.00 22,790.62 45,581.24 45,581.24 - - 45,581.24 -
(Deen Pump) single phase for 150 ft head
with all accessories.

Making and fixing steel grated doors,


139 25-30 complete with locking arrangements & angle M2 13.75 13.75 8,088.33 111,214.54 111,214.54 - - 111,214.54 -
iron frame

Provide , Place & compact shoulder material


(sandy / silty gravel) in Dam Embankment, of
140 03-65 specified grading, leveling/dressing i/c M3 30,391.34 39,074.58 284.77 8,654,541.45 11,127,267.58 - - 8,654,541.45 -
haulage for obtaining of 95% modified
AASHTHO dry density.
Construction of Siran Right Bank Canal
District Mansehra
ITEM WISE COMPARISON BETWEEN DETAILED ESTIMATE BOQ & VO-1 QUANTITIES AND COSTS
Revised
Detailed Approved Difference
Sr. MRS 2016 Detailed VO-1 MRS 2016 Revised Detailed Detailed Estimate Approved BOQ Difference
Description of Items Unit Estimate BOQ VO-1 Amount ( Revised Detailed
No. Item Code Estimate Quantity Rate Estimate Amount Amount Amount (BOQ - VO-1)
Quantity Quantity Estimate - BOQ)
Quantity

Supply & fill new synthetic fibre/plastic bags


141 19-04-a 4-5 cft capacity with sand or earth,sewing, Nos. 16,587.00 16,587.00 218.85 3,630,064.95 3,630,064.95 - - 3,630,064.95 -
stacking : in dry

Supply & fill new synthetic fibre/plastic bags


142 19-04-b 4-5cft capacity with sand or earth,sewing, Nos. 16,587.00 16,587.00 263.85 4,376,479.95 4,376,479.95 - - 4,376,479.95 -
stacking : Under water

Supplying clean and screened river or pit


143 03-43 sand within 150m including removal of loose M3 4,696.76 4,696.76 715.12 3,358,750.07 3,358,750.07 - - 3,358,750.07 -
earth or overburden.

Providing and fixing GI pipe railing (3 feet


144 16-14 M 10.65 10.65 2,752.93 29,309.77 29,309.77 - - 29,309.77 -
high)

Providing and Laying expansion joint of


145 16-44 R. M. 1,097.68 1,097.68 643.06 705,876.44 705,876.44 - - 705,876.44 -
neoprene strip 4"x1/4" and plastic bitumen

Providing and Laying cut, joint, test &


146 24-16-c-03 disinfect GI pipe line Using light quality GI R. M. 120.69 120.69 392.44 47,363.58 47,363.58 - - 47,363.58 -
Pipe : 1" i/d

147 19-33 Grouting stone filling or pitching with bajri M3 85.93 85.93 610.21 52,433.75 52,433.75 - - 52,433.75 -

Levelling and dressing stone filling under


148 19-36 M3 107.04 107.04 498.07 53,312.21 53,312.21 - - 53,312.21 -
blocks and grouting with shingle

Boring for Cast-in-place RCC Piles in Alluvial


149 16-27-a R. M. 4,583.97 4,583.97 5,103.35 23,393,594.64 23,393,594.64 - - 23,393,594.64 -
Soils : Dia up to 760mm

Plain woodwork for regulation karries or


150 12-02-a needles etc. complete as per specs : Deodar M3 2.76 2.76 144,275.56 398,690.88 398,690.88 - - 398,690.88 -
wood

Rehandling of Earthwork up to a lead of 25


151 03-14-b M³ 113,682.05 104,530.59 69.53 7,904,312.81 7,268,012.07 - - 7,904,312.81 -
m.
Construction of Siran Right Bank Canal
District Mansehra
ITEM WISE COMPARISON BETWEEN DETAILED ESTIMATE BOQ & VO-1 QUANTITIES AND COSTS
Revised
Detailed Approved Difference
Sr. MRS 2016 Detailed VO-1 MRS 2016 Revised Detailed Detailed Estimate Approved BOQ Difference
Description of Items Unit Estimate BOQ VO-1 Amount ( Revised Detailed
No. Item Code Estimate Quantity Rate Estimate Amount Amount Amount (BOQ - VO-1)
Quantity Quantity Estimate - BOQ)
Quantity

Formation of Embankment from Roadway


152 03-61-a Excavation in Common Material including M³ 29,150.22 50,879.14 321.26 9,364,800.70 16,345,433.24 - - 9,364,800.70 -
compaction by power roller

Granular Sub Base Course using Pit Run


153 16-03-a M³ 54,699.89 54,699.89 1,257.96 68,810,269.54 68,810,269.54 - - 68,810,269.54 -
Gravel

154 06-21-a Filling expansion joints with bitumen R. M 11,000.71 5,448.52 294.62 3,241,029.42 1,605,242.06 - - 3,241,029.42 -
Formation, dressing and preparing sub-grade
155 17-01-a M² 42,602.80 1,783.36 69.36 2,954,929.88 123,694.12 - - 2,954,929.88 -
In bed

Formation, dressing and preparing sub-grade


156 17-01-b M² 111,394.77 13,766.24 96.84 10,787,469.59 1,333,122.91 - - 10,787,469.59 -
On slope

Providing and Laying cut, joint, test, disinfect


157 24-18-a-01 PVC pipeline BSS Class 'B' working pressure R. M 18,273.88 28,144.17 375.08 6,854,168.02 10,556,315.08 - - 6,854,168.02 -
: 3" i/d

Filter granular backfill behind retaining wall


158 19-47 (stone/boulder filling upto one meter to M³ 525.98 820.27 1,257.27 661,294.83 1,031,303.13 - - 661,294.83 -
prevent choking of weep holes)

Removal of tree:gith 150mm -300mm i/c


159 03-57-a Nos. 800.00 300.00 486.61 389,288.00 145,983.00 - - 389,288.00 -
removal of stump
Removal of tree:gith 300mm -600mm i/c
160 03-57-b Nos. 900.00 100.00 973.22 875,898.00 97,322.00 - - 875,898.00 -
removal of stump

161 NSI Providing and installing air/water relief valves Nos. 13.000 10.000 78,185.55 1,016,412.21 781,855.54 - - 1,016,412.21 -

Extra labour for laying concrete (plain or


162 06-12-a M3 1,022.020 861.060 794.58 812,076.65 684,181.05 - - 812,076.65 -
reinforced) From 20' upto 40' height

Extra labour for laying concrete (plain or


06-12-a + 06-
163 reinforced) For every extra 10' height (upto M3 681.340 574.040 1,589.16 1,082,758.27 912,241.41 - - 1,082,758.27 -
12-b
60' height)

Painting two feet wide gauges, reading to


164 13-18 M 115.818 115.818 422.61 48,945.99 48,945.99 - - 48,945.99 -
1/10th of a foot.

165 04-19-b Dismantling: Plain cement concrete 1:3:6 M3 226.501 226.501 1,727.81 391,349.94 391,349.94 - 391,349.94 -

Filling and Compacting Soil, Earth and


166 03-32 Boulders behind retaining walls (Available M3 11,350.733 11,350.733 178.78 2,029,284.07 2,029,284.07 - 2,029,284.07 -
material)

Provide and place 4" thick PCC lining in


167 NSI M3 - - - -
channel (1:2:4)
Provide and place1.5" thick Cement sand
168 NSI M3 - - - -
Mortar

169 19-38-g-01 Laying stone or spawl filling M3 - - - -

Provide, place and compact coarse filter


170 03-67 material under stone pitching on horizontal M3 - - - -
slope surfaces

171 NSI Provide RCC railing as per drawings. M - - - -


Construction of Siran Right Bank Canal
District Mansehra
ITEM WISE COMPARISON BETWEEN DETAILED ESTIMATE BOQ & VO-1 QUANTITIES AND COSTS
Revised
Detailed Approved Difference
Sr. MRS 2016 Detailed VO-1 MRS 2016 Revised Detailed Detailed Estimate Approved BOQ Difference
Description of Items Unit Estimate BOQ VO-1 Amount ( Revised Detailed
No. Item Code Estimate Quantity Rate Estimate Amount Amount Amount (BOQ - VO-1)
Quantity Quantity Estimate - BOQ)
Quantity

Plain Cement Concrete including placing


172 06-05-b compacting finishing and curing complete M3 - - - -
1:1.5:1.5

Supply & fill bricks in wire crates including


173 19-18-a sewing crates, excl cost of crates: Stone M3 7,678.690 6,710.960 1,247.67 9,580,471.15 - 8,373,063.46 9,580,471.15 8,373,063.46
orboulders

Stabilized layer of cement, sand mortar 1:30


176 17-02 M² 134,974.708 259.42 35,015,138.75 35,015,138.75 -
2" thick

4" thick PCC lining, using washed screened


&
177 17-10-a-01 M³ 3,836.125 6,818.71 26,157,420.64 26,157,420.64 -
graded/curshed stone aggregate : in bed :
Ratio 1:2:4
4" thick PCC lining, using washed screened
&
178 17-10-b-01 M³ 9,055.139 7,106.74 64,352,520.48 64,352,520.48 -
graded/curshed stone aggregate : On slope :
Ratio 1:2:4

Cement Concrete (brick/stone ballast, 1.5"


to 2"/nullah
179 06-03-e shingle well graded and cleaned) in M³ 7,638.080 3,188.12 24,351,116.91 24,351,116.91
foundation & plinth
(Ratio 1:6:18)

180 NSI Admixture Chemical Liter 3,406.850 500.00 1,703,425.24 1,703,425.24 -

Supply and Fixing Neoprene Bearing Pad as


181 16-30-a per specs & design cm3 200,000.000 1.61 322,000.00 322,000.00 -

Supplying and filling sand under floor or


182 07-30 M3 670.053 1,106.79 741,607.79 741,607.79 -
plugging in wells

Providing and Laying segments in Precast


183 17-11-a M 4,268.820 2,420.66 10,333,362.99 10,333,362.99 -
lining (Parabola type) Type A

Total Amount Rs. 2,050,680,208.16 2,196,990,479.91 1,999,788,293 1,996,644,543 50,891,915.64 (3,143,749.21)


Total Amount (Non Schedule Items) Rs. 22,534,186.67 87,134,895.24 82,131,454.45 82,131,454.45 (59,597,267.78) -
Add 8% for District Mansehra Area Cost Factor Except in NSI/Market Rate 162,251,681.72 168,788,446.77 153,412,547.05 153,161,047.11 8,839,134.67 (251,499.94)

Total Amount Rs. 2,212,931,889.88 2,365,778,926.68 2,153,200,839.57 2,149,805,590.42 59,731,050.32 (3,395,249.15)


Converting into millions 2,212.932 2,365.779 2,153.201 2,149.806 59.73 (3.40)
Contractor's Premium at 10% below (221.293) (236.578) (215.320) (214.981) (5.97) 0.34
G. Total Amount Rs. 1,991.639 2,129.201 1,937.881 1,934.825 53.76 (3.06)
Construction of Siran Right Bank Canal
District Mansehra
BILL OF QUANTITY
Bill No. 01 Offtake Structure & Head Regulator Main Canal
MRS 2016
Sr.No. Description of items Unit Quantity Rate Amount Remarks
Item Code
ATR
1.1 16-64 Bailing out water by Mechanical mean. M3 106,468.86 17.90 1,905,792.59 BOQ
Item # 117

Provide , Place & compact shoulder material


(sandy / silty gravel) in Dam Embankment, of
Required as per
1.2 03-65 specified grading, leveling/dressing i/c haulage M3 30,391.34 284.77 8,654,541.45
site conditions
for obtaining of 95% modified AASHTHO dry
density.

Supply & fill new synthetic fibre/plastic bags 4-5


Required as per
1.3 19-04-a cft capacity with sand or earth,sewing, Nos. 16,587.00 218.85 3,630,064.95
site conditions
stacking : in dry

Supply & fill new synthetic fibre/plastic bags 4-


Required as per
1.4 19-04-b 5cft capacity with sand or earth,sewing, Nos. 16,587.00 263.85 4,376,479.95
site conditions
stacking : Under water

Supplying clean and screened river or pit sand


Required as per
1.5 03-43 within 150m including removal of loose earth or M3 4,696.76 715.12 3,358,750.07
site conditions
overburden.

Excavation for core trench of Dam Embankment


/Spillway/Intake & Outlet Structure and Irrigation ATR
1.6 03-68-a System upto a minimum depth of 35 ft in M3 39,974.09 215.37 8,609,219.95 BOQ
shingle gravel including removing of excavated Item # 141
material by machinery in 1 KM radius

Rock Excavation, dressing & disposal up to ATR


1.7 03-11-b 50m Medium hard rock, requiring occasional M3 7,054.25 643.35 4,538,352.59 BOQ
blasting Item # 136

Plain Cement Concrete including placing, ATR


1.8 06-05-i compacting, finishing & curing (Ratio 1:4:8) M3 107.25 5090.88 545,986.70 BOQ Item #99 &
#133
ATR
Provide & weave GI wire netting for wire crates
1.9 19-13-a-03 M2 24,334.21 369.52 8,991,979.12 BOQ
6"x9" mesh : 8 SWG wire
Item # 123
ATR
Supplying stone and stone filling in GI wire
1.10 19-26 M3 0.00 1,716.12 0.00 BOQ
crate and its sewing, excluding cost of crates
Item # 122

Reinforced cement concrete work as in dams,


spillways, weirs, barrages, cross drainage
works and other hydrolic structures using
crushed stone aggregate(screening &
washing) and coarse sand i/c cost of all labour
ATR
and material and all kinds of form works,
1.11 06-06-d-03 M3 3,406.85 10,081.98 34,347,798.45 BOQ
moulds, shuttering lifting/pumping, curing,
Item # 121
rendering and finishing the exposed surface,
cast in situ/precast excluding the cost of steel
reinforcement and labour for bending binding
also excludig cost of additives which have to be
paid separately. Type C (1:2:4)

Supply & fabricate M.S. reinforcement for ATR


1.12 06-07-b cement concrete (Hot rolled deformed bars Tonne 468.09 110,254.06 51,608,822.95 BOQ
Grade 60) Item # 126
Required as per
1.13 16-14 Providing and fixing GI pipe railing (3 feet high) M 10.65 2,752.93 29,309.77
site conditions
ATR
PCC 1:3:6 in mass concrete less formwork
1.14 06-36-b M3 4,176.92 4,221.30 17,632,053.11 BOQ
using 40% boulders
Item # 120
ATR
Plain Cement Concrete including placing,
1.15 06-05-h M3 57.55 5,861.65 337,361.03 BOQ Item #66
compacting, finishing & curing (Ratio 1:3:6)
& #131
ATR
Providing & Laying precast PCC blocks of ration
1.16 ATR No. 1,493 802.14 1,197,595.02 BOQ
1:2:4 having size 2' x 2' x 1'.
Item # 119
Construction of Siran Right Bank Canal
District Mansehra
BILL OF QUANTITY
Bill No. 01 Offtake Structure & Head Regulator Main Canal
MRS 2016
Sr.No. Description of items Unit Quantity Rate Amount Remarks
Item Code

Providing and Laying expansion joint of Required as per


1.17 16-44 R. M. 1,098 643.06 705,876.44
neoprene strip 4"x1/4" and plastic bitumen site conditions

Supply & fabricate M.S. reinforcement for ATR


1.18 06-07-c cement concrete (Hot rolled deformed bars Tonne 0.370 103,529.94 38,306.08 BOQ Item #96
Grade 40) & #127

Providing and Laying cut, joint, test & disinfect Required as per
1.19 24-16-c-03 R. M. 120.69 392.44 47,363.58
GI pipe line Using light quality GI Pipe : 1" i/d site conditions

Required as per
1.20 19-33 Grouting stone filling or pitching with bajri M3 85.93 610.21 52,433.75
site conditions

Levelling and dressing stone filling under blocks Required as per


1.21 19-36 M3 107.04 498.07 53,312.21
and grouting with shingle site conditions

Boring for Cast-in-place RCC Piles in Alluvial Required as per


1.22 16-27-a R. M. 4,583.97 5,103.35 23,393,594.64
Soils : Dia up to 760mm site conditions
Erection and removal of steel Form work for ATR
1.23 06-39-b RCC or Plain Concrete vertical M2 3.00 772.27 2,316.81 BOQ
Item # 118
Erection and removal of steel formwork for RCC ATR
1.24 ATR or plain concrete vertical (Labor Rate only) (06- M² 15.00 47.98 719.70 BOQ
39-b) Item # 102
ATR
P/I gates for head regulator & Under Sluice i/c
1.25 ATR M2 14.14 260,000 3,677,647.50 BOQ
hoisting device complete in all respect.
Item # 116
ATR
Providing and fixing MS steel grated trash rack
1.26 ATR M2 2.23 13,000 29,034.06 BOQ
as per drawings and instructions of Engineer.
Item # 124

Plain woodwork for regulation karries or


Required as per
1.27 12-02-a needles etc. complete as per specs : Deodar M3 1.793 144,275.56 258,743.59
site conditions
wood
Filling and Compacting Soil, Earth and Boulders
behind retaining walls (Available material) Required as per
1.28 03-32 M3 11,350.73 178.78 2,029,284.07
site conditions
ATR
Supplying and Fixing PVC Water Stopper 8"
1.29 24-40 M 1,467.96 440.77 647,031.55 BOQ
wide 3/8" thick
Item # 103

Supply & fill bricks in wire crates including


Required as per
1.30 19-18-a sewing crates, excl cost of crates: Stone M3 7,678.69 1,247.67 9,580,471.15
site conditions
orboulders

Required as per
1.31 NSI Admixture Chemical Liter 3,406.85 500.00 1,703,425.24
site conditions

Erecting & removing formwork to concrete in


ATR
1.32 06-38-b any shape / position (Vertical) M² 1,614.57 515.47 832,262.40
BOQ Item #95

Total Amount Rs. 192,815,930.46


Add 8% for District Mansehra Area Cost Factor Except in NSI/Market Rate 14,249,380.54
G. Total Amount Rs. 207,065,311
Converting into millions 207.065
Construction of Siran Right Bank Canal
District Mansehra
BILL OF QUANTITY

Bill No. 02 Irrigation Canal


MRS 2016 Rate Amount
Sr.No Description of items Unit Quantity Remarks
Item Code (Rs.) (Rs.)

Excavation for core trench of Dam


Embankment/Spillway/Intake & Outlet Structure ATR
2.1 03-68 and Irrigation System upto a minimum depth of M³ 221,679.99 206.56 45,790,219.55 BOQ Item #
35 ft in common soil including removing of 140
excavated material by machinery in 1 km radius

Excavation for core trench of Dam


Embankment/Spillway/Intake & Outlet Structure
ATR
and Irrigation System upto design depth in Soft
2.2 03-68-b M³ 682,092.29 306.89 209,327,302.57 BOQ Item #
Rock/Shale requiring 20% blasting including
139
removing of excavated material from outside of
the structure area

Excavation for core trench of Dam


Embankment/Spillway/Intake & Outlet Structure ATR
2.3 03-68-a and Irrigation System upto a minimum depth of M³ 28,420.51 215.37 6,120,925.68 BOQ Item #
35 ft in shingle gravel including removing of 141
excavated material by machinery in 1 km radius

Excavation for core trench of Dam


Embankment/Spillway/Intake & Outlet Structure
ATR
and Irrigation System upto design depth in
2.4 03-68-c M³ 127,892.30 371.52 47,514,548.85 BOQ Item #
Medium Hard Rock requiring 50% blasting
138
including removing of material outside of the
structure area

Excavation for core trench of Dam


Embankment/Spillway/Intake & Outlet Structure ATR
2.5 03-68-d and Irrigation System upto design depth in Hard M³ 71,051.28 436.15 30,989,015.82 BOQ Item #
Rock requiring 75% blasting including removing 137
of material outside of the structure area

ATR
Structural Back fill using Common Material
2.6 03-60-c M³ 87,450.67 435.23 38,061,154.89 BOQ Item #
available at site
115
Required as per site
2.7 03-14-b Rehandling of Earthwork up to a lead of 25 m. M³ 113,682.05 69.53 7,904,312.81
conditions
Formation of Embankment from Roadway
Required as per site
2.8 03-61-a Excavation in Common Material including M³ 29,150.22 321.26 9,364,800.70
conditions
compaction by power roller
Required as per site
2.9 16-03-a Granular Sub Base Course using Pit Run Gravel M³ 54,699.89 1257.96 68,810,269.54
conditions
ATR
Random rubble masonry in foundn. & plinth Dry
2.10 08-01-a M³ 28,533.91 2715.59 77,486,396.53 BOQ Item #
masonry
ATR 108
PCC 1:3:6 in mass concrete less formwork
2.11 06-36-b M³ 52,281.25 4221.30 220,694,832.40 BOQ Item #
using 40% boulders
120
ATR
Plain Cement Concrete including placing,
2.12 06-05-h M3 4,216.54 5,861.65 24,715,872.21 BOQ Item #66
compacting, finishing & curing (Ratio 1:3:6)
& #131
ATR
Plain Cement Concrete including placing,
2.13 06-05-f M³ 5,987.30 6758.12 40,462,921.54 BOQ Item #
compacting,finishing & curing (Ratio 1:2:4)
132
ATR
Plain Cement Concrete including placing,
2.14 06-05-i M³ 7,033.14 5090.88 35,804,859.90 BOQ Item #99
compacting, finishing & curing (Ratio 1:4:8)
& #133

RCC in roof slab , beam , column and other ATR


2.15 06-06-a-03 structural member , in situ or precast. Type C M³ 1,457.14 8,710.19 12,691,994.14 BOQ Item #97 &
1:2:4. #129

RCC in raft foundation slab, base slab of column ATR


2.16 06-06-b-03 & ret. wall etc, not including in 06-06. Type C M3 7,789.31 7,830.79 60,996,483.86 BOQ Item #98 &
(1:2:4) #128

Supply & fabricate M.S. reinforcement for ATR


2.17 06-07-b cement concrete (Hot rolled deformed bars Tonne 1,234.14 110,254.06 136,068,945.61 BOQ Item #
Grade 60) 126
Required as per site
2.18 06-21-a Filling expansion joints with bitumen R. M 11,000.71 294.62 3,241,029.42
conditions
ATR
P/I gates for head regulator & Under Sluice i/c
2.19 ATR M2 1.63 260,000 422,765.56 BOQ Item #
hoisting device complete in all respect.
116
Formation, dressing and preparing sub-grade In Required as per site
2.20 17-01-a M² 40,934.77 69.36 2,839,235.72
bed conditions
Construction of Siran Right Bank Canal
District Mansehra
BILL OF QUANTITY

Bill No. 02 Irrigation Canal


MRS 2016 Rate Amount
Sr.No Description of items Unit Quantity Remarks
Item Code (Rs.) (Rs.)
Formation, dressing and preparing sub-grade Required as per site
2.21 17-01-b M² 107,906.95 96.84 10,449,708.93
On slope conditions
ATR
Providing and Laying stone pitching for top layer
2.22 19-28-a M3 3,096.263 3,052.57 9,451,558.75 BOQ Item #
only : On slope
107
ATR
Erecting & removing formwork for RCC or plain
2.23 06-39-b M² 2.00 772.27 1,544.54 BOQ Item #
concrete Vertical
95
Erection and removal of steel formwork for RCC ATR
2.24 ATR or plain concrete vertical (Labor Rate only) (06- M² 10.00 47.98 479.80 BOQ Item #
39-b) 102
Providing and Laying cut, joint, test, disinfect
Required as per site
2.25 24-18-a-01 PVC pipeline BSS Class 'B' working pressure : R. M 18,273.88 375.08 6,854,168.02
conditions
3" i/d
Filter granular backfill behind retaining wall
Required as per site
2.26 19-47 (stone/boulder filling upto one meter to prevent M³ 525.98 1,257.27 661,294.83
conditions
choking of weep holes)
Removal of tree:gith 150mm -300mm i/c Required as per site
2.27 03-57-a Nos. 800.00 486.61 389,288.00
removal of stump conditions

Removal of tree:gith 300mm -600mm i/c Required as per site


2.28 03-57-b Nos. 900.00 973.22 875,898.00
removal of stump conditions
Required as per site
2.29 04-19-b Dismantling: Plain cement concrete 1:3:6 M³ 226.50 1787.81 404,939.98
conditions
Stabilized layer of cement, sand mortar 1:30 2" Required as per site
2.32 17-02 M² 134,974.71 259.42 35,015,138.75
thick conditions

4" thick PCC lining, using washed screened &


Required as per site
2.33 17-10-a-01 graded/curshed stone aggregate : in bed : Ratio M³ 3,836.12 6818.71 26,157,420.64
conditions
1:2:4

4" thick PCC lining, using washed screened &


Required as per site
2.34 17-10-b-01 graded/curshed stone aggregate : On slope : M³ 9,055.14 7106.74 64,352,520.48
conditions
Ratio 1:2:4
Cement Concrete (brick/stone ballast, 1.5" to
2"/nullah
Required as per site
2.35 06-03-e shingle well graded and cleaned) in foundation & M³ 7,638.08 3188.12 24,351,116.91
plinth conditions
(Ratio 1:6:18)
Carriage of surplus materials i/c ATR
2.36 ATR loading/unloading to specified disposal site as Job 0.36 26054468.00 9,379,608.48 BOQ Item #
per instructions of Engineer 101
Erecting & removing formwork to concrete in
ATR BOQ
2.37 06-38-b any shape / M² 158,458.37 515.47 81,680,536.25
Item #95
position (Vertical)
Providing and Laying RCC pipe sewers ATR
2.38 23-03-c-09 complete as per ASTM C-76-79, Class IV : 36" M 20.00 12118.93 242,378.60 BOQ Item
i/d, Wall B #110
Providing and Laying RCC pipe sewers ATR
2.39 23-03-c-05 complete as per ASTM C-76-79, Class IV : 24" M 20.00 5465.50 109,310.00 BOQ Item
i/d, Wall B #111
Providing and Laying RCC pipe seweres ATR
2.40 23-03-c-03 complete as per ASTM C-76-79, Class IV : 18" M 50.00 3850.96 192,548.00 BOQ Item
i/d, Wall B #112
Dressing & levelling earth to designed section ATR
2.41 03-19-c gravel work or soft rock not requiring blasting M3 100.00 40.83 4,083.00 BOQ Item
upto cut or fill 6 inches #113

07-30 Supplying and filling sand under floor or M3 Required as per site
2.42 670.05 1106.79 741,607.79
plugging in wells conditions

17-11-a Providing and Laying segments in Precast lining M Required as per site
2.43 4,268.82 2420.66 10,333,362.99
(Parabola type) Type A conditions

03-60-b Structural Excavation in Rock Material requiring M3


2.44 2,273.64 1629.01 3,703,783.87
blasting

Total Amount Rs. 1,364,660,183.890

Add 8% for District Mansehra Area Cost Factor Except in NSI/Market Rate 108,388,586.404

G. Total Amount Rs. 1,473,048,770.294


Construction of Siran Right Bank Canal
District Mansehra
BILL OF QUANTITY

Bill No. 02 Irrigation Canal


MRS 2016 Rate Amount
Sr.No Description of items Unit Quantity Remarks
Item Code (Rs.) (Rs.)

Converting into millions 1,473.049


Construction of Siran Right Bank Canal
District Mansehra
BILL OF QUANTITY
Bill No. 03 Canal Affiliated Structues
MRS 2016 Item
Sr. No. Description of items Unit Quantity Rate Amount Remarks
Code

A: Syphons (4 Nos.)
ATR
A-1 03-60-a Structural Excavation in Common Material M³ 8,220.266 315.25 2,591,438.749 BOQ Item
# 135
ATR
Plain Cement Concrete including placing, compacting,
A-2 06-05-i M3 396.326 5,090.88 2,017,646.839 BOQ Item
finishing & curing (Ratio 1:4:8)
#99 & #133

Reinforced cement concrete work as in dams,


spillways, weirs, barrages, cross drainage works and
other hydraulic structures using crushed stone
aggregate(screening & washing) and coarse sand i/c
cost of all labour and material and all kinds of form ATR
A-3 06-06-d-03 works, moulds, shuttering lifting/pumping, curing, M3 1,762.600 10,081.98 17,770,497.948 BOQ Item
rendering and finishing the exposed surface, cast in # 121
situ/precast excluding the cost of steel reinforcement
and labour for bending binding also excluding cost of
additives which have to be paid separately. Type C
(1:2:4)

ATR
Supply & fabricate M.S. reinforcement for cement
A-4 06-07-c Tonne 207.580 103,529.94 21,490,744.945 BOQ Item #96 &
concrete (Hot rolled deformed bars Grade 40)
#127

Procuring 6 mm steel sheets, cold bending &


fabricating to make 3.08 diameter circular pipe in
suitable lengths including inlets/outlet, cone, horizontal
& verticals bends, manholes & drainage arrangement,
painting on the inner sides all as per drawings &
specifications, ready to be lowered in pipe trenched, ATR
A-5 ATR supported on temporary or permanently embedded Tonne 0.000 227,530.00 0.000 BOQ Item
steel/concrete supports. The pipe is to be aligned # 125
/installed to line & grade field welded, including the
costs of non destructive tests, complete in all respects.
The work shall include the costs of all the items
required for providing complete steel pipe in place,
ready for concrete cladding

ATR
Providing and fixing MS steel grated trash rack as per
A-6 ATR M2 113.800 13,000.00 1,479,400.000 BOQ Item
drawings and instructions of Engineer.
# 124
ATR
Structural backfill using Common Material available at
A-7 03-60-c M3 5,349.120 435.23 2,328,097.498 BOQ Item
site
# 115
Required as per
A-8 NSI Providing and installing air/water relief valves Nos. 13 78,185.55 1,016,412.207
site conditions
ATR
A-9 03-60-b Structural Excavation in Rock Material requiring blasting M3 1,404 1,629.01 2,287,651.323 BOQ Item
# 134
NSI HDPE Pipe for Syphon-1 M 975.310 174,862.00 170,544,657.220

NSI HDPE Pipe for Syphon-2 M 76.200 141,861.00 10,809,808.200

NSI HDPE Pipe for Syphon-3 M 914.340 88,450.00 80,873,373.000

0.000

Total Amount Rs. 313,209,727.930


Add 8% for District Mansehra Except in NSI 24,857,113.258
G. Total Amount Rs. 338,066,841.188
Converting into millions 338.067

B: Aqueducts (40 Nos.)


ATR
B-1 03-60-a Structural Excavation in Common Material M3 8,793.330 315.250 2,772,097.283 BOQ Item
ATR # 135
B-2 03-60-b Structural Excavation in Rock Material requiring blasting M3 879.330 1,629.010 1,432,437.363 BOQ Item
# 134
ATR
Plain Cement Concrete including placing, compacting,
B-3 06-05-i M3 263.520 5,090.880 1,341,548.698 BOQ Item
finishing & curing (Ratio 1:4:8)
#99 & #133

ATR
Plain Cement Concrete including placing, compacting,
B-4 06-05-f M3 737.750 6,758.120 4,985,803.030 BOQ Item
finishing & curing (Ratio 1:2:4)
# 132

RCC in roof slab, beam, column & other structural ATR BOQ
B-5 06-06-a-03 M3 3,260.060 8,710.190 28,395,742.011
members, insitu or precast. Type C (1:2:4) Item #97 & #129
Construction of Siran Right Bank Canal
District Mansehra
BILL OF QUANTITY
Bill No. 03 Canal Affiliated Structues
MRS 2016 Item
Sr. No. Description of items Unit Quantity Rate Amount Remarks
Code

Reinforced cement concrete work as in dams,


spillways, weirs, barrages, cross drainage works and
other hydrolic structures using crushed stone
aggregate(screening & washing) and coarse sand i/c
costof all labour and material and all kinds of form ATR
B-6 06-06-d-03 works, moulds, shuttering lifting/pumping, curing, M3 3,553.380 10,081.980 35,825,106.092 BOQ Item
rendering and finishing the exposed surface, cast in # 121
situ/precast excluding the cost of steel reinforcement
and labour for bending binding also excludig cost of
additives which have to be paid separately. Type C
(1:2:4)

Extra labour for laying concrete (plain or reinforced) Required as per


B-7 06-12-a M3 1,022.020 794.580 812,076.652
From 20' upto 40' height site conditions

06-12-a + 06- Extra labour for laying concrete (plain or reinforced) For Required as per
B-8 M3 681.340 1,589.160 1,082,758.274
12-b every extra10' height (upto 60' height) site conditions

ATR
Supply & fabricate M.S. reinforcement for cement
B-9 06-07-c Tonne 1,069.880 103,529.940 110,764,612.207 BOQ Item #96 &
concrete (Hot rolled deformed bars Grade 40)
#127
ATR
Supplying and Fixing PVC Water Stopper 8" wide 3/8"
B-10 24-40 M 7,548.970 440.770 3,327,359.507 BOQ Item
thick
ATR # 103
Structural backfill using Common Material available at
B-11 03-60-c M3 5,862.220 435.230 2,551,414.011 BOQ Item
site
ATR # 115
PCC 1:3:6 in mass concrete less formwork using 40%
B-12 06-36-b M3 2,786.360 4,221.300 11,762,061.468 BOQ Item
boulders
ATR # 120
Erection and removal of steel Form work for RCC or
B-13 06-39-b M² 2.000 772.270 1,544.540 BOQ Item
Plain Concrete vertical
ATR # 118
Erection and removal of steel formwork for RCC or
B-14 ATR M² 10.00 47.98 479.800 BOQ Item
plain concrete vertical (Labor Rate only) (06-39-b)
# 102
Required as per
B-15 17-01-a Formation, dressing and preparing sub-grade In bed M² 327.86 69.36 22,740.66
site conditions
Required as per
B-16 17-01-b Formation, dressing and preparing sub-grade On slope M² 585.04 96.84 56,655.44
site conditions
ATR
Providing and Laying stone pitching/filling, dry hand
B-17 19-25 M3 603.671 1,676.390 1,011,988.015 BOQ Item
packed in pitching & aprons
Provide & weave GI wire netting for wire crates 6"x9" ATR # 105
B-18 19-13-a-03 mesh : 8 SWG wire M2 917.26 369.52 338,947.336 BOQ Item
ATR # 123
Supplying stone and stone filling in GI wire crate and its
B-19 19-26 sewing, excluding cost of crates M3 339.80 1,716.12 583,137.576 BOQ Item
# 122
Painting two feet wide gauges, reading to 1/10th of a Required as per
B-20 13-18 M 115.82 422.610 48,945.992
foot. site conditions
Supply and Fixing Neoprene Bearing Pad as per specs
Required as per
B-21 16-30-a & design cm3 200,000.00 1.610 322,000.000
site conditions

Erecting & removing formwork to concrete in any


ATR BOQ
B-22 06-38-b shape / position (Vertical) M² 4,243.69 515.470 2,187,494.626
Item #95

Total Amount Rs. 209,626,950.579


Add 8% for District Mansehra Except in NSI 16,770,117.662
G. Total Amount Rs. 226,397,068.241
Converting into millions 226.397

C: Superpassages (175 Nos.)


ATR
C-1 03-60-a Structural Excavation in Common Material M3 9,002.469 315.250 2,838,028.347 BOQ Item
# 135
ATR
Plain Cement Concrete including placing, compacting,
C-2 06-05-i M3 290.594 5,090.880 1,479,379.932 BOQ Item
finishing & curing (Ratio 1:4:8)
#99 & #133

RCC in roof slab, beam, column & other structural ATR BOQ
C-3 06-06-a-03 M3 920.602 8,710.190 8,018,615.217
members, insitu or precast. Type C (1:2:4) Item #97 & #129

RCC in raft foundation slab, base slab of column & ret. ATR BOQ
C-4 06-06-b-03 M3 6,197.054 7,830.790 48,527,826.515
wall etc, not including in 06-06. Type C(1:2:4) Item #98 & #128

ATR
Supply & fabricate M.S. reinforcement for cement
C-5 06-07-c Tonne 726.474 103,529.940 75,211,852.034 BOQ Item #96 &
concrete (Hot rolled deformed bars Grade 40).
#127
ATR
Erection and removal of steel Form work for RCC or
C-6 06-39-b M2 3.000 772.270 2,316.810 BOQ Item
Plain Concrete vertical
# 118
ATR
Erection and removal of steel formwork for RCC or
C-7 ATR M² 15.00 47.98 719.700 BOQ Item
plain concrete vertical (Labor Rate only) (06-39-b)
# 102
Construction of Siran Right Bank Canal
District Mansehra
BILL OF QUANTITY
Bill No. 03 Canal Affiliated Structues
MRS 2016 Item
Sr. No. Description of items Unit Quantity Rate Amount Remarks
Code
ATR
PCC 1:3:6 in mass concrete less formwork using 40%
C-8 06-36-b M3 1,500.500 4,221.300 6,334,060.650 BOQ Item
boulders
ATR # 120
Provide & weave GI wire netting for wire crates 6"x9"
C-9 19-13-a-03 mesh : 8 SWG wire M2 13,582.88 369.52 5,019,147.19 BOQ Item
# 123
Construction of Siran Right Bank Canal
District Mansehra
BILL OF QUANTITY
Bill No. 03 Canal Affiliated Structues
MRS 2016 Item
Sr. No. Description of items Unit Quantity Rate Amount Remarks
Code
Supplying stone and stone filling in GI wire crate and its ATR
C-10 19-26 sewing, excluding cost of crates M3 3,062.29 1,716.12 5,255,253.09 BOQ Item
ATR # 122
Providing and Laying stone pitching/filling, dry hand
C-11 19-25 M3 1,386.820 1,676.390 2,324,852.015 BOQ Item
packed in pitching & aprons
ATR # 105
Structural backfill using Common Material available at
C-12 03-60-c M3 2,792.816 435.230 1,215,517.171 BOQ Item
site
# 115
Erecting & removing formwork to concrete in any
C-13 06-38-b shape / position (Vertical) M² 9,311.770 515.470 4,799,938.082

Total Amount Rs. 161,027,506.758


Add 8% for District Mansehra Except in NSI 12,882,142.965
G. Total Amount Rs. 173,909,649.722
Converting into millions 173.910

D: Cross Drainage Culverts (24 Nos.)


ATR
D-1 03-60-a Structural Excavation in Common Material M3 3,082.170 315.250 971,654.093 BOQ Item
# 135
ATR
Plain Cement Concrete including placing, compacting,
D-2 06-05-i M3 83.150 5,090.880 423,306.672 BOQ Item
finishing & curing (Ratio 1:4:8)
#99 & #133

RCC in raft foundation slab, base slab of column & ret. ATR BOQ
D-3 06-06-b-03 M3 673.130 7,830.790 5,271,139.673
wall etc, not including in 06-06. Type C(1:2:4) Item #98 & #128

RCC in roof slab, beam, column & other structural ATR BOQ
D-4 06-06-a-03 M3 310.600 8,710.190 2,705,385.014
members, insitu or precast. Type C (1:2:4) Item #97 & #129

ATR
Supply & fabricate M.S. reinforcement for cement
D-5 06-07-c Tonne 154.470 103,529.940 15,992,269.832 BOQ Item #96 &
concrete (Hot rolled deformed bars Grade 40).
#127
ATR
Structural backfill using Common Material available at
D-6 03-60-c M3 627.350 435.230 273,041.541 BOQ Item
site
# 115
Required as per
D-7 17-01-b Formation, dressing and preparing sub-grade On slope M² 2,902.78 96.84 281,105.22
site conditions
Required as per
D-8 17-01-a Formation, dressing and preparing sub-grade In bed M² 1,340.16 69.36 92,953.50
site conditions
ATR
Providing and Laying stone pitching for top layer only :
D-9 19-28-a M3 883.210 3,052.570 2,696,060.350 BOQ Item
On slope
ATR # 107
Providing and Laying stone pitching for top layer only :
D-10 19-28-b M3 815.520 2,655.280 2,165,433.946 BOQ Item
On level
# 106
Plain Cement Concrete including placing, compacting, ATR BOQ
D-11 06-05-h M3 127.41 5,861.65 746,832.83
finishing & curing (Ratio 1:3:6) Item #66 & #131
ATR
PCC 1:3:6 in mass concrete less formwork using 40%
D-12 06-36-b M3 428.150 4,221.300 1,807,349.595 BOQ Item
boulders
ATR # 120
Erection and removal of steel Form work for RCC or
D-13 06-39-b M² 4.000 772.270 3,089.080 BOQ Item
Plain Concrete vertical
# 118
ATR
Erection and removal of steel formwork for RCC or
D-14 ATR M² 20.00 47.98 959.600 BOQ Item
plain concrete vertical (Labor Rate only) (06-39-b)
# 102
Erecting & removing formwork to concrete in any
ATR BOQ
D-15 06-38-b shape / M² 2,724.81 515.47 1,404,557.811
Item #95
position (Vertical)

Total Amount Rs. 34,835,138.744

Add 8% for District Mansehra Except in NSI 2,786,734.332

G. Total Amount Rs. 37,621,873.075

Converting into millions 37.622


Construction of Siran Right Bank Canal
District Mansehra
BILL OF QUANTITY
Bill No. 03 Canal Affiliated Structues
MRS 2016 Item
Sr. No. Description of items Unit Quantity Rate Amount Remarks
Code

E: Road Culverts (11 Nos.)


ATR
E-1 03-60-a Structural Excavation in Common Material M3 631.570 315.250 199,102.443 BOQ Item
# 135
ATR
Plain Cement Concrete including placing, compacting,
E-2 06-05-i M3 17.030 5,090.880 86,697.686 BOQ Item
finishing & curing (Ratio 1:4:8)
#99 & #133

RCC in raft foundation slab, base slab of column & ret. ATR BOQ
E-3 06-06-b-03 M3 89.040 7,830.790 697,253.542
wall etc, not including in 06-06. Type C(1:2:4) Item #98 & #128

RCC in roof slab, beam, column & other structural ATR BOQ
E-4 06-06-a-03 M3 68.350 8,710.190 595,341.487
members, insitu or precast. Type C (1:2:4) Item #97 & #129

ATR
Supply & fabricate M.S. reinforcement for cement
E-5 06-07-c Tonne 15.550 103,529.940 1,609,890.567 BOQ Item #96 &
concrete (Hot rolled deformed bars Grade 40)
#127

ATR
Plain Cement Concrete including placing,
E-6 06-05-f M³ 92.92 6758.12 627,964.510 BOQ Item
compacting,finishing & curing (Ratio 1:2:4)
# 132
ATR
Structural backfill using Common Material available at
E-7 03-60-c M3 150.860 435.230 65,658.798 BOQ Item
site
# 115
Total Amount Rs. 3,881,909.032
Add 8% for District Mansehra Except in NSI 310,552.723
G. Total Amount Rs. 4,192,461.755
Converting into millions 4.192

F: Pipe Outlets (61 Nos.)


ATR
F-1 03-60-a Structural Excavation in Common Material M3 476.784 315.250 150,306.059 BOQ Item
# 135
ATR
Plain Cement Concrete including placing, compacting,
F-2 06-05-i M3 18.144 5,090.880 92,367.089 BOQ Item
finishing & curing (Ratio 1:4:8)
#99 & #133

RCC in raft foundation slab, base slab of column & ret. ATR BOQ
F-3 06-06-b-03 M³ 265.486 7,830.790 2,078,962.828
wall etc, not including in 06-06. Type C(1:2:4) Item #98 & #128

ATR
Supply & fabricate M.S. reinforcement for cement
F-4 06-07-c Tonne 41.688 103,529.940 4,315,957.065 BOQ Item #96 &
concrete (Hot rolled deformed bars Grade 40).
#127
ATR
Supply and Fixing of GI Pipe as per required diameter
F-5 ATR R. Ft. 1,220 1,295.00 1,579,900.000 BOQ Item
on the direction of Engineer Incharge
# 109
ATR
Structural backfill using Common Material available at
F-6 03-60-c M3 333.399 435.230 145,105.419 BOQ Item
site
# 115
Total Amount Rs. 8,362,598.460

Add 8% for District Mansehra Except in NSI 542,615.877

G. Total Amount Rs. 8,905,214.337

Converting into millions 8.905


Construction of Siran Right Bank Canal
District Mansehra
BILL OF QUANTITY
Bill No. 03 Canal Affiliated Structues
MRS 2016 Item
Sr. No. Description of items Unit Quantity Rate Amount Remarks
Code

G: Head Regulator (Minor Canal)


ATR
G-1 03-60-a Structural Excavation in Common Material M3 18.890 315.250 5,955.073 BOQ Item
# 135
ATR
Plain Cement Concrete including placing, compacting,
G-2 06-05-i M3 0.350 5,090.880 1,781.808 BOQ Item
finishing & curing (Ratio 1:4:8)
#99 & #133

RCC in raft foundation slab, base slab of column & ret. ATR BOQ
G-3 06-06-b-03 M³ 9.900 7,830.790 77,524.821
wall etc, not including in 06-06. Type C(1:2:4) Item #98 & #128

ATR
Supply & fabricate M.S. reinforcement for cement
G-4 06-07-c Tonne 1.360 103,529.940 140,800.718 BOQ Item #96 &
concrete (Hot rolled deformed bars Grade 40).
#127
ATR
P/I gates for head regulator i/c hoisting device complete
G-5 ATR M2 0.730 260,000.00 189,800.000 BOQ Item
in all respect.
ATR # 116
Providing and fixing MS steel grated trash rack as per
G-6 ATR M2 0.730 13,000.00 9,490.000 BOQ Item
drawings and instructions of Engineer.
# 124
Plain woodwork for regulation karries or needles etc. Required as per
G-7 12-02-a M3 0.09 144,275.56 12,984.80
complete as per specs : Deodar wood site conditions
ATR
Structural backfill using Common Material available at
G-8 03-60-c M3 4.760 435.230 2,071.695 BOQ Item
site
# 115
Total Amount Rs. 440,408.915
Add 8% for District Mansehra Area Cost Factor Except in NSI 19,289.513
G. Total Amount Rs. 459,698.428
Converting into millions 0.460
H: Escape Regulator (03 Nos.)
ATR
H-1 03-60-a Structural Excavation in Common Material M3 339.800 315.250 107,121.950 BOQ Item
# 135

ATR
Plain Cement Concrete including placing, compacting,
H-2 06-05-i M3 12.740 5,090.880 64,857.811 BOQ Item
finishing & curing (Ratio 1:4:8)
#99 & #133

RCC in raft foundation slab, base slab of column & ret. ATR BOQ
H-3 06-06-b-03 M³ 407.760 7,830.790 3,193,082.930
wall etc, not including in 06-06. Type C(1:2:4) Item #98 & #128

ATR
Supply & fabricate M.S. reinforcement for cement
H-4 06-07-c Tonne 64.030 103,529.940 6,629,022.058 BOQ Item #96 &
concrete (Hot rolled deformed bars Grade 40).
#127
ATR
Supplying stone and stone filling in GI wire crate and its
H-5 19-26 M3 89.336 1,716.120 153,310.553 BOQ Item
sewing, excluding cost of crates
#122
ATR
Provide & weave GI wire netting for wire crates 6"x9"
H-6 19-13-a-03 M2 6.98 369.52 2,579.25 BOQ Item
mesh : 8 SWG wire
# 123
ATR
P/I gates for head regulator i/c hoisting device complete
H-7 ATR M2 6.980 260,000.00 1,814,800.000 BOQ Item
in all respect.
# 116
Plain woodwork for regulation karries or needles etc. Required as per
H-8 12-02-a M3 0.88 144,275.56 126,962.49
complete as per specs : Deodar wood site conditions

ATR
Structural backfill using Common Material available at
H-9 03-60-c M3 101.940 435.230 44,367.346 BOQ Item
site
# 115

Total Amount Rs. 12,136,104.391

Add 8% for District Mansehra Area Cost Factor Except in NSI 825,704.351

G. Total Amount Rs. 12,961,808.742

Converting into millions 12.962

Grand Total of Bill No. 03 802.515


Construction of Siran Right Bank Canal
District Mansehra
BILL OF QUANTITIES
Bill No. 4: BUILDING-I (SUB-ENGINEER OFFICE CUM RESIDENCE)

MRS 2016
Sr. No. Description of Items Unit Qty Rate Amount Remarks
Item Code

Providing and fixing stainless steel sink with drain board ATR
4.1.1 14-06-b Each 3.00 2585.8 7,757.40
size 18"x36" including set of brackets, waste pipe etc BOQ Item #1

Providing & Fixing Steel manhole cover with frame ATR


4.1.2 14-37-d Each 4.00 3443.75 13,775.00
18"x18" full heavy duty BOQ Item #2

ATR
4.1.3 23-11 Soakage pit ( 6' dia x 15' deep ) complete. No 4.00 16376.25 65,505.00
BOQ Item #3
Providing and installing PVC tees BSS Class 'B'working ATR
4.1.4 24-27-a-02 Each 20.00 500.45 10,009.00
pressure : 3" i/d BOQ Item #4
Providing and installing PVC bends BSS Class ATR
4.1.5 24-26-c-02 Each 15.00 291.54 4,373.10
'D'working pressure : 3" i/d BOQ Item #5
Providing and Laying cut, joint, test, disinfect PVC pipe ATR
4.1.6 24-18-c-05 R. M 15.00 699.29 10,489.35
line BSS Class 'D' working pressure : 3" i/d BOQ Item #6
Providing and installing PVC tees BSS Class 'B'working ATR
4.1.7 24-27-a-03 Each 10.00 687.85 6,878.50
pressure : 4" i/d BOQ Item #7
Providing and installing PVC bends BSS Class ATR
4.1.8 24-26-c-03 Each 10.00 438.29 4,382.90
'D'working pressure : 4" i/d BOQ Item #8
Providing and Laying cut, joint, test, disinfect PVC pipe ATR
4.1.9 24-18-c-06 R. M 60.00 788.7 47,322.00
line BSS Class 'D' working pressure : 4" i/d BOQ Item #9
Providing and installing PVC sockets BSS Class ATR
4.1.10 24-28-a-04 Each 5.00 1360.3 6,801.50
'B'working pressure : 6" i/d BOQ Item #10
Providing and installing PVC bends BSS Class ATR
4.1.11 24-26-a-04 Each 5.00 920.87 4,604.35
'B'working pressure : 6" i/d BOQ Item #11
Providing and Laying cut, joint, test, disinfect PVC pipe ATR
4.1.12 24-18-a-03 R. M 110.00 914.2 100,562.00
line BSS Class 'B'working pressure : 6" i/d BOQ Item #12
Providing and Fixing of poly dex high pressure
ATR
4.1.13 14-71-b PPR(green including testing ect complete 20 R. M 115.00 399.64 45,958.60
BOQ Item #13
mm(including all special etc)
Providing and Fixing of poly dex high pressure
ATR
4.1.14 14-71-a PPR(green including testing ect complete 25 R. M 100.00 427.66 42,766.00
BOQ Item #14
mm(including all special etc)
Supply and Fixing CI manhole cover with frame etc ATR
4.1.15 14-37-b Each 7.00 1909.96 13,369.72
complete 18" dia BOQ Item #15
Providing and fixing CI main hole cover with frame etc ATR
4.1.16 14-37-a No 7.00 1110.86 7,776.02
complete 12" dia BOQ Item #16
Providing and Fixing CI floor trap including CI grating & ATR
4.1.17 14-31-b Each 4.00 793.8 3,175.20
concrete chamber all round : 4"x3" BOQ Item #17
ATR
4.1.18 14-26-b Providing and fixing CP shower rose : 3/4"x6". No 3.00 665.13 1,995.39
BOQ Item #18
Providing and fixing gun metal peet / gate valve ATR
4.1.19 14-28-a No 2.00 1331.8 2,663.60
(screwed ) 1" dia. BOQ Item #19
Providing and Fixing CP mixing valve for WHB, sink or ATR
4.1.20 14-27 No 3.00 2129.13 6,387.39
shower BOQ Item #20
Providing and Fixing CP or brass oxidized swan-neck ATR
4.1.21 14-29-b Each 3.00 2320 6,960.00
cock 1/2" dia : Double way BOQ Item #21
ATR
4.1.22 14-25 Providing and Fixing 1/2" CP tee stop cock Each 6.00 567.53 3,405.18
BOQ Item #22
Providing and Fixing glazed earthen ware soap dish ATR
4.1.23 14-14-b Each 4.00 421.13 1,684.52
Coloured BOQ Item #23
Providing and fixing best quality 5mm glass mirror ATR
4.1.24 14-17 No 3.00 914.81 2,744.43
22"x16" size BOQ Item #24
ATR
4.1.25 14-16-a Providing and fixing CP rail :24" long, 3/4" dia. No 3.00 787.13 2,361.39
BOQ Item #25
ATR
4.1.26 14-15 Providing and fixing CP tailot paper holder. No 3.00 286.92 860.76
BOQ Item #26
ATR
4.1.27 14-13 Providing and fixing CP soap dish. No 3.00 537.03 1,611.09
BOQ Item #27
Providing and Fixing glazed earthen ware low down ATR
4.1.28 14-10-b Each 3.00 2781 8,343.00
flushing cistern 3 gallons capacity : Coloured BOQ Item #28

Providing and Fixing glazed earthen ware WC European ATR


4.1.29 14-01-b Each 3.00 5118.63 15,355.89
type excluding cost of seat & cover : Coloured BOQ Item #29

ATR
4.1.30 14-78 Supply and Fixing low level plastic flushing cistern Each 3.00 1001.2 3,003.60
BOQ Item #30
Construction of Siran Right Bank Canal
District Mansehra
BILL OF QUANTITIES
Bill No. 4: BUILDING-I (SUB-ENGINEER OFFICE CUM RESIDENCE)

MRS 2016
Sr. No. Description of Items Unit Qty Rate Amount Remarks
Item Code

Providing and Fixing glazed earthen ware WC squatting ATR


4.1.31 14-03-b Each 3.00 1719.75 5,159.25
type with built-in foot rests : Coloured BOQ Item #31
Providing and Fixing angle iron brackets for : WHB and ATR
4.1.32 14-46-a Each 2.00 246 492.00
cistern BOQ Item #32
Providing and Fixing glazed earthen ware WHB ATR
4.1.33 14-05-a-02 Each 3.00 3012.8 9,038.40
complete Size 22"x16" : Coloured with pedestal BOQ Item #33
Energy saver 32 Watts (Phillips or eq) with down light / ATR
4.1.34 ATR No. 10.00 450 4,500.00
simple holder and extra accessories etc as specified BOQ Item #34
ATR
4.1.35 ATR Supply and erection plastic box size 7"x4" No. 15.00 600 9,000.00
BOQ Item #35
ATR
4.1.36 ATR Supply and erection plastic box size 4"x4" No. 15.00 500 7,500.00
BOQ Item #36

Supply and Erection gate-light fitting complete with ATR


4.1.37 15-63-a Each 6.00 796.65 4,779.90
holder & 160-Watt mercury blended lamp: Small BOQ Item #37

Earthing of iron clad/aluminium switches etc with GI wire ATR


4.1.38 15-41 Job 1.00 5822.66 5,822.66
#8 SWG in GI pipe 0.5" dia BOQ Item #38
Supply and Erection 2'x2'x1/8" copper plate including
ATR
4.1.39 15-42 rivetting to copper tape & placing in mixture of salt and Each 2.00 9231.69 18,463.38
BOQ Item #39
charcol etc
Supply and Erection single phase imported auto circuit ATR
4.1.40 15-71-d Each 2.00 624.94 1,249.88
breaker 30 Amp. BOQ Item #40
Supply and Erection single phase imported auto circuit ATR
4.1.41 15-71-c Each 5.00 472.44 2,362.20
breaker 20 Amp BOQ Item #41
Supply and Erection single phase imported auto circuit ATR
4.1.42 15-71-b Each 6.00 472.44 2,834.64
breaker 15 Amp BOQ Item #42
Supply and Erection transpower auto circuit breaker ATR
4.1.43 15-70-a Each 4.00 2006.25 8,025.00
3-phase, 400V fungus moisture proofing : 30 Amp. BOQ Item #43
Supply and Erection transpower auto circuit breaker ATR
4.1.44 15-70-c Each 2.00 5238.94 10,477.88
3-phase, 400V fungus moisture proofing : 100 Amp BOQ Item #44
Supply and Erection single core PVC insulated copper ATR
4.1.45 15-05-e R. M 20.00 164.83 3,296.60
conductor 250/440 V grade cable : 7/0.044" BOQ Item #45
Supply and Erection single core PVC insulated copper ATR
4.1.46 15-05-c R. M 200.00 69.5 13,900.00
conductor 250/440 V grade cable : 7/0.029" BOQ Item #46
Supply and Erection single core PVC insulated copper ATR
4.1.47 15-05-a R. M 225.00 42.14 9,481.50
conductor 250/440 V grade cable : 3/0.029" BOQ Item #47
Supply and Erection white round globe with holder, ATR
4.1.48 15-56-c Each 2.00 221.43 442.86
gallery & 100 Watt bulb complete : 10" dia. BOQ Item #48
Supply and Erection PVC pipe for wiring purpose ATR
4.1.49 15-02-b-03 R. M 90.00 275.83 24,824.70
complete Recessed in walls including chase etc : 1" i/d BOQ Item #49
Supply and Erection PVC pipe for wiring purpose ATR
4.1.50 15-02-b-02 R. M 90.00 302.02 27,181.80
complete Recessed in walls including chase etc : 3/4" i/d BOQ Item #50
Floor S/E cubical type factory fabricated floor / wall ATR
4.1.51 15-75-b No 1.00 38157.65 38,157.65
mounted main board steel complete recessed. BOQ Item #51
Supply and fixing electric AC exhaust/fresh air
ATR
4.1.52 15-77-c circulation(Double way) 220/230 single phase plastic Each 2.00 3086.07 6,172.14
BOQ Item #52
frame body and blade complete 12"x12"
S/E best quality ceilling fan complete with G-I rod ATR
4.1.53 15-68-c No 10.00 3845.53 38,455.30
conopy blade & regulator 56" sweep. BOQ Item #53
Supply and Erection girder clamp hook, 5/8" dia.for ATR
4.1.54 15-25 Each 6.00 318.11 1,908.66
hanging ceiling fans BOQ Item #54
Supply and Erection tube light, including rod, choke etc
ATR
4.1.55 15-24-a complete Double rod (2x40 watts) with 2 chokes & 2 Set 10.00 975.58 9,755.80
BOQ Item #55
starters
ATR
4.1.56 15-24-b S/E tube light rod and choke complete 40 watt. No 10.00 454.14 4,541.40
BOQ Item #56
ATR
4.1.57 15-82 Supply and Fixing Asia porcelin power plug 30 Amp Each 20.00 151.88 3,037.60
BOQ Item #57
Wiring of 2/3 pin 5 AMP plug point in 3/029 pvc insulated ATR
4.1.58 15-51 No 20.00 368.80 7,376.00
cable in pvc pipe recessed. BOQ Item #58
Wiring of light / fan / call bell point in 3-29 pvc insulated ATR
4.1.59 15-50 No 60.00 850.55 51,033.00
cable in pvc pipe recessed. BOQ Item #59
Making and fixing grating in opening, including fixing at ATR
4.1.60 25-32 M2 40.00 2344.44 93,777.60
site with flat iron 2"x3/8" and 3/4" sq. bars BOQ Item #61
Filling, watering and ramming earth under floor with ATR
4.1.61 03-16-a M3 73.69 103.3 7,611.91
surplus earth from foundation, etc BOQ Item #62
Shoes, bends or offsets for cast iron rain water down ATR
4.1.62 09-21 Each 9.00 1747.97 15,731.73
pipe, including fixing & painting BOQ Item #63
Construction of Siran Right Bank Canal
District Mansehra
BILL OF QUANTITIES
Bill No. 4: BUILDING-I (SUB-ENGINEER OFFICE CUM RESIDENCE)

MRS 2016
Sr. No. Description of Items Unit Qty Rate Amount Remarks
Item Code

Heads for cast iron rain water down pipe fixed in place ATR
4.1.63 09-20 Each 9.00 1832.34 16,491.06
including cost of clamp holdfast and painting BOQ Item #64
Cast iron rain water down pipe fixed in position excluding ATR
4.1.64 09-19-a R. M 36.59 2212.05 80,928.66
heads & shoes : 4" dia BOQ Item #65
ATR
Plain Cement Concrete including placing, compacting,
4.1.65 06-05-h M3 19.62 5861.65 115,027.43 BOQ Item #66
finishing & curing (Ratio 1:3:6)
& #131
Preparing surface & painting with snowcem / ATR
4.1.66 13-38-b M2 293.73 85.56 25,131.26
weathershield paint : 2nd & subsequent coats BOQ Item #67
Preparing surface & painting with snowcem / ATR
4.1.67 13-38-a M2 293.73 166.86 49,011.25
weathershield paint : First coat BOQ Item #68
ATR
4.1.68 11-23-a-03 Distember New surface: three coats. M² 1,378.36 79.31 109,317.39
BOQ Item #69
ATR
4.1.69 11-25-a-03 White washing: New surface : Three coats M2 1,378.36 40.16 55,354.76
BOQ Item #70
ATR
4.1.70 11-22 Priming coat of chalk under distemper M2 1,378.36 19.34 26,657.40
BOQ Item #71

Providing and Fixing terrace railing of 2" i/d conduit pipe


ATR
4.1.71 25-33 16 SWG welded with 5/8"x5/8" sq bar 2.75' high M2 35.00 3368.16 117,885.60
BOQ Item #72
complete

MS flat 1/2"x1/8" grill in windows of approved design ATR


4.1.72 12-50 M2 29.69 3073.3 91,256.45
including painting 3 coats, complete BOQ Item #73
ATR
4.1.73 13-08-a French polishing complete : on new work . M² 237.12 671.13 159,138.35
BOQ Item #74
Varnishing wood work, including cleaning & preparing ATR
4.1.74 13-09-c M2 237.12 53.44 12,671.69
surface : Third coat BOQ Item #75
Varnishing wood work, including cleaning & preparing ATR
4.1.75 13-09-b M2 237.12 61.53 14,589.99
surface : Second coat BOQ Item #76
Varnishing wood work, including cleaning & preparing ATR
4.1.76 13-09-a M2 237.12 93.65 22,206.29
surface : First coat BOQ Item #77
ATR
4.1.77 12-17-b P/F hydraulic Door Closer (Best Quality) Each 12.00 1682.5 20,190.00
BOQ Item #78
Providing and fixing sliding bolt to doors Brass sliding ATR
4.1.78 12-18-c-01 Each 12.00 1121.05 13,452.60
bolts : 10" long BOQ Item #79
Providing and fixing sliding bolt to doors Brass sliding ATR
4.1.79 12-18-c-02 Each 12.00 1426.05 17,112.60
bolts : 12" long BOQ Item #80
Provide & fix wooden box type wardrobe 22" deep ATR
4.1.80 12-23-b M2 14.87 10896.4 162,028.25
Deodar wood boxing & deodar shelves etc BOQ Item #81
Supply and Fixing aluminium door/window, Economy ATR
4.1.81 12-53-a-01 M2 31.64 7334.76 232,108.34
model Sliding window BOQ Item #82
Deodar wood framed, braced & battened doors & ATR
4.1.82 12-08-b M2 27.65 8858.29 244,920.19
windows: 1.75" thick, 1" battens & 3/4" planks BOQ Item #83
Provide & fix chowkat for doors, windows & CS windows, ATR
4.1.83 12-24-c M2 27.65 2758.6 76,271.70
including holdfast etc : Deodar wood BOQ Item #84
Providing and fixing glazed tile colour printed border 3" ATR
4.1.84 10-26-g R. M 30.73 636.89 19,571.35
wide BOQ Item #85
Glazed tile 1/4" thick dado jointed in white cement ATR
4.1.85 10-38-c M2 110.59 1542.43 170,584.73
complete : Printed tiles BOQ Item #86
Cement pointing struck joints, on walls, upto 20' height : ATR
4.1.86 11-18-b M2 534.15 225.48 120,440.65
Ratio 1:3 BOQ Item #87
1.375" thick mosaic flooring, including rubbing and ATR
4.1.87 10-21-a M2 1,129.64 1117.03 1,261,846.01
polishing complete : Using grey cement BOQ Item #88
Provide & lay marble fine dressed stone flooring on
ATR
4.1.88 10-26-a surface in white cement complete: 3/4" thick (Badel, M2 126.74 1943.89 246,378.02
BOQ Item #89
Silky black, Sunny white, Sunny Grey or eq)
ATR
4.1.89 11-09-b Cement plaster 1:4 upto 20' height 1/2" thick M2 1,177.62 215 253,187.61
BOQ Item #90
Cement plaster 3/8" thick under soffit of RCC roof slabs ATR
4.1.90 11-10-b M2 200.74 253.11 50,809.02
only upto 20' height : (1:3) BOQ Item #91
Pacca brick work in ground floor Cement, sand mortar ATR
4.1.91 07-05-a-05 M3 121.63 8003.98 973,502.11
1:6 BOQ Item #92
Damp proof course of cem. conc. 1:2:4 including
ATR
4.1.92 06-22-a-03 bitumen coat, 1 layer polythene & 1 coat bitumen (3" M2 2.00 770.95 1,538.64
BOQ Item #93
thick)
Pacca brick work in foundation and plinth in Cement, ATR
4.1.93 07-04-a-05 M3 57.80 7433.74 429,666.03
sand mortar 1:6 BOQ Item #94
Single layer of tiles 10"x5"x1.25" laid over 4" earth and Required as
4.1.94 09-05 M2 200.74 1261.92 253,316.41
1" mud plaster on top of RC roof slab per site
Construction of Siran Right Bank Canal
District Mansehra
BILL OF QUANTITIES
Bill No. 4: BUILDING-I (SUB-ENGINEER OFFICE CUM RESIDENCE)

MRS 2016
Sr. No. Description of Items Unit Qty Rate Amount Remarks
Item Code

ATR
Supply fabricate M.S reinforcement for cement concrete BOQ
4.1.95 06-07-c TON 10.96 103529.94 1,134,428.82
( hot rolled deformed bars Grade 40) Item #96 &
#127
ATR
RCC in roof slab , beam , column and other structural
4.1.96 06-06-a-03 M³ 67.52 8710.19 588,150.85 BOQ Item #97
member , in sithu or precast.type C 1:2:4.
& #129
ATR
RCC in raft foundation slab, base slab of column & ret.
4.1.97 06-06-b-03 M3 2.26 7830.79 17,675.67 BOQ Item #98
wall etc, not including in 06-06. Type C(1:2:4)
& #128
ATR
Plain Cement Concrete including placing, compacting, BOQ
4.1.98 06-05-i M3 34.51 5090.88 175,694.88
finishing & curing (Ratio 1:4:8) Item #99 &
#133
Excavation in foundation of building bridges etc ATR
4.1.99 03-23-d M³ 101.20 273.34 27,661.72
complete in Shingle gravel. BOQ Item #100

Required as
4.1.100 14-69-a-02 P/F Fiber glass Water Tank 400 gallons. No. 1.00 9,379.42 9,379.42
per site
Supply and fixing of 2.0 HP Monoblock water pump
Required as
4.1.101 14-80-a 1.5"x1.25" 3 stage model DE-S3 (Deen Pump) single No. 1.00 22,790.62 22,790.62
per site
phase for 150 ft head with all accessories.
Making and fixing steel grated doors, complete with Required as
4.1.102 25-30 M2 8.75 8,088.33 70,772.89
locking arrangements & angle iron frame per site
Total Amount Rs. 8,388,420.02

Add 8% for District Mansehra Except in NSI 669,393.60

G. Total Amount Rs. 9,057,813.62

Grand Total Amount (Rs.) 9.058


Construction of Siran Right Bank Canal
District Mansehra
BILL OF QUANTITIES
Bill No. 4: BUILDING-II (CHOWKIDAR HUT)

MRS 2016
Sr. No. Description of Items Unit Qty Rate Amount Remarks
Item Code

Providing and fixing stainless steel sink with drain board ATR
4.2.1 14-06-b Each 1.00 2585.8 2,585.80
size 18"x36" including set of brackets, waste pipe etc BOQ Item #1

Providing & Fixing Steel manhole cover with frame ATR


4.2.2 14-37-d Each 2.00 3443.75 6,887.50
18"x18" full heavy duty BOQ Item #2
ATR
4.2.3 23-11 Soakage pit ( 6' dia x 15' deep ) complete. No 2.00 16376.25 32,752.50
BOQ Item #3
Providing and installing PVC tees BSS Class 'B'working ATR
4.2.4 24-27-a-02 Each 10.00 500.45 5,004.50
pressure : 3" i/d BOQ Item #4
Providing and installing PVC bends BSS Class ATR
4.2.5 24-26-c-02 Each 7.00 291.54 2,040.78
'D'working pressure : 3" i/d BOQ Item #5
Providing and Laying cut, joint, test, disinfect PVC pipe ATR
4.2.6 24-18-c-05 R. M 10.00 699.29 6,992.90
line BSS Class 'D' working pressure : 3" i/d BOQ Item #6
Providing and installing PVC tees BSS Class 'B'working ATR
4.2.7 24-27-a-03 Each 5.00 687.85 3,439.25
pressure : 4" i/d BOQ Item #7
Providing and installing PVC bends BSS Class ATR
4.2.8 24-26-c-03 Each 5.00 438.29 2,191.45
'D'working pressure : 4" i/d BOQ Item #8
Providing and Laying cut, joint, test, disinfect PVC pipe ATR
4.2.9 24-18-c-06 R. M 30.00 788.7 23,661.00
line BSS Class 'D' working pressure : 4" i/d BOQ Item #9
ATR
Providing and installing PVC sockets BSS Class
4.2.10 24-28-a-04 Each 5.00 1360.3 6,801.50 BOQ Item
'B'working pressure : 6" i/d
#10
ATR
Providing and installing PVC bends BSS Class
4.2.11 24-26-a-04 Each 4.00 920.87 3,683.48 BOQ Item
'B'working pressure : 6" i/d
#11
ATR
Providing and Laying cut, joint, test, disinfect PVC pipe
4.2.12 24-18-a-03 R. M 50.00 914.2 45,710.00 BOQ Item
line BSS Class 'B'working pressure : 6" i/d
#12
Providing and Fixing of poly dex high pressure ATR
4.2.13 14-71-b PPR(green including testing ect complete 20 R. M 70.00 399.64 27,974.80 BOQ Item
mm(including all special etc) #13
Providing and Fixing of poly dex high pressure ATR
4.2.14 14-71-a PPR(green including testing ect complete 25 R. M 60.00 427.66 25,659.60 BOQ Item
mm(including all special etc) #14
ATR
Supply and Fixing CI manhole cover with frame etc
4.2.15 14-37-b Each 3.00 1909.96 5,729.88 BOQ Item
complete 18" dia
#15
ATR
Providing and fixing CI main hole cover with frame etc
4.2.16 14-37-a No 3.00 1110.86 3,332.58 BOQ Item
complete 12" dia
#16
ATR
Providing and Fixing CI floor trap including CI grating &
4.2.17 14-31-b Each 2.00 793.8 1,587.60 BOQ Item
concrete chamber all round : 4"x3"
#17
ATR
4.2.18 14-26-b Providing and fixing CP shower rose : 3/4"x6". No 2.00 665.13 1,330.26 BOQ Item
#18
ATR
Providing and fixing gun metal peet / gate valve
4.2.19 14-28-a No 2.00 1331.8 2,663.60 BOQ Item
(screwed ) 1" dia.
#19
ATR
Providing and Fixing CP mixing valve for WHB, sink or
4.2.20 14-27 No 1.00 2129.13 2,129.13 BOQ Item
shower
#20
ATR
Providing and Fixing CP or brass oxidized swan-neck
4.2.21 14-29-b Each 2.00 2320 4,640.00 BOQ Item
cock 1/2" dia : Double way
#21
ATR
4.2.22 14-25 Providing and Fixing 1/2" CP tee stop cock Each 5.00 567.53 2,837.65 BOQ Item
#22
Construction of Siran Right Bank Canal
District Mansehra
BILL OF QUANTITIES
Bill No. 4: BUILDING-II (CHOWKIDAR HUT)

MRS 2016
Sr. No. Description of Items Unit Qty Rate Amount Remarks
Item Code

ATR
Providing and Fixing glazed earthen ware soap dish
4.2.23 14-14-b Each 2.00 421.13 842.26 BOQ Item
Coloured
#23
ATR
Providing and fixing best quality 5mm glass mirror
4.2.24 14-17 No 2.00 914.81 1,829.62 BOQ Item
22"x16" size
#24
ATR
4.2.25 14-16-a Providing and fixing CP rail :24" long, 3/4" dia. No 2.00 787.13 1,574.26 BOQ Item
#25
ATR
4.2.26 14-15 Providing and fixing CP tailot paper holder. No 2.00 286.92 573.84 BOQ Item
#26
ATR
4.2.27 14-13 Providing and fixing CP soap dish. No 2.00 537.03 1,074.06 BOQ Item
#27
ATR
Providing and Fixing glazed earthen ware low down
4.2.28 14-10-b Each 2.00 2781 5,562.00 BOQ Item
flushing cistern 3 gallons capacity : Coloured
#28
ATR
Providing and Fixing glazed earthen ware WC European
4.2.29 14-01-b Each 2.00 5118.63 10,237.26 BOQ Item
type excluding cost of seat & cover : Coloured
#29
ATR
4.2.30 14-78 Supply and Fixing low level plastic flushing cistern Each 2.00 1001.2 2,002.40 BOQ Item
#30
ATR
Providing and Fixing glazed earthen ware WC squatting
4.2.31 14-03-b Each 2.00 1719.75 3,439.50 BOQ Item
type with built-in foot rests : Coloured
#31
ATR
Providing and Fixing angle iron brackets for : WHB and
4.2.32 14-46-a Each 2.00 246 492.00 BOQ Item
cistern
#32
ATR
Providing and Fixing glazed earthen ware WHB
4.2.33 14-05-a-02 Each 2.00 3012.8 6,025.60 BOQ Item
complete Size 22"x16" : Coloured with pedestal
#33
ATR
Energy saver 32 Watts (Phillips or eq) with down light /
4.2.34 ATR No. 5.00 450 2,250.00 BOQ Item
simple holder and extra accessories etc as specified
#34
ATR
4.2.35 ATR Supply and erection plastic box size 7"x4" No. 7.00 600 4,200.00 BOQ Item
#35
ATR
4.2.36 ATR Supply and erection plastic box size 4"x4" No. 7.00 500 3,500.00 BOQ Item
#36
ATR
Supply and Erection gate-light fitting complete with
4.2.37 15-63-a Each 6.00 796.65 4,779.90 BOQ Item
holder & 160-Watt mercury blended lamp: Small
#37
ATR
Earthing of iron clad/aluminium switches etc with GI wire
4.2.38 15-41 Job 1.00 5822.66 5,822.66 BOQ Item
#8 SWG in GI pipe 0.5" dia
#38
Supply and Erection 2'x2'x1/8" copper plate including ATR
4.2.39 15-42 rivetting to copper tape & placing in mixture of salt and Each 1.00 9231.69 9,231.69 BOQ Item
charcol etc #39
ATR
Supply and Erection single phase imported auto circuit
4.2.40 15-71-d Each 1.00 624.94 624.94 BOQ Item
breaker 30 Amp.
#40
ATR
Supply and Erection single phase imported auto circuit
4.2.41 15-71-c Each 3.00 472.44 1,417.32 BOQ Item
breaker 20 Amp
#41
ATR
Supply and Erection single phase imported auto circuit
4.2.42 15-71-b Each 4.00 472.44 1,889.76 BOQ Item
breaker 15 Amp
#42
Construction of Siran Right Bank Canal
District Mansehra
BILL OF QUANTITIES
Bill No. 4: BUILDING-II (CHOWKIDAR HUT)

MRS 2016
Sr. No. Description of Items Unit Qty Rate Amount Remarks
Item Code

ATR
Supply and Erection transpower auto circuit breaker
4.2.43 15-70-a Each 2.00 2006.25 4,012.50 BOQ Item
3-phase, 400V fungus moisture proofing : 30 Amp.
#43
ATR
Supply and Erection transpower auto circuit breaker
4.2.44 15-70-c Each 1.00 5238.94 5,238.94 BOQ Item
3-phase, 400V fungus moisture proofing : 100 Amp
#44
ATR
Supply and Erection single core PVC insulated copper
4.2.45 15-05-e R. M 10.00 164.83 1,648.30 BOQ Item
conductor 250/440 V grade cable : 7/0.044"
#45
ATR
Supply and Erection single core PVC insulated copper
4.2.46 15-05-c R. M 100.00 69.5 6,950.00 BOQ Item
conductor 250/440 V grade cable : 7/0.029"
#46
ATR
Supply and Erection single core PVC insulated copper
4.2.47 15-05-a R. M 125.00 42.14 5,267.50 BOQ Item
conductor 250/440 V grade cable : 3/0.029"
#47
ATR
Supply and Erection white round globe with holder,
4.2.48 15-56-c Each 1.00 221.43 221.43 BOQ Item
gallery & 100 Watt bulb complete : 10" dia.
#48
ATR
Supply and Erection PVC pipe for wiring purpose
4.2.49 15-02-b-03 R. M 40.00 275.83 11,033.20 BOQ Item
complete Recessed in walls including chase etc : 1" i/d
#49

ATR
Supply and Erection PVC pipe for wiring purpose
4.2.50 15-02-b-02 R. M 40.00 302.02 12,080.80 BOQ Item
complete Recessed in walls including chase etc : 3/4" i/d
#50

ATR
Floor S/E cubical type factory fabricated floor / wall
4.2.51 15-75-b No 1.00 38157.65 38,157.65 BOQ Item
mounted main board steel complete recessed.
#51

Supply and fixing electric AC exhaust/fresh air ATR


4.2.52 15-77-c circulation(Double way) 220/230 single phase plastic Each 1.00 3086.07 3,086.07 BOQ Item
frame body and blade complete 12"x12" #52

ATR
S/E best quality ceilling fan complete with G-I rod
4.2.53 15-68-c No 5.00 3845.53 19,227.65 BOQ Item
conopy blade & regulator 56" sweep.
#53

ATR
Supply and Erection girder clamp hook, 5/8" dia.for
4.2.54 15-25 Each 3.00 318.11 954.33 BOQ Item
hanging ceiling fans
#54

Supply and Erection tube light, including rod, choke ATR


4.2.55 15-24-a etccomplete Double rod (2x40 watts) with 2 chokes & 2 Set 4.00 975.58 3,902.32 BOQ Item
starters #55

ATR
4.2.56 15-24-b S/E tube light rod and choke complete 40 watt. No 4.00 454.14 1,816.56 BOQ Item
#56

ATR
4.2.57 15-82 Supply and Fixing Asia porcelin power plug 30 Amp Each 10.00 151.88 1,518.80 BOQ Item
#57

ATR
Wiring of 2/3 pin 5 AMP plug point in 3/029 pvc insulated
4.2.58 15-51 No 10.00 368.80 3,688.00 BOQ Item
cable in pvc pipe recessed.
#58

ATR
Wiring of light / fan / call bell point in 3-29 pvc insulated
4.2.59 15-50 No 30.00 850.55 25,516.50 BOQ Item
cable in pvc pipe recessed.
#59

ATR
Making and fixing grating in opening, including fixing at
4.2.60 25-32 M2 20.00 2344.44 46,888.80 BOQ Item
site with flat iron 2"x3/8" and 3/4" sq. bars
#61
Construction of Siran Right Bank Canal
District Mansehra
BILL OF QUANTITIES
Bill No. 4: BUILDING-II (CHOWKIDAR HUT)

MRS 2016
Sr. No. Description of Items Unit Qty Rate Amount Remarks
Item Code

ATR
Filling, watering and ramming earth under floor with
4.2.61 03-16-a M3 25.47 103.3 2,631.20 BOQ Item
surplus earth from foundation, etc
#62

ATR
Shoes, bends or offsets for cast iron ran water down
4.2.62 09-21 Each 8.00 1747.97 13,983.76 BOQ Item
pipe, including fixing & painting
#63

ATR
Heads for cast iron rain water down pipe fixed in place
4.2.63 09-20 Each 8.00 1832.34 14,658.72 BOQ Item
including cost of clamp holdfast and painting
#64

ATR
Cast iron rain water down pipe fixed in position excluding
4.2.64 09-19-a R. M 18.29 2212.05 40,464.33 BOQ Item
heads & shoes : 4" dia
#65

ATR
Plain Cement Concrete including placing, compacting,
4.2.65 06-05-h M3 36.16 5861.65 211,958.86 BOQ Item
finishing & curing (Ratio 1:3:6)
#66 & #131

ATR
Preparing surface & painting with snowcem /
4.2.66 13-38-b M2 122.49 85.56 10,480.30 BOQ Item
weathershield paint : 2nd & subsequent coats
#67

ATR
Preparing surface & painting with snowcem /
4.2.67 13-38-a M2 137.10 166.86 22,876.57 BOQ Item
weathershield paint : First coat
#68

ATR
4.2.68 11-23-a-03 Distember New surface: three coats. M² 609.59 79.31 48,346.58 BOQ Item
#69

ATR
4.2.69 11-25-a-03 White washing: New surface : Three coats M2 609.59 40.16 24,481.13 BOQ Item
#70

ATR
4.2.70 11-22 Priming coat of chalk under distemper M2 609.59 19.34 11,789.47 BOQ Item
#71

Providing and Fixing terrace railing of 2" i/d conduit pipe ATR
4.2.71 25-33 16 SWG welded with 5/8"x5/8" sq bar 2.75' high M2 20.00 3368.16 67,363.20 BOQ Item
complete #72

ATR
MS flat 1/2"x1/8" grill in windows of approved design
4.2.72 12-50 M2 18.40 3073.3 56,553.29 BOQ Item
including painting 3 coats, complete
#73

ATR
4.2.73 13-08-a French polishing complete : on new work . M² 121.00 671.13 81,206.73 BOQ Item
#74

ATR
Varnishing wood work, including cleaning & preparing
4.2.74 13-09-c M2 121.00 53.44 6,466.24 BOQ Item
surface : Third coat
#75

ATR
Varnishing wood work, including cleaning & preparing
4.2.75 13-09-b M2 121.00 61.53 7,445.13 BOQ Item
surface : Second coat
#76

ATR
Varnishing wood work, including cleaning & preparing
4.2.76 13-09-a M2 121.00 93.65 11,331.65 BOQ Item
surface : First coat
#77

ATR
4.2.77 12-17-b P/F hydraulic Door Closer (Best Quality) Each 6.00 1682.5 10,095.00 BOQ Item
#78
Construction of Siran Right Bank Canal
District Mansehra
BILL OF QUANTITIES
Bill No. 4: BUILDING-II (CHOWKIDAR HUT)

MRS 2016
Sr. No. Description of Items Unit Qty Rate Amount Remarks
Item Code

ATR
Providing and fixing sliding bolt to doors Brass sliding
4.2.78 12-18-c-01 Each 6.00 1121.05 6,726.30 BOQ Item
bolts : 10" long
#79

ATR
Providing and fixing sliding bolt to doors Brass sliding
4.2.79 12-18-c-02 Each 6.00 1426.05 8,556.30 BOQ Item
bolts : 12" long
#80

ATR
Provide & fix wooden box type wardrobe 22" deep
4.2.80 12-23-b M2 11.15 10896.4 121,521.19 BOQ Item
Deodar wood boxing & deodar shelves etc
#81

ATR
Supply and Fixing aluminium door/window, Economy
4.2.81 12-53-a-01 M2 18.40 7334.76 134,970.49 BOQ Item
model Sliding window
#82

ATR
Deodar wood framed, braced & battened doors &
4.2.82 12-08-b M2 11.71 8858.29 103,730.91 BOQ Item
windows: 1.75" thick, 1" battens & 3/4" planks
#83

ATR
Provide & fix chowkat for doors, windows & CS windows,
4.2.83 12-24-c M2 14.31 2758.6 39,481.82 BOQ Item
including holdfast etc : Deodar wood
#84
ATR
Providing and fixing glazed tile colour printed border 3"
4.2.84 10-26-g R. M 24.47 636.89 15,581.90 BOQ Item
wide
#85
ATR
Glazed tile 1/4" thick dado jointed in white cement
4.2.85 10-38-c M2 59.20 1542.43 91,313.00 BOQ Item
complete : Printed tiles
#86

ATR
Cement pointing struck joints, on walls, upto 20' height :
4.2.86 11-18-b M2 213.38 225.48 48,113.58 BOQ Item
Ratio 1:3
#87

ATR
1.375" thick mosaic flooring, including rubbing and
4.2.87 10-21-a M2 117.00 1117.03 130,692.51 BOQ Item
polishing complete : Using grey cement
#88

Provide & lay marble fine dressed stone flooring on ATR


4.2.88 10-26-a surface in white cement complete: 3/4" thick (Badel, M2 77.01 1943.89 149,690.02 BOQ Item
Silky black, Sunny white, Sunny Grey or eq) #89
ATR
4.2.89 11-09-b Cement plaster 1:4 upto 20' height 1/2" thick M2 384.72 215 82,715.78 BOQ Item
#90
ATR
Cement plaster 3/8" thick under soffit of RCC roof slabs
4.2.90 11-10-b M2 109.02 253.11 27,593.37 BOQ Item
only upto 20' height : (1:3)
#91

ATR
Pacca brick work in ground floor Cement, sand mortar
4.2.91 07-05-a-05 M3 64.66 8003.98 517,539.95 BOQ Item
1:6
#92

Damp proof course of cem. conc. 1:2:4 including ATR


4.2.92 06-22-a-03 bitumen coat, 1 layer polythene & 1 coat bitumen (3" M2 2.23 770.95 1,718.74 BOQ Item
thick) #93

ATR
Pacca brick work in foundation and plinth in Cement,
4.2.93 07-04-a-05 M3 21.81 7433.74 162,164.90 BOQ Item
sand mortar 1:6
#94

Single layer of tiles 10"x5"x1.25" laid over 4" earth and Required as
4.2.94 09-05 M2 127.01 1261.92 160,278.87
1" mud plaster on top of RC roof slab per site
Construction of Siran Right Bank Canal
District Mansehra
BILL OF QUANTITIES
Bill No. 4: BUILDING-II (CHOWKIDAR HUT)

MRS 2016
Sr. No. Description of Items Unit Qty Rate Amount Remarks
Item Code

ATR
Supply fabricate M.S reinforcement for cement concrete
4.2.95 06-07-c TON 2.39 103529.94 246,959.59 BOQ Item
( hot rolled deformed bars Grad 40)
#96 & #127
ATR
RCC in roof slab , beam , column and other structural
4.2.96 06-06-a-03 M³ 12.57 8710.19 109,527.59 BOQ Item
member , in sithu or precast.type C 1:2:4.
#97 & #129
ATR
RCC in raft foundation slab, base slab of column & ret.
4.2.97 06-06-b-03 M3 2.62 7830.79 20,489.06 BOQ Item
wall etc, not including in 06-06. Type C(1:2:4)
#98 & #128
ATR
Plain Cement Concrete including placing, compacting,
4.2.98 06-05-i M 3
24.36 5090.88 124,038.91
finishing & curing (Ratio 1:4:8) BOQ Item #99
& #133
ATR
Excavation in foundation of building bridges etc
4.2.99 03-23-d M³ 153.25 273.34 41,889.53 BOQ Item
complete in Shingle gravel.
#100
Required as
4.2.100 14-69-a-01 P/F Fiber glass Water Tank 300 gallons. No. 1.00 7884.51 7,884.51
per site
Supply and fixing of 2.0 HP Monoblock water pump
Required as
4.2.101 14-80-a 1.5"x1.25" 3 stage model DE-S3 (Deen Pump) single No. 1.00 22790.62 22,790.62
per site
phase for 150 ft head with all accessories.
Making and fixing steel grated doors, complete with Required as
4.2.102 25-30 M2 5.00 8,088.33 40,441.65
locking arrangements & angle iron frame per site

Total Amount Rs. 3,536,757.44

Add 8% for District Mansehra Except in NSI 282,144.59

G. Total Amount Rs. 3,818,902.03

Grand Total Amount (Rs.) 3.819


Construction of Siran Right Bank Canal
District Mansehra
COST ESTIMATE OF PROJECT DIRECTORATE FOR SRBC PROJECT

Project Office
Allocation as
S. No Name of item/Particular requirements for 5 Remarks
per PC-I
Years

1 Salaries of Project Staff 106,200,000 120,000,000 Detail of staff attached

2 Pension Contribution / Gratuity & Salary 1,300,000 1,250,000

3 Medical charges 410,000 50,000

4 FWD Vehicles 7 Nos 19,850,000 17,758,745

5 Motorcycles 6 Nos 640,000 341,146

Machinery & equipment (including


6 Photocopier Fax Machine & Computers 2,000,000 900,000
with all accessories Generator, UPS)
7 Furniture and fixture 1,500,000 1,000,000

Repair of Durable Goods

8 Vehicle 7 Nos + 6 M/Cycle 1,560,000 2,200,000


Machinery & equipment (including
9 Photocopier Fax Machine & Computers with 500,000 300,000
all accessories Generator, UPS)

Commodities & Services

10 Travelling Allowances 2,000,000 3,400,000

11 Transportation of Goods 200,000 100,000


12 POL 6,000,000 12,500,000
13 Postage and Telegraph 75,000 150,000
14 Courier Charges 350,000

15 Electricity & Gas Charges 1,500,000 1,100,000

16 Stationery Charges 800,000 700,000

17 Printing & Photography Charges 445,000 200,000

18 News Paper Books Charges 100,000 -


19 Rent of Office Building (Shelter) 900,000 900,000
20 Advertisement charges 400,000 600,000
Others (including logistics, information
21 1,500,000 500,000
campaign, site briefing to higher ups

22 Misc: Expenditure 3,000,000 -

23 Conference/seminar/workshop/symposia/ 3,000,000 150,000


physical model for the project
Total 154,230,000 164,099,891
COST ESTIMATE OF PROJECT DIRECTORATE FOR SRBC PROJECT

Project Office
Allocation as
S. No Name of item/Particular requirements for 5 Remarks
per PC-I
Years

Total in Rs. Millions 154.230 164.100


Construction of Siran Right Bank Canal
District Mansehra
Detail Of Project Directorate Staff For SRBC Project

S# Name of Post BPS No of Post


1 Project Director 19 1
2 Deputy Director 18 2
3 Accounts Officer 17 1
4 Assistant Director 17 3
5 Office Superintendent 17 1
6 Circle Head Draftsman 16 1
7 Accounts Assistant 16 1
8 Computer Operator 16 1
9 Ziladar 15 1
10 Sub Engineer 12 3
11 Junior Clerk 11 1
12 Patwari 7 1
13 Driver 7 6
14 Chowkidar 3 2
15 Naib Qasid (i.e Sweeper) 3 6
Total 31
Construction of Siran Right Bank Canal
District Mansehra
Off-take Structure & Head Regulator
BOQ Item Description Calculations
1.1 Bailing out water by Mechanical mean

Quantity of water in a minute 4 x 60 240 cft


Quantity of water in a hour 240 x 60 14400 cft
Total average hours in a day 9 hours
Quantity of water in a day 14400 x 9 129600 cft
Total average days required 60 days
Quantity of water in a day 129600 x 29 3758400 cft
Converting in to Cum 3758400 / (3.2804)^3 106468.9 M3

Provide , Place & compact shoulder material (sandy / silty gravel) in Dam Embankment, of specified grading, leveling/dressing i/c haulage for
1.2
obtaining of 95% modified AASHTHO dry density.

Coffer Dam Filling


Description X-Sectional area
Length Volume
(ft) (cft)
(sft)
Stage I Coffer Dam for Undersluice 700 786.86 550802

Stage II Coffer Dam U/S Wier 700 219.5 153650

Stage II Coffer Dam D/S Wier 700 526.87 368809


Total 1073261 Cft
30391.338 cub. M

1.3 Supply & fill new synthetic fibre/plastic bags 4-5 cft capacity with sand or earth,sewing, stacking : in dry

Sand bags
Total Length (ft) Slope Width (ft) Depth (ft) Volume (cft)
1533.23 36.06 3 165864.821
No. of bags 165864.821 / 5.000
33173 bags
16587 Take 50%

1.4 Supply & fill new synthetic fibre/plastic bags 4-5cft capacity with sand or earth,sewing, stacking : Under water

Take 50% of item 1.3 = 16587 bags

1.5 Supplying clean and screened river or pit sand within 150m including removal of loose earth or overburden.

Capacity of one bag = 5 cft


No. of bags = 33173 bags
Qty of Sand = 165865 cft
OR 4696.764 m3

Excavation for core trench of Dam Embankment /Spillway/Intake & Outlet Structure and Irrigation System upto a minimum depth of 35 ft in shingle
1.6
gravel including removing of excavated material by machinery in 1 KM radius

Earth Work Diversion Weir


Section @ Area Mean area (ft) Length Volume
(sft) (ft) (cft)
0 0
U/S 2081.24 1040.62 139 144646.18
Mid 2113.34 2097.29 292 612408.68
D/S 3808 2960.67 195 577330.65
End 0 1904 139 264656
Total Quantity (cft) 1599041.51
Total Quantity (m3) 45279.770

Marginal Retaining Wall


Construction of Siran Right Bank Canal
District Mansehra
Off-take Structure & Head Regulator
BOQ Item Description Calculations
Section @ Area Mean area (ft) Length Volume
(sft) (ft) (cft)

Start 0
0+100 134.93 67.465 100 6746.5
0+200 111.9 123.415 100 12341.5
0+300 213.12 162.51 100 16251
0+400 233.81 223.465 100 22346.5
0+434.77 0 116.905 34.77 4064.78685
Total Quantity (cft) 61750.28685
Total Quantity (m3) 1748.572

Total Quantity of earth work for Diversion Weir and Marginal Bund (m3) 47028.342
Take 85% of the total excavation qty 39974.090883

1.7 Rock Excavation, dressing & disposal up to 50m Medium hard rock, requiring occasional blasting

cub. M.
Take 15% of total excavation (Item 1.6) = 47028.342 x 0.150 = 7054.251 cub. M.

1.8 Plain Cement Concrete including placing, compacting, finishing & curing (Ratio 1:4:8)

Length Width Thickness Volume


(ft) (ft) (ft) (cft)
Undersluices 41.5 21.33 sft area 885.195
Head regulator D/S Toe Wall 26.58 14 0.33 122.800
Head regulator U/S Toe Wall 7.5 14 0.33 34.650
U/S & D/S Cut off walls (3 No.) 210 1 0.33 207.900
RCC Retaining Wall 375 20.5 0.33 2536.875
Total Quantity (cft) 3787.420
Total Quantity (m3) 107.248

1.9 Provide & weave GI wire netting for wire crates 6"x9" mesh : 8 SWG wire

Description Length
Gabion R/Wall Left & Right Upstream of Weir 598 ft
Gabion R/Wall Left & RightDownstream of Weir 215 ft
Total Length of Gabion Retaining Wall 813 ft

Description No. of crates Nos. Area (sft) Qty (sft)


Guide Bund Body Step 1 (13x10x4)
Top & Bottom (13x10) 81.3 2 130 21138
Ends (10x4) 81.3 2 40 6504
Sides (13x4) 81.3 2 52 8455.2

Guide Bund Body Step 2 (11x10x4)


Top & Bottom (11x10) 81.3 2 110 17886
Ends (10x4) 81.3 2 40 6504
Sides (11x4) 81.3 2 44 7154.4

Guide Bund Body Step 3 (10x10x4)


Top & Bottom (10x10) 81.3 2 100 16260
Ends (10x4) 81.3 2 40 6504
Sides (10x4) 81.3 2 40 6504

Guide Bund Body Step 4 (9x10x4)


Top & Bottom (9x10) 81.3 2 90 14634
Construction of Siran Right Bank Canal
District Mansehra
Off-take Structure & Head Regulator
BOQ Item Description Calculations
Ends (10x4) 81.3 2 40 6504
Sides (9x4) 81.3 2 36 5853.6

Guide Bund Body Step 5 (8x10x4)


Top & Bottom (8x10) 81.3 2 80 13008
Ends (10x4) 81.3 2 40 6504
Sides (8x4) 81.3 2 32 5203.2

Guide Bund Body Step 6 (7x10x4)


Top & Bottom (7x10) 81.3 2 70 11382
Ends (10x4) 81.3 2 40 6504
Sides (7x4) 81.3 2 28 4552.8

Guide Bund Body Step 7 (6x10x3)


Top & Bottom (6x10) 81.3 2 60 9756
Ends (10x3) 81.3 2 30 4878
Sides (6x3) 81.3 2 18 2926.8

Guide Bund Body Step 8 (5x10x1.5)


Top & Bottom (5x10) 81.3 2 50 8130
Ends (10x1.5) 81.3 2 15 2439
Sides (5x1.5) 81.3 2 7.5 1219.5

Guide Bund Apron (10x10x4)


Top & Bottom (10x10) 81.3 2 100 16260
Ends (10x4) 81.3 2 40 6504
Sides (10x4) 81.3 2 40 6504

Guide Bund Apron (5x10x4)


Top & Bottom (5x10) 81.3 2 50 8130
Ends (10x4) 81.3 2 40 6504
Sides (5x4) 81.3 2 20 3252

Marginal Bund Apron (10x10x3) Length = 434.77


Top & Bottom (10x10) 43.477 2 100 8695.4
Ends (10x3) 43.477 2 30 2608.62
Sides (10x3) 43.477 2 30 2608.62

Total Area 261471.14 sft


OR 24334.215 sq. m.

1.10 Supply & fill bricks in wire crates including sewing crates, excl cost of crates: Stone orboulders

Description Length Width Depth Quantity


(ft) (ft) (ft) (cft)

Guide Bund Body Step 1 813 13 4 42276


Guide Bund Body Step 2 813 11 4 35772
Guide Bund Body Step 3 813 10 4 32520
Guide Bund Body Step 4 813 9 4 29268
Guide Bund Body Step 5 813 8 4 26016
Guide Bund Body Step 6 813 7 4 22764
Guide Bund Body Step 7 813 6 3 14634
Guide Bund Body Step 8 813 5 1.5 6097.5
Guide Bund Apron 813 15 4 48780
Marginal Bund Apron 434.77 10 3 13043.1
Total Quantity (cft) 271170.6
Total Quantity (m3) 7678.69
Construction of Siran Right Bank Canal
District Mansehra
Off-take Structure & Head Regulator
BOQ Item Description Calculations

Reinforced cement concrete work as in dams, spillways, weirs, barrages, cross drainage works and other hydraulic
structures using crushed stone aggregate(screening & washing) and coarse sand i/c costof all labour and material
1.11 and all kinds of form works, moulds, shuttering lifting/pumping, curing, rendering and finishing the exposed surface,
cast in situ/precast excluding the cost of steel reinforcement and labour for bending binding also excludig cost of
additives which have to be paid separately. Type C (1:2:4)

Description Length Width Thickness Qty


(ft) (ft) (ft) (cft)

RCC Slab / Cover in Weir body 182 153.16 (area) 27875.12


RCC Side Walls 375 129.25 (area) 48468.75
RCC Divide Wall 24.58 155.93 (area) 3832.7594
Undersluice RCC 32.75 324.35 (area) 10622.4625
Breast wall 7 18.69 (area) 130.83
RCC platform undersluice 32.75 15.55 (area) 509.2625
RCC Sheet Piles (344 Nos) 32 2.006 (area) 22082.048
U/S RCC Cut off wall 210 1 4 840
D/S RCC Cut off wall (2 Nos) 210 1 4 1680
Centre Pier at Undersluice 23.58 47.480 (area) 1119.5784
Head Regulator U/S Toe Wall 9.75 1 4 39
Head Regulator Base Slab D/S Toe 26.58 13.5 1 358.83
Head Regulator Base Slab U/S Toe 7.5 13.5 1 101.25
Head Regulator Walls (2 No.s) 26.58 1.5 24 1913.76
Breast wall 7 25.620 (area) 179.34
RCC Stair 34.932 4 4 558.912
Total Quantity (cft) 120311.9028 cft.
Total Quantity (m3) 3406.850 cub. M.

1.12 Supply & fabricate M.S. reinforcement for cement concrete (Hot rolled deformed bars Grade 60)

Concrete Volume as per item 1.11 = 120311.9028 cft

Taking steel as 1.75% of concrete volume = 120311.9028 x1.75% x 490

= 1031674.56651 lbs

OR 468.09 tonnes

1.13 Providing and fixing GI pipe railing (3 feet high)

Length of railing 34.932 ft.


OR 10.65 m.

1.14 PCC 1:3:6 in mass concrete less formwork using 40% boulders

Description Length Width Thickness Qty


(ft) (ft) (ft) (cft)

Below weir body 182 564.27 (area) 102697.14


Below undersluice 32 296.98 (area) 9503.36
Margenal Band
1st Step 100 11.5 3.61 4151.5
1st Step 190 11.5 2.61 5702.85
2nd Step 290 8.5 1.5 3697.5
Construction of Siran Right Bank Canal
District Mansehra
Off-take Structure & Head Regulator
BOQ Item Description Calculations
3rd Step 290 7.5 2 4350
4th Step 290 6.5 2 3770
5th Step 290 5.5 2 3190
6th Step 290 4.5 2 2610
7th Step 290 3.5 2 2030
8th Step 290 2.5 2 1450
9th Step 290 1.5 2 870
1st Step 46 8.5 1.5 586.5
2nd Step 46 7.5 2 690
3rd Step 46 6.5 2 598
4th Step 46 5.5 2 506
5th Step 46 4.5 2 414
6th Step 46 3.5 2 322
7th Step 46 2.5 2 230
8th Step 46 1.5 2 138

Total Quantity (cft) 147506.85


Total Quantity (m3) 4176.925

1.15 Plain Cement Concrete including placing, compacting, finishing & curing (Ratio 1:3:6)
Area Length Volume
Description Length Width Thickness Qty
(ft) (ft) (ft) (cft)

Coping on Gabion Guide Bund 813 5 0.5 2032.5


Total Quantity (cft) 2032.5
Total Quantity (m3) 57.554

1.16 Providing & Laying precast PCC blocks of ratio 1:2:4 having size 2' x 2' x 1'.

Block size i/c space for filling bajri = 2 +0.25 = 2.25ft square

Description Length Width Area


(ft) (ft) (sft)

U/S Floor 210 16 3360


D/S Floor 210 20 4200
Total Area (sft) 7560
No. of blocks = Total Area / (2+0.25)(2+0.25) 1493
Total No. of Blocks 1493

1.17 Providing and Laying expansion joint of neoprene strip 4"x1/4" and plastic bitumen

Weir Joints (20'x20') Length Width Along length Along Width Total
171.5 210 1801 1801 3602 In R. ft.
1098 In R. m.
Construction of Siran Right Bank Canal
District Mansehra
Off-take Structure & Head Regulator
BOQ Item Description Calculations
1.18 Supply & fabricate M.S. reinforcement for cement concrete (Hot rolled deformed bars Grade 40)

#5 Dowel bars in joints


Joint Along length = 171.5/20 = 8.6 Say 9 No.
Joint Along Width = 210/20 = 10.5 Say 11 No.
Dowel along length = 11 x 2 = 22 No.
Total Dowels = 9 x 22 x 2
= 396 No.
Length of one dowel = 2 ft
Total length of 5/8" dia dowel bar = 396 x 2 = 792 ft
Unit weight lb per foot of 5/8" bar = 1.043 lb/ft
Total weight = 792 x 1.043 = 826.056 lb
OR 0.37 Tonne

1.19 Providing and Laying cut, joint, test & disinfect GI pipe line Using light quality GI Pipe : 1" i/d

Joint Along length = 171.5/20 = 8.6 Say 9 No.


Joint Along Width = 210/20 = 10.5 Say 11 No.
Pipes along length = 11 x 2 = 22 No.
Total Pipes (No.) = 9 x 22 x 2
= 396 No.
Length of one pipe = 1 ft
Total length of pipe = 396 x 1 = 396 ft
OR 120.69 Meter

1.20 Grouting stone filling or pitching with bajri in blocks

Filter material in blocks


Along sides
D/S 168 20 1.00 0.25 840
210 16 1.00 0.25 840
U/S 168 16 1.00 0.25 672
210 13 1.00 0.25 682.5
Total 3034.5 cft
OR 85.927 cub. M.

1.21 Levelling and dressing stone filling under blocks and grouting with shingle

Filter material below blocks


Below blocks
Description Length Width Thickness Qty
(ft) (ft) (ft) (cft)

U/S Floor 210 16 0.5 1680


D/S Floor 210 20 0.5 2100
Total Quantity (cft) 3780
Total Quantity (m3) 107.038

1.22 Boring for Cast-in-place RCC Piles in Alluvial Soils : Dia up to 760mm

Description Total length


Length (ft) No. of piles
(ft)
1' dia RCC Sheet Pile Drilling 32 470 15040.000

Total Length (R ft) 15040.000


Construction of Siran Right Bank Canal
District Mansehra
Off-take Structure & Head Regulator
BOQ Item Description Calculations

Total Length (R. Meter) 4583.97

Erecting & removing formwork to concrete in any shape / position (Vertical)


1.23

Form Work for Mass Concrete in under sluice 8 1.5 32 384.000 Below undersluice
Form Work for Mass Concrete in Wier 8 1.5 182 2184.000 Below weir
Marginal Retaining wall 2 434.77 17 14782.180 sq. ft
Total 17350.180 sft
Total 1614.570 sq. m

1.25 P/I gates for head regulator & Under Sluice i/c hoisting device complete in all respect.

Description Nos. Length Width Area


(ft) (ft) (sft)

Undersluice gates (12'x5') 2 12 5 120

Head regulator gate (4.x8') 1 8 4 32

Total Quantity (sft) 152

Total Quantity (m2) 14.145

1.26 Providing and fixing MS steel grated trash rack as per drawings and instructions of Engineer.

Description Nos. Length Width Area


(ft) (ft) (sft)

Trashrack (8'x3') 1 8 3 24

Total Quantity (sft) 24

Total Quantity (m2) 2.233

1.27 Plain woodwork for regulation karries or needles etc. complete as per specs : Deodar wood

Description Nos. Length Width Thickness Area


(ft) (ft) (ft)
(cft)
Stoplog Undersluice 2 12 5 0.41667 50

Stoplog Head Regulator 1 8 4 0.41667 13.33

Total Quantity (cft) 63.33

Total Quantity (m3) 1.793

1.28 Filling and Compacting Soil, Earth and Boulders behind retaining walls (Available material)

Gabion Guide Bund


Section @ Area Mean area (ft) Length Volume
(sft) (ft) (cft)
0 0
U/S 629.87 314.935 139 43775.965
Mid 447.97 538.92 292 157364.64
D/S 587.35 517.66 195 100943.7
End 0 293.675 139 40820.825
Total Quantity (cft) 342905.13
Total Quantity (m3) 9709.983
Construction of Siran Right Bank Canal
District Mansehra
Off-take Structure & Head Regulator
BOQ Item Description Calculations
Marginal Retaining Wall
Section @ Area Mean area (sft) Length Volume
(sft) (ft) (cft)

Start 0
0+100 127.73 63.865 100 6386.5
0+200 207.18 167.455 100 16745.5
0+300 148.89 178.035 100 17803.5
0+400 141.91 145.4 100 14540
0+434.77 0 70.955 34.77 2467.105
Total Quantity (cft) 57942.605
Total Quantity (m3) 1640.750

Total Quantity of backfill (m3) 11350.733

1.29 Supplying and Fixing PVC Water Stopper 8" wide 3/8" thick

Water stoppers in joints Total length


3602.538 R. ft.
1098 R. m
Water stoppers in side walls 1213.83 R. ft.
369.957 R. m

Total length of water stoppers 1467.957 R.m

1.30 Supply & fill bricks in wire crates including sewing crates, excl cost of crates: Stone orboulders

Description Length Width Depth Quantity


(ft) (ft) (ft) (cft)
Guide Bund Body Step 1 813 13 4 42276
Guide Bund Body Step 2 813 11 4 35772
Guide Bund Body Step 3 813 10 4 32520
Guide Bund Body Step 4 813 9 4 29268
Guide Bund Body Step 5 813 8 4 26016
Guide Bund Body Step 6 813 7 4 22764
Guide Bund Body Step 7 813 6 3 14634
Guide Bund Body Step 8 813 5 1.5 6097.5
Guide Bund Apron 813 15 4 48780
Marginal Bund Apron 434.77 10 3 13043.1
Total Quantity (cft) 271170.6
Total Quantity (m3) 7678.69

1.31 Admixture Chemical 3406.850 Liter


Construction of Siran Right Bank Canal
District Mansehra
Irrigation Canal
BOQ Item Description Measurement
No. Sheet Reference
Excavation for core trench of Dam Embankment/Spillway/Intake & Outlet Structure and Irrigation System
2.1 upto a minimum depth of 35 ft in common soil including removing of excavated material by machinery in 1
km radius
Total excavation (in cub. M.) 1136820.482

Take 19.50% excavation in common soil 221679.994 SRBC Irrigation Canal


Cut & Fill Quantities

Excavation for core trench of Dam Embankment/Spillway/Intake & Outlet Structure and Irrigation System
2.2 upto design depth in Soft Rock/Shale requiring 20% blasting including removing of excavated material from
outside of the structure area
Total excavation (in cub. M.) 1136820.482

Take 60% excavation in soft rock 682092.289 SRBC Irrigation Canal


Cut & Fill Quantities

Excavation for core trench of Dam Embankment/Spillway/Intake & Outlet Structure and Irrigation System
2.3 upto a minimum depth of 35 ft in shingle gravel including removing of excavated material by machinery in
1 km radius
Total excavation (in cub. M.) 1136820.482

Take 2.5% excavation in shingle/gravel 28420.512 SRBC Irrigation Canal


Cut & Fill Quantities

Excavation for core trench of Dam Embankment/Spillway/Intake & Outlet Structure and Irrigation System
2.4 upto design depth in Medium Hard Rock requiring 50% blasting including removing of material outside of
the structure area
Total excavation (in cub. M.) 1136820.482

Take 11.25% excavation in medium hard rock 127892.304 SRBC Irrigation Canal
Cut & Fill Quantities

Excavation for core trench of Dam Embankment/Spillway/Intake & Outlet Structure and Irrigation System
2.5 upto design depth in Hard Rock requiring 75% blasting including removing of material outside of the
structure area

Total excavation (in cub. M.) 1136820.482

Take 6.25% excavation in hard rock 71051.280 SRBC Irrigation Canal


Cut & Fill Quantities
2.6 03-60-b Structural Excavation in Rock Material requiring blasting (in cub. M.)
Total excavation (in cub. M.) 1136820.482
Take .2% of total excavation 2273.641
2.7 Structural Back fill using Common Material available at site
Total excavation (in cub. M.) 116600.893

Take 75% of total excavation 87450.670 SRBC Irrigation Canal


Cut & Fill Quantities

2.8 Rehandling of Earthwork up to a lead of 25 m.


Total excavation (in cub. M.) 1136820.482

Take 10% of total excavation 113682.048 SRBC Irrigation Canal


Cut & Fill Quantities

2.9 Formation of Embankment from Roadway Excavation in Common Material including compaction by power
roller
Total fill (in cub. M.) 116600.893

Take 25% of total fill 29150.223 SRBC Irrigation Canal


Cut & Fill Quantities

2.10 Granular Sub Base Course using Pit Run Gravel

Length Width Thickness Volume

184000 14 0.75 1932000 cft


Construction of Siran Right Bank Canal
District Mansehra
Irrigation Canal
BOQ Item Description Measurement
No. Sheet Reference

54699.89 cub. M

2.11 Random rubble masonry in foundn. & plinth Dry masonry


Filling in RRM retaining walls 28,533.91 cub. M
SRBC RRM & Plum
Concrete Retaining
Wall Quantities

2.12 PCC 1:3:6 in mass concrete less formwork using 40% boulders

Filling in Plum Concrete retaining walls (Main canal) 16000.000


SRBC RRM & Plum
Concrete Retaining
Wall Quantities

Filling in Plum Concrete retaining walls (Minor canal) 1351.854

Filling in canal Plum Concrete section 34929.394

SRBC Irrigation Canal


Concrete Quantities

Total PCC (1:3:6) with 40% boulders 52281.248 cub. M

2.13 Plain Cement Concrete including placing, compacting, finishing & curing (Ratio 1:3:6)

Coping in RRM retaining wall 513.156


SRBC RRM & Plum
Concrete Retaining
Wall Quantities
Sewerage Drain 144.27

Concrete band in RRM retaining walls 3268.413

Stone pitching in canal 290.699


Canal Stone Pitching

Total PCC (1:3:6) 4216.538 Cub. M.

2.14 Plain Cement Concrete including placing, compacting,finishing & curing (Ratio 1:2:4)

Sewerage Drain 0
PCC (1:2:4) in canal bed 5,987.30 Cub. M.
SRBC Irrigation Canal
Concrete Quantities

2.15 Plain Cement Concrete including placing, compacting, finishing & curing (Ratio 1:4:8)

PCC (1:4:8) under canal plum concrete section 6,041.43


SRBC Irrigation Canal
Concrete Quantities

PCC (1:4:8) under canal RCC sections 961.377 SIRAN RBC RCC
Sewerage Drain 30.33 Quantities
Total PCC (1:4:8) 7,033.14 Cub. M.

2.16 RCC in roof slab , beam , column and other structural member , in situ or precast. Type C 1:2:4.

Total RCC in canal conduit (Top Slab) 1,457.14 Cub. M.

2.17 RCC in raft foundation slab, base slab of column & ret. wall etc, not including in 06-06. Type C (1:2:4)
Construction of Siran Right Bank Canal
District Mansehra
Irrigation Canal
BOQ Item Description Measurement
No. Sheet Reference

Total RCC in canal conduit (Bottom slab and side walls) 7,789.31 Cub. M.
Construction of Siran Right Bank Canal
District Mansehra
Irrigation Canal
BOQ Item Description Measurement
No. Sheet Reference

2.18 Supply & fabricate M.S. reinforcement for cement concrete (Hot rolled deformed bars Grade 60)

Steel reinforcement (Grade 60) SIRAN RBC RCC


2.00% of RCC volume 1234.14 tonnes Quantities

2.19 Filling expansion joints with bitumen

Joints in canal reach 11,000.71 m SRBC Irrigation Canal


Concrete Quantities

2.20 P/I gates for head regulator & Under Sluice i/c hoisting device complete in all respect.

Gates at bifurcator SIRAN RBC RCC


S. No Desc. Height Width Area Quantities
1 Gate 1 2.41 6.4 15.424
2 Gate 2 2.41 0.853 2.05573
1.626 sq. m

2.21 Formation, dressing and preparing sub-grade In bed

Canal Stone Pitching


In canal stone pitching 34.88 sq. m

2.22 Formation, dressing and preparing sub-grade On slope

Canal Stone Pitching


In canal stone pitching 10173.02 sq. m

2.23 Providing and Laying stone pitching for top layer only : On slope

Canal Stone Pitching


In canal stone pitching 3096.263 sq. m

2.24 Erecting & removing formwork for RCC or plain concrete Vertical

Formwork in canal plum concrete sections 127,260.70 sq. m SRBC Irrigation Canal
Concrete Quantities
Formwork in RRM retaining walls for band & coping 8800.244 sq. m

Formwork in plum retaining walls (Main canal) 16772.837 sq. m


SRBC RRM & Plum
Concrete Retaining
Formwork in plum retaining walls (Minor canal) 2751.628 sq. m Wall Quantities

Formwork in canal stone pitching for profiles 2038.326 sq. m


Canal Stone Pitching
Sewerage Drain 834.63 sq. m
Total 158,458.37 sq. m

2.25 Providing and Laying cut, joint, test, disinfect PVC pipeline BSS Class 'B' working pressure : 3" i/d

Weep holes in RRM Walls 14071.810 m SRBC RRM & Plum


Concrete Retaining
Wall Quantities
Weep holes in plum Walls (Main canal) 3688.510 m

Weep holes in plum Walls (Minor canal) 513.563 m

Total 18,273.88 m

Filter granular backfill behind retaining wall (stone/boulder filling upto one meter to prevent choking of
2.26
weep holes)
Construction of Siran Right Bank Canal
District Mansehra
Irrigation Canal
BOQ Item Description Measurement
No. Sheet Reference
RRM Walls 394.323 Cub. M.
SRBC RRM & Plum
Concrete Retaining
Wall Quantities
Plum Walls (Main canal) 112.571 Cub. M.

Plum Walls (Minor canal) 19.083 Cub. M.

Total 525.98 Cub. M.

2.27 Removal of tree:gith 150mm -300mm i/c removal of stump

Lump sum 800 no.

2.28 Removal of tree:gith 300mm -600mm i/c removal of stump

Lump sum 900 no.

2.29 Dismantling: Plain cement concrete 1:3:6

Length Width Height No. of walls Volume


500 2 4 2 8000
226.501 Cub. M.

2.30 17-01-a Formation, dressing and preparing sub-grade in bed


40899.89 sq.m Old TS Item

2.31 17-01-b Formation, dressing and preparing sub-grade On slope


97733.93 sq.m Old TS Item

2.32 17-02 Stabilized layer of cement, sand mortar 1:30 2" thick
134974.71 sq.m
4" thick PCC lining, using washed screened &
2.33 17-10-a-01 graded/curshed stone aggregate : in bed : Ratio 1:2:4
3836.12 Cub. M.
4" thick PCC lining, using washed screened &
2.34 17-10-b-01 graded/curshed stone aggregate : On slope : Ratio 1:2:4
9055.14 Cub. M.

Carriage of surplus materials i/c loading/unloading to specified disposal site as per instructions of Engineer
2.35 ATR
0.36 Job
2.36 07-30 Supplying and filling sand under floor or plugging in wells
670.05 Cub. M.

2.37 17-11-a Providing and Laying segments in Precast lining (Parabola type) Type A
4268.82 M.
2.38 06-03-e Cement Concrete (brick/stone ballast, 1.5" to 2"/nullah
shingle well graded and cleaned) in foundation & plinth
(Ratio 1:6:18) 7638.08041
Construction of Siran Right Bank Canal
District Mansehra
Main Canal & Minor Concrete Quantities
Reach Length Deductions Net length
Syphons Aqueducts Conduits
06+920 to 20+000 13080 3500 1724 0 7856
20+000 to 24+235 4235 0 0 4235
24+235 to 27+445 3210 155 100 2955
27+445 to 30+020 2575 0 255 2320
30+020 to 31+000 980 100 0 880
31+000 to 44+100 13100 1514 820 10766
44+100 to 65+200 +195 new aligen 21295 350 279.71 785 19880.29
65+200 to 68+835 3635 0 3635
68+835 to 70+315 1480 0 100 1380
70+315 to 73+050 2735 0 0 2735
73+050 to 82+700 9650 1005 0 550 8095
82+700 to 87+050 4350 169.23 0 4180.77
87+050 to 91+642 4592 0 250 4342
91+642 to 98+500 6858 77 1089 5692
98+500 to 110+000 11500 2010 0 268 9222
110+000 to 128+150 18150 431 600 17119
128+150 to 136+600 8450 96 930 7424
136+600 to 143+750 7150 2631 0 4519
143+750 to 150+200 6450 257 184 6009
150+200 to 156+300 6100 91 250 5759
156+300 to 161+400 5100 794 50 4256
161+400 to 172+600 11200 1074 200 9926
172+600 to 174+400 1800 1048 100 652
174+400 to 176+000 1600 0 0 1600
176+000 to 179+150 3150 437 618 2095
179+150 to 180+650 1500 0 0 1500
180+650 to 182+350 1700 0 0 1700
182+350 to 183+150 800 0 30 770
183+150 to 185+322 2172 162 0 2010
BOQ Item No. Description

1 Plain Cement Concrete including placing, compacting, finishing & curing


(Ratio 1:4:8)
Reach No. Length Width Thickness Volume
(ft) (ft) (ft) (cft)
Main Canal

06+920 to 20+000 1 7856 12.25 0.25 24059.000


20+000 to 24+235 1 4235 12.25 0.25 12969.688
24+235 to 27+445 1 2955 12.25 0.25 9049.688
27+445 to 30+020 1 2320 12.25 0.25 7105.000
30+020 to 31+000 1 880 12.10 0.25 2662.000
31+000 to 44+100 1 10766 12.10 0.25 32567.150
44+100 to 65+200 1 19880.29 12.00 0.25 59640.870
65+200 to 68+835 1 3635 12.00 0.25 10905.000
68+835 to 70+315 1 1380 12.00 0.25 4140.000
70+315 to 73+050 1 2735 12.00 0.25 8205.000
73+050 to 82+700 1 8095 10.14 0.25 20520.825
82+700 to 87+050 1 4180.77 10.14 0.25 10598.252
87+050 to 91+642 1 4342 10.04 0.25 10898.420
Sewerage 30.332
Total Quantity (Cft) 213351.224
Total Quantity (Cu.M) 6041.428

2 Plain Cement Concrete including placing, compacting, finishing & curing


(Ratio 1:2:4)
Reach No. Length Width Thickness Volume
(ft) (ft) (ft) (cft)
Main Canal

06+920 to 20+000 1 7856 6.75 0.334 17711.352


Construction of Siran Right Bank Canal
District Mansehra
Main Canal & Minor Concrete Quantities
Reach Length Deductions Net length
Syphons Aqueducts Conduits
06+920 to 20+000 13080 3500 1724 0 7856
20+000 to 24+235 4235 0 0 4235
24+235 to 27+445 3210 155 100 2955
27+445 to 30+020 2575 0 255 2320
30+020 to 31+000 980 100 0 880
31+000 to 44+100 13100 1514 820 10766
44+100 to 65+200 +195 new aligen 21295 350 279.71 785 19880.29
65+200 to 68+835 3635 0 3635
68+835 to 70+315 1480 0 100 1380
70+315 to 73+050 2735 0 0 2735
73+050 to 82+700 9650 1005 0 550 8095
82+700 to 87+050 4350 169.23 0 4180.77
87+050 to 91+642 4592 0 250 4342
91+642 to 98+500 6858 77 1089 5692
98+500 to 110+000 11500 2010 0 268 9222
110+000 to 128+150 18150 431 600 17119
128+150 to 136+600 8450 96 930 7424
136+600 to 143+750 7150 2631 0 4519
143+750 to 150+200 6450 257 184 6009
150+200 to 156+300 6100 91 250 5759
156+300 to 161+400 5100 794 50 4256
161+400 to 172+600 11200 1074 200 9926
172+600 to 174+400 1800 1048 100 652
174+400 to 176+000 1600 0 0 1600
176+000 to 179+150 3150 437 618 2095
179+150 to 180+650 1500 0 0 1500
180+650 to 182+350 1700 0 0 1700
182+350 to 183+150 800 0 30 770
183+150 to 185+322 2172 162 0 2010
BOQ Item No. Description
20+000 to 24+235 1 4235 6.75 0.334 9547.808
24+235 to 27+445 1 2955 6.75 0.334 6662.048
27+445 to 30+020 1 2320 6.75 0.334 5230.440
30+020 to 31+000 1 880 6.60 0.334 1939.872
31+000 to 44+100 1 10766 6.60 0.334 23732.570
44+100 to 65+200 1 19880.29 6.50 0.334 43160.110
65+200 to 68+835 1 3635 6.50 0.334 7891.585
68+835 to 70+315 1 1380 6.50 0.334 2995.980
70+315 to 73+050 1 2735 6.50 0.334 5937.685
73+050 to 82+700 1 8095 6.30 0.334 17033.499
82+700 to 87+050 1 4180.77 6.30 0.334 8797.176
87+050 to 91+642 1 4342 6.20 0.334 8991.414
Total Quantity (Cft) 159631.538
Total Quantity (Cu.M) 4520.258

3 PCC 1:3:6 in mass concrete less formwork using 40% boulders

Reach No. Length Width Depth Volume


(ft) (ft) (ft) (cft)
Main Canal
06+920 to 20+000 Step 1 2 1338 2.50 2.5 16725.000
06+920 to 20+000 Step 2 2 1338 1.75 2.385 11168.955
06+920 to 20+000 New Design 2 6518 1.875 Avg 4.885 119401.613
20+000 to 24+235 Step 1 2 750 2.50 2.50 9375.000
20+000 to 24+235 Step 2 2 750 1.75 2.30 6037.500
20+000 to 24+236 New Design 2 3485 1.830 Avg 4.8 61224.480
24+235 to 27+445 Step 1 2 1280 2.50 2.50 16000.000
Construction of Siran Right Bank Canal
District Mansehra
Main Canal & Minor Concrete Quantities
Reach Length Deductions Net length
Syphons Aqueducts Conduits
06+920 to 20+000 13080 3500 1724 0 7856
20+000 to 24+235 4235 0 0 4235
24+235 to 27+445 3210 155 100 2955
27+445 to 30+020 2575 0 255 2320
30+020 to 31+000 980 100 0 880
31+000 to 44+100 13100 1514 820 10766
44+100 to 65+200 +195 new aligen 21295 350 279.71 785 19880.29
65+200 to 68+835 3635 0 3635
68+835 to 70+315 1480 0 100 1380
70+315 to 73+050 2735 0 0 2735
73+050 to 82+700 9650 1005 0 550 8095
82+700 to 87+050 4350 169.23 0 4180.77
87+050 to 91+642 4592 0 250 4342
91+642 to 98+500 6858 77 1089 5692
98+500 to 110+000 11500 2010 0 268 9222
110+000 to 128+150 18150 431 600 17119
128+150 to 136+600 8450 96 930 7424
136+600 to 143+750 7150 2631 0 4519
143+750 to 150+200 6450 257 184 6009
150+200 to 156+300 6100 91 250 5759
156+300 to 161+400 5100 794 50 4256
161+400 to 172+600 11200 1074 200 9926
172+600 to 174+400 1800 1048 100 652
174+400 to 176+000 1600 0 0 1600
176+000 to 179+150 3150 437 618 2095
179+150 to 180+650 1500 0 0 1500
180+650 to 182+350 1700 0 0 1700
182+350 to 183+150 800 0 30 770
183+150 to 185+322 2172 162 0 2010
BOQ Item No. Description
24+235 to 27+445 Step 2 2 1280 1.75 2.23 9990.400
24+235 to 27+445 New Design 2 1675 1.790 Avg 4.73 28363.445
27+445 to 30+020 Step 1 2 1140 2.50 2.5 14250.000
27+445 to 30+020 Step 2 2 1140 1.75 2.15 8578.500
27+445 to 30+020 New Design 2 1180 1.790 Avg 4.65 19643.460
30+020 to 31+000 Step 1 2 655 2.50 2.32 7598.000
30+020 to 31+000 Step 2 2 655 1.75 2.32 5318.600
30+020 to 31+000 New Design 2 225 1.790 Avg 4.64 3737.520
31+000 to 44+100 Step 1 2 7121 2.50 2.32 82603.600
31+000 to 44+100 Step 2 2 7121 1.75 2.32 57822.520
31+000 to 44+100 New Design 2 830 1.790 Avg 4.64 13787.296
31+000 to 44+100 New Design 2 2815 1.750 Avg 6.96 68573.400
44+100 to 65+200 Step 1 2 925 2.50 2.32 10730.000
44+100 to 65+200 Step 2 2 925 1.75 2.29 7413.875
44+100 to 65+200 New Design 2 18955.29 1.710 Avg 4.61 298852.893
65+200 to 68+835 Step 1 2 3635 2.50 2.48 45074.000
65+200 to 68+835 Step 2 2 3635 1.75 2.05 26081.125
68+835 to 70+315 Step 1 2 115 2.50 2.22 1276.500
68+835 to 70+315 Step 2 2 115 1.75 2.225 895.563
68+835 to 70+315 New Design 2 1265 1.625 Avg 4.445 18274.506
70+315 to 73+050 New Design 2 2735 1.585 Avg 4.36 37800.982
73+050 to 82+700 New Design 2 8095 1.585 Avg 4.355 111754.308
82+700 to 87+050 New Design 2 4180.77 1.585 Avg 4.29 56855.545
87+050 to 91+642 New Design 2 4342 1.585 Avg 4.25 58497.595
Total Quantity (Cft) 1233706.181
Total Quantity (Cu.M) 34929.394
Construction of Siran Right Bank Canal
District Mansehra
Main Canal & Minor Concrete Quantities
Reach Length Deductions Net length
Syphons Aqueducts Conduits
06+920 to 20+000 13080 3500 1724 0 7856
20+000 to 24+235 4235 0 0 4235
24+235 to 27+445 3210 155 100 2955
27+445 to 30+020 2575 0 255 2320
30+020 to 31+000 980 100 0 880
31+000 to 44+100 13100 1514 820 10766
44+100 to 65+200 +195 new aligen 21295 350 279.71 785 19880.29
65+200 to 68+835 3635 0 3635
68+835 to 70+315 1480 0 100 1380
70+315 to 73+050 2735 0 0 2735
73+050 to 82+700 9650 1005 0 550 8095
82+700 to 87+050 4350 169.23 0 4180.77
87+050 to 91+642 4592 0 250 4342
91+642 to 98+500 6858 77 1089 5692
98+500 to 110+000 11500 2010 0 268 9222
110+000 to 128+150 18150 431 600 17119
128+150 to 136+600 8450 96 930 7424
136+600 to 143+750 7150 2631 0 4519
143+750 to 150+200 6450 257 184 6009
150+200 to 156+300 6100 91 250 5759
156+300 to 161+400 5100 794 50 4256
161+400 to 172+600 11200 1074 200 9926
172+600 to 174+400 1800 1048 100 652
174+400 to 176+000 1600 0 0 1600
176+000 to 179+150 3150 437 618 2095
179+150 to 180+650 1500 0 0 1500
180+650 to 182+350 1700 0 0 1700
182+350 to 183+150 800 0 30 770
183+150 to 185+322 2172 162 0 2010
BOQ Item No. Description

4 Erection and removal of steel Form work for RCC or Plain Concrete
vertical
Reach No. Faces Length Depth Volume
(ft) (ft) (sft)

06+920 to 20+000 Step 1 2 2 1338 2.5 13380.000


06+920 to 20+000 Step 2 2 2 1338 2.385 12764.520
06+920 to 20+000 New 2 2 6518 4.885 127361.720
20+000 to 24+235 Step 1 2 2 750 2.5 7500.000
20+000 to 24+235 Step 2 2 2 750 2.3 6900.000
20+000 to 24+236 New 2 2 3485 4.8 66912.000
24+235 to 27+445 Step 1 2 2 1280 2.5 12800.000
24+235 to 27+445 Step 2 2 2 1280 2.23 11417.600
24+235 to 27+445 New 2 2 1675 4.73 31691.000
27+445 to 30+020 Step 1 2 2 1140 2.5 11400.000
27+445 to 30+020 Step 2 2 2 1140 2.15 9804.000
27+445 to 30+020 New 2 2 1180 4.65 21948.000
30+020 to 31+000 Step 1 2 2 655 2.32 6078.400
30+020 to 31+000 Step 2 2 2 655 2.32 6078.400
30+020 to 31+000 New 2 2 225 4.64 4176.000
31+000 to 44+100 Step 1 2 2 7121 2.32 66082.880
31+000 to 44+100 Step 2 2 2 7121 2.32 66082.880
31+000 to 44+100 New 2 2 830 4.64 15404.800
31+000 to 44+100 New 2 2 2815 6.96 78369.600
44+100 to 65+200 Step 1 2 2 925 2.32 8584.000
44+100 to 65+200 Step 2 2 2 925 2.29 8473.000
Construction of Siran Right Bank Canal
District Mansehra
Main Canal & Minor Concrete Quantities
Reach Length Deductions Net length
Syphons Aqueducts Conduits
06+920 to 20+000 13080 3500 1724 0 7856
20+000 to 24+235 4235 0 0 4235
24+235 to 27+445 3210 155 100 2955
27+445 to 30+020 2575 0 255 2320
30+020 to 31+000 980 100 0 880
31+000 to 44+100 13100 1514 820 10766
44+100 to 65+200 +195 new aligen 21295 350 279.71 785 19880.29
65+200 to 68+835 3635 0 3635
68+835 to 70+315 1480 0 100 1380
70+315 to 73+050 2735 0 0 2735
73+050 to 82+700 9650 1005 0 550 8095
82+700 to 87+050 4350 169.23 0 4180.77
87+050 to 91+642 4592 0 250 4342
91+642 to 98+500 6858 77 1089 5692
98+500 to 110+000 11500 2010 0 268 9222
110+000 to 128+150 18150 431 600 17119
128+150 to 136+600 8450 96 930 7424
136+600 to 143+750 7150 2631 0 4519
143+750 to 150+200 6450 257 184 6009
150+200 to 156+300 6100 91 250 5759
156+300 to 161+400 5100 794 50 4256
161+400 to 172+600 11200 1074 200 9926
172+600 to 174+400 1800 1048 100 652
174+400 to 176+000 1600 0 0 1600
176+000 to 179+150 3150 437 618 2095
179+150 to 180+650 1500 0 0 1500
180+650 to 182+350 1700 0 0 1700
182+350 to 183+150 800 0 30 770
183+150 to 185+322 2172 162 0 2010
BOQ Item No. Description
44+100 to 65+200 New 2 2 18955.29 4.61 349535.548
65+200 to 68+835 Step 1 2 2 3635 2.48 36059.200
65+200 to 68+835 Step 2 2 2 3635 2.05 29807.000
68+835 to 70+315 Step 1 2 2 115 2.22 1021.200
68+835 to 70+315 Step 2 2 2 115 2.225 1023.500
68+835 to 70+315 New 2 2 1265 4.445 22491.700
70+315 to 73+050 New 2 2 2735 4.36 47698.400
73+050 to 82+700 New 2 2 8095 4.355 141014.900
82+700 to 87+050 New 2 2 4180.77 4.29 71742.013
87+050 to 91+642 New 2 2 4342 4.25 73814.000

Total Quantity (Sft) 1367416.261


Total Quantity (Sq.M) 127260.704

3 Filing Expansion Joint with Bitumen

Joints at 50' c/c

Reach No. Reach Length No. of Joints Joint length Quantity


(ft) (ft) (Rft)
Main Canal
07+100 to 20+000 1 7856 157.12 0.000
Construction of Siran Right Bank Canal
District Mansehra
Main Canal & Minor Concrete Quantities
Reach Length Deductions Net length
Syphons Aqueducts Conduits
06+920 to 20+000 13080 3500 1724 0 7856
20+000 to 24+235 4235 0 0 4235
24+235 to 27+445 3210 155 100 2955
27+445 to 30+020 2575 0 255 2320
30+020 to 31+000 980 100 0 880
31+000 to 44+100 13100 1514 820 10766
44+100 to 65+200 +195 new aligen 21295 350 279.71 785 19880.29
65+200 to 68+835 3635 0 3635
68+835 to 70+315 1480 0 100 1380
70+315 to 73+050 2735 0 0 2735
73+050 to 82+700 9650 1005 0 550 8095
82+700 to 87+050 4350 169.23 0 4180.77
87+050 to 91+642 4592 0 250 4342
91+642 to 98+500 6858 77 1089 5692
98+500 to 110+000 11500 2010 0 268 9222
110+000 to 128+150 18150 431 600 17119
128+150 to 136+600 8450 96 930 7424
136+600 to 143+750 7150 2631 0 4519
143+750 to 150+200 6450 257 184 6009
150+200 to 156+300 6100 91 250 5759
156+300 to 161+400 5100 794 50 4256
161+400 to 172+600 11200 1074 200 9926
172+600 to 174+400 1800 1048 100 652
174+400 to 176+000 1600 0 0 1600
176+000 to 179+150 3150 437 618 2095
179+150 to 180+650 1500 0 0 1500
180+650 to 182+350 1700 0 0 1700
182+350 to 183+150 800 0 30 770
183+150 to 185+322 2172 162 0 2010
BOQ Item No. Description
20+000 to 24+235 1 4235 84.7 6.75 571.725
24+235 to 27+445 1 2955 59.1 6.75 398.925
27+445 to 30+020 1 2320 46.4 6.75 313.200
30+020 to 31+000 1 880 17.6 6.60 116.160
31+000 to 44+100 1 10766 215.32 6.60 1421.112
44+100 to 65+200 1 19880.29 397.6058 6.50 2584.438
65+200 to 68+835 1 3635 72.7 6.50 472.550
68+835 to 70+315 1 1380 27.6 6.50 179.400
70+315 to 73+050 1 2735 54.7 6.50 355.550
73+050 to 82+700 1 8095 161.9 6.30 1019.970
82+700 to 87+050 1 4180.77 83.6154 6.30 526.777
87+050 to 91+642 1 4342 86.84 6.20 538.408

Total Quantity (Rft) 8498.215


Total Quantity (R.M) 2590.129
Construction of Siran Right Bank Canal
District Mansehra
Open / Conduit RCC sections
BOQ Item No. Description

1 Plain Cement Concrete including placing, compacting, finishing &


curing (Ratio 1:4:8)
Reach Length Width Thickness Volume (cft)
(ft) (ft) (ft)

RD: 0+000 to 0+500 500 9.25 0.25 1156.250


RD: 0+500 to 6+638 6138 11 0.25 16879.500
RD: 6+638 to6+688 50 12.09 0.5 302.250 Road Crossing
RD: 6+688 to7+100 412 11 0.25 1133.000
RD: 26+250 to 26+350 100 9.25 0.25 231.250
RD: 28+500 to 28+550 50 9.25 0.25 115.625
RD: 28+675 to 28+825 150 9.25 0.25 346.875
RD: 31+525 to 31+625 100 9.1 0.25 227.500
RD: 32+250 to 32450 200 9.1 0.25 455.000
RD: 34+450 to 34+600 150 9.1 0.25 341.250
RD: 35+750 to 35+850 100 9.1 0.25 227.500
RD: 39+675 to 39+775 100 9.1 0.25 227.500
RD: 42+875 to 42+995 120 9.1 0.25 273.000
RD: 47+250 to 47+500 250 9 0.25 562.500
RD: 48+975 to 49+240 265 9 0.25 596.250
RD: 54+000 to 54+050 50 9 0.25 112.500
RD: 54+250 to 54+370 120 9 0.25 270.000
RD: 64+430 to 64+530 100 9 0.25 225.000
RD: 66+900 to 67+000 100 9 0.25 225.000
RD: 69+750 to 69+850 100 9 0.25 225.000
RD: 73+225 to 73+275 50 8.8 0.25 110.000
RD: 73+575 to 73+725 150 8.8 0.25 330.000
RD: 75+475 to 75+725 250 8.8 0.25 550.000
RD: 77+900 to 78+000 100 8.8 0.25 220.000
RD: 89+131 to 89+281 150 8.7 0.25 326.250
RD: 90+376 to 90+476 100 8.7 0.25 217.500
RD: 91+654 to 92+643 989 7.5 0.25 1854.375
RD: 94+559 to 94+609 50 7.5 0.25 93.750
RD: 95+219 to 95+269 50 7.5 0.25 93.750
RD: 98+551 to 98+651 100 7.5 0.25 187.500
RD: 105+219 to 105+387 168 7.5 0.25 315.000
RD: 110+750 to 110+900 150 7.5 0.25 281.250
RD: 123+423 to 123+523 100 7.5 0.25 187.500
RD: 124+731 to 125+081 350 7.5 0.25 656.250
RD: 128+250 to 128+400 150 7.25 0.25 271.875
RD: 129+039 to 129+169 130 7.25 0.25 235.625
RD: 130+031 to 130+481 450 7.25 0.25 815.625
RD: 135+631 to 135+731 100 7.25 0.25 181.250
RD: 135+750 to 135+850 100 7.25 0.25 181.250
RD: 144+804 to 144+988 184 7 0.25 322.000
RD: 150+399 to 150+499 100 6.8 0.25 170.000
RD: 150+622 to 150+672 50 6.8 0.25 85.000
RD: 151+500 to 151+600 100 6.8 0.25 170.000
RD: 158+736 to 158+786 50 6.5 0.25 81.250
RD: 161+444 to 161+544 100 6.2 0.25 155.000
RD: 166+130 to 166+580 450 6.2 0.25 697.500
RD: 173+050 to 173+150 100 5.8 0.25 145.000
RD: 176+472 to 176+740 268 5.5 0.25 368.500
RD: 177+856 to 178+206 350 5.5 0.25 481.250
RD: 182+941 to 182+971 30 4.5 0.25 33.750

Total 33950.750 Cub. ft.


OR 961.377 Cub. M.
2 RCC in raft foundation slab, base slab of column & ret.
wall etc, not including in 06-06. Type C(1:2:4)

Reach No. Length Width Depth Volume (cft)


(ft) (ft) (ft)

RD: 0+000 to 0+500 Bed 1 500 8.75 0.75 3281.250


Side Walls 2 500 0.75 4.75 3562.500
RD: 0+500 to 6+638 Bed 1 6138 10.5 0.75 48336.750
Side Walls 2 6138 0.75 4.555 41937.885
Divide Wall 1 6138 0.5 4.555 13979.295
RD: 6+638to 6+688 Bed 1 50 11.09 1 554.500 Road xing
Side Walls 2 50 1 4.555 455.500
Divide Wall 1 50 0.67 4.555 152.593
RD: 6+688 to 7+100 Bed 1 412 10.5 0.67 2898.420
Side Walls 2 412 0.75 4.555 2814.990
Divide Wall 1 412 0.67 4.555 1257.362
RD: 26+250 to 26+350 Bed 1 100 8.75 1 875.000
Side Walls 2 100 1 6 1200.000
RD: 28+500 to 28+550 Bed 1 50 8.75 1 437.500
Side Walls 2 50 1 6 600.000
RD: 28+675 to 28+880 Bed 1 205 8.75 1 1793.750
Side Walls 2 205 1 6 2460.000
RD: 31+525 to 31+625 Bed 1 100 8.6 1 860.000
Side Walls 2 100 1 6 1200.000
RD: 32+250 to 32+500Bed 1 250 8.6 1 2150.000
Side Walls 2 250 1 6 3000.000
RD: 34+450 to 34+600 Bed 1 150 8.6 1 1290.000
Side Walls 2 150 1 6 1800.000
RD: 35+750 to 35+850 Bed 1 100 8.6 1 860.000
Side Walls 2 100 1 6 1200.000
RD: 39+675 to 39+775 Bed 1 100 8.6 1 860.000
Side Walls 2 100 1 6 1200.000
RD: 42+875 to 42+995 Bed 1 120 8.6 1 1032.000
Side Walls 2 120 1 6 1440.000
RD: 47+250 to 47+500 Bed 1 250 8.5 1 2125.000
Side Walls 2 250 1 6 3000.000
RD: 48+975 to 49+240 Bed 1 265 8.5 1 2252.500
Side Walls 2 265 1 6 3180.000
RD: 54+000 to 54+050 Bed 1 50 8.5 1 425.000
Side Walls 2 50 1 6 600.000
RD: 54+250 to 54+370 Bed 1 120 8.5 1 1020.000
Side Walls 2 120 1 6 1440.000
RD: 64+430 to 64+530 Bed 1 100 8.5 1 850.000
Side Walls 2 100 1 6 1200.000
RD: 66+900 to 67+000 Bed 1 100 8.5 1 850.000
Side Walls 2 100 1 6 1200.000
RD: 69+750 to 69+850 Bed 1 100 8.5 1 850.000
Side Walls 2 100 1 6 1200.000
RD: 73+225 to 73+275 Bed 1 50 8.3 1 415.000
Side Walls 2 50 1 6 600.000
RD: 73+575 to 73+725 Bed 1 150 8.3 1 1245.000
Side Walls 2 150 1 6 1800.000
RD: 75+475 to 75+725 Bed 1 250 8.3 1 2075.000
Side Walls 2 250 1 6 3000.000
RD: 77+900 to 78+000 Bed 1 100 8.3 1 830.000
Side Walls 2 100 1 6 1200.000
RD: 89+131 to 89+281 Bed 1 150 8.2 1 1230.000
Side Walls 2 150 1 6 1800.000
RD: 90+376 to 90+476 Bed 1 100 8.2 1 820.000
Side Walls 2 100 1 6 1200.000
RD: 91+654 to 92+643 Bed 1 989 7 1 6923.000
Side Walls 2 989 1 6 11868.000
RD: 94+559 to 94+609 Bed 1 50 7 1 350.000
Side Walls 2 50 1 6 600.000
RD: 95+219 to 95+269 Bed 1 50 7 1 350.000
Side Walls 2 50 1 6 600.000
RD: 98+551 to 98+651 Bed 1 100 7 1 700.000
Side Walls 2 100 1 6 1200.000
RD: 105+219 to 105+387 Bed 1 168 7 1 1176.000
Side Walls 2 168 1 6 2016.000
RD: 110+750 to 110+900 Bed 1 150 7 1 1050.000
Side Walls 2 150 1 6 1800.000
RD: 123+423 to 123+523 Bed 1 100 7 1 700.000
Side Walls 2 100 1 6 1200.000
RD: 124+731 to 125+081 Bed 1 350 7 1 2450.000
Side Walls 2 350 1 6 4200.000
RD: 128+250 to 128+400 Bed 1 150 6.75 1 1012.500
Side Walls 2 150 1 6 1800.000
RD: 129+039 to 129+169 Bed 1 130 6.75 1 877.500
Side Walls 2 130 1 6 1560.000
RD: 130+031 to 130+481 Bed 1 450 6.75 1 3037.500
Side Walls 2 450 1 6 5400.000
RD: 135+631 to 135+731 Bed 1 100 6.75 1 675.000
Side Walls 2 100 1 6 1200.000
RD: 135+750 to 135+850 Bed 1 100 6.75 1 675.000
Side Walls 2 100 1 6 1200.000
RD: 144+804 to 144+988 Bed 1 184 6.5 1 1196.000
Side Walls 2 184 1 6 2208.000
RD: 150+399 to 150+499 Bed 1 100 6.3 1 630.000
Side Walls 2 100 1 6 1200.000
RD: 150+622 to 150+672 Bed 1 50 6.3 1 315.000
Side Walls 2 50 1 6 600.000
RD: 151+500 to 151+600 Bed 1 100 6.3 1 630.000
Side Walls 2 100 1 6 1200.000
RD: 158+736 to 158+786 Bed 1 50 6 1 300.000
Side Walls 2 50 1 6 600.000
RD: 161+444 to 161+544 Bed 1 100 5.7 1 570.000
Side Walls 2 100 1 6 1200.000
RD: 166+130 to 166+580 Bed 1 350 5.7 1 1995.000
Side Walls 2 350 1 6 4200.000
RD: 173+050 to 173+150 Bed 1 100 5.3 1 530.000
Side Walls 2 100 1 61 12200.000
RD: 176+472 to 176+740 Bed 1 268 5 1 1340.000
Side Walls 2 268 1 6 3216.000
RD: 177+856 to 178+206 Bed 1 350 5 1 1750.000
Side Walls 2 350 1 6 4200.000
RD: 182+941 to 182+971 Bed 1 30 4 1 120.000
Side Walls 2 30 1 6 360.000

Total 275077.295 Cub. ft.


OR 7789.314 Cub. M.

3 RCC in roof slab, beam, column & other structural


members, insitu or precast. Type C (1:2:4)

Reach No. Length Width Depth Volume (cft)


(ft) (ft) (ft)

RD:6+638 to 6+688 Top Slab 1 50 11.09 1 554.500 Road xing


RD: 26+250 to 26+350 Top Slab 1 100 8.75 1 875.000
RD: 28+500 to 28+550 Top Slab 1 50 8.75 1 437.500
RD: 28+675 to 28+825 Top Slab 1 150 8.75 0.75 984.375
RD: 31+525 to 31+625 Top Slab 1 100 8.6 0.75 645.000
RD:32+250 to 32+450 Top Slab 1 200 8.6 1 1720.000
RD: 34+450 to 34+600 Top Slab 1 150 8.6 1 1290.000
RD: 35+750 to 35+850 Top Slab 1 100 8.6 1 860.000
RD: 39+675 to 39+775 Top Slab 1 100 8.6 1 860.000
RD: 42+875 to 42+995 Top Slab 1 120 8.6 1 1032.000
RD: 47+250 to 47+500 Top Slab 1 235 8.5 1 1997.500
RD: 48+975 to 49+240 Top Slab 1 250 8.5 1 2125.000
RD: 54+000 to 54+050 Top Slab 1 50 8.5 1 425.000
RD: 54+250 to 54+370 Top Slab 1 120 8.5 1 1020.000
RD: 64+430 to 64+530 Top Slab 1 100 8.5 0.75 637.500
RD: 66+900 to 67+000 Top Slab 1 100 8.5 0.75 637.500
RD: 69+750 to 69+850 Top Slab 1 100 8.5 0.75 637.500
RD: 73+225 to 73+275 Top Slab 1 50 8.3 1 415.000
RD: 73+575 to 73+725 Top Slab 1 150 8.3 1 1245.000
RD: 75+475 to 75+725 Top Slab 1 250 8.3 1 2075.000
RD: 77+900 to 78+000 Top Slab 1 100 8.3 1 830.000
RD: 89+131 to 89+281 Top Slab 1 150 8.2 1 1230.000
RD: 90+376 to 90+476 Top Slab 1 100 8.2 1 820.000
RD: 91+654 to 92+643 Top Slab 1 989 7 1 6923.000
RD: 94+559 to 94+609 Top Slab 1 50 7 1 350.000
RD: 95+219 to 95+269 Top Slab 1 50 7 1 350.000
RD: 98+551 to 98+651 Top Slab 1 100 7 1 700.000
RD: 105+219 to 105+387 Top Slab 1 168 7 1 1176.000
RD: 110+750 to 110+900 Top Slab 1 150 7 1 1050.000
RD: 123+423 to 123+523 Top Slab 1 100 7 1 700.000
RD: 124+731 to 125+081 Top Slab 1 350 7 1 2450.000
RD: 128+250 to 128+400 Top Slab 1 150 6.75 1 1012.500
RD: 129+039 to 129+169 Top Slab 1 130 6.75 1 877.500
RD: 130+031 to 130+481 Top Slab 1 300 6.75 1 2025.000
RD: 135+631 to 135+731 Top Slab 1 100 6.75 1 675.000
RD: 135+750 to 135+850 Top Slab 1 100 6.75 1 675.000
RD: 144+804 to 144+988 Top Slab 1 184 6.5 1 1196.000
RD: 150+399 to 150+499 Top Slab 1 100 6.3 1 630.000
RD: 150+622 to 150+672 Top Slab 1 50 6.3 1 315.000
RD: 151+500 to 151+600 Top Slab 1 100 6.3 1 630.000
RD: 158+736 to 158+786 Top Slab 1 50 6 1 300.000
RD: 161+444 to 161+544 Top Slab 1 100 5.7 1 570.000
RD: RD: 166+130 to 166+580 Top Slab 1 250 5.7 1 1425.000
RD: 173+050 to 173+150 Top Slab 1 100 5.3 1 530.000
RD: 176+472 to 176+740 Top Slab 1 268 5 1 1340.000
RD: 177+856 to 178+206 Top Slab 1 350 5 1 1750.000
RD: 182+941 to 182+971 Top Slab 1 30 4 1 120.000
Sewerage Drain 335.2
Total 51458.575 Cub. ft.
OR 1457.143 Cub. M.

4 Supply & fabricate M.S. reinforcement for cement concrete (Hot rolled
deformed bars Grade 40)

Taking 2.00% of RCC Volume as per Item 2 & 3


Concrete Quantity = 275077.29 + 51458.575 = 326535.87 cft
Steel Quantity = 326535.87 x 1.75% x 490
= 2720043.795 lbs
OR 1234.14 tonnes
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

1 0+000 0.00 17.21 8.61 0.00


2 0+050 50.00 16.77 16.99 849.48
3 0+100 50.00 13.35 15.06 752.90
4 0+150 50.00 15.28 14.31 715.65
5 0+200 50.00 11.54 13.41 670.45
6 0+250 50.00 11.75 11.65 582.28
7 0+300 50.00 15.29 13.52 676.03
8 0+350 50.00 20.16 17.73 886.25
9 0+400 50.00 23.18 21.67 1083.53
10 0+450 50.00 29.97 26.58 1328.83
11 0+500 50.00 24.60 27.28 1364.20
12 0+500 0.00 29.82 27.21 0.00
13 0+550 50.00 42.30 36.06 1803.00
14 0+600 50.00 37.46 39.88 1994.00
15 0+600 0.00 36.10 36.78 0.00
16 0+650 50.00 49.43 42.77 2138.30
17 0+700 50.00 65.03 57.23 2861.55
18 0+750 50.00 65.13 65.08 3254.00
19 0+800 50.00 59.34 62.24 3111.75
20 0+850 50.00 61.11 60.23 3011.25
21 0+850 0.00 62.69 61.90 0.00
22 0+950 100.00 46.41 54.55 5455.00
23 1+000 50.00 46.46 46.44 2321.75
24 1+050 50.00 52.29 49.38 2468.75
25 1+100 50.00 56.63 54.46 2723.00
26 1+110 10.00 59.93 58.28 582.80
27 1+110 0.00 57.07 58.50 0.00
28 1+120 10.00 70.12 63.60 635.95
29 1+155 35.00 54.04 62.08 2172.80
30 1+250 95.00 53.95 54.00 5129.53
31 1+295 45.00 49.88 51.92 2336.18
32 1+310 15.00 46.16 48.02 720.30
33 1+310 0.00 55.91 51.04 0.00
34 1+375 65.00 57.80 56.86 3695.58
35 1+475 100.00 54.88 56.34 5634.00
36 1+544 69.00 42.39 48.64 3355.82
37 1+594 50.00 35.26 38.83 1941.25
38 1+594 0.00 25.29 30.28 0.00
39 1+680 86.00 41.41 33.35 2868.10
40 1+740 60.00 58.10 49.76 2985.30
41 1+825 85.00 54.06 56.08 4766.80
42 1+845 20.00 38.24 46.15 923.00
43 1+870 25.00 51.37 44.81 1120.13
44 1+920 50.00 45.55 48.46 2423.00
45 2+000 80.00 35.88 40.72 3257.20
46 2+100 100.00 35.55 35.72 3571.50
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

47 2+200 100.00 49.41 42.48 4248.00


48 2+275 75.00 68.42 58.92 4418.63
49 2+375 100.00 54.21 61.32 6131.50
50 2+475 100.00 30.59 42.40 4240.00
51 2+575 100.00 39.26 34.93 3492.50
52 2+675 100.00 48.63 43.95 4394.50
53 2+775 100.00 31.81 40.22 4022.00
54 2+875 100.00 29.99 30.90 3090.00
55 2+935 60.00 29.53 29.76 1785.60
56 2+950 15.00 38.97 34.25 513.75
57 3+050 100.00 31.42 35.20 3519.50
58 3+110 60.00 54.13 42.78 2566.50
59 3+200 90.00 37.15 45.64 4107.60
60 3+270 70.00 37.69 37.42 2619.40
61 3+350 80.00 43.01 40.35 3228.00
62 3+410 60.00 35.57 39.29 2357.40
63 3+482 72.00 51.86 43.72 3147.48
64 3+493 11.00 66.98 59.42 653.62
65 3+504 11.00 31.71 49.35 542.80
66 3+525 21.00 45.72 38.72 813.02
67 3+625 100.00 37.42 41.57 4157.00
68 3+700 75.00 39.07 38.25 2868.38
69 3+725 25.00 37.80 38.44 960.88
70 3+840 115.00 46.46 42.13 4844.95
71 3+860 20.00 28.91 37.69 753.74
72 3+860 0.00 32.63 30.77 0.00
73 3+918 58.00 53.75 43.19 2504.96
74 3+981 63.00 57.96 55.85 3518.80
75 4+030 49.00 60.14 59.05 2893.43
76 4+131 101.00 52.56 56.35 5691.60
77 4+196 65.00 56.34 54.45 3539.22
78 4+301 105.00 54.81 55.57 5835.27
79 4+401 100.00 60.47 57.64 5764.25
80 4+450 49.00 61.18 60.82 2980.40
81 4+450 0.00 63.72 62.45 0.00
82 4+506 56.00 49.74 56.73 3176.94
83 4+576 70.00 90.79 70.27 4918.76
84 4+626 50.00 63.00 76.90 3844.80
85 4+726 100.00 70.14 66.57 6656.70
86 4+752 26.00 64.54 67.34 1750.80
87 4+790 38.00 65.84 65.19 2477.24
88 4+913 123.00 72.61 69.22 8514.43
89 4+913 0.00 63.78 68.19 0.00
90 4+963 50.00 45.49 54.63 2731.73
91 5+005 42.00 78.44 61.97 2602.55
92 5+101 96.00 38.12 58.28 5594.88
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

93 5+200 99.00 42.59 40.35 3994.95


94 5+280 80.00 45.50 44.04 3523.40
95 5+356 76.00 39.63 42.56 3234.90
96 5+379 23.00 47.31 43.47 999.82
97 5+439 60.00 60.78 54.05 3242.79
98 5+479 40.00 70.78 65.78 2631.20
99 5+509 30.00 56.12 63.45 1903.47
100 5+527 18.00 49.17 52.65 947.61
101 5+560 33.00 37.64 43.41 1432.43
102 5+600 40.00 41.57 39.61 1584.26
103 5+625 25.00 34.92 38.25 956.15
104 5+650 25.00 36.25 35.58 889.61
105 5+742 92.00 56.27 46.26 4255.55
106 5+782 40.00 39.15 47.71 1908.38
107 5+837 55.00 41.79 40.47 2225.96
108 5+876 39.00 34.19 37.99 1481.59
109 5+932 56.00 28.20 31.19 1746.86
110 5+947 15.00 31.13 29.66 444.95
111 6+047 100.00 25.55 28.34 2833.75
112 6+147 100.00 21.99 23.77 2376.85
113 6+177 30.00 24.00 22.99 689.84
114 6+213 36.00 23.61 23.80 856.96
115 6+308 95.00 21.60 22.61 2147.52
116 6+396 88.00 29.53 25.57 2249.98
117 6+449 53.00 27.75 28.64 1518.00
118 6+549 100.00 20.61 24.18 2418.10
119 6+579 30.00 20.35 20.48 614.40
120 6+638 59.00 8.15 14.25 840.72
121 6+668 30.00 20.61 14.38 431.39
122 6+732 64.00 41.13 30.87 1975.55
123 6+775 43.00 25.88 33.50 1440.59
124 6+800 25.00 29.11 27.49 687.35
125 6+850 50.00 50.19 39.65 1982.58
126 6+900 50.00 65.06 57.62 2881.23
127 6+925 25.00 83.39 74.23 1855.64
128 6+950 25.00 104.25 93.82 2345.46
129 6+975 25.00 100.92 102.58 2564.60
130 7+027 52.00 96.32 98.62 5128.40
131 7+085 58.00 24.89 60.61 3515.26
132 7+100 15.00 24.18 24.54 368.07
133 7+100 0.00 23.25 23.72 0.00
134 7+113 13.00 11.33 17.29 224.76
136 7+146 0.00 0.00 0.00
Aqueduct
7+158 0.00
137 0.00 0.00
138 7+170 0.00 0.00 0.00
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

139 7+175 0.00 0.00 0.00


140 7+197 0.00 0.00 0.00
141 7+255 0.00 0.00 0.00
142 7+292 0.00 0.00 0.00
143 7+329 37.00 1.56 0.78 28.93
144 7+359 30.00 68.39 34.98 1049.30
145 7+402 43.00 86.04 77.21 3320.18
146 7+500 98.00 117.44 101.74 9970.47
147 7+586 86.00 108.07 112.76 9697.02
148 7+614 28.00 142.75 125.41 3511.54
149 7+648 34.00 56.23 99.49 3382.64
150 7+686 38.00 27.17 41.70 1584.56
151 7+703 17.00 0.00 13.59 230.96
152
Aqueduct
153
154
155 7+721 18.00 0.00 0.00 0.00
156 7+752 31.00 40.56 20.28 628.62
157 7+797 45.00 6.84 23.70 1066.37
158 7+820 23.00 39.18 23.01 529.18
159 7+877 57.00 66.86 53.02 3021.94
160 7+914 37.00 60.60 63.73 2357.99
161 7+960 46.00 70.27 65.44 3010.15
162 8+045 85.00 99.98 85.12 7235.58
163 8+073 28.00 175.54 137.76 3857.27
164
165
Aqueduct
166
167 87.77 0.00
168 8+775 0.00 0.00 0.00
169 8+877 102.00 154.89 77.44 7899.29
170 8+904 27.00 178.03 166.46 4494.33
171 8+953 49.00 401.20 289.61 14191.01
172 8+988 35.00 303.12 352.16 12325.60
173 9+048 60.00 152.46 227.79 13667.37
174 9+078 30.00 159.19 155.82 4674.66
175 9+138 60.00 116.16 137.67 8260.26
176 9+160 22.00 154.68 135.42 2979.22
177 9+165 5.00 151.77 153.22 766.12
178 9+219 54.00 129.58 140.67 7596.26
179 9+299 80.00 165.36 147.47 11797.52
180 9+339 40.00 111.05 138.21 5528.24
181 9+383 44.00 256.55 183.80 8087.20
182 9+413 30.00 234.26 245.40 7362.08
183 9+453 40.00 582.56 408.41 16336.32
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

184 9+503 50.00 547.95 565.25 28262.68


185 9+528 25.00 686.68 617.31 15432.81
186 9+558 30.00 916.92 801.80 24053.94
187 9+583 25.00 987.23 952.08 23801.88
188 9+633 50.00 674.74 830.99 41549.35
189 9+683 50.00 331.60 503.17 25158.53
190 9+733 50.00 321.54 326.57 16328.40
191 9+758 25.00 395.84 358.69 8967.25
192 9+808 50.00 295.39 345.62 17280.93
193 9+883 75.00 288.37 291.88 21890.96
194 9+923 40.00 354.59 321.48 12859.16
195 9+953 30.00 246.94 300.77 9023.04
196 9+983 30.00 176.01 211.48 6344.37
197 10+013 30.00 335.93 255.97 7679.13
10+035
198 106.08
Aqueduct
10+063
199 76.63
200 10+088 25.00 237.76 157.19 3929.78
201 10+098 10.00 517.19 377.47 3774.73
202 10+133 35.00 214.23 365.71 12799.82
203 10+183 50.00 187.69 200.96 10047.80
204 10+233 50.00 448.97 318.33 15916.43
205 10+283 50.00 172.57 310.77 15538.50
206 10+333 50.00 91.66 132.12 6605.78
207 10+353 20.00 112.93 102.29 2045.88
208 10+383 30.00 66.48 89.70 2691.14
209 10+428 45.00 128.76 97.62 4392.92
210 10+445 17.00 31.19 79.97 1359.56
211 10+477 32.00 105.03 68.11 2179.52
212 10+501 24.00 311.88 208.45 5002.91
213 10+533 32.00 731.11 521.50 16687.89
214 10+583 50.00 500.15 615.63 30781.48
215 10+633 50.00 407.14 453.64 22682.08
216 10+643 10.00 383.84 395.49 3954.86
217 10+675 32.00 562.89 473.36 15147.66
218 10+683 8.00 980.88 771.88 6175.08
219 10+708 25.00 1204.25 1092.56 27314.06
220 10+733 25.00 1340.01 1272.13 31803.25
221 10+763 30.00 802.99 1071.50 32144.99
222 10+803 40.00 432.06 617.53 24701.04
223 10+833 30.00 281.46 356.76 10702.86
224 10+858 25.00 190.28 235.87 5896.80
225 10+898 40.00 398.57 294.42 11776.98
226 10+943 45.00 359.06 378.81 17046.59
227 10+983 40.00 330.32 344.69 13787.50
228 11+000 17.00 274.77 302.54 5143.22
229 11+023 23.00 163.10 218.94 5035.55
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

230 11+048 25.00 265.78 214.44 5361.00


231 11+088 40.00 213.49 239.63 9585.34
232 11+133 45.00 228.37 220.93 9941.87
233 11+153 20.00 451.31 339.84 6796.82
234 11+173 20.00 317.22 384.27 7685.31
235 11+199 26.00 791.67 554.44 14415.49
236 11+223 24.00 691.77 741.72 17801.26
237 11+253 30.00 354.29 523.03 15690.89
238 11+273 20.00 215.00 284.64 5692.87
239 11+303 30.00 131.63 173.32 5199.51
240 11+348 45.00 135.63 133.63 6013.37
241 11+388 40.00 0.00 67.81 2712.56

11+475
242 Aqueduct
12+049
243
244 12+050 0.00 60.02 30.01 0.00
245 12+200 150.00 60.02 60.02 9003.30
246 12+300 100.00 60.02 60.02 6002.20
247 12+540 240.00 60.02 60.02 14405.28
248 12+583 43.00 64.97 62.50 2687.33
249 12+640 57.00 29.94 47.45 2704.82
250 12+695 55.00 58.79 44.36 2439.86
251 12+735 40.00 71.46 65.12 2604.96
252 12+760 25.00 57.93 64.70 1617.38
253 12+810 50.00 114.88 86.40 4320.23
254 12+860 50.00 219.69 167.29 8364.25
255 12+900 40.00 111.76 165.72 6628.90
256 12+925 25.00 142.22 126.99 3174.69
257 12+960 35.00 81.78 112.00 3919.90
258 12+990 30.00 121.32 101.55 3046.38
259 13+027 37.00 78.08 99.70 3688.83
260 13+040 13.00 62.55 70.32 914.10
261 13+090 50.00 54.97 58.76 2937.93
262 13+120 30.00 247.66 151.31 4539.42
263 13+160 40.00 263.63 255.64 10225.78
264 13+172 12.00 154.60 209.11 2509.37
265 13+206 34.00 182.14 168.37 5724.67
266 13+234 28.00 341.34 261.74 7328.83
267 13+284 50.00 409.26 375.30 18765.13
268 13+314 30.00 403.17 406.22 12186.53
269 13+364 50.00 391.17 397.17 19858.60
270 13+394 30.00 465.59 428.38 12851.36
271 13+422 28.00 602.90 534.24 14958.75
272 13+437 15.00 507.89 555.39 8330.87
273 13+473 36.00 349.90 428.89 15440.09
274 13+560 87.00 295.83 322.86 28088.91
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

275 13+620 60.00 263.18 279.50 16770.09


276 13+690 70.00 261.81 262.49 18374.48
277 13+720 30.00 203.55 232.68 6980.37
278 13+770 50.00 292.44 248.00 12399.83
279 13+800 30.00 173.94 233.19 6995.73
280 13+830 30.00 169.72 171.83 5154.87
281 13+880 50.00 213.68 191.70 9584.93
282 13+890 10.00 270.05 241.86 2418.63
283 13+920 30.00 308.16 289.11 8673.15
284 13+960 40.00 391.20 349.68 13987.28
285 13+960 0.00 125.20 258.20 0.00
286 13+980 47.25 86.22 0.00
287 14+000 49.82 48.53 0.00
288 14+030 46.60 48.21 0.00
289 14+070 46.13 46.36 0.00
290 14+110 133.43 89.78 0.00
291 14+160 45.23 89.33 0.00
292 14+220 46.29 45.76 0.00
293 14+260 41.81 44.05 0.00
294 14+310 117.02 79.42 0.00
295 14+363 117.02 117.02 0.00
296 14+368 44.48 80.75 0.00
297 14+385 45.69 45.09 0.00
298 14+455 43.77 44.73 0.00
299 14+490 45.71 44.74 0.00
300 14+540 45.76 45.73 0.00
301 14+600 44.73 45.24 0.00
302 14+621 44.33 44.53 0.00
303 14+642 44.78 44.55 0.00
304 14+750 44.08 44.43 0.00
305 14+775 45.50 44.79 0.00
306 14+825 40.03 42.77 0.00
307 14+875 44.55 42.29 0.00
308 14+975 44.41 44.48 0.00
309 15+075 44.67 44.54 0.00
310 15+119 44.34 44.50 0.00
311 15+149 62.95 53.65 0.00
312 15+182 63.01 62.98 0.00
313 15+200 44.11 53.56 0.00
314 15+300 42.88 43.50 0.00
315 15+341 42.34 42.61 0.00
Syphon
316 15+351 42.47 42.41 0.00
317 15+379 48.55 45.51 0.00
318 15+400 41.93 45.24 0.00
319 15+500 43.76 42.85 0.00
320 15+600 44.38 44.07 0.00
321 15+700 44.08 44.23 0.00
322 15+820 44.27 44.17 0.00
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

323 15+920 44.71 44.49 0.00


324 16+020 44.12 44.42 0.00
325 16+120 44.38 44.25 0.00
326 16+220 44.14 44.26 0.00
327 16+320 44.04 44.09 0.00
328 16+420 44.66 44.35 0.00
329 16+520 44.22 44.44 0.00
330 16+620 44.27 44.25 0.00
331 16+720 45.61 44.94 0.00
332 16+820 44.22 44.92 0.00
333 16+853 42.08 43.15 0.00
334 16+936 44.30 43.19 0.00
335 16+948 66.30 55.30 0.00
336 16+966 45.08 55.69 0.00
337 17+003 50.30 47.69 0.00
338 17+033 44.14 47.22 0.00
339 17+043 104.13 74.14 0.00
340 17+063 42.85 73.49 0.00
341 17+163 44.44 43.64 0.00
342 17+210 51.53 47.98 0.00
343 17+268 48.06 49.80 0.00
344 17+325 48.48 48.27 0.00
345 17+350 42.92 45.70 0.00
346 17+375 25.00 43.97 43.44 1086.06
347 17+425 50.00 309.26 176.61 8830.65
348 17+450 25.00 271.13 290.20 7254.88
349 17+500 50.00 245.57 258.35 12917.50
350 17+530 30.00 393.43 319.50 9584.96
351 17+550 20.00 320.96 357.19 7143.87
352 17+600 50.00 117.69 219.33 10966.25
353 17+650 50.00 137.44 127.57 6378.25
354 17+700 50.00 188.95 163.20 8159.75
355 17+750 50.00 260.29 224.62 11230.95
356 17+784 34.00 151.37 205.83 6998.20
357 17+870 86.00 170.89 161.13 13857.22
358 17+938 68.00 232.45 201.67 13713.56
359 18+000 62.00 124.99 178.72 11080.76
360 18+050 50.00 219.42 172.21 8610.25
361 18+100 50.00 272.11 245.76 12288.13
362 18+150 50.00 166.74 219.42 10971.23
363 18+200 50.00 107.81 137.27 6863.65
364 18+250 50.00 293.07 200.44 10021.90
365 18+300 50.00 286.63 289.85 14492.43
366 18+350 50.00 365.50 326.07 16303.25
367 18+390 40.00 288.88 327.19 13087.62
368 18+412 22.00 217.41 253.14 5569.11
369 18+450 38.00 162.47 189.94 7217.55
370 18+500 50.00 223.21 192.84 9641.78
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

371 18+550 50.00 218.23 220.72 11035.90


372 18+600 50.00 132.27 175.25 8762.60
373 18+657 57.00 236.51 184.39 10510.40
374 18+702 45.00 168.61 202.56 9115.34
375 18+733 31.00 100.77 134.69 4175.44
376 18+757 24.00 124.05 112.41 2697.84
377 18+800 43.00 189.98 157.02 6751.65
378 18+838 38.00 210.25 200.11 7604.28
379 18+902 64.00 60.21 135.23 8654.59
380 18+925 23.00 135.26 97.74 2247.91
381 18+950 25.00 197.37 166.31 4157.84
382 18+976 26.00 241.59 219.48 5706.43
383 19+064 88.00 268.38 254.98 22438.55
384 19+114 50.00 103.67 186.02 9301.10
385 19+141 27.00 53.93 78.80 2127.53
386 19+166 25.00 117.22 85.58 2139.40
387 19+189 23.00 103.58 110.40 2539.23
388 19+217 28.00 54.85 79.22 2218.03
389 19+237 20.00 151.98 103.42 2068.30
390 19+274 37.00 125.44 138.71 5132.27
391 19+284 10.00 336.09 230.77 2307.65
392 19+306 22.00 543.64 439.87 9677.03
393 19+320 14.00 394.37 469.01 6566.07
394 19+338 18.00 284.45 339.41 6109.34
395 19+350 12.00 118.58 201.51 2418.13
396 19+400 50.00 124.18 121.38 6068.90
397 19+460 60.00 162.50 143.34 8600.40
398 19+510 50.00 382.61 272.56 13627.75
399 19+550 40.00 206.86 294.74 11789.40
400 19+600 50.00 230.09 218.47 10923.65
401 19+650 50.00 256.48 243.28 12164.15
402 19+700 50.00 162.64 209.56 10478.10
403 19+750 50.00 213.28 187.96 9398.18
404 19+850 100.00 164.35 188.82 18881.50
405 19+900 50.00 149.37 156.86 7842.83
406 19+950 50.00 109.31 129.34 6466.98
407 20+000 50.00 118.26 113.79 5689.33
408 20+025 25.00 81.76 100.01 2500.25
409 20+100 75.00 142.03 111.90 8392.13
410 20+150 50.00 102.11 122.07 6103.50
411 20+200 50.00 239.43 170.77 8538.40
412 20+250 50.00 269.66 254.54 12727.15
413 20+300 50.00 336.65 303.16 15157.75
414 20+350 50.00 167.50 252.08 12603.75
415 20+400 50.00 160.28 163.89 8194.48
416 20+500 100.00 146.86 153.57 15356.95
417 20+600 100.00 518.74 332.80 33280.00
418 20+700 100.00 307.97 413.36 41335.50
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

419 20+750 50.00 277.36 292.67 14633.25


420 20+825 75.00 145.51 211.44 15857.63
421 20+900 75.00 97.78 121.65 9123.38
422 20+935 35.00 80.41 89.09 3118.29
423 21+000 65.00 78.10 79.25 5151.51
424 21+075 75.00 55.53 66.82 5011.13
425 21+175 100.00 98.34 76.94 7693.50
426 21+225 50.00 140.04 119.19 5959.50
427 21+250 25.00 163.74 151.89 3797.25
428 21+300 50.00 128.31 146.03 7301.25
429 21+350 50.00 136.21 132.26 6613.00
430 21+400 50.00 107.72 121.97 6098.25
431 21+450 50.00 154.89 131.31 6565.25
432 21+500 50.00 236.39 195.64 9782.00
433 21+550 50.00 155.98 196.19 9809.25
434 21+600 50.00 216.18 186.08 9304.00
435 21+700 100.00 147.21 181.70 18169.50
436 21+750 50.00 81.51 114.36 5718.00
437 21+850 100.00 137.58 109.55 10954.50
438 21+950 100.00 286.19 211.89 21188.50
439 22+000 50.00 200.24 243.22 12160.75
440 22+050 50.00 422.56 311.40 15570.00
441 22+100 50.00 253.22 337.89 16894.50
442 22+150 50.00 252.17 252.70 12634.75
443 22+175 23.90 420.92 336.55 8043.43
444 22+200 25.44 442.26 431.59 10979.65
445 22+225 29.94 365.67 403.97 12094.71
446 22+250 27.35 288.94 327.31 8951.79
447 22+300 50.00 110.81 199.88 9993.75
448 22+350 44.41 185.78 148.30 6585.87
449 22+425 68.94 399.07 292.43 20159.78
450 22+450 28.76 452.67 425.87 12247.96
451 22+500 49.96 189.10 320.89 16031.41
452 22+575 73.68 123.19 156.15 11504.76
453 22+600 23.76 132.93 128.06 3042.71
454 22+700 100.22 45.68 89.31 8950.15
455 22+715 15.96 52.26 48.97 781.59
456 22+742 26.81 0.00 26.13 700.60
457 22+750 8.25 42.65 21.33 175.93
458 22+775 20.98 100.64 71.65 1503.11
459 22+800 25.63 131.86 116.25 2979.49
460 22+875 32.19 176.83 154.35 4968.40
461 22+925 50.08 198.83 187.83 9406.58
462 22+975 49.50 107.22 153.03 7574.74
463 23+000 40.01 229.43 168.33 6734.68
464 23+050 56.05 150.26 189.85 10640.87
465 23+075 22.75 215.26 182.76 4157.81
466 23+125 43.58 150.14 182.70 7962.07
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

467 23+175 48.28 79.08 114.61 5533.47


468 23+200 36.75 254.25 166.67 6125.01
469 23+250 50.64 163.62 208.94 10580.47
470 23+300 52.62 175.70 169.66 8927.54
471 23+350 46.51 215.45 195.58 9096.22
472 23+450 97.75 166.74 191.10 18679.54
473 23+500 51.77 100.36 133.55 6913.88
474 23+525 26.14 138.85 119.61 3126.47
475 23+575 52.79 130.26 134.56 7103.16
476 23+625 50.12 136.44 133.35 6683.50
477 23+675 45.00 157.14 146.79 6605.55
478 23+725 48.72 240.58 198.86 9688.46
479 23+750 23.84 312.48 276.53 6592.48
480 23+825 76.24 127.51 220.00 16772.42
481 23+875 55.27 25.92 76.72 4240.04
482 23+900 31.50 26.10 26.01 819.32
483 24+000 87.36 147.53 86.82 7584.16
484 24+050 49.30 114.93 131.23 6469.64
485 24+100 45.50 94.99 104.96 4775.68
486 24+125 25.21 103.18 99.09 2497.93
487 24+150 25.57 107.67 105.43 2695.72
488 24+200 52.96 100.77 104.22 5519.49
489 24+250 53.35 96.68 98.73 5266.98
490 24+300 43.91 78.54 87.61 3846.96
491 24+350 58.88 69.38 73.96 4354.76
492 24+400 54.18 118.15 93.76 5080.11
493 24+425 23.03 150.85 134.50 3097.50
494 24+450 24.29 81.80 116.33 2825.53
495 24+500 28.53 58.46 70.13 2000.81
496 24+525 25.00 185.91 122.18 3054.60
497 24+575 46.70 142.98 164.44 7679.53
498 24+625 50.09 142.14 142.56 7140.83
499 24+650 31 131.42 136.78 4256.59
500 24+675 20 168.40 149.91 3001.22
501 24+700 23 132.69 150.55 3504.71
502 24+750 50 91.35 112.02 5612.20
503 24+800 47 176.39 133.87 6325.29
504 24+825 25 198.55 187.47 4641.72
505 24+850 25 170.92 184.74 4574.04
506 24+900 25 143.13 157.03 3887.94
507 24+950 25 187.84 165.49 4097.41
508 25+000 25 111.00 149.42 3699.64
509 25+050 52 171.93 141.47 7401.45
510 25+070 18 85.59 128.76 2267.46
511 25+100 33 165.25 125.42 4106.25
512 25+150 49 110.54 137.90 6697.56
513 25+180 30 100.78 105.66 3183.54
514 25+200 18 204.76 152.77 2795.73
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

515 25+225 20 361.28 283.02 5646.29


516 25+250 25 511.65 436.47 10850.52
517 25+275 25 405.21 458.43 11249.87
518 25+300 23 329.00 367.11 8344.30
519 25+350 49 143.25 236.13 11605.54
520 25+375 25 128.43 135.84 3367.47
521 25+400 25 91.98 110.21 2724.27
522 25+425 28 116.97 104.48 2909.63
523 25+450 23 114.44 115.71 2679.73
524 25+475 25 93.55 104.00 2642.54
525 25+500 25 96.44 95.00 2410.05
526 25+525 25 180.74 138.59 3399.61
527 25+550 24 307.65 244.20 5941.26
528 25+575 24 596.34 452.00 10766.56
529 25+600 25 752.94 674.64 16913.26
530 25+625 26 656.84 704.89 18179.11
531 25+650 25 543.68 600.26 15126.55
532 25+675 24 377.43 460.56 11099.38
533 25+700 24 196.52 286.98 6838.61
534 25+750 50 160.77 178.65 8967.98
535 25+765 27 131.71 146.24 4009.90
536 25+775 14 230.73 181.22 2573.35
537 25+800 22 135.49 183.11 4065.09
538 25+825 32 131.48 133.49 4320.91
539 25+875 54 341.61 236.55 12849.12
540 25+905 29 458.16 399.89 11524.69
541 25+950 42 379.05 418.61 17577.22
542 26+000 47 214.98 297.02 13983.47
543 26+050 50 147.21 181.10 8966.01
544 26+100 47 128.13 137.67 6520.05
545 26+150 45 286.97 207.55 9375.03
546 26+175 24 423.73 355.35 8471.54
547 26+200 24 369.46 396.60 9553.97
548 26+225 24 390.98 380.22 9083.46
549 26+250 27 286.09 338.54 9032.11
550 26+300 49 188.68 237.39 11655.60
551 26+350 51 140.69 164.69 8412.11
552 26+375 32 245.66 193.18 6193.19
553 26+400 26 175.23 210.45 5418.96
554 26+425 25 178.95 177.09 4406.00
555 26+440 16 122.15 150.55 2381.70
556 26+450 9 238.49 180.32 1559.77
557 26+475 24 133.25 185.87 4451.59
558 26+490 15 99.80 116.53 1746.71
559 26+500 11 134.10 116.95 1227.98
560 26+550 35 143.26 138.68 4787.23
561 26+600 50 228.00 185.63 9188.69
562 26+625 26 367.62 297.81 7632.87
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

563 26+650 26 239.15 303.39 7748.45


564 26+675 26 120.41 179.78 4742.60
565 26+700 25 124.53 122.47 3096.04
566 26+750 52 172.80 148.67 7751.39
567 26+800 49 191.19 182.00 8883.18
568 26+835 39 89.42 140.31 5424.19
569 26+850 11 158.61 124.02 1334.40
570 26+900 51 190.14 174.38 8968.11
571 26+930 31 269.20 229.67 7041.68
572 26+950 14 154.49 211.85 3044.21
573 26+970 20 242.48 198.49 3933.97
574 27+000 30 208.68 225.58 6749.35
575 27+075 68 209.32 209.00 14209.91
576 27+100 25 178.75 194.04 4862.52
577 27+125 32 142.62 160.69 5180.48
578 27+175 47 208.59 175.61 8330.70
579 27+200 26 204.30 206.45 5346.93
580 27+250 51 195.92 200.11 10277.65
581 27+300 51 65.51 130.72 6706.99
582 27+321 22 0.00 32.76 711.11

Aqueduct
583
584 27+430 0 0.00 0.00 0.00
585 27+445 15 58.90 29.45 427.03
586 27+465 18 94.61 76.76 1416.90
587 27+500 64 116.64 105.63 6710.36
588 27+550 48 174.50 145.57 6932.04
589 27+580 28 93.83 134.17 3752.60
590 27+600 20 138.62 116.23 2267.55
591 27+625 24 141.41 140.01 3374.33
592 27+650 24 224.66 183.03 4347.05
593 27+675 23 239.47 232.07 5288.76
594 27+750 55 47.84 143.66 7946.99
595 27+780 31 59.70 53.77 1679.77
596 27+805 26 94.24 76.97 2018.92
597 27+825 26 108.07 101.16 2584.51
598 27+850 22 105.95 107.01 2376.69
599 27+880 33 58.85 82.40 2711.78
600 27+925 52 61.52 60.19 3107.95
601 27+975 50 85.72 73.62 3706.77
602 28+000 25 139.28 112.50 2862.00
603 28+025 25 121.67 130.48 3261.88
604 28+050 25 164.71 143.19 3579.75
605 28+075 25 178.71 171.71 4292.75
606 28+115 40 186.67 182.69 7307.60
607 28+140 25 128.89 157.78 3944.50
608 28+155 15 71.58 100.24 1503.53
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

609 28+175 20 206.64 139.11 2782.20


610 28+195 20 189.18 197.91 3958.20
611 28+230 35 160.58 174.88 6120.80
612 28+250 20 111.68 136.13 2722.60
613 28+275 25 87.08 99.38 2484.50
614 28+300 25 96.00 91.54 2288.50
615 28+325 25 101.31 98.66 2466.38
616 28+400 75 119.07 110.19 8264.25
617 28+425 25 212.83 165.95 4148.75
618 28+450 25 273.84 243.34 6083.38
619 28+475 25 423.12 348.48 8712.00
620 28+486 11 204.31 313.72 3450.87
621 28+500 14 191.84 198.08 2773.05
622 28+550 50 216.06 203.95 10197.50
623 28+600 50 111.88 163.97 8198.50
624 28+625 25 101.17 106.53 2663.13
625 28+650 25 177.95 139.56 3489.00
626 28+675 25 325.35 251.65 6291.25
627 28+725 50 553.12 439.24 21961.75
628 28+750 25 573.45 563.29 14082.13
629 28+825 75 620.97 597.21 44892.28
630 28+875 54 353.70 487.34 26223.50
631 28+925 50 221.25 287.48 14388.12
632 28+975 42 152.84 187.05 7766.11
633 29+000 30 98.01 125.43 3701.29
634 29+050 49 96.37 97.19 4806.05
635 29+100 50 93.13 94.75 4763.08
636 29+150 50 81.76 87.45 4329.40
637 29+200 29 70.75 76.26 2199.19
638 29+250 48 91.11 80.93 3884.64
639 29+300 45 90.86 90.99 4094.33
640 29+325 31 365.61 228.24 7066.16
641 29+350 30 153.20 259.41 7901.48
642 29+400 54 86.89 120.05 6516.04
643 29+415 15 129.32 108.11 1621.58
644 29+450 36 107.97 118.65 4296.14
645 29+500 50 230.09 169.03 8380.51
646 29+550 48 123.06 176.58 8530.34
647 29+600 53 129.13 126.10 6700.69
648 29+625 27 189.50 159.32 4269.64
649 29+650 45 274.91 232.21 10525.85
650 29+700 49 173.61 224.26 10988.74
651 29+750 53 228.52 201.07 10559.93
652 29+782 30 31.21 129.87 3849.20
653 29+800 25 99.70 65.46 1614.77
654 29+850 48 141.59 120.65 5778.90
655 29+885 35 143.89 142.74 5014.46
656 29+925 38 131.23 137.56 5276.80
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

657 29+950 27 113.17 122.20 3358.06


658 30+000 51 137.68 125.43 6404.20
659 30+050 49 125.95 131.82 6431.25
660 30+100 48 174.44 150.20 7227.38
661 30+150 56 172.53 173.49 9755.06
662 30+200 50 138.06 155.30 7764.75
663 30+250 52 125.02 131.54 6780.89
664 30+300 50 116.44 120.73 6050.99
665 30+350 55 187.63 152.04 8339.12
666 30+400 48 164.70 176.17 8484.11
667 30+500 84 93.23 128.97 10817.58
668 30+525 25 73.99 83.61 2117.01
669 30+550 28 96.11 85.05 2374.60
670 30+575 24 208.24 152.18 3623.29
671 30+600 24 159.60 183.92 4439.83
672 30+650 53 125.06 142.33 7560.57
673 30+675 25 114.10 119.58 2946.45
674 30+700 36 151.23 132.67 4718.89
675 30+725 32 65.20 108.22 3427.17
676 30+750 26 73.78 69.49 1805.35
677 30+775 25 121.56 97.67 2482.77
678 30+825 49 151.45 136.51 6677.82
679 30+850 25 212.89 182.17 4485.03
680 30+900 50 116.05 164.47 8269.55
681 30+950 49 105.99 111.02 5439.98
682 31+000 50 283.42 194.71 9702.15
683 31+050 49 137.21 210.32 10332.78
684 31+080 30 126.02 131.62 3922.13
685 31+100 20 205.23 165.63 3239.63
686 31+150 50 149.67 177.45 8824.59
687 31+175 24 144.29 146.98 3580.43
688 31+200 25 166.24 155.27 3939.07
689 31+250 50 275.45 220.85 10931.83
690 31+300 51 215.42 245.44 12443.55
691 31+325 25 102.54 158.98 4022.19
692 31+375 49 84.93 93.74 4636.13
693 31+425 53 184.76 134.85 7146.79
694 31+450 26 191.73 188.25 4856.72
695 31+475 25 68.89 130.31 3295.54
696 31+500 25 140.79 104.84 2617.85
697 31+525 23 143.83 142.31 3266.01
698 31+545 0.00 71.92 0.00
137.11 0.00
699 31+560 Trugh 68.56
310.01 0.00
700 31+700 223.56
701 31+750 48 173.35 241.68 11482.22
702 31+800 55 214.15 193.75 10749.25
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

703 31+825 18 173.39 193.77 3505.30


704 31+850 26 148.17 160.78 4124.01
705 31+875 25 161.98 155.08 3875.32
706 31+900 24 4.62 83.30 2016.69
707 31+925 24 135.32 69.97 1711.47
708 31+950 24 191.37 163.35 3843.51
709 31+975 28 54.70 123.04 3454.82
710 32+000 25 80.36 67.53 1695.00
711 32+025 34 112.37 96.37 3309.17
712 32+050 53 131.99 122.18 6453.55
713 32+100 29 204.23 168.11 4791.14
714 32+125 18 178.51 191.37 3442.75
715 32+175 55 184.62 181.57 9978.81
716 32+200 25 161.59 173.11 4362.25
717 32+225 25 157.48 159.54 4033.04
718 32+250 22 201.24 179.36 4028.43
719 32+275 24 271.73 236.49 5616.52
720 32+300 25 183.08 227.41 5730.61
721 32+325 25 251.35 217.22 5504.23
722 32+350 25 214.07 232.71 5701.40
723 32+375 25 231.52 222.80 5540.91
724 32+400 24 171.07 201.30 4859.26
725 32+425 25 180.76 175.92 4404.91
726 32+450 25 169.08 174.92 4350.26
727 32+475 25 147.66 158.37 3900.65
728 32+500 25 43.14 95.40 2357.33

Aqueduct
729 32+525
730 32+575 50 91.99 46.00 2299.75
731 32+625 50 83.63 87.81 4390.50
732 32+640 15 109.57 96.60 1449.00
733 32+665 25 143.46 126.52 3162.88
734 32+690 25 127.76 135.61 3390.25
735 32+715 25 297.23 212.50 5312.38
736 32+750 35 175.59 236.41 8274.35
737 32+780 30 182.61 179.10 5373.00
738 32+800 20 258.95 220.78 4415.60
739 32+825 25 174.71 216.83 5420.75
740 32+875 25 224.51 199.61 4890.45
741 32+900 50 229.84 227.18 11431.45
742 32+925 25 467.24 348.54 8863.37
743 32+950 25 256.69 361.97 8915.20
744 32+980 25 382.51 319.60 7874.94
745 32+995 15 151.84 267.18 0.00
0.00 0.00
746 33+004 75.92
Aqueduct
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

Aqueduct
0.00 0.00
747 33+260 0.00
748 33+265 5 55.16 27.58 142.59
749 33+280 15 50.01 52.59 788.78
750 33+300 20 70.88 60.45 1208.90
751 33+375 150 129.72 100.30 15045.00
752 33+425 50 90.80 110.26 5517.41
753 33+475 50 89.33 90.07 4473.53
754 33+525 50 167.12 128.23 6407.40
755 33+575 50 168.73 167.93 8419.76
756 33+625 51 268.25 218.49 11075.26
757 33+650 26 42.87 155.56 4094.34
758 33+675 24 21.44 518.08
759 33+725 50 183.61 91.81 4590.25
760 33+775 58 183.53 183.57 10705.80
761 33+825 50 168.26 175.90 8754.29
762 33+875 49 223.78 196.02 9685.35
763 33+925 50 450.30 337.04 16872.22
764 34+000 77 556.44 503.37 38598.41
765 34+015 14 281.87 419.16 6006.49
766 34+050 36 125.80 203.84 7380.87
767 34+100 48 149.18 137.49 6606.39
768 34+150 50 155.98 152.58 7644.26
769 34+200 51 199.51 177.75 8997.45
770 34+250 51 211.96 205.74 10397.85
771 34+260 13 116.62 164.29 2135.77
772 34+275 12 220.47 168.55 2105.13
773 34+300 24 202.92 211.70 5148.42
774 34+325 25 173.39 188.16 4762.20
775 34+350 25 189.34 181.37 4474.27
776 34+375 24 132.53 160.94 3867.27
777 34+450 75 76.79 104.66 7865.20
778 34+475 25 60.51 68.65 1724.49
779 34+490 16 57.17 58.84 912.61
780 34+550 60 81.96 69.57 4194.77
781 34+625 75 125.22 103.59 7766.14
782 34+675 64 139.49 132.36 8532.93
783 34+725 56 216.35 177.92 9975.97
784 34+775 48 101.58 158.97 7631.91
785 34+825 50 203.19 152.39 7593.34
786 34+875 50 176.24 189.72 9491.44
787 34+925 49 160.42 168.33 8211.14
788 34+975 52 61.74 111.08 5732.84
789 35+025 51 98.74 80.24 4098.66
790 35+075 49 141.87 120.31 5887.73
791 35+125 50 246.61 194.24 9776.10
792 35+175 53 89.78 168.20 8947.97
793 35+200 25 146.37 118.08 2921.18
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

794 35+225 23 202.78 174.58 4093.78


795 35+250 25 216.31 209.55 5255.39
796 35+275 25 137.61 176.96 4471.78
797 35+325 49 112.91 125.26 6130.22
798 35+375 50 121.37 117.14 5855.83
799 35+425 48 206.18 163.78 7939.81
800 35+450 29 182.40 194.29 5700.47
801 35+500 49 66.12 124.26 6087.50
802 35+525 24 53.26 59.69 1452.26
803 35+550 25 48.39 50.83 1247.75
804 35+575 24 49.24 48.82 1155.94
805 35+600 25 61.67 55.46 1410.78
806 35+650 50 154.30 107.99 5379.81
807 35+675 23 165.44 159.87 3724.97
808 35+735 60 192.00 178.72 10701.75
809 35+740 2 15.18 103.59 207.18
810 35+825 82 19.59 17.39 1433.22
811 35+850 25 18.41 19.00 468.73
812 35+935 56 24.08 21.25 1189.93
813 35+950 15 0.00 12.04 180.48
814 35+965 16 96.98 48.49 754.02
815 35+990 25 115.13 106.06 2651.38
816 36+040 50 115.02 115.08 5728.43
817 36+080 40 157.66 136.34 5414.06
818 36+100 23 53.05 105.36 2465.31
819 36+120 20 134.65 93.85 1872.31
820 36+150 30 184.91 159.78 4771.03
821 36+185 35 210.73 197.82 6838.64
822 36+220 33 95.83 153.28 5030.65
823 36+245 23 63.35 79.59 1865.59
824 36+260 14 98.43 80.89 1164.74
825 36+290 28 254.61 176.52 4995.52
826 36+305 14 372.87 313.74 4285.69
827 36+325 19 278.01 325.44 6199.63
828 36+350 34 93.08 185.55 6228.75
829 36+400 65 99.47 96.28 6238.62
830 36+425 25 93.18 96.33 2434.13
831 36+450 39 64.34 78.76 3074.00
832 36+500 48 91.36 77.85 3748.48
833 36+550 48 137.45 114.41 5438.81
834 36+600 50 81.54 109.50 5459.42
835 36+650 52 126.28 103.91 5431.38
836 36+700 50 97.37 111.83 5605.79
837 36+750 48 269.55 183.46 8872.13
838 36+800 48 407.06 338.31 16343.51
839 36+850 51 426.35 416.71 21343.63
840 36+860 10 381.82 404.09 4214.61
841 36+900 45 326.58 354.20 15970.88
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

842 36+910 10 177.57 252.08 2568.64


843 36+950 40 161.60 169.59 6729.13
844 37+000 50 98.89 130.25 6471.87
845 37+065 63 62.96 80.93 5123.36
846 37+090 24 334.79 198.88 4860.51
847 37+150 58 119.67 227.23 13172.52
848 37+250 101 89.90 104.79 10549.75
849 37+300 50 87.39 88.65 4452.64
850 37+350 51 225.64 156.52 7979.13
851 37+400 50 299.25 262.45 13040.89
852 37+425 24 262.81 281.03 6840.27
853 37+475 49 89.54 176.18 8717.14
854 37+525 50 92.59 91.07 4529.57
855 37+550 25 139.22 115.91 2920.81
856 37+600 50 116.58 127.90 6343.84
857 37+650 48 181.80 149.19 7208.86
858 37+675 25 216.84 199.32 4998.95
859 37+700 25 89.68 153.26 3779.39
860 37+750 50 108.94 99.31 4959.54
861 37+775 26 139.14 124.04 3233.72
862 37+800 26 154.64 146.89 3750.10
863 37+825 25 185.05 169.85 4212.16
864 37+860 34 142.32 163.69 5601.30
865 37+875 15 160.10 151.21 2331.66
866 37+925 51 143.96 152.03 7811.30
867 37+975 49 96.47 120.22 5947.04
868 38+000 49 134.42 115.45 5616.40
869 38+050 49 148.65 141.54 6997.49
870 38+110 60 167.57 158.11 9526.13
871 38+130 20 193.20 180.39 3681.66
872 38+150 20 227.72 210.46 4232.35
873 38+175 25 190.25 208.99 5314.49
874 38+200 25 221.92 206.09 5232.50
875 38+250 54 203.78 212.85 11493.90
876 38+275 25 196.75 200.27 5006.63
877 38+300 25 234.24 215.50 5443.40
878 38+350 50 275.58 254.91 12773.54
879 38+375 26 342.15 308.87 7931.65
880 38+400 25 302.87 322.51 8130.48
881 38+425 24 198.15 250.51 6064.85
882 38+450 26 86.08 142.12 3648.09
883 38+475 24 167.90 126.99 3097.29
884 38+500 25 199.70 183.80 4637.27
885 38+550 48 141.29 170.50 8105.33
886 38+575 23 120.28 130.79 3049.91
887 38+625 49 500.14 310.21 15076.21
888 38+650 31 807.33 653.74 20507.67
889 38+700 50 1104.99 956.16 47339.48
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

890 38+740 39 1431.53 1268.26 49842.62


891 38+800 58 174.78 803.16 46631.18
892 38+825 25 122.31 148.55 3669.06
893 38+850 25 214.04 168.18 4241.37
894 38+875 25 211.15 212.60 5314.88
895 38+899 24.25 0.00 105.58 2560.19

Aqueduct
896 38+958
897 38+966 7.87 108.09 54.05 425.33
898 38+980 12 337.78 222.94 2612.80
899 39+000 21 476.95 407.37 8599.48
900 39+025 24 381.39 429.17 10252.87
901 39+050 25 406.71 394.05 10032.51
902 39+090 41 138.14 272.43 11275.67
903 39+110 20 30.65 84.40 1668.49
904 39+120 9 25.70 28.18 248.79
905 39+145 24 258.36 142.03 3447.49
906 39+180 39 326.97 292.67 11523.10
907 39+200 20 300.65 313.81 6178.92
908 39+225 25 230.75 265.70 6562.79
909 39+250 25 165.30 198.03 4978.35
910 39+300 50 106.62 135.96 6762.65
911 39+350 52 131.73 119.18 6218.55
912 39+425 75 163.44 147.59 11057.07
913 39+475 52 129.32 146.38 7545.89
914 39+525 52 208.99 169.16 8714.87
915 39+575 48 124.20 166.60 7933.25
916 39+625 50 80.98 102.59 5129.50
917 39+650 25 67.00 73.99 1849.75
918 39+675 25 73.79 70.40 1759.88
919 39+700 25 89.15 81.47 2036.75
920 39+730 30 77.10 83.13 2493.75
921 39+755 25 87.91 82.51 2062.63
922 39+780 25 117.41 102.66 2566.50
923 39+805 25 239.83 178.62 4465.50
924 39+830 25 119.19 179.51 4487.75
925 39+875 45 150.28 134.74 6063.08
926 39+900 25 205.64 177.96 4449.00
927 39+925 24 330.86 268.25 6545.30
928 39+950 25 296.52 313.69 7986.55
929 39+975 25 133.75 215.14 5449.37
930 40+000 25 177.68 155.72 3846.21
931 40+050 47 293.50 235.59 11103.45
932 40+100 49 271.30 282.40 13905.38
933 40+185 84 234.84 253.07 21179.43
934 40+235 49 315.82 275.33 13514.57
935 40+260 26 294.79 305.31 7837.18
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

936 40+310 50 412.03 353.41 17737.65


937 40+360 49 213.87 312.95 15484.77
938 40+410 51 190.89 202.38 10291.63
939 40+440 30 240.87 215.88 6577.86
940 40+475 34 252.51 246.69 8473.80
941 40+500 24 183.90 218.21 5315.47
942 40+550 52 210.61 197.26 10336.16
943 40+600 50 256.67 233.64 11665.52
944 40+650 45 508.48 382.57 17032.13
945 40+700 47 359.12 433.80 20549.11
946 40+750 48 367.04 363.08 17387.90
947 40+800 47 165.87 266.45 12627.18
948 40+850 51 295.64 230.75 11849.04
949 40+900 57 267.02 281.33 16077.90
950 40+925 25 132.57 199.79 4972.87
951 40+950 20 73.42 102.99 2095.88
952 40+975 32 252.86 163.14 5248.17
953 41+000 23 363.07 307.96 7110.88
954 41+025 25 630.70 496.88 12367.41
955 41+075 46 397.75 514.23 23813.76
956 41+110 38 148.72 273.24 10361.07
957 41+135 24 213.50 181.11 4341.21
958 41+185 42 224.52 219.01 9301.35
959 41+220 33 202.09 213.31 7068.93
960 41+265 43 284.52 243.30 10576.38
961 41+275 11 208.11 246.31 2810.41

Aqueduct 1560.80
962 41+289 104.05
963 41+394 105 0.00 0.00 0.00
964 41+400 3 222.82 111.41 0.00
965 41+425 24 533.70 378.26 8934.51
966 41+510 85 254.10 393.90 33418.48
967 41+550 40 142.97 198.54 8006.92
968 41+575 24 288.90 215.94 5167.32
969 41+625 50 507.57 398.24 19919.71
970 41+675 47 371.13 439.35 20614.30
971 41+725 51 259.53 315.33 15949.39
972 41+777 52 212.85 236.19 12229.92
973 41+800 22 351.41 282.13 6342.28
974 41+850 49 218.98 285.20 13911.81
975 41+900 51 106.77 162.88 8353.86
976 41+950 50 190.43 148.60 7455.26
977 41+975 24 175.26 182.85 4459.59
978 41+995 19 167.31 171.29 3184.19
979 42+075 79 209.78 188.55 14972.36
980 42+125 49 207.61 208.70 10305.36
981 42+175 50 285.55 246.58 12333.93
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

982 42+205 31 86.03 185.79 5830.04


983 42+216 11 43.01 471.00
984 42+252 36 0.00 0.00
985 42+274 21 104.16 52.08 0.00
986 42+300 26 226.77 165.47 4274.01
987 42+350 50 228.54 227.65 11309.85
988 42+400 49 139.05 183.80 9035.39
989 42+425 26 148.41 143.73 3698.22
990 42+475 49 127.74 138.08 6814.00
991 42+550 72 175.37 151.55 10855.74
992 42+575 25 187.10 181.23 4550.79
993 42+610 32 70.17 128.63 4093.15
994 42+635 27 202.48 136.33 3694.41
995 42+665 34 251.67 227.08 7784.13
996 42+715 51 225.85 238.76 12088.34
997 42+775 59 149.12 187.49 11084.23
998 42+825 50 118.18 133.65 6702.62
999 42+850 25 163.60 140.89 3571.49
1000 42+875 25 136.72 150.16 3761.45
1001 42+900 25 113.84 125.28 0.00
1002 42+950 50 141.02 127.43 0.00
1003 43+000 51 208.61 174.82 8905.18
1004 43+050 49 259.67 234.14 11470.59
1005 43+100 50 560.54 410.11 20480.82
1006 43+150 51 440.74 500.64 25773.05
1007 43+200 49 201.79 321.26 15693.75
1008 43+215 15 75.87 138.83 2087.96
1009 43+230 0.00 0.00

Aqueduct
1010 43+825
1011 43+883 57.92 25.14 12.57 728.05
1012 43+900 18.48 88.76 56.95 1052.43
1013 44+000 87 216.18 152.47 13278.57
1014 44+050 50 180.50 198.34 9974.54
1015 44+100 50 165.50 173.00 8563.48
1016 44+150 51 175.43 170.47 8611.92
1017 44+200 50 70.14 122.79 6080.36
1018 44+250 48 147.18 108.66 5261.34
1019 44+270 20 228.29 187.74 3707.77
1020 44+283 13 0.00 114.14 1497.57

Aqueduct 0.00
1021 44+367 0.00
1022 44+380 13 305.89 152.94 2038.75
1023 44+400 14 251.78 278.83 4040.29
1024 44+450 50 190.52 221.15 11108.31
1025 44+500 49 258.21 224.36 11103.75
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

1026 44+550 49 317.26 287.73 13980.92


1027 44+578 26 129.41 223.34 5784.39
1028 44+596 18 144.44 136.92 2426.30
1029 44+620 22 238.49 191.46 4212.19
1030 44+670 45 280.29 259.39 11739.95
1031 44+720 45 97.53 188.91 8444.28
1032 44+800 80 153.45 125.49 10039.40
1033 44+850 50 185.27 169.36 8413.78
1034 44+900 52 178.63 181.95 9529.16
1035 44+950 50 256.78 217.70 10843.81
1036 45+025 71 193.31 225.04 16083.93
1037 45+075 49 204.19 198.75 9770.67
1038 45+100 24 286.75 245.47 5957.54
1039 45+150 50 142.16 214.45 10658.29
1040 45+200 49 73.89 108.02 5322.24
1041 45+250 50 88.66 81.28 4045.87
1042 45+290 40 123.07 105.87 4191.20
1043 45+320 30 80.27 101.67 3088.61
1044 45+370 48 183.21 131.74 6289.10
1045 45+420 50 437.53 310.37 15518.38
1046 45+470 53 364.28 400.90 21079.40
1047 45+520 50 230.35 297.31 14865.55
1048 45+570 50 167.61 198.98 9935.69
1049 45+630 60 299.58 233.59 14015.61
1050 45+655 25 1241.16 770.37 19259.26
1051 45+680 23 864.51 1052.84 24215.21
1052 45+730 49 430.90 647.71 31737.55
1053 45+755 27 302.15 366.53 9896.18
1054 45+785 25 53.90 178.03 4450.63
1055 45+801 16 0.00 26.95 431.20

1056 45+813 Aqueduct

1057 45+845 32 0.00 0.00 0.00


1058 45+852 9 49.63 24.82 223.34
1059 45+878 20 341.58 195.61 3912.10
1060 45+900 21 452.39 396.99 8336.69
1061 45+940 35 173.73 313.06 10957.10
1062 45+650 25 721.96 447.85 11196.13
1063 45+670 20 146.21 434.09 8681.70
1064 45+763 7 198.29 172.25 1205.76
1065 45+790 27 441.86 307.79 8310.40
1066 45+850 60 395.29 418.57 25114.26
1067 45+900 49 191.71 293.50 14381.33
1068 45+950 50 187.64 189.67 9483.68
1069 46+000 50 124.82 156.23 7811.63
1070 46+050 49 425.52 275.17 13483.50
1071 46+100 50 332.22 378.87 18943.53
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

1072 46+150 51 168.06 250.14 12644.53


1073 46+175 25 114.14 141.10 3527.54
1074 46+225 50 314.73 214.43 10721.73
1075 46+275 52 0.00 157.36 8182.88
1076 46+300 26 157.43 78.71 2007.22
1077 46+350 51 228.18 192.80 9736.55
1078 46+400 50 350.11 289.14 14457.05
1079 46+450 49 255.99 303.05 14697.88
1080 46+500 54 121.72 188.86 10103.82
1081 46+550 48 208.67 165.20 7846.76
1082 46+600 47 169.02 188.85 8781.32
1083 46+650 49 59.60 114.31 5601.21
1084 46+700 50 310.68 185.14 9257.00
1085 46+750 49 174.89 242.78 11896.42
1086 46+800 50 208.38 191.63 9581.60
1087 46+850 47 76.52 142.45 6695.06
1088 46+900 48 165.51 121.02 5808.74
1089 46+950 51 75.54 120.52 6146.72
1090 47+000 51 192.73 134.13 6840.83
1091 47+050 51 91.29 142.01 7242.56
1092 47+080 33 135.18 113.23 3680.07
1093 47+100 19 286.51 210.84 4005.98
1094 47+150 49 708.29 497.40 24372.45
1095 47+200 49 1104.29 906.29 44408.14
1096 47+250 49 725.02 914.66 44818.17
1097 47+300 48 446.52 585.77 28117.01
1098 47+350 49 198.97 322.74 15814.48
1099 47+400 57 205.09 202.03 11515.71
1100 47+425 25 299.72 252.40 6310.10
1101 47+475 47 503.65 401.68 18879.10
1102 47+500 23 259.35 381.50 8774.45

Aqueduct 0.00 0.00


1103 47+510 129.67
1104 47+618 108 0.00 0.00 0.00
1105 47+619 1 171.61 85.81 85.81
1106 47+650 28.76 449.72 310.67 8934.80
1107 47+700 53 300.43 375.08 19879.00
1108 47+750 44 197.98 249.21 10965.02
1109 47+800 49.5 176.64 187.31 9271.94
1110 47+850 68 155.06 165.85 11277.97
1111 47+950 110 279.84 217.45 23919.61
1112 48+050 90 282.47 281.15 0.00
1113 48+100 64 242.19 262.33 0.00
1114 48+200 98 393.04 317.61 0.00
1115 48+300 100 436.35 414.69 0.00
1116 48+400 101 529.04 482.69 48751.89
1117 48+500 100 399.20 464.12 46411.80
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

1118 48+540 38 66.63 232.92 8850.79


1119 48+560 18 43.58 55.10 991.86
1120 48+600 39 424.41 233.99 9125.65
1121 48+650 50 392.94 408.67 20433.55
1122 48+700 52 426.73 409.83 21311.37
1123 48+750 52 330.49 378.61 19687.90
1124 48+800 51 300.58 315.53 16092.26
1125 48+860 61 197.61 249.09 15194.73
1126 48+875 16 163.61 180.61 2889.77
1127 48+885 10 0.00 81.80 818.04
1128 48+975 90 0.00 0.00 0.00
1129 48+990 15 90.45 45.22 678.35
1130 49+015 26 85.81 88.13 2291.32
1131 49+040 25 6.28 46.04 1151.11
1132 49+065 25 22.82 14.55 363.79
1133 49+115 49 36.47 29.64 1452.53
1134 49+125 10 67.51 51.99 519.88
1135 49+150 25 65.84 66.68 1666.88
1136 49+200 49 227.05 146.44 7175.73
1137 49+250 51 404.73 315.89 16110.21
1138 49+300 49 308.80 356.76 17481.41
1139 49+350 50 148.31 228.56 11427.88
1140 49+400 53 371.00 259.66 13761.82
1141 49+450 49 256.88 313.94 15382.99
1142 49+500 51 193.22 225.05 11477.52
1143 49+550 49 362.05 277.64 13604.14
1144 49+580 30 412.88 387.46 11623.92
1145 49+630 60 191.29 302.08 18125.07
1146 49+655 26 423.99 307.64 7998.60
1147 49+700 38 267.36 345.68 13135.65
1148 49+750 51 84.54 175.95 8973.55
1149 49+780 30 173.73 129.13 3874.04
1150 49+800 20 209.77 191.75 3835.00
1151 49+850 44 184.62 197.20 8676.71
1152 49+900 49 46.42 115.52 5660.58
1153 49+950 44 183.03 114.72 5047.79
1154 50+000 52 155.23 169.13 8794.71
1155 50+050 51 201.49 178.36 9096.33
1156 50+100 50.5 157.04 179.26 9052.81
1157 50+150 50 207.87 182.46 9122.80
1158 50+200 47 179.41 193.64 9101.08
1159 50+225 24 117.96 148.69 3568.48
1160 50+275 50 0.00 58.98 0.00
1161 50+325 50 0.00 0.00 0.00
1162 50+370 45 0.00 0.00 0.00
1163 50+393 23 0.00 0.00 0.00
1164 50+410 17 0.00 0.00 0.00
1165 50+450 40 0.00 0.00 0.00
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

1166 50+500 50 0.00 0.00 0.00


1167 50+550 50 205.74 102.87 5143.40
1168 50+550 0 102.87 0.00
1169 50+550 0 146.77 73.39 0.00
1170 50+600 50 324.94 235.85 11792.67
1171 50+650 50 129.08 227.01 11350.40
1172 50+675 24 220.47 174.78 4194.60
1173 50+700 25 280.94 250.71 6267.66
1174 50+750 52 316.08 298.51 15522.62
1175 50+800 48 379.18 347.63 16686.34
1176 50+850 51 159.14 269.16 13727.24
1177 50+900 54 313.49 236.32 12761.09
1178 50+950 51 250.94 282.21 14392.89
1179 51+000 50 173.63 212.28 10614.15
1180 51+050 50 180.84 177.24 8861.78
1181 51+100 47 299.87 240.36 11296.69
1182 51+150 50 345.42 322.65 16132.30
1183 51+200 49 345.21 345.31 16920.39
1184 51+250 50 155.69 250.45 12522.43
1185 51+275 23 156.70 156.20 3592.54
1186 51+300 25 273.19 214.95 5373.69
1187 51+350 55 268.05 270.62 14884.21
1188 51+400 44 333.06 300.56 13224.42
1189 51+450 49 347.68 340.37 16678.08
1190 51+500 49 329.05 338.37 16580.01
1191 51+550 48 321.13 325.09 15604.39
1192 51+600 50 354.03 337.58 16878.85
1193 51+635 33 616.15 485.09 16007.94
1194 51+670 35 260.06 438.11 15333.78
1195 51+720 49 366.56 313.31 15352.19
1196 51+770 51 235.59 301.07 15354.67
1197 51+800 29 197.75 216.67 6283.40
1198 51+825 25 196.17 196.96 4924.04
1199 51+875 51 240.63 218.40 11138.53
1200 51+925 50 431.38 336.01 16800.25
1201 51+965 39 69.15 250.26 9760.20
1202 51+985 23 62.73 65.94 1516.54
1203 52+000 17 252.19 157.46 2676.75
1204 52+050 49 325.35 288.77 14149.49
1205 52+100 50 315.61 320.48 16023.75
1206 52+130 29.24 424.87 370.24 10825.79
1207 52+150 17 713.74 569.30 9678.18
1208 52+200 51 256.06 484.90 24729.90
1209 52+250 51 206.75 231.40 11801.63
1210 52+300 53 134.10 170.42 9032.29
1211 52+325 26 37.23 85.66 2227.28
1212 52+350 25 69.98 53.61 1340.19
1213 52+375 24 237.38 153.68 3688.33
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

1214 52+425 50 265.28 251.33 12566.58


1215 52+470 45 190.29 227.79 10250.48
1216 52+500 28 238.96 214.63 6009.57
1217 52+550 49 243.39 241.17 11817.53
1218 52+600 49 272.13 257.76 12630.02
1219 52+650 50 245.07 258.60 12929.83
1220 52+700 49 272.85 258.96 12688.87
1221 52+750 49 214.81 243.83 11947.50
1222 52+790 34 161.40 188.10 6395.45
1223 52+830 36 213.19 187.29 6742.46
1224 52+878 40 354.83 284.01 11360.26
1225 52+910 40 204.05 279.44 11177.60
1226 52+950 40 88.20 146.13 5845.000
1227 53+000 48 666.01 377.10 18100.97
1228 53+020 17 974.43 820.22 13943.77
1229 53+030 10 915.00 944.71 9447.15
1230 53+040 10 773.52 844.26 8442.58
1231 53+060 19 224.48 499.00 9481.00
1232 53+080 20 192.88 208.68 4173.60
1233 53+130 49 139.30 166.09 8138.41
1234 53+180 50 216.67 177.99 8899.25
1235 53+215 36 180.20 198.44 7143.66
1236 53+255 39 5.22 92.71 3615.69
1237 53+275 20 7.07 6.15 122.90
1238 53+300 25 64.29 35.68 892.00
1239 53+325 28 188.36 126.33 3537.10
1240 53+375 51 368.42 278.39 14197.89
1241 53+425 46 185.29 276.86 12735.33
1242 53+475 50 290.37 237.83 11891.50
1243 53+525 50 180.55 235.46 11773.00
1244 53+575 50 168.60 174.58 8728.75
1245 53+625 52 163.19 165.90 8626.54
1246 53+675 49 178.99 171.09 8383.41
1247 53+725 49 279.96 229.48 11244.28
1248 53+740 15 411.95 345.96 5189.33
1249 53+765 25 300.02 355.99 8899.63
1250 53+800 35 316.00 308.01 10780.35
1251 53+850 47 400.04 358.02 16826.99
1252 53+900 49 710.33 555.19 27204.16
1253 53+950 50 954.25 832.29 41614.45
1254 53+980 31 240.84 597.54 18523.80
1255 54+055 75 141.12 190.98 14323.43
1256 54+080 24 223.75 182.44 4378.44
1257 54+120 40 272.57 248.16 9926.40
1258 54+145 28 201.61 237.09 6638.52
1259 54+175 32 148.25 174.93 5597.76
1260 54+200 24 285.79 217.02 5208.48
1261 54+225 24 190.71 238.25 5718.00
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

1262 54+250 26 171.41 181.06 4707.56


1263 54+300 50 251.84 211.63 10581.25
1264 54+350 47 268.41 260.13 12225.88
1265 54+400 50 322.77 295.59 14779.50
1266 54+450 50 435.63 379.20 18960.00
1267 54+480 27 107.48 271.56 7331.99
1268 54+500 21 312.94 210.21 4414.41
1269 54+550 47 366.78 339.86 15973.42
1270 54+580 29 333.17 349.98 10149.28
1271 54+610 27 260.62 296.90 8016.17
1272 54+650 39 173.58 217.10 8466.90
1273 54+700 52 194.65 184.12 9573.98
1274 54+740 41 78.51 136.58 5599.78
1275 54+790 48 387.71 233.11 11189.28
1276 54+840 50 807.52 597.62 29880.75
1277 54+875 37 811.33 809.43 29948.73
1278 54+900 22 427.53 619.43 13627.46
1279 54+925 22 309.04 368.29 8102.27
1280 54+975 48 436.24 372.64 17886.72
1281 55+000 26 276.32 356.28 9263.28
1282 55+050 50 350.49 313.41 15670.25
1283 55+100 52 401.33 375.91 19547.32
1284 55+125 18 183.66 292.50 5264.91
1285 55+145 25 386.55 285.11 7127.63
1286 55+200 56 242.62 314.59 17616.76
1287 55+250 45 486.24 364.43 16399.35
1288 55+290 37 209.95 348.10 12879.52
1289 55+340 47 300.56 255.26 11996.99
1290 55+390 47 291.29 295.93 13908.48
1291 55+415 26 339.35 315.32 8198.32
1292 55+450 34 262.29 300.82 10227.88
1293 55+520 70 206.44 234.37 16405.55
1294 55+560 35 196.53 201.49 7051.98
1295 55+600 40 268.94 232.74 9309.40
1296 55+650 51 333.54 301.24 15363.24
1297 55+700 49 252.13 292.84 14348.92
1298 55+760 59 245.22 248.68 14671.83
1299 55+800 41 229.79 237.51 9737.71
1300 55+850 49 274.17 251.98 12347.02
1301 55+900 50 299.43 286.80 14340.00
1302 55+960 60 288.69 294.06 17643.60
1303 56+010 51 292.98 290.84 14832.59
1304 56+050 42 223.54 258.26 10846.92
1305 56+100 50 315.65 269.60 13479.75
1306 56+150 49 351.39 333.52 16342.48
1307 56+210 59 290.23 320.81 18927.79
1308 56+250 41 292.58 291.41 11947.61
1309 56+300 52 328.63 310.61 16151.46
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

1310 56+360 63 351.92 340.28 21437.33


1311 56+400 37 359.77 355.85 13166.27
1312 56+450 46 248.98 304.38 14001.25
1313 56+500 50 212.81 230.90 11544.75
1314 56+550 50 269.27 241.04 12052.00
1315 56+610 60 275.01 272.14 16328.40
1316 56+650 38 262.97 268.99 10221.62
1317 56+700 47 246.42 254.70 11970.67
1318 56+750 44 325.98 286.20 12592.80
1319 56+800 54 274.33 300.16 16208.37
1320 56+850 51 291.74 283.04 14434.79
1321 56+900 52 305.70 298.72 15533.44
1322 56+975 74 0.00 152.85 11310.90
1323 57+000 29 351.05 175.53 5090.23
1324 57+040 38 104.41 227.73 8653.74
1325 57+070 29 159.30 131.86 3823.80
1326 57+110 40 300.69 230.00 9199.80
1327 57+150 38 275.48 288.09 10947.23
1328 57+210 60 181.44 228.46 13707.60
1329 57+260 51 143.14 162.29 8276.79
1330 57+290 27 310.31 226.73 6121.58
1331 57+330 37 293.22 301.77 11165.31
1332 57+385 56 0.00 146.61 8210.16
1333 57+440 54 150.42 75.21 4061.34
1334 57+490 49 232.73 191.58 9387.18
1335 57+515 26 303.42 268.08 6969.95
1336 57+550 34 185.24 244.33 8307.22
1337 57+590 37 225.03 205.14 7590.00
1338 57+660 70 230.19 227.61 15932.70
1339 57+737 78 301.81 266.00 20748.00
1340 57+752 15 197.88 249.85 3747.68
1341 57+773 16 264.67 231.28 3700.40
1342 57+807 34 324.63 294.65 10018.10
1343 57+838 32 383.20 353.92 11325.28
1344 57+871 33 362.11 372.66 12297.62
1345 57+896 25 360.04 361.08 9026.88
1346 57+952 57 325.75 342.90 19545.02
1347 57+968 17 282.58 304.17 5170.81
1348 58+010 44 334.34 308.46 13572.24
1349 58+080 67 306.52 320.43 21468.81
1350 58+125 45 317.36 311.94 14037.30
1351 58+150 24 359.71 338.54 8124.84
1352 58+200 50 238.34 299.03 14951.25
1353 58+225 25 256.69 247.52 6187.88
1354 58+265 39 258.15 257.42 10039.38
1355 58+295 29 475.90 367.03 10643.73
1356 58+320 23 420.57 448.24 10309.41
1357 58+350 30 258.09 339.33 10179.90
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

1358 58+390 41 220.90 239.50 9819.30


1359 58+430 41 156.90 188.90 7744.90
1360 58+455 25 188.44 172.67 4316.75
1361 58+480 25 215.08 201.76 5044.00
1362 58+556 89 184.64 199.86 17787.54
1363 58+580 24 227.26 205.95 4942.80
1364 58+600 20 188.80 208.03 4160.60
1365 58+625 26 139.24 164.02 4264.52
1366 58+675 49 96.93 118.09 5786.17
1367 58+695 20 120.92 108.93 2178.50
1368 58+760 55 174.36 147.64 8120.20
1369 58+800 40 210.17 192.27 7690.60
1370 58+840 41 191.99 201.08 8244.28
1371 58+855 16 417.42 304.71 4875.28
1372 58+870 15 511.45 464.44 6966.53
1373 58+900 30 305.40 408.43 12252.75
1374 58+930 28 192.19 248.80 6966.26
1375 58+955 26 202.76 197.48 5134.35
1376 58+990 35 170.74 186.75 6536.25
1377 59+015 24 168.22 169.48 4067.52
1378 59+042 28 61.29 114.76 3213.14
1379 59+060 19 238.82 150.06 2851.05
1380 59+100 40 222.45 230.64 9225.40
1381 59+140 40 335.44 278.95 11157.80
1382 59+170 31 203.97 269.71 8360.86
1383 59+185 15 102.30 153.14 2297.03
1384 59+200 16 255.60 178.95 2863.20
1385 59+225 24 234.76 245.18 5884.32
1386 59+260 35 142.17 188.47 6596.28
1387 59+300 42 96.49 119.33 5011.86
1388 59+335 35 190.71 143.60 5026.00
1389 59+375 40 373.07 281.89 11275.60
1390 59+410 35 414.66 393.87 13785.28
1391 59+435 35 267.34 341.00 11935.00
1392 59+485 49 163.82 215.58 10563.42
1393 59+535 51 318.89 241.36 12309.11
1394 59+575 40 207.61 263.25 10530.00
1395 59+605 30 169.36 188.49 5654.55
1396 59+650 46 173.16 171.26 7877.96
1397 59+676 26 128.88 151.02 3926.52
1398 59+759 83 235.18 182.03 15108.49
1399 59+794 35 216.42 225.80 7903.00
1400 59+830 35 103.36 159.89 5596.15
1401 59+862 32 197.34 150.35 4811.20
1402 59+880 18 181.97 189.66 3413.79
1403 59+910 30 245.68 213.83 6414.75
1404 59+958 48 225.06 235.37 11297.76
1405 60+000 43 83.65 154.36 6637.27
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

1406 60+250 250 426.93 255.29 63822.50


1407 60+430 180 507.01 466.97 84054.33
1408 60+525 95 229.74 368.37 34995.25
1409 60+575 51 311.85 270.79 13810.34
1410 60+625 50 330.13 320.99 16049.35
1411 60+675 50 403.83 366.98 18348.83
1412 60+725 50 366.80 385.31 19265.60
1413 60+775 50 313.25 340.02 17001.13
1414 60+825 51 269.79 291.52 14867.55
1415 60+875 49 301.19 285.49 13989.06
1416 60+925 52 387.69 344.44 17910.72
1417 60+975 51 338.80 363.24 18525.42
1418 61+025 51 271.12 304.96 15552.88
1419 61+075 52 450.07 360.59 18750.76
1420 61+100 25 294.22 372.14 9303.58
1421 61+150 51 276.69 285.45 14558.15
1422 61+200 52 349.34 313.01 16276.62
1423 61+220 24 190.06 269.70 6472.76
1424 61+245 25 239.66 214.86 5371.49
1425 61+270 26 308.92 274.29 7131.54
1426 61+320 51 296.85 302.89 15447.24
1427 61+370 52 440.66 368.76 19175.26
1428 61+400 28 163.01 301.83 8451.31
1429 61+450 52 141.93 152.47 7928.28
1430 61+500 50 136.29 139.11 6955.48
1431 61+565 65 63.99 100.14 6508.97
1432 61+600 33.43 325.10 194.54 6503.54
1433 61+660 62 255.79 290.44 18007.53
1434 61+700 42 205.69 230.74 9691.04
1435 61+725 25 119.90 162.79 4069.80
1436 61+750 25 228.84 174.37 4359.19
1437 61+785 36 358.37 293.61 10569.78
1438 61+835 50 378.55 368.46 18423.00
1439 61+885 50 370.79 374.67 18733.50
1440 61+935 52 463.96 417.38 21703.50
1441 61+985 50 399.85 431.91 21595.25
1442 62+015 30 360.06 379.96 11398.65
1443 62+065 51 313.06 336.56 17164.56
1444 62+115 52 366.24 339.65 17661.80
1445 62+150 35 361.88 364.06 12742.10
1446 62+180 31 418.20 390.04 12091.24
1447 62+220 40 509.37 463.79 18551.40
1448 62+270 48 770.16 639.77 30708.72
1449 62+290 21 438.51 604.34 12691.04
1450 62+305 15 273.40 355.96 5339.33
1451 62+320 16 438.06 355.73 5691.68
1452 62+350 31 521.47 479.77 14872.72
1453 62+400 49 426.59 474.03 23227.47
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

1454 62+450 64 460.08 443.34 28373.44


1455 62+506 48 364.34 412.21 19786.08
1456 62+550 51 316.69 340.52 17366.27
1457 62+600 51 368.34 342.52 17468.27
1458 62+650 52 353.53 360.94 18768.62
1459 62+700 50 373.10 363.32 18165.75
1460 62+750 56 306.35 339.73 19024.60
1461 62+800 49 472.59 389.47 19084.03
1462 62+860 60 456.17 464.38 27862.80
1463 62+910 52 425.12 440.65 22913.54
1464 62+960 50 312.74 368.93 18446.50
1465 63+010 54 725.69 519.21 28037.50
1466 63+065 54 932.40 829.04 44768.38
1467 63+090 25 629.63 781.01 19525.34
1468 63+140 51 616.06 622.84 31764.92
1469 63+190 53 655.93 635.99 33707.58
1470 63+240 49 321.97 488.95 23958.45
1471 63+270 51 336.13 329.05 16781.55
1472 63+340 51 255.42 295.78 15084.53
1473 63+410 71 313.65 284.54 20201.99
1474 63+450 39 395.66 354.66 13831.55
1475 63+480 31 621.55 508.61 15766.76
1476 63+500 21 509.12 565.34 11872.04
1477 63+545 45 718.20 613.66 27614.70
1478 63+595 51 718.65 718.43 36639.68
1479 63+625 36 410.88 564.77 20331.54
1480 63+660 36 242.54 326.71 11761.61
1481 63+710 51 305.75 274.15 13981.47
1482 63+750 35 356.40 331.08 11587.68
1483 63+795 43 491.01 423.71 18219.47
1484 63+860 60 172.30 331.66 19899.39
1485 63+900 36 276.93 224.61 8086.07
1486 63+950 53 205.29 241.11 12778.80
1487 63+970 20 296.00 250.65 5012.91
1488 64+020 53 715.73 505.86 26810.82
1489 64+050 30 339.20 527.47 15823.95
1490 64+100 49 416.16 377.68 18506.32
1491 64+150 50 208.55 312.36 15617.78
1492 64+180 30 179.84 194.20 5825.87
1493 64+210 32 271.50 225.67 7221.44
1494 64+250 39 278.27 274.89 10720.52
1495 64+300 43 348.24 313.26 13469.97
1496 64+344 43 369.71 358.98 15435.99
1497 64+364 19 206.71 288.21 5476.00

Aqueduct 175.83 0.00


1498 64+475 191.27
1499 64+500 25 479.47 327.65 8191.30
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

1500 64+550 52 405.52 442.50 23009.74


1501 64+600 51 431.50 418.51 21344.01
1502 64+650 51 413.55 422.53 21548.78
1503 64+700 52 523.23 468.39 24356.28
1504 64+735 30 547.63 535.43 16062.90
1505 64+765 31 484.47 516.05 15997.55
1506 64+800 32 517.87 501.17 16037.44
1507 64+850 51 205.05 361.46 18434.46
1508 64+900 57 253.09 229.07 13057.10
1509 64+950 45 362.12 307.61 13842.32
1510 65+000 49 359.28 360.70 17674.30
1511 65+020 25 305.31 332.29 8307.31
1512 65+050 27 300.64 302.97 8180.22
1513 65+100 50 456.56 378.60 18929.93
1514 65+150 46 350.37 403.47 18559.39
1515 65+180 32 352.41 351.39 11244.48
1516 65+210 33 254.76 303.59 10018.37
1517 65+260 55 277.00 265.88 14623.57
1518 65+285 26 207.71 242.36 6301.31
1519 65+315 29 134.24 170.97 4958.26
1520 65+345 35 125.39 129.81 4543.44
1521 65+375 31 215.58 170.48 5284.97
1522 65+425 54 297.53 256.55 13853.78
1523 65+475 50 501.69 399.61 19980.37
1524 65+525 54 483.77 492.73 26607.39
1525 65+540 14 240.49 362.13 5069.84
1526 65+570 30 386.11 313.30 9399.09
1527 65+600 29 240.58 313.35 9087.09
1528 65+650 51 158.91 199.74 10186.94
1529 65+700 48 254.17 206.54 9913.87
1530 65+750 52 308.22 281.19 14622.06
1531 65+800 48 309.58 308.90 14827.18
1532 65+830 24 106.20 207.89 4989.42
1533 65+850 21 220.78 163.49 3433.32
1534 65+900 49 220.71 220.75 10816.55
1535 65+950 52 219.89 220.30 11455.63
1536 66+000 50 222.98 221.44 11071.83
1537 66+025 24 254.03 238.51 5724.16
1538 66+075 47 199.18 226.61 10650.51
1539 66+125 51 157.43 178.31 9093.56
1540 66+175 49 233.05 195.24 9566.71
1541 66+225 51 284.30 258.68 13192.53
1542 66+275 49 323.07 303.69 14880.66
1543 66+325 43 284.47 303.77 13062.11
1544 66+375 49 270.84 277.65 13605.07
1545 66+425 50 293.15 281.99 14099.60
1546 66+500 74 281.13 287.14 21248.29
1547 66+550 47 223.75 252.44 11864.80
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

1548 66+575 27 437.68 330.72 8929.32


1549 66+600 24 319.65 378.66 9087.95
1550 66+650 50 240.41 280.03 14001.58
1551 66+700 47 265.18 252.80 11881.46
1552 66+750 52 230.42 247.80 12885.70
1553 66+800 50 207.24 218.83 10941.58
1554 66+850 49 192.91 200.08 9803.70
1555 66+900 48 175.40 184.15 8839.39
1556 66+950 49 201.72 188.56 9239.39
1557 67+000 49 243.37 222.54 10904.66
1558 67+050 48 294.68 269.02 12913.01
1559 67+080 31 374.86 334.77 10377.79
1560 67+100 19 401.33 388.10 7373.83
1561 67+125 24 337.98 369.65 8871.70
1562 67+175 50 250.26 294.12 14705.93
1563 67+225 51 274.03 262.15 13369.45
1564 67+275 50 384.62 329.32 16466.20
1565 67+300 20 444.65 414.64 8292.72
1566 67+350 47 311.03 377.84 17758.60
1567 67+400 49 273.97 292.50 14332.62
1568 67+440 39 135.19 204.58 7978.74
1569 67+480 36 275.98 205.58 7401.04
1570 67+530 47 312.96 294.47 13840.02
1571 67+560 30 258.78 285.87 8576.10
1572 67+600 39 391.19 324.99 12674.42
1573 67+650 51 247.17 319.18 16278.18
1574 67+700 48 210.49 228.83 10983.89
1575 67+750 50 242.29 226.39 11319.65
1576 67+800 47 253.48 247.89 11650.71
1577 67+825 23 127.22 190.35 4378.07
1578 67+850 26 249.33 188.27 4895.14
1579 67+900 48 398.23 323.78 15541.49
1580 67+950 49 375.88 387.06 18965.72
1581 68+000 53 287.95 331.91 17591.42
1582 68+050 46 310.25 299.10 13758.60
1583 68+100 49 318.15 314.20 15395.85
1584 68+140 41 217.23 267.69 10975.37
1585 68+165 39 232.98 225.11 8779.13
1586 68+200 35 277.93 255.46 8940.93
1587 68+250 55 293.52 285.73 15714.88
1588 68+300 47 294.24 293.88 13812.27
1589 68+340 40 394.68 344.46 13778.32
1590 68+365 24 451.70 423.19 10156.56
1591 68+390 27 569.31 510.51 13783.64
1592 68+435 52 669.52 619.42 32209.58
1593 68+500 38 789.72 729.62 27725.56
1594 68+550 48 808.13 798.93 38348.40
1595 68+600 50 801.03 804.58 40229.00
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

1596 68+650 50 422.05 611.54 30577.00


1597 68+700 50 457.77 439.91 21995.60
1598 68+740 37 476.90 467.34 17291.45
1599 68+758 19 247.78 362.34 6884.42
1600 68+798 39 149.96 198.87 7755.77
1601 68+850 50 267.30 208.63 10431.30
1602 68+900 50 225.65 246.47 12323.63
1603 68+950 46 255.04 240.35 11055.87
1604 69+000 50 207.68 231.36 11567.95
1605 69+050 50 210.23 208.95 10447.68
1606 69+100 48 239.55 224.89 10794.84
1607 69+150 51 232.14 235.85 12028.15
1608 69+200 51 228.29 230.21 11740.79
1609 69+250 48 271.57 249.93 11996.52
1610 69+300 48 222.76 247.17 11864.02
1611 69+350 52 292.55 257.66 13398.11
1612 69+400 50 238.34 265.44 13272.20
1613 69+450 52 234.08 236.21 12283.00
1614 69+490 41 160.55 197.31 8089.87
1615 69+520 30 282.28 221.41 6642.38
1616 69+550 31 302.36 292.32 9061.87
1617 69+600 48 311.00 306.68 14720.64
1618 69+650 51 300.07 305.54 15582.41
1619 69+700 52 304.34 302.20 15714.58
1620 69+720 19 291.58 297.96 5661.15
1621 69+745 26 338.71 315.14 8193.72
1622 69+795 50 445.04 391.88 19593.80
1623 69+830 35 338.74 391.89 13716.12
1624 69+870 40 435.84 387.29 15491.42
1625 69+930 60 481.46 458.65 27518.97
1626 69+980 50 297.98 389.72 19486.18
1627 70+010 30 250.06 274.02 8220.60
1628 70+060 50 259.77 254.91 12745.55
1629 70+110 50 242.41 251.09 12554.25
1630 70+140 30 185.30 213.85 6415.59
1631 70+200 60 212.49 198.90 11933.79
1632 70+250 50 107.29 159.89 7994.43
1633 70+305 55 114.32 110.80 6094.11
1634 70+315 10 114.55 114.44 1144.36
1635 70+315 0 116.12 115.33 0.00
1636 70+355 40 182.22 149.17 5966.70
1637 70+447 92 201.46 191.84 17649.33
1638 70+500 53 117.17 159.31 8443.67
1639 70+540 40 84.92 101.04 4041.66
1640 70+570 30 178.43 131.67 3950.21
1641 70+595 25 178.20 178.32 4457.91
1642 70+625 30 456.51 317.36 9520.65
1643 70+655 30 196.67 326.59 9797.73
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

1644 70+670 15 140.06 168.36 2525.47


1645 70+700 30 217.08 178.57 5357.07
1646 70+750 50 190.97 204.03 10201.33
1647 70+800 50 135.68 163.33 8166.28
1648 70+850 50 185.02 160.35 8017.58
1649 70+900 50 232.62 208.82 10441.10
1650 70+950 50 128.12 180.37 9018.50
1651 71+000 50 216.41 172.26 8613.20
1652 71+050 50 136.79 176.60 8830.08
1653 71+100 50 183.59 160.19 8009.48
1654 71+150 50 163.82 173.70 8685.05
1655 71+200 50 193.51 178.67 8933.28
1656 71+250 50 191.07 192.29 9614.60
1657 71+300 50 140.85 165.96 8297.90
1658 71+337 37 212.29 176.57 6533.07
1659 71+354 17 186.20 199.25 3387.17
1660 71+400 46 310.47 248.34 11423.46
1661 71+440 40 227.35 268.91 10756.44
1662 71+490 50 225.45 226.40 11319.85
1663 71+525 35 226.68 226.06 7912.17
1664 71+545 20 143.84 185.26 3705.22
1665 71+600 55 221.59 182.72 10049.44
1666 71+650 50 282.50 252.04 12602.13
1667 71+700 50 163.27 222.88 11144.18
1668 71+750 50 131.27 147.27 7363.65
1669 71+800 50 216.31 173.79 8689.65
1670 71+850 50 226.49 221.40 11070.10
1671 71+900 50 189.50 208.00 10399.90
1672 71+950 50 318.88 254.19 12709.63
1673 72+000 50 185.38 252.13 12606.43
1674 72+050 50 234.15 209.76 10488.05
1675 72+100 50 255.49 244.82 12240.80
1676 72+125 25 336.10 295.79 7394.83
1677 72+150 25 159.33 247.71 6192.84
1678 72+200 50 270.13 214.73 10736.53
1679 72+250 50 254.37 262.25 13112.68
1680 72+300 50 196.22 225.30 11264.78
1681 72+350 50 209.90 203.06 10152.85
1682 72+400 50 184.11 197.00 9850.15
1683 72+450 50 191.03 187.57 9378.55
1684 72+500 50 216.58 203.81 10190.30
1685 72+550 50 210.44 213.51 10675.38
1686 72+600 50 372.19 291.31 14565.70
1687 72+650 50 303.38 337.79 16889.35
1688 72+700 50 221.41 262.40 13119.75
1689 72+750 50 230.30 225.85 11292.65
1690 72+793 43 0.00 115.15 4951.39
1691 72+809 16 130.93 65.46 1047.41
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

1692 72+858 49 125.50 128.21 6282.39


1693 72+900 42 122.58 124.04 5209.66
1694 72+933 33 121.21 121.89 4022.52
1695 72+955 22 132.33 126.77 2788.95
1696 73+000 45 254.90 193.62 8712.83
1697 73+033 33 384.27 319.59 10546.44
1698 73+050 17 409.96 397.12 6750.98
1699 73+050 0 409.14 409.55 0.00
1700 73+058 8 409.43 409.28 3274.25
1701 73+086 28 347.37 378.40 10595.09
1702 73+115 29 335.90 341.63 9907.37
1703 73+146 31 387.74 361.82 11216.36
1704 73+196 50 405.81 396.77 0.00
1705 73+246 50 531.49 468.65 23432.60
1706 73+296 50 632.64 582.07 29103.28
1707 73+346 50 912.66 772.65 38632.53
1708 73+396 50 999.40 956.03 47801.63
1709 73+426 30 1006.06 1002.73 30081.96
1710 73+490 64 466.21 736.14 47112.74
1711 73+510 20 307.11 386.66 7733.20
1712 73+575 65 87.92 197.51 12838.44
1713 73+605 30 38.44 63.18 1895.34
1714 73+650 45 196.95 117.70 5296.28
1715 73+700 50 180.64 188.80 9439.83
1716 73+750 50 197.23 188.94 9446.75
1717 73+775 25 272.58 234.90 5872.58
1718 73+825 50 237.85 255.21 12760.73
1719 73+875 50 173.39 205.62 10281.13
1720 73+900 25 177.57 175.48 4386.98
1721 73+925 25 310.40 243.98 6099.55
1722 73+955 30 272.39 291.39 8741.79
1723 74+005 50 145.35 208.87 10443.43
1724 74+035 30 160.04 152.69 4580.79
1725 74+085 50 166.74 163.39 8169.50
1726 74+145 60 121.80 144.27 8656.20
1727 74+185 40 239.52 180.66 7226.40
1728 74+210 25 229.94 234.73 5868.26
1729 74+260 50 149.24 189.59 9479.55
1730 74+330 70 222.59 226.26 15838.48
1731 74+380 50 212.73 217.66 10882.90
1732 74+470 90 197.09 204.91 18441.63
1733 74+486 16 89.85 143.47 2295.53
1734 74+514 28 225.30 157.57 4412.09
1735 74+562 48 218.48 221.89 10650.70
1736 74+604 42 249.68 234.08 9831.49
1737 74+611 7 135.85 192.77 1349.38
1738 74+626 15 299.52 217.69 3265.33
1739 74+652 26 272.96 286.24 7442.27
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

1740 74+712 60 122.02 197.49 11849.40


1741 74+735 23 141.60 131.81 3031.58
1742 74+761 26 142.45 142.02 3692.53
1743 74+795 34 99.12 120.78 4106.54
1744 74+845 50 260.59 179.85 8992.68
1745 74+890 45 199.67 230.13 10355.81
1746 74+940 50 156.47 178.07 8903.40
1747 74+990 50 157.19 156.83 7841.43
1748 75+026 36 139.47 148.33 5339.77
1749 75+076 50 222.97 181.22 9060.85
1750 75+096 20 230.23 226.60 4532.01
1751 75+176 80 86.39 158.31 12664.92
1752 75+245 69 86.33 86.36 5958.67
1753 75+295 50 204.38 145.35 7267.53
1754 75+325 30 522.56 363.47 10903.97
1755 75+380 55 1013.57 768.06 42243.52
1756 75+410 30 720.39 866.98 26009.37
1757 75+435 25 304.85 512.62 12815.41
1758 75+460 25 99.74 202.29 5057.35
1759 75+505 45 54.94 77.34 3480.39
1760 75+540 35 115.39 85.17 2980.86
1761 75+590 50 149.52 132.45 6622.68
1762 75+640 50 153.35 151.43 7571.53
1763 75+705 65 277.57 215.46 14004.84
1764 75+725 20 483.44 380.50 7610.09
1765 75+750 25 269.47 376.46 9411.39
1766 75+780 30 264.73 267.10 8013.03
1767 75+830 50 304.61 284.67 14233.55
1768 75+860 30 348.49 326.55 9796.58
1769 75+890 30 191.63 270.06 8101.79
1770 75+926 36 237.68 214.66 7727.62
1771 75+949 23 136.28 186.98 4300.53
1772 76+009 60 111.15 123.71 7422.63
1773 76+039 30 134.31 122.73 3681.84
1774 76+084 45 124.12 129.21 5814.59
1775 76+099 15 128.00 126.06 1890.88
1776 76+149 50 174.23 151.12 7555.83
1777 76+190 41 219.19 351.31 14403.77
1778 76+250 60 200.88 210.03 12601.98
1779 76+500 250 183.09 191.99 47996.25
1780 76+750 250 171.16 177.13 44281.25
1781 77+000 250 242.83 207.00 51748.75
1782 77+250 250 187.76 215.30 53823.75
1783 77+500 250 192.92 190.34 47585.00
1784 77+750 250 155.65 174.29 43571.25
1785 78+000 250 127.94 141.80 35448.75
1786 78+250 250 231.26 179.60 44900.00
1787 78+500 250 157.08 194.17 48542.50
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

1788 78+750 250 217.81 187.45 46861.25


1789 79+000 250 165.04 191.43 47856.25
1790 79+250 250 212.59 188.82 47203.75
1791 79+500 250 662.48 437.54 109383.75
1792 79+750 250 312.84 487.66 121915.00
1793 80+000 250 219.14 265.99 66497.50
1794 80+250 250 148.60 183.87 45967.50
1795 80+500 250 181.32 164.96 41240.00
1796 80+750 250 344.63 262.98 65743.75
1797 81+000 250 195.87 270.25 67562.50
1798 81+250 250 203.57 199.72 49930.00
1799 81+500 250 172.30 187.94 46983.75
1800 81+525 86.15
1801 81+750 0.00 0.00
1802 82+000 0.00 0.00
SYPHON
1803 82+250 0.00 0.00
1804 82+500 0.00 0.00
1805 82+530 0.00 0.00
1806 82+750 0 435.05 217.53 0.00
1807 83+000 250 152.05 293.55 73387.50
1808 83+250 250 173.94 163.00 40748.75
1809 83+500 250 212.69 193.32 48328.75
1810 83+750 250 109.61 161.15 40287.50
1811 84+000 250 138.64 124.13 31031.25
1812 84+250 250 232.47 185.56 46388.75
1813 84+500 250 161.37 196.92 49230.00
1814 84+750 250 68.09 114.73 28682.50
1815 85+000 250 162.63 115.36 28840.00
1816 85+175
1817 85+250 AQUEDUCT 0.00 0.00
1818 85+390 0.00 0.00
1819 85+500 110 282.60 141.30 15543.00
1820 85+750 250 138.15 210.38 52593.75
1821 86+000 250 174.80 156.48 39118.75
1822 86+250 250 210.72 192.76 48190.00
1823 86+500 250 151.55 181.14 45283.75
1824 86+750 250 174.32 162.94 40733.75
1825 87+000 250 303.25 238.79 59696.25
1826 87+250 250 293.78 298.52 74628.75
1827 87+500 250 188.54 241.16 60290.00
1828 87+750 250 248.75 218.65 54661.25
1829 88+000 250 282.08 265.42 66353.75
1830 88+250 250 336.97 309.53 77381.25
1831 88+500 250 200.88 268.93 67231.25
1832 88+750 250 255.61 228.25 57061.25
1833 89+000 250 157.02 206.32 51578.75
1833 89+250 250 361.55 259.29 64821.25
1835 89+500 250 350.08 355.82 88953.75
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

1836 89+750 250 223.02 286.55 71637.50


1837 90+000 250 154.30 188.66 47165.00
1838 90+250 250 245.97 200.14 50033.75
1838 90+500 250 189.58 217.78 54443.75
1839 90+750 250 192.75 191.17 47791.25
1840 91+000 250 145.74 169.25 42311.25
1841 91+642 642 126.96 136.35 87536.70
1842 91+700 58 466.69 296.83 17215.85
1843 91+750 50 925.44 696.07 34803.25
1844 91+800 50 1666.61 1296.03 64801.25
1845 91+850 50 2602.34 2134.48 106723.75
1846 91+900 50 4053.86 3328.10 166405.00
1847 91+950 50 5174.24 4614.05 230702.50
1848 92+000 50 6243.24 5708.74 285437.00
1849 92+050 50 8226.99 7235.12 361755.75
1850 92+100 50 9645.73 8936.36 446818.00
1851 92+150 50 11246.70 10446.22 522310.75
1852 92+200 50 12776.83 12011.77 600588.25
1853 92+250 50 12010.12 12393.48 619673.75
1854 92+300 50 10010.96 11010.54 550527.00
1855 92+350 50 7568.93 8789.95 439497.25
1856 92+400 50 5273.99 6421.46 321073.00
1857 92+430 30 4099.93 4686.96 140608.80
1858 92+500 70 2472.01 3285.97 230017.90
1859 92+650 150 1322.55 1897.28 284592.00
1859 92+750 100 173.09 747.82 74782.00
1860 93+000 250 137.10 155.10 38773.75
1861 93+250 250 124.46 130.78 32695.00
1862 93+500 250 208.19 166.33 41581.25
1863 93+750 250 179.22 193.71 48426.25
1864 94+000 250 123.32 151.27 37817.50
1865 94+250 250 166.71 145.02 36253.75
1866 94+500 250 168.75 167.73 41932.50
1867 94+750 250 221.82 195.29 48821.25
1868 95+000 250 185.61 203.72 50928.75
1869 95+250 250 112.93 149.27 37317.50
1870 95+500 250 203.94 158.44 39608.75
1871 95+750 250 147.73 175.84 43958.75
1872 96+000 250 157.37 152.55 38137.50
1873 96+250 250 152.15 154.76 38690.00
1874 96+500 250 145.33 148.74 37185.00
1875 96+750 250 97.23 121.28 30320.00
1876 97+000 250 188.74 142.99 35746.25
1877 97+250 250 125.49 157.12 39278.75
1878 97+500 250 135.65 130.57 32642.50
1879 97+750 250 148.25 141.95 35487.50
1880 98+000 74.13
AQUEDUCT
1880 98+077 0.00 0.00
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

1881 98+250 173 236.19 118.10 20430.44


1882 98+500 250 236.19 236.19 59047.50
1883 98+750 250 103.62 169.91 42476.25
1884 99+000 250 135.00 119.31 29827.50
1885 99+250 250 227.57 181.29 45321.25
1886 99+500 250 193.69 210.63 52657.50
1887 99+750 250 173.92 183.81 45951.25
1888 100+000 250 136.97 155.45 38861.25
1889 100+250 250 131.63 134.30 33575.00
1890 100+500 250 318.17 224.90 56225.00
1891 100+750 250 265.54 291.86 72963.75
1892 100+920 132.77
1893 101+000 0.00 0.00
1894 101+250 0.00 0.00
1895 101+500 0.00 0.00
1896 101+750 0.00 0.00
SYPHON
1897 102+000 0.00 0.00
1898 102+250 0.00 0.00
1899 102+500 0.00 0.00
1900 102+750 0.00 0.00
1901 102+930 0.00 0.00
1901 103+000 70 209.49 104.75 7332.15
1902 103+250 250 157.56 183.53 45881.25
1903 103+500 250 169.86 163.71 40927.50
1904 103+750 250 152.19 161.03 40256.25
1905 104+000 250 198.35 175.27 43817.50
1906 104+250 250 149.66 174.01 43501.25
1907 104+500 250 134.47 142.07 35516.25
1908 104+750 250 253.84 194.16 48538.75
1909 105+000 250 209.76 231.80 57950.00
1910 105+250 250 708.43 459.10 114773.75
1911 105+500 250 147.74 428.09 107021.25
1912 105+750 250 162.49 155.12 38778.75
1913 106+000 250 123.64 143.07 35766.25
1914 106+250 250 125.44 124.54 31135.00
1915 106+500 250 105.68 115.56 28890.00
1916 106+750 250 127.16 116.42 29105.00
1917 107+000 250 132.04 129.60 32400.00
1918 107+250 250 175.27 153.66 38413.75
1919 107+500 250 164.75 170.01 42502.50
1920 107+750 250 255.83 210.29 52572.50
1921 108+000 250 149.92 202.88 50718.75
1922 108+250 250 237.17 193.55 48386.25
1922 108+500 250 187.74 212.46 53113.75
1923 108+750 250 168.42 178.08 44520.00
1924 109+000 250 223.40 195.91 48977.50
1925 109+250 250 309.88 266.64 66660.00
1926 109+500 250 221.82 265.85 66462.50
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

1927 109+750 250 295.37 258.60 64648.75


1928 110+000 250 147.92 221.65 55411.25
1929 110+030 73.96
AQUEDUCT
1930 110+227 0.00 0.00
1931 110+250 23 192.55 96.28 2214.33
1932 110+500 250 223.56 208.06 52013.75
1933 110+750 250 223.56 223.56 55890.00
1934 111+000 250 80.23 151.90 37973.75
1935 111+250 250 258.79 169.51 42377.50
1936 111+500 250 178.08 218.44 54608.75
1937 111+750 250 163.35 170.72 42678.75
1938 112+000 250 177.42 170.39 42596.25
1939 112+250 250 118.02 147.72 36930.00
1940 112+500 250 128.09 123.06 30763.75
1941 112+750 250 107.10 117.60 29398.75
1942 113+000 250 186.68 146.89 36722.50
1943 113+250 250 184.33 185.51 46376.25
1943 113+500 250 51.91 118.12 29530.00
1944 113+750 250 227.80 139.86 34963.75
1945 114+000 250 158.93 193.37 48341.25
1946 114+250 250 34.58 96.76 24188.75
114+349 AQUEDUCT
1947 17.29
1948 114+500 151 61.65 30.83 4654.58
1949 114+750 250 80.58 71.12 17778.75
1950 115+000 250 269.84 175.21 43802.50
1951 115+069 134.92
AQUEDUCT
1952 115+146 0.00 0.00
1953 115+250 104 167.83 83.92 8727.16
1954 115+500 250 133.91 150.87 37717.50
1955 115+750 250 360.76 247.34 61833.75
1956 116+000 250 175.51 268.14 67033.75
1957 116+250 250 229.71 202.61 50652.50
1958 116+500 250 209.78 219.75 54936.25
1959 116+750 250 233.84 221.81 55452.50
1960 117+000 250 123.43 178.64 44658.75
1961 117+250 250 61.89 92.66 23165.00
1962 117+500 250 245.82 153.86 38463.75
1963 117+750 250 219.78 232.80 58200.00
1964 118+000 250 136.64 178.21 44552.50
1964 118+250 250 107.97 122.31 30576.25
1965 118+500 250 178.44 143.21 35801.25
1966 118+750 250 191.82 185.13 46282.50
1967 119+000 250 205.23 198.53 49631.25
1968 119+250 250 225.05 215.14 53785.00
1969 119+500 250 147.34 186.20 46548.75
1970 119+750 250 105.21 126.28 31568.75
1971 120+000 250 269.55 187.38 46845.00
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

1972 120+136 134.78


AQUEDUCT
1973 120+194 0.00 0.00
1974 120+250 56 165.43 82.72 4632.04
1975 120+500 250 70.54 117.99 29496.25
1976 120+750 250 225.53 148.04 37008.75
1977 121+000 250 172.73 199.13 49782.50
1978 121+250 250 166.15 169.44 42360.00
1979 121+500 250 99.85 133.00 33250.00
1980 121+750 250 189.50 144.68 36168.75
1981 122+000 250 94.54 142.02 35505.00
1982 122+250 250 222.64 158.59 39648.00
1983 122+500 250 130.81 176.73 44181.75
1984 122+750 250 99.47 115.14 28785.00
1985 123+000 250 187.55 143.51 35877.50
1985 123+250 250 238.95 213.25 53312.50
1986 123+500 250 63.16 151.06 37763.75
1987 123+750 250 36.46 49.81 12452.50
1988 124+000 250 50.13 43.30 10823.75
1989 124+250 250 119.02 84.58 21143.75
1990 124+500 250 226.05 172.54 43133.75
1991 124+750 250 314.92 270.49 67621.25
1992 125+000 250 138.53 226.73 56681.25
1993 125+250 250 155.42 146.98 36743.75
1994 125+500 250 175.02 165.22 41305.00
1995 125+750 250 130.75 152.89 38221.25
1996 126+000 250 85.07 107.91 26977.50
1997 126+250 250 159.76 122.42 30603.75
1998 126+500 250 122.49 141.13 35281.25
1999 126+750 250 134.92 128.71 32176.25
2000 127+000 250 98.16 116.54 29135.00
2001 127+250 250 150.61 124.39 31096.25
2002 127+500 250 163.16 156.89 39221.25
2003 127+750 250 170.36 166.76 41690.00
2004 128+000 250 355.31 262.84 65708.75
2005 128+250 250 180.63 267.97 66992.50
2006 128+500 250 166.75 173.69 43422.50
2006 128+750 250 184.42 175.59 43896.25
2007 129+000 250 119.30 151.86 37965.00
2008 129+250 250 230.31 174.81 43701.25
2009 129+500 250 271.61 250.96 62740.00
2010 129+750 250 213.00 242.31 60576.25
2011 129+808 106.50
AQUEDUCT
2012 129+904 0.00 0.00
2013 130+000 96 156.03 78.02 7489.44
2014 130+250 250 355.20 255.62 63903.75
2015 130+500 250 166.04 260.62 65155.00
2016 130+750 250 160.18 163.11 40777.50
2017 131+000 250 300.98 230.58 57645.00
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

2018 131+250 250 130.78 215.88 53970.00


2019 131+500 250 127.41 129.10 32273.75
2020 131+750 250 251.30 189.36 47338.75
2021 132+000 250 65.24 158.27 39567.50
2022 132+250 250 102.16 83.70 20925.00
2023 132+500 250 97.96 100.06 25015.00
2024 132+750 250 259.97 178.97 44741.25
2025 133+000 250 158.56 209.27 52316.25
2026 133+250 250 262.98 210.77 52692.50
2027 133+500 250 105.14 184.06 46015.00
2027 133+750 250 72.38 88.76 22190.00
2028 134+000 250 63.26 67.82 16955.00
2029 134+250 250 159.37 111.32 27828.75
2030 134+500 250 152.97 156.17 39042.50
2031 134+750 250 171.34 162.16 40538.75
2032 135+000 250 264.85 218.10 54523.75
2033 135+250 250 167.76 216.31 54076.25
2034 135+500 250 322.93 245.35 61336.25
2035 135+750 250 157.99 240.46 60115.00
2036 136+000 250 226.74 192.37 48091.25
2037 136+250 250 156.06 191.40 47850.00
2038 136+500 250 39.01 97.54 24383.75
2039 136+732 19.51
2040 136+750 0.00 0.00
AQUEDUCT
2041 137+000 0.00 0.00
2042 137+250 0.00 0.00
2043 137+500 250 165.14 82.57 20642.50
2044 137+750 250 55.95 110.55 27636.25
2045 138+000 250 379.87 217.91 54477.50
2046 138+250 250 113.01 246.44 61610.00
2047 138+500 250 122.65 117.83 29457.50
2048 138+750 250 101.00 111.83 27956.25
2048 139+000 250 179.03 140.02 35003.75
2049 139+250 250 68.54 123.79 30946.25
2050 139+500 250 185.74 127.14 31785.00
2051 139+750 250 250.07 217.91 54476.25
2052 140+000 250 283.95 267.01 66752.50
2053 140+250 250 59.97 171.96 42990.00
140+370 0.00
2054 AQUEDUCT 29.99
2055 140+490 0.00 0.00
2056 140+500 10 169.82 84.91 849.10
2057 140+750 250 179.27 174.55 43636.25
2058 140+914 89.64
2059 141+000 0.00 0.00
2060 141+250 0.00 0.00
AQUEDUCT
2061 141+500 0.00 0.00
2062 141+750 0.00 0.00
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

AQUEDUCT

2063 141+905 0.00 0.00


2064 142+000 95 25.67 12.84 1219.33
2065 142+250 250 215.65 120.66 30165.00
2066 142+500 250 69.13 142.39 35597.50
2067 142+727 34.57
2068 142+750 0.00 0.00
2069 143+000 0.00 0.00
AQUEDUCT
2069 143+250 0.00 0.00
2070 143+500 0.00 0.00
2071 143+729 0.00 0.00
2072 143+750 21 256.96 128.48 2698.08
2073 144+000 250 112.21 184.59 46146.25
2074 144+250 250 82.02 97.12 24278.75
2075 144+500 250 107.69 94.86 23713.75
2076 144+750 250 86.16 96.93 24231.25
2077 145+000 250 292.78 189.47 47367.50
2078 145+250 250 83.45 188.12 47028.75
2079 145+500 250 458.27 270.86 67715.00
2080 145+750 250 129.45 293.86 73465.00
2081 146+000 250 81.90 105.68 26418.75
2082 146+250 250 114.78 98.34 24585.00
2083 146+500 250 126.60 120.69 30172.50
2084 146+750 250 240.31 183.46 45863.75
2085 147+000 250 30.47 135.39 33847.50
2086 147+250 250 156.34 93.41 23351.25
2087 147+500 250 204.51 180.43 45106.25
2088 147+515 15 102.26 1533.83

147+581 AQUEDUCT 0.00


2089 0.00
2090 147+750 169 131.72 65.86 11130.34
2090 148+000 250 155.82 143.77 35942.50
2091 148+097 77.91
AQUEDUCT
2092 148+161 0.00 0.00
2093 148+250 89 411.12 205.56 18294.84
2094 148+500 250 191.67 301.40 75348.75
2095 148+750 250 354.98 273.33 68331.25
2096 149+000 250 205.88 280.43 70107.50
2097 149+250 250 85.78 145.83 36457.50
2098 149+500 250 145.91 115.85 28961.25
2099 149+750 250 164.77 155.34 38835.00
2100 150+000 250 81.01 122.89 30722.50
2101 150+250 250 130.22 105.62 26403.75
2102 150+500 250 240.61 185.42 46353.75
2103 150+750 250 266.40 253.51 63376.25
2104 151+000 250 60.95 163.68 40918.75
2105 151+250 250 197.52 129.24 32308.75
2106 151+500 250 246.30 221.91 55477.50
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

2107 151+750 250 203.57 224.94 56233.75


2108 151+796 101.79
AQUEDUCT
2109 151+921 0.00 0.00
2110 152+000 79 183.87 91.94 7262.87
2111 152+250 250 116.79 150.33 37582.50
2111 152+500 250 221.40 169.10 42273.75
2112 152+750 250 100.47 160.94 40233.75
2113 153+000 250 147.37 123.92 30980.00
2114 153+250 250 117.05 132.21 33052.50
2115 153+500 250 137.17 127.11 31777.50
2116 153+559 68.59
AQUEDUCT
2117 153+650 0.00 0.00
2118 153+750 100 134.58 67.29 6729.00
2119 154+000 250 137.13 135.86 33963.75
2120 154+250 250 107.43 122.28 30570.00
2121 154+500 250 141.98 124.71 31176.25
2122 154+750 250 89.14 115.56 28890.00
2123 155+000 250 116.27 102.71 25676.25
2124 155+250 250 143.52 129.90 32473.75
2125 155+500 250 97.20 120.36 30090.00
2126 155+750 250 101.20 99.20 24800.00
2127 156+000 250 113.84 107.52 26880.00
2128 156+250 250 222.86 168.35 42087.50
2129 156+500 250 104.04 163.45 40862.50
2130 156+750 250 230.13 167.09 41771.25
2131 157+000 250 177.90 204.02 51003.75
2132 157+250 250 87.27 132.59 33146.25
2132 157+500 250 140.87 114.07 28517.50
2133 157+750 250 273.03 206.95 51737.50
2134 158+000 250 306.39 289.71 72427.50
2135 158+250 250 169.97 238.18 59545.00
2136 158+500 250 82.50 126.24 31558.75
2137 158+683 41.25
2138 158+750 0.00 0.00
AQUEDUCT
2139 159+000 0.00 0.00
2140 159+177 0.00 0.00
2141 159+250 73 18.20 9.10 664.30
2142 159+500 250 97.50 57.85 14462.50
2143 159+750 250 82.63 90.07 22516.25
2144 160+000 250 60.49 71.56 17890.00
2145 160+250 250 78.25 69.37 17342.50
2146 160+500 250 71.66 74.96 18738.75
2147 160+750 250 202.80 137.23 34307.50
2148 161+000 250 41.90 122.35 30587.50
2149 161+089 20.95
2150 161+250 AQUEDUCT 0.00 0.00
2151 161+389 0.00 0.00
2152 161+500 111 50.85 25.43 2822.18
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

2153 161+750 250 106.39 78.62 19655.00


2153 162+000 250 33.37 69.88 17470.00
2154 162+250 250 256.71 145.04 36260.00
2155 162+500 250 218.62 237.67 59416.25
2156 162+750 250 129.81 174.22 43553.75
2157 163+000 250 53.14 91.48 22868.75
2158 163+250 250 84.29 68.72 17178.75
2159 163+500 250 71.56 77.93 19481.25
2160 163+586 35.78
AQUEDUCT
2161 163+681 0.00 0.00
2162 163+750 69 78.96 39.48 2724.12
2163 164+000 250 102.10 90.53 22632.50
2164 164+250 250 260.20 181.15 45287.50
2165 164+500 250 163.73 211.97 52991.25
2166 164+750 250 128.49 146.11 36527.50
2167 165+000 250 141.24 134.87 33716.25
2168 165+250 250 105.57 123.41 30851.25
2169 165+500 250 306.86 206.22 51553.75
2170 165+750 250 306.86 306.86 76715.00
2171 166+000 250 62.45 184.66 46163.75
2172 166+250 250 1399.34 730.90 182723.75
2173 166+500 250 661.53 1030.44 257608.75
2174 166+750 250 94.01 377.77 94442.50
2174 166+770 47.01
2175 167+000 0.00 0.00
2176 167+250 AQUEDUCT 0.00 0.00
2177 167+500 0.00 0.00
2178 167+689 0.00 0.00
2179 167+750 61 141.15 70.58 4305.08
2180 168+000 250 67.90 104.53 26131.25
2181 168+250 250 83.38 75.64 18910.00
2182 168+500 250 117.05 100.22 25053.75
2183 168+750 250 231.06 174.06 43513.75
2184 169+000 250 130.83 180.95 45236.25
2185 169+250 250 121.58 126.21 31551.25
2186 169+500 250 75.45 98.52 24628.75
2187 169+750 250 457.27 266.36 66590.00
2188 170+000 250 49.57 253.42 63355.00
2189 170+250 250 13.69 31.63 7907.50
2190 170+500 250 109.50 61.60 15398.75
2191 170+750 250 112.95 111.23 27806.25
2192 170+890 140 112.95 112.95 15813.00
171+000 AQUEDUCT 71.72 0.00
2193 92.34
2194 171+250 250 93.05 82.39 20596.25
2195 171+500 250 36.09 64.57 16142.50
2195 171+750 250 95.64 65.87 16466.25
2196 172+000 250 105.96 100.80 25200.00
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

2197 172+250 250 113.15 109.56 27388.75


2198 172+500 250 99.49 106.32 26580.00
2199 172+750 250 117.66 108.58 27143.75
2200 172+991 58.83
2201 173+000 0.00 0.00
2202 173+250 0.00 0.00
2203 173+500 AQUEDUCT 0.00 0.00
2204 173+750 0.00 0.00
2205 174+000 0.00 0.00
2206 174+039 0.00 0.00
2207 174+250 211 66.52 33.26 7017.86
2208 174+500 250 120.78 93.65 23412.50
2209 174+750 250 64.12 92.45 23112.50
2210 175+000 250 160.93 112.53 28131.25
2211 175+250 250 125.81 143.37 35842.50
2212 175+500 250 96.28 111.05 27761.25
2213 175+750 250 137.26 116.77 29192.50
2214 176+000 250 139.63 138.45 34611.25
2215 176+250 250 141.60 140.62 35153.75
2216 176+500 250 382.41 262.01 65501.25
2216 176+750 250 1738.17 1060.29 265072.50
2217 177+000 250 859.04 1298.61 324651.25
2218 177+250 250 119.31 489.18 122293.75
2219 177+500 250 72.26 95.79 23946.25
2220 177+750 250 62.01 67.14 16783.75
2221 178+000 250 410.97 236.49 59122.50
2222 178+154 205.49
2223 178+250 0.00 0.00
AQUEDUCT
2224 178+500 0.00 0.00
2225 178+591 0.00 0.00
2226 178+750 159 208.20 104.10 16551.90
2227 179+000 250 132.82 170.51 42627.50
2228 179+250 250 107.76 120.29 30072.50
2229 179+500 250 115.82 111.79 27947.50
2230 179+750 250 207.29 161.56 40388.75
2231 180+000 250 47.04 127.17 31791.25
2232 180+250 250 69.35 58.20 14548.75
2233 180+500 250 134.12 101.74 25433.75
2234 180+750 250 103.25 118.69 29671.25
2235 181+000 250 98.87 101.06 25265.00
2236 181+250 250 59.76 79.32 19828.75
2237 181+500 250 55.50 57.63 14407.50
2237 181+750 250 97.05 76.28 19068.75
2238 182+000 250 15.18 56.12 14028.75
2239 182+250 250 38.71 26.95 6736.25
2240 182+500 250 31.97 35.34 8835.00
2241 182+750 250 139.53 85.75 21437.50
2242 183+000 250 106.37 122.95 30737.50
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

2243 183+250 250 85.70 96.04 24008.75


2244 183+500 250 37.51 61.61 15401.25
2245 183+750 250 50.23 43.87 10967.50
2246 184+000 250 110.60 80.42 20103.75
2247 184+250 250 41.22 75.91 18977.50
2248 184+500 250 55.86 48.54 12135.00
2249 184+745 245 55.86 55.86 13685.70
2250 184+750 AQUEDUCT 27.93
2251 184+907 157 0.00 0.00
2252 185+000 93 66.60 33.30 3096.90
2253 185+250 250 78.62 72.61 18152.50
2254 185+522 272 78.62 78.62 21384.64
2255 MINOR CANAL 39.31 0.00
2256 0+000 208.20 104.10 0.00
2257 0+250 250 132.82 170.51 42627.50
2258 0+500 250 107.76 120.29 30072.50
2258 0+750 250 115.82 111.79 27947.50
2259 1+000 250 207.29 161.56 40388.75
2260 1+250 250 47.04 127.17 31791.25
2261 1+500 250 69.35 58.20 14548.75
2262 1+750 250 134.12 101.74 25433.75
2263 2+000 250 103.25 118.69 29671.25
2264 2+250 250 98.87 101.06 25265.00
2265 2+500 250 59.76 79.32 19828.75
2266 2+750 250 55.50 57.63 14407.50
2267 3+000 250 97.05 76.28 19068.75
2268 3+250 250 15.18 56.12 14028.75
2269 3+500 250 38.71 26.95 6736.25
2270 3+750 250 31.97 35.34 8835.00
2271 4+000 250 139.53 85.75 21437.50
2272 4+250 250 106.37 122.95 30737.50
2273 4+500 250 85.70 96.04 24008.75
2274 4+750 250 37.51 61.61 15401.25
2275 5+000 250 50.23 43.87 10967.50
2276 5+250 250 110.60 80.42 20103.75
2277 5+500 250 41.22 75.91 18977.50
2278 5+750 250 55.86 48.54 12135.00
2279 6+000 250 55.86 55.86 13965.00
2279 6+250 250 141.15 98.51 24626.25
2280 6+500 250 67.90 104.53 26131.25
2281 6+750 250 83.38 75.64 18910.00
2282 7+000 250 117.05 100.22 25053.75
2283 7+250 250 231.06 174.06 43513.75
2284 7+500 250 130.83 180.95 45236.25
2285 7+750 250 121.58 126.21 31551.25
2286 8+000 250 75.45 98.52 24628.75
2287 8+250 250 457.27 266.36 66590.00
2288 8+500 250 49.57 253.42 63355.00
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

2289 8+750 250 13.69 31.63 7907.50


2290 9+000 250 109.50 61.60 15398.75
2291 9+250 250 112.95 111.23 27806.25
2292 9+500 250 78.96 95.96 23988.75
2293 9+750 250 102.10 90.53 22632.50
2294 10+000 250 260.20 181.15 45287.50
2295 10+250 250 163.73 211.97 52991.25
2296 10+500 250 128.49 146.11 36527.50
2297 10+750 250 141.24 134.87 33716.25
2298 11+000 250 105.57 123.41 30851.25
2299 11+250 250 306.86 206.22 51553.75
2300 11+500 250 306.86 306.86 76715.00
2300 11+750 250 62.45 184.66 46163.75
2301 12+000 250 411.12 236.79 59196.25
2302 12+250 250 191.67 301.40 75348.75
2303 12+500 250 354.98 273.33 68331.25
2304 12+750 250 205.88 280.43 70107.50
2305 13+000 250 85.78 145.83 36457.50
2306 13+250 250 145.91 115.85 28961.25
2307 13+500 250 164.77 155.34 38835.00
2308 13+750 250 81.01 122.89 30722.50
2309 14+000 250 130.22 105.62 26403.75
2310 14+250 250 240.61 185.42 46353.75
2311 14+500 250 266.40 253.51 63376.25
2312 14+750 250 60.95 163.68 40918.75
2313 15+000 250 197.52 129.24 32308.75
2314 15+250 250 246.30 221.91 55477.50
2315 15+500 250 203.57 224.94 56233.75
2316 15+750 250 256.96 230.27 57566.25
2317 16+000 250 112.21 184.59 46146.25
2318 16+250 250 82.02 97.12 24278.75
2319 16+500 250 107.69 94.86 23713.75
2320 16+750 250 86.16 96.93 24231.25
2321 17+000 250 292.78 189.47 47367.50
2321 17+250 250 83.45 188.12 47028.75
2322 17+500 250 458.27 270.86 67715.00
2323 17+750 250 129.45 293.86 73465.00
2324 18+000 250 81.90 105.68 26418.75
2325 18+250 250 114.78 98.34 24585.00
2326 18+500 250 126.60 120.69 30172.50
2327 18+750 250 240.31 183.46 45863.75
2328 19+000 250 30.47 135.39 33847.50
2329 19+250 250 156.34 93.41 23351.25
2330 19+500 250 204.51 180.43 45106.25
2331 19+750 250 141.15 172.83 43207.50
2332 20+000 250 67.90 104.53 26131.25
2333 20+250 250 83.38 75.64 18910.00
2334 20+500 250 117.05 100.22 25053.75
Total X-Section
S.No Chainage Length
Area (Sft)
Average Area Total Qty

2335 20+750 250 231.06 174.06 43513.75


2336 21+000 250 130.83 180.95 45236.25
2337 21+250 250 121.58 126.21 31551.25
2338 21+500 250 75.45 98.52 24628.75
2339 21+750 250 457.27 266.36 66590.00
2340 22+000 250 49.57 253.42 63355.00
2341 22+250 250 13.69 31.63 7907.50
2342 22+500 250 129.45 71.57 17892.50
2342 22+976 476
Total Qty in Cft 40113403.35
Boulders Qty in CM 1106.91
Qty in CM 1136820.48167964
Construction of Siran Right Bank Canal
District Mansehra
Aqueducts

BOQ Item No. Description


B-1 Structural Excavation in Common Material

RD: Description No. Length Width Depth Volume (cft) Remarks


(ft) (ft) (ft)

Aqueduct Piers 2 11 11 5 1210


1.5ft added on both
Abutments 8 15.25 5 4 2440 sides for working
RD: 7+093 space
Cut off wall Nullah 2 23 5 5 1150
Bridge Abutments 2 21 12.5 6.25 3281.25

Abutments 6 15.96 16.12 4 6174.6048


RD:7+686
Cut off wall Nullah 2 25 5 5 1250

RD: 8+089 Detour Aqueduct Piers 17 15 18 6 27540


Aqueduct Abutments 2 15.25 5 4 610

Aqueduct Piers 1 11 11 6 726


RD: 10+035 Abutments 2 15.25 5 4 610
Cut off wall Nullah 2 41 5 5 2050

Aqueduct Piers 18 16 18 6 31104


RD: 11+388 Detour
Aqueduct Abutment U/S 1 15.25 5 4 305
Abutment D/S 1 15.25 12 3 549

Aqueduct Piers 3 11 11 6 2178


RD: 27+275
Abutments 2 15.25 5 4 610

Aqueduct Piers 10 11 11 6 7260


RD: 31+500 to31+725
Cut off walls 2 13.6 5 4 544

RD: 30+600 Abutments 7 15.25 5 4 610

Walls 2 225 6.5 4.5 13162.5


RD: 31+500
Cut off wall Nullah 2 23 5 5 1150
Causeway bed 1 23 12 2 552

Aqueduct Piers 1 11 11 6 726


Abutments 2 13.6 5 4 544
RD: 32+500 Bridge Abutments 2 21.25 14.5 10.5 6470.625
Centre pier bridge 1 8.5 8.5 5 361.25
Wing Wall 4 18 12 10.5 9072
L Area
Exc; AB# 01 21.33 344.65 7351.3845
Wing Walls AB 01 55* 23 338 7774
Wing Walls AB 01 90* 1st step 11 151.81 1669.91
Wing Walls AB 01 90* 2nd Step 9.83 349.17 3432.3411
Pile #01 23.08 456.33 10532.0964
Pile #02 23.08 456.33 10532.0964
RD: 33+020
Exc; AB# 02 21.33 184.81 3941.9973
Wing Walls L/S 30* 1st Step 12 190.02 2280.24
Wing Walls L/S 30* 2nd Step 11.25 146.73 1650.7125
Wing Walls R/S 90* 1st Step a 10.83 59.03 639.2949
Wing Walls R/S 90* 1st Step b 2.75 194.9 535.975
Wing Walls R/S 90* 2nd Step 10.5 252.67 2653.035
Construction of Siran Right Bank Canal
District Mansehra
Aqueducts

BOQ Item No. Description

Abutments 1 11.88 137.38 1632.0744


RD: 38+875
Abutments 1 11.88 38.33 455.3604

Abutments 1 11 11 8 968
RD: 41+300 Bridge Abutments 2 21 9 6 2268
Centre pier bridge 1 21 8.5 6 1071

RD: 43+825 Detour Aqueduct Piers 20 12 12 6 17280


aqueduct Abutments 2 14.75 5 5 737.5

Abutments 1 11 11 8 968
RD: 44+300 Bridge Abutments 2 21 9 6 2268
Centre pier bridge 1 21 8.5 6 1071

Aqueduct Piers 1 11 11 6 726

RD: 45+785 Detour Abutments 2 14.75 5 5 737.5


aqueduct Bridge Abutments 2 21 12 14.5 7308
Centre pier bridge 1 21 8.5 5 892.5

Aqueduct Piers 2 11 11 12 2904


RD: 47+500
Causeway bed 1 26 19 3.5 1729

Aqueduct Piers 2 11 11 10 2420


Causeway Toe wall 1 30 8.5 3.5 892.5
RD: 64+475 Causeway Cut off wall 2 19 2 4 304
RCC Brest wall 1 48 10 12 5760
Ramp cut off walls 2 19 2 4 304

Aqueduct Piers 4 11 11 6 2904


RD: 85+175
Abutments 2 11 5 4 440

Aqueduct Piers 1 11 11 6 726


Cut off walls 2 13 5 4 520
RD: 98+000
Bridge Abutments 2 21 9 6 2268
Centre pier bridge 1 21 8.5 6 1071

Aqueduct Piers 3 11 11 6 2178


RD: 110+030
Cut off walls 2 13 6 5 780

Aqueduct Piers 1 11 11 6 726


Cut off walls 2 12 5 4 480
RD: 114+250
Bridge Abutments 2 21 9 6 2268
Centre pier bridge 1 21 8.5 6 1071

Aqueduct Piers 1 11 11 6 726


RD: 115+069 Cut off walls 2 12 5 4 480
Causeway bed 1 26 19 3.5 1729

Cut off walls 2 12 13 4 1248


RD: 120+136 Bridge Abutments 2 21 9 6 2268
Centre pier bridge 1 21 8.5 6 1071

Aqueduct Piers 1 11 11 6 726


RD: 129+808
Cut off walls 2 11.75 5 4 470

Aqueduct Piers 10 11 11 6 7260


RD: 136+732
Cut off walls 2 11.6 5 5 580

Aqueduct Piers 2 11 11 6 1452


Cut off walls 2 11.6 5 4 464
RD: 140+370
Bridge Abutments 2 21 9 6 2268
Construction of Siran Right Bank Canal
District Mansehra
Aqueducts
RD: 140+370
BOQ Item No. Description

Centre pier bridge 1 21 8.5 6 1071

Aqueduct Piers 19 11 11 6 13794


RD: 140+914
Cut off walls 2 11.6 5 5 580

Aqueduct Piers 18 11 11 6 13068


RD: 142+727
Cut off walls 2 11.6 5 5 580

Cut off walls 2 11.5 5 4 460

Causeway Toe wall 1 30 8.5 3.5 892.5


RD: 147+515 Causeway Cut off wall 2 19 2 4 304
RCC Brest wall 1 48 10 12 5760
Ramp cut off walls 2 19 2 4 304

RD: 148+097 Cut off walls 2 11.5 5 4 460

Aqueduct Piers 1 11 11 6 726


RD: 151+796 Cut off walls 2 11.3 5 4 452
Causeway bed 1 26 19 3.5 1729

RD: 153+559 Cut off walls 2 11.3 13 4 1175.2

Aqueduct Piers 6 11 11 6 4356


Cut off walls 2 11 6 5 660
Causeway Toe wall 1 30 8.5 3.5 892.5
RD: 158+683
Causeway Cut off wall 2 19 2 4 304
RCC Brest wall 1 48 10 12 5760
Ramp cut off walls 2 19 2 4 304

Aqueduct Piers 2 11 11 6 1452


RD: 161+089
Cut off walls 2 11 5 4 440

Cut off walls 2 10.7 13 4 1112.8


RD: 163+586
Causeway bed 1 23 12 2 552

Aqueduct Piers 1 11 11 6 726


RD: 170+890
Cut off walls 2 10.7 5 4 428

Aqueduct Piers 20 11 11 6 14520


RD: 172+991
Cut off walls 2 10.3 5 5 515

Aqueduct Piers 7 11 11 6 5082


RD: 178+154
Cut off walls 2 10 5 5 500

Aqueduct Piers 2 11 11 6 1452


RD: 184+743
Cut off walls 2 8.7 6 5 522

Total 345037.748 Cft


Take 90% as excavation in common material 310533.97 Cft
OR 8793.33 Cum

B-2 Structural Excavation in Rock Material requiring blasting

Take 10% of excavation quantity of item B-1 31053.4


OR 879.33 Cum

B-3 Plain Cement Concrete including placing, compacting, finishing & curing (Ratio 1:4:8)
RD Description No. Length Width Depth Volume (cft)
(ft) (ft) (ft)

Rcc Abutment 2 7.25 11.09 0.25 40.20125


RD: 7+093
Construction of Siran Right Bank Canal
District Mansehra
Aqueducts

BOQ Item No. Description


RD: 7+093
Pcc abutments 8 6.5 11.09 0.25 144.17

RD: 7+686 Rcc Abutment 6 12.5 14.5 0.25 271.88

RD: 8+089 Rcc Abutment 17 12.5 14.5 0.25 770.31

RD: 10+03520 Aqueduct Piers 3 11.93 12.41 0.25 111.04

RD: 11+388 Aqueduct Piers 18 10.5 10.5 0.25 496.125

RD: 27+275 Aqueduct Piers 5 12.5 14.5 0.25 226.5625

RD: 30+600 Abutments 7 8.5 8.5 0.25 126.4375

RD: 31+500 Rcc canal 1 150 8.44 0.25 316.5

Aqueduct Piers 6 8.5 8.5 0.25 108.375

RD: 32+275 Causeway ramps u/s 1 55 14 0.25 192.5

Causeway ramps d/s 1 75 14 0.25 262.5

RD: 32+500 Bridge Abutments 2 17.5 21.35 0.25 186.8125

Wing Wall 4 18 12.5 0.25 225

Aqueduct Piers 2 17.5 21.35 0.25 186.8125

RD: 33+020 Bridge Abutments 2 17.5 20.16 0.25 176.4

Wing Wall 4 18 12.5 0.25 225

RD: 38+875 Abutments 2 8.85 12 0.25 53.1

Abutment 2 8.5 8.5 0.25 36.125

RD: 41+300 Abutment 2 18 8.5 0.25 76.5

Bridge centre pier 1 18 5.5 0.25 24.75

RD: 43+825 Aqueduct Piers 20 12.5 14.5 0.25 906.25

Aqueduct abutment 2 8.5 8.5 0.25 36.125

RD: 44+300 Bridge Abutments 2 18 6.5 0.25 58.5

Bridge centre pier 1 18 5.5 0.25 24.75

Aqueduct Pier 2 8.5 8.5 0.25 36.125


RD: 45+785
Bridge centre pier 1 18 5.5 0.25 24.75

RD: 47+500 Aqueduct Pier 2 8.5 8.5 0.25 36.125

Aqueduct Pier 2 8.5 8.5 0.25 36.125

Causeway 1 30 20 0.25 150


RD: 64+475
U/S Aqueduct 1 30 14.75 0.25 110.625

Below 5ft wide floor 1 30 4 0.25 30

RD: 85+175 Aqueduct Pier 6 12.5 14.5 0.25 271.875


Construction of Siran Right Bank Canal
District Mansehra
Aqueducts

BOQ Item No. Description

Aqueduct Pier 1 8.5 8.5 0.25 18.0625

RD: 98+000 Bridge Abutments 2 18 6.5 0.25 58.5

Bridge centre pier 1 18 5.5 0.25 24.75

RD: 110+030 Aqueduct Pier 7 8.5 8.5 0.25 126.4375

Aqueduct Pier 1 8.5 8.5 0.25 18.0625

RD: 114+250 Bridge Abutments 2 18 6.5 0.25 58.5

Bridge centre pier 1 18 5.5 0.25 24.75

RD: 115+069 Aqueduct Pier 1 8.5 8.5 0.25 18.0625

Bridge Abutments 2 18 6.5 0.25 58.5


RD: 120+136
Bridge centre pier 1 18 5.5 0.25 24.75

RD: 129+808 Aqueduct Pier 1 8.5 8.5 0.25 18.0625

RD: 136+732 Aqueduct Pier 17 8.5 8.5 0.25 307.0625

Aqueduct Pier 2 8.5 8.5 0.25 36.125

RD: 140+370 Bridge Abutments 2 18 6.5 0.25 58.5

Bridge centre pier 1 18 5.5 0.25 24.75

RD: 140+914 Aqueduct Pier 19 8.5 8.5 0.25 343.1875

RD: 142+727 Aqueduct Pier 18 8.5 8.5 0.25 325.125

RD: 147+515 Causeway 1 30 20 0.25 150

RD: 151+796 Aqueduct Pier 1 8.5 8.5 0.25 18.0625

Aqueduct Pier 16 8.5 8.5 0.25 289


RD: 158+683
Causeway 1 30 20 0.25 150

RD: 161+089 Aqueduct Pier 10 8.5 8.5 0.25 180.625

Causeway ramps u/s 1 55 14 0.25 192.5


RD: 163+586
Causeway ramps d/s 1 75 14 0.25 262.5

RD: 170+890 Aqueduct Pier 1 8.5 8.5 0.25 18.0625

RD: 172+991 Aqueduct Pier 20 8.5 8.5 0.25 361.25

RD: 178+154 Aqueduct Pier 7 8.5 8.5 0.25 126.4375

RD: 184+743 Aqueduct Pier 2 8.5 8.5 0.25 36.125

Total Quantity (Cft) 9306.09723

Total Quantity (CuM) 263.52

B-4 Plain Cement Concrete including placing, compacting, finishing & curing (Ratio 1:2:4)

RD Description No. Length Width Depth Volume (cft)


(ft) (ft) (ft)

Causeway ramps u/s 1 55 14 0.75 577.5


RD: 32+275
Causeway ramps d/s 1 75 14 0.75 787.5

RD: 47+500 Causeway ramps 2 15 14 0.75 315

RD: 64+350 Causeway ramps 2 33 19 0.75 940.5

Causeway 1 30 21.17 0.75 476.325


RD: 85+175
Causeway ramps 2 70 20 0.75 2100
Construction of Siran Right Bank Canal
District Mansehra
Aqueducts

BOQ Item No. Description

Causeway 1 30 21.17 0.75 476.325


RD: 110+030
Causeway ramps 2 70 20 0.75 2100

Causeway 1 30 21.17 0.75 476.325


RD: 129+808
Causeway ramps 2 70 20 0.75 2100

Causeway 1 30 21.17 0.75 476.325


RD: 136+732
Causeway ramps 2 70 20 0.75 2100

Causeway 1 30 21.17 0.75 476.325


RD: 140+914
Causeway ramps 2 70 20 0.75 2100

Causeway 1 30 21.17 0.75 476.325


RD: 142+727
Causeway ramps 2 70 20 0.75 2100

RD: 147+515 Causeway ramps 2 33 19 0.75 940.5

RD: 151+796 Causeway ramps 2 15 14 0.75 315

RD: 158+638 Causeway ramps 2 33 19 0.75 940.5

Causeway 1 30 21.17 0.75 476.325


RD: 161+089
Causeway ramps 2 70 20 0.75 2100

Causeway ramps u/s 1 55 14 0.75 577.5


RD: 163+586
Causeway ramps d/s 1 75 14 0.75 787.5

Causeway ramps 1 175 14 0.75 1837.5

Total Quantity (Cft) 26053.275

Total Quantity (CuM) 737.75

B-5 RCC in roof slab, beam, column & other structural members, insitu or precast. Type C (1:2:4)
RD Description No. Length Width Depth Volume (cft)
(ft) (ft) (ft)

RD: 7+093
Abutments 2 9.63 3.38 1 65.0988

Abutments Footing 6.000 11.960 11.110 1.750 1395.1938


RD:7+686 Abutments 6 10 6.000 2.00 693.36
Parapet wall 2 42 1 0.5 31.5

Pedestal Footing 2 10 10 2 300


Piers Footing 15 12 14 1.5 3780
RD: 8+089
Pier Columns 17 7.069 sft 17 2042.941
Transom Beam 17 3 8.560 sft 436.56

Piers Footing 1 8 8 1.5 96


Pier Columns 1 7.069 sft 12.78 90.34182
RD: 10+035 Transom Beam 1 3 17.874 sft 53.622
Bridge slab 1 72 7.417 0.75 400.518
Parapet wall 2 72 1 0.5 54

Pedestal Footing 2 10 10 1.5 300


Pedestal 2 2 4 6.0 96
Piers Footing 2 10 18 2 720
Piers Footing 3 12 20 2 1440
RD: 11+740 Piers Footing 10 12 12 2 2880
Pier Columns 15 7.069 sft 26.5 2809.9275
Pedestal Transom Beam 2 3 10.760 sft 64.56
Transom Beam 2 3 9.310 sft 55.86
Transom Beam 15 3 8.560 sft 385.2

Piers Footing 5 8 8 1.5 480


RD: 27+275 Pier Columns 5 7.069 sft 16.51 583.54595
Transom Beam 5 3 8.560 sft 128.4

RD: 30+600 Abutments Footing 7.000 11.960 11.110 1.750 1627.7261


Abutments 6 10 6.000 2.00 693.36
Construction of Siran Right Bank Canal
District Mansehra
Aqueducts

BOQ Item No. Description

0
RD: 31+500 0 Plum Abutments
0

Pedestal 2 2 4 6.0 96
Piers Footing 4 12 14 1.5 1008
Pier Columns 2 7.069 sft 30 424.14
RD: 32+275 Transom Beam 2 3 8.560 sft 51.36

Abutments Footing 2.00 21.25 14.50 3.50 2156.88


Abutments 2.00 21.35 3.00 19.00 2433.90

Aqueduct Wingwal Footing 2.00 20.00 12.00 2.50 1200.00

Aqueduct Wingwal Footing 2.00 18.00 12.00 2.50 1080.00

Wing Walls 4.00 18.00 2.37 19.00 3235.32


RD: 32+500 Bridge Abutment top 2.00 12.75 6.800 sft 173.40
Aqueduct Abutment top 2.00 12.75 5.440 sft 138.72
None-Shrink concrete block 4.00 1.75 1.50 0.75 7.88
Retaining Block 2.00 4.25 2.50 1.00 21.25
Girder With parapet wall and Slab 1.00 44.00 24.690 sft 1086.36
Diaphragm 5.00 5.16 0.75 2.50 48.38
Aproch Slab 2 9.840 sft 12.75 250.92

Piers Footing 2 17 20.58 3.5 2449.02


Pier Columns Aqueduct 2 7.069 sft 39 551.382
Pier Columns Bridge 2 34.285 sft 39 2674.230
Aqueduct Abtment Footing 2 2 21 15 3.5 2156.875
Aqueduct Wingwal Footing D/SL/s 45* 1 20 12 2.5 600
Aqueduct Wingwal Footing D/S R/s 90*
1 13 5 2.5 162.5
Aqueduct Abtment Footing 1&2
2 21 13 3 1599.75

Aqueduct D/S Wing Wall Footing R/S 1


1 12 5 2.5 154.125
Aqueduct D/S Wing Wall Footing R/S 2
1 7 4 2.5 69.1
Aqueduct D/S Wing Wall Footing L/S
1 13 8 2.5 251.875
Aqueduct D/S Wing Wall Footing L/S
1 2 7 2.5 24.375
Aqueduct D/S Wing Wall Footing R/S
1 9 12 2.5 277.5
Extand Portion
Aqueduct D/S Wing Wall Footing L/S
1 10 12 2.5 295.2
Extand Portion
Aqueduct U/S Wing Wall Footing R/S
1 89.000 sft 2.500 sft 222.500
90* AB 01 33+020
Aqueduct U/S Wing Wall Footing R/S
90* Extand AB 0133+020 1 6 12 3 180

Aqueduct U/S Wing Wall Footing L/S


55* 33+020 1 108.000 sft 2.50 270.000
RD: 33+020
Aqueduct U/S Wing Wall Footing L/S
1 11.83 11.75 2.50 347.51
55* Extand AB 0133+020

Aqueduct Portion Abtment 01 U/S 1 8.60 2.50 12.00 258.00

Aqueduct Bridge Portion Abtment 01


1 12.73 12.73 8.00 1296.42
U/S

Wing Waal AB 01 L/S 55* 1 17.50 1.50 15.00 393.75

Wing Waal AB 01 R/S 90* 1 18.33 1.50 15.00 412.43

Wing Waal AB 02 L/S 1st Step 30* 1 12.65 1.50 12.84 243.64

Wing Waal AB 02 L/S 2nd Step 30* 1 5.35 1.50 10.34 82.98

Wing Waal AB 02 R/S 1st Step 90* 1 12.33 1.50 12.84 237.48
Wing Waal AB 02 R/S 2nd Step 90* 1 5.67 1.50 10.34 87.94
Bridge Abutment top 1 5.770 sft 12.01 69.30
Aqueduct Abutment top 1 4.330 sft 12.01 52.00
None-Shrink concrete block 4 1.75 1.50 0.75 7.88
Retaining Block 4 4.25 2.50 1.00 42.50

Girder With parapet wall and Slab 1 135.00 5.770 sft 778.95

Diaphragm 15 5.08 0.75 2.50 142.88


Construction of Siran Right Bank Canal
District Mansehra
Aqueducts

BOQ Item No. Description

Aproch Slab 2 9.840 sft 12.08 237.7344

Abutment wall U/S 01 1 8.6 2 12 206.40


Abutment wall D/S 02 1 8.6 2 8 137.60

Abutments Footing 6.000 11.960 11.110 1.750 1395.1938


RD: 41+300 Abutments 6 10 6.000 2.00 693.36
Parapet wall 2 42 1 0.5 31.5

Pedestal Footing 2 10 10 1.5 300


Pedestal 2 2 4 6.0 96
Piers Footing 3 10 18 2 1080
Piers Footing 4 12 20 2 1920
Piers Footing 10 12 12 2 2880
RD: 43+940
Pier Columns 17 7.069 sft 33 3965.709
Pedestal Transom Beam 2 3 10.760 sft 64.56
Transom Beam 2 3 9.310 sft 55.86
Transom Beam 15 3 8.560 sft 385.2

Abutments Footing 2.000 14.530 6.520 3.510 665.043912


RD: 44+300
Abutments 2 10 21.000 2.00 808.92
Parapet wall 2 42 1 0.5 31.5

Piers Footing 1 8 8 1.5 96


Pier Columns 1 7.069 sft 16.69 117.98161
Transom Beam 1 3 17.499 sft 52.497
Bridge footing 1 18 5 1.5 135
RD: 45+600 Bridge Centre pier 1 18 1 15.19 273.42
Bridge Transom 1 18 2 1 36
Bridge Slab 1 44 18 1.25 990
Bridge Parapet 1 44 0.833 4.250 155.771
Bridge end beams 2 18 2 1 72

Piers Footing 2 8 8 1.5 192


Pier Columns 2 7.069 sft 16.1 227.6218
Transom Beam 2 3 17.499 sft 104.994
RD: 47+500
Causeway Bed 1 23 16 1 368
Causeway piers 3 16 1 8 384
Causeway slab 1 23 16 0.75 276

Piers Footing 2 8 8 1.5 192


Pier Columns 2 7.069 sft 10 141.38
Transom Beam 2 3 17.499 sft 104.994
Causeway 1 30 20 1 600
Wall on U/S causeway 1 30 1 6 180

RD: 64+350 B/W aqueduct piers 1 30 2 1 60


U/S Aqueduct pier 1 30 1.75 3.6 189
Sump well bed 1 30 10 1.0 300
Breast wall Sump well 1 30 1 12.0 360
Sump well U/S floor 1 30 5 1.0 150
Sump well end walls 2 20 1 12.0 474

Piers Footing 4 8 8 1.5 384


RD: 85+175 Pier Columns 4 7.069 sft 19.59 553.927
Transom Beam 4 3 17.199 sft 206.388

Piers Footing 1 8 8 1.5 96


Pier Columns 1 7.069 sft 17.76 125.545
Transom Beam 1 3 15.249 sft 45.747
Bridge footing 1 18 5 1.5 135
RD: 98+000 Bridge Centre pier 1 18 1 15.19 273.42
Bridge Transom 1 18 2 1 36
Bridge Slab 1 34 18 1 612
Bridge Parapet 1 34 0.833 4.250 120.3685
Bridge end beams 2 18 2 1 72

Piers Footing 3 8 8 1.5 288


RD: 110+030 Pier Columns 3 7.069 sft 73.51 1558.927
Transom Beam 3 3 15.249 sft 137.241

Piers Footing 1 8 8 1.5 96


Pier Columns 1 7.069 sft 13.9 98.259

RD: 114+250
Construction of Siran Right Bank Canal
District Mansehra
Aqueducts

BOQ Item No. Description

Transom Beam 1 3 15.249 sft 45.747


Bridge footing 1 18 5 1.5 135
RD: 114+250 Bridge Centre pier 1 18 1 15.19 273.42
Bridge Transom 1 18 2 1 36
Bridge Slab 1 34 18 1 612
Bridge Parapet 1 34 0.833 4.250 120.3685
Bridge end beams 2 18 2 1 72

Piers Footing 1 8 8 1.5 96


Pier Columns 1 7.069 sft 9.7 68.569
Transom Beam 1 3 15.249 sft 45.747
RD: 115+069
Causeway Bed 1 23 16 1 368
Causeway piers 3 16 1 8 384
Causeway slab 1 23 16 0.75 276

Bridge footing 1 18 5 1.5 135


Bridge Centre pier 1 18 1 15.19 273.42
Bridge Transom 1 18 2 1 36
RD: 120+736
Bridge Slab 1 34 18 1 612
Bridge Parapet 1 34 0.833 4.250 120.3685
Bridge end beams 2 18 2 1 72

Piers Footing 1 8 8 1.5 96


RD: 129+808 Pier Columns 1 7.069 sft 6.95 49.130
Transom Beam 1 3 14.874 sft 44.622

Piers Footing 10 8 8 1.5 960


RD: 136+732 Pier Columns 10 7.069 sft 37.23 2631.789
Transom Beam 10 3 14.649 sft 439.47

Piers Footing 2 8 8 1.5 192


Pier Columns 2 7.069 sft 21.98 310.753
RD: 140+370 Transom Beam 2 3 14.649 sft 87.894

Piers Footing 19 8 8 1.5 1824


RD: 140+914 Pier Columns 19 7.069 sft 16.42 2205.387
Transom Beam 19 3 14.649 sft 834.993

Piers Footing 18 8 8 1.5 1728


RD: 142+727 Pier Columns 18 7.069 sft 42.88 5456.137
Transom Beam 18 3 14.649 sft 791.046

RD: 147+515 Causeway 1 30 20 1 600

Piers Footing 1 8 8 1.5 96


Pier Columns 1 7.069 sft 13.25 93.664
Transom Beam 1 3 14.199 sft 42.597
RD: 151+796
Causeway Bed 1 23 16 1 368
Causeway piers 3 16 1 8 384
Causeway slab 1 23 16 0.75 276

Bridge slab 1 42 7.417 0.75 233.6355


RD: 153+559
Parapet wall 2 42 1 0.5 31.5

Piers Footing 6 8 8 1.5 576


Pier Columns 6 7.069 sft 12.3 521.692
RD: 158+683
Transom Beam 6 3 13.749 sft 247.482
Causeway 1 30 20 1 600

Piers Footing 2 8 8 1.5 192


RD: 161+089 Pier Columns 2 7.069 sft 22.87 323.336
Transom Beam 2 3 13.749 sft 82.494

Causeway Bed 1 23 16 1 368


RD: 163+586 Causeway piers 3 16 1 10 480
Causeway slab 1 23 16 0.75 276

Piers Footing 1 8 8 1.5 96


RD: 170+890 Pier Columns 1 7.069 sft 6.9 48.776
Transom Beam 1 3 13.299 sft 39.897

Piers Footing 20 8 8 1.5 1920


RD: 172+991 Pier Columns 20 7.069 sft 32.65 4616.057
Transom Beam 20 3 12.699 sft 761.94
Construction of Siran Right Bank Canal
District Mansehra
Aqueducts

BOQ Item No. Description

Piers Footing 7 8 8 1.5 672


RD: 178+154 Pier Columns 7 7.069 sft 29.89 1479.047
Transom Beam 7 3 12.249 sft 257.229

Piers Footing 2 8 8 1.5 192


RD: 184+743 Pier Columns 2 7.069 sft 15.83 223.805
Transom Beam 2 3 10.299 sft 61.794

Total Quantity (Cft) 115128.151


Total Quantity (M3) 3260.06

Reinforced cement concrete work as in dams, spillways, weirs, barrages, cross drainage works and other hydraulic
structures using crushed stone aggregate(screening & washing) and coarse sand i/c costof all labour and material and all
B-6 kinds of form works, moulds, shuttering lifting/pumping, curing, rendering and finishing the exposed surface, cast in
situ/precast excluding the cost of steel reinforcement and labour for bending binding also excluding cost of additives which
have to be paid separately. Type C (1:2:4)

RD Description No. Length Width Depth Volume (cft)


(ft) (ft) (ft)

Trough bed 1 253 7.94 0.67 1345.9094

RD: 7+093 Trough side walls 2 253 0.67 4.92 1667.9784

Chamfer 1 253 0.35 0.35 30.9925

Trough bed 1 190 9.42 1.00 1789.8


RD:7+686
Trough side walls 2 190 0.833 4.75 1503.565

Trough bed 1 740 9.42 1.00 6970.8


RD: 8+089
Trough side walls 2 740 0.833 4.75 5855.99

Trough bed 1 72 9.42 1.00 678.24


RD: 10+035
Trough side walls 2 72 0.833 4.75 569.772

Trough bed 1 610 9.42 1 5746.2


RD: 11+388
Trough side walls 2 610 0.833 4.75 4827.235

Trough bed 1 155 7.94 0.67 824.569


RD: 27+275
Trough side walls 2 155 0.833 4.40 1136.212

1 200 8.42 0.75 1263


RD: 30+600
2 200 0.833 4.40 1466.08

Trough bed 1 225 7.94 0.67 1196.955


RD: 31+500
Trough side walls 2 225 0.833 4.57 1713.0645

Trough bed 1 50 8.27 0.75 310.125


RD: 32+275
Trough side walls 2 50 0.833 4.4 366.52

Trough bed 1 134 8.5 1.00 1139


RD: 32+500
Trough side walls 2 134 1.00 4.40 1179.2

Trough bed 1 300 8.5 1.00 2550


RD: 33+020
Trough side walls 2 300 1.00 4.40 2640

Trough bed 1 70 8.5 1.00 595


RD: 38+875
Trough side walls 2 70 1.00 4.40 616

Trough bed 1 109 8.27 0.75 676.0725


RD: 41+300
Trough side walls 2 109 0.833 4.31 782.67014

Trough bed 1 676 8.27 0.75 4192.89


RD: 43+825
Trough side walls 2 676 0.833 4.31 4853.99096
Construction of Siran Right Bank Canal
District Mansehra
Aqueducts

BOQ Item No. Description

Trough bed 1 74 8.17 0.75 453.435


RD: 44+300
Trough side walls 2 74 0.833 4.28 527.65552

Trough bed 1 90 8.17 0.75 551.475


RD: 45+785
Trough side walls 2 90 0.833 4.28 641.7432

Trough bed 1 48 8.17 0.75 294.12


RD: 47+500
Trough side walls 2 48 0.833 4.28 342.26304

Trough bed 1 68 8.17 0.75 416.67


RD: 64+475
Trough side walls 2 68 0.833 4.28 484.87264

Trough bed 1 169.23 7.97 0.75 1011.57233


RD: 85+175
Trough side walls 2 169.23 0.833 3.96 1116.47123

Trough bed 1 77 6.67 0.75 385.1925


RD: 98+000
Trough side walls 2 77 0.833 3.79 486.18878

Trough bed 1 197 6.67 0.75 985.4925


RD: 110+030
Trough side walls 2 197 0.833 3.55 1165.1171

Trough bed 1 99 6.67 0.75 495.2475


RD: 114+250
Trough side walls 2 99 0.833 3.55 585.5157

Trough bed 1 77 6.67 0.75 385.1925


RD: 115+069
Trough side walls 2 77 0.833 3.55 455.4011

Trough bed 1 58 6.67 0.75 290.145


RD: 120+136
Trough side walls 2 58 0.833 3.55 343.0294

Trough bed 1 96 6.42 0.75 462.24


RD: 129+808
Trough side walls 2 96 0.833 3.51 561.37536

Trough bed 1 518 6.27 0.75 2435.895


RD: 136+732
Trough side walls 2 518 0.833 3.47 2994.56836

Trough bed 1 120 6.27 0.75 564.3


RD: 140+370
Trough side walls 2 120 0.833 3.47 693.7224

Trough bed 1 991 6.27 0.75 4660.1775


RD: 140+914
Trough side walls 2 991 0.833 3.47 5728.99082

Trough bed 1 1002 6.27 0.75 4711.905


RD: 142+727
Trough side walls 2 1002 0.833 3.47 5792.58204

Trough bed 1 66 6.17 0.75 305.415


RD: 147+515
Trough side walls 2 66 0.833 3.37 370.55172

Trough bed 1 66 6.17 0.75 305.415


RD: 148+097
Trough side walls 2 66 0.833 3.37 370.55172

Trough bed 1 125 5.97 0.75 559.6875


RD: 151+796
Trough side walls 2 125 0.833 3.3 687.225

Trough bed 1 91 5.97 0.75 407.4525


RD: 153+559
Trough side walls 2 91 0.833 3.3 500.2998
Construction of Siran Right Bank Canal
District Mansehra
Aqueducts

BOQ Item No. Description

Trough bed 1 494 5.67 0.75 2100.735


RD: 158+683
Trough side walls 2 494 0.833 3.26 2682.99304

Trough bed 1 300 5.67 0.75 1275.75


RD: 161+089
Trough side walls 2 300 0.833 3.26 1629.348

Trough bed 1 45 5.37 0.75 181.2375


RD: 163+586
Trough side walls 2 45 0.833 3.2 239.904

Trough bed 1 110 5.37 0.75 443.025


RD: 170+890
Trough side walls 2 110 0.833 3.2 586.432

Trough bed 1 1048 4.97 0.75 3906.42


RD: 172+991
Trough side walls 2 1048 0.833 3.18 5552.17824

Trough bed 1 437 4.67 0.75 1530.5925


RD: 178+154
Trough side walls 2 437 0.833 3.1 2256.9302

Trough bed 1 162 3.37 0.75 409.455


RD: 184+743
Trough side walls 2 162 0.833 2.5 674.73

Total Quantity (Cft) 125486.717

Total Quantity (Cum) 3553.38

B-7 Extra labour for laying concrete (plain or reinforced) From 20' upto 40' height

Concrete Qty Item (B-4) + (B-5) = 115128.15 + 125486.7 = 240614.87 Cft

Taking 15% of item B-4 & B-5 = 15% x 240614.87 = 36092.23 Cft

OR 1022.02 Cum

B-8 Extra labour for laying concrete (plain or reinforced) For every extra 10' height (upto 60' height)

Concrete Qty Item (B-4) + (B-5) = 115128.15 + 125486.7 = 240614.87 Cft

Taking 10% of item B-4 & B-5 = 10% x 240614.87 = 24061.49 Cft

OR 681.34 Cum

B-9 Supply & fabricate M.S. reinforcement for cement concrete (Hot rolled deformed bars Grade 40)
Taking 2.00% of RCC as steel quantity

RCC Quantity = 115128.1513 + 125486.717 =240614.87 Cft

Steel Quantity = 0.02 x 240614.87 x 490 = 2358025.71 lbs


OR 1069.88 Tonnes

B-10 Supplying and Fixing PVC Water Stopper 8" wide 3/8" thick
RD Description No. Length Total Length
(ft) (ft)

Along length 2 253 506.000 7+540


RD: 7+093
Transverse 10 17.423 174.233

Along length 2 190 380.000


8+150
RD: 8+089
Transverse 6 17.083 102.500

Along length 2 714 1428.000


8+089
Transverse 19 17.083 324.583
8+565

Along length 2 72 144.000 10+420


RD: 10+035
Transverse 3 16.583 49.750

Along length 2 610 1220.000 11+740


RD: 11+388
Transverse 17 17.083 290.417
Construction of Siran Right Bank Canal
District Mansehra
Aqueducts

BOQ Item No. Description

Along length 2 155 310.000


RD: 27+275
Transverse 5 16.383 81.917
Construction of Siran Right Bank Canal
District Mansehra
Aqueducts

BOQ Item No. Description

Along length 2 200 400.000


RD: 30+650
Transverse 7 16.383 114.683

Along length 2 225 450.000


RD: 31+500
Transverse 12 16.583 199.000

Along length 2 50 100.000


RD: 32+275
Transverse 3 16.053 48.160

Along length 2 125 250.000


RD: 32+500
Transverse 3 16.053 48.160

Along length 2 300 600.000


RD: 33+020
Transverse 2 16.300 32.600

Along length 2 70 140.000


RD: 38+875
Transverse 3 16.300 48.900

Along length 2 48 96.000


RD: 41+300
Transverse 2 16.053 32.107

Along length 2 676 1352.000


RD: 43+940
Transverse 16 16.053 256.853

Along length 2 48 96.000


RD: 44+300
Transverse 2 15.893 31.787

Along length 2 90 180.000


RD: 45+600
Transverse 2 15.893 31.787

Along length 2 48 96.000


RD: 47+500
Transverse 2 15.893 31.787

Along length 2 68 136.000


RD: 64+350
Transverse 4 15.893 63.573

Along length 2 169.23 338.460


RD: 85+175
Transverse 6 15.053 90.320

Along length 2 77 154.000


RD: 98+000
Transverse 4 13.413 53.653

Along length 2 197 394.000


RD: 110+030
Transverse 5 12.933 64.667

Along length 2 99 198.000


RD: 114+250
Transverse 3 12.933 38.800

Along length 2 77 154.000


RD: 115+069
Transverse 3 12.933 38.800

Along length 2 58 116.000


RD: 120+136
Transverse 2 12.933 25.867

Along length 2 96 192.000


RD: 129+808
Transverse 3 12.603 37.810

Along length 2 518 1036.000


RD: 136+732
Transverse 12 12.373 148.480

Along length 2 120 240.000


RD: 140+370
Transverse 4 12.373 49.493

Along length 2 991 1982.000


RD: 140+370
Construction of Siran Right Bank Canal
District Mansehra
Aqueducts

BOQ Item No. Description


RD: 140+370
Transverse 21 12.373 259.840

Along length 2 1002 2004.000


RD: 142+727
Transverse 21 12.373 259.840

Along length 2 66 132.000


RD: 147+515
Transverse 21 12.073 253.540

Along length 2 66 132.000


RD: 148+097
Transverse 21 12.073 253.540

Along length 2 125 250.000


RD: 151+796
Transverse 3 11.733 35.200

Along length 2 91 182.000


RD: 153+559
Transverse 3 11.733 35.200

Along length 2 494 988.000


RD: 158+683
Transverse 8 11.353 90.827

Along length 2 300 600.000


RD: 161+089
Transverse 4 11.353 45.413

Along length 2 45 90.000


RD: 163+586
Transverse 2 10.933 21.867

Along length 2 110 220.000


RD: 170+890
Transverse 3 10.933 32.800

Along length 2 1048 2096.000


RD: 172+991
Transverse 22 10.493 230.853

Along length 2 437 874.000


RD: 178+154
Transverse 9 10.033 90.300

Along length 2 162 324.000


RD: 184+743
Transverse 9 7.533 67.800

Total Quantity (R.Ft) 24768.167

Total Quantity (R.Meter) 7548.97

B-11 Structural backfill using Common Material available at site

Total Excavation Quantity as per Item B-1 = 345037.748 Cft

Taking 60% as structural backfill = 60% x 345037.748 = 207022.649 Cft

OR 5862.22 Cum

B-12 PCC 1:3:6 in mass concrete less formwork using 40% boulders

RD Description No. Length Width Depth Volume (cft)


(ft) (ft) (ft)

Aqueduct cut off wall 2 12.25 2 4 196


Cut off wall Nullah 2 20 2 5 400
Bridge abutments
Step 1 2 6.5 10.6 1 137.8
Step 2 1 4 8.6 2.52 86.688
Step 3 1 4 8.6 4.55 156.52
Step 4 1 4 8.6 4.55 156.52
Step 5 1 4 8.6 4.55 156.52
RD: 7+093
Step 6 1 4 8.6 7.08 243.552
Step 7 1 4 8.6 6.13 210.872
Step 8 1 4 8.6 5.18 178.192
Step 9 1 4 8.6 4.39 151.016
Step 10 1 4 8.6 3.61 124.184
Footings 8 6.5 10.6 1 551.2
Construction of Siran Right Bank Canal
District Mansehra
Aqueducts

BOQ Item No. Description

Aqueduct cut off walls 2 12.25 10 4 980


RD: 7+686
Cut off wall Nullah 2 22 2 5 440

RD: 8+089 Aqueduct cut off walls 2 12.25 10 4 980

RD: 11+388 Aqueduct U/S cut off walls 1 12.25 2 4 98


Aqueduct D/S cut off walls 1 12.25 12 3 441

RD: 27+275 Trugh 2 20 10 20 8000

RD:30+600 Trugh 2 14 3 8 672

RD: 31+500 Aqueduct cut off walls 2 10.6 10 4 848

Culvert U/S wall step1 1.00 6.50 4.50 2.00 58.50

Culvert U/S wall step2 1.00 6.50 3.50 2.00 45.50

Culvert U/S wall step3 1.00 6.50 2.50 2.00 32.50


Culvert D/S wall step1 1.00 7.50 4.50 2.00 67.50
Culvert D/S wall step2 1.00 7.50 3.50 2.00 52.50
Culvert D/S wall step3 1.00 7.50 2.50 1.75 32.81

W 1 Culvert U/S step1 1.00 23.00 5.50 1.50 189.75

W 1 Culvert U/S step2 1.00 23.00 4.50 1.50 155.25

W 1Culvert U/S step3 1.00 23.00 3.50 2.00 161.00

W 1 Culvert U/S step4 1.00 23.00 2.50 2.00 115.00

W 2 Culvert Portion Step1 1.00 6.00 5.50 1.50 49.50

W 2 Culvert Portion Step2 1.00 6.00 4.50 1.50 40.50

W 2 Culvert Portion Step3 1.00 6.00 3.50 1.83 38.43

W 2 Culvert Portion Step4 1.00 6.00 2.50 1.75 26.25


W2&W3 Step1 1.00 78.00 5.50 1.50 643.50
W2&W3 Step2 1.00 78.00 4.50 1.50 526.50
W2&W3 Step3 1.00 78.00 3.50 2.00 546.00
W2&W3 Step4 1.00 78.00 2.50 2.00 390.00
W2&W3 Step5 1.00 78.00 1.50 1.25 146.25
W4 Step 1 1.00 27.00 3.50 1.75 165.38
W4 Step 2 1.00 27.00 2.50 2.00 135.00
W4 Step 3 1.00 27.00 1.50 0.67 27.14

Aqueduct cut off walls 2 12.25 10 4 980


RD: 32+275 Below causeway 1 23 16 1.25 460
Cut off wall Nullah 2 23 2 5 460

Aqueduct cut off walls 2 10.6 2 4 169.6


Bridge abutments
Step 1 2 18 8 3 864
Step 2 2 18 7 2 504
RD: 32+500 Step 3 2 18 6 2 432
Step 4 2 18 5 2 360
Step 5 2 18 4 2 288
Step 6 2 18 3 3 324
Step 7 2 18 2 2 144

Aqueduct cut off walls 2 11.75 2 4 188


Bridge abutments
Step 1 2 18 8 3 864
Step 2 2 18 7 2 504
RD: 38+875 Step 3 2 18 6 2 432
Step 4 2 18 5 2 360
Step 5 2 18 4 2 288
Step 6 2 18 3 3 324
Step 7 2 18 2 2 144

Bridge abutments
Step 1 2 18 6 3 648
Step 2 2 18 5 2 360
RD: 41+300
Construction of Siran Right Bank Canal
District Mansehra
Aqueducts

BOQ Item No. Description


RD: 41+300
Step 3 2 18 4 2 288
Step 4 2 18 3 2 216
Step 5 2 18 2 2 144

RD: 43+250 Aqueduct cut off walls 2 11.75 2 5 235

Bridge abutments

Step 1 2 18 6 3 648
Step 2 2 18 5 2 360
RD: 44+300
Step 3 2 18 4 2 288
Step 4 2 18 3 2 216
Step 5 2 18 2 2 144

Aqueduct cut off walls 2 11.75 2 4 188


Bridge abutments
Step 1 2 18 9 3 972
Step 2 2 18 8 2 576
RD: 45+600 Step 3 2 18 7 2 504
Step 4 2 18 6 2 432
Step 5 2 18 5 2 360
Step 6 2 18 4 3 432
Step 7 2 18 3 2 216
Step 8 2 18 2 2 144

Aqueduct cut off wall U/S 1 11.75 4 3 141


RD: 47+500 Aqueduct cut off walls D/S 1 11.75 6 3 211.5
Below causeway 1 23 16 2 736

Aqueduct cut off walls 2 11.75 2 2.33 109.51


Crest sump well 1 30 2 3.6 216
Cway Toe wall step 1 1 30 5 2 300
Cway Toe wall step 2 1 30 4 2 240
RD: 64+350 Cway Toe wall step 3 1 30 3 2 180
Cway Toe wall step 4 1 30 2 2 120
Causeway end walls 2 19 2 4 304
Cway ramp end walls 2 19 2 4 304
Cway ramps 2 31 19 1.5 1767

Causeway 1 30 21.17 1.5 952.65


RD: 85+175 Causeway Ramps 2 70 20 1.5 4200
Ramp end walls 2 20 2 4 320

Aqueduct cut off walls 2 10 2 4 160


Bridge abutments
Step 1 2 18 6 3 648
RD: 98+000 Step 2 2 18 5 2 360
Step 3 2 18 4 2 288
Step 4 2 18 3 2 216
Step 5 2 18 2 2 144

Aqueduct cut off walls 2 10 3 5 300


Causeway 1 30 21.17 1.5 952.65
RD: 110+030
Causeway Ramps 2 70 20 1.5 4200
Ramp end walls 2 20 2 4 320

Aqueduct cut off walls 2 9 2 4 144


Bridge abutments
Step 1 2 18 6 3 648
RD: 114+250 Step 2 2 18 5 2 360
Step 3 2 18 4 2 288
Step 4 2 18 3 2 216
Step 5 2 18 2 2 144

Aqueduct cut off walls 2 9 2 4 144


RD: 115+069
Construction of Siran Right Bank Canal
District Mansehra
Aqueducts

BOQ Item No. Description


RD: 115+069
Below causeway 1 23 16 2 736

Aqueduct cut off walls 2 9 10 5 900

Bridge abutments

Step 1 2 18 6 3 648
RD: 120+136 Step 2 2 18 5 2 360
Step 3 2 18 4 2 288
Step 4 2 18 3 2 216
Step 5 2 18 2 2 144

Aqueduct cut off walls 2 8.75 2 4 140


Causeway 1 30 21.17 1.5 952.65
RD: 129+808
Causeway Ramps 2 70 20 1.5 4200
Ramp end walls 2 20 2 4 320

Aqueduct cut off walls 2 8.6 2 5 172


Causeway 1 30 21.17 1.5 952.65
RD: 136+732
Causeway Ramps 2 70 20 1.5 4200
Ramp end walls 2 20 2 4 320

Aqueduct cut off walls 2 8.6 2 4 137.6

Bridge abutments

Step 1 2 18 6 3 648
RD: 140+370 Step 2 2 18 5 2 360
Step 3 2 18 4 2 288
Step 4 2 18 3 2 216
Step 5 2 18 2 2 144

Aqueduct cut off walls 2 8.6 2 5 172


Causeway 1 30 21.17 1.5 952.65
RD: 140+914
Causeway Ramps 2 70 20 1.5 4200
Ramp end walls 2 20 2 4 320

Aqueduct cut off walls 2 8.6 2 5 172


Causeway 1 30 21.17 1.5 952.65
RD: 142+727
Causeway Ramps 2 70 20 1.5 4200
Ramp end walls 2 20 2 4 320

Aqueduct cut off walls 2 8.5 10 4 680


Cway Toe wall step 1 1 30 5 2 300
Cway Toe wall step 2 1 30 4 2 240
Cway Toe wall step 3 1 30 3 2 180
RD: 147+515
Cway Toe wall step 4 1 30 2 2 120
Causeway end walls 2 19 2 4 304
Cway ramp end walls 2 19 2 4 304
Cway ramps 2 31 19 1.5 1767

RD: 148+097 Aqueduct cut off walls 2 8.5 10 4 680

Aqueduct cut off walls 2 8.3 2 4 132.8


RD: 151+796
Below causeway 1 23 16 2 736

RD: 153+559 Aqueduct cut off walls 2 8.3 10 4 664

Aqueduct cut off walls 2 8 3 5 240


Cway Toe wall step 1 1 30 5 2 300
Cway Toe wall step 2 1 30 4 2 240
Cway Toe wall step 3 1 30 3 2 180
RD: 158+683
Cway Toe wall step 4 1 30 2 2 120
Causeway end walls 2 19 2 4 304
Cway ramp end walls 2 19 2 4 304
Cway ramps 2 31 19 1.5 1767

Aqueduct cut off walls 2 8 2 4 128

RD: 161+089
Construction of Siran Right Bank Canal
District Mansehra
Aqueducts

BOQ Item No. Description

Causeway 1 30 21.17 1.5 952.65


RD: 161+089
Causeway Ramps 2 70 20 1.5 4200
Ramp end walls 2 20 2 4 320

Aqueduct cut off walls 2 7.7 10 4 616


RD: 163+586
Below causeway 1 23 16 1.25 460

RD: 170+890 Aqueduct cut off walls 2 7.7 2 4 123.2

RD: 172+991 Aqueduct cut off walls 2 7.3 2 5 146

RD: 178+154 Aqueduct cut off walls 2 7 2 5 140

RD: 184+743 Aqueduct cut off walls 2 5.7 3 5 171

Total Quantity (Cft) 98399.5765


Total Quantity (Cum) 2786.36

B-13 Erecting & removing formwork to concrete in any shape / position (Vertical)

RD Description No. Length Depth Volume (sft)


(ft) (ft)

Aqueduct cut off walls 4 12.25 4 196


Sides 4 2 4 32
Cut off wall Nullah 4 20 5 400
Sides 4 2 5 40
Bridge abutments
Front & Back 4 18 17 1224
Sides Step 1 4 10.6 1 42.4
RD: 7+093
Sides Step 2 4 8.6 2.52 86.688
Sides Step 3 4 8.6 4.55 156.52
Sides Step 4 4 8.6 4.55 156.52
Sides Step 5 4 8.6 4.55 156.52
Sides Step 6 4 8.6 7.08 243.552
Sides Step 7 4 8.6 6.13 210.872
Sides Step 8 4 8.6 5.18 178.192
Sides Step 9 4 8.6 4.39 151.016
Sides Step 10 4 8.6 3.61 124.184

Aqueduct cut off walls 4 12.25 4 196


Sides 4 10 4 160
RD: 7+686
Cut off wall Nullah 4 22 5 440
Sides 4 2 5 40

Aqueduct cut off walls 4 12.25 4 196


RD: 8+089
Sides 4 10 4 160

Aqueduct cut off walls 4 12.25 4 196


Sides 4 10 4 160
RD: 10+035
Cut off wall Nullah 4 38 5 760
Sides 4 2 5 40

Aqueduct U/S cut off wall 2 12.25 4 98


Sides 2 2 4 16
RD: 11+388
Aqueduct D/S cut off wall 2 12.25 3 73.5
Sides 2 12 3 72

Trugh cut off walls 4 12.25 4 196


RD: 27+275
Sides 20 20 20 8000

Trugh 2 14 8 224
RD: 30+600

Culvert U/S wall step1 2.00 6.50 2.00 26


RD: 31+500
Construction of Siran Right Bank Canal
District Mansehra
Aqueducts

BOQ Item No. Description


RD: 31+500
Culvert U/S wall step2 2.00 6.50 2.00 26

Culvert U/S wall step3 2.00 6.50 2.00 26


Culvert D/S wall step1 2.00 7.50 2.00 30
Culvert D/S wall step2 2.00 7.50 2.00 30
Culvert D/S wall step3 2.00 7.50 1.75 26.25

W 1 Culvert U/S step1 2.00 23.00 1.50 69

W 1 Culvert U/S step2 2.00 23.00 1.50 69

W 1Culvert U/S step3 2.00 23.00 2.00 92

W 1 Culvert U/S step4 2.00 23.00 2.00 92

W 2 Culvert Portion Step1 2.00 6.00 1.50 18

W 2 Culvert Portion Step2 2.00 6.00 1.50 18

W 2 Culvert Portion Step3 2.00 6.00 1.83 21.96

W 2 Culvert Portion Step4 2.00 6.00 1.75 21


W2&W3 Step1 2.00 78.00 1.50 234
W2&W3 Step2 2.00 78.00 1.50 234
W2&W3 Step3 2.00 78.00 2.00 312
W2&W3 Step4 2.00 78.00 2.00 312
W2&W3 Step5 2.00 78.00 1.25 195
W4 Step 1 2.00 27.00 1.75 94.5
W4 Step 2 2.00 27.00 2.00 108
W4 Step 3 2.00 27.00 0.67 36.18

Aqueduct cut off walls 4 12.25 4 196


Sides 4 10 4 160
Causeway front back 2 23 1.25 57.5
RD: 32+275
Causeway ends 2 16 1.25 40
Cut off wall Nullah 4 23 5 460
Sides 4 2 5 40

Aqueduct cut off walls 4 10.6 4 169.6


Sides 4 2 4 32
Bridge abutments
Front & Back 4 18 16 1152
Sides of Step 1 4 8 2 64
RD: 32+500 Sides of Step 2 4 7 3 84
Sides of Step 3 4 6 2 48
Sides of Step 4 4 5 2 40
Sides of Step 5 4 4 2 32
Sides of Step 6 4 3 2 24
Sides of Step 7 4 2 3 24

Aqueduct cut off walls 4 12.25 4 196


Sides 4 2 4 32
Bridge abutments
Front & Back 4 18 16 1152
Sides of Step 1 4 8 2 64
RD: 38+875 Sides of Step 2 4 7 3 84
Sides of Step 3 4 6 2 48
Sides of Step 4 4 5 2 40
Sides of Step 5 4 4 2 32
Sides of Step 6 4 3 2 24
Sides of Step 7 4 2 3 24

Bridge abutments
Front & Back 4 18 11 792
Sides of Step 1 4 6 3 72
RD: 41+300 Sides of Step 2 4 5 2 40
Sides of Step 3 4 4 2 32
Sides of Step 4 4 3 2 24
Sides of Step 5 4 2 2 16

Aqueduct cut off walls 4 11.75 5 235


RD: 43+250
Sides 4 2 5 40

Bridge abutments

RD: 44+300
Construction of Siran Right Bank Canal
District Mansehra
Aqueducts

BOQ Item No. Description

Front & Back 4 18 11 792


Sides of Step 1 4 6 3 72
RD: 44+300 Sides of Step 2 4 5 2 40
Sides of Step 3 4 4 2 32
Sides of Step 4 4 3 2 24
Sides of Step 5 4 2 2 16

Aqueduct cut off walls 4 11.75 4 188


Sides 4 2 4 32
Bridge abutments
Front & Back 4 18 18 1296
Sides of Step 1 4 9 3 108
RD: 45+600 Sides of Step 2 4 8 2 64
Sides of Step 3 4 7 2 56
Sides of Step 4 4 6 2 48
Sides of Step 5 4 5 2 40
Sides of Step 6 4 4 2 32
Sides of Step 7 4 3 2 24
Sides of Step 8 4 2 2 16

Aqueduct cut off wall U/S 2 11.75 3 70.5


Sides 2 4 3 24
Aqueduct cut off wall D/S 2 11.75 3 70.5
RD: 47+500
Sides 2 6 3 36
Causeway front back 2 23 2 92
Causeway ends 2 16 2 64

Aqueduct cut off wall U/S 2 11.75 2.33 54.755


Sides 2 2 2.33 9.32
Crest sump well front back 2 30 3.6 216
Crest sump well end 2 2 3.6 14.4
Cway Toe wall Front back 2 30 8 480
Cway Toe wall end step 1 2 5 2 20
RD: 64+350
Cway Toe wall end step 2 2 4 2 16
Cway Toe wall end step 3 2 3 2 12
Cway Toe wall end step 4 2 2 2 8
C/way & Ramp End walls F&B 8 19 4 608
C/way & Ramp End walls Sides 8 2 4 64
C/Way ramp sides 4 31 1.5 186

Causeway Front & Back 2 30 1.5 90


Causeway Ends 2 21.17 1.5 63.51
RD: 85+175 Causeway Ramps 4 70 1.5 420
Ramp End Walls F&B 4 20 4 320
Ramp End Walls Sides 4 2 4 32

Aqueduct cut off walls F&B 4 10 4 160


Aqueduct cut off walls Sides 4 2 4 32
Bridge abutments
Front & Back 4 18 11 792
RD: 98+000 Sides of Step 1 4 6 3 72
Sides of Step 2 4 5 2 40
Sides of Step 3 4 4 2 32
Sides of Step 4 4 3 2 24
Sides of Step 5 4 2 2 16

Aqueduct cut off walls F&B 4 10 5 200


Aqueduct cut off walls Sides 4 3 5 60
Causeway Front & Back 2 30 1.5 90
RD: 110+030 Causeway Ends 2 21.17 1.5 63.51
Causeway Ramps 4 70 1.5 420
Ramp End Walls F&B 4 20 4 320
Ramp End Walls Sides 4 2 4 32
Construction of Siran Right Bank Canal
District Mansehra
Aqueducts

BOQ Item No. Description

Aqueduct cut off walls F&B 4 9 4 144


Aqueduct cut off walls Sides 4 2 4 32
Bridge abutments
Front & Back 4 18 11 792
RD: 114+250 Sides of Step 1 4 6 3 72
Sides of Step 2 4 5 2 40
Sides of Step 3 4 4 2 32
Sides of Step 4 4 3 2 24
Sides of Step 5 4 2 2 16

Aqueduct cut off walls F&B 4 9 4 144


Aqueduct cut off walls Sides 4 2 4 32
RD: 115+069
Causeway front back 2 23 2 92
Causeway ends 2 16 2 64

Aqueduct cut off walls F&B 4 9 5 180


Aqueduct cut off walls Sides 4 10 5 200
Bridge abutments
Front & Back 4 18 11 792
RD: 120+136 Sides of Step 1 4 6 3 72
Sides of Step 2 4 5 2 40
Sides of Step 3 4 4 2 32
Sides of Step 4 4 3 2 24
Sides of Step 5 4 2 2 16

Aqueduct cut off walls F&B 4 8.75 4 140


Aqueduct cut off walls Sides 4 2 4 32
Causeway Front & Back 2 30 1.5 90
RD: 129+808 Causeway Ends 2 21.17 1.5 63.51
Causeway Ramps 4 70 1.5 420
Ramp End Walls F&B 4 20 4 320
Ramp End Walls Sides 4 2 4 32

Aqueduct cut off walls F&B 4 8.6 5 172


Aqueduct cut off walls Sides 4 2 5 40
Causeway Front & Back 2 30 1.5 90
RD: 136+732 Causeway Ends 2 21.17 1.5 63.51
Causeway Ramps 4 70 1.5 420
Ramp End Walls F&B 4 20 4 320
Ramp End Walls Sides 4 2 4 32

Aqueduct cut off walls F&B 4 8.6 4 137.6


Aqueduct cut off walls Sides 4 2 4 32
Bridge abutments
Front & Back 4 18 11 792
RD: 140+370 Sides of Step 1 4 6 3 72
Sides of Step 2 4 5 2 40
Sides of Step 3 4 4 2 32
Sides of Step 4 4 3 2 24
Sides of Step 5 4 2 2 16

Aqueduct cut off walls F&B 4 8.6 5 172


Aqueduct cut off walls Sides 4 2 5 40
Causeway Front & Back 2 30 1.5 90
RD: 140+914 Causeway Ends 2 21.17 1.5 63.51
Causeway Ramps 4 70 1.5 420
Ramp End Walls F&B 4 20 4 320
Ramp End Walls Sides 4 2 4 32

Aqueduct cut off walls F&B 4 8.6 5 172


Aqueduct cut off walls Sides 4 2 5 40
Causeway Front & Back 2 30 1.5 90
RD: 142+727 Causeway Ends 2 21.17 1.5 63.51
Causeway Ramps 4 70 1.5 420
Construction of Siran Right Bank Canal
District Mansehra
Aqueducts
RD: 142+727
BOQ Item No. Description

Ramp End Walls F&B 4 20 4 320


Ramp End Walls Sides 4 2 4 32

Aqueduct cut off walls F&B 4 8.5 4 136


Aqueduct cut off walls Sides 4 10 4 160
Cway Toe wall Front back 2 30 8 480
Cway Toe wall end step 1 2 5 2 20

RD: 147+515
Construction of Siran Right Bank Canal
District Mansehra
Aqueducts

BOQ Item No. Description

Cway Toe wall end step 2 2 4 2 16


RD: 147+515
Cway Toe wall end step 3 2 3 2 12
Cway Toe wall end step 4 2 2 2 8
C/way & Ramp End walls F&B 8 19 4 608
C/way & Ramp End walls Sides 8 2 4 64
C/Way ramp sides 4 31 1.5 186

Aqueduct cut off walls F&B 4 8.5 4 136


RD: 148+097
Aqueduct cut off walls Sides 4 10 4 160

Aqueduct cut off walls F&B 4 8.3 4 132.8


Aqueduct cut off walls Sides 4 2 4 32
RD: 151+796
Causeway front back 2 23 2 92
Causeway ends 2 16 2 64

Aqueduct cut off walls F&B 4 8.3 4 132.8


RD: 153+559
Aqueduct cut off walls Sides 4 10 4 160

Aqueduct cut off walls F&B 4 8 5 160


Aqueduct cut off walls Sides 4 3 5 60
Cway Toe wall Front back 2 30 8 480
Cway Toe wall end step 1 2 5 2 20
Cway Toe wall end step 2 2 4 2 16
RD: 158+683
Cway Toe wall end step 3 2 3 2 12
Cway Toe wall end step 4 2 2 2 8
C/way & Ramp End walls F&B 8 19 4 608
C/way & Ramp End walls Sides 8 2 4 64
C/Way ramp sides 4 31 1.5 186

Aqueduct cut off walls F&B 4 8 4 128


Aqueduct cut off walls Sides 4 2 4 32
Causeway Front & Back 2 30 1.5 90
RD: 161+089 Causeway Ends 2 21.17 1.5 63.51
Causeway Ramps 4 70 1.5 420
Ramp End Walls F&B 4 20 4 320
Ramp End Walls Sides 4 2 4 32

Aqueduct cut off walls F&B 4 7.7 4 123.2


Aqueduct cut off walls Sides 4 10 4 160
Causeway front back 2 23 1.25 57.5
RD: 163+586
Causeway ends 2 16 1.25 40
Cut off wall Nullah 4 23 5 460
Sides 4 2 5 40

Aqueduct cut off walls F&B 4 7.7 4 123.2


RD: 170+890
Aqueduct cut off walls Sides 4 2 4 32

Aqueduct cut off walls F&B 4 7.3 5 146


RD: 172+991
Aqueduct cut off walls Sides 4 2 5 40

Aqueduct cut off walls F&B 4 7 5 140


RD: 178+154
Aqueduct cut off walls Sides 4 2 5 40

Aqueduct cut off walls F&B 4 5.7 5 114


RD: 184+743
Aqueduct cut off walls Sides 4 3 5 60

Total formwork (sft) 45662.099 sft


Total formwork (sq.m) 4243.689 (sq.m

B-14
Construction of Siran Right Bank Canal
District Mansehra
Aqueducts

BOQ Item No. Description

B-15 Formation, dressing and preparing sub-grade in bed

Description No. Length Width Quantity


(ft) (ft) (Sft)

RD:RD: 7+093 Nullah Bed 1 66.5 10 665


RD: 7+686Nullah Bed 1 40.5 11.8 477.9
RD: 10+035 Nullah Bed 1 40 19 760
RD: 32+275 Nullah Bed 1 20 21 420
RD: 38+875 Nullah Bed 1 20 12 240
RD: 41+300 Nullah Bed 1 20 16 320
RD: 44+300 Nullah Bed 1 20 16 320
RD: 98+000 Nullah Bed 1 20 16 320
Total Quantity (Sft) 3522.9
Total Quantity (Sq. M) 327.864

B-16 Formation, dressing and preparing sub-grade On slope

Description No. Length Slope Width Quantity


(ft) (ft) (Sft)

RD: 7+093 Left & Right 1 66.5 20.06 1333.99


RD: 7+686 Left & Right 1 40.5 15.14 613.17
RD: 10+035 Left & Right 1 40 37.58 1503.2
RD: 32+275 Left & Rigth 2 20 13.55 542
RD: 38+875 Left & Rigth 2 20 11 440
RD: 41+300 Left & Rigth 2 20 16.72 668.8
RD: 44+300 Left & Rigth 2 16.72 17.72 592.5568
RD: 98+000 Left & Right 2 16.72 17.72 592.5568
Total Quantity (Sft) 6286.2736
Total Quantity (Sq. M) 585.042

B-17 Providing and Laying stone pitching/filling, dry hand packed in pitching & aprons

Description No. Length Width Depth Volume (cft)


(ft) (ft) (ft)

RD: 7+093 1 66.5 30.06 1 1998.99


RD: 7+686 1 40.5 26.94 1 1091.07
RD: 10+035 1 40 56.58 1 2263.2
RD: 32+275 1 20 48.1 1 962
RD: 38+875 1 20 34 1 680
RD: 41+300 2 20 49.44 1 1977.6
RD: 44+300 3 20 51.44 2 6172.8
RD: 98+000 3 20 51.44 2 6172.8
Total Quantity (Cft) 21318.46
Total Quantity (Cu. M) 603.671

B-18 Provide & weave GI wire netting for wire crates 6"x9" mesh : 8 SWG wire

Description Length No. of crates Nos. Area (sft) Qty (sft)


RD: 32+275 D/S Apron
Top & Bottom (10x10) 22 2.2 2 100 440
Ends (10x3) 22 2.2 2 30 132
Sides (10x3) 22 2.2 2 30 132
RD: 47+500 D/S Apron
Top & Bottom (10x10) 23 2.3 2 100 460
Ends (10x3) 23 2.3 2 30 138
Sides (10x3) 23 2.3 2 30 138
RD: 64+350 D/S Apron
Top & Bottom (10x10) 30 3 2 100 600
Ends (10x3) 30 3 2 30 180
Sides (10x3) 30 3 2 30 180
RD: 85+175 D/S Apron
Top & Bottom (10x10) 30 3 2 100 600
Ends (10x3) 30 3 2 30 180
Sides (10x3) 30 3 2 30 180
RD: 110+030 D/S Apron
Top & Bottom (10x10) 30 3 2 100 600
Ends (10x3) 30 3 2 30 180
Construction of Siran Right Bank Canal
District Mansehra
Aqueducts

BOQ Item No. Description

Sides (10x3) 30 3 2 30 180


RD: 115+069 D/S Apron
Top & Bottom (10x10) 23 2.3 2 100 460
Ends (10x3) 23 2.3 2 30 138
Sides (10x3) 23 2.3 2 30 138
RD: 129+808 D/S Apron
Top & Bottom (10x10) 30 3 2 100 600
Ends (10x3) 30 3 2 30 180
Sides (10x3) 30 3 2 30 180
RD: 136+732 D/S Apron
Top & Bottom (10x10) 30 3 2 100 600
Ends (10x3) 30 3 2 30 180
Sides (10x3) 30 3 2 30 180
RD: 140+914 D/S Apron
Top & Bottom (10x10) 30 3 2 100 600
Ends (10x3) 30 3 2 30 180
Sides (10x3) 30 3 2 30 180
RD: 142+727 D/S Apron
Top & Bottom (10x10) 30 3 2 100 600
Construction of Siran Right Bank Canal
District Mansehra
Aqueducts

BOQ Item No. Description

Ends (10x3) 30 3 2 30 180


Sides (10x3) 30 3 2 30 180
RD: 147+515 D/S Apron
Top & Bottom (10x10) 30 3 2 100 600
Ends (10x3) 30 3 2 30 180
Sides (10x3) 30 3 2 30 180
RD: 151+796 D/S Apron
Top & Bottom (10x10) 30 3 2 100 600
Ends (10x3) 30 3 2 30 180
Sides (10x3) 30 3 2 30 180
RD: 161+089 D/S Apron
Top & Bottom (10x10) 30 3 2 100 600
Ends (10x3) 30 3 2 30 180
Sides (10x3) 30 3 2 30 180
RD: 163+586 D/S Apron
Top & Bottom (10x10) 25 2.5 2 100 500
Ends (10x3) 25 2.5 2 30 150
Sides (10x3) 25 2.5 2 30 150
Total Quantity (Sft) 9856
Total Quantity (Sq. M) 917.264

B-19 Supplying stone and stone filling in GI wire crate and its sewing, excluding cost of crates

Description Length Width Depth Quantity


(ft) (ft) (cft)
(ft)
RD: 32+275 Apron 22 10 3 660
RD: 47+500 Apron 23 10 3 690
RD: 64+350 Apron 30 10 3 900
RD: 85+175 Apron 30 10 3 900
RD: 110+030 Apron 30 10 3 900
RD: 115+069 Apron 30 10 3 900
RD: 129+808 Apron 30 10 3 900
RD: 136+732 Apron 30 10 3 900
RD: 140+914 Apron 30 10 3 900
RD: 142+727 Apron 30 10 3 900
RD: 147+515 Apron 30 10 3 900
RD: 151+796 Apron 30 10 3 900
RD: 161+089 Apron 30 10 3 900
RD: 163+586 Apron 25 10 3 750
Total Quantity (cft) 12000
Total Quantity (m3) 339.8

B-20 Painting two feet wide gauges, reading to 1/10th of a foot.

No. of aqueducts 38
No of sides 2
Length of paint 5
Total in M 115.818

Supply and Fixing Neoprene Bearing


B-21 Pad as per specs & design

200000 cm3
Construction of Siran Right Bank Canal
District Mansehra
Syphons

BOQ Item No. Description


A-1 Structural Excavation in Common Material

Area (sft) Width (ft) Volume (cft) RD


Syphon-1 22801.49 7.25 115717.5625 13+960 to 17+335
Syphon-2 2766.64 7 19366.48 50+250 to 50+600
Syphon-3 7510.13 7 52570.91 81+525 to 82+530
Syphon-4 12497.77 6.16 76986.2632 100+920 to 102+930
Syphon-5 5131 5 25655 166+691 to 167+424
Total 290296.216 Cub. ft.
OR 8220.266 Cub. M.
Structural Excavation in Rock Material requiring blasting
Take 10% of excavation quantity of item B-1 49593.24
OR 1404.32 Cum

A-2 Plain Cement Concrete including placing, compacting, finishing &


curing (Ratio 1:4:8)
Length Width Thickness Volume
(ft) (ft) (ft) (cft)
Syphon-1
Below tube 3400 4.25 0.25 3612.500
Below inlet 15.5 9 0.25 34.875
Below outlet 15.5 9 0.25 34.875
Syphon-2
Below tube 250 4 0.25 250.000
Below inlet 15.5 9 0.25 34.875
Below outlet 15.5 9 0.25 34.875
Syphon-3
Below tube 900 4 0.25 900.000
Below inlet 15.5 9 0.25 34.875
Below outlet 15.5 9 0.25 34.875
Syphon-4
Below tube 1800 3.16 0.25 1422.000
Below inlet 15.5 9 0.25 34.875
Below outlet 15.5 9 0.25 34.875
Syphon-5
Below tube 600 3.33 0.25 499.500
Below inlet 8.5 8.25 0.25 17.531
Below outlet 8.5 8.25 0.25 17.531

Total 6998.063 Cub. ft.


OR 396.326 Cub. M.
Construction of Siran Right Bank Canal
District Mansehra
Syphons

BOQ Item No. Description

Reinforced cement concrete work as in dams, spillways, weirs,


barrages, cross drainage works and other hydraulic structures using
crushed stone aggregate(screening & washing) and coarse sand i/c
A-3 cost of all labour and material and all kinds of form works, moulds,
shuttering lifting/pumping, curing, rendering and finishing the exposed
surface, cast in situ/precast excluding the cost of steel reinforcement
and labour for bending binding also excluding cost of additives which
have to be paid separately. Type C (1:2:4)

Length Width Thickness Volume


(ft) (ft) (ft) (cft)
Syphon-1
Inlet structure
Cutoff wall 9 0.75 2 13.500
U/S slab 9 1.5 0.667 9.005
Bottom slab 13.25 9 0.667 79.540
Long wall L/S 13.25 0.75 10.5 104.344
Long wall R/S 13.25 0.75 10.5 104.344
Shortwall U/S 7.5 0.75 10.5 59.063
Shortwall U/S 7.5 1.5 10.5 118.125
D/d U/S opening 6.75 4.5 0.75 -22.781
D/d siphon tube entry π/4 x 3.25^2 1.5 -8.296

Siphon tube encasement


3400 4.25 4.25 61412.50
D/d pipe 3400 π/4 x 3.25^2 -28205.61

Outlet structure
Cutoff wall 9 0.75 2 13.500
D/S slab 9 1.5 0.667 9.005
Bottom slab 13.25 9 0.667 79.540
Long wall L/S 13.25 0.75 10.5 104.344
Long wall R/S 13.25 0.75 10.5 104.344
Shortwall U/S 7.5 0.75 10.5 59.063
Shortwall U/S 7.5 1.5 10.5 118.125
D/d siphon tube exit π/4 x 3.25^2 1.5 -8.296
D/d D/S opening 6.75 4.5 0.75 -22.781

Syphon-2
Inlet structure
Cutoff wall 9 0.75 2 13.500
U/S slab 9 1.5 0.667 9.005
Bottom slab 13.25 9 0.667 79.540
Long wall L/S 13.25 0.75 10.5 104.344
Long wall R/S 13.25 0.75 10.5 104.344
Shortwall U/S 7.5 0.75 10.5 59.063
Shortwall U/S 7.5 1.5 10.5 118.125
Construction of Siran Right Bank Canal
District Mansehra
Syphons

BOQ Item No. Description


D/d U/S opening 6.5 4.5 0.75 -21.938
D/d siphon tube entry π/4 x 3^2 1.5 -7.069

Siphon tube encasement


250 4 4 4000.00
D/d pipe 250 π/4 x 3^2 -1767.15

Outlet structure
Cutoff wall 9 0.75 2 13.500
D/S slab 9 1.5 0.667 9.005
Bottom slab 13.25 9 0.667 79.540
Long wall L/S 13.25 0.75 10.5 104.344
Long wall R/S 13.25 0.75 10.5 104.344
Shortwall U/S 7.5 0.75 10.5 59.063
Shortwall U/S 7.5 1.5 10.5 118.125
D/d siphon tube exit π/4 x 3^2 1.5 -7.069
D/d D/S opening 6.5 4.5 0.75 -21.938

Syphon-3
Inlet structure
Cutoff wall 9 0.75 2 13.500
U/S slab 9 1.5 0.667 9.005
Bottom slab 13.25 9 0.667 79.540
Long wall L/S 13.25 0.75 10.5 104.344
Long wall R/S 13.25 0.75 10.5 104.344
Shortwall U/S 7.5 0.75 10.5 59.063
Shortwall U/S 7.5 1.5 10.5 118.125
D/d U/S opening 6.3 4.5 0.75 -21.263
D/d siphon tube entry π/4 x 2.75^2 1.5 -5.940

Siphon tube encasement


900 4 4 14400.00
D/d pipe 900 π/4x 2.75^2 -5345.62

Outlet structure
Cutoff wall 9 0.75 2 13.500
D/S slab 9 1.5 0.667 9.005
Bottom slab 13.25 9 0.667 79.540
Long wall L/S 13.25 0.75 10.5 104.344
Long wall R/S 13.25 0.75 10.5 104.344
Shortwall U/S 7.5 0.75 10.5 59.063
Shortwall U/S 7.5 1.5 10.5 118.125
D/d siphon tube exit π/4 x 2.75^2 1.5 -5.940
D/d D/S opening 6.3 4.5 0.75 -21.263

Syphon-4
Construction of Siran Right Bank Canal
District Mansehra
Syphons

BOQ Item No. Description


Inlet structure
Cutoff wall 9 0.75 2 13.500
U/S slab 9 1.5 0.667 9.005
Bottom slab 13.25 9 0.667 79.540
Long wall L/S 13.25 0.75 10.5 104.344
Long wall R/S 13.25 0.75 10.5 104.344
Shortwall U/S 7.5 0.75 10.5 59.063
Shortwall U/S 7.5 1.5 10.5 118.125
D/d U/S opening 5 4.5 0.75 -16.875
D/d siphon tube entry π/4 x 2.16^2 1.5 -3.664

Siphon tube encasement


1800 3.16 3.16 17974.08
D/d pipe 1800 π/4 x 2.16^2 -6595.84

Outlet structure
Cutoff wall 9 0.75 2 13.500
D/S slab 9 1.5 0.667 9.005
Bottom slab 13.25 9 0.667 79.540
Long wall L/S 13.25 0.75 10.5 104.344
Long wall R/S 13.25 0.75 10.5 104.344
Shortwall U/S 7.5 0.75 10.5 59.063
Shortwall U/S 7.5 1.5 10.5 118.125
D/d siphon tube exit π/4 x 2.16^2 1.5 -3.664
D/d D/S opening 5 4.5 0.75 -16.875
Syphon-5
Inlet structure
Cutoff wall u/d 7.83 2 0.5 7.830 2
Shortwall U/S front Site 7.83 1 6.25 48.938
Bottom slab 6 7.83 0.75 35.235
Long wall L/S 9 6.25 0.75 42.188
Long wall R/S 9 6.25 0.75 42.188
Shortwall U/S 0.75 7.83 1.5 8.809
Shortwall U/S 3 7.83 0.75 17.618
top opening wall 0.75 7.83 2 11.745
Quantity
D/d siphon tube entry π/4 x 1.83^2 1.5 -3.9458414
Net QTY
Siphon tube encasement
421 2.83 2.83 3371.75
D/d pipe 421 π/4 x 1.83^2 -1107.4662
Net QTY

Outlet structure
Cutoff wall u/d 7.83 2 0.5 7.830
Shortwall U/S front Site 7.83 1 6.25 48.938
Construction of Siran Right Bank Canal
District Mansehra
Syphons

BOQ Item No. Description


Bottom slab 6 7.83 0.75 35.235
Long wall L/S 9 6.25 0.75 42.188
Long wall R/S 9 6.25 0.75 42.188
Shortwall U/S 0.75 7.83 1.5 8.809
Shortwall U/S 3 7.83 0.75 17.618
top opening wall 0.75 7.83 2 11.745
Quantity
D/d siphon tube entry π/4 x 1.83^2 1.5 -3.9458414
Total RCC 62245.56 cub. Ft
OR 1762.600 cub. M

A-4 Supply & fabricate M.S. reinforcement for cement concrete (Hot rolled
deformed bars Grade 40)

Taking 1.50% of RCC Volume as per Item A-3


Steel Quantity = 62245.56 x 1.50% x 490
= 457504.875 lbs
OR 207.58 tonnes

Procuring 6 mm steel sheets, cold bending & fabricating to make 3.08


diameter circular pipe in suitable lengths including inlets/outlet, cone,
horizontal & verticals bends, manholes & drainage arrangement,
painting on the inner sides all as per drawings & specifications, ready
A-5 to be lowered in pipe trenched, supported on temporary or
permanently embedded steel/concrete supports. The pipe is to be
aligned /installed to line & grade field welded, including the costs of
non destructive tests, complete in all respects. The work shall include
the costs of all the items required for providing complete steel pipe in
place, ready for concrete cladding

Pipe Dia (ft.) Length Thickness Volume Weight


(ft.) (ft.) (cub. Ft) (lbs)
Syphon-1 3.25 3500 0.0197 703.992 344955.905
Syphon-2 3 350 0.0197 64.984 31842.084
Syphon-3 2.75 1050 0.0197 178.706 87565.730
Syphon-4 2.16 2010 0.0197 268.699 131662.467
Syphon-5 1.83 733 0.0197 83.018 40678.717
Total Weight (lbs) 636704.902
Total Weight (Tonnes) 0.000

A-6 Providing and fixing MS steel grated trash rack as per drawings and
instructions of Engineer.

Nos. Length (ft) Width (ft) Area (sft)


Syphon-1
Trash Racks 2 6.5 6.5 84.5
Gratings 2 8 11.5 184
Syphon-2
Trash Racks 2 6.5 6.5 84.5
Construction of Siran Right Bank Canal
District Mansehra
Syphons

BOQ Item No. Description


Gratings 2 8 11.5 184
Syphon-3
Trash Racks 2 6.3 6.5 81.9
Gratings 2 8 11.5 184
Syphon-4
Trash Racks 2 5 6.5 65
Gratings 2 8 11.5 184
Syphon-5
Trash Racks 2 6 4.13 49.56
Gratings 2 7.75 7.83 121.365
Total 1222.825 sq. ft.
OR 113.800 sq. m.

A-7 Structural backfill using Common Material available at site

No. Length Width Depth Volume (cft)


(ft) (ft) (ft)
Syphon-1
Sides 2 3400 1.5 4.5 45900
Top 1 3400 7.5 2 51000
Syphon-2
Sides 2 250 1.5 4.25 3187.5
Top 1 250 7.25 2 3625
Syphon-3
Sides 2 900 1.5 4.25 11475
Top 1 900 7.25 2 13050
Syphon-4
Sides 2 1800 1.5 3.41 18414
Top 1 1800 6.41 2 23076
Syphon-5
Sides 2 650 1.5 4.5 8775
Top 1 650 8 2 10400
Total 188902.5 cub. Ft
OR 5349.12 cub. M

A-8 Providing and installing air/water relief valves


No. of valves
Syphon-1 3
Syphon-2 1
Syphon-3 3
Syphon-4 3
Syphon-5 3
Total 13
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description

C-1 Structural Excavation in Common Material

Excavation in U/S guide walls

R.D Bottom Width + 1.5' Length Height No. of walls Volume


working space (5/cos 45)
6+000 to 20+000 116.400 20No's 7.072 3 2 4939.17963
20+100 5.82 7.072 3 2 246.958982
20+350 5.82 7.072 3 2 246.958982
20+935 5.82 7.072 3 2 246.958982
22+750 5.82 7.072 3 2 246.958982
24+500 5.82 7.072 3 2 246.958982
25+765 5.82 7.072 3 2 246.958982
26+500 5.82 7.072 3 2 246.958982
26+835 5.82 7.072 3 2 246.958982
28+175 5.82 7.072 3 2 246.958982
28+650 5.82 7.072 3 2 246.958982
29+400 5.82 7.072 3 2 246.958982
29+800 5.82 7.072 3 2 246.958982
29+925 5.82 7.072 3 2 246.958982
31+060 5.82 7.072 3 2 246.958982
31+460 5.82 7.072 3 2 246.958982
31+500 5.82 7.072 3 2 246.958982
31+525 5.82 7.072 3 2 246.958982
31+855 5.82 7.072 3 2 246.958982
33+000 5.82 7.072 3 2 246.958982
33+600 5.82 7.072 3 2 246.958982
33+612 5.82 7.072 3 2 246.958982
34+235 5.82 7.072 3 2 246.958982
34+950 5.82 7.072 3 2 246.958982
39+725 5.82 7.072 3 2 246.958982
39+950 5.82 7.072 3 2 246.958982
40+925 5.82 7.072 3 2 246.958982
41+125 5.82 7.072 3 2 246.958982
42+575 5.82 7.072 3 2 246.958982
44+590 5.82 7.072 3 2 246.958982
46+220 5.82 7.072 3 2 246.958982
47+400 5.82 7.072 3 2 246.958982
48+575 5.82 7.072 3 2 246.958982
49+730 5.82 7.072 3 2 246.958982
49+850 5.82 7.072 3 2 246.958982
51+425 5.82 7.072 3 2 246.958982
52+075 5.82 7.072 3 2 246.958982
52+200 5.82 7.072 3 2 246.958982
52+450 5.82 7.072 3 2 246.958982
52+600 5.82 7.072 3 2 246.958982
52+935 5.82 7.072 3 2 246.958982
54+505 5.82 7.072 3 2 246.958982
54+775 5.82 7.072 3 2 246.958982
55+150 5.82 7.072 3 2 246.958982
57+115 5.82 7.072 3 2 246.958982
58+150 5.82 7.072 3 2 246.958982
58+750 5.82 7.072 3 2 246.958982
59+033 5.82 7.072 3 2 246.958982
59+190 5.82 7.072 3 2 246.958982
59+325 5.82 7.072 3 2 246.958982
59+790 5.82 7.072 3 2 246.958982
60+025 5.82 7.072 3 2 246.958982
60+100 5.82 7.072 3 2 246.958982
60+410 5.82 7.072 3 2 246.958982
61+200 5.82 7.072 3 2 246.958982
61+250 5.82 7.072 3 2 246.958982
61+715 5.82 7.072 3 2 246.958982
62+323 5.82 7.072 3 2 246.958982
63+750 5.82 7.072 3 2 246.958982
64+750 5.82 7.072 3 2 246.958982
65+035 5.82 7.072 3 2 246.958982
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description
65+850 5.82 7.072 3 2 246.958982
67+425 5.82 7.072 3 2 246.958982
67+825 5.82 7.072 3 2 246.958982
68+145 5.82 7.072 3 2 246.958982
68+450 5.82 7.072 3 2 246.958982
68+750 5.82 7.072 3 2 246.958982
69+495 5.82 7.072 3 2 246.958982
70+300 5.82 7.072 3 2 246.958982
70+575 5.82 7.072 3 2 246.958982
71+528 5.82 7.072 3 2 246.958982
72+055 5.82 7.072 3 2 246.958982
72+695 5.82 7.072 3 2 246.958982
74+715 5.82 7.072 3 2 246.958982
75+610 5.82 7.072 3 2 246.958982
76+418 5.82 7.072 3 2 246.958982
77+750 5.82 7.072 3 2 246.958982
78+000 5.82 7.072 3 2 246.958982
78+190 5.82 7.072 3 2 246.958982
78+645 5.82 7.072 3 2 246.958982
78+850 5.82 7.072 3 2 246.958982
79+480 5.82 7.072 3 2 246.958982
80+250 5.82 7.072 3 2 246.958982
80+600 5.82 7.072 3 2 246.958982
80+825 5.82 7.072 3 2 246.958982
81+325 5.82 7.072 3 2 246.958982
82+060 5.82 7.072 3 2 246.958982
82+229 5.82 7.072 3 2 246.958982
83+625 5.82 7.072 3 2 246.958982
84+150 5.82 7.072 3 2 246.958982
84+361 5.82 7.072 3 2 246.958982
85+265 5.82 7.072 3 2 246.958982
85+811 5.82 7.072 3 2 246.958982
86+197 5.82 7.072 3 2 246.958982
87+148 5.82 7.072 3 2 246.958982
87+829 5.82 7.072 3 2 246.958982
88+914 5.82 7.072 3 2 246.958982
89+296 5.82 7.072 3 2 246.958982
89+606 5.82 7.072 3 2 246.958982
89+995 5.82 7.072 3 2 246.958982
92+953 5.82 7.072 3 2 246.958982
93+085 5.82 7.072 3 2 246.958982
93+577 5.82 7.072 3 2 246.958982
94+097 5.82 7.072 3 2 246.958982
94+901 5.82 7.072 3 2 246.958982
95+318 5.82 7.072 3 2 246.958982
95+715 5.82 7.072 3 2 246.958982
97+263 5.82 7.072 3 2 246.958982
97+581 5.82 7.072 3 2 246.958982
97+722 5.82 7.072 3 2 246.958982
98+040 5.82 7.072 3 2 246.958982
98+746 5.82 7.072 3 2 246.958982
98+990 5.82 7.072 3 2 246.958982
99+372 5.82 7.072 3 2 246.958982
99+548 5.82 7.072 3 2 246.958982
100+491 5.82 7.072 3 2 246.958982
100+596 5.82 7.072 3 2 246.958982
103+451 5.82 7.072 3 2 246.958982
103+871 5.82 7.072 3 2 246.958982
104+647 5.82 7.072 3 2 246.958982
105+862 5.82 7.072 3 2 246.958982
106+602 5.82 7.072 3 2 246.958982
107+480 5.82 7.072 3 2 246.958982
108+180 5.82 7.072 3 2 246.958982
108+223 5.82 7.072 3 2 246.958982
108+853 5.82 7.072 3 2 246.958982
109+093 5.82 7.072 3 2 246.958982
109+226 5.82 7.072 3 2 246.958982
110+116 5.82 7.072 3 2 246.958982
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description
111+268 5.82 7.072 3 2 246.958982
111+420 5.82 7.072 3 2 246.958982
113+763 5.82 7.072 3 2 246.958982
114+301 5.82 7.072 3 2 246.958982
116+742 5.82 7.072 3 2 246.958982
117+773 5.82 7.072 3 2 246.958982
117+982 5.82 7.072 3 2 246.958982
118+204 5.82 7.072 3 2 246.958982
119+349 5.82 7.072 3 2 246.958982
120+228 5.82 7.072 3 2 246.958982
120+611 5.82 7.072 3 2 246.958982
120+956 5.82 7.072 3 2 246.958982
122+397 5.82 7.072 3 2 246.958982
123+125 5.82 7.072 3 2 246.958982
125+804 5.82 7.072 3 2 246.958982
126+298 5.82 7.072 3 2 246.958982
127+529 5.82 7.072 3 2 246.958982
127+663 5.82 7.072 3 2 246.958982
128+217 5.82 7.072 3 2 246.958982
129+307 5.82 7.072 3 2 246.958982
130+954 5.82 7.072 3 2 246.958982
131+319 5.82 7.072 3 2 246.958982
131+636 5.82 7.072 3 2 246.958982
131+781 5.82 7.072 3 2 246.958982
132+594 5.82 7.072 3 2 246.958982
132+710 5.82 7.072 3 2 246.958982
133+674 5.82 7.072 3 2 246.958982
143+988 5.82 7.072 3 2 246.958982
145+182 5.82 7.072 3 2 246.958982
145+400 5.82 7.072 3 2 246.958982
146+798 5.82 7.072 3 2 246.958982
146+872 5.82 7.072 3 2 246.958982
148+655 5.82 7.072 3 2 246.958982
150+396 5.82 7.072 3 2 246.958982
151+123 5.82 7.072 3 2 246.958982
152+924 5.82 7.072 3 2 246.958982
155+398 5.82 7.072 3 2 246.958982
155+907 5.82 7.072 3 2 246.958982
157+151 5.82 7.072 3 2 246.958982
159+055 5.82 7.072 3 2 246.958982
159+568 5.82 7.072 3 2 246.958982
163+805 5.82 7.072 3 2 246.958982
171+472 5.82 7.072 3 2 246.958982
174+790 5.82 7.072 3 2 246.958982
175+608 5.82 7.072 3 2 246.958982
175+705 5.82 7.072 3 2 246.958982
180+458 5.82 7.072 3 2 246.958982
Total excavation 48157.0014 cub. Ft.
OR 1363.44851 cub. M.

Excavation in D/S guide walls


Bottom Width + 1.5' Length
R.D (11/cos Height No. of walls Volume
working space
45)
6+000 to 20+000 116.400 20No's 15.559 3 2 10866.1952

20+100 5.82 15.559 3 2 543.30976


20+350 5.82 15.559 3 2 543.30976
20+935 5.82 15.559 3 2 543.30976
22+750 5.82 15.559 3 2 543.30976
24+500 5.82 15.559 3 2 543.30976
25+765 5.82 15.559 3 2 543.30976
26+500 5.82 15.559 3 2 543.30976
26+835 5.82 15.559 3 2 543.30976
28+175 5.82 15.559 3 2 543.30976
28+650 5.82 15.559 3 2 543.30976
29+400 5.82 15.559 3 2 543.30976
29+800 5.82 15.559 3 2 543.30976
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description
29+925 5.82 15.559 3 2 543.30976
31+060 5.82 15.559 3 2 543.30976
31+460 5.82 15.559 3 2 543.30976
31+500 5.82 15.559 3 2 543.30976
31+525 5.82 15.559 3 2 543.30976
31+855 5.82 15.559 3 2 543.30976
33+000 5.82 15.559 3 2 543.30976
33+600 5.82 15.559 3 2 543.30976
33+612 5.82 15.559 3 2 543.30976
34+235 5.82 15.559 3 2 543.30976
34+950 5.82 15.559 3 2 543.30976
39+725 5.82 15.559 3 2 543.30976
39+950 5.82 15.559 3 2 543.30976
40+925 5.82 15.559 3 2 543.30976
41+125 5.82 15.559 3 2 543.30976
42+575 5.82 15.559 3 2 543.30976
44+590 5.82 15.559 3 2 543.30976
46+220 5.82 15.559 3 2 543.30976
47+400 5.82 15.559 3 2 543.30976
48+575 5.82 15.559 3 2 543.30976
49+730 5.82 15.559 3 2 543.30976
49+850 5.82 15.559 3 2 543.30976
51+425 5.82 15.559 3 2 543.30976
52+075 5.82 15.559 3 2 543.30976
52+200 5.82 15.559 3 2 543.30976
52+450 5.82 15.559 3 2 543.30976
52+600 5.82 15.559 3 2 543.30976
52+935 5.82 15.559 3 2 543.30976
54+505 5.82 15.559 3 2 543.30976
54+775 5.82 15.559 3 2 543.30976
55+150 5.82 15.559 3 2 543.30976
57+115 5.82 15.559 3 2 543.30976
58+150 5.82 15.559 3 2 543.30976
58+750 5.82 15.559 3 2 543.30976
59+033 5.82 15.559 3 2 543.30976
59+190 5.82 15.559 3 2 543.30976
59+325 5.82 15.559 3 2 543.30976
59+790 5.82 15.559 3 2 543.30976
60+025 5.82 15.559 3 2 543.30976
60+100 5.82 15.559 3 2 543.30976
60+410 5.82 15.559 3 2 543.30976
61+200 5.82 15.559 3 2 543.30976
61+250 5.82 15.559 3 2 543.30976
61+715 5.82 15.559 3 2 543.30976
62+323 5.82 15.559 3 2 543.30976
63+750 5.82 15.559 3 2 543.30976
64+750 5.82 15.559 3 2 543.30976
65+035 5.82 15.559 3 2 543.30976
65+850 5.82 15.559 3 2 543.30976
67+425 5.82 15.559 3 2 543.30976
67+825 5.82 15.559 3 2 543.30976
68+145 5.82 15.559 3 2 543.30976
68+450 5.82 15.559 3 2 543.30976
68+750 5.82 15.559 3 2 543.30976
69+495 5.82 15.559 3 2 543.30976
70+300 5.82 15.559 3 2 543.30976
70+575 5.82 15.559 3 2 543.30976
71+528 5.82 15.559 3 2 543.30976
72+055 5.82 15.559 3 2 543.30976
72+695 5.82 15.559 3 2 543.30976
74+715 5.82 15.559 3 2 543.30976
75+610 5.82 15.559 3 2 543.30976
76+418 5.82 15.559 3 2 543.30976
77+750 5.82 15.559 3 2 543.30976
78+000 5.82 15.559 3 2 543.30976
78+190 5.82 15.559 3 2 543.30976
78+645 5.82 15.559 3 2 543.30976
78+850 5.82 15.559 3 2 543.30976
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description
79+480 5.82 15.559 3 2 543.30976
80+250 5.82 15.559 3 2 543.30976
80+600 5.82 15.559 3 2 543.30976
80+825 5.82 15.559 3 2 543.30976
81+325 5.82 15.559 3 2 543.30976
82+060 5.82 15.559 3 2 543.30976
82+229 5.82 15.559 3 2 543.30976
83+625 5.82 15.559 3 2 543.30976
84+150 5.82 15.559 3 2 543.30976
84+361 5.82 15.559 3 2 543.30976
85+265 5.82 15.559 3 2 543.30976
85+811 5.82 15.559 3 2 543.30976
86+197 5.82 15.559 3 2 543.30976
87+148 5.82 15.559 3 2 543.30976
87+829 5.82 15.559 3 2 543.30976
88+914 5.82 15.559 3 2 543.30976
89+296 5.82 15.559 3 2 543.30976
89+606 5.82 15.559 3 2 543.30976
89+995 5.82 15.559 3 2 543.30976
92+953 5.82 15.559 3 2 543.30976
93+085 5.82 15.559 3 2 543.30976
93+577 5.82 15.559 3 2 543.30976
94+097 5.82 15.559 3 2 543.30976
94+901 5.82 15.559 3 2 543.30976
95+318 5.82 15.559 3 2 543.30976
95+715 5.82 15.559 3 2 543.30976
97+263 5.82 15.559 3 2 543.30976
97+581 5.82 15.559 3 2 543.30976
97+722 5.82 15.559 3 2 543.30976
98+040 5.82 15.559 3 2 543.30976
98+746 5.82 15.559 3 2 543.30976
98+990 5.82 15.559 3 2 543.30976
99+372 5.82 15.559 3 2 543.30976
99+548 5.82 15.559 3 2 543.30976
100+491 5.82 15.559 3 2 543.30976
100+596 5.82 15.559 3 2 543.30976
103+451 5.82 15.559 3 2 543.30976
103+871 5.82 15.559 3 2 543.30976
104+647 5.82 15.559 3 2 543.30976
105+862 5.82 15.559 3 2 543.30976
106+602 5.82 15.559 3 2 543.30976
107+480 5.82 15.559 3 2 543.30976
108+180 5.82 15.559 3 2 543.30976
108+223 5.82 15.559 3 2 543.30976
108+853 5.82 15.559 3 2 543.30976
109+093 5.82 15.559 3 2 543.30976
109+226 5.82 15.559 3 2 543.30976
110+116 5.82 15.559 3 2 543.30976
111+268 5.82 15.559 3 2 543.30976
1111+420 5.82 15.559 3 2 543.30976
113+763 5.82 15.559 3 2 543.30976
114+301 5.82 15.559 3 2 543.30976
116+742 5.82 15.559 3 2 543.30976
117+773 5.82 15.559 3 2 543.30976
117+982 5.82 15.559 3 2 543.30976
118+204 5.82 15.559 3 2 543.30976
119+349 5.82 15.559 3 2 543.30976
120+228 5.82 15.559 3 2 543.30976
120+611 5.82 15.559 3 2 543.30976
120+956 5.82 15.559 3 2 543.30976
122+397 5.82 15.559 3 2 543.30976
123+125 5.82 15.559 3 2 543.30976
125+804 5.82 15.559 3 2 543.30976
126+298 5.82 15.559 3 2 543.30976
127+529 5.82 15.559 3 2 543.30976
127+663 5.82 15.559 3 2 543.30976
128+217 5.82 15.559 3 2 543.30976
129+307 5.82 15.559 3 2 543.30976
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description
130+954 5.82 15.559 3 2 543.30976
131+319 5.82 15.559 3 2 543.30976
131+636 5.82 15.559 3 2 543.30976
131+781 5.82 15.559 3 2 543.30976
132+594 5.82 15.559 3 2 543.30976
132+710 5.82 15.559 3 2 543.30976
133+674 5.82 15.559 3 2 543.30976
143+988 5.82 15.559 3 2 543.30976
145+182 5.82 15.559 3 2 543.30976
145+400 5.82 15.559 3 2 543.30976
146+798 5.82 15.559 3 2 543.30976
146+872 5.82 15.559 3 2 543.30976
148+655 5.82 15.559 3 2 543.30976
150+396 5.82 15.559 3 2 543.30976
151+123 5.82 15.559 3 2 543.30976
152+924 5.82 15.559 3 2 543.30976
155+398 5.82 15.559 3 2 543.30976
155+907 5.82 15.559 3 2 543.30976
157+151 5.82 15.559 3 2 543.30976
159+055 5.82 15.559 3 2 543.30976
159+568 5.82 15.559 3 2 543.30976
163+805 5.82 15.559 3 2 543.30976
171+472 5.82 15.559 3 2 543.30976
174+790 5.82 15.559 3 2 543.30976
175+608 5.82 15.559 3 2 543.30976
175+705 5.82 15.559 3 2 543.30976
180+458 5.82 15.559 3 2 543.30976
Total excavation 105945.403 cub. Ft.
OR 2999.58672 cub. M.

Excavation in toe wall Bottom


Width +
R.D Length 1.5' Height Volume
working
space
6+000 to 20+000 282.880 20No's 4.5 5 6364.8

20+100 40.000 4.5 5 900


20+350 40.000 4.5 5 900
20+935 40.000 4.5 5 900
22+750 40.000 4.5 5 900
24+500 40.000 4.5 5 900
25+765 40.000 4.5 5 900
26+500 40.000 4.5 5 900
26+835 40.000 4.5 5 900
28+175 40.000 4.5 5 900
28+650 40.000 4.5 5 900
29+400 40.000 4.5 5 900
29+800 40.000 4.5 5 900
29+925 40.000 4.5 5 900
31+060 40.000 4.5 5 900
31+460 40.000 4.5 5 900
31+500 40.000 4.5 5 900
31+525 40.000 4.5 5 900
31+855 40.000 4.5 5 900
33+000 40.000 4.5 5 900
33+600 40.000 4.5 5 900
33+612 40.000 4.5 5 900
34+235 40.000 4.5 5 900
34+950 40.000 4.5 5 900
39+725 40.000 4.5 5 900
39+950 40.000 4.5 5 900
40+925 40.000 4.5 5 900
41+125 40.000 4.5 5 900
42+575 40.000 4.5 5 900
44+590 40.000 4.5 5 900
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description
46+220 40.000 4.5 5 900
47+400 40.000 4.5 5 900
48+575 40.000 4.5 5 900
49+730 40.000 4.5 5 900
49+850 40.000 4.5 5 900
51+425 40.000 4.5 5 900
52+075 40.000 4.5 5 900
52+200 40.000 4.5 5 900
52+450 40.000 4.5 5 900
52+600 40.000 4.5 5 900
52+935 40.000 4.5 5 900
54+505 40.000 4.5 5 900
54+775 40.000 4.5 5 900
55+150 40.000 4.5 5 900
57+115 40.000 4.5 5 900
58+150 40.000 4.5 5 900
58+750 40.000 4.5 5 900
59+033 40.000 4.5 5 900
59+190 40.000 4.5 5 900
59+325 40.000 4.5 5 900
59+790 40.000 4.5 5 900
60+025 40.000 4.5 5 900
60+100 40.000 4.5 5 900
60+410 40.000 4.5 5 900
61+200 40.000 4.5 5 900
61+250 40.000 4.5 5 900
61+715 40.000 4.5 5 900
62+323 40.000 4.5 5 900
63+750 40.000 4.5 5 900
64+750 40.000 4.5 5 900
65+035 40.000 4.5 5 900
65+850 40.000 4.5 5 900
67+425 40.000 4.5 5 900
67+825 40.000 4.5 5 900
68+145 40.000 4.5 5 900
68+450 40.000 4.5 5 900
68+750 40.000 4.5 5 900
69+495 40.000 4.5 5 900
70+300 40.000 4.5 5 900
70+575 40.000 4.5 5 900
71+528 40.000 4.5 5 900
72+055 40.000 4.5 5 900
72+695 40.000 4.5 5 900
74+715 40.000 4.5 5 900
75+610 40.000 4.5 5 900
76+418 40.000 4.5 5 900
77+750 40.000 4.5 5 900
78+000 40.000 4.5 5 900
78+190 40.000 4.5 5 900
78+645 40.000 4.5 5 900
78+850 40.000 4.5 5 900
79+480 40.000 4.5 5 900
80+250 40.000 4.5 5 900
80+600 40.000 4.5 5 900
80+825 40.000 4.5 5 900
81+325 40.000 4.5 5 900
82+060 40.000 4.5 5 900
82+229 40.000 4.5 5 900
83+625 40.000 4.5 5 900
84+150 40.000 4.5 5 900
84+361 40.000 4.5 5 900
85+265 40.000 4.5 5 900
85+811 40.000 4.5 5 900
86+197 40.000 4.5 5 900
87+148 40.000 4.5 5 900
87+829 40.000 4.5 5 900
88+914 40.000 4.5 5 900
89+296 40.000 4.5 5 900
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description
89+606 40.000 4.5 5 900
89+995 40.000 4.5 5 900
92+953 40.000 4.5 5 900
93+085 40.000 4.5 5 900
93+577 40.000 4.5 5 900
94+097 40.000 4.5 5 900
94+901 40.000 4.5 5 900
95+318 40.000 4.5 5 900
95+715 40.000 4.5 5 900
97+263 40.000 4.5 5 900
97+581 40.000 4.5 5 900
97+722 40.000 4.5 5 900
98+040 40.000 4.5 5 900
98+746 40.000 4.5 5 900
98+990 40.000 4.5 5 900
99+372 40.000 4.5 5 900
99+548 40.000 4.5 5 900
100+491 40.000 4.5 5 900
100+596 40.000 4.5 5 900
103+451 40.000 4.5 5 900
103+871 40.000 4.5 5 900
104+647 40.000 4.5 5 900
105+862 40.000 4.5 5 900
106+602 40.000 4.5 5 900
107+480 40.000 4.5 5 900
108+180 40.000 4.5 5 900
108+223 40.000 4.5 5 900
108+853 40.000 4.5 5 900
109+093 40.000 4.5 5 900
109+226 40.000 4.5 5 900
110+116 40.000 4.5 5 900
111+268 40.000 4.5 5 900
1111+420 40.000 4.5 5 900
113+763 40.000 4.5 5 900
114+301 40.000 4.5 5 900
116+742 40.000 4.5 5 900
117+773 40.000 4.5 5 900
117+982 40.000 4.5 5 900
118+204 40.000 4.5 5 900
119+349 40.000 4.5 5 900
120+228 40.000 4.5 5 900
120+611 40.000 4.5 5 900
120+956 40.000 4.5 5 900
122+397 40.000 4.5 5 900
123+125 40.000 4.5 5 900
125+804 40.000 4.5 5 900
126+298 40.000 4.5 5 900
127+529 40.000 4.5 5 900
127+663 40.000 4.5 5 900
128+217 40.000 4.5 5 900
129+307 40.000 4.5 5 900
130+954 40.000 4.5 5 900
131+319 40.000 4.5 5 900
131+636 40.000 4.5 5 900
131+781 40.000 4.5 5 900
132+594 40.000 4.5 5 900
132+710 40.000 4.5 5 900
133+674 40.000 4.5 5 900
143+988 40.000 4.5 5 900
145+182 40.000 4.5 5 900
145+400 40.000 4.5 5 900
146+798 40.000 4.5 5 900
146+872 40.000 4.5 5 900
148+655 40.000 4.5 5 900
150+396 40.000 4.5 5 900
151+123 40.000 4.5 5 900
152+924 40.000 4.5 5 900
155+398 40.000 4.5 5 900
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description
155+907 40.000 4.5 5 900
157+151 40.000 4.5 5 900
159+055 40.000 4.5 5 900
159+568 40.000 4.5 5 900
163+805 40.000 4.5 5 900
171+472 40.000 4.5 5 900
174+790 40.000 4.5 5 900
175+608 40.000 4.5 5 900
175+705 40.000 4.5 5 900
180+458 40.000 4.5 5 900
Total excavation 163864.8 cub. Ft.
OR 4639.43375 cub. M.

Total excavation 9002.469 Cub. M.

C-2 Plain Cement Concrete including placing, compacting, finishing & curing (Ratio 1:4:8)
Under drainage waterway section
R.D Length Width Thickness Volume
6+000 to 20+000 282.880 20No's 8.750 0.250 618.8
20+100 12 8.750 0.250 26.25
20+350 42 8.750 0.250 91.875
20+935 12 8.750 0.250 26.25
22+750 7 8.750 0.250 15.3125
24+500 12 8.750 0.250 26.25
25+765 42 8.750 0.250 91.875
26+500 12 8.750 0.250 26.25
26+835 12 8.750 0.250 26.25
28+175 12 8.750 0.250 26.25
28+650 42 8.750 0.250 91.875
29+400 12 8.750 0.250 26.25
29+800 12 8.750 0.250 26.25
29+925 12 8.750 0.250 26.25
31+060 12 8.750 0.250 26.25
31+460 12 8.750 0.250 26.25
31+500 12 8.750 0.250 26.25
31+525 12 8.750 0.250 26.25
31+855 12 8.750 0.250 26.25
33+000 82 8.750 0.250 179.375
33+600 82 8.750 0.250 179.375
33+612 12 8.750 0.250 26.25
34+235 12 8.750 0.250 26.25
34+950 12 8.750 0.250 26.25
39+725 12 8.750 0.250 26.25
39+950 12 8.750 0.250 26.25
40+925 12 8.750 0.250 26.25
41+125 12 8.750 0.250 26.25
42+575 12 8.750 0.250 26.25
44+590 22 8.500 0.250 46.75
46+220 22 8.500 0.250 46.75
47+400 22 8.500 0.250 46.75
48+575 22 8.500 0.250 46.75
49+730 12 8.500 0.250 25.5
49+850 12 8.500 0.250 25.5
51+425 12 8.500 0.250 25.5
52+075 12 8.500 0.250 25.5
52+200 12 8.500 0.250 25.5
52+450 12 8.500 0.250 25.5
52+600 12 8.500 0.250 25.5
52+935 12 8.500 0.250 25.5
54+505 42 8.500 0.250 89.25
54+775 12 8.500 0.250 25.5
55+150 22 8.500 0.250 46.75
57+115 42 8.500 0.250 89.25
58+150 42 8.500 0.250 89.25
58+750 42 8.500 0.250 89.25
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description
59+033 12 8.500 0.250 25.5
59+190 12 8.500 0.250 25.5
59+325 12 8.500 0.250 25.5
59+790 12 8.500 0.250 25.5
60+025 12 8.500 0.250 25.5
60+100 12 8.500 0.250 25.5
60+410 12 8.500 0.250 25.5
61+200 12 8.500 0.250 25.5
61+250 12 8.500 0.250 25.5
61+715 12 8.500 0.250 25.5
62+323 32 8.500 0.250 68
63+750 227 8.500 0.250 482.375
64+750 17 8.500 0.250 36.125
65+035 12 8.500 0.250 25.5
65+850 22 8.500 0.250 46.75
67+425 22 8.500 0.250 46.75
67+825 32 8.500 0.250 68
68+145 42 8.500 0.250 89.25
68+450 32 8.500 0.250 68
68+750 42 8.500 0.250 89.25
69+495 22 8.500 0.250 46.75
70+300 32 8.500 0.250 68
70+575 42 8.500 0.250 89.25
71+528 32 8.500 0.250 68
72+055 32 8.500 0.250 68
72+695 32 8.500 0.250 68
74+715 32 8.300 0.250 66.4
75+610 32 8.300 0.250 66.4
76+418 82 8.300 0.250 170.15
77+750 62 8.300 0.250 128.65
78+000 32 8.300 0.250 66.4
78+190 32 8.300 0.250 66.4
78+645 12 8.300 0.250 24.9
78+850 32 8.300 0.250 66.4
79+480 32 8.300 0.250 66.4
80+250 32 8.300 0.250 66.4
80+600 32 8.300 0.250 66.4
80+825 12 8.300 0.250 24.9
81+325 12 8.300 0.250 24.9
82+060 32 8.300 0.250 66.4
82+229 12 8.300 0.250 24.9
83+625 12 8.300 0.250 24.9
84+150 12 8.300 0.250 24.9
84+361 12 8.300 0.250 24.9
85+265 32 8.300 0.250 66.4
85+811 32 8.300 0.250 66.4
86+197 32 8.300 0.250 66.4
87+148 32 8.200 0.250 65.6
87+829 32 8.200 0.250 65.6
88+914 12 8.200 0.250 24.6
89+296 12 8.200 0.250 24.6
89+606 12 8.200 0.250 24.6
89+995 12 8.200 0.250 24.6
92+953 12 7.000 0.250 21
93+085 12 7.000 0.250 21
93+577 12 7.000 0.250 21
94+097 12 7.000 0.250 21
94+901 12 7.000 0.250 21
95+318 12 7.000 0.250 21
95+715 12 7.000 0.250 21
97+263 32 7.000 0.250 56
97+581 12 7.000 0.250 21
97+722 32 7.000 0.250 56
98+040 12 7.000 0.250 21
98+746 32 7.000 0.250 56
98+990 12 7.000 0.250 21
99+372 12 7.000 0.250 21
99+548 32 7.000 0.250 56
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description
100+491 32 7.000 0.250 56
100+596 32 7.000 0.250 56
103+451 32 7.000 0.250 56
103+871 22 7.000 0.250 38.5
104+647 32 7.000 0.250 56
105+862 12 7.000 0.250 21
106+602 12 7.000 0.250 21
107+480 12 7.000 0.250 21
108+180 32 7.000 0.250 56
108+223 12 7.000 0.250 21
108+853 12 7.000 0.250 21
109+093 32 7.000 0.250 56
109+226 12 7.000 0.250 21
110+116 32 7.000 0.250 56
111+268 12 7.000 0.250 21
111+420 12 7.000 0.250 21
113+763 14 7.000 0.250 24.5
114+301 32 7.000 0.250 56
116+742 12 7.000 0.250 21
117+773 12 7.000 0.250 21
117+982 12 7.000 0.250 21
118+204 12 7.000 0.250 21
119+349 12 7.000 0.250 21
120+228 12 7.000 0.250 21
120+611 32 7.000 0.250 56
120+956 32 7.000 0.250 56
122+397 12 7.000 0.250 21
123+125 12 7.000 0.250 21
125+804 12 7.000 0.250 21
126+298 12 7.000 0.250 21
127+529 32 7.000 0.250 56
127+663 32 7.000 0.250 56
128+217 32 6.750 0.250 54
129+307 32 6.750 0.250 54
130+954 32 6.750 0.250 54
131+319 32 6.750 0.250 54
131+636 12 6.750 0.250 20.25
131+781 32 6.750 0.250 54
132+594 32 6.750 0.250 54
132+710 32 6.750 0.250 54
133+674 12 6.750 0.250 20.25
143+988 12 6.500 0.250 19.5
145+182 12 6.500 0.250 19.5
145+400 12 6.500 0.250 19.5
146+798 12 6.500 0.250 19.5
146+872 32 6.500 0.250 52
148+655 12 6.500 0.250 19.5
150+396 12 6.300 0.250 18.9
151+123 32 6.300 0.250 50.4
152+924 12 6.300 0.250 18.9
155+398 12 6.300 0.250 18.9
155+907 12 6.300 0.250 18.9
157+151 12 6.300 0.250 18.9
159+055 12 6.000 0.250 18
159+568 12 6.000 0.250 18
163+805 12 5.700 0.250 17.1
171+472 12 5.700 0.250 17.1
174+790 12 5.000 0.250 15
175+608 12 5.000 0.250 15
175+705 32 5.000 0.250 40
180+458 5 4.500 0.250 5.625
Total excavation 8275.463 cub. Ft.
OR 234.300 cub. M
Under guide walls Length of
Length of both U/S guide both D/S Total length
R.D Width Thickness Volume
walls guide (U/S + D/S)
walls
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description

6+000 to 20+000 282.880 20No's 31.118 313.998 2.820 0.250 221.3686

20+100 14.144 31.118 45.262 2.820 0.250 31.9097


20+350 14.144 31.118 45.262 2.820 0.250 9.97152
20+935 14.144 31.118 45.262 2.820 0.250 9.97152
22+750 14.144 31.118 45.262 2.820 0.250 9.97152
24+500 14.144 31.118 45.262 2.820 0.250 9.97152
25+765 14.144 31.118 45.262 2.820 0.250 9.97152
26+500 14.144 31.118 45.262 2.820 0.250 9.97152
26+835 14.144 31.118 45.262 2.820 0.250 9.97152
28+175 14.144 31.118 45.262 2.820 0.250 9.97152
28+650 14.144 31.118 45.262 2.820 0.250 9.97152
29+400 14.144 31.118 45.262 2.820 0.250 9.97152
29+800 14.144 31.118 45.262 2.820 0.250 9.97152
29+925 14.144 31.118 45.262 2.820 0.250 9.97152
31+060 14.144 31.118 45.262 2.820 0.250 9.97152
31+460 14.144 31.118 45.262 2.820 0.250 9.97152
31+500 14.144 31.118 45.262 2.820 0.250 9.97152
31+525 14.144 31.118 45.262 2.820 0.250 9.97152
31+855 14.144 31.118 45.262 2.820 0.250 9.97152
33+000 14.144 31.118 45.262 2.820 0.250 9.97152
33+600 14.144 31.118 45.262 2.820 0.250 9.97152
33+612 14.144 31.118 45.262 2.820 0.250 9.97152
34+235 14.144 31.118 45.262 2.820 0.250 9.97152
34+950 14.144 31.118 45.262 2.820 0.250 9.97152
39+725 14.144 31.118 45.262 2.820 0.250 9.97152
39+950 14.144 31.118 45.262 2.820 0.250 9.97152
40+925 14.144 31.118 45.262 2.820 0.250 9.97152
41+125 14.144 31.118 45.262 2.820 0.250 9.97152
42+575 14.144 31.118 45.262 2.820 0.250 9.97152
44+590 14.144 31.118 45.262 2.820 0.250 9.97152
46+220 14.144 31.118 45.262 2.820 0.250 9.97152
47+400 14.144 31.118 45.262 2.820 0.250 9.97152
48+575 14.144 31.118 45.262 2.820 0.250 9.97152
49+730 14.144 31.118 45.262 2.820 0.250 9.97152
49+850 14.144 31.118 45.262 2.820 0.250 9.97152
51+425 14.144 31.118 45.262 2.820 0.250 9.97152
52+075 14.144 31.118 45.262 2.820 0.250 9.97152
52+200 14.144 31.118 45.262 2.820 0.250 9.97152
52+450 14.144 31.118 45.262 2.820 0.250 9.97152
52+600 14.144 31.118 45.262 2.820 0.250 9.97152
52+935 14.144 31.118 45.262 2.820 0.250 9.97152
54+505 14.144 31.118 45.262 2.820 0.250 9.97152
54+775 14.144 31.118 45.262 2.820 0.250 9.97152
55+150 14.144 31.118 45.262 2.820 0.250 9.97152
57+115 14.144 31.118 45.262 2.820 0.250 9.97152
58+150 14.144 31.118 45.262 2.820 0.250 9.97152
58+750 14.144 31.118 45.262 2.820 0.250 9.97152
59+033 14.144 31.118 45.262 2.820 0.250 9.97152
59+190 14.144 31.118 45.262 2.820 0.250 9.97152
59+325 14.144 31.118 45.262 2.820 0.250 9.97152
59+790 14.144 31.118 45.262 2.820 0.250 9.97152
60+025 14.144 31.118 45.262 2.820 0.250 9.97152
60+100 14.144 31.118 45.262 2.820 0.250 9.97152
60+410 14.144 31.118 45.262 2.820 0.250 9.97152
61+200 14.144 31.118 45.262 2.820 0.250 9.97152
61+250 14.144 31.118 45.262 2.820 0.250 9.97152
61+715 14.144 31.118 45.262 2.820 0.250 9.97152
62+323 14.144 31.118 45.262 2.820 0.250 9.97152
63+750 14.144 31.118 45.262 2.820 0.250 9.97152
64+750 14.144 31.118 45.262 2.820 0.250 9.97152
65+035 14.144 31.118 45.262 2.820 0.250 9.97152
65+850 14.144 31.118 45.262 2.820 0.250 9.97152
67+425 14.144 31.118 45.262 2.820 0.250 9.97152
67+825 14.144 31.118 45.262 2.820 0.250 9.97152
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description
68+145 14.144 31.118 45.262 2.820 0.250 9.97152
68+450 14.144 31.118 45.262 2.820 0.250 9.97152
68+750 14.144 31.118 45.262 2.820 0.250 9.97152
69+495 14.144 31.118 45.262 2.820 0.250 9.97152
70+300 14.144 31.118 45.262 2.820 0.250 9.97152
70+575 14.144 31.118 45.262 2.820 0.250 9.97152
71+528 14.144 31.118 45.262 2.820 0.250 9.97152
72+055 14.144 31.118 45.262 2.820 0.250 9.97152
72+695 14.144 31.118 45.262 2.820 0.250 9.97152
74+715 14.144 31.118 45.262 2.820 0.250 9.97152
75+610 14.144 31.118 45.262 2.820 0.250 9.97152
76+418 14.144 31.118 45.262 2.820 0.250 9.97152
77+750 14.144 31.118 45.262 2.820 0.250 9.97152
78+000 14.144 31.118 45.262 2.820 0.250 9.97152
78+190 14.144 31.118 45.262 2.820 0.250 9.97152
78+645 14.144 31.118 45.262 2.820 0.250 9.97152
78+850 14.144 31.118 45.262 2.820 0.250 9.97152
79+480 14.144 31.118 45.262 2.820 0.250 9.97152
80+250 14.144 31.118 45.262 2.820 0.250 9.97152
80+600 14.144 31.118 45.262 2.820 0.250 9.97152
80+825 14.144 31.118 45.262 2.820 0.250 9.97152
81+325 14.144 31.118 45.262 2.820 0.250 9.97152
82+060 14.144 31.118 45.262 2.820 0.250 9.97152
82+229 14.144 31.118 45.262 2.820 0.250 9.97152
83+625 14.144 31.118 45.262 2.820 0.250 9.97152
84+150 14.144 31.118 45.262 2.820 0.250 9.97152
84+361 14.144 31.118 45.262 2.820 0.250 9.97152
85+265 14.144 31.118 45.262 2.820 0.250 9.97152
85+811 14.144 31.118 45.262 2.820 0.250 9.97152
86+197 14.144 31.118 45.262 2.820 0.250 9.97152
87+148 14.144 31.118 45.262 2.820 0.250 9.97152
87+829 14.144 31.118 45.262 2.820 0.250 9.97152
88+914 14.144 31.118 45.262 2.820 0.250 9.97152
89+296 14.144 31.118 45.262 2.820 0.250 9.97152
89+606 14.144 31.118 45.262 2.820 0.250 9.97152
89+995 14.144 31.118 45.262 2.820 0.250 9.97152
92+953 14.144 31.118 45.262 2.820 0.250 9.97152
93+085 14.144 31.118 45.262 2.820 0.250 9.97152
93+577 14.144 31.118 45.262 2.820 0.250 9.97152
94+097 14.144 31.118 45.262 2.820 0.250 9.97152
94+901 14.144 31.118 45.262 2.820 0.250 9.97152
95+318 14.144 31.118 45.262 2.820 0.250 9.97152
95+715 14.144 31.118 45.262 2.820 0.250 9.97152
97+263 14.144 31.118 45.262 2.820 0.250 9.97152
97+581 14.144 31.118 45.262 2.820 0.250 9.97152
97+722 14.144 31.118 45.262 2.820 0.250 9.97152
98+040 14.144 31.118 45.262 2.820 0.250 9.97152
98+746 14.144 31.118 45.262 2.820 0.250 9.97152
98+990 14.144 31.118 45.262 2.820 0.250 9.97152
99+372 14.144 31.118 45.262 2.820 0.250 9.97152
99+548 14.144 31.118 45.262 2.820 0.250 9.97152
100+491 14.144 31.118 45.262 2.820 0.250 9.97152
100+596 14.144 31.118 45.262 2.820 0.250 9.97152
103+451 14.144 31.118 45.262 2.820 0.250 9.97152
103+871 14.144 31.118 45.262 2.820 0.250 9.97152
104+647 14.144 31.118 45.262 2.820 0.250 9.97152
105+862 14.144 31.118 45.262 2.820 0.250 9.97152
106+602 14.144 31.118 45.262 2.820 0.250 9.97152
107+480 14.144 31.118 45.262 2.820 0.250 9.97152
108+180 14.144 31.118 45.262 2.820 0.250 9.97152
108+223 14.144 31.118 45.262 2.820 0.250 9.97152
108+853 14.144 31.118 45.262 2.820 0.250 9.97152
109+093 14.144 31.118 45.262 2.820 0.250 9.97152
109+226 14.144 31.118 45.262 2.820 0.250 9.97152
110+116 14.144 31.118 45.262 2.820 0.250 9.97152
111+268 14.144 31.118 45.262 2.820 0.250 9.97152
111+420 14.144 31.118 45.262 2.820 0.250 9.97152
113+763 14.144 31.118 45.262 2.820 0.250 9.97152
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description
114+301 14.144 31.118 45.262 2.820 0.250 9.97152
116+742 14.144 31.118 45.262 2.820 0.250 9.97152
117+773 14.144 31.118 45.262 2.820 0.250 9.97152
117+982 14.144 31.118 45.262 2.820 0.250 9.97152
118+204 14.144 31.118 45.262 2.820 0.250 9.97152
119+349 14.144 31.118 45.262 2.820 0.250 9.97152
120+228 14.144 31.118 45.262 2.820 0.250 9.97152
120+611 14.144 31.118 45.262 2.820 0.250 9.97152
120+956 14.144 31.118 45.262 2.820 0.250 9.97152
122+397 14.144 31.118 45.262 2.820 0.250 9.97152
123+125 14.144 31.118 45.262 2.820 0.250 9.97152
125+804 14.144 31.118 45.262 2.820 0.250 9.97152
126+298 14.144 31.118 45.262 2.820 0.250 9.97152
127+529 14.144 31.118 45.262 2.820 0.250 9.97152
127+663 14.144 31.118 45.262 2.820 0.250 9.97152
128+217 14.144 31.118 45.262 2.820 0.250 9.97152
129+307 14.144 31.118 45.262 2.820 0.250 9.97152
130+954 14.144 31.118 45.262 2.820 0.250 9.97152
131+319 14.144 31.118 45.262 2.820 0.250 9.97152
131+636 14.144 31.118 45.262 2.820 0.250 9.97152
131+781 14.144 31.118 45.262 2.820 0.250 9.97152
132+594 14.144 31.118 45.262 2.820 0.250 9.97152
132+710 14.144 31.118 45.262 2.820 0.250 9.97152
133+674 14.144 31.118 45.262 2.820 0.250 9.97152
143+988 14.144 31.118 45.262 2.820 0.250 9.97152
145+182 14.144 31.118 45.262 2.820 0.250 9.97152
145+400 14.144 31.118 45.262 2.820 0.250 9.97152
146+798 14.144 31.118 45.262 2.820 0.250 9.97152
146+872 14.144 31.118 45.262 2.820 0.250 9.97152
148+655 14.144 31.118 45.262 2.820 0.250 9.97152
150+396 14.144 31.118 45.262 2.820 0.250 9.97152
151+123 14.144 31.118 45.262 2.820 0.250 9.97152
152+924 14.144 31.118 45.262 2.820 0.250 9.97152
155+398 14.144 31.118 45.262 2.820 0.250 9.97152
155+907 14.144 31.118 45.262 2.820 0.250 9.97152
157+151 14.144 31.118 45.262 2.820 0.250 9.97152
159+055 14.144 31.118 45.262 2.820 0.250 9.97152
159+568 14.144 31.118 45.262 2.820 0.250 9.97152
163+805 14.144 31.118 45.262 2.820 0.250 9.97152
171+472 14.144 31.118 45.262 2.820 0.250 9.97152
174+790 14.144 31.118 45.262 2.820 0.250 9.97152
175+608 14.144 31.118 45.262 2.820 0.250 9.97152
175+705 14.144 31.118 45.262 2.820 0.250 9.97152
180+458 14.144 31.118 45.262 2.820 0.250 9.97152
Total PCC 1:4:8 under guide walls 1988.323 cub. Ft.
OR 56.295 cub. M

Total quantity of PCC 1:4:8 under drainage waterway and guide walls 290.594 cub. M

C-3 RCC in roof slab, beam, column & other structural members, insitu or precast. Type C (1:2:4)
RCC in top slab
R.D Length Width Thickness Volume
6+000 to 20+000 200.000 20No's 6.750 1.000 1767.5
20+100 10 6.750 1.000 105
20+350 40 6.750 1.000 367.5
20+935 10 6.750 1.000 105
22+750 5 6.750 1.000 61.25
24+500 10 6.750 1.000 105
25+765 40 6.750 1.000 367.5
26+500 10 6.750 1.000 105
26+835 10 6.750 1.000 105
28+175 10 6.750 1.000 105
28+650 40 6.750 1.000 367.5
29+400 10 6.750 1.000 105
29+800 10 6.750 1.000 105
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description
29+925 10 6.750 1.000 105
31+060 10 6.750 1.000 105
31+460 10 6.750 1.000 105
31+500 10 6.750 1.000 105
31+525 10 6.750 1.000 105
31+855 10 6.750 1.000 105
33+000 80 6.750 1.000 717.5
33+600 80 6.750 1.000 717.5
33+612 10 6.750 1.000 105
34+235 10 6.750 1.000 105
34+950 10 6.750 1.000 105
39+725 10 6.750 1.000 105
39+950 10 6.750 1.000 105
40+925 10 6.750 1.000 105
41+125 10 6.750 1.000 105
42+575 10 6.750 1.000 105
44+590 20 6.500 1.000 187
46+220 20 6.500 1.000 187
47+400 20 6.500 1.000 187
48+575 20 6.500 1.000 187
49+730 10 6.500 1.000 102
49+850 10 6.500 1.000 102
51+425 10 6.500 1.000 102
52+075 10 6.500 1.000 102
52+200 10 6.500 1.000 102
52+450 10 6.500 1.000 102
52+600 10 6.500 1.000 102
52+935 10 6.500 1.000 102
54+505 40 6.500 1.000 357
54+775 10 6.500 1.000 102
55+150 20 6.500 1.000 187
57+115 40 6.500 1.000 357
58+150 40 6.500 1.000 357
58+750 40 6.500 1.000 357
59+033 10 6.500 1.000 102
59+190 10 6.500 1.000 102
59+325 10 6.500 1.000 102
59+790 10 6.500 1.000 102
60+025 10 6.500 1.000 102
60+100 10 6.500 1.000 102
60+410 10 6.500 1.000 102
61+200 10 6.500 1.000 102
61+250 10 6.500 1.000 102
61+715 10 6.500 1.000 102
62+323 30 6.500 1.000 272
63+750 225 6.500 1.000 1929.5
64+750 15 6.500 1.000 144.5
65+035 10 6.500 1.000 102
65+850 20 6.500 1.000 187
67+425 20 6.500 1.000 187
67+825 30 6.500 1.000 272
68+145 40 6.500 1.000 357
68+450 30 6.500 1.000 272
68+750 40 6.500 1.000 357
69+495 20 6.500 1.000 187
70+300 30 6.500 1.000 272
70+575 40 6.500 1.000 357
71+528 30 6.500 1.000 272
72+055 30 6.500 1.000 272
72+695 30 6.500 1.000 272
74+715 30 6.300 1.000 265.6
75+610 30 6.300 1.000 265.6
76+418 80 6.300 1.000 680.6
77+750 60 6.300 1.000 514.6
78+000 30 6.300 1.000 265.6
78+190 30 6.300 1.000 265.6
78+645 10 6.300 1.000 99.6
78+850 30 6.300 1.000 265.6
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description
79+480 30 6.300 1.000 265.6
80+250 30 6.300 1.000 265.6
80+600 30 6.300 1.000 265.6
80+825 10 6.300 1.000 99.6
81+325 10 6.300 1.000 99.6
82+060 30 6.300 1.000 265.6
82+229 10 6.300 1.000 99.6
83+625 10 6.300 1.000 99.6
84+150 10 6.300 1.000 99.6
84+361 10 6.300 1.000 99.6
85+265 30 6.300 1.000 265.6
85+811 30 6.300 1.000 265.6
86+197 30 6.300 1.000 265.6
87+148 30 6.200 1.000 262.4
87+829 30 6.200 1.000 262.4
88+914 10 6.200 1.000 98.4
89+296 10 6.200 1.000 98.4
89+606 10 6.200 1.000 98.4
89+995 10 6.200 1.000 98.4
92+953 10 5.000 1.000 84
93+085 10 5.000 1.000 84
93+577 10 5.000 1.000 84
94+097 10 5.000 1.000 84
94+901 10 5.000 1.000 84
95+318 10 5.000 1.000 84
95+715 10 5.000 1.000 84
97+263 30 5.000 1.000 224
97+581 10 5.000 1.000 84
97+722 30 5.000 1.000 224
98+040 10 5.000 1.000 84
98+746 30 5.000 1.000 224
98+990 10 5.000 1.000 84
99+372 10 5.000 1.000 84
99+548 30 5.000 1.000 224
100+491 30 5.000 1.000 224
100+596 30 5.000 1.000 224
103+451 30 5.000 1.000 224
103+871 20 5.000 1.000 154
104+647 30 5.000 1.000 224
105+862 10 5.000 1.000 84
106+602 10 5.000 1.000 84
107+480 10 5.000 1.000 84
108+180 30 5.000 1.000 224
108+223 10 5.000 1.000 84
108+853 10 5.000 1.000 84
109+093 30 5.000 1.000 224
109+226 10 5.000 1.000 84
110+116 30 5.000 1.000 224
111+268 10 5.000 1.000 84
111+420 10 5.000 1.000 84
113+763 12 5.000 1.000 98
114+301 30 5.000 1.000 224
116+742 10 5.000 1.000 84
117+773 10 5.000 1.000 84
117+982 10 5.000 1.000 84
118+204 10 5.000 1.000 84
119+349 10 5.000 1.000 84
120+228 10 5.000 1.000 84
120+611 30 5.000 1.000 224
120+956 30 5.000 1.000 224
122+397 10 5.000 1.000 84
123+125 10 5.000 1.000 84
125+804 10 5.000 1.000 84
126+298 10 5.000 1.000 84
127+529 30 5.000 1.000 224
127+663 30 5.000 1.000 224
128+217 30 4.750 1.000 216
129+307 30 4.750 1.000 216
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description
130+954 30 4.750 1.000 216
131+319 30 4.750 1.000 216
131+636 10 4.750 1.000 81
131+781 30 4.750 1.000 216
132+594 30 4.750 1.000 216
132+710 30 4.750 1.000 216
133+674 10 4.750 1.000 81
143+988 10 4.500 1.000 78
145+182 10 4.500 1.000 78
145+400 10 4.500 1.000 78
146+798 10 4.500 1.000 78
146+872 30 4.500 1.000 208
148+655 10 4.500 1.000 78
150+396 10 4.300 1.000 75.6
151+123 30 4.300 1.000 201.6
152+924 10 4.300 1.000 75.6
155+398 10 4.300 1.000 75.6
155+907 10 4.300 1.000 75.6
157+151 10 4.300 1.000 75.6
159+055 10 4.000 1.000 72
159+568 10 4.000 1.000 72
163+805 10 3.700 1.000 68.4
171+472 10 3.700 1.000 68.4
174+790 10 3.000 1.000 60
175+608 10 3.000 1.000 60
175+705 30 3.000 1.000 160
180+458 30 2.500 1.000 144
Total RCC in top slab 32515.650 cub. Ft.
OR 920.602 cub. M

C-4 RCC in raft foundation slab, base slab of column & ret. wall etc, not including in 06-06. Type C (1:2:4)

RCC in side walls

R.D Length Depth Width No. of walls Volume


6+000 to 20+000 200.000 20No's 6.000 1.000 2 2400.000
20+100 10 6.000 1.000 2 120.000
20+350 40 6.000 1.000 2 480.000
20+935 10 6.000 1.000 2 120.000
22+750 5 6.000 1.000 2 60.000
24+500 10 6.000 1.000 2 120.000
25+765 40 6.000 1.000 2 480.000
26+500 10 6.000 1.000 2 120.000
26+835 10 6.000 1.000 2 120.000
28+175 10 6.000 1.000 2 120.000
28+650 40 6.000 1.000 2 480.000
29+400 10 6.000 1.000 2 120.000
29+800 10 6.000 1.000 2 120.000
29+925 10 6.000 1.000 2 120.000
31+060 10 6.000 1.000 2 120.000
31+460 10 6.000 1.000 2 120.000
31+500 10 6.000 1.000 2 120.000
31+525 10 6.000 1.000 2 120.000
31+855 10 6.000 1.000 2 120.000
33+000 80 6.000 1.000 2 960.000
33+600 80 6.000 1.000 2 960.000
33+612 10 6.000 1.000 2 120.000
34+235 10 6.000 1.000 2 120.000
34+950 10 6.000 1.000 2 120.000
39+725 10 6.000 1.000 2 120.000
39+950 10 6.000 1.000 2 120.000
40+925 10 6.000 1.000 2 120.000
41+125 10 6.000 1.000 2 120.000
42+575 10 6.000 1.000 2 120.000
44+590 20 6.000 1.000 2 240.000
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description
46+220 20 6.000 1.000 2 240.000
47+400 20 6.000 1.000 2 240.000
48+575 20 6.000 1.000 2 240.000
49+730 10 6.000 1.000 2 120.000
49+850 10 6.000 1.000 2 120.000
51+425 10 6.000 1.000 2 120.000
52+075 10 6.000 1.000 2 120.000
52+200 10 6.000 1.000 2 120.000
52+450 10 6.000 1.000 2 120.000
52+600 10 6.000 1.000 2 120.000
52+935 10 6.000 1.000 2 120.000
54+505 40 6.000 1.000 2 480.000
54+775 10 6.000 1.000 2 120.000
55+150 20 6.000 1.000 2 240.000
57+115 40 6.000 1.000 2 480.000
58+150 40 6.000 1.000 2 480.000
58+750 40 6.000 1.000 2 480.000
59+033 10 6.000 1.000 2 120.000
59+190 10 6.000 1.000 2 120.000
59+325 10 6.000 1.000 2 120.000
59+790 10 6.000 1.000 2 120.000
60+025 10 6.000 1.000 2 120.000
60+100 10 6.000 1.000 2 120.000
60+410 10 6.000 1.000 2 120.000
61+200 10 6.000 1.000 2 120.000
61+250 10 6.000 1.000 2 120.000
61+715 10 6.000 1.000 2 120.000
62+323 30 6.000 1.000 2 360.000
63+750 225 6.000 1.000 2 2700.000
64+750 15 6.000 1.000 2 180.000
65+035 10 6.000 1.000 2 120.000
65+850 20 6.000 1.000 2 240.000
67+425 20 6.000 1.000 2 240.000
67+825 30 6.000 1.000 2 360.000
68+145 40 6.000 1.000 2 480.000
68+450 30 6.000 1.000 2 360.000
68+750 40 6.000 1.000 2 480.000
69+495 20 6.000 1.000 2 240.000
70+300 30 6.000 1.000 2 360.000
70+575 40 6.000 1.000 2 480.000
71+528 30 6.000 1.000 2 360.000
72+055 30 6.000 1.000 2 360.000
72+695 30 6.000 1.000 2 360.000
74+715 30 6.000 1.000 2 360.000
75+610 30 6.000 1.000 2 360.000
76+418 80 6.000 1.000 2 960.000
77+750 60 6.000 1.000 2 720.000
78+000 30 6.000 1.000 2 360.000
78+190 30 6.000 1.000 2 360.000
78+645 10 6.000 1.000 2 120.000
78+850 30 6.000 1.000 2 360.000
79+480 30 6.000 1.000 2 360.000
80+250 30 6.000 1.000 2 360.000
80+600 30 6.000 1.000 2 360.000
80+825 10 6.000 1.000 2 120.000
81+325 10 6.000 1.000 2 120.000
82+060 30 6.000 1.000 2 360.000
82+229 10 6.000 1.000 2 120.000
83+625 10 6.000 1.000 2 120.000
84+150 10 6.000 1.000 2 120.000
84+361 10 6.000 1.000 2 120.000
85+265 30 6.000 1.000 2 360.000
85+811 30 6.000 1.000 2 360.000
86+197 30 6.000 1.000 2 360.000
87+148 30 6.000 1.000 2 360.000
87+829 30 6.000 1.000 2 360.000
88+914 10 6.000 1.000 2 120.000
89+296 10 6.000 1.000 2 120.000
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description
89+606 10 6.000 1.000 2 120.000
89+995 10 6.000 1.000 2 120.000
92+953 10 6.000 1.000 2 120.000
93+085 10 6.000 1.000 2 120.000
93+577 10 6.000 1.000 2 120.000
94+097 10 6.000 1.000 2 120.000
94+901 10 6.000 1.000 2 120.000
95+318 10 6.000 1.000 2 120.000
95+715 10 6.000 1.000 2 120.000
97+263 30 6.000 1.000 2 360.000
97+581 10 6.000 1.000 2 120.000
97+722 30 6.000 1.000 2 360.000
98+040 10 6.000 1.000 2 120.000
98+746 30 6.000 1.000 2 360.000
98+990 10 6.000 1.000 2 120.000
99+372 10 6.000 1.000 2 120.000
99+548 30 6.000 1.000 2 360.000
100+491 30 6.000 1.000 2 360.000
100+596 30 6.000 1.000 2 360.000
103+451 30 6.000 1.000 2 360.000
103+871 20 6.000 1.000 2 240.000
104+647 30 6.000 1.000 2 360.000
105+862 10 6.000 1.000 2 120.000
106+602 10 6.000 1.000 2 120.000
107+480 10 6.000 1.000 2 120.000
108+180 30 6.000 1.000 2 360.000
108+223 10 6.000 1.000 2 120.000
108+853 10 6.000 1.000 2 120.000
109+093 30 6.000 1.000 2 360.000
109+226 10 6.000 1.000 2 120.000
110+116 30 6.000 1.000 2 360.000
111+268 10 6.000 1.000 2 120.000
111+420 10 6.000 1.000 2 120.000
113+763 12 6.000 1.000 2 144.000
114+301 30 6.000 1.000 2 360.000
116+742 10 6.000 1.000 2 120.000
117+773 10 6.000 1.000 2 120.000
117+982 10 6.000 1.000 2 120.000
118+204 10 6.000 1.000 2 120.000
119+349 10 6.000 1.000 2 120.000
120+228 10 6.000 1.000 2 120.000
120+611 30 6.000 1.000 2 360.000
120+956 30 6.000 1.000 2 360.000
122+397 10 6.000 1.000 2 120.000
123+125 10 6.000 1.000 2 120.000
125+804 10 6.000 1.000 2 120.000
126+298 10 6.000 1.000 2 120.000
127+529 30 6.000 1.000 2 360.000
127+663 30 6.000 1.000 2 360.000
128+217 30 6.000 1.000 2 360.000
129+307 30 6.000 1.000 2 360.000
130+954 30 6.000 1.000 2 360.000
131+319 30 6.000 1.000 2 360.000
131+636 10 6.000 1.000 2 120.000
131+781 30 6.000 1.000 2 360.000
132+594 30 6.000 1.000 2 360.000
132+710 30 6.000 1.000 2 360.000
133+674 10 6.000 1.000 2 120.000
143+988 10 6.000 1.000 2 120.000
145+182 10 6.000 1.000 2 120.000
145+400 10 6.000 1.000 2 120.000
146+798 10 6.000 1.000 2 120.000
146+872 30 6.000 1.000 2 360.000
148+655 10 6.000 1.000 2 120.000
150+396 10 6.000 1.000 2 120.000
151+123 30 6.000 1.000 2 360.000
152+924 10 6.000 1.000 2 120.000
155+398 10 6.000 1.000 2 120.000
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description
155+907 10 6.000 1.000 2 120.000
157+151 10 6.000 1.000 2 120.000
159+055 10 6.000 1.000 2 120.000
159+568 10 6.000 1.000 2 120.000
163+805 10 6.000 1.000 2 120.000
171+472 10 6.000 1.000 2 120.000
174+790 10 6.000 1.000 2 120.000
175+608 10 6.000 1.000 2 120.000
175+705 30 6.000 1.000 2 360.000
180+458 30 6.000 1.000 2 360.000
Total RCC in side walls 45324.000 cub. Ft.
OR 1283.239 cub. M
RCC in bottom slab
R.D Length Width Thickness Volume
6+000 to 20+000 200.000 20No's 6.750 1.000 1767.5
20+100 10 6.750 1.000 105
20+350 40 6.750 1.000 367.5
20+935 10 6.750 1.000 105
22+750 5 6.750 1.000 61.25
24+500 10 6.750 1.000 105
25+765 40 6.750 1.000 367.5
26+500 10 6.750 1.000 105
26+835 10 6.750 1.000 105
28+175 10 6.750 1.000 105
28+650 40 6.750 1.000 367.5
29+400 10 6.750 1.000 105
29+800 10 6.750 1.000 105
29+925 10 6.750 1.000 105
31+060 10 6.750 1.000 105
31+460 10 6.750 1.000 105
31+500 10 6.750 1.000 105
31+525 10 6.750 1.000 105
31+855 10 6.750 1.000 105
33+000 80 6.750 1.000 717.5
33+600 80 6.750 1.000 717.5
33+612 10 6.750 1.000 105
34+235 10 6.750 1.000 105
34+950 10 6.750 1.000 105
39+725 10 6.750 1.000 105
39+950 10 6.750 1.000 105
40+925 10 6.750 1.000 105
41+125 10 6.750 1.000 105
42+575 10 6.750 1.000 105
44+590 20 6.500 1.000 187
46+220 20 6.500 1.000 187
47+400 20 6.500 1.000 187
48+575 20 6.500 1.000 187
49+730 10 6.500 1.000 102
49+850 10 6.500 1.000 102
51+425 10 6.500 1.000 102
52+075 10 6.500 1.000 102
52+200 10 6.500 1.000 102
52+450 10 6.500 1.000 102
52+600 10 6.500 1.000 102
52+935 10 6.500 1.000 102
54+505 40 6.500 1.000 357
54+775 10 6.500 1.000 102
55+150 20 6.500 1.000 187
57+115 40 6.500 1.000 357
58+150 40 6.500 1.000 357
58+750 40 6.500 1.000 357
59+033 10 6.500 1.000 102
59+190 10 6.500 1.000 102
59+325 10 6.500 1.000 102
59+790 10 6.500 1.000 102
60+025 10 6.500 1.000 102
60+100 10 6.500 1.000 102
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description
60+410 10 6.500 1.000 102
61+200 10 6.500 1.000 102
61+250 10 6.500 1.000 102
61+715 10 6.500 1.000 102
62+323 30 6.500 1.000 272
63+750 225 6.500 1.000 1929.5
64+750 15 6.500 1.000 144.5
65+035 10 6.500 1.000 102
65+850 20 6.500 1.000 187
67+425 20 6.500 1.000 187
67+825 30 6.500 1.000 272
68+145 40 6.500 1.000 357
68+450 30 6.500 1.000 272
68+750 40 6.500 1.000 357
69+495 20 6.500 1.000 187
70+300 30 6.500 1.000 272
70+575 40 6.500 1.000 357
71+528 30 6.500 1.000 272
72+055 30 6.500 1.000 272
72+695 30 6.500 1.000 272
74+715 30 6.300 1.000 265.6
75+610 30 6.300 1.000 265.6
76+418 80 6.300 1.000 680.6
77+750 60 6.300 1.000 514.6
78+000 30 6.300 1.000 265.6
78+190 30 6.300 1.000 265.6
78+645 10 6.300 1.000 99.6
78+850 30 6.300 1.000 265.6
79+480 30 6.300 1.000 265.6
80+250 30 6.300 1.000 265.6
80+600 30 6.300 1.000 265.6
80+825 10 6.300 1.000 99.6
81+325 10 6.300 1.000 99.6
82+060 30 6.300 1.000 265.6
82+229 10 6.300 1.000 99.6
83+625 10 6.300 1.000 99.6
84+150 10 6.300 1.000 99.6
84+361 10 6.300 1.000 99.6
85+265 30 6.300 1.000 265.6
85+811 30 6.300 1.000 265.6
86+197 30 6.300 1.000 265.6
87+148 30 6.200 1.000 262.4
87+829 30 6.200 1.000 262.4
88+914 10 6.200 1.000 98.4
89+296 10 6.200 1.000 98.4
89+606 10 6.200 1.000 98.4
89+995 10 6.200 1.000 98.4
92+953 10 5.000 1.000 84
93+085 10 5.000 1.000 84
93+577 10 5.000 1.000 84
94+097 10 5.000 1.000 84
94+901 10 5.000 1.000 84
95+318 10 5.000 1.000 84
95+715 10 5.000 1.000 84
97+263 30 5.000 1.000 224
97+581 10 5.000 1.000 84
97+722 30 5.000 1.000 224
98+040 10 5.000 1.000 84
98+746 30 5.000 1.000 224
98+990 10 5.000 1.000 84
99+372 10 5.000 1.000 84
99+548 30 5.000 1.000 224
100+491 30 5.000 1.000 224
100+596 30 5.000 1.000 224
103+451 30 5.000 1.000 224
103+871 20 5.000 1.000 154
104+647 30 5.000 1.000 224
105+862 10 5.000 1.000 84
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description
106+602 10 5.000 1.000 84
107+480 10 5.000 1.000 84
108+180 30 5.000 1.000 224
108+223 10 5.000 1.000 84
108+853 10 5.000 1.000 84
109+093 30 5.000 1.000 224
109+226 10 5.000 1.000 84
110+116 30 5.000 1.000 224
111+268 10 5.000 1.000 84
111+420 10 5.000 1.000 84
113+763 12 5.000 1.000 98
114+301 30 5.000 1.000 224
116+742 10 5.000 1.000 84
117+773 10 5.000 1.000 84
117+982 10 5.000 1.000 84
118+204 10 5.000 1.000 84
119+349 10 5.000 1.000 84
120+228 10 5.000 1.000 84
120+611 30 5.000 1.000 224
120+956 30 5.000 1.000 224
122+397 10 5.000 1.000 84
123+125 10 5.000 1.000 84
125+804 10 5.000 1.000 84
126+298 10 5.000 1.000 84
127+529 30 5.000 1.000 224
127+663 30 5.000 1.000 224
128+217 30 4.750 1.000 216
129+307 30 4.750 1.000 216
130+954 30 4.750 1.000 216
131+319 30 4.750 1.000 216
131+636 10 4.750 1.000 81
131+781 30 4.750 1.000 216
132+594 30 4.750 1.000 216
132+710 30 4.750 1.000 216
133+674 10 4.750 1.000 81
143+988 10 4.500 1.000 78
145+182 10 4.500 1.000 78
145+400 10 4.500 1.000 78
146+798 10 4.500 1.000 78
146+872 30 4.500 1.000 208
148+655 10 4.500 1.000 78
150+396 10 4.300 1.000 75.6
151+123 30 4.300 1.000 201.6
152+924 10 4.300 1.000 75.6
155+398 10 4.300 1.000 75.6
155+907 10 4.300 1.000 75.6
157+151 10 4.300 1.000 75.6
159+055 10 4.000 1.000 72
159+568 10 4.000 1.000 72
163+805 10 3.700 1.000 68.4
171+472 10 3.700 1.000 68.4
174+790 10 3.000 1.000 60
175+608 10 3.000 1.000 60
175+705 30 3.000 1.000 160
180+458 30 2.500 1.000 144
Total RCC in bottom slab 32515.650 cub. Ft.
OR 920.602 cub. M

RCC in head wall


R.D Drainage waterway depth Volume
Thickness Width No. of sides
+ F.B
6+000 to 20+000 60.000 20No's 1.000 10.75 2 1290.000
20+100 3.000 1.000 10.75 2 64.500
20+350 3.000 1.000 10.75 2 64.500
20+935 4.000 1.000 10.75 2 86.000
22+750 2.200 1.000 10.75 2 47.300
24+500 3.500 1.000 10.75 2 75.250
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description
25+765 4.000 1.000 10.75 2 86.000
26+500 2.500 1.000 10.75 2 53.750
26+835 2.500 1.000 10.75 2 53.750
28+175 3.500 1.000 10.75 2 75.250
28+650 4.000 1.000 10.75 2 86.000
29+400 2.500 1.000 10.75 2 53.750
29+800 2.500 1.000 10.75 2 53.750
29+925 3.500 1.000 10.75 2 75.250
31+060 3.500 1.000 10.75 2 75.250
31+460 3.500 1.000 10.75 2 75.250
31+500 3.500 1.000 10.75 2 75.250
31+525 3.500 1.000 10.75 2 75.250
31+855 3.500 1.000 10.75 2 75.250
33+000 4.000 1.000 10.75 2 86.000
33+600 4.000 1.000 10.75 2 86.000
33+612 3.500 1.000 10.75 2 75.250
34+235 2.500 1.000 10.75 2 53.750
34+950 3.500 1.000 10.75 2 75.250
39+725 2.500 1.000 10.75 2 53.750
39+950 3.500 1.000 10.75 2 75.250
40+925 3.500 1.000 10.75 2 75.250
41+125 2.500 1.000 10.75 2 53.750
42+575 2.500 1.000 10.75 2 53.750
44+590 4.000 1.000 10.5 2 84.000
46+220 4.000 1.000 10.5 2 84.000
47+400 4.000 1.000 10.5 2 84.000
48+575 4.000 1.000 10.5 2 84.000
49+730 2.500 1.000 10.5 2 52.500
49+850 2.500 1.000 10.5 2 52.500
51+425 2.500 1.000 10.5 2 52.500
52+075 2.500 1.000 10.5 2 52.500
52+200 2.500 1.000 10.5 2 52.500
52+450 2.500 1.000 10.5 2 52.500
52+600 2.500 1.000 10.5 2 52.500
52+935 2.500 1.000 10.5 2 52.500
54+505 4.000 1.000 10.5 2 84.000
54+775 2.500 1.000 10.5 2 52.500
55+150 4.000 1.000 10.5 2 84.000
57+115 4.000 1.000 10.5 2 84.000
58+150 4.000 1.000 10.5 2 84.000
58+750 4.000 1.000 10.5 2 84.000
59+033 4.000 1.000 10.5 2 84.000
59+190 4.000 1.000 10.5 2 84.000
59+325 4.000 1.000 10.5 2 84.000
59+790 3.500 1.000 10.5 2 73.500
60+025 2.500 1.000 10.5 2 52.500
60+100 2.500 1.000 10.5 2 52.500
60+410 3.500 1.000 10.5 2 73.500
61+200 3.500 1.000 10.5 2 73.500
61+250 2.500 1.000 10.5 2 52.500
61+715 3.500 1.000 10.5 2 73.500
62+323 3.500 1.000 10.5 2 73.500
63+750 4.000 1.000 10.5 2 84.000
64+750 4.000 1.000 10.5 2 84.000
65+035 3.500 1.000 10.5 2 73.500
65+850 4.000 1.000 10.5 2 84.000
67+425 4.000 1.000 10.5 2 84.000
67+825 3.500 1.000 10.5 2 73.500
68+145 4.000 1.000 10.5 2 84.000
68+450 3.500 1.000 10.5 2 73.500
68+750 4.000 1.000 10.5 2 84.000
69+495 4.000 1.000 10.5 2 84.000
70+300 3.500 1.000 10.5 2 73.500
70+575 4.000 1.000 10.5 2 84.000
71+528 3.500 1.000 10.5 2 73.500
72+055 3.500 1.000 10.5 2 73.500
72+695 3.500 1.000 10.5 2 73.500
74+715 3.500 1.000 10.3 2 72.100
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description
75+610 3.500 1.000 10.3 2 72.100
76+418 4.000 1.000 10.3 2 82.400
77+750 4.000 1.000 10.3 2 82.400
78+000 3.500 1.000 10.3 2 72.100
78+190 3.500 1.000 10.3 2 72.100
78+645 2.500 1.000 10.3 2 51.500
78+850 3.500 1.000 10.3 2 72.100
79+480 3.500 1.000 10.3 2 72.100
80+250 3.500 1.000 10.3 2 72.100
80+600 3.500 1.000 10.3 2 72.100
80+825 3.500 1.000 10.3 2 72.100
81+325 3.500 1.000 10.3 2 72.100
82+060 3.500 1.000 10.3 2 72.100
82+229 2.500 1.000 10.3 2 51.500
83+625 2.500 1.000 10.3 2 51.500
84+150 3.500 1.000 10.3 2 72.100
84+361 3.500 1.000 10.3 2 72.100
85+265 3.500 1.000 10.3 2 72.100
85+811 3.500 1.000 10.3 2 72.100
86+197 3.500 1.000 10.3 2 72.100
87+148 3.500 1.000 10.2 2 71.400
87+829 3.500 1.000 10.2 2 71.400
88+914 3.500 1.000 10.2 2 71.400
89+296 3.500 1.000 10.2 2 71.400
89+606 3.500 1.000 10.2 2 71.400
89+995 3.500 1.000 10.2 2 71.400
92+953 2.500 1.000 9 2 45.000
93+085 2.500 1.000 9 2 45.000
93+577 2.500 1.000 9 2 45.000
94+097 2.500 1.000 9 2 45.000
94+901 2.500 1.000 9 2 45.000
95+318 3.500 1.000 9 2 63.000
95+715 3.500 1.000 9 2 63.000
97+263 3.500 1.000 9 2 63.000
97+581 3.500 1.000 9 2 63.000
97+722 3.500 1.000 9 2 63.000
98+040 2.500 1.000 9 2 45.000
98+746 3.500 1.000 9 2 63.000
98+990 3.500 1.000 9 2 63.000
99+372 3.500 1.000 9 2 63.000
99+548 3.500 1.000 9 2 63.000
100+491 3.500 1.000 9 2 63.000
100+596 3.500 1.000 9 2 63.000
103+451 3.500 1.000 9 2 63.000
103+871 4.000 1.000 9 2 72.000
104+647 4.000 1.000 9 2 72.000
105+862 3.500 1.000 9 2 63.000
106+602 3.500 1.000 9 2 63.000
107+480 3.500 1.000 9 2 63.000
108+180 3.500 1.000 9 2 63.000
108+223 4.000 1.000 9 2 72.000
108+853 4.000 1.000 9 2 72.000
109+093 3.500 1.000 9 2 63.000
109+226 2.500 1.000 9 2 45.000
110+116 3.500 1.000 9 2 63.000
111+268 2.500 1.000 9 2 45.000
111+420 2.500 1.000 9 2 45.000
113+763 4.000 1.000 9 2 72.000
114+301 3.500 1.000 9 2 63.000
116+742 2.500 1.000 9 2 45.000
117+773 3.500 1.000 9 2 63.000
117+982 2.500 1.000 9 2 45.000
118+204 2.500 1.000 9 2 45.000
119+349 3.500 1.000 9 2 63.000
120+228 3.500 1.000 9 2 63.000
120+611 3.500 1.000 9 2 63.000
120+956 3.500 1.000 9 2 63.000
122+397 3.500 1.000 9 2 63.000
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description
123+125 3.500 1.000 9 2 63.000
125+804 3.500 1.000 9 2 63.000
126+298 3.500 1.000 9 2 63.000
127+529 3.500 1.000 9 2 63.000
127+663 3.500 1.000 9 2 63.000
128+217 3.500 1.000 8.75 2 61.250
129+307 3.500 1.000 8.75 2 61.250
130+954 3.500 1.000 8.75 2 61.250
131+319 3.500 1.000 8.75 2 61.250
131+636 3.500 1.000 8.75 2 61.250
131+781 3.500 1.000 8.75 2 61.250
132+594 3.500 1.000 8.75 2 61.250
132+710 3.500 1.000 8.75 2 61.250
133+674 2.500 1.000 8.75 2 43.750
143+988 3.500 1.000 8.5 2 59.500
145+182 3.500 1.000 8.5 2 59.500
145+400 3.500 1.000 8.5 2 59.500
146+798 2.500 1.000 8.5 2 42.500
146+872 3.500 1.000 8.5 2 59.500
148+655 2.500 1.000 8.5 2 42.500
150+396 2.500 1.000 8.3 2 41.500
151+123 3.500 1.000 8.3 2 58.100
152+924 2.500 1.000 8.3 2 41.500
155+398 3.500 1.000 8.3 2 58.100
155+907 3.500 1.000 8.3 2 58.100
157+151 3.500 1.000 8.3 2 58.100
159+055 3.500 1.000 8 2 56.000
159+568 3.500 1.000 8 2 56.000
163+805 3.500 1.000 7.7 2 53.900
171+472 3.500 1.000 7.7 2 53.900
174+790 2.500 1.000 7 2 35.000
175+608 2.500 1.000 7 2 35.000
175+705 3.500 1.000 7 2 49.000
180+458 3.500 1.000 6.5 2 45.500
Total RCC in head wall 12669.050 cub. Ft.
OR 358.693 cub. M
RCC in D/S guide walls
R.D Length (11/cos 45) Thickness Height No. of walls Volume
6+000 to 20+000 311.180 20No's 1.000 14 2 8713.040
20+100 15.559 1.000 14 2 435.644
20+350 15.559 1.000 14 2 435.644
20+935 15.559 1.000 15 2 466.761
22+750 15.559 1.000 13.7 2 426.308
24+500 15.559 1.000 15 2 466.761
25+765 15.559 1.000 15 2 466.761
26+500 15.559 1.000 14 2 435.644
26+835 15.559 1.000 14 2 435.644
28+175 15.559 1.000 15 2 466.761
28+650 15.559 1.000 15 2 466.761
29+400 15.559 1.000 14 2 435.644
29+800 15.559 1.000 14 2 435.644
29+925 15.559 1.000 15 2 466.761
31+060 15.559 1.000 15 2 466.761
31+460 15.559 1.000 15 2 466.761
31+500 15.559 1.000 15 2 466.761
31+525 15.559 1.000 15 2 466.761
31+855 15.559 1.000 15 2 466.761
33+000 15.559 1.000 15 2 466.761
33+600 15.559 1.000 15 2 466.761
33+612 15.559 1.000 15 2 466.761
34+235 15.559 1.000 14 2 435.644
34+950 15.559 1.000 15 2 466.761
39+725 15.559 1.000 14 2 435.644
39+950 15.559 1.000 15 2 466.761
40+925 15.559 1.000 15 2 466.761
41+125 15.559 1.000 14 2 435.644
42+575 15.559 1.000 14 2 435.644
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description
44+590 15.559 1.000 15 2 466.761
46+220 15.559 1.000 15 2 466.761
47+400 15.559 1.000 15 2 466.761
48+575 15.559 1.000 15 2 466.761
49+730 15.559 1.000 14 2 435.644
49+850 15.559 1.000 14 2 435.644
51+425 15.559 1.000 14 2 435.644
52+075 15.559 1.000 14 2 435.644
52+200 15.559 1.000 14 2 435.644
52+450 15.559 1.000 14 2 435.644
52+600 15.559 1.000 14 2 435.644
52+935 15.559 1.000 14 2 435.644
54+505 15.559 1.000 15 2 466.761
54+775 15.559 1.000 14 2 435.644
55+150 15.559 1.000 15 2 466.761
57+115 15.559 1.000 15 2 466.761
58+150 15.559 1.000 15 2 466.761
58+750 15.559 1.000 15 2 466.761
59+033 15.559 1.000 15 2 466.761
59+190 15.559 1.000 15 2 466.761
59+325 15.559 1.000 15 2 466.761
59+790 15.559 1.000 15 2 466.761
60+025 15.559 1.000 14 2 435.644
60+100 15.559 1.000 14 2 435.644
60+410 15.559 1.000 15 2 466.761
61+200 15.559 1.000 15 2 466.761
61+250 15.559 1.000 14 2 435.644
61+715 15.559 1.000 15 2 466.761
62+323 15.559 1.000 14.5 2 451.202
63+750 15.559 1.000 15 2 466.761
64+750 15.559 1.000 15 2 466.761
65+035 15.559 1.000 15 2 466.761
65+850 15.559 1.000 15 2 466.761
67+425 15.559 1.000 15 2 466.761
67+825 15.559 1.000 14.5 2 451.202
68+145 15.559 1.000 15 2 466.761
68+450 15.559 1.000 14.5 2 451.202
68+750 15.559 1.000 15 2 466.761
69+495 15.559 1.000 15 2 466.761
70+300 15.559 1.000 14.5 2 451.202
70+575 15.559 1.000 15 2 466.761
71+528 15.559 1.000 14.5 2 451.202
72+055 15.559 1.000 14.5 2 451.202
72+695 15.559 1.000 14.5 2 451.202
74+715 15.559 1.000 14.5 2 451.202
75+610 15.559 1.000 14.5 2 451.202
76+418 15.559 1.000 15 2 466.761
77+750 15.559 1.000 15 2 466.761
78+000 15.559 1.000 14.5 2 451.202
78+190 15.559 1.000 14.5 2 451.202
78+645 15.559 1.000 14 2 435.644
78+850 15.559 1.000 14.5 2 451.202
79+480 15.559 1.000 14.5 2 451.202
80+250 15.559 1.000 14.5 2 451.202
80+600 15.559 1.000 14.5 2 451.202
80+825 15.559 1.000 15 2 466.761
81+325 15.559 1.000 15 2 466.761
82+060 15.559 1.000 14.5 2 451.202
82+229 15.559 1.000 14 2 435.644
83+625 15.559 1.000 14 2 435.644
84+150 15.559 1.000 15 2 466.761
84+361 15.559 1.000 15 2 466.761
85+265 15.559 1.000 14.5 2 451.202
85+811 15.559 1.000 14.5 2 451.202
86+197 15.559 1.000 14.5 2 451.202
87+148 15.559 1.000 14.5 2 451.202
87+829 15.559 1.000 14.5 2 451.202
88+914 15.559 1.000 15 2 466.761
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description
89+296 15.559 1.000 15 2 466.761
89+606 15.559 1.000 15 2 466.761
89+995 15.559 1.000 15 2 466.761
92+953 15.559 1.000 14 2 435.644
93+085 15.559 1.000 14 2 435.644
93+577 15.559 1.000 14 2 435.644
94+097 15.559 1.000 14 2 435.644
94+901 15.559 1.000 14 2 435.644
95+318 15.559 1.000 15 2 466.761
95+715 15.559 1.000 15 2 466.761
97+263 15.559 1.000 14.5 2 451.202
97+581 15.559 1.000 15 2 466.761
97+722 15.559 1.000 14.5 2 451.202
98+040 15.559 1.000 14 2 435.644
98+746 15.559 1.000 14.5 2 451.202
98+990 15.559 1.000 15 2 466.761
99+372 15.559 1.000 15 2 466.761
99+548 15.559 1.000 14.5 2 451.202
100+491 15.559 1.000 14.5 2 451.202
100+596 15.559 1.000 14.5 2 451.202
103+451 15.559 1.000 14.5 2 451.202
103+871 15.559 1.000 15 2 466.761
104+647 15.559 1.000 15 2 466.761
105+862 15.559 1.000 15 2 466.761
106+602 15.559 1.000 15 2 466.761
107+480 15.559 1.000 15 2 466.761
108+180 15.559 1.000 14.5 2 451.202
108+223 15.559 1.000 15 2 466.761
108+853 15.559 1.000 15 2 466.761
109+093 15.559 1.000 14.5 2 451.202
109+226 15.559 1.000 14 2 435.644
110+116 15.559 1.000 14.5 2 451.202
111+268 15.559 1.000 14 2 435.644
111+420 15.559 1.000 14 2 435.644
113+763 15.559 1.000 15 2 466.761
114+301 15.559 1.000 14.5 2 451.202
116+742 15.559 1.000 14 2 435.644
117+773 15.559 1.000 15 2 466.761
117+982 15.559 1.000 14 2 435.644
118+204 15.559 1.000 14 2 435.644
119+349 15.559 1.000 15 2 466.761
120+228 15.559 1.000 15 2 466.761
120+611 15.559 1.000 14.5 2 451.202
120+956 15.559 1.000 14.5 2 451.202
122+397 15.559 1.000 15 2 466.761
123+125 15.559 1.000 15 2 466.761
125+804 15.559 1.000 15 2 466.761
126+298 15.559 1.000 15 2 466.761
127+529 15.559 1.000 14.5 2 451.202
127+663 15.559 1.000 14.5 2 451.202
128+217 15.559 1.000 14.5 2 451.202
129+307 15.559 1.000 14.5 2 451.202
130+954 15.559 1.000 14.5 2 451.202
131+319 15.559 1.000 14.5 2 451.202
131+636 15.559 1.000 15 2 466.761
131+781 15.559 1.000 14.5 2 451.202
132+594 15.559 1.000 14.5 2 451.202
132+710 15.559 1.000 14.5 2 451.202
133+674 15.559 1.000 14 2 435.644
143+988 15.559 1.000 15 2 466.761
145+182 15.559 1.000 15 2 466.761
145+400 15.559 1.000 15 2 466.761
146+798 15.559 1.000 14 2 435.644
146+872 15.559 1.000 14.5 2 451.202
148+655 15.559 1.000 14 2 435.644
150+396 15.559 1.000 14 2 435.644
151+123 15.559 1.000 14.5 2 451.202
152+924 15.559 1.000 14 2 435.644
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description
155+398 15.559 1.000 15 2 466.761
155+907 15.559 1.000 15 2 466.761
157+151 15.559 1.000 15 2 466.761
159+055 15.559 1.000 15 2 466.761
159+568 15.559 1.000 15 2 466.761
163+805 15.559 1.000 15 2 466.761
171+472 15.559 1.000 15 2 466.761
174+790 15.559 1.000 14 2 435.644
175+608 15.559 1.000 14 2 435.644
175+705 15.559 1.000 14.5 2 451.202
180+458 15.559 1.000 14.5 2 451.202
Total RCC in D/S guide walls 88255.331 cub. Ft.
OR 2498.735 cub. M
RCC in U/S guide walls
R.D Length (5/cos 45) Thickness Height No. of walls Volume
6+000 to 20+000 141.440 20No's 1.000 14 2 3960.320
20+100 7.072 1.000 14 2 198.020
20+350 7.072 1.000 14 2 198.020
20+935 7.072 1.000 15 2 212.164
22+750 7.072 1.000 13.7 2 193.777
24+500 7.072 1.000 15 2 212.164
25+765 7.072 1.000 15 2 212.164
26+500 7.072 1.000 14 2 198.020
26+835 7.072 1.000 14 2 198.020
28+175 7.072 1.000 15 2 212.164
28+650 7.072 1.000 15 2 212.164
29+400 7.072 1.000 14 2 198.020
29+800 7.072 1.000 14 2 198.020
29+925 7.072 1.000 15 2 212.164
31+060 7.072 1.000 15 2 212.164
31+460 7.072 1.000 15 2 212.164
31+500 7.072 1.000 15 2 212.164
31+525 7.072 1.000 15 2 212.164
31+855 7.072 1.000 15 2 212.164
33+000 7.072 1.000 15 2 212.164
33+600 7.072 1.000 15 2 212.164
33+612 7.072 1.000 15 2 212.164
34+235 7.072 1.000 14 2 198.020
34+950 7.072 1.000 15 2 212.164
39+725 7.072 1.000 14 2 198.020
39+950 7.072 1.000 15 2 212.164
40+925 7.072 1.000 15 2 212.164
41+125 7.072 1.000 14 2 198.020
42+575 7.072 1.000 14 2 198.020
44+590 7.072 1.000 15 2 212.164
46+220 7.072 1.000 15 2 212.164
47+400 7.072 1.000 15 2 212.164
48+575 7.072 1.000 15 2 212.164
49+730 7.072 1.000 14 2 198.020
49+850 7.072 1.000 14 2 198.020
51+425 7.072 1.000 14 2 198.020
52+075 7.072 1.000 14 2 198.020
52+200 7.072 1.000 14 2 198.020
52+450 7.072 1.000 14 2 198.020
52+600 7.072 1.000 14 2 198.020
52+935 7.072 1.000 14 2 198.020
54+505 7.072 1.000 15 2 212.164
54+775 7.072 1.000 14 2 198.020
55+150 7.072 1.000 15 2 212.164
57+115 7.072 1.000 15 2 212.164
58+150 7.072 1.000 15 2 212.164
58+750 7.072 1.000 15 2 212.164
59+033 7.072 1.000 15 2 212.164
59+190 7.072 1.000 15 2 212.164
59+325 7.072 1.000 15 2 212.164
59+790 7.072 1.000 15 2 212.164
60+025 7.072 1.000 14 2 198.020
60+100 7.072 1.000 14 2 198.020
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description
60+410 7.072 1.000 15 2 212.164
61+200 7.072 1.000 15 2 212.164
61+250 7.072 1.000 14 2 198.020
61+715 7.072 1.000 15 2 212.164
62+323 7.072 1.000 14.5 2 205.092
63+750 7.072 1.000 15 2 212.164
64+750 7.072 1.000 15 2 212.164
65+035 7.072 1.000 15 2 212.164
65+850 7.072 1.000 15 2 212.164
67+425 7.072 1.000 15 2 212.164
67+825 7.072 1.000 14.5 2 205.092
68+145 7.072 1.000 15 2 212.164
68+450 7.072 1.000 14.5 2 205.092
68+750 7.072 1.000 15 2 212.164
69+495 7.072 1.000 15 2 212.164
70+300 7.072 1.000 14.5 2 205.092
70+575 7.072 1.000 15 2 212.164
71+528 7.072 1.000 14.5 2 205.092
72+055 7.072 1.000 14.5 2 205.092
72+695 7.072 1.000 14.5 2 205.092
74+715 7.072 1.000 14.5 2 205.092
75+610 7.072 1.000 14.5 2 205.092
76+418 7.072 1.000 15 2 212.164
77+750 7.072 1.000 15 2 212.164
78+000 7.072 1.000 14.5 2 205.092
78+190 7.072 1.000 14.5 2 205.092
78+645 7.072 1.000 14 2 198.020
78+850 7.072 1.000 14.5 2 205.092
79+480 7.072 1.000 14.5 2 205.092
80+250 7.072 1.000 14.5 2 205.092
80+600 7.072 1.000 14.5 2 205.092
80+825 7.072 1.000 15 2 212.164
81+325 7.072 1.000 15 2 212.164
82+060 7.072 1.000 14.5 2 205.092
82+229 7.072 1.000 14 2 198.020
83+625 7.072 1.000 14 2 198.020
84+150 7.072 1.000 15 2 212.164
84+361 7.072 1.000 15 2 212.164
85+265 7.072 1.000 14.5 2 205.092
85+811 7.072 1.000 14.5 2 205.092
86+197 7.072 1.000 14.5 2 205.092
87+148 7.072 1.000 14.5 2 205.092
87+829 7.072 1.000 14.5 2 205.092
88+914 7.072 1.000 15 2 212.164
89+296 7.072 1.000 15 2 212.164
89+606 7.072 1.000 15 2 212.164
89+995 7.072 1.000 15 2 212.164
92+953 7.072 1.000 14 2 198.020
93+085 7.072 1.000 14 2 198.020
93+577 7.072 1.000 14 2 198.020
94+097 7.072 1.000 14 2 198.020
94+901 7.072 1.000 14 2 198.020
95+318 7.072 1.000 15 2 212.164
95+715 7.072 1.000 15 2 212.164
97+263 7.072 1.000 14.5 2 205.092
97+581 7.072 1.000 15 2 212.164
97+722 7.072 1.000 14.5 2 205.092
98+040 7.072 1.000 14 2 198.020
98+746 7.072 1.000 14.5 2 205.092
98+990 7.072 1.000 15 2 212.164
99+372 7.072 1.000 15 2 212.164
99+548 7.072 1.000 14.5 2 205.092
100+491 7.072 1.000 14.5 2 205.092
100+596 7.072 1.000 14.5 2 205.092
103+451 7.072 1.000 14.5 2 205.092
103+871 7.072 1.000 15 2 212.164
104+647 7.072 1.000 15 2 212.164
105+862 7.072 1.000 15 2 212.164
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description
106+602 7.072 1.000 15 2 212.164
107+480 7.072 1.000 15 2 212.164
108+180 7.072 1.000 14.5 2 205.092
108+223 7.072 1.000 15 2 212.164
108+853 7.072 1.000 15 2 212.164
109+093 7.072 1.000 14.5 2 205.092
109+226 7.072 1.000 14 2 198.020
110+116 7.072 1.000 14.5 2 205.092
111+268 7.072 1.000 14 2 198.020
111+420 7.072 1.000 14 2 198.020
113+763 7.072 1.000 15 2 212.164
114+301 7.072 1.000 14.5 2 205.092
116+742 7.072 1.000 14 2 198.020
117+773 7.072 1.000 15 2 212.164
117+982 7.072 1.000 14 2 198.020
118+204 7.072 1.000 14 2 198.020
119+349 7.072 1.000 15 2 212.164
120+228 7.072 1.000 15 2 212.164
120+611 7.072 1.000 14.5 2 205.092
120+956 7.072 1.000 14.5 2 205.092
122+397 7.072 1.000 15 2 212.164
123+125 7.072 1.000 15 2 212.164
125+804 7.072 1.000 15 2 212.164
126+298 7.072 1.000 15 2 212.164
127+529 7.072 1.000 14.5 2 205.092
127+663 7.072 1.000 14.5 2 205.092
128+217 7.072 1.000 14.5 2 205.092
129+307 7.072 1.000 14.5 2 205.092
130+954 7.072 1.000 14.5 2 205.092
131+319 7.072 1.000 14.5 2 205.092
131+636 7.072 1.000 15 2 212.164
131+781 7.072 1.000 14.5 2 205.092
132+594 7.072 1.000 14.5 2 205.092
132+710 7.072 1.000 14.5 2 205.092
133+674 7.072 1.000 14 2 198.020
143+988 7.072 1.000 15 2 212.164
145+182 7.072 1.000 15 2 212.164
145+400 7.072 1.000 15 2 212.164
146+798 7.072 1.000 14 2 198.020
146+872 7.072 1.000 14.5 2 205.092
148+655 7.072 1.000 14 2 198.020
150+396 7.072 1.000 14 2 198.020
151+123 7.072 1.000 14.5 2 205.092
152+924 7.072 1.000 14 2 198.020
155+398 7.072 1.000 15 2 212.164
155+907 7.072 1.000 15 2 212.164
157+151 7.072 1.000 15 2 212.164
159+055 7.072 1.000 15 2 212.164
159+568 7.072 1.000 15 2 212.164
163+805 7.072 1.000 15 2 212.164
171+472 7.072 1.000 15 2 212.164
174+790 7.072 1.000 14 2 198.020
175+608 7.072 1.000 14 2 198.020
175+705 7.072 1.000 14.5 2 205.092
180+458 7.072 1.000 14.5 2 205.092
Total RCC in U/S guide walls 40115.907 cub. Ft.
OR 1135.784 cub. M

Total RCC in raft foundation slab, base slab of column & ret. wall etc 218879.938 cub. Ft.
Total RCC in raft foundation slab, base slab of column & ret. wall etc 6197.054 cub. M

C-5 Supply & fabricate M.S. reinforcement for cement concrete (Hot rolled deformed bars Grade 40)

Steel Quantity (Grade 40)


Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description

Total RCC in roof slab, beam, column & other structural members, insitu or precast 920.602

Total RCC in raft foundation slab, base slab of column & ret. wall etc 6197.054

Total RCC quantity 7117.66 cum

Take 1.3% of RCC quantity 726.474 tonnes

C-6 Erecting & removing formwork to concrete in any shape / position (Vertical)

Along
Total
R.D Length Width Height length both Face & back formwork
sides
6+000 to 20+000 800.000 20No's 1.500 5.000 8000.000 15.000 8015.000

20+100 40.000 1.500 5.000 400.000 15.000 415.000


20+350 40.000 1.500 5.000 400.000 15.000 415.000
20+935 40.000 1.500 5.000 400.000 15.000 415.000
22+750 40.000 1.500 5.000 400.000 15.000 415.000
24+500 40.000 1.500 5.000 400.000 15.000 415.000
25+765 40.000 1.500 5.000 400.000 15.000 415.000
26+500 40.000 1.500 5.000 400.000 15.000 415.000
26+835 40.000 1.500 5.000 400.000 15.000 415.000
28+175 40.000 1.500 5.000 400.000 15.000 415.000
28+650 40.000 1.500 5.000 400.000 15.000 415.000
29+400 40.000 1.500 5.000 400.000 15.000 415.000
29+800 40.000 1.500 5.000 400.000 15.000 415.000
29+925 40.000 1.500 5.000 400.000 15.000 415.000
31+060 40.000 1.500 5.000 400.000 15.000 415.000
31+460 40.000 1.500 5.000 400.000 15.000 415.000
31+500 40.000 1.500 5.000 400.000 15.000 415.000
31+525 40.000 1.500 5.000 400.000 15.000 415.000
31+855 40.000 1.500 5.000 400.000 15.000 415.000
33+000 40.000 1.500 5.000 400.000 15.000 415.000
33+600 40.000 1.500 5.000 400.000 15.000 415.000
33+612 40.000 1.500 5.000 400.000 15.000 415.000
34+235 40.000 1.500 5.000 400.000 15.000 415.000
34+950 40.000 1.500 5.000 400.000 15.000 415.000
39+725 40.000 1.500 5.000 400.000 15.000 415.000
39+950 40.000 1.500 5.000 400.000 15.000 415.000
40+925 40.000 1.500 5.000 400.000 15.000 415.000
41+125 40.000 1.500 5.000 400.000 15.000 415.000
42+575 40.000 1.500 5.000 400.000 15.000 415.000
44+590 40.000 1.500 5.000 400.000 15.000 415.000
46+220 40.000 1.500 5.000 400.000 15.000 415.000
47+400 40.000 1.500 5.000 400.000 15.000 415.000
48+575 40.000 1.500 5.000 400.000 15.000 415.000
49+730 40.000 1.500 5.000 400.000 15.000 415.000
49+850 40.000 1.500 5.000 400.000 15.000 415.000
51+425 40.000 1.500 5.000 400.000 15.000 415.000
52+075 40.000 1.500 5.000 400.000 15.000 415.000
52+200 40.000 1.500 5.000 400.000 15.000 415.000
52+450 40.000 1.500 5.000 400.000 15.000 415.000
52+600 40.000 1.500 5.000 400.000 15.000 415.000
52+935 40.000 1.500 5.000 400.000 15.000 415.000
54+505 40.000 1.500 5.000 400.000 15.000 415.000
54+775 40.000 1.500 5.000 400.000 15.000 415.000
55+150 40.000 1.500 5.000 400.000 15.000 415.000
57+115 40.000 1.500 5.000 400.000 15.000 415.000
58+150 40.000 1.500 5.000 400.000 15.000 415.000
58+750 40.000 1.500 5.000 400.000 15.000 415.000
59+033 40.000 1.500 5.000 400.000 15.000 415.000
59+190 40.000 1.500 5.000 400.000 15.000 415.000
59+325 40.000 1.500 5.000 400.000 15.000 415.000
59+790 40.000 1.500 5.000 400.000 15.000 415.000
60+025 40.000 1.500 5.000 400.000 15.000 415.000
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description
60+100 40.000 1.500 5.000 400.000 15.000 415.000
60+410 40.000 1.500 5.000 400.000 15.000 415.000
61+200 40.000 1.500 5.000 400.000 15.000 415.000
61+250 40.000 1.500 5.000 400.000 15.000 415.000
61+715 40.000 1.500 5.000 400.000 15.000 415.000
62+323 40.000 1.500 5.000 400.000 15.000 415.000
63+750 40.000 1.500 5.000 400.000 15.000 415.000
64+750 40.000 1.500 5.000 400.000 15.000 415.000
65+035 40.000 1.500 5.000 400.000 15.000 415.000
65+850 40.000 1.500 5.000 400.000 15.000 415.000
67+425 40.000 1.500 5.000 400.000 15.000 415.000
67+825 40.000 1.500 5.000 400.000 15.000 415.000
68+145 40.000 1.500 5.000 400.000 15.000 415.000
68+450 40.000 1.500 5.000 400.000 15.000 415.000
68+750 40.000 1.500 5.000 400.000 15.000 415.000
69+495 40.000 1.500 5.000 400.000 15.000 415.000
70+300 40.000 1.500 5.000 400.000 15.000 415.000
70+575 40.000 1.500 5.000 400.000 15.000 415.000
71+528 40.000 1.500 5.000 400.000 15.000 415.000
72+055 40.000 1.500 5.000 400.000 15.000 415.000
72+695 40.000 1.500 5.000 400.000 15.000 415.000
74+715 40.000 1.500 5.000 400.000 15.000 415.000
75+610 40.000 1.500 5.000 400.000 15.000 415.000
76+418 40.000 1.500 5.000 400.000 15.000 415.000
77+750 40.000 1.500 5.000 400.000 15.000 415.000
78+000 40.000 1.500 5.000 400.000 15.000 415.000
78+190 40.000 1.500 5.000 400.000 15.000 415.000
78+645 40.000 1.500 5.000 400.000 15.000 415.000
78+850 40.000 1.500 5.000 400.000 15.000 415.000
79+480 40.000 1.500 5.000 400.000 15.000 415.000
80+250 40.000 1.500 5.000 400.000 15.000 415.000
80+600 40.000 1.500 5.000 400.000 15.000 415.000
80+825 40.000 1.500 5.000 400.000 15.000 415.000
81+325 40.000 1.500 5.000 400.000 15.000 415.000
82+060 40.000 1.500 5.000 400.000 15.000 415.000
82+229 40.000 1.500 5.000 400.000 15.000 415.000
83+625 40.000 1.500 5.000 400.000 15.000 415.000
84+150 40.000 1.500 5.000 400.000 15.000 415.000
84+361 40.000 1.500 5.000 400.000 15.000 415.000
85+265 40.000 1.500 5.000 400.000 15.000 415.000
85+811 40.000 1.500 5.000 400.000 15.000 415.000
86+197 40.000 1.500 5.000 400.000 15.000 415.000
87+148 40.000 1.500 5.000 400.000 15.000 415.000
87+829 40.000 1.500 5.000 400.000 15.000 415.000
88+914 40.000 1.500 5.000 400.000 15.000 415.000
89+296 40.000 1.500 5.000 400.000 15.000 415.000
89+606 40.000 1.500 5.000 400.000 15.000 415.000
89+995 40.000 1.500 5.000 400.000 15.000 415.000
92+953 40.000 1.500 5.000 400.000 15.000 415.000
93+085 40.000 1.500 5.000 400.000 15.000 415.000
93+577 40.000 1.500 5.000 400.000 15.000 415.000
94+097 40.000 1.500 5.000 400.000 15.000 415.000
94+901 40.000 1.500 5.000 400.000 15.000 415.000
95+318 40.000 1.500 5.000 400.000 15.000 415.000
95+715 40.000 1.500 5.000 400.000 15.000 415.000
97+263 40.000 1.500 5.000 400.000 15.000 415.000
97+581 40.000 1.500 5.000 400.000 15.000 415.000
97+722 40.000 1.500 5.000 400.000 15.000 415.000
98+040 40.000 1.500 5.000 400.000 15.000 415.000
98+746 40.000 1.500 5.000 400.000 15.000 415.000
98+990 40.000 1.500 5.000 400.000 15.000 415.000
99+372 40.000 1.500 5.000 400.000 15.000 415.000
99+548 40.000 1.500 5.000 400.000 15.000 415.000
100+491 40.000 1.500 5.000 400.000 15.000 415.000
100+596 40.000 1.500 5.000 400.000 15.000 415.000
103+451 40.000 1.500 5.000 400.000 15.000 415.000
103+871 40.000 1.500 5.000 400.000 15.000 415.000
104+647 40.000 1.500 5.000 400.000 15.000 415.000
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description
105+862 40.000 1.500 5.000 400.000 15.000 415.000
106+602 40.000 1.500 5.000 400.000 15.000 415.000
107+480 40.000 1.500 5.000 400.000 15.000 415.000
108+180 40.000 1.500 5.000 400.000 15.000 415.000
108+223 40.000 1.500 5.000 400.000 15.000 415.000
108+853 40.000 1.500 5.000 400.000 15.000 415.000
109+093 40.000 1.500 5.000 400.000 15.000 415.000
109+226 40.000 1.500 5.000 400.000 15.000 415.000
110+116 40.000 1.500 5.000 400.000 15.000 415.000
111+268 40.000 1.500 5.000 400.000 15.000 415.000
111+420 40.000 1.500 5.000 400.000 15.000 415.000
113+763 40.000 1.500 5.000 400.000 15.000 415.000
114+301 40.000 1.500 5.000 400.000 15.000 415.000
116+742 40.000 1.500 5.000 400.000 15.000 415.000
117+773 40.000 1.500 5.000 400.000 15.000 415.000
117+982 40.000 1.500 5.000 400.000 15.000 415.000
118+204 40.000 1.500 5.000 400.000 15.000 415.000
119+349 40.000 1.500 5.000 400.000 15.000 415.000
120+228 40.000 1.500 5.000 400.000 15.000 415.000
120+611 40.000 1.500 5.000 400.000 15.000 415.000
120+956 40.000 1.500 5.000 400.000 15.000 415.000
122+397 40.000 1.500 5.000 400.000 15.000 415.000
123+125 40.000 1.500 5.000 400.000 15.000 415.000
125+804 40.000 1.500 5.000 400.000 15.000 415.000
126+298 40.000 1.500 5.000 400.000 15.000 415.000
127+529 40.000 1.500 5.000 400.000 15.000 415.000
127+663 40.000 1.500 5.000 400.000 15.000 415.000
128+217 40.000 1.500 5.000 400.000 15.000 415.000
129+307 40.000 1.500 5.000 400.000 15.000 415.000
130+954 40.000 1.500 5.000 400.000 15.000 415.000
131+319 40.000 1.500 5.000 400.000 15.000 415.000
131+636 40.000 1.500 5.000 400.000 15.000 415.000
131+781 40.000 1.500 5.000 400.000 15.000 415.000
132+594 40.000 1.500 5.000 400.000 15.000 415.000
132+710 40.000 1.500 5.000 400.000 15.000 415.000
133+674 40.000 1.500 5.000 400.000 15.000 415.000
143+988 40.000 1.500 5.000 400.000 15.000 415.000
145+182 40.000 1.500 5.000 400.000 15.000 415.000
145+400 40.000 1.500 5.000 400.000 15.000 415.000
146+798 40.000 1.500 5.000 400.000 15.000 415.000
146+872 40.000 1.500 5.000 400.000 15.000 415.000
148+655 40.000 1.500 5.000 400.000 15.000 415.000
150+396 40.000 1.500 5.000 400.000 15.000 415.000
151+123 40.000 1.500 5.000 400.000 15.000 415.000
152+924 40.000 1.500 5.000 400.000 15.000 415.000
155+398 40.000 1.500 5.000 400.000 15.000 415.000
155+907 40.000 1.500 5.000 400.000 15.000 415.000
157+151 40.000 1.500 5.000 400.000 15.000 415.000
159+055 40.000 1.500 5.000 400.000 15.000 415.000
159+568 40.000 1.500 5.000 400.000 15.000 415.000
163+805 40.000 1.500 5.000 400.000 15.000 415.000
171+472 40.000 1.500 5.000 400.000 15.000 415.000
174+790 40.000 1.500 5.000 400.000 15.000 415.000
175+608 40.000 1.500 5.000 400.000 15.000 415.000
175+705 40.000 1.500 5.000 400.000 15.000 415.000
180+458 40.000 1.500 5.000 400.000 15.000 415.000
Wing Walls 1940.000 1.500 5.000 19400.000 15.000 19415.000
Total formwork 100055.000 sq. ft.
Total Quantity (Sqm) 9311.77

C-7
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description

C-8 PCC 1:3:6 in mass concrete less formwork using 40% boulders

R.D Length Width Height Volume


6+000 to 20+000 800.000 20No's 1.500 5.000 6000.000
20+350 30.000 1.500 5.000 225.000
20+935 30.000 1.500 5.000 225.000
22+750 30.000 1.500 5.000 225.000
24+500 30.000 1.500 5.000 225.000
25+765 30.000 1.500 5.000 225.000
26+500 30.000 1.500 5.000 225.000
26+835 30.000 1.500 5.000 225.000
28+175 30.000 1.500 5.000 225.000
28+650 30.000 1.500 5.000 225.000
29+400 30.000 1.500 5.000 225.000
29+800 30.000 1.500 5.000 225.000
29+925 25.000 1.500 5.000 187.500
31+060 25.000 1.500 5.000 187.500
31+460 25.000 1.500 5.000 187.500
31+500 25.000 1.500 5.000 187.500
31+525 25.000 1.500 5.000 187.500
31+855 25.000 1.500 5.000 187.500
33+000 25.000 1.500 5.000 187.500
33+600 25.000 1.500 5.000 187.500
33+612 30.000 1.500 5.000 225.000
34+235 30.000 1.500 5.000 225.000
34+950 30.000 1.500 5.000 225.000
39+725 30.000 1.500 5.000 225.000
39+950 30.000 1.500 5.000 225.000
40+925 30.000 1.500 5.000 225.000
41+125 30.000 1.500 5.000 225.000
42+575 30.000 1.500 5.000 225.000
44+590 30.000 1.500 5.000 225.000
46+220 25.000 1.500 5.000 187.500
47+400 28.000 1.500 5.000 210.000
48+575 29.500 1.500 5.000 221.250
49+730 30.000 1.500 5.000 225.000
49+850 30.000 1.500 5.000 225.000
51+425 30.000 1.500 5.000 225.000
52+075 30.000 1.500 5.000 225.000
52+200 30.000 1.500 5.000 225.000
52+450 30.000 1.500 5.000 225.000
52+600 30.000 1.500 5.000 225.000
52+935 30.000 1.500 5.000 225.000
54+505 30.000 1.500 5.000 225.000
54+775 30.000 1.500 5.000 225.000
55+150 30.000 1.500 5.000 225.000
57+115 30.000 1.500 5.000 225.000
58+150 30.000 1.500 5.000 225.000
58+750 30.000 1.500 5.000 225.000
59+033 30.000 1.500 5.000 225.000
59+190 30.000 1.500 5.000 225.000
59+325 30.000 1.500 5.000 225.000
59+790 30.000 1.500 5.000 225.000
60+025 30.000 1.500 5.000 225.000
60+100 30.000 1.500 5.000 225.000
60+410 30.000 1.500 5.000 225.000
61+200 30.000 1.500 5.000 225.000
61+250 30.000 1.500 5.000 225.000
61+715 30.000 1.500 5.000 225.000
62+323 30.000 1.500 5.000 225.000
63+750 30.000 1.500 5.000 225.000
64+750 30.000 1.500 5.000 225.000
65+035 30.000 1.500 5.000 225.000
65+850 30.000 1.500 5.000 225.000
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description
67+425 30.000 1.500 5.000 225.000
67+825 30.000 1.500 5.000 225.000
68+145 30.000 1.500 5.000 225.000
68+450 30.000 1.500 5.000 225.000
68+750 30.000 1.500 5.000 225.000
69+495 30.000 1.500 5.000 225.000
70+300 30.000 1.500 5.000 225.000
70+575 30.000 1.500 5.000 225.000
71+528 30.000 1.500 5.000 225.000
72+055 30.000 1.500 5.000 225.000
72+695 30.000 1.500 5.000 225.000
74+715 30.000 1.500 5.000 225.000
75+610 30.000 1.500 5.000 225.000
76+418 30.000 1.500 5.000 225.000
77+750 30.000 1.500 5.000 225.000
78+000 30.000 1.500 5.000 225.000
78+190 30.000 1.500 5.000 225.000
78+645 30.000 1.500 5.000 225.000
78+850 30.000 1.500 5.000 225.000
79+480 30.000 1.500 5.000 225.000
80+250 30.000 1.500 5.000 225.000
80+600 30.000 1.500 5.000 225.000
80+825 30.000 1.500 5.000 225.000
81+325 30.000 1.500 5.000 225.000
82+060 30.000 1.500 5.000 225.000
82+229 30.000 1.500 5.000 225.000
83+625 30.000 1.500 5.000 225.000
84+150 30.000 1.500 5.000 225.000
84+361 30.000 1.500 5.000 225.000
85+265 30.000 1.500 5.000 225.000
85+811 30.000 1.500 5.000 225.000
86+197 30.000 1.500 5.000 225.000
87+148 30.000 1.500 5.000 225.000
87+829 30.000 1.500 5.000 225.000
88+914 30.000 1.500 5.000 225.000
89+296 30.000 1.500 5.000 225.000
89+606 30.000 1.500 5.000 225.000
89+995 30.000 1.500 5.000 225.000
92+953 30.000 1.500 5.000 225.000
93+085 30.000 1.500 5.000 225.000
93+577 30.000 1.500 5.000 225.000
94+097 30.000 1.500 5.000 225.000
94+901 30.000 1.500 5.000 225.000
95+318 30.000 1.500 5.000 225.000
95+715 30.000 1.500 5.000 225.000
97+263 30.000 1.500 5.000 225.000
97+581 30.000 1.500 5.000 225.000
97+722 30.000 1.500 5.000 225.000
98+040 30.000 1.500 5.000 225.000
98+746 30.000 1.500 5.000 225.000
98+990 30.000 1.500 5.000 225.000
99+372 30.000 1.500 5.000 225.000
99+548 30.000 1.500 5.000 225.000
100+491 30.000 1.500 5.000 225.000
100+596 30.000 1.500 5.000 225.000
103+451 30.000 1.500 5.000 225.000
103+871 30.000 1.500 5.000 225.000
104+647 30.000 1.500 5.000 225.000
105+862 30.000 1.500 5.000 225.000
106+602 30.000 1.500 5.000 225.000
107+480 30.000 1.500 5.000 225.000
108+180 30.000 1.500 5.000 225.000
108+223 30.000 1.500 5.000 225.000
108+853 30.000 1.500 5.000 225.000
109+093 30.000 1.500 5.000 225.000
109+226 30.000 1.500 5.000 225.000
110+116 30.000 1.500 5.000 225.000
111+268 30.000 1.500 5.000 225.000
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description
111+420 30.000 1.500 5.000 225.000
113+763 30.000 1.500 5.000 225.000
114+301 30.000 1.500 5.000 225.000
116+742 30.000 1.500 5.000 225.000
117+773 30.000 1.500 5.000 225.000
117+982 30.000 1.500 5.000 225.000
118+204 30.000 1.500 5.000 225.000
119+349 30.000 1.500 5.000 225.000
120+228 30.000 1.500 5.000 225.000
120+611 30.000 1.500 5.000 225.000
120+956 30.000 1.500 5.000 225.000
122+397 30.000 1.500 5.000 225.000
123+125 30.000 1.500 5.000 225.000
125+804 30.000 1.500 5.000 225.000
126+298 30.000 1.500 5.000 225.000
127+529 30.000 1.500 5.000 225.000
127+663 30.000 1.500 5.000 225.000
128+217 30.000 1.500 5.000 225.000
129+307 30.000 1.500 5.000 225.000
130+954 30.000 1.500 5.000 225.000
131+319 30.000 1.500 5.000 225.000
131+636 30.000 1.500 5.000 225.000
131+781 30.000 1.500 5.000 225.000
132+594 30.000 1.500 5.000 225.000
132+710 30.000 1.500 5.000 225.000
133+674 30.000 1.500 5.000 225.000
143+988 30.000 1.500 5.000 225.000
145+182 30.000 1.500 5.000 225.000
145+400 30.000 1.500 5.000 225.000
146+798 30.000 1.500 5.000 225.000
146+872 30.000 1.500 5.000 225.000
148+655 30.000 1.500 5.000 225.000
150+396 30.000 1.500 5.000 225.000
151+123 30.000 1.500 5.000 225.000
152+924 30.000 1.500 5.000 225.000
155+398 30.000 1.500 5.000 225.000
155+907 30.000 1.500 5.000 225.000
157+151 30.000 1.500 5.000 225.000
159+055 30.000 1.500 5.000 225.000
159+568 30.000 1.500 5.000 225.000
163+805 30.000 1.500 5.000 225.000
171+472 30.000 1.500 5.000 225.000
174+790 30.000 1.500 5.000 225.000
175+608 30.000 1.500 5.000 225.000
175+705 30.000 1.500 5.000 225.000
180+458 30.000 1.500 5.000 225.000
Wing Walls 800.000 5.000 5.000 20000.000

Total volume of PCC 1:3:6 64793.750 cub. Ft.


Total volume of PCC 1:3:6 1500.500 cub. M

C-9 Provide & weave GI wire netting for wire crates 6"x9" mesh : 8 SWG wire

Gabions
Width of superpasages 1352.00 ft.
4 apron steps of 5' width 20.00 ft.
GI Wire Netting Area (sft) No. of crates No. of faces Qty (sft)

D/S Step 1 (10x5x3)


Top & Bottom (10x5) 50 135.2 2 13520
Ends (10x3) 30 135.2 2 8112
Sides (5x3) 15 135.2 2 4056

Step 2 (10x5x3)
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description
Top & Bottom (10x5) 50 135.2 2 13520
Ends (10x3) 30 135.2 2 8112
Sides (5x3) 15 135.2 2 4056

Step 3 (10x5x3)
Top & Bottom (10x5) 50 135.2 2 13520
Ends (10x3) 30 135.2 2 8112
Sides (5x3) 15 135.2 2 4056

Step 4 (10x5x3)
Top & Bottom (10x5) 50 135.2 2 13520
Ends (10x3) 30 135.2 2 8112
Sides (5x3) 15 135.2 2 4056

Upstream step (10x10x2)


Top & Bottom (10x10) 100 135.2 2 27040
Ends (10x2) 20 135.2 2 5408
Sides (10x2) 20 135.2 4 10816
146016 sft
13582.884 sq m

C-10 Supplying stone and stone filling in GI wire crate and its sewing, excluding cost of crates

Stone filling
Volume of
Length Width Depth Nos. U/S and D/S
steps
D/S
1352.00 5 3 4 81120
U/S 1352.00 10 2 1 27040
Total volume of stone filling 108160 cub. Ft..
OR 3062.288 cub. M.

C-11 Providing and Laying stone pitching/filling, dry hand packed in pitching & aprons

Stone filling on slope


Total length 2721.25 ft.

Length Width Thickness Nos. Volume


D/S 2721.25 4.5 2 2 48982.5 cub. Ft.

OR 1386.820 cub. M.

C-12 Structural backfill using Common Material available at site


Backfill along guide walls
U/S guide wall
Length Backfill depth Backfill Volume
width Sides

cub. Ft
1237.25 3.00 1.50 2.00 11135.25
315.27 cub. M
D/S guide wall
Backfill
Length Backfill depth width Sides Volume

cub. Ft
2723.00 3.00 1.50 2.00 24507.00
693.86 cub. M
Construction of Siran Right Bank Canal
District Mansehra
Superpassages
BOQ Item No. Description

Backfill along toe wall


Length Backfill depth Backfill Volume
width Sides

cub. Ft
7000.00 3.00 1.50 2.00 63000.00
1783.69 cub. M

Total volume of backfill 2792.82 cub. M


S.No Chainage Length Area Total Qty

1 0+000 0.00 30.84 0.00


2 0+050 50.00 30.84 1542.00
3 0+100 50.00 30.84 1542.00
4 0+150 50.00 30.84 1542.00
5 0+200 50.00 30.84 1542.00
6 0+250 50.00 30.84 1542.00
7 0+300 50.00 30.84 1542.00
8 0+350 50.00 30.84 1542.00
9 0+400 50.00 30.84 1542.00
10 0+450 50.00 30.84 1542.00
11 0+500 50.00 30.84 1542.00
12 0+500 0.00 30.84 0.00
13 0+550 50.00 30.84 1542.00
14 0+600 50.00 30.84 1542.00
15 0+600 0.00 30.84 0.00
16 0+650 50.00 30.84 1542.00
17 0+700 50.00 30.84 1542.00
18 0+750 50.00 30.84 1542.00
19 0+800 50.00 30.84 1542.00
20 0+850 50.00 30.84 1542.00
21 0+850 0.00 30.84 0.00
22 0+950 100.00 30.84 3084.00
23 1+000 50.00 30.84 1542.00
24 1+050 50.00 30.84 1542.00
25 1+100 50.00 30.84 1542.00
26 1+110 10.00 30.84 308.40
27 1+110 0.00 30.84 0.00
28 1+120 10.00 30.84 308.40
29 1+155 35.00 30.84 1079.40
30 1+250 95.00 30.84 2929.80
31 1+295 45.00 30.84 1387.80
32 1+310 15.00 30.84 462.60
33 1+310 0.00 30.84 0.00
34 1+375 65.00 30.84 2004.60
35 1+475 100.00 30.84 3084.00
36 1+544 69.00 30.84 2127.96
37 1+594 50.00 30.84 1542.00
38 1+594 0.00 30.84 0.00
39 1+680 86.00 30.84 2652.24
40 1+740 60.00 30.84 1850.40
41 1+825 85.00 30.84 2621.40
42 1+845 20.00 30.84 616.80
43 1+870 25.00 30.84 771.00
44 1+920 50.00 30.84 1542.00
45 2+000 80.00 30.84 2467.20
46 2+100 100.00 30.84 3084.00
47 2+200 100.00 30.84 3084.00
S.No Chainage Length Area Total Qty

48 2+275 75.00 30.84 2313.00


49 2+375 100.00 30.84 3084.00
50 2+475 100.00 30.84 3084.00
51 2+575 100.00 30.84 3084.00
52 2+675 100.00 30.84 3084.00
53 2+775 100.00 30.84 3084.00
54 2+875 100.00 30.84 3084.00
55 2+935 60.00 30.84 1850.40
56 2+950 15.00 30.84 462.60
57 3+050 100.00 30.84 3084.00
58 3+110 60.00 30.84 1850.40
59 3+200 90.00 30.84 2775.60
60 3+270 70.00 30.84 2158.80
61 3+350 80.00 30.84 2467.20
62 3+410 60.00 30.84 1850.40
63 3+482 72.00 30.84 2220.48
64 3+493 11.00 30.84 339.24
65 3+504 11.00 30.84 339.24
66 3+525 21.00 30.84 647.64
67 3+625 100.00 30.84 3084.00
68 3+700 75.00 30.84 2313.00
69 3+725 25.00 30.84 771.00
70 3+840 115.00 30.84 3546.60
71 3+860 20.00 30.84 616.80
72 3+860 0.00 30.84 0.00
73 3+918 58.00 30.84 1788.72
74 3+981 63.00 30.84 1942.92
75 4+030 49.00 30.84 1511.16
76 4+131 101.00 30.84 3114.84
77 4+196 65.00 30.84 2004.60
78 4+301 105.00 30.84 3238.20
79 4+401 100.00 30.84 3084.00
80 4+450 49.00 30.84 1511.16
81 4+450 0.00 30.84 0.00
82 4+506 56.00 30.84 1727.04
83 4+576 70.00 30.84 2158.80
84 4+626 50.00 30.84 1542.00
85 4+726 100.00 30.84 3084.00
86 4+752 26.00 30.84 801.84
87 4+790 38.00 30.84 1171.92
88 4+913 123.00 30.84 3793.32
89 4+913 0.00 30.84 0.00
90 4+963 50.00 30.84 1542.00
91 5+005 42.00 30.84 1295.28
92 5+101 96.00 30.84 2960.64
93 5+200 99.00 30.84 3053.16
94 5+280 80.00 30.84 2467.20
95 5+356 76.00 30.84 2343.84
96 5+379 23.00 30.84 709.32
S.No Chainage Length Area Total Qty

97 5+439 60.00 30.84 1850.40


98 5+479 40.00 30.84 1233.60
99 5+509 30.00 30.84 925.20
100 5+527 18.00 30.84 555.12
101 5+560 33.00 30.84 1017.72
102 5+600 40.00 30.84 1233.60
103 5+625 25.00 30.84 771.00
104 5+650 25.00 30.84 771.00
105 5+742 92.00 30.84 2837.28
106 5+782 40.00 30.84 1233.60
107 5+837 55.00 30.84 1696.20
108 5+876 39.00 30.84 1202.76
109 5+932 56.00 30.84 1727.04
110 5+947 15.00 30.84 462.60
111 6+047 100.00 30.84 3084.00
112 6+147 100.00 30.84 3084.00
113 6+177 30.00 30.84 925.20
114 6+213 36.00 30.84 1110.24
115 6+308 95.00 30.84 2929.80
116 6+396 88.00 30.84 2713.92
117 6+449 53.00 30.84 1634.52
118 6+549 100.00 30.84 3084.00
119 6+579 30.00 30.84 925.20
120 6+638 59.00 30.84 1819.56
121 6+668 30.00 30.84 925.20
122 6+732 64.00 30.84 1973.76
123 6+775 43.00 30.84 1326.12
124 6+800 25.00 30.84 771.00
125 6+850 50.00 30.84 1542.00
126 6+900 50.00 30.84 1542.00
127 6+925 25.00 30.84 771.00
128 6+950 25.00 30.84 771.00
129 6+975 25.00 30.84 771.00
130 7+027 52.00 30.84 1603.68
131 7+085 58.00 30.84 1788.72
132 7+100 15.00 30.84 462.60
133 7+100 0.00 30.84 0.00
134 7+113 13.00 30.84 400.92
136 7+146 0.00
Aqueduct
7+158 0.00
137
138 7+170 48.12 0.00
139 7+175 48.12 0.00
140 7+197 48.12 0.00
141 7+255 48.12 0.00
142 7+292 34.56 0.00
143 7+329 37.00 34.56 1278.72
144 7+359 30.00 34.56 1036.80
145 7+402 43.00 34.56 1486.08
S.No Chainage Length Area Total Qty

146 7+500 98.00 34.56 3386.88


147 7+586 86.00 34.56 2972.16
148 7+614 28.00 34.56 967.68
149 7+648 34.00 34.56 1175.04
150 7+686 38.00 34.56 1313.28
151 7+703 17.00 34.56 587.52
152 0.00
Aqueduct
0.00
153
154 0.00
155 7+721 18.00 80.47 1448.46
156 7+752 31.00 80.47 2494.57
157 7+797 45.00 80.47 3621.15
158 7+820 23.00 80.47 1850.81
159 7+877 57.00 80.47 4586.79
160 7+914 37.00 80.47 2977.39
161 7+960 46.00 80.47 3701.62
162 8+045 85.00 80.47 6839.95
163 8+073 28.00 80.47 2253.16
164 0.00
165 0.00
Aqueduct
166 0.00
167 0.00
168 8+775 0.00 7.05 0.00
169 8+877 102.00 7.05 719.10
170 8+904 27.00 7.05 190.35
171 8+953 49.00 7.05 345.45
172 8+988 35.00 7.05 246.75
173 9+048 60.00 7.05 423.00
174 9+078 30.00 7.05 211.50
175 9+138 60.00 7.05 423.00
176 9+160 22.00 7.05 155.10
177 9+165 5.00 7.05 35.25
178 9+219 54.00 7.05 380.70
179 9+299 80.00 7.05 564.00
180 9+339 40.00 7.05 282.00
181 9+383 44.00 7.05 310.20
182 9+413 30.00 7.05 211.50
183 9+453 40.00 7.05 282.00
184 9+503 50.00 7.05 352.50
185 9+528 25.00 7.05 176.25
186 9+558 30.00 7.05 211.50
187 9+583 25.00 7.05 176.25
188 9+633 50.00 7.05 352.50
189 9+683 50.00 7.05 352.50
190 9+733 50.00 7.05 352.50
191 9+758 25.00 7.05 176.25
192 9+808 50.00 7.05 352.50
193 9+883 75.00 7.05 528.75
S.No Chainage Length Area Total Qty

194 9+923 40.00 7.05 282.00


195 9+953 30.00 7.05 211.50
196 9+983 30.00 7.05 211.50
197 10+013 30.00 7.05 211.50
10+035 0.00
198
Aqueduct
10+063 0.00
199
200 10+088 25.00 59.00 1475.00
201 10+098 10.00 59.00 590.00
202 10+133 35.00 59.00 2065.00
203 10+183 50.00 59.00 2950.00
204 10+233 50.00 59.00 2950.00
205 10+283 50.00 59.00 2950.00
206 10+333 50.00 59.00 2950.00
207 10+353 20.00 59.00 1180.00
208 10+383 30.00 59.00 1770.00
209 10+428 45.00 59.00 2655.00
210 10+445 17.00 59.00 1003.00
211 10+477 32.00 59.00 1888.00
212 10+501 24.00 59.00 1416.00
213 10+533 32.00 59.00 1888.00
214 10+583 50.00 59.00 2950.00
215 10+633 50.00 59.00 2950.00
216 10+643 10.00 59.00 590.00
217 10+675 32.00 59.00 1888.00
218 10+683 8.00 59.00 472.00
219 10+708 25.00 59.00 1475.00
220 10+733 25.00 59.00 1475.00
221 10+763 30.00 59.00 1770.00
222 10+803 40.00 59.00 2360.00
223 10+833 30.00 59.00 1770.00
224 10+858 25.00 59.00 1475.00
225 10+898 40.00 59.00 2360.00
226 10+943 45.00 59.00 2655.00
227 10+983 40.00 59.00 2360.00
228 11+000 17.00 59.00 1003.00
229 11+023 23.00 59.00 1357.00
230 11+048 25.00 59.00 1475.00
231 11+088 40.00 59.00 2360.00
232 11+133 45.00 59.00 2655.00
233 11+153 20.00 59.00 1180.00
234 11+173 20.00 59.00 1180.00
235 11+199 26.00 59.00 1534.00
236 11+223 24.00 59.00 1416.00
237 11+253 30.00 59.00 1770.00
238 11+273 20.00 59.00 1180.00
239 11+303 30.00 59.00 1770.00
240 11+348 45.00 59.00 2655.00
S.No Chainage Length Area Total Qty

241 11+388 40.00 59.00 2360.00

11+475 0.00
242 Aqueduct
12+049 0.00
243
244 12+050 0.00 22.00 0.00
245 12+200 150.00 22.00 3300.00
246 12+300 100.00 22.00 2200.00
247 12+540 240.00 22.00 5280.00
248 12+583 43.00 22.00 946.00
249 12+640 57.00 22.00 1254.00
250 12+695 55.00 22.00 1210.00
251 12+735 40.00 22.00 880.00
252 12+760 25.00 22.00 550.00
253 12+810 50.00 22.00 1100.00
254 12+860 50.00 22.00 1100.00
255 12+900 40.00 22.00 880.00
256 12+925 25.00 22.00 550.00
257 12+960 35.00 22.00 770.00
258 12+990 30.00 22.00 660.00
259 13+027 37.00 22.00 814.00
260 13+040 13.00 22.00 286.00
261 13+090 50.00 22.00 1100.00
262 13+120 30.00 22.00 660.00
263 13+160 40.00 22.00 880.00
264 13+172 12.00 22.00 264.00
265 13+206 34.00 22.00 748.00
266 13+234 28.00 22.00 616.00
267 13+284 50.00 22.00 1100.00
268 13+314 30.00 22.00 660.00
269 13+364 50.00 22.00 1100.00
270 13+394 30.00 22.00 660.00
271 13+422 28.00 22.00 616.00
272 13+437 15.00 22.00 330.00
273 13+473 36.00 22.00 792.00
274 13+560 87.00 22.00 1914.00
275 13+620 60.00 22.00 1320.00
276 13+690 70.00 22.00 1540.00
277 13+720 30.00 22.00 660.00
278 13+770 50.00 22.00 1100.00
279 13+800 30.00 22.00 660.00
280 13+830 30.00 22.00 660.00
281 13+880 50.00 22.00 1100.00
282 13+890 10.00 22.00 220.00
283 13+920 30.00 22.00 660.00
284 13+960 40.00 22.00 880.00
285 13+960 0.00 0.00
286 13+980 0.00
287 14+000 0.00
S.No Chainage Length Area Total Qty

288 14+030 0.00


289 14+070 0.00
290 14+110 0.00
291 14+160 0.00
292 14+220 0.00
293 14+260 0.00
294 14+310 0.00
295 14+363 0.00
296 14+368 0.00
297 14+385 0.00
298 14+455 0.00
299 14+490 0.00
300 14+540 0.00
301 14+600 0.00
302 14+621 0.00
303 14+642 0.00
304 14+750 0.00
305 14+775 0.00
306 14+825 0.00
307 14+875 0.00
308 14+975 0.00
309 15+075 0.00
310 15+119 0.00
311 15+149 0.00
312 15+182 0.00
313 15+200 0.00
314 15+300 0.00
315 15+341 0.00
Syphon
316 15+351 0.00
317 15+379 0.00
318 15+400 0.00
319 15+500 0.00
320 15+600 0.00
321 15+700 0.00
322 15+820 0.00
323 15+920 0.00
324 16+020 0.00
325 16+120 0.00
326 16+220 0.00
327 16+320 0.00
328 16+420 0.00
329 16+520 0.00
330 16+620 0.00
331 16+720 0.00
332 16+820 0.00
333 16+853 0.00
334 16+936 0.00
335 16+948 0.00
336 16+966 0.00
S.No Chainage Length Area Total Qty

337 17+003 0.00


338 17+033 0.00
339 17+043 0.00
340 17+063 0.00
341 17+163 0.00
342 17+210 0.00
343 17+268 0.00
344 17+325 0.00
345 17+350 0.00
346 17+375 25.00 8.65 216.25
347 17+425 50.00 8.65 432.50
348 17+450 25.00 8.65 216.25
349 17+500 50.00 8.65 432.50
350 17+530 30.00 8.65 259.50
351 17+550 20.00 8.65 173.00
352 17+600 50.00 8.65 432.50
353 17+650 50.00 8.65 432.50
354 17+700 50.00 8.65 432.50
355 17+750 50.00 8.65 432.50
356 17+784 34.00 8.65 294.10
357 17+870 86.00 8.65 743.90
358 17+938 68.00 8.65 588.20
359 18+000 62.00 8.65 536.30
360 18+050 50.00 8.65 432.50
361 18+100 50.00 8.65 432.50
362 18+150 50.00 8.65 432.50
363 18+200 50.00 8.65 432.50
364 18+250 50.00 8.65 432.50
365 18+300 50.00 8.65 432.50
366 18+350 50.00 8.65 432.50
367 18+390 40.00 8.65 346.00
368 18+412 22.00 8.65 190.30
369 18+450 38.00 8.65 328.70
370 18+500 50.00 8.65 432.50
371 18+550 50.00 8.65 432.50
372 18+600 50.00 8.65 432.50
373 18+657 57.00 8.65 493.05
374 18+702 45.00 8.65 389.25
375 18+733 31.00 8.65 268.15
376 18+757 24.00 8.65 207.60
377 18+800 43.00 8.65 371.95
378 18+838 38.00 8.65 328.70
379 18+902 64.00 8.65 553.60
380 18+925 23.00 8.65 198.95
381 18+950 25.00 8.65 216.25
382 18+976 26.00 8.65 224.90
383 19+064 88.00 8.65 761.20
384 19+114 50.00 8.65 432.50
385 19+141 27.00 8.65 233.55
S.No Chainage Length Area Total Qty

386 19+166 25.00 8.65 216.25


387 19+189 23.00 8.65 198.95
388 19+217 28.00 8.65 242.20
389 19+237 20.00 8.65 173.00
390 19+274 37.00 8.65 320.05
391 19+284 10.00 8.65 86.50
392 19+306 22.00 8.65 190.30
393 19+320 14.00 8.65 121.10
394 19+338 18.00 8.65 155.70
395 19+350 12.00 8.65 103.80
396 19+400 50.00 8.65 432.50
397 19+460 60.00 8.65 519.00
398 19+510 50.00 8.65 432.50
399 19+550 40.00 8.65 346.00
400 19+600 50.00 8.65 432.50
401 19+650 50.00 8.65 432.50
402 19+700 50.00 8.65 432.50
403 19+750 50.00 8.65 432.50
404 19+850 100.00 8.65 865.00
405 19+900 50.00 8.65 432.50
406 19+950 50.00 13.10 655.00
407 20+000 50.00 13.10 655.00
408 20+025 25.00 13.10 327.50
409 20+100 75.00 13.10 982.50
410 20+150 50.00 13.10 655.00
411 20+200 50.00 13.10 655.00
412 20+250 50.00 13.10 655.00
413 20+300 50.00 13.10 655.00
414 20+350 50.00 13.10 655.00
415 20+400 50.00 13.10 655.00
416 20+500 100.00 13.10 1310.00
417 20+600 100.00 13.10 1310.00
418 20+700 100.00 13.10 1310.00
419 20+750 50.00 13.10 655.00
420 20+825 75.00 13.10 982.50
421 20+900 75.00 13.10 982.50
422 20+935 35.00 13.10 458.50
423 21+000 65.00 13.10 851.50
424 21+075 75.00 13.10 982.50
425 21+175 100.00 13.10 1310.00
426 21+225 50.00 13.10 655.00
427 21+250 25.00 13.10 327.50
428 21+300 50.00 13.10 655.00
429 21+350 50.00 13.10 655.00
430 21+400 50.00 13.10 655.00
431 21+450 50.00 13.10 655.00
432 21+500 50.00 13.10 655.00
433 21+550 50.00 13.10 655.00
434 21+600 50.00 13.10 655.00
S.No Chainage Length Area Total Qty

435 21+700 100.00 13.10 1310.00


436 21+750 50.00 13.10 655.00
437 21+850 100.00 13.10 1310.00
438 21+950 100.00 13.10 1310.00
439 22+000 50.00 13.10 655.00
440 22+050 50.00 13.10 655.00
441 22+100 50.00 13.10 655.00
442 22+150 50.00 13.10 655.00
443 22+175 23.90 13.10 313.09
444 22+200 25.44 13.10 333.26
445 22+225 29.94 13.10 392.21
446 22+250 27.35 13.10 358.28
447 22+300 50.00 13.10 655.00
448 22+350 44.41 13.10 581.77
449 22+425 68.94 13.10 903.11
450 22+450 28.76 13.10 376.76
451 22+500 49.96 13.10 654.48
452 22+575 73.68 13.10 965.21
453 22+600 23.76 13.10 311.26
454 22+700 100.22 13.10 1312.88
455 22+715 15.96 13.10 209.08
456 22+742 26.81 13.10 351.21
457 22+750 8.25 13.10 108.08
458 22+775 20.98 13.10 274.84
459 22+800 25.63 13.10 335.75
460 22+875 32.19 13.10 421.69
461 22+925 50.08 13.10 656.05
462 22+975 49.50 13.10 648.45
463 23+000 40.01 13.10 524.13
464 23+050 56.05 13.10 734.25
465 23+075 22.75 13.10 298.03
466 23+125 43.58 13.10 570.90
467 23+175 48.28 13.10 632.47
468 23+200 36.75 13.10 481.43
469 23+250 50.64 13.10 663.38
470 23+300 52.62 13.10 689.32
471 23+350 46.51 13.10 609.28
472 23+450 97.75 13.10 1280.53
473 23+500 51.77 13.10 678.19
474 23+525 26.14 13.10 342.43
475 23+575 52.79 13.10 691.55
476 23+625 50.12 13.10 656.57
477 23+675 45.00 13.10 589.50
478 23+725 48.72 13.10 638.23
479 23+750 23.84 13.10 312.30
480 23+825 76.24 13.10 998.74
481 23+875 55.27 13.10 724.04
482 23+900 31.50 13.10 412.65
483 24+000 87.36 13.10 1144.42
S.No Chainage Length Area Total Qty

484 24+050 49.30 13.10 645.83


485 24+100 45.50 13.10 596.05
486 24+125 25.21 13.10 330.25
487 24+150 25.57 13.10 334.97
488 24+200 52.96 13.10 693.78
489 24+250 53.35 13.10 698.88
490 24+300 43.91 13.10 575.22
491 24+350 58.88 13.10 771.33
492 24+400 54.18 13.10 709.76
493 24+425 23.03 13.10 301.69
494 24+450 24.29 13.10 318.20
495 24+500 28.53 13.10 373.74
496 24+525 25.00 13.10 327.50
497 24+575 46.70 13.10 611.77
498 24+625 50.09 13.10 656.18
499 24+650 31 13.10 407.67
500 24+675 20 13.10 262.26
501 24+700 23 13.10 304.97
502 24+750 50 13.10 656.31
503 24+800 47 13.10 618.98
504 24+825 25 13.10 324.36
505 24+850 25 13.10 324.36
506 24+900 25 13.10 324.36
507 24+950 25 13.10 324.36
508 25+000 25 13.10 324.36
509 25+050 52 13.10 685.39
510 25+070 18 13.10 230.69
511 25+100 33 13.10 428.89
512 25+150 49 13.10 636.27
513 25+180 30 13.10 394.70
514 25+200 18 13.10 239.73
515 25+225 20 13.10 261.35
516 25+250 25 13.10 325.67
517 25+275 25 13.10 321.47
518 25+300 23 13.10 297.76
519 25+350 49 13.10 643.87
520 25+375 25 13.10 324.75
521 25+400 25 13.10 323.83
522 25+425 28 13.10 364.83
523 25+450 23 13.10 303.40
524 25+475 25 13.10 332.87
525 25+500 25 13.10 332.35
526 25+525 25 13.10 321.34
527 25+550 24 13.10 318.72
528 25+575 24 13.10 312.04
529 25+600 25 13.10 328.42
530 25+625 26 13.10 337.85
531 25+650 25 13.10 330.12
532 25+675 24 13.10 315.71
S.No Chainage Length Area Total Qty

533 25+700 24 13.10 312.17


534 25+750 50 13.10 657.62
535 25+765 27 13.10 359.20
536 25+775 14 13.10 186.02
537 25+800 22 13.10 290.82
538 25+825 32 13.10 424.05
539 25+875 54 13.10 711.59
540 25+905 29 13.10 377.54
541 25+950 42 13.10 550.07
542 26+000 47 13.10 616.75
543 26+050 50 13.10 648.58
544 26+100 47 13.10 620.42
545 26+150 45 13.10 591.73
546 26+175 24 13.10 312.30
547 26+200 24 13.10 315.58
548 26+225 24 13.10 312.96
549 26+250 27 13.10 349.51
550 26+300 49 13.10 643.21
551 26+350 51 13.10 669.15
552 26+375 32 13.10 419.99
553 26+400 26 13.10 337.33
554 26+425 25 13.10 325.93
555 26+440 16 13.10 207.24
556 26+450 9 13.10 113.32
557 26+475 24 13.10 313.75
558 26+490 15 13.10 196.37
559 26+500 11 13.10 137.55
560 26+550 35 13.10 452.21
561 26+600 50 13.10 648.45
562 26+625 26 13.10 335.75
563 26+650 26 13.10 334.57
564 26+675 26 13.10 345.58
565 26+700 25 13.10 331.17
566 26+750 52 13.10 683.03
567 26+800 49 13.10 639.41
568 26+835 39 13.10 506.45
569 26+850 11 13.10 140.96
570 26+900 51 13.10 673.73
571 26+930 31 13.10 401.65
572 26+950 14 13.10 188.25
573 26+970 20 13.10 259.64
574 27+000 30 13.10 391.95
575 27+075 68 13.10 890.67
576 27+100 25 13.10 328.29
577 27+125 32 13.10 422.34
578 27+175 47 13.10 621.46
579 27+200 26 13.10 339.29
580 27+250 51 13.10 672.82
581 27+300 51 13.10 672.16
S.No Chainage Length Area Total Qty

582 27+321 22 13.10 284.40

Aqueduct 0.00
583
584 27+430 0 20.40 0.00
585 27+445 15 20.40 295.80
586 27+465 18 20.40 376.58
587 27+500 64 20.40 1296.01
588 27+550 48 20.40 971.45
589 27+580 28 20.40 570.59
590 27+600 20 20.40 398.00
591 27+625 24 20.40 491.64
592 27+650 24 20.40 484.50
593 27+675 23 20.40 464.92
594 27+750 55 20.40 1128.53
595 27+780 31 20.40 637.30
596 27+805 26 20.40 535.09
597 27+825 26 20.40 521.22
598 27+850 22 20.40 453.08
599 27+880 33 20.40 671.36
600 27+925 52 20.40 1053.46
601 27+975 50 20.40 1027.14
602 28+000 25 20.40 518.98
603 28+025 25 20.40 510.00
604 28+050 25 20.40 510.00
605 28+075 25 20.40 510.00
606 28+115 40 20.40 816.00
607 28+140 25 20.40 510.00
608 28+155 15 20.40 306.00
609 28+175 20 20.40 408.00
610 28+195 20 20.40 408.00
611 28+230 35 20.40 714.00
612 28+250 20 20.40 408.00
613 28+275 25 20.40 510.00
614 28+300 25 20.40 510.00
615 28+325 25 20.40 510.00
616 28+400 75 20.40 1530.00
617 28+425 25 20.40 510.00
618 28+450 25 20.40 510.00
619 28+475 25 20.40 510.00
620 28+486 11 20.40 224.40
621 28+500 14 20.40 285.60
622 28+550 50 20.40 1020.00
623 28+600 50 20.40 1020.00
624 28+625 25 20.40 510.00
625 28+650 25 20.40 510.00
626 28+675 25 20.40 510.00
627 28+725 50 20.40 1020.00
628 28+750 25 20.40 510.00
629 28+825 75 20.40 1533.47
S.No Chainage Length Area Total Qty

630 28+875 54 20.40 1097.72


631 28+925 50 20.40 1021.02
632 28+975 42 20.40 847.01
633 29+000 30 20.40 602.00
634 29+050 49 20.40 1008.78
635 29+100 50 20.40 1025.51
636 29+150 50 20.40 1010.00
637 29+200 29 20.40 588.34
638 29+250 48 20.40 979.20
639 29+300 45 20.40 918.00
640 29+325 31 20.40 631.58
641 29+350 30 20.40 621.38
642 29+400 54 20.40 1107.31
643 29+415 15 20.40 306.00
644 29+450 36 20.40 738.68
645 29+500 50 20.40 1011.43
646 29+550 48 20.40 985.52
647 29+600 53 20.40 1084.06
648 29+625 27 20.40 546.72
649 29+650 45 20.40 924.73
650 29+700 49 20.40 999.60
651 29+750 53 20.40 1071.41
652 29+782 30 20.40 604.66
653 29+800 25 20.40 503.27
654 29+850 48 20.40 977.16
655 29+885 35 20.40 716.65
656 29+925 38 20.40 782.54
657 29+950 27 20.40 560.59
658 30+000 51 20.40 1041.62
659 30+050 49 20.40 995.32
660 30+100 48 20.40 981.65
661 30+150 56 20.40 1147.09
662 30+200 50 20.40 1020.00
663 30+250 52 20.40 1051.62
664 30+300 50 20.40 1022.45
665 30+350 55 20.40 1118.94
666 30+400 48 20.40 982.46
667 30+500 84 20.40 1711.15
668 30+525 25 20.40 516.53
669 30+550 28 20.40 569.57
670 30+575 24 20.40 485.72
671 30+600 24 20.40 492.46
672 30+650 53 20.40 1083.65
673 30+675 25 20.40 502.66
674 30+700 36 20.40 725.63
675 30+725 32 20.40 646.07
676 30+750 26 20.40 529.99
677 30+775 25 20.40 518.57
678 30+825 49 20.40 997.97
S.No Chainage Length Area Total Qty

679 30+850 25 20.40 502.25


680 30+900 50 20.40 1025.71
681 30+950 49 20.40 999.60
682 31+000 50 20.40 1016.53
683 31+050 49 20.40 1002.25
684 31+080 30 20.40 607.92
685 31+100 20 20.40 399.02
686 31+150 50 20.40 1014.49
687 31+175 24 20.40 496.94
688 31+200 25 20.40 517.55
689 31+250 50 20.40 1009.80
690 31+300 51 20.40 1034.28
691 31+325 25 20.40 516.12
692 31+375 49 20.40 1008.98
693 31+425 53 20.40 1081.20
694 31+450 26 20.40 526.32
695 31+475 25 20.40 515.92
696 31+500 25 20.40 509.39
697 31+525 23 20.40 468.18
698 31+545 0.00
0.00
699 31+560 Trugh
0.00
700 31+700
701 31+750 48 20.40 969.20
702 31+800 55 20.40 1131.79
703 31+825 18 20.40 369.04
704 31+850 26 20.40 523.26
705 31+875 25 20.40 509.80
706 31+900 24 20.40 493.88
707 31+925 24 20.40 498.98
708 31+950 24 20.40 480.01
709 31+975 28 20.40 572.83
710 32+000 25 20.40 512.04
711 32+025 34 20.40 700.54
712 32+050 53 20.40 1077.53
713 32+100 29 20.40 581.40
714 32+125 18 20.40 367.00
715 32+175 55 20.40 1121.18
716 32+200 25 20.40 514.08
717 32+225 25 20.40 515.71
718 32+250 22 20.40 458.18
719 32+275 24 20.40 484.50
720 32+300 25 20.40 514.08
721 32+325 25 20.40 516.94
722 32+350 25 20.40 499.80
723 32+375 25 20.40 507.35
724 32+400 24 20.40 492.46
725 32+425 25 20.40 510.82
726 32+450 25 20.40 507.35
S.No Chainage Length Area Total Qty

727 32+475 25 20.40 502.45


728 32+500 25 20.40 504.08

Aqueduct 0.00
729 32+525
730 32+575 50 20.40 1020.00
731 32+625 50 20.40 1020.00
732 32+640 15 20.40 306.00
733 32+665 25 20.40 510.00
734 32+690 25 20.40 510.00
735 32+715 25 20.40 510.00
736 32+750 35 20.40 714.00
737 32+780 30 20.40 612.00
738 32+800 20 20.40 408.00
739 32+825 25 20.40 510.00
740 32+875 25 20.40 499.80
741 32+900 50 20.40 1026.53
742 32+925 25 20.40 518.77
743 32+950 25 20.40 502.45
744 32+980 25 20.40 502.66
745 32+995 15 20.40 306.00
0.00
746 33+004
Aqueduct
0.00
747 33+260
748 33+265 5 24.03 124.24
749 33+280 15 24.03 360.45
750 33+300 20 24.03 480.60
751 33+375 150 24.03 3604.50
752 33+425 50 24.03 1202.46
753 33+475 50 24.03 1193.57
754 33+525 50 24.03 1200.78
755 33+575 50 24.03 1204.86
756 33+625 51 24.03 1218.08
757 33+650 26 24.03 632.47
758 33+675 24 24.03 580.81
759 33+725 50 24.03 1201.50
760 33+775 58 24.03 1401.43
761 33+825 50 24.03 1195.97
762 33+875 49 24.03 1187.32
763 33+925 50 24.03 1202.94
764 34+000 77 24.03 1842.62
765 34+015 14 24.03 344.35
766 34+050 36 24.03 870.13
767 34+100 48 24.03 1154.64
768 34+150 50 24.03 1203.90
769 34+200 51 24.03 1216.40
770 34+250 51 24.03 1214.48
771 34+260 13 24.03 312.39
772 34+275 12 24.03 300.13
S.No Chainage Length Area Total Qty

773 34+300 24 24.03 584.41


774 34+325 25 24.03 608.20
775 34+350 25 24.03 592.82
776 34+375 24 24.03 577.44
777 34+450 75 24.03 1805.85
778 34+475 25 24.03 603.63
779 34+490 16 24.03 372.71
780 34+550 60 24.03 1449.01
781 34+625 75 24.03 1801.53
782 34+675 64 24.03 1549.21
783 34+725 56 24.03 1347.36
784 34+775 48 24.03 1153.68
785 34+825 50 24.03 1197.41
786 34+875 50 24.03 1202.22
787 34+925 49 24.03 1172.18
788 34+975 52 24.03 1240.19
789 35+025 51 24.03 1227.45
790 35+075 49 24.03 1176.03
791 35+125 50 24.03 1209.43
792 35+175 53 24.03 1278.40
793 35+200 25 24.03 594.50
794 35+225 23 24.03 563.50
795 35+250 25 24.03 602.67
796 35+275 25 24.03 607.24
797 35+325 49 24.03 1176.03
798 35+375 50 24.03 1201.26
799 35+425 48 24.03 1164.97
800 35+450 29 24.03 705.04
801 35+500 49 24.03 1177.23
802 35+525 24 24.03 584.65
803 35+550 25 24.03 589.94
804 35+575 24 24.03 569.03
805 35+600 25 24.03 611.32
806 35+650 50 24.03 1197.17
807 35+675 23 24.03 559.90
808 35+735 60 24.03 1438.92
809 35+740 2 24.03 48.06
810 35+825 82 24.03 1981.03
811 35+850 25 24.03 592.82
812 35+935 56 24.03 1345.92
813 35+950 15 24.03 360.21
814 35+965 16 24.03 373.67
815 35+990 25 24.03 600.75
816 36+040 50 24.03 1196.21
817 36+080 40 24.03 954.23
818 36+100 23 24.03 562.30
819 36+120 20 24.03 479.40
820 36+150 30 24.03 717.54
821 36+185 35 24.03 830.72
S.No Chainage Length Area Total Qty

822 36+220 33 24.03 788.66


823 36+245 23 24.03 563.26
824 36+260 14 24.03 346.01
825 36+290 28 24.03 680.05
826 36+305 14 24.03 328.25
827 36+325 19 24.03 457.77
828 36+350 34 24.03 806.69
829 36+400 65 24.03 1557.14
830 36+425 25 24.03 607.24
831 36+450 39 24.03 937.89
832 36+500 48 24.03 1157.04
833 36+550 48 24.03 1142.39
834 36+600 50 24.03 1198.14
835 36+650 52 24.03 1256.05
836 36+700 50 24.03 1204.62
837 36+750 48 24.03 1162.09
838 36+800 48 24.03 1160.89
839 36+850 51 24.03 1230.82
840 36+860 10 24.03 250.63
841 36+900 45 24.03 1083.51
842 36+910 10 24.03 244.87
843 36+950 40 24.03 953.51
844 37+000 50 24.03 1194.05
845 37+065 63 24.03 1521.34
846 37+090 24 24.03 587.29
847 37+150 58 24.03 1393.02
848 37+250 101 24.03 2419.34
849 37+300 50 24.03 1207.03
850 37+350 51 24.03 1225.05
851 37+400 50 24.03 1194.05
852 37+425 24 24.03 584.89
853 37+475 49 24.03 1189.00
854 37+525 50 24.03 1195.25
855 37+550 25 24.03 605.56
856 37+600 50 24.03 1191.89
857 37+650 48 24.03 1161.13
858 37+675 25 24.03 602.67
859 37+700 25 24.03 592.58
860 37+750 50 24.03 1200.06
861 37+775 26 24.03 626.46
862 37+800 26 24.03 613.49
863 37+825 25 24.03 595.94
864 37+860 34 24.03 822.31
865 37+875 15 24.03 370.54
866 37+925 51 24.03 1234.66
867 37+975 49 24.03 1188.76
868 38+000 49 24.03 1169.06
869 38+050 49 24.03 1188.04
870 38+110 60 24.03 1447.81
S.No Chainage Length Area Total Qty

871 38+130 20 24.03 490.45


872 38+150 20 24.03 483.24
873 38+175 25 24.03 611.08
874 38+200 25 24.03 610.12
875 38+250 54 24.03 1297.62
876 38+275 25 24.03 600.75
877 38+300 25 24.03 607.00
878 38+350 50 24.03 1204.14
879 38+375 26 24.03 617.09
880 38+400 25 24.03 605.80
881 38+425 24 24.03 581.77
882 38+450 26 24.03 616.85
883 38+475 24 24.03 586.09
884 38+500 25 24.03 606.28
885 38+550 48 24.03 1142.39
886 38+575 23 24.03 560.38
887 38+625 49 24.03 1167.86
888 38+650 31 24.03 753.82
889 38+700 50 24.03 1189.73
890 38+740 39 24.03 944.38
891 38+800 58 24.03 1395.18
892 38+825 25 24.03 593.54
893 38+850 25 24.03 606.04
894 38+875 25 24.03 600.75
895 38+899 24.25 0.00

Aqueduct 0.00
896 38+958
897 38+966 7.87 42.62 335.42
898 38+980 12 42.62 499.51
899 39+000 21 42.62 899.71
900 39+025 24 42.62 1018.19
901 39+050 25 42.62 1085.11
902 39+090 41 42.62 1764.04
903 39+110 20 42.62 842.60
904 39+120 9 42.62 376.33
905 39+145 24 42.62 1034.52
906 39+180 39 42.62 1678.08
907 39+200 20 42.62 839.19
908 39+225 25 42.62 1052.71
909 39+250 25 42.62 1071.47
910 39+300 50 42.62 2119.92
911 39+350 52 42.62 2223.91
912 39+425 75 42.62 3193.09
913 39+475 52 42.62 2197.06
914 39+525 52 42.62 2195.78
915 39+575 48 42.62 2029.56
916 39+625 50 42.62 2131.00
917 39+650 25 42.62 1065.50
918 39+675 25 42.62 1065.50
S.No Chainage Length Area Total Qty

919 39+700 25 42.62 1065.50


920 39+730 30 42.62 1278.60
921 39+755 25 42.62 1065.50
922 39+780 25 42.62 1065.50
923 39+805 25 42.62 1065.50
924 39+830 25 42.62 1065.50
925 39+875 45 42.62 1917.90
926 39+900 25 42.62 1065.50
927 39+925 24 42.62 1039.93
928 39+950 25 42.62 1085.11
929 39+975 25 42.62 1079.56
930 40+000 25 42.62 1052.71
931 40+050 47 42.62 2008.68
932 40+100 49 42.62 2098.61
933 40+185 84 42.62 3566.87
934 40+235 49 42.62 2092.00
935 40+260 26 42.62 1094.06
936 40+310 50 42.62 2139.10
937 40+360 49 42.62 2108.84
938 40+410 51 42.62 2167.35
939 40+440 30 42.62 1298.63
940 40+475 34 42.62 1464.00
941 40+500 24 42.62 1038.22
942 40+550 52 42.62 2233.29
943 40+600 50 42.62 2128.02
944 40+650 45 42.62 1897.44
945 40+700 47 42.62 2018.91
946 40+750 48 42.62 2041.07
947 40+800 47 42.62 2019.76
948 40+850 51 42.62 2188.54
949 40+900 57 42.62 2435.73
950 40+925 25 42.62 1060.81
951 40+950 20 42.62 867.32
952 40+975 32 42.62 1371.09
953 41+000 23 42.62 984.10
954 41+025 25 42.62 1060.81
955 41+075 46 42.62 1973.73
956 41+110 38 42.62 1616.15
957 41+135 24 42.62 1021.60
958 41+185 42 42.62 1810.07
959 41+220 33 42.62 1412.43
960 41+265 43 42.62 1852.69
961 41+275 11 42.62 486.29

Aqueduct 0.00
962 41+289
963 41+394 105 35.29 3705.45
964 41+400 3 35.29 105.87
965 41+425 24 35.29 833.55
S.No Chainage Length Area Total Qty

966 41+510 85 35.29 2994.00


967 41+550 40 35.29 1423.25
968 41+575 24 35.29 844.49
969 41+625 50 35.29 1765.21
970 41+675 47 35.29 1655.81
971 41+725 51 35.29 1784.97
972 41+777 52 35.29 1827.32
973 41+800 22 35.29 793.32
974 41+850 49 35.29 1721.45
975 41+900 51 35.29 1810.02
976 41+950 50 35.29 1770.50
977 41+975 24 35.29 860.72
978 41+995 19 35.29 656.04
979 42+075 79 35.29 2802.38
980 42+125 49 35.29 1742.62
981 42+175 50 35.29 1765.21
982 42+205 31 35.29 1107.40
983 42+216 11 35.29 386.43
984 42+252 36 35.29 1270.44
985 42+274 21 35.29 733.68
986 42+300 26 35.29 911.54
987 42+350 50 35.29 1753.21
988 42+400 49 35.29 1734.86
989 42+425 26 35.29 908.01
990 42+475 49 35.29 1741.56
991 42+550 72 35.29 2527.82
992 42+575 25 35.29 886.13
993 42+610 32 35.29 1122.93
994 42+635 27 35.29 956.36
995 42+665 34 35.29 1209.74
996 42+715 51 35.29 1786.73
997 42+775 59 35.29 2086.34
998 42+825 50 35.29 1769.79
999 42+850 25 35.29 894.60
1000 42+875 25 35.29 884.01
1001 42+900 25 35.29 880.84
1002 42+950 50 35.29 1749.68
1003 43+000 51 35.29 1797.67
1004 43+050 49 35.29 1728.86
1005 43+100 50 35.29 1762.38
1006 43+150 51 35.29 1816.73
1007 43+200 49 35.29 1723.92
1008 43+215 15 35.29 530.76
1009 43+230 35.29 0.00

Aqueduct 0.00
1010 43+825
1011 43+883 57.92 28.37 1643.19
1012 43+900 18.48 28.37 524.28
S.No Chainage Length Area Total Qty

1013 44+000 87 28.37 2470.74


1014 44+050 50 28.37 1426.73
1015 44+100 50 28.37 1404.32
1016 44+150 51 28.37 1433.25
1017 44+200 50 28.37 1404.88
1018 44+250 48 28.37 1373.68
1019 44+270 20 28.37 560.31
1020 44+283 13 28.37 372.21

Aqueduct 0.00
1021 44+367
1022 44+380 13 38.91 518.67
1023 44+400 14 38.91 563.81
1024 44+450 50 38.91 1954.45
1025 44+500 49 38.91 1925.66
1026 44+550 49 38.91 1890.64
1027 44+578 26 38.91 1007.77
1028 44+596 18 38.91 689.49
1029 44+620 22 38.91 856.02
1030 44+670 45 38.91 1761.07
1031 44+720 45 38.91 1739.28
1032 44+800 80 38.91 3112.80
1033 44+850 50 38.91 1933.05
1034 44+900 52 38.91 2037.83
1035 44+950 50 38.91 1938.11
1036 45+025 71 38.91 2780.90
1037 45+075 49 38.91 1912.82
1038 45+100 24 38.91 944.35
1039 45+150 50 38.91 1933.83
1040 45+200 49 38.91 1917.10
1041 45+250 50 38.91 1936.94
1042 45+290 40 38.91 1540.45
1043 45+320 30 38.91 1182.09
1044 45+370 48 38.91 1857.56
1045 45+420 50 38.91 1945.50
1046 45+470 53 38.91 2045.89
1047 45+520 50 38.91 1945.50
1048 45+570 50 38.91 1942.93
1049 45+630 60 38.91 2334.60
1050 45+655 25 38.91 972.75
1051 45+680 23 38.91 894.93
1052 45+730 49 38.91 1906.59
1053 45+755 27 38.91 1050.57
1054 45+785 25 38.91 972.75
1055 45+801 16 38.91 622.56

Aqueduct 0.00
1056 45+813
1057 45+845 32 38.91 1245.12
1058 45+852 9 38.91 350.19
S.No Chainage Length Area Total Qty

1059 45+878 20 38.91 778.20


1060 45+900 21 38.91 817.11
1061 45+940 35 38.91 1361.85
1062 45+790 62 38.91 2412.42
1063 45+850 60 38.91 2334.60
1064 45+900 49 38.91 1906.59
1065 45+950 50 38.91 1945.50
1066 46+000 50 38.91 1945.50
1067 46+050 49 38.91 1906.59
1068 46+100 50 38.91 1945.50
1069 46+150 51 38.91 1966.90
1070 46+175 25 38.91 972.75
1071 46+225 50 38.91 1945.50
1072 46+275 52 38.91 2023.32
1073 46+300 26 38.91 992.21
1074 46+350 51 38.91 1964.96
1075 46+400 50 38.91 1945.50
1076 46+450 49 38.91 1887.14
1077 46+500 54 38.91 2081.69
1078 46+550 48 38.91 1848.23
1079 46+600 47 38.91 1809.32
1080 46+650 49 38.91 1906.59
1081 46+700 50 38.91 1945.50
1082 46+750 49 38.91 1906.59
1083 46+800 50 38.91 1945.50
1084 46+850 47 38.91 1828.77
1085 46+900 48 38.91 1867.68
1086 46+950 51 38.91 1984.41
1087 47+000 51 38.91 1984.41
1088 47+050 51 38.91 1984.41
1089 47+080 33 38.91 1264.58
1090 47+100 19 38.91 739.29
1091 47+150 49 38.91 1906.59
1092 47+200 49 38.91 1906.59
1093 47+250 49 38.91 1906.59
1094 47+300 48 38.91 1867.68
1095 47+350 49 38.91 1906.59
1096 47+400 57 38.91 2217.87
1097 47+425 25 38.91 972.75
1098 47+475 47 38.91 1828.77
1099 47+500 23 38.91 894.93

Aqueduct 0.00
1100 47+510
1101 47+618 108 30.00 3240.00
1102 47+619 1 30.00 30.00
1103 47+650 28.76 30.00 862.80
1104 47+700 53 30.00 1590.00
1105 47+750 44 30.00 1320.00
S.No Chainage Length Area Total Qty

1106 47+800 49.5 30.00 1485.00


1107 47+850 68 30.00 2040.00
1108 47+950 110 30.00 3300.00
1109 48+050 90 30.00 2700.00
1110 48+100 64 30.00 1920.00
1111 48+200 98 30.00 2940.00
1112 48+300 100 30.00 3000.00
1113 48+400 101 30.00 3030.00
1114 48+500 100 30.00 3000.00
1115 48+540 38 30.00 1140.00
1116 48+560 18 30.00 540.00
1117 48+600 39 30.00 1170.00
1118 48+650 50 30.00 1500.00
1119 48+700 52 30.00 1560.00
1120 48+750 52 30.00 1560.00
1121 48+800 51 30.00 1530.00
1122 48+860 61 30.00 1830.00
1123 48+875 16 30.00 480.00
1124 48+885 10 30.00 300.00
1125 48+975 90 30.00 2700.00
1126 48+990 15 30.00 450.00
1127 49+015 26 30.00 780.00
1128 49+040 25 30.00 750.00
1129 49+065 25 30.00 750.00
1130 49+115 49 30.00 1470.00
1131 49+125 10 30.00 300.00
1132 49+150 25 30.00 750.00
1133 49+200 49 30.00 1470.00
1134 49+250 51 30.00 1530.00
1135 49+300 49 30.00 1470.00
1136 49+350 50 30.00 1500.00
1137 49+400 53 30.00 1590.00
1138 49+450 49 30.00 1470.00
1139 49+500 51 30.00 1530.00
1140 49+550 49 30.00 1470.00
1141 49+580 30 30.00 900.00
1142 49+630 60 30.00 1800.00
1143 49+655 26 30.00 780.00
1144 49+700 38 30.00 1140.00
1145 49+750 51 30.00 1530.00
1146 49+780 30 30.00 900.00
1147 49+800 20 30.00 600.00
1148 49+850 44 30.00 1320.00
1149 49+900 49 30.00 1470.00
1150 49+950 44 30.00 1320.00
1151 50+000 52 30.00 1560.00
1152 50+050 51 30.00 1530.00
1153 50+100 50.5 30.00 1515.00
1154 50+150 50 30.00 1500.00
S.No Chainage Length Area Total Qty

1155 50+200 47 30.00 1410.00


1156 50+225 24 30.00 720.00
1157 50+275 50 30.00 1500.00
1158 50+325 50 30.00 1500.00
1159 50+370 45 30.00 1350.00
1160 50+393 23 30.00 690.00
1161 50+410 17 30.00 510.00
1162 50+450 40 30.00 1200.00
1163 50+500 50 30.00 1500.00
1164 50+550 50 30.00 1500.00
1165 50+550 0.00
Syphon
1166 50+550 0.00
1167 50+600 50 20.88 1044.00
1168 50+650 50 20.88 1044.00
1169 50+675 24 20.88 501.12
1170 50+700 25 20.88 522.00
1171 50+750 52 20.88 1085.76
1172 50+800 48 20.88 1002.24
1173 50+850 51 20.88 1064.88
1174 50+900 54 20.88 1127.52
1175 50+950 51 20.88 1064.88
1176 51+000 50 20.88 1044.00
1177 51+050 50 20.88 1044.00
1178 51+100 47 20.88 981.36
1179 51+150 50 20.88 1044.00
1180 51+200 49 20.88 1023.12
1181 51+250 50 20.88 1044.00
1182 51+275 23 20.88 480.24
1183 51+300 25 20.88 522.00
1184 51+350 55 20.88 1148.40
1185 51+400 44 20.88 918.72
1186 51+450 49 20.88 1023.12
1187 51+500 49 20.88 1023.12
1188 51+550 48 20.88 1002.24
1189 51+600 50 20.88 1044.00
1190 51+635 33 20.88 689.04
1191 51+670 35 20.88 730.80
1192 51+720 49 20.88 1023.12
1193 51+770 51 20.88 1064.88
1194 51+800 29 20.88 605.52
1195 51+825 25 20.88 522.00
1196 51+875 51 20.88 1064.88
1197 51+925 50 20.88 1044.00
1198 51+965 39 20.88 814.32
1199 51+985 23 20.88 480.24
1200 52+000 17 20.88 354.96
1201 52+050 49 20.88 1023.12
1202 52+100 50 20.88 1044.00
1203 52+130 29.24 20.88 610.53
S.No Chainage Length Area Total Qty

1204 52+150 17 20.88 354.96


1205 52+200 51 20.88 1064.88
1206 52+250 51 20.88 1064.88
1207 52+300 53 20.88 1106.64
1208 52+325 26 20.88 542.88
1209 52+350 25 20.88 522.00
1210 52+375 24 20.88 501.12
1211 52+425 50 20.88 1044.00
1212 52+470 45 20.88 939.60
1213 52+500 28 20.88 584.64
1214 52+550 49 20.88 1023.12
1215 52+600 49 20.88 1023.12
1216 52+650 50 20.88 1044.00
1217 52+700 49 20.88 1023.12
1218 52+750 49 20.88 1023.12
1219 52+790 34 20.88 709.92
1220 52+830 36 20.88 751.68
1221 52+878 40 20.88 835.20
1222 52+910 40 20.88 835.20
1223 52+950 40 20.88 835.20
1224 53+000 48 20.88 1002.24
1225 53+020 17 20.88 354.96
1226 53+030 10 20.88 208.80
1227 53+040 10 20.88 208.80
1229 53+060 19 20.88 396.72
1230 53+080 20 20.88 417.60
1231 53+130 49 20.88 1023.12
1232 53+180 50 20.88 1044.00
1233 53+215 36 20.88 751.68
1234 53+255 39 20.88 814.32
1235 53+275 20 20.88 417.60
1236 53+300 25 20.88 522.00
1237 53+325 28 20.88 584.64
1238 53+375 51 20.88 1064.88
1239 53+425 46 20.88 960.48
1240 53+475 50 20.88 1044.00
1241 53+525 50 20.88 1044.00
1242 53+575 50 20.88 1044.00
1243 53+625 52 20.88 1085.76
1244 53+675 49 20.88 1023.12
1245 53+725 49 20.88 1023.12
1246 53+740 15 20.88 313.20
1247 53+765 25 20.88 522.00
1248 53+800 35 20.88 730.80
1249 53+850 47 20.88 981.36
1252 53+900 49 20.88 1023.12
1253 53+950 50 20.88 1044.00
1254 53+980 31 20.88 647.28
1255 54+055 75 20.88 1566.00
S.No Chainage Length Area Total Qty

1256 54+080 24 20.88 501.12


1257 54+120 40 20.88 835.20
1258 54+145 28 20.88 584.64
1259 54+175 32 20.88 668.16
1260 54+200 24 20.88 501.12
1261 54+225 24 20.88 501.12
1262 54+250 26 20.88 542.88
1263 54+300 50 20.88 1044.00
1264 54+350 47 20.88 981.36
1265 54+400 50 20.88 1044.00
1266 54+450 50 20.88 1044.00
1267 54+480 27 20.88 563.76
1268 54+500 21 20.88 438.48
1269 54+550 47 20.88 981.36
1270 54+580 29 20.88 605.52
1271 54+610 27 20.88 563.76
1272 54+650 39 20.88 814.32
1273 54+700 52 20.88 1085.76
1274 54+740 41 20.88 856.08
1275 54+790 48 20.88 1002.24
1276 54+840 50 20.88 1044.00
1277 54+875 37 20.88 772.56
1278 54+900 22 20.88 459.36
1279 54+925 22 20.88 459.36
1280 54+975 48 20.88 1002.24
1281 55+000 26 20.88 542.88
1282 55+050 50 20.88 1044.00
1283 55+100 52 20.88 1085.76
1284 55+125 18 20.88 375.84
1285 55+145 25 20.88 522.00
1286 55+200 56 20.88 1169.28
1287 55+250 45 20.88 939.60
1288 55+290 37 20.88 772.56
1289 55+340 47 20.88 981.36
1290 55+390 47 20.88 981.36
1291 55+415 26 20.88 542.88
1292 55+450 34 20.88 709.92
1293 55+520 70 20.88 1461.60
1294 55+560 35 20.88 730.80
1295 55+600 40 20.88 835.20
1296 55+650 51 20.88 1064.88
1297 55+700 49 20.88 1023.12
1298 55+760 59 20.88 1231.92
1299 55+800 41 20.88 856.08
1300 55+850 49 20.88 1023.12
1301 55+900 50 20.88 1044.00
1302 55+960 60 20.88 1252.80
1303 56+010 51 20.88 1064.88
1304 56+050 42 20.88 876.96
S.No Chainage Length Area Total Qty

1305 56+100 50 20.88 1044.00


1306 56+150 49 20.88 1023.12
1307 56+210 59 20.88 1231.92
1308 56+250 41 20.88 856.08
1309 56+300 52 20.88 1085.76
1310 56+360 63 20.88 1315.44
1311 56+400 37 20.88 772.56
1312 56+450 46 20.88 960.48
1313 56+500 50 20.88 1044.00
1314 56+550 50 20.88 1044.00
1315 56+610 60 20.88 1252.80
1316 56+650 38 20.88 793.44
1317 56+700 47 20.88 981.36
1318 56+750 44 20.88 918.72
1319 56+800 54 20.88 1127.52
1320 56+850 51 20.88 1064.88
1321 56+900 52 20.88 1085.76
1322 56+975 74 20.88 1545.12
1323 57+000 29 20.88 605.52
1324 57+040 38 20.88 793.44
1325 57+070 29 20.88 605.52
1326 57+110 40 20.88 835.20
1327 57+150 38 20.88 793.44
1328 57+210 60 20.88 1252.80
1329 57+260 51 20.88 1064.88
1330 57+290 27 20.88 563.76
1331 57+330 37 20.88 772.56
1332 57+385 56 20.88 1169.28
1333 57+440 54 20.88 1127.52
1334 57+490 49 20.88 1023.12
1335 57+515 26 20.88 542.88
1336 57+550 34 20.88 709.92
1337 57+590 37 20.88 772.56
1338 57+660 70 20.88 1461.60
1339 57+737 78 20.88 1628.64
1340 57+752 15 20.88 313.20
1341 57+773 16 20.88 334.08
1342 57+807 34 20.88 709.92
1343 57+838 32 20.88 668.16
1344 57+871 33 20.88 689.04
1345 57+896 25 20.88 522.00
1346 57+952 57 20.88 1190.16
1347 57+968 17 20.88 354.96
1348 58+010 44 20.88 918.72
1349 58+080 67 20.88 1398.96
1350 58+125 45 20.88 939.60
1351 58+150 24 20.88 501.12
1352 58+200 50 20.88 1044.00
1353 58+225 25 20.88 522.00
S.No Chainage Length Area Total Qty

1354 58+265 39 20.88 814.32


1355 58+295 29 20.88 605.52
1356 58+320 23 20.88 480.24
1357 58+350 30 20.88 626.40
1358 58+390 41 20.88 856.08
1359 58+430 41 20.88 856.08
1360 58+455 25 20.88 522.00
1361 58+480 25 20.88 522.00
1362 58+556 89 20.88 1858.32
1363 58+580 24 20.88 501.12
1364 58+600 20 20.88 417.60
1365 58+625 26 20.88 542.88
1366 58+675 49 20.88 1023.12
1367 58+695 20 20.88 417.60
1368 58+760 55 20.88 1148.40
1369 58+800 40 20.88 835.20
1370 58+840 41 20.88 856.08
1371 58+855 16 20.88 334.08
1372 58+870 15 20.88 313.20
1373 58+900 30 20.88 626.40
1374 58+930 28 20.88 584.64
1375 58+955 26 20.88 542.88
1376 58+990 35 20.88 730.80
1377 59+015 24 20.88 501.12
1378 59+042 28 20.88 584.64
1379 59+060 19 20.88 396.72
1380 59+100 40 20.88 835.20
1381 59+140 40 20.88 835.20
1382 59+170 31 20.88 647.28
1383 59+185 15 20.88 313.20
1384 59+200 16 20.88 334.08
1385 59+225 24 20.88 501.12
1386 59+260 35 20.88 730.80
1387 59+300 42 20.88 876.96
1388 59+335 35 20.88 730.80
1389 59+375 40 20.88 835.20
1390 59+410 35 20.88 730.80
1391 59+435 35 20.88 730.80
1392 59+485 49 20.88 1023.12
1393 59+535 51 20.88 1064.88
1394 59+575 40 20.88 835.20
1395 59+605 30 20.88 626.40
1396 59+650 46 20.88 960.48
1397 59+676 26 20.88 542.88
1398 59+759 83 20.88 1733.04
1399 59+794 35 20.88 730.80
1400 59+830 35 20.88 730.80
1401 59+862 32 20.88 668.16
1402 59+880 18 20.88 375.84
S.No Chainage Length Area Total Qty

1403 59+910 30 20.88 626.40


1404 59+958 48 20.88 1002.24
1405 60+000 43 20.88 897.84
1406 60+250 250 20.88 5220.00
1408 60+430 180 20.88 3758.40 old ts area
1409 60+525 95 20.88 1983.60
1410 60+575 51 20.88 1064.88
1411 60+625 50 20.88 1044.00
1412 60+675 50 20.88 1044.00
1413 60+725 50 20.88 1044.00
1414 60+775 50 20.88 1044.00
1415 60+825 51 20.88 1064.88
1416 60+875 49 20.88 1023.12
1417 60+925 52 20.88 1085.76
1418 60+975 51 20.88 1064.88
1419 61+025 51 20.88 1064.88
1420 61+075 52 20.88 1085.76
1421 61+100 25 20.88 522.00
1422 61+150 51 20.88 1064.88
1423 61+200 52 20.88 1085.76
1424 61+220 24 20.88 501.12
1425 61+245 25 20.88 522.00
1426 61+270 26 20.88 542.88
1427 61+320 51 20.88 1064.88
1428 61+370 52 20.88 1085.76
1429 61+400 28 20.88 584.64
1430 61+450 52 20.88 1085.76
1431 61+500 50 20.88 1044.00
1432 61+565 65 20.88 1357.20
1433 61+600 33.43 20.88 698.02
1434 61+660 62 20.88 1294.56
1435 61+700 42 20.88 876.96
1436 61+725 25 20.88 522.00
1437 61+750 25 20.88 522.00
1438 61+785 36 20.88 751.68
1439 61+835 50 20.88 1044.00
1440 61+885 50 20.88 1044.00
1441 61+935 52 20.88 1085.76
1442 61+985 50 20.88 1044.00
1443 62+015 30 20.88 626.40
1444 62+065 51 20.88 1064.88
1445 62+115 52 20.88 1085.76
1446 62+150 35 20.88 730.80
1447 62+180 31 20.88 647.28
1448 62+220 40 20.88 835.20
1449 62+270 48 20.88 1002.24
1450 62+290 21 20.88 438.48
1451 62+305 15 20.88 313.20
1452 62+320 16 20.88 334.08
S.No Chainage Length Area Total Qty

1453 62+350 31 20.88 647.28


1454 62+400 49 20.88 1023.12
1455 62+450 64 20.88 1336.32
1456 62+506 48 20.88 1002.24
1457 62+550 51 20.88 1064.88
1458 62+600 51 20.88 1064.88
1459 62+650 52 20.88 1085.76
1460 62+700 50 20.88 1044.00
1461 62+750 56 20.88 1169.28
1462 62+800 49 20.88 1023.12
1463 62+860 60 20.88 1252.80
1464 62+910 52 20.88 1085.76
1465 62+960 50 20.88 1044.00
1466 63+010 54 20.88 1127.52
1467 63+065 54 20.88 1127.52
1468 63+090 25 20.88 522.00
1469 63+140 51 20.88 1064.88
1470 63+190 53 20.88 1106.64
1471 63+240 49 20.88 1023.12
1472 63+270 51 20.88 1064.88
1473 63+340 51 20.88 1064.88
1474 63+410 71 20.88 1482.48
1475 63+450 39 20.88 814.32
1476 63+480 31 20.88 647.28
1477 63+500 21 20.88 438.48
1478 63+545 45 20.88 939.60
1479 63+595 51 20.88 1064.88
1480 63+625 36 20.88 751.68
1481 63+660 36 20.88 751.68
1482 63+710 51 20.88 1064.88
1483 63+750 35 20.88 730.80
1484 63+795 43 20.88 897.84
1485 63+860 60 20.88 1252.80
1486 63+900 36 20.88 751.68
1487 63+950 53 20.88 1106.64
1488 63+970 20 20.88 417.60
1489 64+020 53 20.88 1106.64
1490 64+050 30 20.88 626.40
1491 64+100 49 20.88 1023.12
1492 64+150 50 20.88 1044.00
1493 64+180 30 20.88 626.40
1494 64+210 32 20.88 668.16
1495 64+250 39 20.88 814.32
1496 64+300 43 20.88 897.84
1497 64+344 43 20.88 897.84
1498 64+364 19 20.88 396.72

Aqueduct 0.00
1499 64+475
1500 64+500 25 33.18 829.50
S.No Chainage Length Area Total Qty

1501 64+550 52 33.18 1725.36


1502 64+600 51 33.18 1692.18
1503 64+650 51 33.18 1692.18
1504 64+700 52 33.18 1725.36
1505 64+735 30 33.18 995.40
1506 64+765 31 33.18 1028.58
1507 64+800 32 33.18 1061.76
1508 64+850 51 33.18 1692.18
1509 64+900 57 33.18 1891.26
1510 64+950 45 33.18 1493.10
1511 65+000 49 33.18 1625.82
1512 65+020 25 33.18 829.50
1513 65+050 27 33.18 895.86
1514 65+100 50 33.18 1659.00
1515 65+150 46 33.18 1526.28
1516 65+180 32 33.18 1061.76
1517 65+210 33 33.18 1094.94
1518 65+260 55 33.18 1824.90
1519 65+285 26 33.18 862.68
1520 65+315 29 33.18 962.22
1521 65+345 35 33.18 1161.30
1522 65+375 31 33.18 1028.58
1523 65+425 54 33.18 1791.72
1524 65+475 50 33.18 1659.00
1525 65+525 54 33.18 1791.72
1526 65+540 14 33.18 464.52
1527 65+570 30 33.18 995.40
1528 65+600 29 33.18 962.22
1529 65+650 51 33.18 1692.18
1530 65+700 48 33.18 1592.64
1531 65+750 52 33.18 1725.36
1532 65+800 48 33.18 1592.64
1533 65+830 24 33.18 796.32
1534 65+850 21 33.18 696.78
1535 65+900 49 33.18 1625.82
1536 65+950 52 33.18 1725.36
1537 66+000 50 33.18 1659.00
1538 66+025 24 33.18 796.32
1539 66+075 47 33.18 1559.46
1540 66+125 51 33.18 1692.18
1541 66+175 49 33.18 1625.82
1542 66+225 51 33.18 1692.18
1543 66+275 49 33.18 1625.82
1544 66+325 43 33.18 1426.74
1545 66+375 49 33.18 1625.82
1546 66+425 50 33.18 1659.00
1547 66+500 74 33.18 2455.32
1548 66+550 47 33.18 1559.46
1549 66+575 27 33.18 895.86
S.No Chainage Length Area Total Qty

1550 66+600 24 33.18 796.32


1551 66+650 50 33.18 1659.00
1552 66+700 47 33.18 1559.46
1553 66+750 52 33.18 1725.36
1554 66+800 50 33.18 1659.00
1555 66+850 49 33.18 1625.82
1556 66+900 48 33.18 1592.64
1557 66+950 49 33.18 1625.82
1558 67+000 49 33.18 1625.82
1559 67+050 48 33.18 1592.64
1560 67+080 31 33.18 1028.58
1561 67+100 19 33.18 630.42
1562 67+125 24 33.18 796.32
1563 67+175 50 33.18 1659.00
1564 67+225 51 33.18 1692.18
1565 67+275 50 33.18 1659.00
1566 67+300 20 33.18 663.60
1567 67+350 47 33.18 1559.46
1568 67+400 49 33.18 1625.82
1569 67+440 39 33.18 1294.02
1570 67+480 36 33.18 1194.48
1571 67+530 47 33.18 1559.46
1572 67+560 30 33.18 995.40
1573 67+600 39 33.18 1294.02
1574 67+650 51 33.18 1692.18
1575 67+700 48 33.18 1592.64
1576 67+750 50 33.18 1659.00
1577 67+800 47 33.18 1559.46
1578 67+825 23 33.18 763.14
1579 67+850 26 33.18 862.68
1580 67+900 48 33.18 1592.64
1581 67+950 49 33.18 1625.82
1582 68+000 53 33.18 1758.54
1583 68+050 46 33.18 1526.28
1584 68+100 49 33.18 1625.82
1585 68+140 41 33.18 1360.38
1586 68+165 39 33.18 1294.02
1587 68+200 35 33.18 1161.30
1588 68+250 55 33.18 1824.90
1589 68+300 47 33.18 1559.46
1590 68+340 40 33.18 1327.20
1591 68+365 24 33.18 796.32
1592 68+390 27 33.18 895.86
1593 68+435 52 33.18 1725.36
1594 68+500 38 33.18 1260.84
1595 68+550 48 33.18 1592.64
1596 68+600 50 33.18 1659.00
1597 68+650 50 33.18 1659.00
1598 68+700 50 33.18 1659.00
S.No Chainage Length Area Total Qty

1599 68+740 37 33.18 1227.66


1600 68+758 19 33.18 630.42
1601 68+798 39 33.18 1294.02
1602 68+850 50 33.18 1659.00
1603 68+900 50 33.18 1659.00
1604 68+950 46 33.18 1526.28
1605 69+000 50 33.18 1659.00
1606 69+050 50 33.18 1659.00
1607 69+100 48 33.18 1592.64
1608 69+150 51 33.18 1692.18
1609 69+200 51 33.18 1692.18
1610 69+250 48 33.18 1592.64
1611 69+300 48 33.18 1592.64
1612 69+350 52 33.18 1725.36
1613 69+400 50 33.18 1659.00
1614 69+450 52 33.18 1725.36
1615 69+490 41 33.18 1360.38
1616 69+520 30 33.18 995.40
1617 69+550 31 33.18 1028.58
1618 69+600 48 33.18 1592.64
1619 69+650 51 33.18 1692.18
1620 69+700 52 33.18 1725.36
1621 69+720 19 33.18 630.42
1622 69+745 26 33.18 862.68
1623 69+795 50 33.18 1659.00
1624 69+830 35 33.18 1161.30
1625 69+870 40 33.18 1327.20
1626 69+930 60 33.18 1990.80
1627 69+980 50 33.18 1659.00
1628 70+010 30 33.18 995.40
1629 70+060 50 33.18 1659.00
1630 70+110 50 33.18 1659.00
1631 70+140 30 33.18 995.40
1632 70+200 60 33.18 1990.80
1633 70+250 50 33.18 1659.00
1634 70+305 55 33.18 1824.90
1635 70+315 10 33.18 331.80
1636 70+315 0 33.18 0.00
1637 70+355 40 33.18 1327.20
1638 70+447 92 33.18 3052.56
1639 70+500 53 33.18 1758.54
1640 70+540 40 33.18 1327.20
1641 70+570 30 33.18 995.40
1642 70+595 25 33.18 829.50
1643 70+625 30 33.18 995.40
1644 70+655 30 33.18 995.40
1645 70+670 15 33.18 497.70
1646 70+700 30 33.18 995.40
1647 70+750 50 33.18 1659.00
S.No Chainage Length Area Total Qty

1648 70+800 50 33.18 1659.00


1649 70+850 50 33.18 1659.00
1650 70+900 50 33.18 1659.00
1651 70+950 50 33.18 1659.00
1652 71+000 50 33.18 1659.00
1653 71+050 50 33.18 1659.00
1654 71+100 50 33.18 1659.00
1655 71+150 50 33.18 1659.00
1656 71+200 50 33.18 1659.00
1657 71+250 50 33.18 1659.00
1658 71+300 50 33.18 1659.00
1659 71+337 37 33.18 1227.66
1660 71+354 17 33.18 564.06
1661 71+400 46 33.18 1526.28
1662 71+440 40 33.18 1327.20
1663 71+490 50 33.18 1659.00
1664 71+525 35 33.18 1161.30
1665 71+545 20 33.18 663.60
1666 71+600 55 33.18 1824.90
1667 71+650 50 33.18 1659.00
1668 71+700 50 33.18 1659.00
1669 71+750 50 33.18 1659.00
1670 71+800 50 33.18 1659.00
1671 71+850 50 33.18 1659.00
1672 71+900 50 33.18 1659.00
1673 71+950 50 33.18 1659.00
1674 72+000 50 33.18 1659.00
1675 72+050 50 33.18 1659.00
1676 72+100 50 33.18 1659.00
1677 72+125 25 33.18 829.50
1678 72+150 25 33.18 829.50
1679 72+200 50 33.18 1659.00
1680 72+250 50 33.18 1659.00
1681 72+300 50 33.18 1659.00
1682 72+350 50 33.18 1659.00
1683 72+400 50 33.18 1659.00
1684 72+450 50 33.18 1659.00
1685 72+500 50 33.18 1659.00
1686 72+550 50 33.18 1659.00
1687 72+600 50 33.18 1659.00
1688 72+650 50 33.18 1659.00
1689 72+700 50 33.18 1659.00
1690 72+750 50 33.18 1659.00
1691 72+793 43 33.18 1426.74
1692 72+809 16 33.18 530.88
1693 72+858 49 33.18 1625.82
1694 72+900 42 33.18 1393.56
1695 72+933 33 33.18 1094.94
1696 72+955 22 33.18 729.96
S.No Chainage Length Area Total Qty

1697 73+000 45 33.18 1493.10


1698 73+033 33 33.18 1094.94
1699 73+050 17 33.18 564.06
1700 73+050 0 33.18 0.00
1701 73+058 8 33.18 265.44
1702 73+086 28 33.18 929.04
1703 73+115 29 33.18 962.22
1704 73+146 31 33.18 1028.58
1705 73+196 50 33.18 1659.00
1706 73+246 50 33.18 1659.00
1707 73+296 50 33.18 1659.00
1708 73+346 50 33.18 1659.00
1709 73+396 50 33.18 1659.00
1710 73+426 30 33.18 995.40
1711 73+490 64 33.18 2123.52
1712 73+510 20 33.18 663.60
1713 73+575 65 33.18 2156.70
1714 73+605 30 33.18 995.40
1715 73+650 45 33.18 1493.10
1716 73+700 50 33.18 1659.00
1717 73+750 50 33.18 1659.00
1718 73+775 25 33.18 829.50
1719 73+825 50 33.18 1659.00
1720 73+875 50 33.18 1659.00
1721 73+900 25 33.18 829.50
1722 73+925 25 33.18 829.50
1723 73+955 30 33.18 995.40
1724 74+005 50 33.18 1659.00
1725 74+035 30 33.18 995.40
1726 74+085 50 33.18 1659.00
1727 74+145 60 33.18 1990.80
1728 74+185 40 33.18 1327.20
1729 74+210 25 33.18 829.50
1730 74+260 50 33.18 1659.00
1731 74+330 70 33.18 2322.60
1732 74+380 50 33.18 1659.00
1733 74+470 90 33.18 2986.20
1734 74+486 16 33.18 530.88
1735 74+514 28 33.18 929.04
1736 74+562 48 33.18 1592.64
1737 74+604 42 33.18 1393.56
1738 74+611 7 33.18 232.26
1739 74+626 15 33.18 497.70
1740 74+652 26 33.18 862.68
1741 74+712 60 33.18 1990.80
1742 74+735 23 33.18 763.14
1743 74+761 26 33.18 862.68
1744 74+795 34 33.18 1128.12
1745 74+845 50 33.18 1659.00
S.No Chainage Length Area Total Qty

1746 74+890 45 33.18 1493.10


1747 74+940 50 33.18 1659.00
1748 74+990 50 33.18 1659.00
1749 75+026 36 33.18 1194.48
1750 75+076 50 33.18 1659.00
1751 75+096 20 33.18 663.60
1752 75+176 80 33.18 2654.40
1753 75+245 69 33.18 2289.42
1754 75+295 50 33.18 1659.00
1755 75+325 30 33.18 995.40
1756 75+380 55 33.18 1824.90
1757 75+410 30 33.18 995.40
1758 75+435 25 33.18 829.50
1759 75+460 25 33.18 829.50
1760 75+505 45 33.18 1493.10
1761 75+540 35 33.18 1161.30
1762 75+590 50 33.18 1659.00
1763 75+640 50 33.18 1659.00
1764 75+705 65 33.18 2156.70
1765 75+725 20 33.18 663.60
1766 75+750 25 33.18 829.50
1767 75+780 30 33.18 995.40
1768 75+830 50 33.18 1659.00
1769 75+860 30 33.18 995.40
1770 75+890 30 33.18 995.40
1771 75+926 36 33.18 1194.48
1772 75+949 23 33.18 763.14
1773 76+009 60 33.18 1990.80
1774 76+039 30 33.18 995.40
1775 76+084 45 33.18 1493.10
1776 76+099 15 33.18 497.70
1777 76+149 50 33.18 1659.00
1778 76+190 41 33.18 1360.38
1779 76+250 60 33.18 1990.80
1780 76+500 250 33.18 8295.00
1781 76+750 250 33.18 8295.00
1782 77+000 250 33.18 8295.00
1783 77+250 250 33.18 8295.00
1784 77+500 250 33.18 8295.00
1785 77+750 250 33.18 8295.00
1786 78+000 250 33.18 8295.00
1787 78+250 250 33.18 8295.00
1788 78+500 250 33.18 8295.00
1789 78+750 250 33.18 8295.00
1790 79+000 250 33.18 8295.00
1791 79+250 250 33.18 8295.00
1792 79+500 250 33.18 8295.00
1793 79+750 250 33.18 8295.00
1794 80+000 250 33.18 8295.00
S.No Chainage Length Area Total Qty

1795 80+250 250 33.18 8295.00


1796 80+500 250 33.18 8295.00
1797 80+750 250 33.18 8295.00
1798 81+000 250 33.18 8295.00
1799 81+250 250 33.18 8295.00
1800 81+500 250 33.18 8295.00
1801 81+525 0.00
1802 81+750 0.00
1803 82+000 0.00
SYPHON
1804 82+250 0.00
1805 82+500 0.00
1806 82+530 0.00
1807 82+750 0 18.31 0.00
1808 83+000 250 18.31 4577.50
1809 83+250 250 18.31 4577.50
1810 83+500 250 18.31 4577.50
1811 83+750 250 18.31 4577.50
1812 84+000 250 18.31 4577.50
1813 84+250 250 18.31 4577.50
1814 84+500 250 18.31 4577.50
1815 84+750 250 18.31 4577.50
1816 85+000 250 18.31 4577.50
1817 85+175 0.00
1818 85+250 AQUEDUCT 0.00
1819 85+390 0.00
1820 85+500 110 29.47 3241.70
1821 85+750 250 29.47 7367.50
1822 86+000 250 29.47 7367.50
1823 86+250 250 29.47 7367.50
1824 86+500 250 29.47 7367.50
1825 86+750 250 29.47 7367.50
1826 87+000 250 29.47 7367.50
1827 87+250 250 29.47 7367.50
1828 87+500 250 29.47 7367.50
1829 87+750 250 29.47 7367.50
1830 88+000 250 29.47 7367.50
1831 88+250 250 29.47 7367.50
1832 88+500 250 29.47 7367.50
1833 88+750 250 29.47 7367.50
1834 89+000 250 29.47 7367.50
1835 89+250 250 29.47 7367.50
1836 89+500 250 29.47 7367.50
1837 89+750 250 29.47 7367.50
1838 90+000 250 29.47 7367.50
1839 90+250 250 29.47 7367.50
1840 90+500 250 29.47 7367.50
1841 90+750 250 29.47 7367.50
1842 91+000 250 29.47 7367.50
1843 91+500 500 29.47 14735.00
S.No Chainage Length Area Total Qty

1844 91+750 250 29.47 7367.50


1845 92+000 250 29.47 7367.50
1846 92+250 250 29.47 7367.50
1847 92+500 250 29.47 7367.50
1848 92+750 250 29.47 7367.50
1849 93+000 250 29.47 7367.50
1850 93+250 250 29.47 7367.50
1851 93+500 250 29.47 7367.50
1852 93+750 250 29.47 7367.50
1853 94+000 250 29.47 7367.50
1854 94+250 250 29.47 7367.50
1855 94+500 250 29.47 7367.50
1856 94+750 250 29.47 7367.50
1857 95+000 250 29.47 7367.50
1858 95+250 250 29.47 7367.50
1859 95+500 250 29.47 7367.50
1860 95+750 250 29.47 7367.50
1861 96+000 250 29.47 7367.50
1862 96+250 250 29.47 7367.50
1863 96+500 250 29.47 7367.50
1864 96+750 250 29.47 7367.50
1865 97+000 250 29.47 7367.50
1866 97+250 250 29.47 7367.50
1867 97+500 250 29.47 7367.50
1868 97+750 250 29.47 7367.50
1869 98+000 29.47 0.00
AQUEDUCT
1870 98+077 29.47 0.00
1871 98+250 173 29.47 5098.31
1872 98+500 250 29.47 7367.50
1873 98+750 250 29.47 7367.50
1874 99+000 250 29.47 7367.50
1875 99+250 250 29.47 7367.50
1876 99+500 250 29.47 7367.50
1877 99+750 250 29.47 7367.50
1878 100+000 250 29.47 7367.50
1879 100+250 250 29.47 7367.50
1880 100+500 250 29.47 7367.50
1881 100+750 250 29.47 7367.50
1882 100+920 29.47 0.00
1883 101+000 29.47 0.00
1884 101+250 29.47 0.00
1885 101+500 29.47 0.00
1886 101+750 29.47 0.00
SYPHON
1887 102+000 29.47 0.00
1888 102+250 29.47 0.00
1889 102+500 29.47 0.00
1890 102+750 29.47 0.00
1891 102+930 29.47 0.00
1892 103+000 70 29.47 2062.90
S.No Chainage Length Area Total Qty

1893 103+250 250 29.47 7367.50


1894 103+500 250 29.47 7367.50
1895 103+750 250 29.47 7367.50
1896 104+000 250 29.47 7367.50
1897 104+250 250 29.47 7367.50
1898 104+500 250 29.47 7367.50
1899 104+750 250 29.47 7367.50
1900 105+000 250 29.47 7367.50
1901 105+250 250 29.47 7367.50
1902 105+500 250 29.47 7367.50
1903 105+750 250 29.47 7367.50
1904 106+000 250 29.47 7367.50
1905 106+250 250 29.47 7367.50
1906 106+500 250 29.47 7367.50
1907 106+750 250 29.47 7367.50
1908 107+000 250 29.47 7367.50
1909 107+250 250 29.47 7367.50
1910 107+500 250 29.47 7367.50
1911 107+750 250 29.47 7367.50
1912 108+000 250 29.47 7367.50
1913 108+250 250 29.47 7367.50
1914 108+500 250 29.47 7367.50
1915 108+750 250 29.47 7367.50
1916 109+000 250 29.47 7367.50
1917 109+250 250 29.47 7367.50
1918 109+500 250 29.47 7367.50
1919 109+750 250 29.47 7367.50
1920 110+000 250 29.47 7367.50
1921 110+030 0.00
AQUEDUCT
1922 110+227 0.00
1923 110+250 23 23.24 534.52
1924 110+500 250 23.24 5810.00
1925 110+750 250 23.24 5810.00
1926 111+000 250 23.24 5810.00
1927 111+250 250 23.24 5810.00
1928 111+500 250 23.24 5810.00
1929 111+750 250 23.24 5810.00
1930 112+000 250 23.24 5810.00
1931 112+250 250 23.24 5810.00
1932 112+500 250 23.24 5810.00
1933 112+750 250 23.24 5810.00
1934 113+000 250 23.24 5810.00
1935 113+250 250 23.24 5810.00
1936 113+500 250 23.24 5810.00
1937 113+750 250 23.24 5810.00
1938 114+000 250 23.24 5810.00
1939 114+250 250 23.24 5810.00
114+349 AQUEDUCT 0.00
1940
1941 114+500 151 3.98 600.98
S.No Chainage Length Area Total Qty

1942 114+750 250 27.62 6905.00


1943 115+000 250 16.43 4107.50
1944 115+069 0.00
AQUEDUCT
1945 115+146 0.00
1946 115+250 104 26.11 2715.44
1947 115+500 250 26.80 6700.00
1948 115+750 250 3.76 940.00
1949 116+000 250 73.09 18272.50
1950 116+250 250 36.41 9102.50
1951 116+500 250 52.46 13115.00
1952 116+750 250 3.72 930.00
1953 117+000 250 5.00 1250.00
1954 117+250 250 17.16 4290.00
1955 117+500 250 4.26 1065.00
1956 117+750 250 4.26 1065.00
1957 118+000 250 41.64 10410.00
1958 118+250 250 78.02 19505.00
1959 118+500 250 4.32 1080.00
1960 118+750 250 4.26 1065.00
1961 119+000 250 9.53 2382.50
1962 119+250 250 30.81 7702.50
1963 119+500 250 38.87 9717.50
1964 119+750 250 25.01 6252.50
1965 120+000 250 58.43 14607.50
1966 120+136 0.00
AQUEDUCT
1967 120+194 0.00
1968 120+250 56 6.40 358.40
1969 120+500 250 5.15 1287.50
1970 120+750 250 3.71 927.50
1971 121+000 250 23.83 5957.50
1972 121+250 250 4.53 1132.50
1973 121+500 250 12.19 3047.50
1974 121+750 250 7.46 1865.00
1975 122+000 250 50.30 12575.00
1976 122+250 250 7.18 1795.00
1977 122+500 250 4.53 1132.50
1978 122+750 250 6.09 1522.50
1979 123+000 250 4.27 1067.50
1980 123+250 250 17.41 4352.50
1981 123+500 250 9.06 2265.00
1982 123+750 250 19.73 4932.50
1983 124+000 250 27.08 6770.00
1984 124+250 250 13.42 3355.00
1985 124+500 250 4.27 1067.50
1986 124+750 250 3.72 930.00
1987 125+000 250 5.01 1252.50
1988 125+250 250 3.76 940.00
1989 125+500 250 40.14 10035.00
1990 125+750 250 61.83 15457.50
S.No Chainage Length Area Total Qty

1991 126+000 250 76.09 19022.50


1992 126+250 250 10.81 2702.50
1993 126+500 250 7.29 1822.50
1994 126+750 250 48.34 12085.00
1995 127+000 250 21.83 5457.50
1996 127+250 250 32.62 8155.00
1997 127+500 250 59.96 14990.00
1998 127+750 250 28.22 7055.00
1999 128+000 250 3.72 930.00
2000 128+250 250 73.23 18307.50
2001 128+500 250 3.71 927.50
2002 128+750 250 3.68 920.00
2003 129+000 250 3.68 920.00
2004 129+250 250 3.68 920.00
2005 129+500 250 46.51 11627.50
2006 129+750 250 77.34 19335.00
2007 129+808 0.00
AQUEDUCT
2008 129+904 0.00
2009 130+000 96 3.68 353.28
2010 130+250 250 3.67 917.50
2011 130+500 250 3.68 920.00
2012 130+750 250 11.25 2812.50
2013 131+000 250 11.25 2812.50
2014 131+250 250 11.25 2812.50
2015 131+500 250 11.25 2812.50
2016 131+750 250 11.25 2812.50
2017 132+000 250 11.25 2812.50
2018 132+250 250 11.25 2812.50
2019 132+500 250 11.25 2812.50
2020 132+750 250 11.25 2812.50
2021 133+000 250 11.25 2812.50
2022 133+250 250 11.25 2812.50
2023 133+500 250 11.25 2812.50
2024 133+750 250 11.25 2812.50
2025 134+000 250 8.01 2002.50
2026 134+250 250 3.68 920.00
2027 134+500 250 3.68 920.00
2028 134+750 250 4.23 1057.50
2029 135+000 250 3.63 907.50
2030 135+250 250 39.09 9772.50
2031 135+500 250 3.56 890.00
2032 135+750 250 17.99 4497.50
2033 136+000 250 3.68 920.00
2034 136+250 250 3.95 987.50
2035 136+500 250 3.49 872.50
2036 136+732 0.00
2037 136+750 0.00
AQUEDUCT
2038 137+000 0.00
2039 137+250 0.00
S.No Chainage Length Area Total Qty

2040 137+500 250 3.90 975.00


2041 137+750 250 3.90 975.00
2042 138+000 250 4.19 1047.50
2043 138+250 250 4.66 1165.00
2044 138+500 250 3.88 970.00
2045 138+750 250 3.55 887.50
2046 139+000 250 3.90 975.00
2047 139+250 250 4.18 1045.00
2048 139+500 250 4.19 1047.50
2049 139+750 250 4.19 1047.50
2050 140+000 250 4.19 1047.50
2051 140+250 250 6.91 1727.50
2052 140+370 0.00
AQUEDUCT
2053 140+490 0.00
2054 140+500 10 0.00
2055 140+750 250 0.00
2056 140+914 0.00
2057 141+000 0.00
2058 141+250 0.00
AQUEDUCT
2059 141+500 0.00
2060 141+750 0.00
2061 141+905 0.00
2062 142+000 95 18.86 1791.70
2063 142+250 250 3.88 970.00
2064 142+500 250 3.88 970.00
2065 142+727 0.00
2066 142+750 0.00
2067 143+000 0.00
AQUEDUCT
2068 143+250 0.00
2069 143+500 0.00
2070 143+729 0.00
2071 143+750 21 4.18 87.78
2072 144+000 250 12.29 3072.50
2073 144+250 250 46.24 11560.00
2074 144+500 250 63.17 15792.50
2075 144+750 250 5.01 1252.50
2076 145+000 250 4.09 1022.50
2077 145+250 250 42.19 10547.50
2078 145+500 250 3.54 885.00
2079 145+750 250 5.09 1272.50
2080 146+000 250 10.06 2515.00
2081 146+250 250 20.66 5165.00
2082 146+500 250 2.61 652.50
2083 146+750 250 15.00 3750.00
2084 147+000 250 15.60 3900.00
2085 147+250 250 12.96 3240.00
2086 147+500 250 3.78 945.00
2087 147+515 15 0.00
S.No Chainage Length Area Total Qty

147+581 AQUEDUCT 0.00


2088
2089 147+750 169 5.11 863.59
2090 148+000 250 3.65 912.50
2091 148+097 0.00
AQUEDUCT
2092 148+161 0.00
2093 148+250 89 4.09 364.01
2094 148+500 250 38.92 9730.00
2095 148+750 250 3.54 885.00
2096 149+000 250 3.54 885.00
2097 149+250 250 11.04 2760.00
2098 149+500 250 34.98 8745.00
2099 149+750 250 3.78 945.00
2100 150+000 250 38.56 9640.00
2101 150+250 250 7.36 1840.00
2102 150+500 250 14.36 3590.00
2103 150+750 250 3.50 875.00
2104 151+000 250 7.51 1877.50
2105 151+250 250 3.76 940.00
2106 151+500 250 17.49 4372.50
2107 151+750 250 6.21 1552.50
2108 151+796 0.00
AQUEDUCT
2109 151+921 0.00
2110 152+000 79 11.32 894.28
2111 152+250 250 3.50 875.00
2112 152+500 250 5.60 1400.00
2113 152+750 250 80.00 20000.00
2114 153+000 250 22.29 5572.50
2115 153+250 250 14.05 3512.50
2116 153+500 250 44.07 11017.50
2117 153+559 0.00
AQUEDUCT
2118 153+650 0.00
2119 153+750 100 3.50 350.00
2120 154+000 250 3.75 937.50
2121 154+250 250 15.65 3912.50
2122 154+500 250 14.29 3572.50
2123 154+750 250 4.63 1157.50
2124 155+000 250 4.84 1210.00
2125 155+250 250 14.96 3740.00
2126 155+500 250 81.29 20322.50
2127 155+750 250 8.08 2020.00
2128 156+000 250 11.82 2955.00
2129 156+250 250 46.44 11610.00
2130 156+500 250 32.13 8032.50
2131 156+750 250 3.69 922.50
2132 157+000 250 4.07 1017.50
2133 157+250 250 8.82 2205.00
2134 157+500 250 4.32 1080.00
2135 157+750 250 6.22 1555.00
S.No Chainage Length Area Total Qty

2136 158+000 250 3.69 922.50


2137 158+250 250 8.86 2215.00
2138 158+500 250 26.72 6680.00
2139 158+683 0.00
2140 158+750 0.00
AQUEDUCT
2141 159+000 0.00
2142 159+177 0.00
2143 159+250 73 128.44 9376.12
2144 159+500 250 31.10 7775.00
2145 159+750 250 4.04 1010.00
2146 160+000 250 8.16 2040.00
2147 160+250 250 3.69 922.50
2148 160+500 250 3.69 922.50
2149 160+750 250 3.44 860.00
2150 161+000 250 8.16 2040.00
2151 161+089 0.00
2152 161+250 AQUEDUCT 0.00
2153 161+389 0.00
2154 161+500 111 54.09 6003.99
2155 161+750 250 34.37 8592.50
2156 162+000 250 44.27 11067.50
2157 162+250 250 3.61 902.50
2158 162+500 250 3.61 902.50
2159 162+750 250 3.95 987.50
2160 163+000 250 3.50 875.00
2161 163+250 250 3.61 902.50
2162 163+500 250 3.61 902.50
2163 163+586 0.00
AQUEDUCT
2164 163+681 0.00
2165 163+750 69 3.61 249.09
2166 164+000 250 77.61 19402.50
2167 164+250 250 38.98 9745.00
2168 164+500 250 29.87 7467.50
2169 164+750 250 14.88 3720.00
2170 165+000 250 64.79 16197.50
2171 165+250 250 3.37 842.50
2172 165+500 250 3.37 842.50
2173 165+750 250 3.37 842.50
2174 166+000 250 33.59 8397.50
2175 166+250 250 11.70 2925.00
2176 166+500 250 11.70 2925.00
2177 166+750 250 3.61 902.50
2178 166+770 0.00
2179 167+000 0.00
2180 167+250 AQUEDUCT 0.00
2181 167+500 0.00
2182 167+689 0.00
2183 167+750 61 3.92 239.12
2184 168+000 250 40.67 10167.50
S.No Chainage Length Area Total Qty

2185 168+250 250 34.36 8590.00


2186 168+500 250 3.92 980.00
2187 168+750 250 34.42 8605.00
2188 169+000 250 38.87 9717.50
2189 169+250 250 15.04 3760.00
2190 169+500 250 3.61 902.50
2191 169+750 250 3.37 842.50
2192 170+000 250 3.92 980.00
2193 170+250 250 48.34 12085.00
2194 170+500 250 10.54 2635.00
2195 170+750 250 7.02 1755.00
2196 170+890 140 0.00
171+000 AQUEDUCT 0.00
2197
2198 171+250 250 43.64 10910.00
2199 171+500 250 3.61 902.50
2200 171+750 250 62.86 15715.00
2201 172+000 250 3.37 842.50
2202 172+250 250 41.22 10305.00
2203 172+500 250 31.75 7937.50
2204 172+750 250 22.33 5582.50
2205 172+991 0.00
2206 173+000 0.00
2207 173+250 0.00
2208 173+500 AQUEDUCT 0.00
2209 173+750 0.00
2210 174+000 0.00
2211 174+039 0.00
2212 174+250 211 61.80 13039.80
2213 174+500 250 45.28 11320.00
2214 174+750 250 6.74 1685.00
2215 175+000 250 33.90 8475.00
2216 175+250 250 44.82 11205.00
2217 175+500 250 58.83 14707.50
2218 175+750 250 80.64 20160.00
2219 176+000 250 104.39 26097.50
2220 176+250 250 3.51 877.50
2221 176+500 250 19.91 4977.50
2222 176+750 250 11.36 2840.00
2223 177+000 250 19.91 4977.50
2224 177+250 250 15.81 3952.50
2225 177+500 250 3.51 877.50
2226 177+750 250 47.72 11930.00
2227 178+000 250 3.26 815.00
2228 178+154 0.00
2229 178+250 0.00
AQUEDUCT
2230 178+500 0.00
2231 178+591 0.00
2232 178+750 159 3.26 518.34
S.No Chainage Length Area Total Qty

2233 179+000 250 42.54 10635.00


2234 179+250 250 20.89 5222.50
2235 179+500 250 3.31 827.50
2236 179+750 250 3.17 792.50
2237 180+000 250 4.84 1210.00
2238 180+250 250 66.07 16517.50
2239 180+500 250 56.23 14057.50
2240 180+750 250 3.02 755.00
2241 181+000 250 3.07 767.50
2242 181+250 250 6.22 1555.00
2243 181+500 250 22.35 5587.50
2244 181+750 250 3.29 822.50
2245 182+000 250 39.14 9785.00
2246 182+250 250 3.62 905.00
2247 182+500 250 12.01 3002.50
2248 182+750 250 53.11 13277.50
2249 183+000 250 3.22 805.00
2250 183+250 250 16.97 4242.50
2251 183+500 250 26.05 6512.50
2252 183+750 250 17.93 4482.50
2253 184+000 250 2.66 665.00
2254 184+250 250 3.22 805.00
2255 184+500 250 17.14 4285.00
2256 184+745 245 17.14 4199.30
2257 184+750 AQUEDUCT 0.00
2258 184+907 157 16.30 2559.10
2259 185+000 93 35.81 3330.33
2260 185+250 250 0.00
2261 185+522 272 0.00
2262 MINOR CANAL 0.00
2263 0+000 3.26 0.00
2264 0+250 250 3.26 815.00
2265 0+500 250 3.26 815.00
2266 0+750 250 3.26 815.00
2267 1+000 250 3.17 792.50
2268 1+250 250 4.84 1210.00
2269 1+500 250 4.84 1210.00
2270 1+750 250 4.84 1210.00
2271 2+000 250 4.84 1210.00
2272 2+250 250 3.07 767.50
2273 2+500 250 3.07 767.50
2274 2+750 250 3.07 767.50
2275 3+000 250 3.07 767.50
2276 3+250 250 6.00 1500.00
2277 3+500 250 6.33 1582.50
2278 3+750 250 6.33 1582.50
2279 4+000 250 6.33 1582.50
2280 4+250 250 6.33 1582.50
2281 4+500 250 6.33 1582.50
S.No Chainage Length Area Total Qty

2282 4+750 250 6.33 1582.50


2283 5+000 250 6.33 1582.50
2284 5+250 250 6.33 1582.50
2285 5+500 250 6.33 1582.50
2286 5+750 250 6.33 1582.50
2287 6+000 250 6.33 1582.50
2288 6+250 250 6.33 1582.50
2289 6+500 250 6.33 1582.50
2290 6+750 250 6.33 1582.50
2291 7+000 250 6.33 1582.50
2292 7+250 250 6.33 1582.50
2293 7+500 250 6.33 1582.50
2294 7+750 250 6.33 1582.50
2295 8+000 250 6.33 1582.50
2296 8+250 250 6.33 1582.50
2297 8+500 250 6.33 1582.50
2298 8+750 250 6.33 1582.50
2299 9+000 250 6.33 1582.50
2300 9+250 250 6.33 1582.50
2301 9+500 250 6.33 1582.50
2302 9+750 250 6.33 1582.50
2303 10+000 250 6.33 1582.50
2304 10+250 250 29.87 7467.50
2305 10+500 250 14.88 3720.00
2306 10+750 250 64.79 16197.50
2307 11+000 250 3.37 842.50
2308 11+250 250 3.37 842.50
2309 11+500 250 3.37 842.50
2310 11+750 250 5.00 1250.00
2311 12+000 250 5.00 1250.00
2312 12+250 250 5.00 1250.00
2313 12+500 250 5.00 1250.00
2314 12+750 250 5.00 1250.00
2315 13+000 250 5.00 1250.00
2316 13+250 250 5.00 1250.00
2317 13+500 250 5.00 1250.00
2318 13+750 250 5.00 1250.00
2319 14+000 250 5.00 1250.00
2320 14+250 250 5.00 1250.00
2321 14+500 250 5.00 1250.00
2322 14+750 250 7.51 1877.50
2323 15+000 250 7.51 1877.50
2324 15+250 250 7.51 1877.50
2325 15+500 250 7.51 1877.50
2326 15+750 250 7.51 1877.50
2327 16+000 250 7.51 1877.50
2328 16+250 250 7.51 1877.50
2329 16+500 250 7.51 1877.50
2330 16+750 250 5.01 1252.50
S.No Chainage Length Area Total Qty

2331 17+000 250 5.01 1252.50


2332 17+250 250 5.01 1252.50
2333 17+500 250 5.01 1252.50
2334 17+750 250 5.01 1252.50
2335 18+000 250 5.01 1252.50
2336 18+250 250 5.01 1252.50
2337 18+500 250 5.01 1252.50
2338 18+750 250 5.01 1252.50
2339 19+000 250 5.01 1252.50
2340 19+250 250 5.01 1252.50
2341 19+500 250 3.78 945.00
2342 19+750 250 3.92 980.00
2343 20+000 250 3.92 980.00
2344 20+250 250 3.92 980.00
2345 20+500 250 3.92 980.00
2346 20+750 250 3.92 980.00
2347 21+000 250 3.92 980.00
2348 21+250 250 15.04 3760.00
2349 21+500 250 3.61 902.50
2350 21+750 250 3.37 842.50
2351 22+000 250 3.92 980.00
2352 22+250 250 48.34 12085.00
2353 22+500 250 5.09 1272.50
2354 22+976 476 2.00 952.00
Total Qty in Cft 4118343.53
Qty in CM 116600.892673273
IRRIGATION SYSTEM/
SIRAN CANAL PR
Design of Main C
Offtakes Balance
Reach
Off-take Discharg
Wise
Descripti GCA CCA Discharg e in
Sr. No Location RDs Discharg Reach
ons e Parent
e
Channel
ft Acre Acre ft3/Sec ft3/Sec ft3/Sec
85.000 ft
Siran Canal
10 Cfs Water Share For Existing Canal 10.000 75.000
1 Outlet-1 L 07+100 253.000 191.256 1.195 1.195 73.8050+000 to 07+100
2 Outlet-2 L 20+000 534.000 403.679 2.523 2.523 71.282
07+100 to 20+000
3 Outlet-3 L 24+235 528.000 399.143 2.495 2.495 68.787
20+000 to 24+235
4 Outlet-4 L 27+445 520.000 393.096 2.457 2.457 66.330
24+235 to 27+445
27+345 to 28+000
5 Outlet-5 L 30+020 479.000 362.102 2.263 2.263 64.067
28+000 to 30+020
30+020 to 34+000
Outlet-6 L 44+100 509.000 384.780 2.405 2.405 61.662
6 34+000 to 44+100
7 Outlet-7 L 65+200 483.000 365.125 2.282 2.282 59.380
44+100 to 65+200
8 Outlet-8 L 68+835 539.000 407.459 2.547 2.547 56.834
65+200 to 68+835
9 Outlet-9 L 70+315 528.000 399.143 2.495 2.495 54.339
68+835 to 70+315
10 Outlet-10 L 73+050 476.000 359.834 2.249 2.249 52.090
70+315 to 73+050
11 Outlet-11 L 82+700 392.000 296.334 1.852 1.852 50.23873+050 to 82+700
12 Outlet-12 L 87+050 447.000 337.911 2.112 2.112 48.12682+700 to 87+050
13 Minor-1 L 91+265 3078.000 2326.824 14.543 14.543 33.58387+050 to 91+265
14 Outlet-13 L 98+500 500.000 377.977 2.362 2.362 31.22191+265 to 98+500
15 Outlet-14 L 110+000 459.000 346.982 2.169 2.169 29.052
98+500 to 110+000
16 Outlet-15 L 128+150 550.000 415.774 2.599 2.599 26.454
110+000 to 128+150
17 Outlet-16 L 136+600 410.000 309.941 1.937 1.937 24.517
128+150 to 136+600
18 Outlet-17 L 143+750 463.000 350.006 2.188 2.188 22.329
136+600 to 143+750
19 Outlet-18 L 150+200 523.000 395.363 2.471 2.471 19.858
143+750 to 150+200
20 Outlet-19 L 156+300 483.000 365.125 2.282 2.282 17.576
150+200 to 156+300
21 Outlet-20 L 161+400 517.000 390.828 2.443 2.443 15.133
156+300 to 161+400
22 Outlet-21 L 172+600 530.000 400.655 2.504 2.504 12.629
161+400 to 172+600
23 Outlet-22 L 174+400 528.000 399.143 2.495 2.495 10.134
172+600 to 174+400
24 Outlet-23 L 179+150 544.000 411.239 2.570 2.570 7.564
174+400 to 179+150
Offtakes Balance
Reach
Off-take Discharg
Wise
Descripti GCA CCA Discharg e in
Sr. No Location RDs Discharg Reach
ons e Parent
e
Channel
ft Acre Acre ft3/Sec ft3/Sec ft3/Sec
85.000 ft
25 Outlet-24 L 180+650 554.000 418.798 2.617 2.617 4.947
179+150 to180+650
26 Outlet-25 L 182+350 526.000 397.631 2.485 2.485 2.462
180+650 to 182+350
27 Outlet-26 Tail 185+322 521.000 393.852 2.462 2.462 0.000
182+350 to 185+322
15874.00 12000.00
Water
Allowanc
e 6.25000

Design of Mino
Balance
Offtakes Reach
Off-take Discharg
Wise
GCA CCA Discharg e in
Discharg
Sr. No e Parent
Descripti e
Location RDs Channel
ons
Reach
ft Acre Acre ft3/Sec ft3/Sec ft3/Sec

14.543 ft
Minor-1
1 Outlet-1 L 11+300 565.000 427.114 0.000 0.000 14.5430+000 to 11+300
2 Outlet-2 L 14+950 529.000 399.899 0.000 0.000 14.543
11+300 to 14+950

3 Outlet-3 L 17+050 529.000 399.899 0.000 0.000 14.543


14+950 to 17+050
4 Outlet-4 L 18+700 504.000 381.000 0.000 0.000 14.543
17+050 to 18+700
5 Outlet-5 Tail-L 22+976 441.000 333.375 0.000 0.000 14.543
18+700 to 22+976
6 Outlet-6 Tail-R 22+976 510.000 385.536 0.000
3078.00 2326.8
IRRIGATION SYSTEM/ NETWORK
SIRAN CANAL PROJECT
Design of Main Canal
Design of Trapezoidal Channel Side Slope 1:1
Calculate
Wetted Hydraulic
d Manning' Bed Side Bed Flow Velocity
Area 'A' Perimete Radius
Discharg s 'n' Slope 'S' Slope Width 'B' Depth 'Y' 'V'
r 'P' 'R'
e 'Q'

ft3/Sec ft/ft ft ft ft2 ft ft ft/Sec


Siran Canal

85.000 0.018 0.001 1:1 6.750 3.400 23.440 16.367 1.432 3.704
73.805 0.018 0.001 1:1 3.650 3.055 20.484 12.291 1.667 3.603
71.282 0.018 0.001 1:1 3.650 2.970 19.661 12.050 1.632 3.625
68.787 0.018 0.001 1:1 3.650 2.900 18.995 11.852 1.603 3.621
66.330 0.018 0.001 1:1 3.650 2.850 18.525 11.711 1.582 3.581
66.330 0.018 0.001 1:1 3.650 2.850 18.525 11.711 1.582 3.581
64.067 0.018 0.001 1:1 3.650 2.810 18.153 11.598 1.565 3.529
64.067 0.018 0.001 1:1 3.650 2.810 18.153 11.598 1.565 3.529
61.662 0.018 0.001 1:1 3.650 2.780 17.875 11.513 1.553 3.450
59.380 0.018 0.001 1:1 3.650 2.700 17.145 11.287 1.519 3.463
56.834 0.018 0.001 1:1 3.650 2.615 16.383 11.046 1.483 3.469
54.339 0.018 0.001 1:1 3.700 2.530 15.762 10.856 1.452 3.447
52.090 0.018 0.001 1:1 3.700 2.525 15.718 10.842 1.450 3.314
50.238 0.018 0.001 1:1 3.700 2.460 15.154 10.658 1.422 3.315
48.126 0.018 0.001 1:1 3.700 2.420 14.810 10.545 1.405 3.249
33.583 0.018 0.001 1:1 2.600 2.285 11.162 9.063 1.232 3.009
31.221 0.018 0.001 1:1 2.700 2.170 10.568 8.838 1.196 2.954
29.052 0.018 0.001 1:1 2.850 2.050 10.045 8.648 1.162 2.892
26.454 0.018 0.001 1:1 2.700 2.010 9.467 8.385 1.129 2.794
24.517 0.018 0.001 1:1 2.400 2.010 8.864 8.085 1.096 2.766
22.329 0.018 0.001 1:1 2.100 2.010 8.261 7.785 1.061 2.703
19.858 0.018 0.001 1:1 1.700 2.010 7.457 7.385 1.010 2.663
17.576 0.018 0.001 1:1 1.400 2.010 6.854 7.085 0.967 2.564
15.133 0.018 0.001 1:1 1.100 2.010 6.251 6.785 0.921 2.421
12.629 0.018 0.001 1:1 1.000 2.010 6.050 6.685 0.905 2.087
10.134 0.018 0.001 1:1 1.000 2.010 6.050 6.685 0.905 1.675
Design of Parabolic Section
Calculate
Wetted Hydraulic
d Manning' Bed Side Top Flow Velocity
Area 'A' Perimete Radius
Discharg s 'n' Slope 'S' Slope Width 'T' Depth 'Y' 'V'
r 'P' 'R'
e 'Q'

ft3/Sec ft/ft ft ft ft2 ft ft ft/Sec


7.564 0.012 0.001 Varies 2.900 1.500 2.90 4.969 0.584 2.608
4.947 0.012 0.001 Varies 2.500 1.400 2.33 4.591 0.508 2.120
2.462 0.012 0.001 Varies 2.500 1.000 1.67 3.567 0.467 1.477

Design of Minor-1

Design of Trapezoidal Section

Calculate
Wetted Hydraulic
d Manning' Bed Side Top Flow Velocity
Area 'A' Perimete Radius
Discharg s 'n' Slope 'S' Slope Width 'T' Depth 'Y' 'V'
r 'P' 'R'
e 'Q'
ft3/Sec ft/ft ft ft ft2 ft ft ft/Sec
Minor-1
14.543 0.018 0.001 1:1 1.000 2.010 6.050 6.685 0.905 2.404
14.543 0.018 0.001 1:1 1.000 2.010 6.050 6.685 0.905 2.404
Design of Parabolic Section
14.543 0.012 0.001 Varies 3.200 1.600 3.41 5.333 0.640 4.261
14.543 0.012 0.001 Varies 2.700 1.520 2.74 4.982 0.549 5.315
14.543 0.012 0.001 Varies 2.300 1.458 2.24 4.765 0.469 6.505
Designed
Discharg
e 'Q'

ft3/Sec

77.958
75.372
71.330
68.094
65.834
65.834
64.056
64.056
62.740
59.306
55.773
52.903
52.705
50.156
48.622
33.573
31.165
29.054
26.870
24.671
22.497
19.647
17.550
15.493
14.818
14.818

Designed
Discharg
e 'Q'

ft3/Sec
7.952
5.835
3.941

Designed
Discharg
e 'Q'

ft3/Sec

14.818
14.818

9.953
7.204
5.300
Subgrade Preparation 4'' Thick Cement Concrete Lining

Cross
Length
Area Bed Slope Sectional Slope Cross
Reach after Bed
Total Bed Reach including Length Area Area Length Slope Sectional Volume Volume
deductio Bed Thicknes FSD+FB
width Length 1' top Both Slope (bed) Both Thicknes Area (In bed) (on
n for Width (ft) s (ft)
ft ft lining Sides (ft²) including Sides s (ft) (slope) M³ slope) M³
Structure (ft)
(ft²) ft. 1' top ft. (ft²)
s ft.
lining (ft²)

92+538 to 98+500 3.594 5962 4796 26828.82 12.572 60297.03 2.600 0.33 1.736 3.785 11.639 0.33 3.841 8324.897 18420.78
98+500 to 110+000 3.694 11500 9222 52510.07 12.247 112942.7 2.700 0.33 1.769 3.67 11.314 0.33 3.734 16311.87 34430.56
110+000 to 128+150 3.844 18150 17119 100043.4 11.908 203847.5 2.850 0.33 1.818 3.55 10.974 0.33 3.622 31127.48 61996.77
128+150 to 136+600 3.694 8450 7424 42272.26 11.795 87562.67 2.700 0.33 1.769 3.51 10.861 0.33 3.584 13131.57 26608.97
136+600 to 143+750 3.394 7150 4519 24375.49 11.795 53299.53 2.400 0.33 1.670 3.51 10.861 0.33 3.584 7545.826 16196.92
143+750 to 150+200 3.094 6450 6009 30609.85 11.795 70873.4 2.100 0.33 1.571 3.51 10.861 0.33 3.584 9438.937 21537.35
150+200 to 156+300 2.694 6100 5759 27032.75 11.795 67924.76 1.700 0.33 1.439 3.51 10.861 0.33 3.584 8286.049 20641.31
156+300 to 161+400 2.394 5100 4256 18700.86 11.795 50197.57 1.400 0.33 1.340 3.51 10.861 0.33 3.584 5702.189 15254.28
161+400 to 172+600 2.094 11200 9926 40637.04 11.795 117072.6 1.100 0.33 1.241 3.51 10.861 0.33 3.584 12316.18 35576.6
172+600 to 174+400 1.994 1800 652 2604.088 11.795 7690.041 1.000 0.33 1.208 3.51 10.861 0.33 3.584 787.4856 2336.887
174+400 to 179+150 1.994 4750 3695 14757.83 11.795 43580.83 1.000 0.33 1.208 3.51 10.861 0.33 3.584 4462.821 13243.56
Minor-1
0+000 to 11+300 1.994 11300 11300 45132.2 11.795 133278.3 1.000 0.33 1.208 3.51 10.861 0.33 3.584 13648.14 40501.27
11+300 to 14+950 1.994 3650 3650 14578.1 11.795 43050.08 1.000 0.33 1.208 3.51 10.861 0.33 3.584 4408.47 13082.27
440082.8 1051617 135491.9 319827.5
40899.89 97733.93 3836.125 9055.139
sq. m sq. m cub m cub m
17-01-a 17-01-b 17-10-a-0117-10-b-01
2'' Thick Stabilized Layer of Plain Cement Concrete including placing,
Re fill concrete (1:6:18)
Cement Sand compacting,finishing & curing (Ratio 1:2:4)

Cross
Cross
Reach Sectional
Sectional Volume
Thicknes Area (bed) No. of Expansio Total
Area Length (Area Length Area volume
s (ft.) (ft²) inluding profiles n joints length
(slope) (ft²) 0.75*.5*L)
1' top lining X
x Length
Length

92+538 to 98+500 0.167 26828.824 58085.914 480.6 16.899 3045.618 96 16.899 1620.95 3.575 4 19184
98+500 to 110+000 0.167 52510.068 108691.007 923.2 16.674 5772.438 184 16.674 3075.299 3.46 3 27666
110+000 to 128+150 0.167 100043.436 195955.108 1712.9 16.484 10588.482 342 16.484 5643.894 3.34 3 51357
128+150 to 136+600 0.167 42272.256 84139.960 743.4 16.221 4522.054 148 16.221 2408.518 3.3 3 22272
136+600 to 143+750 0.167 24375.486 51216.120 452.9 15.921 2704.010 90 15.921 1438.954 3.3 3 13557
143+750 to 150+200 0.167 30609.846 68103.047 601.9 15.621 3525.891 120 15.621 1877.351 3.3 3 18027
150+200 to 156+300 0.167 27032.746 65269.670 576.9 15.221 3292.908 115 15.221 1753.173 3.3 3 17277
156+300 to 161+400 0.167 18700.864 48235.408 426.6 14.921 2387.013 85 14.921 1270.089 3.3 3 12768
161+400 to 172+600 0.167 40637.044 112496.395 993.6 14.621 5447.844 199 14.621 2902.593 3.3 3 29778
172+600 to 174+400 0.167 2604.088 7389.447 66.2 14.521 360.488 13 14.521 189.3559 3.3 3 1956
174+400 to 179+150 0.167 14757.83 41877.310 370.5 14.521 2017.534 74 14.521 1073.114 3.3 3 11085
Minor-1 0
0+000 to 11+300 0.167 45132.2 128068.635 1131 14.521 6158.787 226 14.521 3281.782 3.3 3 33900
11+300 to 14+950 0.167 14578.1 41367.302 366 14.521 1993.029 73 14.521 1060.045 3.3 3 10950
40937.933767 94036.7742 51816.096 27595.12 269777
134974.708 1467.04688 8410.581 7638.08
sq. m cub m M
17-10-b-01 17-02 06-05-f 06-21 06-03-e
Quantities parabola

Length after
Reach Discharge Length 3" Sand bed
Deductions
a = FSD+FB b = top width L Thickness Volume
179+150 to180+650 7.564 1500 1500 3 2.9 7.150 0.250 2681.20067463
180+650 to 182+350 4.947 1700 1670 2.9 2.5 6.686 0.250 2791.34978348
182+350 to 185+322 2.462 2972 2810 2.5 2.5 5.981 0.250 4201.87963922
Minor-1
14+950 to 17+050 19.858 2100 2100 3.1 3.2 7.558 0.250 3968.04443859
17+050 to 18+700 17.576 1650 1650 3.02 2.7 7.038 0.250 2903.13576011
18+700 to 22+976 15.133 4276 4276 2.958 2.3 6.661 0.250 7120.65639838
14006 23666.2666944
4268.820 670.053
cub. m
m.
07-30
17-11-a
GOVERNMENT OF KHYBER PAKHTUNKHWA
IRRAGATION DEPARTMENT
CONSTRUCTION OF SIRAN RIGHT BANK CANAL DISTRICT MANSEHRA
Measurement Sheet :-
Erecting & removing formwork to concrete in any shape /position (Vertical)
BOQ Item Code
SEWEARG NALLA 0+500 TO 7+000
06-39-b
S-no Qty
RD DESCRIPTION Nos. Sides Hight(ft) Length Remarks
(Sq.ft)
1 01+310 01+595 NALLA BED 1.00 1.00 0.50 285.00 142.50
2 01+310 01+595 NALLA WALL 1.00 2.00 2.50 285.00 1425.00
1+110 & 1+593 PIPE CULVERT 2.00 2.00 2.90 16.00 185.60
1+110 & 1+593 MAIN HOLE BED 2.00 4.00 0.50 3.84 15.36
MAIN HOLE WALL 2.00 2.00 3.00 2.50
1+110 & 1+593 30.00
INNER SITE
MAIN HOLE WALL 2.00 2.00 3.00 3.84
1+110 & 1+593 46.08
3 OUTER SITE
01+845 & 4+963 PIPE CULVERT 2.00 2.00 2.90 16.00 185.60
4 03+525 PIPE CULVERT 1.00 2.00 2.90 80.00 464.00
5 03+525 NALLA BED 1.00 2.00 0.50 60.00 60.00
6 03+525 NALLA WALL 2.00 2.00 1.50 60.00 360.00
29 03+860 04+963 NALLA BED 1.00 1.00 0.50 1103.00 551.50
30 03+860 04+963 NALLA WALL 1.00 2.00 2.50 1103.00 5515.00

TOTAL QTY in Sq.ft: 8980.64


TOTAL QTY in Sq.m: 834.63 Paid in Irrigation canal

GOVERNMENT OF KHYBER PAKHTUNKHWA


IRRAGATION DEPARTMENT
CONSTRUCTION OF SIRAN RIGHT BANK CANAL DISTRICT MANSEHRA
Measurement Sheet :-
Plain Cement Concrete including placing, compacting, finishing & curing (Ratio 1:4:8)
SEWERAGE NALLA 0+500 TO 7+000 BOQ Item Code 06-05-i
Qty
S-no RD DESCRIPTION Sides Width (ft) Hight (ft) Length (FT)
1 00+600 00+850 NALLA 1.00 1.00 0.25 250.00 62.50
2 00+850 01+110 NALLA 1.00 1.50 0.25 260.00 97.50
3 01+110 01+310 NALLA 1.00 1.00 0.25 200.00 50.00
4 01+310 01+595 NALLA 1.00 2.17 0.25 285.00 154.61
6 1+110 & 1+593 PIPE CULVERT (area) 2.00 3.40 0.25 16.25 27.63
7 1+110 & 1+593 MAIN HOLE BED 2.00 3.37 0.25 3.37 5.68
10 01+845&4+963 PIPE CULVERT (area) 2.00 3.40 0.25 16.50 28.05
11 03+525 PIPE CULVERT (area) 1.00 3.40 0.25 80.00 68.00
12 03+525 NALLA BED 1.00 3.35 0.25 60.00 50.18
14 03+860 04+450 NALLA 1.00 1.67 0.25 590.00 246.33
15 04+450 04+963 NALLA 1.00 2.19 0.25 513.00 280.87
TOTAL QTY in Cu.ft: 1071.33
TOTAL QTY in Cu.m: 30.33 Paid in Irrigation canal

Sructural Excavation
Measurement Sheet :- Structural Excavation in Common Material
00+600 to 7+00 SEWERAGE NALLA
Qty
S-no RD DESCRIPTION Sides Width (ft) Hight (ft) Length (FT) Remarks
1 00+600 00+850 NALLA 1.00 1.00 3.00 250.00 750.00
2 00+850 01+110 NALLA 1.00 1.50 3.00 260.00 1170.00
3 01+110 01+310 NALLA 1.00 1.00 3.00 200.00 600.00
4 01+310 01+595 NALLA 1.00 3.17 3.00 285.00 2710.35
6 1+110 & 1+593 PIPE CULVERT (area) 2.00 4.90 2.90 16.00 156.80
7 1+110 & 1+593 MAIN HOLE BED 2.00 5.17 3.00 5.17 160.37
10 01+845&4+963 PIPE CULVERT (area) 2.00 4.90 2.90 16.00 92.80
11 03+525 PIPE CULVERT (area) 1.00 4.90 2.90 80.00 392.00
12 03+525 NALLA BED 1.00 4.84 3.00 60.00 871.20
14 03+860 04+450 NALLA BED 1.00 2.67 3.00 590.00 4725.90
15 04+450 04+963 NALLA BED 1.00 3.19 3.00 513.00 4909.41
TOTAL QTY in Cu.ft: 16538.83
TOTAL QTY in Cu.m: 468.26 Paid in Drainage culvert
IRRAGATION DEPARTMENT
CONSTRUCTION OF SIRAN RIGHT BANK CANAL DISTRICT MANSEHRA
Measurement Sheet :-
Plain Cement Concrete including placing, compacting, finishing & curing (Ratio 1:3:6)
SEWERAG NALLA 1:3:6 BOQ Item Code (06-05-h)
00+500 TO 07+000
Qty
S-no RD DESCRIPTION Sides Width (ft) Hight (ft) Length (FT) Remarks
1 00+600 00+850 NALLA BED 1.00 1.00 0.50 250.00 125.00
2 00+850 01+110 NALLA BED 1.00 1.50 0.50 260.00 195.00
3 01+110 01+310 NALLA BED 1.00 1.00 0.50 200.00 100.00
4 01+310 01+595 NALLA BED 1.00 2.17 0.50 285.00 309.23
5 01+310 01+595 NALLA WALL 1.00 0.67 2.50 285.00 477.38
6 1+110 & 1+593 PIPE CULVERT (area) 2.00 5.57 16.00 178.24
7 1+110 & 1+593 MAIN HOLE BED 2.00 3.17 0.50 3.17 10.05
MAIN HOLE WALL INNER
8 1+110 & 1+593 SITE 4.00 0.67 3.00 3.17 25.49
MAIN HOLE WALL
9 1+110 & 1+593 OUTER SITE 4.00 0.67 3.00 0.50 4.02
10 01+845&4+963 PIPE CULVERT (area) 2.00 5.57 16.00 178.24
11 03+525 PIPE CULVERT (area) 1.00 5.57 80.00 445.60
12 03+525 NALLA BED 1.00 2.84 0.50 60.00 85.20
13 03+525 NALLA WALL 1.00 0.67 1.50 60.00 60.30
14 03+860 04+450 NALLA BED 1.00 1.67 0.50 590.00 492.65
15 04+450 04+963 NALLA BED 1.00 2.19 0.50 513.00 561.74
16 03+860 04+963 NALLA WALL 1.00 0.67 2.50 1103.00 1847.53
TOTAL QTY in Cu.ft: 5095.65
TOTAL QTY in Cu.m: 144.27 Paid in Irrigation canal

113 03-60-c Structural backfill using Common Material available at site


60% concrete 86.56 Paid in Drainage culvert
RCC in raft foundation slab, base slab of column & ret.
10.00 CuM
Construction of Siran Right Bank Canal
District Mansehra
Canal Stone Pitching
1 Formation, dressing and preparing sub-grade In bed

Width Qty
R.D Length (ft)
(ft) (sft)

26150-26400 250 1.5 375


27300-27350 50 1.5 75
28475-28650 175 1.5 262.5
31500-31650 150 1.5 225
34350-34600 250 1.5 375
35575-35935 360 1.5 540
39500-39725 225 1.5 337.5
42750-42950 200 1.5 300
43500-43700 200 1.5 300
48975-49240 265 1.5 397.5
53950-54100 150 1.5 225
54200-54350 150 1.5 225
69675-69895 220 1.5 330
73050-73250 200 1.5 300
77865-78000 135 1.5 202.5
89035-89250 215 1.5 322.5
90250-90450 200 1.5 300
94500-94750 250 1.5 375
95185-95250 65 1.5 97.5
98550-98644 94 1.5 141
110750-110905 155 1.5 232.5
123423-123487 64 1.5 96
124688-124750 62 1.5 93
128250-128352 102 1.5 153
130031-130450 419 1.5 628.5
133322-133438 116 1.5 174
135354-135422 68 1.5 102
135750-135860 110 1.5 165
139870-139928 58 1.5 87
150389-150405 16 1.5 24
150520-150700 180 1.5 270
151500-151573 73 1.5 109.5
161403-161500 97 1.5 145.5
177856-178000 144 1.5 216
Total length 5468 8202 sq. ft
OR 34.884 Sq.M
2 Formation, dressing and preparing sub-grade On slope

Width Qty
Length (ft)
(ft) (sft)

5468 20 109360

10173.023 Sq.M

3 Providing and Laying stone pitching for top layer only :


On slope
Width Thickness (ft.) Qty
Length (ft)
(ft) (cft)

5468 20 1 109360
cub. Ft.
3096.263 Cub.M

4 Plain Cement Concrete including placing,


compacting,finishing & curing (Ratio 1:3:6)
Width Thickness (ft.) Nos. Qty
Length (ft)
(ft) (cft)
Vertical profiles 1 547.8
20 0.75 8217
(9"x12") @ 10' C/C

3" PCC cover on 0.25 1


5468 1.5 2050.5
top 1.5' width

10267.5 cub. Ft.


290.699 Cub.M

5 Erecting & removing formwork to concrete in any


shape /position (Vertical)

Qty
Length (ft) Thickness (ft.) Nos.
(sq ft.)

Vertical profiles 1 1095.6 21912


20
(9"x12") @ 10' C/C
sq. ft

Total formwork 2038.33


sq. m

6
Construction of Siran Right Bank Canal
District Mansehra
SRBC Irrigation Canal RRM Retaining Wall Quantities
RD Wall Area (ft2) Reach Volume of No. of Weep Length of Total length Width of PCC Thickness of Volume of Volume of filter Width of 3" Volume of PCC No. of PCC Formwork
height Length (ft.) RRM (ft3) holes (5' c/c) weep hole of weep holes (1:3:6) PCC (1:3:6) concrete band material behind PCC (1:3:6) (1:3:6) 3" Coping Band layers (ft)
(ft.) Concrete Concrete PCC (1:3:6) weep holes Coping
band band (1.5'x1'x1')

RRM
ft ft ft ft ft3 ft3 ft ft3 No. Total
7+500 5.5 8.82 32 282.240 6 1.65 9.9 1.65 0.50 26.4 9.000 1.00 8.000 1 48.00
7+532 7.5 24.31 240 5834.400 48 6.63 318.24 6.63 0.50 795.6 72.000 1.50 90.000 2
7+772 6.5 12.15 378 4592.700 75 1.65 123.75 1.65 0.50 311.85 112.500 1.00 94.500 1 567.00
8+150 5.5 8.82 75 661.500 15 1.65 24.75 1.65 0.50 61.875 22.500 1.00 18.750 1
8+225
8+565 5.5 8.82 790 6967.800 158 1.65 260.7 1.65 0.50 651.75 237.000 1.00 197.500 1 1185.00
9+355 7.5 24.31 1065 25890.150 213 6.63 1412.19 6.63 0.50 3530.475 319.500 1.50 399.375 2 2662.50
10+420
10+492 5.5 8.82 1248 11007.360 249 1.65 410.85 1.65 0.50 1029.6 373.500 1.00 312.000 1 1872.00
11+740
12+010 8.5 37.31 1870 69769.700 374 8.630 3227.62 8.63 0.50 8069.05 561.000 2.50 1168.750 2 4675.00
13+880
20+250 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
20+500
20+750 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
21+250 6.5 12.15 250 3037.500 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
22+000 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
22+500 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
23+250 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
24+250 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
29+500 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
30+000 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
30+500 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
30+750 6.5 12.15 250 3037.500 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
31+500 6.5 12.15 250 3037.500 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
31+750 6.5 12.15 250 3037.500 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
32+500 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
32+750 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
33+250 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
33+750 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
34+250 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
35+500 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
36+000 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
36+750 6.5 12.15 250 3037.500 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
37+750 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
39+250 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
39+750 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
40+500 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
42+750 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
43+000 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
Construction of Siran Right Bank Canal
District Mansehra
SRBC Irrigation Canal RRM Retaining Wall Quantities
RD Wall Area (ft2) Reach Volume of No. of Weep Length of Total length Width of PCC Thickness of Volume of Volume of filter Width of 3" Volume of PCC No. of PCC Formwork
height Length (ft.) RRM (ft3) holes (5' c/c) weep hole of weep holes (1:3:6) PCC (1:3:6) concrete band material behind PCC (1:3:6) (1:3:6) 3" Coping Band layers (ft)
(ft.) Concrete Concrete PCC (1:3:6) weep holes Coping
band band (1.5'x1'x1')

RRM
ft ft ft ft ft3 ft3 ft ft3 No. Total
43+250 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
44+000 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
44+250 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
45+000 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
45+500 6.5 12.15 250 3037.500 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
46+250 6.5 12.15 250 3037.500 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
46+500 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
47+000 6.5 12.15 250 3037.500 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
47+500 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
48+250 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
49+750 6.5 12.15 250 3037.500 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
50+000 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
50+750 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
51+250 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
56+500 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
56+750 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
57+000 6.5 12.15 250 3037.500 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
58+250 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
59+750 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
60+500 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
61+750 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
62+000 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
62+250 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
63+000 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
63+750 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
65+250 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
66+000 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
66+750 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
67+750 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
68+000 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
68+750 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
69+250 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
69+500 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
70+500 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
71+250 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
71+750 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
72+250 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
72+750 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
73+250 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
74+000 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
Construction of Siran Right Bank Canal
District Mansehra
SRBC Irrigation Canal RRM Retaining Wall Quantities
RD Wall Area (ft2) Reach Volume of No. of Weep Length of Total length Width of PCC Thickness of Volume of Volume of filter Width of 3" Volume of PCC No. of PCC Formwork
height Length (ft.) RRM (ft3) holes (5' c/c) weep hole of weep holes (1:3:6) PCC (1:3:6) concrete band material behind PCC (1:3:6) (1:3:6) 3" Coping Band layers (ft)
(ft.) Concrete Concrete PCC (1:3:6) weep holes Coping
band band (1.5'x1'x1')

RRM
ft ft ft ft ft3 ft3 ft ft3 No. Total
74+250 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
74+500 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
74+750 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
75+750 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
76+250 6.5 12.15 250 3037.500 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
76+500 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
77+250 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
77+500 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
77+750 6.5 12.15 250 3037.500 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
78+000 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
78+250 6.5 12.15 250 3037.500 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
78+750 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
79+250 6.5 12.15 250 3037.500 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
79+500 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
80+000 6.5 12.15 250 3037.500 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
80+250 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
80+500 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
81+000 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
81+250 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
83+000 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
83+750 6.5 12.15 250 3037.500 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
84+000 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
86+000 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
86+250 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
86+750 6.5 12.15 250 3037.500 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
87+250 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
87+750 6.5 12.15 250 3037.500 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
88+750 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
89+500 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
93+250 6.5 12.15 250 3037.500 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
93+500 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
94+000 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
94+250 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
95+500 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
95+750 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
96+000 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
96+250 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
96+500 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
97+250 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
97+500 6.5 12.15 250 3037.500 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
Construction of Siran Right Bank Canal
District Mansehra
SRBC Irrigation Canal RRM Retaining Wall Quantities
RD Wall Area (ft2) Reach Volume of No. of Weep Length of Total length Width of PCC Thickness of Volume of Volume of filter Width of 3" Volume of PCC No. of PCC Formwork
height Length (ft.) RRM (ft3) holes (5' c/c) weep hole of weep holes (1:3:6) PCC (1:3:6) concrete band material behind PCC (1:3:6) (1:3:6) 3" Coping Band layers (ft)
(ft.) Concrete Concrete PCC (1:3:6) weep holes Coping
band band (1.5'x1'x1')

RRM
ft ft ft ft ft3 ft3 ft ft3 No. Total
97+750 6.5 12.15 250 3037.500 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
98+500 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
99+500 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
99+750 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
100+000 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
100+750 6.5 12.15 250 3037.500 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
103+500 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
103+750 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
104+500 6.5 12.15 250 3037.500 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
105+000 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
105+750 6.5 12.15 250 3037.500 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
106+500 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
107+000 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
107+250 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
107+500 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
108+000 6.5 12.15 250 3037.500 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
108+500 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
108+750 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
109+000 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
110+250 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
111+500 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
114+750 6.5 12.15 250 3037.500 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
115+000 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
115+250 6.5 12.15 250 3037.500 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
115+500 6.5 12.15 250 3037.500 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
116+250 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
119+250 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
119+500 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
121+000 6.5 12.15 250 3037.500 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
125+500 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
127+250 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
127+750 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
130+750 6.5 12.15 250 3037.500 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
131+500 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
132+000 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
133+000 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
133+500 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
133+750 6.5 12.15 250 3037.500 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
145+250 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
149+500 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
Construction of Siran Right Bank Canal
District Mansehra
SRBC Irrigation Canal RRM Retaining Wall Quantities
RD Wall Area (ft2) Reach Volume of No. of Weep Length of Total length Width of PCC Thickness of Volume of Volume of filter Width of 3" Volume of PCC No. of PCC Formwork
height Length (ft.) RRM (ft3) holes (5' c/c) weep hole of weep holes (1:3:6) PCC (1:3:6) concrete band material behind PCC (1:3:6) (1:3:6) 3" Coping Band layers (ft)
(ft.) Concrete Concrete PCC (1:3:6) weep holes Coping
band band (1.5'x1'x1')

RRM
ft ft ft ft ft3 ft3 ft ft3 No. Total
150+500 5.5 8.82 250 2205.000 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
161+750 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
164+500 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
165+000 6.5 12.15 250 3037.500 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
168+000 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
168+250 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
168+750 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
169+000 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
171+000 6.5 12.15 250 3037.500 50 1.650 82.5 1.65 0.50 206.25 75.000 1.00 62.500 1 375.00
172+000 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
172+250 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
174+250 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
175+000 8.5 37.31 250 9327.500 50 8.630 431.5 8.63 0.50 1078.75 75.000 2.50 156.250 2 625.00
175+500 7.5 24.31 250 6077.500 50 6.630 331.5 6.63 0.50 828.75 75.000 1.50 93.750 2 625.00
177+750 7.5 24.31 125 3038.750 25 6.630 165.75 6.63 0.50 414.375 37.500 1.50 46.875 2 312.50
179+000 8.5 37.31 125 4663.750 25 8.630 215.75 8.63 0.50 539.375 37.500 2.50 78.125 2 312.50
182+750 8.5 37.31 125 4663.750 25 8.630 215.75 8.63 0.50 539.375 37.500 2.50 78.125 2 312.50
185+250 8.5 37.31 112.25 4188.048 22 8.630 189.86 8.63 0.50 484.35875 33.000 2.50 70.156 2 280.63
185+522
Total Volume in Cub. Ft. 1,007,817.65 46,169.61 115,440.33 13,927.50 18,124.66 94,602.63
Total Volume in Cub. m. 28,533.91 14,071.81 3,268.413 394.323 513.156 8,800.244
Construction of Siran Right Bank Canal
District Mansehra
SRBC Irrigation Canal Plum Concrete Retaining Wall Quantities (Main Canal)
RD Wall height (ft.) Area (ft2) Reach Length (ft.) Volume of PCC No. of weep Length of weep Total length of Volume of filter Formwork
(1:3:6) 40% holes (5' c/c) pipe weep pipe material behind (ft)
Boulders (ft3) weep holes (1cft)

Plum ft ft ft3 Total


17+385 12.5 54 500 27000.000 100 7.00 700.00 200.000 12500.00
19+086
19+156 14.5 69.5 500 34750.000 100 13.50 1350.00 300.000 14500.00
20+000
30+250 10.5 31.25 0 0.000 0 5.00 0.00 0.000 0.00
31+000 10.5 31.25 250 7812.500 50 5.00 250.00 100.000 5250.00
32+000 9.5 27 0 0.000 0 5.00 0.00 0.000 0.00
35+000 10.5 31.25 0 0.000 0 5.00 0.00 0.000 0.00
37+500 9.5 27 250 6750.000 50 5.00 250.00 100.000 4750.00
40+000 5 31.25 250 7812.500 50 5.00 250.00 100.000 2500.00
40+250 12.5 54 0 0.000 0 7.00 0.00 0.000 0.00
40+750 7 60.75 250 15187.500 50 7.00 350.00 100.000 3500.00
41+250 4 54 0 0.000 0 7.00 0.00 0.000 0.00
41+500 8 107.5 0 0.000 0 22.00 0.00 0.000 0.00
44+500 5 54 0 0.000 0 7.00 0.00 0.000 0.00
45+750 9 69.5 0 0.000 0 13.50 0.00 0.000 0.00
46+000 7.5 46.25 250 11562.500 50 7.00 350.00 100.000 3750.00
48+500 9.5 27 0 0.000 0 5.00 0.00 0.000 0.00
49+250 9.5 27 250 6750.000 50 5.00 250.00 100.000 4750.00
49+500 4.5 46.25 0 0.000 0 7.00 0.00 0.000 0.00
54+250 9.5 27 250 6750.000 50 5.00 250.00 100.000 4750.00
55+500 9.5 27 0 0.000 0 5.00 0.00 0.000 0.00
57+250 6.75 54 0 0.000 0 7.00 0.00 0.000 0.00
59+500 9.5 27 250 6750.000 50 5.00 250.00 100.000 4750.00
61+000 10.5 31.25 0 0.000 0 5.00 0.00 0.000 0.00
61+500 8 69.5 0 0.000 0 13.50 0.00 0.000 0.00
63+250 9 60.75 0 0.000 0 7.00 0.00 0.000 0.00
63+500 14.5 69.5 0 0.000 0 13.50 0.00 0.000 0.00
64+500 7 78 250 19500.000 50 13.50 675.00 150.000 3500.00
64+750 12.5 54 0 0.000 0 7.00 0.00 0.000 0.00
65+500 10.5 31.25 250 7812.500 50 5.00 250.00 100.000 5250.00
66+250 9 69.5 0 0.000 0 13.50 0.00 0.000 0.00
66+500 7 96.5 0 0.000 0 13.50 0.00 0.000 0.00
67+000 9.5 27 0 0.000 0 5.00 0.00 0.000 0.00
67+250 10.5 31.25 250 7812.500 50 5.00 250.00 100.000 5250.00
67+500 9.5 27 250 6750.000 50 5.00 250.00 100.000 4750.00
Construction of Siran Right Bank Canal
District Mansehra
SRBC Irrigation Canal Plum Concrete Retaining Wall Quantities (Main Canal)
RD Wall height (ft.) Area (ft2) Reach Length (ft.) Volume of PCC No. of weep Length of weep Total length of Volume of filter Formwork
(1:3:6) 40% holes (5' c/c) pipe weep pipe material behind (ft)
Boulders (ft3) weep holes (1cft)

Plum ft ft ft3 Total


68+250 12.5 54 0 0.000 0 7.00 0.00 0.000 0.00
68+500 10.5 31.25 0 0.000 0 5.00 0.00 0.000 0.00
69+000 10.5 31.25 0 0.000 0 5.00 0.00 0.000 0.00
70+000 11.5 46.25 0 0.000 0 7.00 0.00 0.000 0.00
70+750 9.5 27 250 6750.000 50 5.00 250.00 100.000 4750.00
72+500 9.5 27 250 6750.000 50 5.00 250.00 100.000 4750.00
73+000 10.5 31.25 0 0.000 0 5.00 0.00 0.000 0.00
76+750 9.5 27 250 6750.000 50 5.00 250.00 100.000 4750.00
77+000 13.5 60.75 250 15187.500 50 7.00 350.00 100.000 6750.00
81+500 9.5 27 0 0.000 0 5.00 0.00 0.000 0.00
84+500 10.5 31.25 0 0.000 0 5.00 0.00 0.000 0.00
87+500 10.5 31.25 0 0.000 0 5.00 0.00 0.000 0.00
90+500 15.5 78 0 0.000 0 13.50 0.00 0.000 0.00
90+750 12.5 54 0 0.000 0 7.00 0.00 0.000 0.00
91+500 9.5 27 250 6750.000 50 5.00 250.00 100.000 4750.00
92+750 9.5 27 0 0.000 0 5.00 0.00 0.000 0.00
93+000 10.5 31.25 250 7812.500 50 5.00 250.00 100.000 5250.00
93+750 12.5 54 0 0.000 0 7.00 0.00 0.000 0.00
94+750 9.5 27 0 0.000 0 5.00 0.00 0.000 0.00
95+000 8 69.5 0 0.000 0 13.50 0.00 0.000 0.00
95+250 7 31.25 250 7812.500 50 5.00 250.00 100.000 3500.00
99+000 6 54 0 0.000 0 7.00 0.00 0.000 0.00
104+000 11.5 46.25 0 0.000 0 7.00 0.00 0.000 0.00
105+500 9.5 27 250 6750.000 50 5.00 250.00 100.000 4750.00
106+250 10.5 31.25 0 0.000 0 5.00 0.00 0.000 0.00
106+750 9.5 27 0 0.000 0 5.00 0.00 0.000 0.00
110+000 9.5 27 0 0.000 0 5.00 0.00 0.000 0.00
111+750 9.5 27 0 0.000 0 5.00 0.00 0.000 0.00
112+250 10.5 31.25 250 7812.500 50 5.00 250.00 100.000 5250.00
112+500 9.5 27 250 6750.000 50 5.00 250.00 100.000 4750.00
113+500 9.5 27 0 0.000 0 5.00 0.00 0.000 0.00
116+000 9.5 27 0 0.000 0 5.00 0.00 0.000 0.00
116+500 11.5 46.25 185 8556.250 37 7.00 259.00 74.000 4255.00
118+000 9.5 27 162 4374.000 32 5.00 160.00 64.000 3078.00
118+250 12.5 54 200 10800.000 40 7.00 280.00 80.000 5000.00
120+000 12.5 54 0 0.000 0 7.00 0.00 0.000 0.00
122+000 9.5 27 0 0.000 0 5.00 0.00 0.000 0.00
Construction of Siran Right Bank Canal
District Mansehra
SRBC Irrigation Canal Plum Concrete Retaining Wall Quantities (Main Canal)
RD Wall height (ft.) Area (ft2) Reach Length (ft.) Volume of PCC No. of weep Length of weep Total length of Volume of filter Formwork
(1:3:6) 40% holes (5' c/c) pipe weep pipe material behind (ft)
Boulders (ft3) weep holes (1cft)

Plum ft ft ft3 Total


125+750 11.5 46.25 0 0.000 0 7.00 0.00 0.000 0.00
126+000 12.5 54 160 8640.000 32 7.00 224.00 64.000 4000.00
126+750 9.5 27 135 3645.000 27 5.00 135.00 54.000 2565.00
127+500 5 54 100 5400.000 20 7.00 140.00 40.000 1000.00
128+250 12.5 54 0 0.000 0 7.00 0.00 0.000 0.00
129+500 10.5 31.25 0 0.000 0 5.00 0.00 0.000 0.00
129+750 5 60.75 110 6682.500 22 7.00 154.00 44.000 1100.00
131+000 5 60.75 150 9112.500 30 7.00 210.00 60.000 1500.00
131+250 9.5 27 0 0.000 0 5.00 0.00 0.000 0.00
131+750 5 96.5 0 0.000 0 13.50 0.00 0.000 0.00
132+500 10.5 31.25 0 0.000 0 5.00 0.00 0.000 0.00
135+250 9.5 27 250 6750.000 50 5.00 250.00 100.000 4750.00
144+500 10.5 31.25 0 0.000 0 5.00 0.00 0.000 0.00
148+500 9.5 27 0 0.000 0 5.00 0.00 0.000 0.00
152+000 6 60.75 250 15187.500 50 7.00 350.00 100.000 3000.00
152+750 12.5 54 0 0.000 0 7.00 0.00 0.000 0.00
153+500 9.5 27 100 2700.000 20 5.00 100.00 40.000 1900.00
155+500 9.5 27 0 0.000 0 5.00 0.00 0.000 0.00
156+250 10.5 31.25 250 7812.500 50 5.00 250.00 100.000 5250.00
159+250 9.5 27 0 0.000 0 5.00 0.00 0.000 0.00
164+000 9.5 27 250 6750.000 50 5.00 250.00 100.000 4750.00
164+250 9.5 27 0 0.000 0 5.00 0.00 0.000 0.00
174+500 9.5 27 0 0.000 0 5.00 0.00 0.000 0.00
175+250 9.5 27 140 3780.000 28 5.00 140.00 56.000 2660.00
175+750 13.5 60.75 0 0.000 0 7.00 0.00 0.000 0.00
176+000 8 78 250 19500.000 50 13.50 675.00 150.000 4000.00
180+250 9.5 27 0 0.000 0 5.00 0.00 0.000 0.00
180+500 5 27 250 6750.000 50 5.00 250.00 100.000 2500.00
180+750
Total Volume in Cub. Ft. 378,565.25 12,102.00 3,976.00 180,308.00
Total Volume in Cub. m. 10,718.155 3,688.51 112.571 16,772.837
Construction of Siran Right Bank Canal
District Mansehra
SRBC Irrigation Canal Plum Concrete Retaining Wall Quantities (Minor Canal)
RD Wall height (ft.) Area (ft2) Reach Length (ft.) Volume of PCC No. of weep Length of weep Total length of Volume of filter Formwork
(1:3:6) 40% holes (5' c/c) pipe weep pipe material behind (ft)
Boulders (ft3) weep holes (1cft)

Plum ft ft ft3 Total


00+000 6 27 110 2970.000 22 5.00 110.00 44.000 1320.00
00+250 6 27 140 3780.000 28 5.00 140.00 56.000 1680.00
00+500 10.5 31.25 0 0.000 0 5.00 0.00 0.000 0.00
00+750 9.5 27 100 2700.000 20 5.00 100.00 40.000 1900.00
01+000 10.5 31.25 0 0.000 0 5.00 0.00 0.000 0.00
01+250 10.5 31.25 0 0.000 0 5.00 0.00 0.000 0.00
01+500 9.5 27 100 2700.000 20 5.00 100.00 40.000 1900.00
01+750 10.5 31.25 0 0.000 0 5.00 0.00 0.000 0.00
02+000 9.5 27 100 2700.000 20 5.00 100.00 40.000 1900.00
02+250 10.5 31.25 0 0.000 0 5.00 0.00 0.000 0.00
02+500 9.5 27 0 0.000 0 5.00 0.00 0.000 0.00
03+250 9.5 27 120 3240.000 24 5.00 120.00 48.000 2280.00
03+500 10.5 31.25 0 0.000 0 5.00 0.00 0.000 0.00
03+750 10.5 31.25 0 0.000 0 5.00 0.00 0.000 0.00
05+250 7 27 160 4320.000 32 5.00 160.00 64.000 2240.00
05+500 10.5 31.25 0 0.000 0 5.00 0.00 0.000 0.00
05+750 9.5 27 0 0.000 0 5.00 0.00 0.000 0.00
06+000 10.5 31.25 0 0.000 0 5.00 0.00 0.000 0.00
06+250 9.5 27 0 0.000 0 5.00 0.00 0.000 0.00
09+250 10.5 31.25 0 0.000 0 5.00 0.00 0.000 0.00
09+500 10.5 31.25 0 0.000 0 5.00 0.00 0.000 0.00
09+750 10.5 31.25 0 0.000 0 5.00 0.00 0.000 0.00
10+000 9.5 27 125 3375.000 25 5.00 125.00 50.000 2375.00
10+250 9.5 27 0 0.000 0 5.00 0.00 0.000 0.00
10+500 10.5 31.25 195 6093.750 39 5.00 195.00 78.000 4095.00
11+000 9.5 27 0 0.000 0 5.00 0.00 0.000 0.00
12+000 7 31.25 135 4218.750 27 5.00 135.00 54.000 1890.00
13+000 10.5 31.25 0 0.000 0 5.00 0.00 0.000 0.00
13+250 9.5 27 200 5400.000 40 5.00 200.00 80.000 3800.00
15+000 10.5 31.25 0 0.000 0 5.00 0.00 0.000 0.00
15+250 9.5 27 0 0.000 0 5.00 0.00 0.000 0.00
16+750 9.5 27 0 0.000 0 5.00 0.00 0.000 0.00
17+500 10.5 31.25 0 0.000 0 5.00 0.00 0.000 0.00
17+750 10.5 31.25 200 6250.000 40 5.00 200.00 80.000 4200.00
Total Volume in Cub. Ft. 47,747.50 1,685.00 674.00 29,580.00
Total Volume in Cub. m. 1,351.854 513.56 19.083 2,751.628
Construction of Siran Right Bank Canal
District Mansehra
Drainage Culverts

BOQ Description Measurement


Item No. Sheet Reference

D-1 Structural Excavation in Common Material

Description No. Length Width Depth Volume


(ft) (ft) (ft) (cft)

RD: 27+750 1 23.5 14.5 5.5 1874.13


Toe Walls 2 14.5 8 8.5 1972.00
RD: 25+070 1 23.5 14.5 5.5 1874.13
Toe Walls 2 14.5 8 8.5 1972.00
RD: 26+440 1 23.5 14.5 5.5 1874.13
Toe Walls 2 14.5 8 8.5 1972.00
RD: 26+950 1 23.5 14.5 5.5 1874.13
Toe Walls 2 14.5 8 8.5 1972.00
RD: 27+625 1 23.5 14.5 5.5 1874.13
Toe Walls 2 14.5 8 8.5 1972.00
RD: 29+400 1 23.5 14.5 5.5 1874.13
Toe Walls 2 14.5 8 8.5 1972.00
RD: 29+800 1 23.5 14.5 5.5 1874.13
Toe Walls 2 14.5 8 8.5 1972.00
RD: 31+545 1 23.5 14.5 5.5 1874.13
Toe Walls 2 14.5 8 8.5 1972.00
RD: 31+855 1 23.5 14.5 5.5 1874.13
Toe Walls 2 14.5 8 8.5 1972.00
RD: 36+090 1 23.5 14.5 5.5 1874.13
Toe Walls 2 14.5 8 8.5 1972.00
RD: 37+065 1 23.5 14.5 5.5 1874.13
Toe Walls 2 14.5 8 8.5 1972.00
RD: 39+100 1 23.5 14.5 5.5 1874.13
Toe Walls 2 14.5 8 8.5 1972.00
RD: 42+290 1 23.5 14.5 5.5 1874.13
Toe Walls 2 14.5 8 8.5 1972.00
RD: 53+325 1 23.5 14.5 5.5 1874.13
Toe Walls 2 14.5 8 8.5 1972.00
RD: 93+577 1 23.5 14.5 5.5 1874.13
Toe Walls 2 14.5 8 8.5 1972.00
RD: 94+097 1 23.5 14.5 5.5 1874.13
Toe Walls 2 14.5 8 8.5 1972.00
RD: 130+954 1 23.5 14.5 5.5 1874.13
Toe Walls 2 14.5 8 8.5 1972.00
RD: 131+319 1 23.5 14.5 5.5 1874.13
Toe Walls 2 14.5 8 8.5 1972.00
RD: 132+258 1 23.5 14.5 5.5 1874.13
Toe Walls 2 14.5 8 8.5 1972.00
Construction of Siran Right Bank Canal
District Mansehra
Drainage Culverts

BOQ Description Measurement


Item No. Sheet Reference
RD: 138+965 1 23.5 14.5 5.5 1874.13
Toe Walls 2 14.5 8 8.5 1972.00
RD: 150+396 1 23.5 14.5 5.5 1874.13
Toe Walls 2 14.5 8 8.5 1972.00
RD: 155+907 1 23.5 14.5 5.5 1874.13
Toe Walls 2 14.5 8 8.5 1972.00
RD: 163+805 1 23.5 14.5 5.5 1874.13
Toe Walls 2 14.5 8 8.5 1972.00
RD: 171+412 1 23.5 14.5 5.5 1874.13
Toe Walls 2 14.5 8 8.5 1972.00
Sewerage Nallah 16538.83
Total Quantity (Cft) 108845.83
Total Quantity (CuM 3082.17

Plain Cement Concrete including placing, compacting, finishing & curing (Ratio
D-2
1:4:8)

Description No. Length Width Depth Volume


(ft) (ft) (ft) (cft)

RD: 27+750 Barrel 1 30.5 11.25 0.25 85.78


Toe Walls 2 11.25 6.5 0.25 36.56
RD: 25+070 Barrel 1 30.5 11.25 0.25 85.78
Toe Walls 2 11.25 6.5 0.25 36.56
RD: 26+440 Barrel 1 30.5 11.25 0.25 85.78
Toe Walls 2 11.25 6.5 0.25 36.56
RD: 26+950 Barrel 1 30.5 11.25 0.25 85.78
Toe Walls 2 11.25 6.5 0.25 36.56
RD: 27+625 Barrel 1 30.5 11.25 0.25 85.78
Toe Walls 2 11.25 6.5 0.25 36.56
RD: 29+400 Barrel 1 30.5 11.25 0.25 85.78
Toe Walls 2 11.25 6.5 0.25 36.56
RD: 29+800 Barrel 1 30.5 11.25 0.25 85.78
Toe Walls 2 11.25 6.5 0.25 36.56
RD: 31+545 Barrel 1 30.5 11.25 0.25 85.78
Toe Walls 2 11.25 6.5 0.25 36.56
RD: 31+855 Barrel 1 30.5 11.25 0.25 85.78
Toe Walls 2 11.25 6.5 0.25 36.56
RD: 36+090 Barrel 1 30.5 11.25 0.25 85.78
Toe Walls 2 11.25 6.5 0.25 36.56
RD: 37+065 Barrel 1 30.5 11.25 0.25 85.78
Toe Walls 2 11.25 6.5 0.25 36.56
Construction of Siran Right Bank Canal
District Mansehra
Drainage Culverts

BOQ Description Measurement


Item No. Sheet Reference
RD: 39+100 Barre 1 30.5 11.25 0.25 85.78
Toe Walls 2 11.25 6.5 0.25 36.56
RD: 42+290 Barrel 1 30.5 11.25 0.25 85.78
Toe Walls 2 11.25 6.5 0.25 36.56
RD: 53+325 Barrel 1 30.5 11.25 0.25 85.78
Toe Walls 2 11.25 6.5 0.25 36.56
RD: 93+577 Barrel 1 30.5 11.25 0.25 85.78
Toe Walls 2 11.25 6.5 0.25 36.56
RD: 94+097 Barrel 1 30.5 11.25 0.25 85.78
Toe Walls 2 11.25 6.5 0.25 36.56
RD: 130+954 Barrel 1 30.5 11.25 0.25 85.78
Toe Walls 2 11.25 6.5 0.25 36.56
RD: 131+319 Barrel 1 30.5 11.25 0.25 85.78
Toe Walls 2 11.25 6.5 0.25 36.56
RD: 132+258 Barrel 1 30.5 11.25 0.25 85.78
Toe Walls 2 11.25 6.5 0.25 36.56
RD: 138+965 Barrel 1 30.5 11.25 0.25 85.78
Toe Walls 2 11.25 6.5 0.25 36.56
RD: 150+396 Barrel 1 30.5 11.25 0.25 85.78
Toe Walls 2 11.25 6.5 0.25 36.56
RD: 155+907 Barrel 1 30.5 11.25 0.25 85.78
Toe Walls 2 11.25 6.5 0.25 36.56
RD: 163+805 Barrel 1 30.5 11.25 0.25 85.78
Toe Walls 2 11.25 6.5 0.25 36.56
RD: 171+412 Barrel 1 30.5 11.25 0.25 85.78
Toe Walls 2 11.25 6.5 0.25 36.56
Total Quantity (Cft) 2936.25
Total Quantity (CuM 83.15

RCC in raft foundation slab, base slab of column & ret.


D-3
wall etc, not including in 06-06. Type C(1:2:4)

Description No. Length Width Depth Volume


(ft) (ft) (ft) (cft)

RD: 27+750 Barrel 1 32.5 11.25 1.25 457.03


Toe Wall Base 2 11.25 6.5 1.25 182.81
Toe Wall vertical 2 11.25 1 2.25 50.63
Side Walls 2 32.5 0.75 5 243.75
Head Walls 2 11.25 1 2.5 56.25
RD: 25+070 Barrel 1 32.5 11.25 1.25 457.03
Toe Wall Base 2 11.25 6.5 1.25 182.81
Construction of Siran Right Bank Canal
District Mansehra
Drainage Culverts

BOQ Description Measurement


Item No. Sheet Reference
Toe Wall vertical 2 11.25 1 2.25 50.63
Side Walls 2 32.5 0.75 5 243.75
Head Walls 2 11.25 1 2.5 56.25
RD: 26+440 Barrel 1 32.5 11.25 1.25 457.03
Toe Wall Base 2 11.25 6.5 1.25 182.81
Toe Wall vertical 2 11.25 1 2.25 50.63
Side Walls 2 32.5 0.75 5 243.75
Head Walls 2 11.25 1 2.5 56.25
RD: 26+950 Barrel 1 32.5 11.25 1.25 457.03
Toe Wall Base 2 11.25 6.5 1.25 182.81
Toe Wall vertical 2 11.25 1 2.25 50.63
Side Walls 2 32.5 0.75 5 243.75
Head Walls 2 11.25 1 2.5 56.25
RD: 27+625 Barrel 1 32.5 11.25 1.25 457.03
Toe Wall Base 2 11.25 6.5 1.25 182.81
Toe Wall vertical 2 11.25 1 2.25 50.63
Side Walls 2 32.5 0.75 5 243.75
Head Walls 2 11.25 1 2.5 56.25
RD: 29+400 Barrel 1 32.5 11.25 1.25 457.03
Toe Wall Base 2 11.25 6.5 1.25 182.81
Toe Wall vertical 2 11.25 1 2.25 50.63
Side Walls 2 32.5 0.75 5 243.75
Head Walls 2 11.25 1 2.5 56.25
RD: 29+800 Barrel 1 32.5 11.25 1.25 457.03
Toe Wall Base 2 11.25 6.5 1.25 182.81
Toe Wall vertical 2 11.25 1 2.25 50.63
Side Walls 2 32.5 0.75 5 243.75
Head Walls 2 11.25 1 2.5 56.25
RD: 31+545 Barrel 1 32.5 11.25 1.25 457.03
Toe Wall Base 2 11.25 6.5 1.25 182.81
Toe Wall vertical 2 11.25 1 2.25 50.63
Side Walls 2 32.5 0.75 5 243.75
Head Walls 2 11.25 1 2.5 56.25
RD: 31+855 Barrel 1 32.5 11.25 1.25 457.03
Toe Wall Base 2 11.25 6.5 1.25 182.81
Toe Wall vertical 2 11.25 1 2.25 50.63
Side Walls 2 32.5 0.75 5 243.75
Head Walls 2 11.25 1 2.5 56.25
RD: 36+090 Barrel 1 32.5 11.25 1.25 457.03
Toe Wall Base 2 11.25 6.5 1.25 182.81
Toe Wall vertical 2 11.25 1 2.25 50.63
Side Walls 2 32.5 0.75 5 243.75
Construction of Siran Right Bank Canal
District Mansehra
Drainage Culverts

BOQ Description Measurement


Item No. Sheet Reference
Head Walls 2 11.25 1 2.5 56.25
RD: 37+065 Barrel 1 32.5 11.25 1.25 457.03
Toe Wall Base 2 11.25 6.5 1.25 182.81
Toe Wall vertical 2 11.25 1 2.25 50.63
Side Walls 2 32.5 0.75 5 243.75
Head Walls 2 11.25 1 2.5 56.25
RD: 39+100 Barrel 1 32.5 11.25 1.25 457.03
Toe Wall Base 2 11.25 6.5 1.25 182.81
Toe Wall vertical 2 11.25 1 2.25 50.63
Side Walls 2 32.5 0.75 5 243.75
Head Walls 2 11.25 1 2.5 56.25
RD: 42+290 Barrel 1 32.5 11.25 1.25 457.03
Toe Wall Base 2 11.25 6.5 1.25 182.81
Toe Wall vertical 2 11.25 1 2.25 50.63
Side Walls 2 32.5 0.75 5 243.75
Head Walls 2 11.25 1 2.5 56.25
RD: 53+325 Barrel 1 32.5 11.25 1.25 457.03
Toe Wall Base 2 11.25 6.5 1.25 182.81
Toe Wall vertical 2 11.25 1 2.25 50.63
Side Walls 2 32.5 0.75 5 243.75
Head Walls 2 11.25 1 2.5 56.25
RD: 93+577 Barrel 1 32.5 11.25 1.25 457.03
Toe Wall Base 2 11.25 6.5 1.25 182.81
Toe Wall vertical 2 11.25 1 2.25 50.63
Side Walls 2 32.5 0.75 5 243.75
Head Walls 2 11.25 1 2.5 56.25
RD: 94+097 Barrel 1 32.5 11.25 1.25 457.03
Toe Wall Base 2 11.25 6.5 1.25 182.81
Toe Wall vertical 2 11.25 1 2.25 50.63
Side Walls 2 32.5 0.75 5 243.75
Head Walls 2 11.25 1 2.5 56.25
RD: 130+954 Barrel 1 32.5 11.25 1.25 457.03
Toe Wall Base 2 11.25 6.5 1.25 182.81
Toe Wall vertical 2 11.25 1 2.25 50.63
Side Walls 2 32.5 0.75 5 243.75
Head Walls 2 11.25 1 2.5 56.25
RD: 131+319 Barrel 1 32.5 11.25 1.25 457.03
Toe Wall Base 2 11.25 6.5 1.25 182.81
Toe Wall vertical 2 11.25 1 2.25 50.63
Side Walls 2 32.5 0.75 5 243.75
Head Walls 2 11.25 1 2.5 56.25
RD: 132+258 Barrel 1 32.5 11.25 1.25 457.03
Construction of Siran Right Bank Canal
District Mansehra
Drainage Culverts

BOQ Description Measurement


Item No. Sheet Reference
Toe Wall Base 2 11.25 6.5 1.25 182.81
Toe Wall vertical 2 11.25 1 2.25 50.63
Side Walls 2 32.5 0.75 5 243.75
Head Walls 2 11.25 1 2.5 56.25
RD: 138+965 Barrel 1 32.5 11.25 1.25 457.03
Toe Wall Base 2 11.25 6.5 1.25 182.81
Toe Wall vertical 2 11.25 1 2.25 50.63
Side Walls 2 32.5 0.75 5 243.75
Head Walls 2 11.25 1 2.5 56.25
RD: 150+396 Barrel 1 32.5 11.25 1.25 457.03
Toe Wall Base 2 11.25 6.5 1.25 182.81
Toe Wall vertical 2 11.25 1 2.25 50.63
Side Walls 2 32.5 0.75 5 243.75
Head Walls 2 11.25 1 2.5 56.25
RD: 155+907 Barrel 1 32.5 11.25 1.25 457.03
Toe Wall Base 2 11.25 6.5 1.25 182.81
Toe Wall vertical 2 11.25 1 2.25 50.63
Head Walls 2 11.25 1 2.5 56.25
Side Walls 2 32.5 0.75 5 243.75
RD: 163+805 Barrel 1 32.5 11.25 1.25 457.03
Toe Wall Base 2 11.25 6.5 1.25 182.81
Toe Wall vertical 2 11.25 1 2.25 50.63
Side Walls 2 32.5 0.75 5 243.75
Head Walls 2 11.25 1 2.5 56.25
RD: 171+412 Barrel 1 32.5 11.25 1.25 457.03
Toe Wall Base 2 11.25 6.5 1.25 182.81
Toe Wall vertical 2 11.25 1 2.25 50.63
Head Walls 2 11.25 1 2.5 56.25
Side Walls 2 32.5 0.75 5 243.75
Total Quantity (Cft) 23771.25
Total Quantity (CuM) 673.13

RCC in roof slab, beam, column & other structural members, insitu or
D-4 precast. Type C (1:2:4)

Description No. Length Width Depth Volume


(ft) (ft) (ft) (cft)

RD: 27+750 Top Slab 1 32.5 11.25 1.25 457.03


RD: 25+070 Top Slab 1 32.5 11.25 1.25 457.03
RD: 26+440 Top Slab 1 32.5 11.25 1.25 457.03
RD: 26+950 Top Slab 1 32.5 11.25 1.25 457.03
Construction of Siran Right Bank Canal
District Mansehra
Drainage Culverts

BOQ Description Measurement


Item No. Sheet Reference
RD: 27+625 Top Slab 1 32.5 11.25 1.25 457.03
RD: 29+400 Top Slab 1 32.5 11.25 1.25 457.03
RD: 29+800 Top Slab 1 32.5 11.25 1.25 457.03
RD: 31+545 Top Slab 1 32.5 11.25 1.25 457.03
RD: 31+855 Top Slab 1 32.5 11.25 1.25 457.03
RD: 36+090 Top Slab 1 32.5 11.25 1.25 457.03
RD: 37+065 Top Slab 1 32.5 11.25 1.25 457.03
RD: 39+100 Top Slab 1 32.5 11.25 1.25 457.03
RD: 42+290 Top Slab 1 32.5 11.25 1.25 457.03
RD: 53+325 Top Slab 1 32.5 11.25 1.25 457.03
RD: 93+577 Top Slab 1 32.5 11.25 1.25 457.03
RD: 94+097 Top Slab 1 32.5 11.25 1.25 457.03
RD: 130+954 Top Slab 1 32.5 11.25 1.25 457.03
RD: 131+319 Top Slab 1 32.5 11.25 1.25 457.03
RD: 132+258 Top Slab 1 32.5 11.25 1.25 457.03
RD: 138+965 Top Slab 1 32.5 11.25 1.25 457.03
RD: 150+396 Top Slab 1 32.5 11.25 1.25 457.03
RD: 155+907 Top Slab 1 32.5 11.25 1.25 457.03
RD: 163+805 Top Slab 1 32.5 11.25 1.25 457.03
RD: 171+412 Top Slab 1 32.5 11.25 1.25 457.03
Total Quantity (Cft) 10968.75
Total Quantity (CuM) 310.6

D-5 Supply & fabricate M.S. reinforcement for cement concrete (Hot rolled deformed
bars Grade 40).

Taking 2.00% of RCC Volume as per Item D-3 & D-4


Concrete Quantity = 23771.25 + 10968.750 = 34740.00 Cft
Steel Quantity = 34740.00 x 2.00% x 490 = 340452 lb
OR 154.47 Tonnes

D-6 Structural backfill using Common Material available at site

Take 10% of excavation as backfill 0.000


Description No. Length Width Depth Volume
(ft) (ft) (ft) (cft)

RD: 27+750 Side Walls 2 32.5 1.5 7.75 755.63


Along Toe Walls 2 11.5 1.5 4.75 163.88
RD: 25+070 Side Walls 2 32.5 1.5 7.75 755.63
Along Toe Walls 2 11.5 1.5 4.75 163.88
RD: 26+440 Side Walls 2 32.5 1.5 7.75 755.63
Construction of Siran Right Bank Canal
District Mansehra
Drainage Culverts

BOQ Description Measurement


Item No. Sheet Reference
Along Toe Walls 2 11.5 1.5 4.75 163.88
RD: 26+950 Side Walls 2 32.5 1.5 7.75 755.63
Along Toe Walls 2 11.5 1.5 4.75 163.88
RD: 27+625 Side Walls 2 32.5 1.5 7.75 755.63
Along Toe Walls 2 11.5 1.5 4.75 163.88
RD: 29+400 Side Walls 2 32.5 1.5 7.75 755.63
Along Toe Walls 2 11.5 1.5 4.75 163.88
RD: 29+800 Side Walls 2 32.5 1.5 7.75 755.63
Along Toe Walls 2 11.5 1.5 4.75 163.88
RD: 31+545 Side Walls 2 32.5 1.5 7.75 755.63
Along Toe Walls 2 11.5 1.5 4.75 163.88
RD: 31+855 Side Walls 2 32.5 1.5 7.75 755.63
Along Toe Walls 2 11.5 1.5 4.75 163.88
RD: 36+090 Side Walls 2 32.5 1.5 7.75 755.63
Along Toe Walls 2 11.5 1.5 4.75 163.88
RD: 37+065 Side Walls 2 32.5 1.5 7.75 755.63
Along Toe Walls 2 11.5 1.5 4.75 163.88
RD: 39+100 Side Walls 2 32.5 1.5 7.75 755.63
Along Toe Walls 2 11.5 1.5 4.75 163.88
RD: 42+290 Side Walls 2 32.5 1.5 7.75 755.63
Along Toe Walls 2 11.5 1.5 4.75 163.88
RD: 53+325 Side Walls 2 32.5 1.5 7.75 755.63
Along Toe Walls 2 11.5 1.5 4.75 163.88
RD: 93+577 Side Walls 2 32.5 1.5 7.75 755.63
Along Toe Walls 2 11.5 1.5 4.75 163.88
RD: 94+097 Side Walls 2 32.5 1.5 7.75 755.63
Along Toe Walls 2 11.5 1.5 4.75 163.88
RD: 130+954 Side Walls 2 32.5 1.5 7.75 755.63
Along Toe Walls 2 11.5 1.5 4.75 163.88
RD: 131+319 Side Walls 2 32.5 1.5 7.75 755.63
Along Toe Walls 2 11.5 1.5 4.75 163.88
RD: 132+258 Side Walls 2 32.5 1.5 7.75 755.63
Along Toe Walls 2 11.5 1.5 4.75 163.88
RD: 138+965 Side Walls 2 32.5 1.5 7.75 755.63
Along Toe Walls 2 11.5 1.5 4.75 163.88
RD: 150+396 Side Walls 2 32.5 1.5 7.75 755.63
Along Toe Walls 2 11.5 1.5 4.75 163.88
RD: 155+907 Side Walls 2 32.5 1.5 7.75 755.63
Along Toe Walls 2 11.5 1.5 4.75 163.88
RD: 163+805 Side Walls 2 32.5 1.5 7.75 755.63
Along Toe Walls 2 11.5 1.5 4.75 163.88
RD: 171+412 Side Walls 2 32.5 1.5 7.75 755.63
Construction of Siran Right Bank Canal
District Mansehra
Drainage Culverts

BOQ Description Measurement


Item No. Sheet Reference
Along Toe Walls 2 11.5 1.5 4.75 163.88
Sewerage Nallah 86.56
Total Quantity (Cft) 22154.56
Total Quantity (CuM 627.35

D-7 Formation, dressing and preparing sub-grade On slope

Description No. Length Width Volume


(ft) (ft) (sft)

RD: 27+750 4 10.83 30 1299.60


RD: 25+070 4 10.83 30 1299.60
RD: 26+440 4 10.83 30 1299.60
RD: 26+950 4 10.83 30 1299.60
RD: 27+625 4 10.83 30 1299.60
RD: 29+400 4 10.83 30 1299.60
RD: 29+800 4 10.83 30 1299.60
RD: 31+545 4 10.83 30 1299.60
RD: 31+855 4 10.83 30 1299.60
RD: 36+090 4 10.83 30 1299.60
RD: 37+065 4 10.83 30 1299.60
RD: 39+100 4 10.83 30 1299.60
RD: 42+290 4 10.83 30 1299.60
RD: 53+325 4 10.83 30 1299.60
RD: 93+577 4 10.83 30 1299.60
RD: 94+097 4 10.83 30 1299.60
RD: 130+954 4 10.83 30 1299.60
RD: 131+319 4 10.83 30 1299.60
RD: 132+258 4 10.83 30 1299.60
RD: 138+965 4 10.83 30 1299.60
RD: 150+396 4 10.83 30 1299.60
RD: 155+907 4 10.83 30 1299.60
RD: 163+805 4 10.83 30 1299.60
RD: 171+412 4 10.83 30 1299.60
Total Quantity (Sft) 31190.40
Total Quantity (Sq.M) 2902.78

D-8 Formation, dressing and preparing sub-grade In bed

Description No. Length Width Volume


(ft) (ft) (sft)

RD: 27+750 2 10 30 600.00


RD: 25+070 2 10 30 600.00
Construction of Siran Right Bank Canal
District Mansehra
Drainage Culverts

BOQ Description Measurement


Item No. Sheet Reference
RD: 26+440 2 10 30 600.00
RD: 26+950 2 10 30 600.00
RD: 27+625 2 10 30 600.00
RD: 29+400 2 10 30 600.00
RD: 29+800 2 10 30 600.00
RD: 31+545 2 10 30 600.00
RD: 31+855 2 10 30 600.00
RD: 36+090 2 10 30 600.00
RD: 37+065 2 10 30 600.00
RD: 39+100 2 10 30 600.00
RD: 42+290 2 10 30 600.00
RD: 53+325 2 10 30 600.00
RD: 93+577 2 10 30 600.00
RD: 94+097 2 10 30 600.00
RD: 130+954 2 10 30 600.00
RD: 131+319 2 10 30 600.00
RD: 132+258 2 10 30 600.00
RD: 138+965 2 10 30 600.00
RD: 150+396 2 10 30 600.00
RD: 155+907 2 10 30 600.00
RD: 163+805 2 10 30 600.00
RD: 171+412 2 10 30 600.00
Total Quantity (Sft) 14400.00
Total Quantity (Sq.M) 1340.16
Construction of Siran Right Bank Canal
District Mansehra
Drainage Culverts

BOQ Description Measurement


Item No. Sheet Reference

D-9 Providing and Laying stone pitching for top layer only : On Slope

Description No. Length Width Depth Volume


(ft) (ft) (ft) (sft)

RD: 27+750 4 10.83 30 1 1299.60


RD: 25+070 4 10.83 30 1 1299.60
RD: 26+440 4 10.83 30 1 1299.60
RD: 26+950 4 10.83 30 1 1299.60
RD: 27+625 4 10.83 30 1 1299.60
RD: 29+400 4 10.83 30 1 1299.60
RD: 29+800 4 10.83 30 1 1299.60
RD: 31+545 4 10.83 30 1 1299.60
RD: 31+855 4 10.83 30 1 1299.60
RD: 36+090 4 10.83 30 1 1299.60
RD: 37+065 4 10.83 30 1 1299.60
RD: 39+100 4 10.83 30 1 1299.60
RD: 42+290 4 10.83 30 1 1299.60
RD: 53+325 4 10.83 30 1 1299.60
RD: 93+577 4 10.83 30 1 1299.60
RD: 94+097 4 10.83 30 1 1299.60
RD: 130+954 4 10.83 30 1 1299.60
RD: 131+319 4 10.83 30 1 1299.60
RD: 132+258 4 10.83 30 1 1299.60
RD: 138+965 4 10.83 30 1 1299.60
RD: 150+396 4 10.83 30 1 1299.60
RD: 155+907 4 10.83 30 1 1299.60
RD: 163+805 4 10.83 30 1 1299.60
RD: 171+412 4 10.83 30 1 1299.60
Total Quantity (Cft) 31190.40
Total Quantity (Cu.M) 883.21
D-10 Providing and Laying stone pitching for top layer only : On level

Description No. Length Width Depth Volume


(ft) (ft) (ft) (sft)

RD: 27+750 2 10 30 2 1200.00


RD: 25+070 2 10 30 2 1200.00
RD: 26+440 2 10 30 2 1200.00
RD: 26+950 2 10 30 2 1200.00
RD: 27+625 2 10 30 2 1200.00
RD: 29+400 2 10 30 2 1200.00
Construction of Siran Right Bank Canal
District Mansehra
Drainage Culverts

BOQ Description Measurement


Item No. Sheet Reference
RD: 29+800 2 10 30 2 1200.00
RD: 31+545 2 10 30 2 1200.00
RD: 31+855 2 10 30 2 1200.00
RD: 36+090 2 10 30 2 1200.00
RD: 37+065 2 10 30 2 1200.00
RD: 39+100 2 10 30 2 1200.00
RD: 42+290 2 10 30 2 1200.00
RD: 53+325 2 10 30 2 1200.00
RD: 93+577 2 10 30 2 1200.00
RD: 94+097 2 10 30 2 1200.00
RD: 130+954 2 10 30 2 1200.00
RD: 131+319 2 10 30 2 1200.00
RD: 132+258 2 10 30 2 1200.00
RD: 138+965 2 10 30 2 1200.00
RD: 150+396 2 10 30 2 1200.00
RD: 155+907 2 10 30 2 1200.00
RD: 163+805 2 10 30 2 1200.00
RD: 171+412 2 10 30 2 1200.00
Total Quantity (Cft) 28800.00
Total Quantity (Cu.M) 815.52

D-11 Plain Cement Concrete including placing, compacting, finishing & curing (Ratio
1:3:6)

PCC Profiles (9"x12") @ 10' C/C


Horizontal Band (18" x 6") on Top

Description No. Length Width Depth Volume


(ft) (ft) (ft) (sft)

RD: 27+750 Profiles 12 10.83 0.75 1 97.47


Horizontal PCC Band 4 30 1.5 0.5 90.00
RD: 25+070 Profiles 12 10.83 0.75 1 97.47
Horizontal PCC Band 4 30 1.5 0.5 90.00
RD: 26+440 Profiles 12 10.83 0.75 1 97.47
Horizontal PCC Band 4 30 1.5 0.5 90.00
RD: 26+950 Profiles 12 10.83 0.75 1 97.47
Horizontal PCC Band 4 30 1.5 0.5 90.00
RD: 27+625 Profiles 12 10.83 0.75 1 97.47
Horizontal PCC Band 4 30 1.5 0.5 90.00
RD: 29+400 Profiles 12 10.83 0.75 1 97.47
Construction of Siran Right Bank Canal
District Mansehra
Drainage Culverts

BOQ Description Measurement


Item No. Sheet Reference
Horizontal PCC Band 4 30 1.5 0.5 90.00
RD: 29+800 Profiles 12 10.83 0.75 1 97.47
Horizontal PCC Band 4 30 1.5 0.5 90.00
RD: 31+545 Profiles 12 10.83 0.75 1 97.47
Horizontal PCC Band 4 30 1.5 0.5 90.00
RD: 31+855 Profiles 12 10.83 0.75 1 97.47
Horizontal PCC Band 4 30 1.5 0.5 90.00
RD: 36+090 Profiles 12 10.83 0.75 1 97.47
Horizontal PCC Band 4 30 1.5 0.5 90.00
RD: 37+065 Profiles 12 10.83 0.75 1 97.47
Horizontal PCC Band 4 30 1.5 0.5 90.00
RD: 39+100 Profiles 12 10.83 0.75 1 97.47
Horizontal PCC Band 4 30 1.5 0.5 90.00
RD: 42+290 Profiles 12 10.83 0.75 1 97.47
Horizontal PCC Band 4 30 1.5 0.5 90.00
RD: 53+325 Profiles 12 10.83 0.75 1 97.47
Horizontal PCC Band 4 30 1.5 0.5 90.00
RD: 93+577 Profiles 12 10.83 0.75 1 97.47
Horizontal PCC Band 4 30 1.5 0.5 90.00
RD: 94+097 Profiles 12 10.83 0.75 1 97.47
Horizontal PCC Band 4 30 1.5 0.5 90.00
RD: 130+954 Profiles 12 10.83 0.75 1 97.47
Horizontal PCC Band 4 30 1.5 0.5 90.00
RD: 131+319 Profiles 12 10.83 0.75 1 97.47
Horizontal PCC Band 4 30 1.5 0.5 90.00
RD: 132+258 Profiles 12 10.83 0.75 1 97.47
Horizontal PCC Band 4 30 1.5 0.5 90.00
RD: 138+965 Profiles 12 10.83 0.75 1 97.47
Horizontal PCC Band 4 30 1.5 0.5 90.00
RD: 150+396 Profiles 12 10.83 0.75 1 97.47
Horizontal PCC Band 4 30 1.5 0.5 90.00
RD: 155+907 Profiles 12 10.83 0.75 1 97.47
Horizontal PCC Band 4 30 1.5 0.5 90.00
RD: 163+805 Profiles 12 10.83 0.75 1 97.47
Horizontal PCC Band 4 30 1.5 0.5 90.00
RD: 171+412 Profiles 12 10.83 0.75 1 97.47
Horizontal PCC Band 4 30 1.5 0.5 90.00
Total Quantity (Cft) 4499.28
Total Quantity (Cu.M) 127.41

D-12 PCC 1:3:6 in mass concrete less formwork using 40% boulders
Construction of Siran Right Bank Canal
District Mansehra
Drainage Culverts

BOQ Description Measurement


Item No. Sheet Reference
Description No. Length Width Depth Volume
(ft) (ft) (ft) (sft)

RD: 27+750 Toe Walls 4 30 1.5 3 540.00


End Toe Walls 2 10 1.5 3 90.00
RD: 25+070 Toe Walls 4 30 1.5 3 540.00
End Toe Walls 2 10 1.5 3 90.00
RD: 26+440 Toe Walls 4 30 1.5 3 540.00
End Toe Walls 2 10 1.5 3 90.00
RD: 26+950 Toe Walls 4 30 1.5 3 540.00
End Toe Walls 2 10 1.5 3 90.00
RD: 27+625 Toe Walls 4 30 1.5 3 540.00
End Toe Walls 2 10 1.5 3 90.00
RD: 29+400 Toe Walls 4 30 1.5 3 540.00
End Toe Walls 2 10 1.5 3 90.00
RD: 29+800 Toe Walls 4 30 1.5 3 540.00
End Toe Walls 2 10 1.5 3 90.00
RD: 31+545 Toe Walls 4 30 1.5 3 540.00
End Toe Walls 2 10 1.5 3 90.00
RD: 31+855 Toe Walls 4 30 1.5 3 540.00
End Toe Walls 2 10 1.5 3 90.00
RD: 36+090 Toe Walls 4 30 1.5 3 540.00
End Toe Walls 2 10 1.5 3 90.00
RD: 37+065 Toe Walls 4 30 1.5 3 540.00
End Toe Walls 2 10 1.5 3 90.00
RD: 39+100 Toe Walls 4 30 1.5 3 540.00
End Toe Walls 2 10 1.5 3 90.00
RD: 42+290 Toe Walls 4 30 1.5 3 540.00
End Toe Walls 2 10 1.5 3 90.00
RD: 53+325 Toe Walls 4 30 1.5 3 540.00
End Toe Walls 2 10 1.5 3 90.00
RD: 93+577 Toe Walls 4 30 1.5 3 540.00
End Toe Walls 2 10 1.5 3 90.00
RD: 94+097 Toe Walls 4 30 1.5 3 540.00
End Toe Walls 2 10 1.5 3 90.00
RD: 130+954 Toe Walls 4 30 1.5 3 540.00
End Toe Walls 2 10 1.5 3 90.00
RD: 131+319 Toe Walls 4 30 1.5 3 540.00
End Toe Walls 2 10 1.5 3 90.00
RD: 132+258 Toe Walls 4 30 1.5 3 540.00
End Toe Walls 2 10 1.5 3 90.00
RD: 138+965 Toe Walls 4 30 1.5 3 540.00
End Toe Walls 2 10 1.5 3 90.00
Construction of Siran Right Bank Canal
District Mansehra
Drainage Culverts

BOQ Description Measurement


Item No. Sheet Reference
RD: 150+396 Toe Walls 4 30 1.5 3 540.00
End Toe Walls 2 10 1.5 3 90.00
RD: 155+907 Toe Walls 4 30 1.5 3 540.00
End Toe Walls 2 10 1.5 3 90.00
RD: 163+805 Toe Walls 4 30 1.5 3 540.00
End Toe Walls 2 10 1.5 3 90.00
RD: 171+412 Toe Walls 4 30 1.5 3 540.00
End Toe Walls 2 10 1.5 3 90.00
Total Quantity (Cft) 15120.00
Total Quantity (Cu.M) 428.15

D-12 Erecting & removing formwork to concrete in any shape / position (Vertical)

Description No. Length Depth Volume


(ft) (ft) (sft)

RD: 27+750 Toe Walls 8 30 3 720.00


End Toe Walls 4 10 3 120.00
Profiles 24 10.83 1 259.92
Horizontal Band 8 30 0.5 120.00
RD: 25+070 Toe Walls 8 30 3 720.00
End Toe Walls 4 10 3 120.00
Profiles 24 10.83 1 259.92
Horizontal Band 8 30 0.5 120.00
RD: 26+440 Toe Walls 8 30 3 720.00
End Toe Walls 4 10 3 120.00
Profiles 24 10.83 1 259.92
Horizontal Band 8 30 0.5 120.00
RD: 26+950 Toe Walls 8 30 3 720.00
End Toe Walls 4 10 3 120.00
Profiles 24 10.83 1 259.92
Horizontal Band 8 30 0.5 120.00
RD: 27+625 Toe Walls 8 30 3 720.00
End Toe Walls 4 10 3 120.00
Profiles 24 10.83 1 259.92
Horizontal Band 8 30 0.5 120.00
RD: 29+400 Toe Walls 8 30 3 720.00
End Toe Walls 4 10 3 120.00
Profiles 24 10.83 1 259.92
Horizontal Band 8 30 0.5 120.00
RD: 29+800 Toe Walls 8 30 3 720.00
Construction of Siran Right Bank Canal
District Mansehra
Drainage Culverts

BOQ Description Measurement


Item No. Sheet Reference
End Toe Walls 4 10 3 120.00
Profiles 24 10.83 1 259.92
Horizontal Band 8 30 0.5 120.00
RD: 31+545 Toe Walls 8 30 3 720.00
End Toe Walls 4 10 3 120.00
Profiles 24 10.83 1 259.92
Horizontal Band 8 30 0.5 120.00
RD: 31+855 Toe Walls 8 30 3 720.00
End Toe Walls 4 10 3 120.00
Profiles 24 10.83 1 259.92
Horizontal Band 8 30 0.5 120.00
RD: 36+090 Toe Walls 8 30 3 720.00
End Toe Walls 4 10 3 120.00
Profiles 24 10.83 1 259.92
Horizontal Band 8 30 0.5 120.00
RD: 37+065 Toe Walls 8 30 3 720.00
End Toe Walls 4 10 3 120.00
Profiles 24 10.83 1 259.92
Horizontal Band 8 30 0.5 120.00
RD: 39+100 Toe Walls 8 30 3 720.00
End Toe Walls 4 10 3 120.00
Profiles 24 10.83 1 259.92
Horizontal Band 8 30 0.5 120.00
RD: 42+290 Toe Walls 8 30 3 720.00
End Toe Walls 4 10 3 120.00
Profiles 24 10.83 1 259.92
Horizontal Band 8 30 0.5 120.00
RD: 53+325 Toe Walls 8 30 3 720.00
End Toe Walls 4 10 3 120.00
Profiles 24 10.83 1 259.92
Horizontal Band 8 30 0.5 120.00
RD: 93+577 Toe Walls 8 30 3 720.00
End Toe Walls 4 10 3 120.00
Profiles 24 10.83 1 259.92
Horizontal Band 8 30 0.5 120.00
RD: 94+097 Toe Walls 8 30 3 720.00
End Toe Walls 4 10 3 120.00
Profiles 24 10.83 1 259.92
Horizontal Band 8 30 0.5 120.00
RD: 130+954 Toe Walls 8 30 3 720.00
End Toe Walls 4 10 3 120.00
Profiles 24 10.83 1 259.92
Construction of Siran Right Bank Canal
District Mansehra
Drainage Culverts

BOQ Description Measurement


Item No. Sheet Reference
Horizontal Band 8 30 0.5 120.00
RD: 131+319 Toe Walls 8 30 3 720.00
End Toe Walls 4 10 3 120.00
Profiles 24 10.83 1 259.92
Horizontal Band 8 30 0.5 120.00
RD: 132+258 Toe Walls 8 30 3 720.00
End Toe Walls 4 10 3 120.00
Profiles 24 10.83 1 259.92
Horizontal Band 8 30 0.5 120.00
RD: 138+965 Toe Walls 8 30 3 720.00
End Toe Walls 4 10 3 120.00
Profiles 24 10.83 1 259.92
Horizontal Band 8 30 0.5 120.00
RD: 150+396 Toe Walls 8 30 3 720.00
End Toe Walls 4 10 3 120.00
Profiles 24 10.83 1 259.92
Horizontal Band 8 30 0.5 120.00
RD: 155+907 Toe Walls 8 30 3 720.00
End Toe Walls 4 10 3 120.00
Profiles 24 10.83 1 259.92
Horizontal Band 8 30 0.5 120.00
RD: 163+805 Toe Walls 8 30 3 720.00
End Toe Walls 4 10 3 120.00
Profiles 24 10.83 1 259.92
Horizontal Band 8 30 0.5 120.00
RD: 171+412 Toe Walls 8 30 3 720.00
End Toe Walls 4 10 3 120.00
Profiles 24 10.83 1 259.92
Horizontal Band 8 30 0.5 120.00
Total Quantity (Sft) 29278.08
Total Quantity (Sqm) 2724.81
Construction of Siran Right Bank Canal
District Mansehra
Road Culverts

BOQ
Description
Item No.
E-1 Structural Excavation in Common Material

Description No. Length Width Depth Volume (cft)


(ft) (ft) (ft)

RD: 5+000 1 12.25 19 7.666 1784.26


RD: 6+000 1 12.25 19 7.666 1784.26
RD: 7+000 1 12.25 19 7.666 1784.26
RD: 8+000 1 12.25 19 7.666 1784.26
RD: 28+000 1 12.25 19 7.666 1784.26
RD: 30+650 1 12.1 19 7.666 1762.41
RD: 31+855 1 12.1 19 7.666 1762.41
RD: 100+116 1 10.5 19 7.166 1429.62
RD: 152+476 1 9.8 19 7.166 1334.31
RD: 153+283 1 9.8 19 7.166 1334.31
RD: 163+260 1 9.2 19 7.166 1252.62
RD: 165+245 1 9.2 19 7.166 1252.62
RD: 165+733 1 9.2 19 7.166 1252.62
RD: 181+501 1 7.5 19 7.166 1021.16
RD: 184+681 1 7.2 19 7.166 980.31
Total Quantity (Cft) 22303.68
Total Quantity (CuM 631.57

Plain Cement Concrete including placing, compacting, finishing & curing


E-2
(Ratio 1:4:8)
Description No. Length Width Depth Volume (cft)
(ft) (ft) (ft)

RD: 5+000 1 9.25 16 0.333 49.28


RD: 6+000 1 9.25 16 0.333 49.28
RD: 7+000 1 9.25 16 0.333 49.28
RD: 8+000 1 9.25 16 0.333 49.28
RD: 28+000 1 9.25 16 0.333 49.28
Construction of Siran Right Bank Canal
District Mansehra
Road Culverts

BOQ
Description
Item No.
RD: 30+650 1 9.1 16 0.333 48.48
RD: 31+855 1 9.1 16 0.333 48.48
RD: 100+116 1 7.5 16 0.333 39.96
RD: 152+476 1 6.8 16 0.333 36.23
RD: 153+283 1 6.8 16 0.333 36.23
RD: 163+260 1 6.2 16 0.333 33.03
RD: 165+245 1 6.2 16 0.333 33.03
RD: 165+733 1 6.2 16 0.333 33.03
RD: 181+501 1 4.5 16 0.333 23.98
RD: 184+681 1 4.2 16 0.333 22.38
Total Quantity (Cft) 601.26
Total Quantity (CuM) 17.03

RCC in raft foundation slab, base slab of column & ret. wall etc, not including in 06-
E-3
06. Type C(1:2:4)
Description No. Length Width Depth Volume (cft)
(ft) (ft) (ft)

RD: 5+000 Base 1 8.75 16 1.5 210.00


Sides 2 16 1 4.5 144.00
RD: 6+000 Base 1 8.75 16 1.5 210.00
Sides 2 16 1 4.5 144.00
RD: 7+000 Base 1 8.75 16 1.5 210.00
Sides 2 16 1 4.5 144.00
RD: 8+000 Base 1 8.75 16 1.5 210.00
Sides 2 16 1 4.5 144.00
RD: 28+000 Base 1 8.75 16 1.5 210.00
Sides 2 16 1 4.5 144.00
RD: 30+650 Base 1 8.6 16 1.5 206.40
Sides 2 16 1 4.5 144.00
RD: 31+855 Base 1 8.6 16 1.5 206.40
Construction of Siran Right Bank Canal
District Mansehra
Road Culverts

BOQ
Description
Item No.
Sides 2 16 1 4.5 144.00
RD: 100+116 Base 1 7 16 1.5 168.00
Sides 2 16 1 4 128.00
RD: 152+476 Base 1 6.3 16 1.5 151.20
Sides 2 16 1 4 128.00
RD: 153+283 Base 1 6.3 16 1.5 151.20
Sides 2 16 1 4 128.00
RD: 163+260 Base 1 5.7 16 1.5 136.80
Sides 2 16 1 4 128.00
RD: 165+245 Base 1 5.7 16 1.5 136.80
Sides 2 16 1 4 128.00
RD: 165+733 Base 1 5.7 16 1.5 136.80
Sides 2 16 1 4 128.00
RD: 181+501 Base 1 4 16 1.5 96.00
Sides 2 16 1 4 128.00
RD: 184+681 Base 1 3.7 16 1.5 88.80
Sides 2 16 1 4 128.00
Total Quantity (Cft) 4560.40
Total Quantity (CuM) 129.14

RCC in roof slab, beam, column & other structural members, insitu or precast. Type
E-4
C (1:2:4)
Description No. Length Width Depth Volume (cft)
(ft) (ft) (ft)

RD: 5+000 Base 1 8.75 16 1.333 186.62


Parapet 2 8.75 0.5 2 17.50
RD: 6+000 Base 1 8.6 16 1.333 183.42
Parapet 2 8.75 0.5 2 17.50
RD: 7+000 Base 1 8.6 16 1.333 183.42
Parapet 2 8.75 0.5 2 17.50
RD: 8+000 Base 1 7 16 1.333 149.30
Construction of Siran Right Bank Canal
District Mansehra
Road Culverts

BOQ
Description
Item No.
` Parapet 2 8.75 0.5 2 17.50
RD: 28+000 Top Slab 1 8.75 16 1.333 186.62
Parapet 2 8.75 0.5 2 17.50
RD: 30+650 Top Slab 1 8.6 16 1.333 183.42
Parapet 2 8.6 0.5 2 17.20
RD: 31+855 Top Slab 1 8.6 16 1.333 183.42
Parapet 2 8.6 0.5 2 17.20
RD: 100+116 Top Slab 1 7 16 1.333 149.30
Parapet 2 7 0.5 2 14.00
RD: 152+476 Top Slab 1 6.3 16 1.333 134.37
Parapet 2 6.3 0.5 2 12.60
RD: 153+283 Top Slab 1 6.3 16 1.333 134.37
Parapet 2 6.3 0.5 2 12.60
RD: 163+260 Top Slab 1 5.7 16 1.333 121.57
Parapet 2 5.7 0.5 2 11.40
RD: 165+245 Top Slab 1 5.7 16 1.333 121.57
Parapet 2 5.7 0.5 2 11.40
RD: 165+733 Top Slab 1 5.7 16 1.333 121.57
Parapet 2 5.7 0.5 2 11.40
RD: 181+501 Top Slab 1 4 16 1.333 85.31
Parapet 2 4 0.5 2 8.00
RD: 184+681 Top Slab 1 3.7 16 1.333 78.91
Parapet 2 3.7 0.5 2 7.40
Total Quantity (Cft) 2413.88
Total Quantity (CuM 68.35

Supply & fabricate M.S. reinforcement for cement concrete (Hot rolled deformed
E-5 bars Grade 40).

Taking 2.00% of RCC Volume as per Item E-3 & E-4


Concrete Quantity = 4560.40 + 2413.882 = 6974.28 cft
Steel Quantity = 6974.28 x 1.75% x 490 = 59804.4716 lbs
Construction of Siran Right Bank Canal
District Mansehra
Road Culverts

BOQ
Description
Item No.
OR 27.13 tonnes

Plain Cement Concrete including placing, compacting,finishing & curing (Ratio


E-6
1:2:4)

Description No. Length Width Depth Volume (cft)


(ft) (ft) (ft)

RD: 5+000 1 8.75 15 7.583 995.27


RD: 6+000 1 8.6 15 0.25 32.25
RD: 7+000 1 8.75 15 7.583 995.27
RD: 8+000 1 8.6 15 0.25 32.25
RD: 28+000 1 8.75 15 7.583 995.27
RD: 30+650 1 8.6 15 0.25 32.25
RD: 31+855 1 8.6 15 0.25 32.25
RD: 100+116 1 7 15 0.25 26.25
RD: 152+476 1 6.3 15 0.25 23.63
RD: 153+283 1 6.3 15 0.25 23.63
RD: 163+260 1 5.7 15 0.25 21.38
RD: 165+245 1 5.7 15 0.25 21.38
RD: 165+733 1 5.7 15 0.25 21.38
RD: 181+501 1 4 15 0.25 15.00
RD: 184+681 1 3.7 15 0.25 13.88
Total Quantity (Cft) 3281.31
Total Quantity (CuM 92.92

E-7 Structural backfill using Common Material available at site

Description No. Length Width Depth Volume (cft)


(ft) (ft) (ft)

RD: 5+000 2 16 1.5 7.666 367.97


RD: 6+000 2 16 1.5 7.666 367.97
Construction of Siran Right Bank Canal
District Mansehra
Road Culverts

BOQ
Description
Item No.
RD: 7+000 2 16 1.5 7.666 367.97
RD: 8+000 2 16 1.5 7.666 367.97
RD: 28+000 2 16 1.5 7.666 367.97
RD: 30+650 2 16 1.5 7.666 367.97
RD: 31+855 2 16 1.5 7.666 367.97
RD: 100+116 2 16 1.5 7.166 343.97
RD: 152+476 2 16 1.5 7.166 343.97
RD: 153+283 2 16 1.5 7.166 343.97
RD: 163+260 2 16 1.5 7.166 343.97
RD: 165+245 2 16 1.5 7.166 343.97
RD: 165+733 2 16 1.5 7.166 343.97
RD: 181+501 2 16 1.5 7.166 343.97
RD: 184+681 2 16 1.5 7.166 343.97
Total Quantity (Cft) 5327.52
Total Quantity (CuM 150.86
Construction of Siran Right Bank Canal
District Mansehra
Pipe Outlets

BOQ Description
Item No.

F-1 Structural Excavation in Common Material


Outlet No. Pipe dia Length Width Depth Volume
Main canal Outlet-1 0.625 20.00 4.625 3.000 277.500
Outlet-2 0.417 20.00 4.417 3.000 265.000
Outlet-3 0.375 20.00 4.375 3.000 262.500
Outlet-4 0.667 20.00 4.667 3.000 280.000
Outlet-5 0.417 20.00 4.417 3.000 265.000
Outlet-6 0.542 20.00 4.542 3.000 272.500
Outlet-7 0.542 20.00 4.542 3.000 272.500
Outlet-8 0.708 20.00 4.708 3.000 282.500
Outlet-9 0.583 20.00 4.583 3.000 275.000
Outlet-10 0.542 20.00 4.542 3.000 272.500
Outlet-11 0.500 20.00 4.500 3.000 270.000
Outlet-12 0.417 20.00 4.417 3.000 265.000
Outlet-13 0.500 20.00 4.500 3.000 270.000
Outlet-14 0.333 20.00 4.333 3.000 260.000
Outlet-15 0.417 20.00 4.417 3.000 265.000
Outlet-16 0.458 20.00 4.458 3.000 267.500
Outlet-17 0.542 20.00 4.542 3.000 272.500
Outlet-18 0.625 20.00 4.625 3.000 277.500
Outlet-19 0.667 20.00 4.667 3.000 280.000
Outlet-20 0.583 20.00 4.583 3.000 275.000
Outlet-21 0.875 20.00 4.875 3.000 292.500
Outlet-22 0.625 20.00 4.625 3.000 277.500
Outlet-23 0.542 20.00 4.542 3.000 272.500
Outlet-24 0.500 20.00 4.500 3.000 270.000
Outlet-25 0.458 20.00 4.458 3.000 267.500
Outlet-26 0.333 20.00 4.333 3.000 260.000
Outlet-27 0.792 20.00 4.792 3.000 287.500
Outlet-28 0.583 20.00 4.583 3.000 275.000
Outlet-29 0.667 20.00 4.667 3.000 280.000
Outlet-30 0.417 20.00 4.417 3.000 265.000
Outlet-31 0.667 20.00 4.667 3.000 280.000
Outlet-32 0.292 20.00 4.292 3.000 257.500
Outlet-33 0.667 20.00 4.667 3.000 280.000
Outlet-34 0.500 20.00 4.500 3.000 270.000
Outlet-35 0.792 20.00 4.792 3.000 287.500
Outlet-36 0.625 20.00 4.625 3.000 277.500
Outlet-37 0.542 20.00 4.542 3.000 272.500
Outlet-38 0.625 20.00 4.625 3.000 277.500
Outlet-39 0.625 20.00 4.625 3.000 277.500
Outlet-40 0.625 20.00 4.625 3.000 277.500
Outlet-41 0.583 20.00 4.583 3.000 275.000
Outlet-42 0.667 20.00 4.667 3.000 280.000
Outlet-43 0.583 20.00 4.583 3.000 275.000
Outlet-44 0.667 20.00 4.667 3.000 280.000
Outlet-45 0.583 20.00 4.583 3.000 275.000
Outlet-46 0.583 20.00 4.583 3.000 275.000
Outlet-47 0.625 20.00 4.625 3.000 277.500
Outlet-48 0.583 20.00 4.583 3.000 275.000
Outlet-49 0.667 20.00 4.667 3.000 280.000
Outlet-50 0.625 20.00 4.625 3.000 277.500
Outlet-51 0.667 20.00 4.667 3.000 280.000
Outlet-52 0.458 20.00 4.458 3.000 267.500
Outlet-53 0.542 20.00 4.542 3.000 272.500
Outlet-54 0.833 20.00 4.833 3.000 290.000
Outlet-55 0.583 20.00 4.583 3.000 275.000
Minor Canal Outlet-1 0.917 20.00 4.917 3.000 295.000
Outlet-2 0.875 20.00 4.875 3.000 292.500
Outlet-3 0.875 20.00 4.875 3.000 292.500
Outlet-4 0.875 20.00 4.875 3.000 292.500
Outlet-5 0.792 20.00 4.792 3.000 287.500
Outlet-6 0.875 20.00 4.875 3.000 292.500
Excavation in pipe outlets 16840.000 Cub. ft.
OR 476.784 Cub. M.

Plain Cement Concrete including placing, compacting, finishing & curing (Ratio
F-2
1:4:8)

Outlet No. Pipe dia Length Width Depth Volume


Main canal Outlet-1 0.625 20.00 2.125 0.250 10.625
Outlet-2 0.417 20.00 1.917 0.250 9.583
Outlet-3 0.375 20.00 1.875 0.250 9.375
Outlet-4 0.667 20.00 2.167 0.250 10.833
Outlet-5 0.417 20.00 1.917 0.250 9.583
Outlet-6 0.542 20.00 2.042 0.250 10.208
Outlet-7 0.542 20.00 2.042 0.250 10.208
Outlet-8 0.708 20.00 2.208 0.250 11.042
Outlet-9 0.583 20.00 2.083 0.250 10.417
Outlet-10 0.542 20.00 2.042 0.250 10.208
Outlet-11 0.500 20.00 2.000 0.250 10.000
Outlet-12 0.417 20.00 1.917 0.250 9.583
Outlet-13 0.500 20.00 2.000 0.250 10.000
Outlet-14 0.333 20.00 1.833 0.250 9.167
Outlet-15 0.417 20.00 1.917 0.250 9.583
Outlet-16 0.458 20.00 1.958 0.250 9.792
Outlet-17 0.542 20.00 2.042 0.250 10.208
Outlet-18 0.625 20.00 2.125 0.250 10.625
Outlet-19 0.667 20.00 2.167 0.250 10.833
Outlet-20 0.583 20.00 2.083 0.250 10.417
Outlet-21 0.875 20.00 2.375 0.250 11.875
Outlet-22 0.625 20.00 2.125 0.250 10.625
Outlet-23 0.542 20.00 2.042 0.250 10.208
Outlet-24 0.500 20.00 2.000 0.250 10.000
Outlet-25 0.458 20.00 1.958 0.250 9.792
Outlet-26 0.333 20.00 1.833 0.250 9.167
Outlet-27 0.792 20.00 2.292 0.250 11.458
Outlet-28 0.583 20.00 2.083 0.250 10.417
Outlet-29 0.667 20.00 2.167 0.250 10.833
Outlet-30 0.417 20.00 1.917 0.250 9.583
Outlet-31 0.667 20.00 2.167 0.250 10.833
Outlet-32 0.292 20.00 1.792 0.250 8.958
Outlet-33 0.667 20.00 2.167 0.250 10.833
Outlet-34 0.500 20.00 2.000 0.250 10.000
Outlet-35 0.792 20.00 2.292 0.250 11.458
Outlet-36 0.625 20.00 2.125 0.250 10.625
Outlet-37 0.542 20.00 2.042 0.250 10.208
Outlet-38 0.625 20.00 2.125 0.250 10.625
Outlet-39 0.625 20.00 2.125 0.250 10.625
Outlet-40 0.625 20.00 2.125 0.250 10.625
Outlet-41 0.583 20.00 2.083 0.250 10.417
Outlet-42 0.667 20.00 2.167 0.250 10.833
Outlet-43 0.583 20.00 2.083 0.250 10.417
Outlet-44 0.667 20.00 2.167 0.250 10.833
Outlet-45 0.583 20.00 2.083 0.250 10.417
Outlet-46 0.583 20.00 2.083 0.250 10.417
Outlet-47 0.625 20.00 2.125 0.250 10.625
Outlet-48 0.583 20.00 2.083 0.250 10.417
Outlet-49 0.667 20.00 2.167 0.250 10.833
Outlet-50 0.625 20.00 2.125 0.250 10.625
Outlet-51 0.667 20.00 2.167 0.250 10.833
Outlet-52 0.458 20.00 1.958 0.250 9.792
Outlet-53 0.542 20.00 2.042 0.250 10.208
Outlet-54 0.833 20.00 2.333 0.250 11.667
Outlet-55 0.583 20.00 2.083 0.250 10.417
Minor Canal Outlet-1 0.917 20.00 2.417 0.250 12.083
Outlet-2 0.875 20.00 2.375 0.250 11.875
Outlet-3 0.875 20.00 2.375 0.250 11.875
Outlet-4 0.875 20.00 2.375 0.250 11.875
Outlet-5 0.792 20.00 2.292 0.250 11.458
Outlet-6 0.875 20.00 2.375 0.250 11.875
PCC 1:4:8 below pipe encasement 640.833 Cub. ft.
OR 18.144 Cub. M.
RCC in raft foundation slab, base slab of column & ret. wall etc, not including in
F-3
06-06. Type C (1:2:4)

RCC in pipe encasement

Outlet No. Pipe dia Length Width Depth Area Volume

Main canal Outlet-1 0.625 20.000 1.625 1.625 2.334 46.680


Outlet-2 0.417 20.000 1.417 1.417 1.871 37.413
Outlet-3 0.375 20.000 1.375 1.375 1.780 35.605
Outlet-4 0.667 20.000 1.667 1.667 2.429 48.578
Outlet-5 0.417 20.000 1.417 1.417 1.871 37.413
Outlet-6 0.542 20.000 1.542 1.542 2.146 42.928
Outlet-7 0.542 20.000 1.542 1.542 2.146 42.928
Outlet-8 0.708 20.000 1.708 1.708 2.525 50.491
Outlet-9 0.583 20.000 1.583 1.583 2.240 44.797
Outlet-10 0.542 20.000 1.542 1.542 2.146 42.928
Outlet-11 0.500 20.000 1.500 1.500 2.054 41.075
Outlet-12 0.417 20.000 1.417 1.417 1.871 37.413
Outlet-13 0.500 20.000 1.500 1.500 2.054 41.075
Outlet-14 0.333 20.000 1.333 1.333 1.691 33.811
Outlet-15 0.417 20.000 1.417 1.417 1.871 37.413
Outlet-16 0.458 20.000 1.458 1.458 1.962 39.237
Outlet-17 0.542 20.000 1.542 1.542 2.146 42.928
Outlet-18 0.625 20.000 1.625 1.625 2.334 46.680
Outlet-19 0.667 20.000 1.667 1.667 2.429 48.578
Outlet-20 0.583 20.000 1.583 1.583 2.240 44.797
Outlet-21 0.875 20.000 1.875 1.875 2.915 58.292
Outlet-22 0.625 20.000 1.625 1.625 2.334 46.680
Outlet-23 0.542 20.000 1.542 1.542 2.146 42.928
Outlet-24 0.500 20.000 1.500 1.500 2.054 41.075
Outlet-25 0.458 20.000 1.458 1.458 1.962 39.237
Outlet-26 0.333 20.000 1.333 1.333 1.691 33.811
Outlet-27 0.792 20.000 1.792 1.792 2.718 54.362
Outlet-28 0.583 20.000 1.583 1.583 2.240 44.797
Outlet-29 0.667 20.000 1.667 1.667 2.429 48.578
Outlet-30 0.417 20.000 1.417 1.417 1.871 37.413
Outlet-31 0.667 20.000 1.667 1.667 2.429 48.578
Outlet-32 0.292 20.000 1.292 1.292 1.602 32.032
Outlet-33 0.667 20.000 1.667 1.667 2.429 48.578
Outlet-34 0.500 20.000 1.500 1.500 2.054 41.075
Outlet-35 0.792 20.000 1.792 1.792 2.718 54.362
Outlet-36 0.625 20.000 1.625 1.625 2.334 46.680
Outlet-37 0.542 20.000 1.542 1.542 2.146 42.928
Outlet-38 0.625 20.000 1.625 1.625 2.334 46.680
Outlet-39 0.625 20.000 1.625 1.625 2.334 46.680
Outlet-40 0.625 20.000 1.625 1.625 2.334 46.680
Outlet-41 0.583 20.000 1.583 1.583 2.240 44.797
Outlet-42 0.667 20.000 1.667 1.667 2.429 48.578
Outlet-43 0.583 20.000 1.583 1.583 2.240 44.797
Outlet-44 0.667 20.000 1.667 1.667 2.429 48.578
Outlet-45 0.583 20.000 1.583 1.583 2.240 44.797
Outlet-46 0.583 20.000 1.583 1.583 2.240 44.797
Outlet-47 0.625 20.000 1.625 1.625 2.334 46.680
Outlet-48 0.583 20.000 1.583 1.583 2.240 44.797
Outlet-49 0.667 20.000 1.667 1.667 2.429 48.578
Outlet-50 0.625 20.000 1.625 1.625 2.334 46.680
Outlet-51 0.667 20.000 1.667 1.667 2.429 48.578
Outlet-52 0.458 20.000 1.458 1.458 1.962 39.237
Outlet-53 0.542 20.000 1.542 1.542 2.146 42.928
Outlet-54 0.833 20.000 1.833 1.833 2.816 56.319
Outlet-55 0.583 20.000 1.583 1.583 2.240 44.797
Minor Canal Outlet-1 0.917 20.000 1.917 1.917 3.014 60.280
Outlet-2 0.875 20.000 1.875 1.875 2.915 58.292
Outlet-3 0.875 20.000 1.875 1.875 2.915 58.292
Outlet-4 0.875 20.000 1.875 1.875 2.915 58.292
Outlet-5 0.792 20.000 1.792 1.792 2.718 54.362
Outlet-6 0.875 20.000 1.875 1.875 2.915 58.292
RCC in pipe encasement 2786.955 Cub. ft.
OR 78.906 Cub. M.

RCC in chamber
Outlet No. Pipe dia Length Width Height Thickness Volume
Main canal Outlet-1 0.625 3.000 3.000 3.625 1.000 108.750
Outlet-2 0.417 3.000 3.000 3.417 1.000 102.500
Outlet-3 0.375 3.000 3.000 3.375 1.000 101.250
Outlet-4 0.667 3.000 3.000 3.667 1.000 110.000
Outlet-5 0.417 3.000 3.000 3.417 1.000 102.500
Outlet-6 0.542 3.000 3.000 3.542 1.000 106.250
Outlet-7 0.542 3.000 3.000 3.542 1.000 106.250
Outlet-8 0.708 3.000 3.000 3.708 1.000 111.250
Outlet-9 0.583 3.000 3.000 3.583 1.000 107.500
Outlet-10 0.542 3.000 3.000 3.542 1.000 106.250
Outlet-11 0.500 3.000 3.000 3.500 1.000 105.000
Outlet-12 0.417 3.000 3.000 3.417 1.000 102.500
Outlet-13 0.500 3.000 3.000 3.500 1.000 105.000
Outlet-14 0.333 3.000 3.000 3.333 1.000 100.000
Outlet-15 0.417 3.000 3.000 3.417 1.000 102.500
Outlet-16 0.458 3.000 3.000 3.458 1.000 103.750
Outlet-17 0.542 3.000 3.000 3.542 1.000 106.250
Outlet-18 0.625 3.000 3.000 3.625 1.000 108.750
Outlet-19 0.667 3.000 3.000 3.667 1.000 110.000
Outlet-20 0.583 3.000 3.000 3.583 1.000 107.500
Outlet-21 0.875 3.000 3.000 3.875 1.000 116.250
Outlet-22 0.625 3.000 3.000 3.625 1.000 108.750
Outlet-23 0.542 3.000 3.000 3.542 1.000 106.250
Outlet-24 0.500 3.000 3.000 3.500 1.000 105.000
Outlet-25 0.458 3.000 3.000 3.458 1.000 103.750
Outlet-26 0.333 3.000 3.000 3.333 1.000 100.000
Outlet-27 0.792 3.000 3.000 3.792 1.000 113.750
Outlet-28 0.583 3.000 3.000 3.583 1.000 107.500
Outlet-29 0.667 3.000 3.000 3.667 1.000 110.000
Outlet-30 0.417 3.000 3.000 3.417 1.000 102.500
Outlet-31 0.667 3.000 3.000 3.667 1.000 110.000
Outlet-32 0.292 3.000 3.000 3.292 1.000 98.750
Outlet-33 0.667 3.000 3.000 3.667 1.000 110.000
Outlet-34 0.500 3.000 3.000 3.500 1.000 105.000
Outlet-35 0.792 3.000 3.000 3.792 1.000 113.750
Outlet-36 0.625 3.000 3.000 3.625 1.000 108.750
Outlet-37 0.542 3.000 3.000 3.542 1.000 106.250
Outlet-38 0.625 3.000 3.000 3.625 1.000 108.750
Outlet-39 0.625 3.000 3.000 3.625 1.000 108.750
Outlet-40 0.625 3.000 3.000 3.625 1.000 108.750
Outlet-41 0.583 3.000 3.000 3.583 1.000 107.500
Outlet-42 0.667 3.000 3.000 3.667 1.000 110.000
Outlet-43 0.583 3.000 3.000 3.583 1.000 107.500
Outlet-44 0.667 3.000 3.000 3.667 1.000 110.000
Outlet-45 0.583 3.000 3.000 3.583 1.000 107.500
Outlet-46 0.583 3.000 3.000 3.583 1.000 107.500
Outlet-47 0.625 3.000 3.000 3.625 1.000 108.750
Outlet-48 0.583 3.000 3.000 3.583 1.000 107.500
Outlet-49 0.667 3.000 3.000 3.667 1.000 110.000
Outlet-50 0.625 3.000 3.000 3.625 1.000 108.750
Outlet-51 0.667 3.000 3.000 3.667 1.000 110.000
Outlet-52 0.458 3.000 3.000 3.458 1.000 103.750
Outlet-53 0.542 3.000 3.000 3.542 1.000 106.250
Outlet-54 0.833 3.000 3.000 3.833 1.000 115.000
Outlet-55 0.583 3.000 3.000 3.583 1.000 107.500
Minor Canal Outlet-1 0.917 3.000 3.000 3.917 1.000 117.500
Outlet-2 0.875 3.000 3.000 3.875 1.000 116.250
Outlet-3 0.875 3.000 3.000 3.875 1.000 116.250
Outlet-4 0.875 3.000 3.000 3.875 1.000 116.250
Outlet-5 0.792 3.000 3.000 3.792 1.000 113.750
Outlet-6 0.875 3.000 3.000 3.875 1.000 116.250
RCC in chamber 6590.000 Cub. ft.
OR 186.580 Cub. M.

Total RCC in encasement and chamber 9376.955 Cub. ft.


OR 265.486 Cub. M.

Supply & fabricate M.S. reinforcement for cement concrete (Hot rolled
F-4
deformed bars Grade 40).

Steel Quantity (Grade 40)


Total RCC quantity 265.49 cum
Take 2.00% of RCC quantity 41.688 tonnes

Supply and Fixing of GI Pipe as per required diameter on the direction of


F-5
Engineer Incharge

Total length of GI Pipes 1220.000


R. ft.

F-6 Structural backfill using Common Material available at site

Depth at
Outlet No. Pipe dia Length Width Depth at top Volume
sides
Main canal Outlet-1 0.625 20.00 1.500 3.000 2.000 194.000
Outlet-2 0.417 20.00 1.500 3.000 2.000 185.667
Outlet-3 0.375 20.00 1.500 3.000 2.000 184.000
Outlet-4 0.667 20.00 1.500 3.000 2.000 195.667
Outlet-5 0.417 20.00 1.500 3.000 2.000 185.667
Outlet-6 0.542 20.00 1.500 3.000 2.000 190.667
Outlet-7 0.542 20.00 1.500 3.000 2.000 190.667
Outlet-8 0.708 20.00 1.500 3.000 2.000 197.333
Outlet-9 0.583 20.00 1.500 3.000 2.000 192.333
Outlet-10 0.542 20.00 1.500 3.000 2.000 190.667
Outlet-11 0.500 20.00 1.500 3.000 2.000 189.000
Outlet-12 0.417 20.00 1.500 3.000 2.000 185.667
Outlet-13 0.500 20.00 1.500 3.000 2.000 189.000
Outlet-14 0.333 20.00 1.500 3.000 2.000 182.333
Outlet-15 0.417 20.00 1.500 3.000 2.000 185.667
Outlet-16 0.458 20.00 1.500 3.000 2.000 187.333
Outlet-17 0.542 20.00 1.500 3.000 2.000 190.667
Outlet-18 0.625 20.00 1.500 3.000 2.000 194.000
Outlet-19 0.667 20.00 1.500 3.000 2.000 195.667
Outlet-20 0.583 20.00 1.500 3.000 2.000 192.333
Outlet-21 0.875 20.00 1.500 3.000 2.000 204.000
Outlet-22 0.625 20.00 1.500 3.000 2.000 194.000
Outlet-23 0.542 20.00 1.500 3.000 2.000 190.667
Outlet-24 0.500 20.00 1.500 3.000 2.000 189.000
Outlet-25 0.458 20.00 1.500 3.000 2.000 187.333
Outlet-26 0.333 20.00 1.500 3.000 2.000 182.333
Outlet-27 0.792 20.00 1.500 3.000 2.000 200.667
Outlet-28 0.583 20.00 1.500 3.000 2.000 192.333
Outlet-29 0.667 20.00 1.500 3.000 2.000 195.667
Outlet-30 0.417 20.00 1.500 3.000 2.000 185.667
Outlet-31 0.667 20.00 1.500 3.000 2.000 195.667
Outlet-32 0.292 20.00 1.500 3.000 2.000 180.667
Outlet-33 0.667 20.00 1.500 3.000 2.000 195.667
Outlet-34 0.500 20.00 1.500 3.000 2.000 189.000
Outlet-35 0.792 20.00 1.500 3.000 2.000 200.667
Outlet-36 0.625 20.00 1.500 3.000 2.000 194.000
Outlet-37 0.542 20.00 1.500 3.000 2.000 190.667
Outlet-38 0.625 20.00 1.500 3.000 2.000 194.000
Outlet-39 0.625 20.00 1.500 3.000 2.000 194.000
Outlet-40 0.625 20.00 1.500 3.000 2.000 194.000
Outlet-41 0.583 20.00 1.500 3.000 2.000 192.333
Outlet-42 0.667 20.00 1.500 3.000 2.000 195.667
Outlet-43 0.583 20.00 1.500 3.000 2.000 192.333
Outlet-44 0.667 20.00 1.500 3.000 2.000 195.667
Outlet-45 0.583 20.00 1.500 3.000 2.000 192.333
Outlet-46 0.583 20.00 1.500 3.000 2.000 192.333
Outlet-47 0.625 20.00 1.500 3.000 2.000 194.000
Outlet-48 0.583 20.00 1.500 3.000 2.000 192.333
Outlet-49 0.667 20.00 1.500 3.000 2.000 195.667
Outlet-50 0.625 20.00 1.500 3.000 2.000 194.000
Outlet-51 0.667 20.00 1.500 3.000 2.000 195.667
Outlet-52 0.458 20.00 1.500 3.000 2.000 187.333
Outlet-53 0.542 20.00 1.500 3.000 2.000 190.667
Outlet-54 0.833 20.00 1.500 3.000 2.000 202.333
Outlet-55 0.583 20.00 1.500 3.000 2.000 192.333
Minor Canal Outlet-1 0.917 20.00 1.500 3.000 2.000 205.667
Outlet-2 0.875 20.00 1.500 3.000 2.000 204.000
Outlet-3 0.875 20.00 1.500 3.000 2.000 204.000
Outlet-4 0.875 20.00 1.500 3.000 2.000 204.000
Outlet-5 0.792 20.00 1.500 3.000 2.000 200.667
Outlet-6 0.875 20.00 1.500 3.000 2.000 204.000
Total backfill 11775.667 Cub. ft.
OR 333.399 Cub. M.
Construction of Siran Right Bank Canal
District Mansehra
Head Regulator (Minor Canal)

BOQ
Item No. Description

G-1 Structural Excavation in Common Material

Description No. Length Width Depth Volume (cft)


(ft) (ft) (ft)

Cistern 1 10 10 6.67 667.00


Total Quantity (Cft) 667.00
Total Quantity (CuM) 18.89

Plain Cement Concrete including placing, compacting, finishing & curing (Ratio
G-2
1:4:8)

Description No. Length Width Depth Volume (cft)


(ft) (ft) (ft)

Cistern 1 7 7 0.25 12.25


Total Quantity (Cft) 12.25
Total Quantity (CuM) 0.35

RCC in raft foundation slab, base slab of column & ret.


G-3
wall etc, not including in 06-06. Type C(1:2:4)

Description No. Length Width Depth Volume (cft)


(ft) (ft) (ft)

Cistern Base 1 5 5 0.75 18.75


Wall with Main Canal 1 7 1 6.5 45.50
Walls along minor 2 5 1 6.5 65.00
Wall with control gate 1 7 5 7.167 250.85
D/d Entry from Main -1 5 1 4.5 -22.50
Canal
D/d Regulation Gate -1 2.79 1 2.83 -7.90
Total Quantity (Cft) 349.70
Total Quantity (CuM) 9.9

Supply & fabricate M.S. reinforcement for cement concrete (Hot rolled
G-4
deformed bars Grade 40).

Total RCC quantity as per Item G-3 = 349.70 cft

Take Steel @ 2.00% of RCC Qty = 2.00% x 349.70 x 490 = 2998.671 lbs
OR 1.360 Tonnes

G-5 P/I gates for head regulator i/c hoisting device complete in all respect.
Description No. Length Width Volume (sft)
(ft) (ft)

Minor H R Gate 1 2.79 2.83 7.90


Total Quantity (sft) 7.90
Total Quantity (Sq. M) 0.73

Providing and fixing MS steel grated trash rack as per drawings and instructions
G-6
of Engineer.

Description No. Length Width Volume (sft)


(ft) (ft)

Trash rack 1 2.79 2.83 7.90


Total Quantity (sft) 7.90
Total Quantity (Sq. M) 0.73

Plain woodwork for regulation karries or needles etc. complete as per specs :
G-7
Deodar wood

Description No. Length Width Depth Volume (cft)


(ft) (ft) (ft)

1 2.79 2.83 0.416667 3.29


Total Quantity (Cft) 3.29
Total Quantity (CuM) 0.09

G-8 Structural backfill using Common Material available at site

Description No. Length Width Depth Volume (cft)


(ft) (ft) (ft)

Along Cistern walls 2 7 1.5 6.67 140.07


Toward Minor 1 7 1.5 2.67 28.04
Total Quantity (Cft) 168.11
Total Quantity (CuM) 4.76
Construction of Siran Right Bank Canal
District Mansehra
Escape Regulator

BOQ
Item No. Description

H-1 Structural Excavation in Common Material

Description No. Length Width Depth Volume


(ft) (ft) (ft) (cft)

Escape channel 3 80 10 5 12000.00


Total Quantity (Cft) 12000.00
Total Quantity (CuM) 339.8

Plain Cement Concrete including placing, compacting, finishing & curing (Ratio
H-2 1:4:8)

Description No. Length Width Depth Volume


(ft) (ft) (ft) (cft)

2 steps of 10ft 3 20 7.5 0.25 112.50


10 steps of 6ft 3 60 7.5 0.25 337.50
Total Quantity (Cft) 450.00
Total Quantity (CuM) 12.74

H-3 RCC in raft foundation slab, base slab of column

Description No. Length Width Depth Volume


(ft) (ft) (ft) (cft)

RCC Base Slab of Ist 2 Steps 3 20 10 1 600.00


RCC Base Slab of 6 Steps 3 60 10 6.5 11700.00
Steps RCC (11 No.s) 3 10 1 2 60.00
Side Walls 6 85 1 4 2040.00
Total Quantity (Cft) 14400.00
Total Quantity (CuM) 407.76

Supply & fabricate M.S. reinforcement for cement concrete (Hot rolled
H-4 deformed bars Grade 40).

Total RCC quantity as per Item H-3 = 14400.00 cft

Take Steel @ 2% of RCC Qty = 2% x 14400.00 x 490 = 141120.0 lbs


OR 64.030 Tonnes
Construction of Siran Right Bank Canal
District Mansehra
Escape Regulator

BOQ
Item No. Description

H-5 Supplying stone and stone filling in GI wire crate and its sewing, excluding cost of crates

Description No. Length Width Depth Quantity


(ft) (ft)
(ft) (cft)
Apron (10x10x3) 3 20 10 3 1800
Total Quantity (cft) 1800
Total Quantity (m3) 50.97

H-6 Provide & weave GI wire netting for wire crates 6"x9" mesh : 8 SWG wire

Description No. of No. of Area Qty


crates structures (sft) (sft)
Top & Bottom (10x10) 2 3 100 600
Ends (10x3) 2 3 30 180
Sides (10x3) 2 3 30 180
Quantity (Sft) 960
Quantity (Sq.M) 89.336

H-6 P/I gates for head regulator i/c hoisting device complete in all respect.

Description No. Length Width Volume


(ft) (ft) (sft)

Escape gates 3 5 5 75.00


Total Quantity (sft) 75.00
Total Quantity (Sq. M) 6.98

H-7 Plain woodwork for regulation karries or needles etc. complete as per specs :
Deodar wood

Description No. Length Width Depth Volume


(ft) (ft) (ft) (cft)

3 5 5 0.416667 31.25
Total Quantity (Cft) 31.25
Total Quantity (CuM) 0.88

H-8 Structural backfill using Common Material available at site

Description No. Length Width Depth Volume


(ft) (ft) (ft) (cft)

Escape channel 6 80 1.5 5 3600.00


Total Quantity (Cft) 3600.00
Total Quantity (CuM) 101.94
Construction of Siran Right Bank Canal
District Mansehra
MEASUREMENT SHEET OF SUB-ENGINEER OFFICE CUM RESIDENCE

Item
Description Unit Nos Length Width Depth Volume
No

Civil and Electrical Works


Providing and fixing stainless steel sink with drain board size
4.1.1 Each 3
18"x36" including set of brackets, waste pipe etc
Total 3.0
Providing & Fixing Steel manhole cover with frame
4.1.2 Each 4
18"x18" full heavy duty
Total 4.0

4.1.3 Soakage pit ( 6' dia x 15' deep ) complete. No 4

Total 4.0
Providing and installing PVC tees BSS Class 'B'working
4.1.4 Each 20
pressure : 3" i/d
Total 20.0
Providing and installing PVC bends BSS Class 'D'working
4.1.5 Each 15
pressure : 3" i/d

Total 15.0

Providing and Laying cut, joint, test, disinfect PVC pipe


4.1.6 R.M 15
line BSS Class 'D' working pressure : 3" i/d
Total 15.0
Providing and installing PVC tees BSS Class 'B'working
4.1.7 Each 10
pressure : 4" i/d
Total 10.0
Providing and installing PVC bends BSS Class 'D'working
4.1.8 Each 10
pressure : 4" i/d
Total 10.0
Providing and Laying cut, joint, test, disinfect PVC pipe
4.1.9 R.M 60
line BSS Class 'D' working pressure : 4" i/d
Total 60.0

Providing and installing PVC sockets BSS Class


4.1.10 Each 5
'B'working pressure : 6" i/d

Total 5.0
Providing and installing PVC bends BSS Class 'B'working
4.1.11 Each 5
pressure : 6" i/d
Total 5.0
Providing and Laying cut, joint, test, disinfect PVC pipe
4.1.12 R.M 110
line BSS Class 'B'working pressure : 6" i/d
Total 110.0

Providing and Fixing of poly dex high pressure PPR(green


4.1.13 R.M 115
including testing ect complete 20 mm(including all special etc)

Total 115.0

Providing and Fixing of poly dex high pressure PPR(green


4.1.14 R.M 100
including testing ect complete 25 mm(including all special etc)

Total 100.0
Supply and Fixing CI manhole cover with frame etc
4.1.15 Each 7
complete 18" dia
Total 7.0
Providing and fixing CI main hole cover with frame etc
4.1.16 No 7
complete 12" dia
Construction of Siran Right Bank Canal
District Mansehra
MEASUREMENT SHEET OF SUB-ENGINEER OFFICE CUM RESIDENCE

Item
Description Unit Nos Length Width Depth Volume
No

7.0
Providing and Fixing CI floor trap including CI grating &
4.1.17 Each 4
concrete chamber all round : 4"x3"
Total 4.0

4.1.18 Providing and fixing CP shower rose : 3/4"x6". No 3

Total 3.0
Providing and fixing gun metal peet / gate valve
4.1.19 No 2
(screwed ) 1" dia.

Total 2.0

4.1.20 Providing and Fixing CP mixing valve for WHB, sink or shower No 3

Total 3.0
Providing and Fixing CP or brass oxidized swan-neck cock
4.1.21 Each 3
1/2" dia : Double way
Total 3.0

4.1.22 Providing and Fixing 1/2" CP tee stop cock Each 6

Total 6.0
Providing and Fixing glazed earthen ware soap dish
4.1.23 Each 4
Coloured
Total 4.0
Providing and fixing best quality 5mm glass mirror 22"x16"
4.1.24 No 3
size
Total 3.0

4.1.25 Providing and fixing CP rail :24" long, 3/4" dia. No 3

Total 3.0

4.1.26 Providing and fixing CP tailot paper holder. No 3

Total 3.0

4.1.27 Providing and fixing CP soap dish. No 3

Total 3.0

Providing and Fixing glazed earthen ware low down


4.1.28 Each 3
flushing cistern 3 gallons capacity : Coloured

Total 3.0
Providing and Fixing glazed earthen ware WC European type
4.1.29 Each 3
excluding cost of seat & cover : Coloured
Total 3.0

4.1.30 Supply and Fixing low level plastic flushing cistern Each 3

Total 3.0

Providing and Fixing glazed earthen ware WC squatting


4.1.31 Each 3
type with built-in foot rests : Coloured
Total 3.0
Providing and Fixing angle iron brackets for : WHB and
4.1.32 Each 2
cistern
Total 2.0
Providing and Fixing glazed earthen ware WHB complete Size
4.1.33 Each 3
22"x16" : Coloured with pedestal
Construction of Siran Right Bank Canal
District Mansehra
MEASUREMENT SHEET OF SUB-ENGINEER OFFICE CUM RESIDENCE

Item
Description Unit Nos Length Width Depth Volume
No

Total 3.0
Energy saver 32 Watts (Phillips or eq) with down light / simple
4.1.34 Each 10
holder and extra accessories etc as specified
Total 10.0

4.1.35 Supply and erection plastic box size 7"x4" Each 15

Total 15.0

4.1.36 Supply and erection plastic box size 4"x4" Each 15

Total 15.0

Supply and Erection gate-light fitting complete with holder &


4.1.37 Each 6
160-Watt mercury blended lamp: Small

Total 6.0

Earthing of iron clad/aluminium switches etc with GI wire #8


4.1.38 Job 1
SWG in GI pipe 0.5" dia

Total 1.0

Supply and Erection 2'x2'x1/8" copper plate including


4.1.39 rivetting to copper tape & placing in mixture of salt and Each 2
charcol etc

Total 2.0

Supply and Erection single phase imported auto circuit


4.1.40 Each 2
breaker 30 Amp.

Total 2.0

Supply and Erection single phase imported auto circuit


4.1.41 Each 5
breaker 20 Amp

Total 5.0

Supply and Erection single phase imported auto circuit


4.1.42 Each 6
breaker 15 Amp
Total 6.0

Supply and Erection transpower auto circuit breaker


4.1.43 Each 4
3-phase, 400V fungus moisture proofing : 30 Amp.

Total 4.0

Supply and Erection transpower auto circuit breaker


4.1.44 Each 2
3-phase, 400V fungus moisture proofing : 100 Amp

Total 2.0

Supply and Erection single core PVC insulated copper


4.1.45 R.M 20
conductor 250/440 V grade cable : 7/0.044"

Total 20.0

Supply and Erection single core PVC insulated copper


4.1.46 R.M 200
conductor 250/440 V grade cable : 7/0.029"

Total 200.0

Supply and Erection single core PVC insulated copper


4.1.47 R.M 225
conductor 250/440 V grade cable : 3/0.029"

Total 225.0
Supply and Erection white round globe with holder, gallery &
4.1.48 Each 2
100 Watt bulb complete : 10" dia
Total 2.0
Construction of Siran Right Bank Canal
District Mansehra
MEASUREMENT SHEET OF SUB-ENGINEER OFFICE CUM RESIDENCE

Item
Description Unit Nos Length Width Depth Volume
No

Supply and Erection PVC pipe for wiring purpose


4.1.49 R.M 90
complete Recessed in walls including chase etc : 1" i/d
Total 90.0

Supply and Erection PVC pipe for wiring purpose


4.1.50 R.M 90
complete Recessed in walls including chase etc : 3/4" i/d

Total 90.0
Floor S/E cubical type factory fabricated floor / wall mounted
4.1.51 No. 1
main board steel complete recessed.
Total 1.0

Supply and fixing electric AC exhaust/fresh air


4.1.52 circulation(Double way) 220/230 single phase plastic frame Each 2
body and blade complete 12"x12"

Total 2.0

S/E best quality ceilling fan complete with G-I rod conopy
4.1.53 No. 10
blade & regulator 56" sweep.

Total 10.0

Supply and Erection girder clamp hook, 5/8" dia.for


4.1.54 Each 6
hanging ceiling fans

Total 6.0

Supply and Erection tube light, including rod, choke etc


4.1.55 Set 10
complete Double rod (2x40 watts) with 2 chokes & 2 starters

Total 10.0

4.1.56 S/E tube light rod and choke complete 40 watt. No. 10

Total 10.0

4.1.57 Supply and Fixing Asia porcelin power plug 30 Amp Each 20

Total 20.0

Wiring of 2/3 pin 5 AMP plug point in 3/029 pvc insulated


4.1.58 No. 20
cable in pvc pipe recessed.

Total 20.0

Wiring of light / fan / call bell point in 3-29 pvc insulated cable
4.1.59 No. 60
in pvc pipe recessed.

Total 60.0
Making and fixing grating in opening, including fixing at
4.1.60 m2 40
site with flat iron 2"x3/8" and 3/4" sq. bars
Total 40.0
Filling, watering and ramming earth under floor with
4.1.61 m3
surplus earth from foundation, etc

Bed Room1 & 2 2 14 12 1.75 588

Kitchen 1 14 10 1.75 245

Dining Room 1 14 18 1.75 441

Lounge 1 14 18 1.75 441

Reception Lobby 1 22 11.5 1.75 442.75

Servant 1 10 10.5 1.75 183.75


Construction of Siran Right Bank Canal
District Mansehra
MEASUREMENT SHEET OF SUB-ENGINEER OFFICE CUM RESIDENCE

Item
Description Unit Nos Length Width Depth Volume
No

Washrooms 2 10 6.25 1.75 218.75

Toilet 1 6 4 1.75 42

Total Quantity (Cft) 2,602.25

Total Quantity (Cu.m) 73.69

Shoes, bends or offsets for cast iron ran water down pipe,
4.1.62 Each 9
including fixing & painting

Total 9.00
Heads for cast iron rain water down pipe fixed in place
4.1.63 Each 9
including cost of clamp holdfast and painting
Total 9.00
Cast iron rain water down pipe fixed in position excluding
4.1.64 R. M 10 12
heads & shoes : 4" dia
Total 36.59

Plain Cement Concrete including placing, compacting,


4.1.65 m3 693.0
finishing & curing (Ratio 1:3:6)

Total 19.62
Preparing surface & painting with snowcem / weathershield
4.1.66 m2 293.73
paint : 2nd & subsequent coats
Total 293.73
Preparing surface & painting with snowcem / weathershield
4.1.67 m2
paint : First coat
External Surface 290 12 323.42
Doors 1 7 49
Windows

W-1 2 8 6 96

W-2 4 6 6 144

W-3 1 6 3.5 21

W-4 2 4 4.5 36
W-5 2 2.5 4.5 22.5
29.69
Total 293.73

4.1.68 Distemper New surface : Three coats m2 1,378.356

Total 1,378.36

4.1.69 White washing: New surface : Three coats m2 1,378.36

Total 1,378.36

4.1.70 Priming coat of chalk under distemper m2 1,378.36

Total 1,378.36
Providing and Fixing terrace railing of 2" i/d conduit pipe
4.1.71 m2 38
16 SWG welded with 5/8"x5/8" sq bar 2.75' high complete
Total 35.00
MS flat 1/2"x1/8" grill in windows of approved design
4.1.72 m2
including painting 3 coats, complete
W-1 2 8 6 96
Construction of Siran Right Bank Canal
District Mansehra
MEASUREMENT SHEET OF SUB-ENGINEER OFFICE CUM RESIDENCE

Item
Description Unit Nos Length Width Depth Volume
No

W-2 4 6 6 144

W-3 1 6 3.5 21

W-4 2 4 4.5 36

W-5 2 2.5 4.5 22.5

Total for (29) 29.69

4.1.73 French polishing complete : on new work . m2 237.12

Total 237.12
Varnishing wood work, including cleaning & preparing
4.1.74 m2 237.12
surface : Third coat
Total 237.12
Varnishing wood work, including cleaning & preparing
4.1.75 m2 237.12
surface : Second Coat
Total 237.12
Varnishing wood work, including cleaning & preparing
4.1.76 m2 237.12
surface : First coat
Total 237.12

4.1.77 P/F hydraulic Door Closer (Best Quality) No 12

Total 12.00
Providing and fixing sliding bolt to doors Brass sliding
4.1.78 No 12
bolts : 10" long
Total 12.00
Providing and fixing sliding bolt to doors Brass sliding
4.1.79 No 12
bolts : 12" long
Total 12.00
Provide & fix wooden box type wardrobe 22" deep Deodar
4.1.80 m2
wood boxing & deodar shelves etc
2 8 10 14.87
Total 14.87
Supply and Fixing aluminium door/window, Economy
4.1.81 m2
model Sliding window
W-1 2 8 6 96

W-2 4 6 6 144

W-3 2 6 3.5 42

W-4 2 4 4.5 36

W-5 2 2.5 4.5 22.5

Total 31.64

Deodar wood framed, braced & battened doors & windows:


4.1.82 m2
1.75" thick, 1" battens & 3/4" planks

WD-1 1 7 7 49

D-1 2 5 7 70

D-2 2 3.5 7 49
Construction of Siran Right Bank Canal
District Mansehra
MEASUREMENT SHEET OF SUB-ENGINEER OFFICE CUM RESIDENCE

Item
Description Unit Nos Length Width Depth Volume
No

D-3 2 3.25 7 45.5

D-4 2 3 7 42

D-5 3 2 7 42

Total 27.65
Provide & fix chowkat for doors, windows & CS windows,
4.1.83 m2
including holdfast etc : Deodar wood
WD-1 1 7 7 49

D-1 2 5 7 70

D-2 2 3.5 7 49

D-3 2 3.25 7 45.5

D-4 2 3 7 42

D-5 3 2 7 42

Total 27.65
Providing and fixing glazed tile colour printed border 3"
4.1.84 R.M
wide
330.65 330.65

Total 30.73
Glazed tile 1/4" thick dado jointed in white cement
4.1.85 m2
complete : Printed tiles
1 170 7 1190

Total for (16) 110.59

Cement pointing struck joints, on walls, upto 20' height :


4.1.86 m2
Ratio 1:3

Boundary Walls 2 410.00 7 5740

Total Quantity (Sft) 5,740.00

Total Quantity (Sq.m) 534.15

1.375" thick mosaic flooring, including rubbing and


4.1.87 m2
polishing complete : Using grey cement

Bath 2 10 6.25 125

Total Quantity (Sft) 12,139.15

Total Quantity (Sq.m) 1,129.64

Provide & lay marble fine dressed stone flooring on surface in


4.1.88 white cement complete: 3/4" thick (Badel, Silky black, Sunny m2
white, Sunny Grey or eq)

Bed Room1 & 2 2 14 12 336

Kitchen 1 14 10 140

Dining Room 1 14 18 252

Lounge 1 14 18 252
Construction of Siran Right Bank Canal
District Mansehra
MEASUREMENT SHEET OF SUB-ENGINEER OFFICE CUM RESIDENCE

Item
Description Unit Nos Length Width Depth Volume
No

Reception Lobby 1 22 11.5 253

Servant 1 10 10.5 105

Toilet 1 6 4 24

Total Quantity (Sft) 1,362.00

Total Quantity (Sq.m) 126.74

4.1.89 Cement plaster 1:4 upto 20' height 1/2" thick m2

Lounge & Dinning Long Wall 8 19.5 10.500 1,638.00

Lounge & Dinning Short Wall 8 14 10.500 1,176.00

Kitchin Long Wall 2 15.5 10.500 325.50

Kitchin Long Wall remaining with Dining 2 4.8 10.500 100.80

Kitchen Short Walls 4 10 10.500 420.00

Bath Long Wall Outer 4 9.5 10.500 399.00

Bath Long Wall Inner 4 9.125 10.500 383.25

Bath Outer Short Wall 4 6.25 10.500 262.50

Bath Short Wall having door 4 4.75 10.500 199.50

Servant Long Wall 2 16.375 10.500 343.88

Servant Short Wall 2 10 10.500 210.00

Servant Long Wall having door 2 4.8 10.500 100.80

Servant Short Wall balance 2 5.675 10.500 119.18

Bed Exterior Wall 2 24 10.500 504.00

Bed Interior Wall near reception 2 20 10.500 420.00

Bed rooms partition wall 2 14 10.500 294.00

Reception Entrance Wall 2 8 10.500 168.00

Servant Toilet Long Wall 2 7.125 10.500 149.63

Servant Toilet Short Wall 2 3.625 10.500 76.13

Boundary Wall 2 410 7.000 5,740.00

Parapet Wall 2 218.5 2.000 874.00

Total Plaster (sft) 13,904.17

Deduction of Door, Windows & Lintels

D1 4 4 7 112.00

D2 4 3.5 7 98.00

D3 4 3.25 7 91.00
Construction of Siran Right Bank Canal
District Mansehra
MEASUREMENT SHEET OF SUB-ENGINEER OFFICE CUM RESIDENCE

Item
Description Unit Nos Length Width Depth Volume
No

D4 4 3 7 84.00

D5 in 9" Wall 4 2.5 7 70.00

D5 in 4.5" Wall 2 2.5 7 35.00

DW1 2 7 7 98.00

W1 4 8 6 192.00

W2 8 6 6 288.00

W3 2 6 3.5 42.00

W4 4 4 4.5 72.00

W5 6 2.5 4.5 67.50

Total Deductions (1,249.50)

Net Quantity (Sft) 12,654.67

Total (Sq.m) 1,177.62

Cement plaster 3/8" thick under soffit of RCC roof slabs


4.1.90 m2
only upto 20' height : (1:3)

Roof Slab 1 2157.14 Sft Area 2,157.14

Total (Sft) 2,157.14

Total (Sq.m) 200.74

4.1.91 Pacca brick work in ground floor Cement, sand mortar 1:6 m3

Lounge & Dinning Long Wall 4 19.5 0.75 10.500 614.25

Lounge & Dinning Short Wall 4 14 0.75 10.500 441.00

Kitchin Long Wall 1 15.5 0.75 10.500 122.06

Kitchin Long Wall remaining with Dining 1 4.8 0.75 10.500 37.80

Kitchen Short Walls 2 10 0.75 10.500 157.50

Bath Long Wall Outer 2 9.5 0.75 10.500 149.63

Bath Long Wall Inner 2 9.125 0.75 10.500 143.72

Bath Outer Short Wall 2 6.25 0.75 10.500 98.44

Bath Short Wall having door 2 4.75 0.75 10.500 74.81

Servant Long Wall 1 16.375 0.75 10.500 128.95

Servant Short Wall 1 10 0.75 10.500 78.75

Servant Long Wall having door 1 4.8 0.75 10.500 37.80

Servant Short Wall balance 1 5.675 0.75 10.500 44.69

Bed Exterior Wall 1 24 0.75 10.500 189.00

Bed Interior Wall near reception 1 20 0.75 10.500 157.50


Construction of Siran Right Bank Canal
District Mansehra
MEASUREMENT SHEET OF SUB-ENGINEER OFFICE CUM RESIDENCE

Item
Description Unit Nos Length Width Depth Volume
No

Bed rooms partition wall 1 14 0.75 10.500 110.25

Reception Entrance Wall 1 8 0.75 10.500 63.00

Servant Toilet Long Wall 1 7.125 0.375 10.500 28.05

Servant Toilet Short Wall 1 3.625 0.375 10.500 14.27

Boundary Wall 1 410 0.75 7.000 2,152.50

Total Brick Work (Cft) 4,843.97

Deduction of Door, Windows & Lintels

D1 2 4 7 0.75 42.00

Lintel 2 5 0.75 0.75 5.63

D2 2 3.5 7 0.75 36.75

Lintel 2 4.5 0.75 0.75 5.06

D3 2 3.25 7 0.75 34.13

Lintel 2 4.25 0.75 0.75 4.78

D4 2 3 7 0.75 31.50

Lintel 2 4 0.75 0.75 4.50

D5 in 9" Wall 2 2.5 7 0.75 26.25

Lintel 2 3.5 0.75 0.75 3.94

D5 in 4.5" Wall 1 2.5 7 0.38 6.56

Lintel 2 3.5 0.375 0.75 1.97

DW1 1 7 7 0.75 36.75

Lintel 1 8.5 0.75 1.00 6.38

W1 2 8 6 0.75 72.00

Lintel 2 9.5 0.75 1.00 14.25

W2 4 6 6 0.75 108.00

Lintel 4 7.5 0.75 1.00 22.50

W3 1 6 3.5 0.75 15.75

Lintel 1 7.5 0.75 1.00 5.63

W4 2 4 4.5 0.75 27.00

Lintel 2 5.5 0.75 0.75 6.19

W5 3 2.5 4.5 0.75 25.31

Lintel 3 3.5 0.75 0.75 5.91

Total Deductions (548.74)


Construction of Siran Right Bank Canal
District Mansehra
MEASUREMENT SHEET OF SUB-ENGINEER OFFICE CUM RESIDENCE

Item
Description Unit Nos Length Width Depth Volume
No

Net Quantity (Cft) 4,295.23

Total (Cum) 121.63

Damp proof course of cem. conc. 1:2:4 including bitumen


4.1.92 m2
coat, 1 layer polythene & 1 coat bitumen (3" thick)

Lounge & Dinning Long Wall 4 19.5 0.75 0.125 7.31

Lounge & Dinning Short Wall 4 14 0.75 0.125 5.25

Kitchin Long Wall 1 15.5 0.75 0.125 1.45

Kitchin Long Wall remaining with Dining 1 4.8 0.75 0.125 0.45

Kitchen Short Walls 2 10 0.75 0.125 1.88

Bath Long Wall Outer 2 9.5 0.75 0.125 1.78

Bath Long Wall Inner 2 9.125 0.75 0.125 1.71

Bath Outer Short Wall 2 6.25 0.75 0.125 1.17

Bath Short Wall having door 2 4.75 0.75 0.125 0.89

Servant Long Wall 1 16.375 0.75 0.125 1.54

Servant Short Wall 1 10 0.75 0.125 0.94

Servant Long Wall having door 1 4.8 0.75 0.125 0.45

Servant Short Wall balance 1 5.675 0.75 0.125 0.53

Bed Exterior Wall 1 24 0.75 0.125 2.25

Bed Interior Wall near reception 1 20 0.75 0.125 1.88

Bed rooms partition wall 1 14 0.75 0.125 1.31

Reception Entrance Wall 1 8 0.75 0.125 0.75

Servant Toilet Long Wall 1 7.125 0.375 0.125 0.33

Servant Toilet Short Wall 1 3.625 0.375 0.125 0.17

Boundary Wall 1 410 0.75 0.125 38.44

Total (Cft) 70.48

Total (Cum) 2.00

Pacca brick work in foundation and plinth in Cement, sand


4.1.93 m3
mortar 1:6

Lounge & Dinning Long Wall Step 1 4 20.25 1.5 0.5 60.75

Lounge & Dinning Long Wall Step 2 4 19.875 1.125 0.5 44.72

Lounge & Dinning Long Wall Step 3 4 19.5 0.75 1.75 102.38

Lounge & Dinning Short Wall Step 1 4 13.25 1.5 0.5 39.75

Lounge & Dinning Short Wall Step 2 4 13.625 1.125 0.5 30.66

Lounge & Dinning Short Wall Step 3 4 14 0.75 1.75 73.50


Construction of Siran Right Bank Canal
District Mansehra
MEASUREMENT SHEET OF SUB-ENGINEER OFFICE CUM RESIDENCE

Item
Description Unit Nos Length Width Depth Volume
No

Kitchin Long Wall Step 1 1 16.25 1.5 0.5 12.19

Kitchin Long Wall Step 2 1 15.875 1.125 0.5 8.93

Kitchin Long Wall Step 3 1 15.5 0.75 1.75 20.34

Kitchin Long Wall remaining with Dining Step 1 1 5.55 1.5 0.5 4.16

Kitchin Long Wall remaining with Dining Step 2 1 5.175 1.125 0.5 2.91

Kitchin Long Wall remaining with Dining Step 3 1 4.8 0.75 1.75 6.30

Kitchen Short Walls Step 1 2 9.25 1.5 0.5 13.88

Kitchen Short Walls Step 2 2 9.625 1.125 0.5 10.83

Kitchen Short Walls Step 3 2 10 0.75 1.75 26.25

Bath Long Wall Outer Step 1 2 10.25 1.5 0.5 15.38

Bath Long Wall Outer Step 2 2 9.875 1.125 0.5 11.11

Bath Long Wall Outer Step 3 2 9.5 0.75 1.75 24.94

Bath Long Wall Inner Step 1 2 9.875 1.5 0.5 14.81

Bath Long Wall Inner Step 2 2 9.5 1.125 0.5 10.69

Bath Long Wall Inner Step 3 2 9.125 0.75 1.75 23.95

Bath Outer Short Wall Step 1 2 5.5 1.5 0.5 8.25

Bath Outer Short Wall Step 2 2 5.875 1.125 0.5 6.61

Bath Outer Short Wall Step 3 2 6.25 0.75 1.75 16.41

Bath Short Wall having door Step 1 2 4 1.5 0.5 6.00

Bath Short Wall having door Step 2 2 4.375 1.125 0.5 4.92

Bath Short Wall having door Step 3 2 4.75 0.75 1.75 12.47

Servant Long Wall Step 1 1 17.125 1.5 0.5 12.84

Servant Long Wall Step 2 1 16.75 1.125 0.5 9.42

Servant Long Wall Step 3 1 16.375 0.75 1.75 21.49

Servant Short Wall Step 1 1 9.25 1.5 0.5 6.94

Servant Short Wall Step 2 1 9.625 1.125 0.5 5.41

Servant Short Wall Step 3 1 10 0.75 1.75 13.13

Servant Long Wall having door Step 1 1 5.55 1.5 0.5 4.16

Servant Long Wall having door Step 2 1 5.175 1.125 0.5 2.91

Servant Long Wall having door Step 3 1 4.8 0.75 1.75 6.30

Servant Short Wall balance Step 1 1 4.925 1.5 0.5 3.69

Servant Short Wall balance Step 2 1 5.3 1.125 0.5 2.98


Construction of Siran Right Bank Canal
District Mansehra
MEASUREMENT SHEET OF SUB-ENGINEER OFFICE CUM RESIDENCE

Item
Description Unit Nos Length Width Depth Volume
No

Servant Short Wall balance Step 3 1 5.675 0.75 1.75 7.45

Bed Exterior Wall Step 1 1 23.25 1.5 0.5 17.44

Bed Exterior Wall Step 2 1 23.625 1.125 0.5 13.29

Bed Exterior Wall Step 3 1 24 0.75 1.75 31.50

Bed Interior Wall near reception Step 1 1 19.25 1.5 0.5 14.44

Bed Interior Wall near reception Step 2 1 19.625 1.125 0.5 11.04

Bed Interior Wall near reception Step 3 1 20 0.75 1.75 26.25

Bed rooms partition wall Step 1 1 13.25 1.5 0.5 9.94

Bed rooms partition wall Step 2 1 13.625 1.125 0.5 7.66

Bed rooms partition wall Step 3 1 14 0.75 1.75 18.38

Reception Entrance Wall Step 1 1 7.25 1.5 0.5 5.44

Reception Entrance Wall Step 2 1 7.625 1.125 0.5 4.29

Reception Entrance Wall Step 3 1 8 0.75 1.75 10.50

Servant Toilet Long Wall Step 1 1 7.125 0.75 0.50 2.67

Servant Toilet Long Wall Step 2 1 6.75 0.375 1.00 2.53

Servant Toilet Short Wall Step 1 1 3.625 0.75 0.50 1.36

Servant Toilet Short Wall Step 2 1 4 0.375 1.00 1.50

Boundary Wall Step 1 1 410 1.5 0.5 307.50

Boundary Wall Step 2 1 410 1.125 0.5 230.63

Boundary Wall Step 3 1 410 0.75 2.0 615.00

Total (Cft) 2,041.17

Total (Cum) 57.80

Single layer of tiles 10"x5"x1.25" laid over 4" earth and 1"
4.1.94 m2
mud plaster on top of RC roof slab

Roof Slab 1 2157.14 Sft Area 2,157.14

Total (Sft) 2,157.14

Total (Sq.m) 200.74

Supply fabricate M.S reinforcement for cement concrete ( hot


4.1.95 Ton
rolled deformed bars Grad 40)
RCC Total Quantity (cft) 2,464.32

Take 2% of concrete Quantity (lbs) = 2.00% 2,464.32 490 24,150.32

Total Quantity (Tonnes) 10.96


Construction of Siran Right Bank Canal
District Mansehra
MEASUREMENT SHEET OF SUB-ENGINEER OFFICE CUM RESIDENCE

Item
Description Unit Nos Length Width Depth Volume
No
RCC in roof slab , beam , column and other structural member
4.1.96 m3
, in sithu or precast.type C 1:2:4.
RCC in Plinth Beams

Lounge & Dinning Long Wall 4 19.5 0.75 0.750 43.88

Lounge & Dinning Short Wall 4 14 0.75 0.750 31.50

Kitchin Long Wall 1 15.5 0.75 0.750 8.72

Kitchin Long Wall remaining with Dining 1 4.8 0.75 0.750 2.70

Kitchen Short Walls 2 10 0.75 0.750 11.25

Bath Long Wall Outer 2 9.5 0.75 0.750 10.69

Bath Long Wall Inner 2 9.125 0.75 0.750 10.27

Bath Outer Short Wall 2 6.25 0.75 0.750 7.03

Bath Short Wall having door 2 4.75 0.75 0.750 5.34

Servant Long Wall 1 16.375 0.75 0.750 9.21

Servant Short Wall 1 10 0.75 0.750 5.63

Servant Long Wall having door 1 4.8 0.75 0.750 2.70

Servant Short Wall balance 1 5.675 0.75 0.750 3.19

Bed Exterior Wall 1 24 0.75 0.750 13.50

Bed Interior Wall near reception 1 20 0.75 0.750 11.25

Bed rooms partition wall 1 14 0.75 0.750 7.88

Reception Entrance Wall 1 8 0.75 0.750 4.50

Servant Toilet Long Wall 1 7.125 0.375 0.750 2.00

Servant Toilet Short Wall 1 3.625 0.375 0.750 1.02

Boundary Wall 1 410 0.75 0.750 230.63

RCC in Lintel Beams

Lintels on D1 2 5 0.75 0.75 5.63

Lintel on D2 2 4.5 0.75 0.75 5.06

Lintel on D3 2 4.25 0.75 0.75 4.78

Lintel on D4 2 4 0.75 0.75 4.50

Lintel on D5 2 3.5 0.75 0.75 3.94

Lintel on D5 (4.5" wall) 2 3.5 0.375 0.75 1.97

Lintel on DW1 1 8.5 0.75 1.00 6.38

Lintel on W1 2 9.5 0.75 1.00 14.25

Lintel on W2 4 7.5 0.75 1.00 22.50


Construction of Siran Right Bank Canal
District Mansehra
MEASUREMENT SHEET OF SUB-ENGINEER OFFICE CUM RESIDENCE

Item
Description Unit Nos Length Width Depth Volume
No

Lintel on W3 1 7.5 0.75 1.00 5.63

Lintel on W4 2 5.5 0.75 0.75 6.19

Lintel on W5 3 3.5 0.75 0.75 5.91

RCC in Column Footing 4 5 5 0.75 75.00

RCC in Columns 4 π/4 x (1)^2 10.00 31.416

Porch Long Beams 2 20 1 1.00 40.00

Porch Short Beams 2 17 1 1.00 34.00

Grid Long Beams 7 6.4167 0.25 0.50 5.61

Grid small Beams 18 1.5 0.25 0.50 3.38

Porch Slab 1 20 17 0.50 170.00

Building Slab 1 2157.14 sft Area 0.50 1,078.57

Parapet Wall 1 218.5 0.5 2.00 437.00

Total (Cft) 2,384.61

Total (Cum) 67.52

RCC in raft foundation slab, base slab of column & ret.


4.1.97 m3
wall etc, not including in 06-06. Type C(1:2:4)

RCC in Column Footing 4 5 5 0.75 75.00

RCC in Columns upto NSL 4 π/4 x (1)^2 1.50 4.712

Total (Cft) 79.71

Total (Cum) 2.26

Plain Cement Concrete including placing, compacting,


4.1.98 m3
finishing & curing (Ratio 1:4:8)

Column Footing 4 5.5 5.5 0.33 39.93

Lounge & Dinning Long Wall 4 21 2.25 0.5 94.50

Lounge & Dinning Short Wall 4 12.5 2.25 0.5 56.25

Kitchin Long Wall 1 17 2.25 0.5 19.13

Kitchin Long Wall remaining with Dining 1 6.3 2.25 0.5 7.09

Kitchen Short Walls 2 8.5 2.25 0.5 19.13

Bath Long Wall Outer 2 11 2.25 0.5 24.75

Bath Long Wall Inner 2 10.625 2.25 0.5 23.91

Bath Outer Short Wall 2 4.75 2.25 0.5 10.69

Bath Short Wall having door 2 3.25 2.25 0.5 7.31

Servant Long Wall 1 17.875 2.25 0.5 20.11

Servant Short Wall 1 8.5 2.25 0.5 9.56


Construction of Siran Right Bank Canal
District Mansehra
MEASUREMENT SHEET OF SUB-ENGINEER OFFICE CUM RESIDENCE

Item
Description Unit Nos Length Width Depth Volume
No

Servant Long Wall having door 1 6.3 2.25 0.5 7.09

Servant Short Wall balance 1 4.175 2.25 0.5 4.70

Bed Exterior Wall 1 22.5 2.25 0.5 25.31

Bed Interior Wall near reception 1 18.5 2.25 0.5 20.81

Bed rooms partition wall 1 12.5 2.25 0.5 14.06

Reception Entrance Wall 1 6.5 2.25 0.5 7.31

Servant Toilet Long Wall 1 7.375 1 0.50 3.69

Servant Toilet Short Wall 1 3.375 1 0.50 1.69

Boundary Wall 1 410 2.25 0.5 461.25

PCC (1:4:8) in flooring

Bed Room1 & 2 2 14 12 0.25 84.00

Kitchen 1 14 10 0.25 35.00

Dining Room 1 14 18 0.25 63.00

Lounge 1 14 18 0.25 63.00

Reception Lobby 1 22 11.5 0.25 63.25

Servant 1 10 10.5 0.25 26.25

Toilet 1 6 4 0.25 6.00

Total (Cft) 1,218.77

Total (Cum) 34.51

Excavation in foundation of building bridges etc complete in


4.1.99 m3
Shingle gravel.

Column Footing 4 5.5 5.5 2 242.00

Lounge & Dinning Long Wall 4 21 2.25 2 378.00

Lounge & Dinning Short Wall 4 12.5 2.25 2 225.00

Kitchin Long Wall 1 17 2.25 2 76.50

Kitchin Long Wall remaining with Dining 1 6.3 2.25 2 28.35

Kitchen Short Walls 2 8.5 2.25 2 76.50

Bath Long Wall Outer 2 11 2.25 2 99.00

Bath Long Wall Inner 2 10.625 2.25 2 95.63

Bath Outer Short Wall 2 4.75 2.25 2 42.75

Bath Short Wall having door 2 3.25 2.25 2 29.25

Servant Long Wall 1 17.875 2.25 2 80.44

Servant Short Wall 1 8.5 2.25 2 38.25


Construction of Siran Right Bank Canal
District Mansehra
MEASUREMENT SHEET OF SUB-ENGINEER OFFICE CUM RESIDENCE

Item
Description Unit Nos Length Width Depth Volume
No

Servant Long Wall having door 1 6.3 2.25 2 28.35

Servant Short Wall balance 1 4.175 2.25 2 18.79

Bed Exterior Wall 1 22.5 2.25 2 101.25

Bed Interior Wall near reception 1 18.5 2.25 2 83.25

Bed rooms partition wall 1 12.5 2.25 2 56.25

Reception Entrance Wall 1 6.5 2.25 2 29.25

Boundary Wall 1 410 2.25 2 1,845.00

Total (Cft) 3,573.81

Total (Cum) 101.20

4.1.100 P/F Fiber glass Water Tank 300 gallons. No 1

Total 1.00

Supply and fixing of 2.0 HP Monoblock water pump


4.1.101 1.5"x1.25" 3 stage model DE-S3 (Deen Pump) single No 1
phase for 150 ft head with all accessories.

Total 1.00

Making and fixing steel grated doors, complete with locking


4.1.102 m2 3.5 2.5 8.75
arrangements & angle iron frame

Total 8.75
Construction of Siran Right Bank Canal
District Mansehra
MEASUREMENT SHEET OF CHOWKIDAR HUT
Item
Description Unit Nos Length Width Depth Volume
No
Civil and Electrical Works
Providing and fixing stainless steel sink with drain board size
4.2.1 18"x36" including set of brackets, waste pipe etc Each 1

Total 1.0
Providing & Fixing Steel manhole cover with frame
4.2.2 18"x18" full heavy duty Each 2

Total 2.0

4.2.3 Soakage pit ( 6' dia x 15' deep ) complete. No 2

Total 2.0
Providing and installing PVC tees BSS Class 'B'working
4.2.4 pressure : 3" i/d Each 10

Total 10.0
Providing and installing PVC bends BSS Class 'D'working
4.2.5 pressure : 3" i/d Each 7

Total 7.0
Providing and Laying cut, joint, test, disinfect PVC pipe
4.2.6 line BSS Class 'D' working pressure : 3" i/d R.M 10

Total 10.0
Providing and installing PVC tees BSS Class 'B'working
4.2.7 pressure : 4" i/d Each 5

Total 5.0
Providing and installing PVC bends BSS Class 'D'working
4.2.8 pressure : 4" i/d Each 5

Total 5.0
Providing and Laying cut, joint, test, disinfect PVC pipe
4.2.9 line BSS Class 'D' working pressure : 4" i/d R.M 30

Total 30.0
Providing and installing PVC sockets BSS Class
4.2.10 'B'working pressure : 6" i/d Each 5

Total 5.0
Providing and installing PVC bends BSS Class 'B'working
4.2.11 pressure : 6" i/d Each 4

Total 4.0
Providing and Laying cut, joint, test, disinfect PVC pipe
4.2.12 line BSS Class 'B'working pressure : 6" i/d R.M 50

Total 50.0

Providing and Fixing of poly dex high pressure PPR(green


4.2.13 including testing ect complete 20 mm(including all special etc) R.M 70

Total 70.0

Providing and Fixing of poly dex high pressure PPR(green


4.2.14 including testing ect complete 25 mm(including all special etc) R.M 60

Total 60.0
Supply and Fixing CI manhole cover with frame etc
4.2.15 complete 18" dia Each 3

Total 3.0
Construction of Siran Right Bank Canal
District Mansehra
MEASUREMENT SHEET OF CHOWKIDAR HUT
Item
Description Unit Nos Length Width Depth Volume
No
Providing and fixing CI main hole cover with frame etc
4.2.16 complete 12" dia No 3

3.0
Providing and Fixing CI floor trap including CI grating &
4.2.17 concrete chamber all round : 4"x3" Each 2

Total 2.0

4.2.18 Providing and fixing CP shower rose : 3/4"x6". No 2

Total 2.0
Providing and fixing gun metal peet / gate valve
4.2.19 (screwed ) 1" dia. No 2

Total 2.0

4.2.20 Providing and Fixing CP mixing valve for WHB, sink or shower No 1

Total 1.0
Providing and Fixing CP or brass oxidized swan-neck cock
4.2.21 1/2" dia : Double way Each 2

Total 2.0

4.2.22 Providing and Fixing 1/2" CP tee stop cock Each 5

Total 5.0
Providing and Fixing glazed earthen ware soap dish
4.2.23 Coloured Each 2

Total 2.0
Providing and fixing best quality 5mm glass mirror 22"x16"
4.2.24 size No 2

Total 2.0

4.2.25 Providing and fixing CP rail :24" long, 3/4" dia. No 2

Total 2.0

4.2.26 Providing and fixing CP tailot paper holder. No 2

Total 2.0

4.2.27 Providing and fixing CP soap dish. No 2

Total 2.0
Providing and Fixing glazed earthen ware low down
4.2.28 flushing cistern 3 gallons capacity : Coloured Each 2

Total 2.0
Providing and Fixing glazed earthen ware WC European type
4.2.29 excluding cost of seat & cover : Coloured Each 2

Total 2.0

4.2.30 Supply and Fixing low level plastic flushing cistern Each 2

Total 2.0
Providing and Fixing glazed earthen ware WC squatting
4.2.31 type with built-in foot rests : Coloured Each 2

Total 2.0
Providing and Fixing angle iron brackets for : WHB and
4.2.32 cistern Each 2
Construction of Siran Right Bank Canal
District Mansehra
MEASUREMENT SHEET OF CHOWKIDAR HUT
Item
Description Unit Nos Length Width Depth Volume
No
Total 2.0
Providing and Fixing glazed earthen ware WHB complete Size
4.2.33 22"x16" : Coloured with pedestal Each 2

Total 2.0

Energy saver 32 Watts (Phillips or eq) with down light / simple


4.2.34 holder and extra accessories etc as specified Each 5

Total 5.0

4.2.35 Supply and erection plastic box size 7"x4" Each 7

Total 7.0

4.2.36 Supply and erection plastic box size 4"x4" Each 7

Total 7.0

Supply and Erection gate-light fitting complete with holder &


4.2.37 160-Watt mercury blended lamp: Small Each 6

Total 6.0

Earthing of iron clad/aluminium switches etc with GI wire #8


4.2.38 SWG in GI pipe 0.5" dia Job 1

Total 1.0
Supply and Erection 2'x2'x1/8" copper plate including
4.2.39 rivetting to copper tape & placing in mixture of salt and Each 1
charcol etc

Total 1.0
Supply and Erection single phase imported auto circuit
4.2.40 breaker 30 Amp. Each 1

Total 1.0
Supply and Erection single phase imported auto circuit
4.2.41 breaker 20 Amp Each 3

Total 3.0

Supply and Erection single phase imported auto circuit


4.2.42 breaker 15 Amp Each 4

Total 4.0
Supply and Erection transpower auto circuit breaker
4.2.43 3-phase, 400V fungus moisture proofing : 30 Amp. Each 2

Total 2.0

Supply and Erection transpower auto circuit breaker


4.2.44 3-phase, 400V fungus moisture proofing : 100 Amp Each 1

Total 1.0
Supply and Erection single core PVC insulated copper
4.2.45 conductor 250/440 V grade cable : 7/0.044" R.M 10

Total 10.0
Supply and Erection single core PVC insulated copper
4.2.46 conductor 250/440 V grade cable : 7/0.029" R.M 100

Total 100.0
Supply and Erection single core PVC insulated copper
4.2.47 conductor 250/440 V grade cable : 3/0.029" R.M 125
Construction of Siran Right Bank Canal
District Mansehra
MEASUREMENT SHEET OF CHOWKIDAR HUT
Item
Description Unit Nos Length Width Depth Volume
No
Total 125.0

Supply and Erection white round globe with holder, gallery &
4.2.48 100 Watt bulb complete : 10" dia Each 1

Total 1.0

Supply and Erection PVC pipe for wiring purpose


4.2.49 complete Recessed in walls including chase etc : 1" i/d R.M 40

Total 40.0

Supply and Erection PVC pipe for wiring purpose


4.2.50 complete Recessed in walls including chase etc : 3/4" i/d R.M 40

Total 40.0

Floor S/E cubical type factory fabricated floor / wall mounted


4.2.51 main board steel complete recessed. No. 1

Total 1.0

Supply and fixing electric AC exhaust/fresh air


4.2.52 circulation (Double way) 220/230 single phase plastic frame Each 1
body and blade complete 12"x12"

Total 1.0

S/E best quality ceilling fan complete with G-I rod conopy
4.2.53 blade & regulator 56" sweep. No. 5

Total 5.0

Supply and Erection girder clamp hook, 5/8" dia.for


4.2.54 hanging ceiling fans Each 3

Total 3.0

Supply and Erection tube light, including rod, choke etc


4.2.55 complete Double rod (2x40 watts) with 2 chokes & 2 starters Set 4

Total 4.0

4.2.56 S/E tube light rod and choke complete 40 watt. No. 4

Total 4.0

4.2.57 Supply and Fixing Asia porcelin power plug 30 Amp Each 10

Total 10.0
Wiring of 2/3 pin 5 AMP plug point in 3/029 pvc insulated cable
4.2.58 in pvc pipe recessed. No. 10

Total 10.0
Wiring of light / fan / call bell point in 3-29 pvc insulated cable
4.2.59 in pvc pipe recessed. No. 30

Total 30.0
Making and fixing grating in opening, including fixing at
4.2.60 site with flat iron 2"x3/8" and 3/4" sq. bars m2 20

Total 20.0
Filling, watering and ramming earth under floor with
4.2.61 surplus earth from foundation, etc m3 0.5 1799.05 899.525

Total 25.47
Shoes, bends or offsets for cast iron ran water down pipe,
4.2.62 including fixing & painting Each 8
Construction of Siran Right Bank Canal
District Mansehra
MEASUREMENT SHEET OF CHOWKIDAR HUT
Item
Description Unit Nos Length Width Depth Volume
No
Total 8.00

Heads for cast iron rain water down pipe fixed in place
4.2.63 including cost of clamp holdfast and painting Each 8

Total 8.00
Construction of Siran Right Bank Canal
District Mansehra
MEASUREMENT SHEET OF CHOWKIDAR HUT
Item
Description Unit Nos Length Width Depth Volume
No
Cast iron rain water down pipe fixed in position excluding
4.2.64 heads & shoes : 4" dia R. M 6 10

Total 18.29

Plain Cement Concrete including placing, compacting,


4.2.65 finishing & curing (Ratio 1:3:6) m3 1,277.0

Total 36.16

Preparing surface & painting with snowcem / weathershield


4.2.66 paint : 2nd & subsequent coats m2 122.49

Total 122.49

Preparing surface & painting with snowcem / weathershield


4.2.67 paint : First coat m2

External Surface 131 12 146.10

Enhance Factor @ 10% 14.61

Doors 2 7 56

Windows

W1 3 6 54

W2 3 6 72

W3 2 6 72

23.61

Total 137.10

4.2.68 Priming coat of chalk under distemper m2 609.59

Total 609.59

4.2.69 White washing: New surface : Three coats m2 609.59

Total 609.59

4.2.70 Priming coat of chalk under distemper m2 609.59

Total 609.59
Providing and Fixing terrace railing of 2" i/d conduit pipe
4.2.71 16 SWG welded with 5/8"x5/8" sq bar 2.75' high complete m2 20

Total 20.00
MS flat 1/2"x1/8" grill in windows of approved design
4.2.72 including painting 3 coats, complete m2

3 6 54

3 6 72

2 6 72

Total 18.40

4.2.73 French polishing complete : on new work . m2 121.00

Total 121.00

Varnishing wood work, including cleaning & preparing


4.2.74 surface : Third coat m2 121.00

Total 121.00
Varnishing wood work, including cleaning & preparing
4.2.75 surface : Second Coat m2 121.00
Construction of Siran Right Bank Canal
District Mansehra
MEASUREMENT SHEET OF CHOWKIDAR HUT
Item
Description Unit Nos Length Width Depth Volume
No
Total 121.00

Varnishing wood work, including cleaning & preparing


4.2.76 surface : First coat m2 121.00

Total 121.00

4.2.77 P/F hydraulic Door Closer (Best Quality) No 6

Total 6.00

Providing and fixing sliding bolt to doors Brass sliding


4.2.78 bolts : 10" long No 6

Total 6.00
Providing and fixing sliding bolt to doors Brass sliding
4.2.79 bolts : 12" long No 6

Total 6.00

Provide & fix wooden box type wardrobe 22" deep Deodar
4.2.80 wood boxing & deodar shelves etc m2

2 6 10 11.15

Total 11.15
Supply and Fixing aluminium door/window, Economy
4.2.81 model Sliding window m2

3 3 6 54

3 4 6 72

2 6 6 72

Total 18.40

Deodar wood framed, braced & battened doors & windows:


4.2.82 1.75" thick, 1" battens & 3/4" planks m2

2 56

4 70

Total 11.71

Provide & fix chowkat for doors, windows & CS windows,


4.2.83 including holdfast etc : Deodar wood m2

2 70

4 84

Total 14.31
Providing and fixing glazed tile colour printed border 3"
4.2.84 wide R.M

263.25 263.25

Total 24.47

Glazed tile 1/4" thick dado jointed in white cement


4.2.85 complete : Printed tiles m2

2 45.5 7 637

Total 59.20
Cement pointing struck joints, on walls, upto 20' height :
4.2.86 Ratio 1:3 m2

Boundary Walls 2 164.00 7 2296

Total 213.38
Construction of Siran Right Bank Canal
District Mansehra
MEASUREMENT SHEET OF CHOWKIDAR HUT
Item
Description Unit Nos Length Width Depth Volume
No
1.375" thick mosaic flooring, including rubbing and
4.2.87 polishing complete : Using grey cement m2

2 58.5 117

Total 117.00

Provide & lay marble fine dressed stone flooring on surface in


4.2.88 white cement complete: 3/4" thick (Badel, Silky black, Sunny m2
white, Sunny Grey or eq)

Bed Rooms 2 14 16 448


Baths 2 6 10 120
Dressing 1 6 5.25 31.5
Kitchen 1 8 5.25 42
Veranda 1 155 155
2.5ft Door 6 2.5 0.75 15
4 ft Door 4 4 0.75 16

Total (Sft) 827.5

Total (Sq.m) 77.005

4.2.89 Cement plaster 1:4 upto 20' height 1/2" thick m2

Bed Room Long Wall 6 16 10.5 1008

Bed Room Short Wall 8 14 10.5 1176

Left / Right side Outer wall 4 16 10.5 672

Right Side Outer Wall 2 16 10.5 336

Bath & Dress Wall 12 6 10.5 756

Kitchen Long Wall 2 8 10.5 168

Kitchen Short Wall 2 5.25 10.5 110.25

Columns 8 1 9.5 76

Veranda Beam 2 34.25 1 68.5

Exterior NSL to plinth 1 131 1.5 196.5

Total (Sft) 4567.25

Deduction of Doors, Windows & Lintels

2.5ft Door 6 2.5 7.00 105

4 ft Door 4 4 7.00 112

6ft Windows 4 6 4.00 96

4ft Windows 6 4 4.00 96

3ft Ventilators 4 3 2.00 24


Construction of Siran Right Bank Canal
District Mansehra
MEASUREMENT SHEET OF CHOWKIDAR HUT
Item
Description Unit Nos Length Width Depth Volume
No

Total Deductions (Sft) -433

Net Quantity (Sft) 4134.25

Quantity (Sq.M) 384.72


Cement plaster 3/8" thick under soffit of RCC roof slabs
4.2.90 only upto 20' height : (1:3) m2

Bed Rooms 2 14 16 448


Baths 2 6 10 120
Dressing 1 6 5.25 31.5
Kitchen 1 8 5.25 42
Veranda 1 155 155
Shades 1 150 2.5 375

Total (Sft) 1171.5

Total (Sq.m) 109.017

4.2.91 Pacca brick work in ground floor Cement, sand mortar 1:6 m3

Bed Room Long Wall 3 16 0.75 10.5 378

Bed Room Short Wall 4 14 0.75 10.5 441

Left / Right side Outer wall 2 16 0.75 10.5 252

Right Side Outer Wall 1 16 0.75 10.5 126

Bath & Dress Wall 6 6 0.75 10.5 283.5

Kitchen Long Wall 1 8 0.75 10.5 63

Kitchen Short Wall 1 5.25 0.75 10.5 41.34

Boundary Walls 1 164 0.75 7.00 861

Total (cft) 2445.84

Deduction of Doors, Windows & Lintels

2.5ft Door 3 2.5 0.75 7.00 39.38

4 ft Door 2 4 0.75 7.00 42

6ft Windows 2 6 0.75 4.00 36

4ft Windows 3 4 0.75 4.00 36

3ft Ventilators 2 3 0.75 2.00 9

Total Deductions (Cft) -162.38

Net Quantity (Cft) 2283.46

Quantity (CuM) 64.66

Damp proof course of cem. conc. 1:2:4 including bitumen


4.2.92 coat, 1 layer polythene & 1 coat bitumen (3" thick) m2
Construction of Siran Right Bank Canal
District Mansehra
MEASUREMENT SHEET OF CHOWKIDAR HUT
Item
Description Unit Nos Length Width Depth Volume
No

Bed Room Long Wall 3 16 0.75 0.25 9

Bed Room Short Wall 4 14 0.75 0.25 10.5

Left / Right side Outer wall 2 16 0.75 0.25 6

Right Side Outer Wall 1 16 0.75 0.25 3

Bath & Dress Wall 6 6 0.75 0.25 6.75

Kitchen Long Wall 1 8 0.75 0.25 1.5

Kitchen Short Wall 1 5.25 0.75 0.25 0.98

Boundary Walls 1 164 0.75 0.25 41

Total (Cft) 78.73

Total (CuM) 2.23

Pacca brick work in foundation and plinth in Cement, sand


4.2.93 mortar 1:6 m3

Bed Room Long Wall 3 16 0.75 2.75 99

Bed Room Short Wall 4 14 0.75 2.75 115.5

Left / Right side Outer wall 2 16 0.75 2 48

Right Side Outer Wall 1 16 0.75 2 24

Bath & Dress Wall 6 6 0.75 2 54

Kitchen Long Wall 1 8 0.75 2 12

Kitchen Short Wall 1 5.25 0.75 2 7.88

Boundary Walls 1 164 0.75 2.50 410

Total (Cft) 770.38

Total (CuM) 21.81

Single layer of tiles 10"x5"x1.25" laid over 4" earth and 1"
4.1.94 mud plaster on top of RC roof slab m2

Roof Slab 1 1364.87 Sft Area 1,364.87

Total (Sft) 1,364.87

Total (Sq.m) 127.01

Supply fabricate M.S reinforcement for cement concrete ( hot


4.2.95 rolled deformed bars Grad 40) Ton

RCC Total Quantity (cft) 536.47

Take 2% of concrete Quantity (lbs) = 2.00% 536.47 490 5,257.41

Total Quantity (Tonnes) 2.39


RCC in roof slab , beam , column and other structural member
4.2.96 , in sithu or precast.type C 1:2:4. m3

C-1 2 0.75 0.75 2.37 2.67


Construction of Siran Right Bank Canal
District Mansehra
MEASUREMENT SHEET OF CHOWKIDAR HUT
Item
Description Unit Nos Length Width Depth Volume
No
C-2 12 0.75 0.75 2.37 16

Plinth Beam 1 232.92 0.75 0.75 131.02

Column NSL to Top

C-1 2 0.75 0.75 10.00 11.25

C-2 12 0.75 0.75 10.00 67.5

Lintel 1 50 0.75 0.75 28.13

Beam 1 37.5 1 1 37.5

Slab 1 1364.87 0.5 0

Parapet Wall 1 150.00 0.5 2.00 150

Total (Cft) 444.07

Total (CuM) 12.57


RCC in raft foundation slab, base slab of column & ret.
4.2.97 wall etc, not including in 06-06. Type C(1:2:4) m3

Base slab of Column

C-1 2 5.25 5.25 1.125 62.02

C-2 12 1.5 1.5 1.125 30.38

Total (Cft) 92.4

Total (CuM) 2.62

Plain Cement Concrete including placing, compacting,


4.2.98 finishing & curing (Ratio 1:4:8) m3

Column C1 12 5 5 0.5 150

Column C2 2 6 6 0.5 36

Bed Room, Bath Room, Dressing,kitchan, 1 208 2.25 0.50 234

Boundary Wall 1 174 2.25 1.13 440.44

Total (Cft) 860.44

Total (CuM) 24.36

Excavation in foundation of building bridges etc complete in


4.2.99 Shingle gravel. m3

Column C1 12 6 6 3 1296.00

Column C2 2 7 7 3 294.00

Bed Rooms, Bath Room, Dressing,kitchan, 1 190 3.5 3 1995.00

Boundary Wall 1 174 3.5 3 1827.00

Total (Cft) 5412

Total (CuM) 153.25

4.2.100 P/F Fiber glass Water Tank 300 gallons. No 1

Total 1.00

Supply and fixing of 2.0 HP Monoblock water pump


4.2.101 1.5"x1.25" 3 stage model DE-S3 (Deen Pump) single No 1
phase for 150 ft head with all accessories.
Construction of Siran Right Bank Canal
District Mansehra
MEASUREMENT SHEET OF CHOWKIDAR HUT
Item
Description Unit Nos Length Width Depth Volume
No
Total 1.00

Making and fixing steel grated doors, complete with locking


4.2.102 arrangements & angle iron frame m2 2.5 2 5.00

Total 5.00
Construction of Siran Right Bank Canal
District Mansehra
Rate Analysis of NSI

Description of item

Providing and fixing air/water relief valves

Details Qty Unit Rate (Rs.) Amount


MATERIAL
Air relief valve 1 No. 64000 64,000.00

LABOUR
Plumber 0.07 Day 1200 84

Sundries (Labour only) 3% 2.52

Total labour 86.52

Cont. profit + overheads


(Material+labour 22% 14,099.03
equipment)

Composite rate per Each 78,185.55