Professional Documents
Culture Documents
Ballard, Tommelein - 2012 - Lean Management Methods For Complex Projects
Ballard, Tommelein - 2012 - Lean Management Methods For Complex Projects
Ballard, Tommelein - 2012 - Lean Management Methods For Complex Projects
21]
On: 23 January 2015, At: 13:12
Publisher: Taylor & Francis
Informa Ltd Registered in England and Wales Registered Number: 1072954 Registered office: Mortimer House,
37-41 Mortimer Street, London W1T 3JH, UK
To cite this article: Glenn Ballard & Iris Tommelein (2012) Lean management methods for complex projects, Engineering
Project Organization Journal, 2:1-2, 85-96, DOI: 10.1080/21573727.2011.641117
Taylor & Francis makes every effort to ensure the accuracy of all the information (the “Content”) contained
in the publications on our platform. However, Taylor & Francis, our agents, and our licensors make no
representations or warranties whatsoever as to the accuracy, completeness, or suitability for any purpose of the
Content. Any opinions and views expressed in this publication are the opinions and views of the authors, and
are not the views of or endorsed by Taylor & Francis. The accuracy of the Content should not be relied upon and
should be independently verified with primary sources of information. Taylor and Francis shall not be liable for
any losses, actions, claims, proceedings, demands, costs, expenses, damages, and other liabilities whatsoever
or howsoever caused arising directly or indirectly in connection with, in relation to or arising out of the use of
the Content.
This article may be used for research, teaching, and private study purposes. Any substantial or systematic
reproduction, redistribution, reselling, loan, sub-licensing, systematic supply, or distribution in any
form to anyone is expressly forbidden. Terms & Conditions of access and use can be found at http://
www.tandfonline.com/page/terms-and-conditions
The Engineering Project Organization Journal (March–June 2012) 2, 85–96
This paper reviews the principles, history, applications and current research issues associated with lean construc-
tion, in order to provide a foundation for future research in this area. Lean is a management approach that
emerged in the automobile industry and spread initially to other forms of repetitive manufacturing and ultimately
Downloaded by [171.67.216.21] at 13:12 23 January 2015
to service industries. Despite its success in practice, the lean philosophy and methods have not been fully eval-
uated and incorporated into the academic literature. The question remains to what extent lean management
methods are unique and beneficial and how they are related to principles and models in management
science, production management and related fields. One of the relevant issues is the adequacy of lean
methods to the management of complex projects. As project complexity increases, emergent phenomena
increase. Consequently, leadership must become more adaptive and less prescriptive in order to be successful.
This paper describes some of the key lean management methods that deliver better outcomes on complex pro-
jects and also the interdependence of these methods with the structuring of commercial terms and organizational
integration. It also describes the relationship between lean project management methods and conventional
methods, and the limitations of both, and suggests directions for future research.
redeveloping Japan. To that end, the Japanese were tags used to communicate requests for specific com-
taught management methods. Most famous were the ponents from one factory workstation to another. Alter-
courses given by Joseph Juran, W. Edwards Deming natively, visual signals, such as empty bins, are used to
and other experts in quality management. Management replenish inventories of parts installed at different work-
training also extended down to direct supervisors. stations. In construction, some companies are having
Toyota is said to still use the Training Within Industry vendors manage inventory replenishment based on
courses in Job Instruction, Job Methods and Job computer information systems that record withdrawals,
Relations (Dinero, 2005). much like the grocery stores that Ohno had observed
So the story goes (Ohno, 1988) that Toyota visited (Ohno, 1988; Elfving et al., 2010). As we will see in
the automotive manufacturers in the USA, but found the later discussion about the Last Planner System,
their way of producing vehicles inappropriate for requests are made directly between the individuals
Toyota. At that time, Toyota was restricted to a national responsible for different, interdependent types of
market and had quite a low demand, but for a wide works, for example, between architects and structural
variety of vehicles. The expensive, high-volume engineers or between pipefitters and electricians.
machines used by Ford and General Motors were not Understanding of Toyota’s contribution has changed
needed and could not be afforded. Engineer Ohno over time. It was initially understood in terms of manu-
was challenged by Toyota’s CEO to overcome within facturing, how products were made in the Toyota Pro-
three years the 9:1 productivity disadvantage the duction System. Harvard’s research on product
Downloaded by [171.67.216.21] at 13:12 23 January 2015
company had relative to US producers and to do so in development (Clark and Fujimoto, 1991) expanded
a way appropriate to Toyota’s circumstances, that is, this understanding from only making to designing and
producing small numbers of a wide variety of products. making. Ward et al. (1995) published a provocative
Ohno reports that he was much taken with the method article in the Sloan Management Review titled ‘The
of restocking American grocery store shelves, a method Second Toyota Paradox’, which offered a solution to
he labelled ‘pull’ as distinct from the ‘push’ observed in the puzzle how Toyota can spend more time on more
US motor vehicle fabrication and assembly plants prototypes and still develop new products faster and
(Ohno, 1988). Customers pulled replacement inventory less expensively than anyone else. This introduced
onto shelves by purchasing and removing them. This another fundamental principle, namely to apply all rel-
seemingly simple idea became the fundamental lean evant criteria to the evaluation of design alternatives sim-
principle: Do work only on customer request. ultaneously. The authors named this ‘set-based
Ohno also identified seven forms of waste, of which engineering’ as distinct from the point-based one. The
‘overproduction’, doing work before it is needed, was underlying issue is how projects are structured, as
said to be the cause of other forms of waste—to be sequential or as organizationally integrated processes.
avoided by pulling. Ohno’s seven forms of waste are Since design criteria are best applied by those expert in
as follows: various specialities, these specialists must be members
of an integrated team in order to realize the principle.
(1) Defects in products Yet another expansion in understanding Toyota’s
(2) Overproduction of goods not needed contribution came in 2003 with the publication of
(3) Inventories of goods awaiting processing or Jeffrey Liker’s The Toyota Way, in which Toyota’s phil-
consumption osophy was presented as a general and fundamental
(4) Unnecessary processing philosophy of management, based on 14 principles
(5) Unnecessary movement of people (Liker, 2004):
(6) Unnecessary transport of goods
(7) Waiting by employees for process equipment to (1) Base management decisions on long-term phil-
finish work or for an upstream activity to com- osophy even at the expense of short-term finan-
plete. (Ohno, 1988) cial goals.
(2) Create continuous process flow to bring pro-
Expressed in this list are the basic elements of the lean blems to the surface.
philosophy of management: ‘lean’ consists of an ideal to (3) Use ‘pull’ systems to avoid overproduction.
be pursued, principles to be followed in that pursuit and (4) Level out the workload (heijunka)––work like
methods to be used to apply the principles. The ideal is the tortoise, not the hare.
to deliver exactly what your customer (immediate or (5) Build culture of stopping to fix problems to get
ultimate) needs, with no waste.1 A representative prin- quality right the first time.
ciple is to only do work on customer request. Different (6) Standardized tasks as the foundation for con-
methods have been developed for applying this principle tinuous improvement and employee
in different circumstances. For example, kanban are empowerment.
Lean Management Methods 87
(7) Use visual control so no problems are hidden. transformation of inputs into outputs (Koskela, 2000).
(8) Use only reliable, thoroughly tested technology More recently, he has discovered the historical under-
that serves people and processes. pinnings of the 1960s shift in management education
(9) Grow leaders who thoroughly understand the and research from a foundation in production to a
work, live the philosophy and teach it to others. focus on quantitative methods, economics and the be-
(10) Develop exceptional people and teams who havioural sciences. This shift, now 50 years running,
follow your company’s philosophy. has been repeatedly criticized for its lack of relevance
(11) Respect your extended network of partners and to management practice (Ackoff, 1979; Barley and
suppliers by challenging them and helping Kunda, 2001). Koskela now calls for an end to a
them improve. failed experiment and a return to management edu-
(12) Go and see for yourself to thoroughly under- cation and research with a foundation in production
stand the situation (genchi genbutsu). (Koskela, 2011).
(13) Make decisions slowly by consensus, Application of lean to practice has not been neg-
thoroughly considering all options; implement lected. Leadership has been provided by the Lean Con-
rapidly. struction Institute (http://www.leanconstruction.org),
(14) Become a learning organization through relent- founded in the USA in 1997 by Gregory Howell and
less reflection (hansei) and continuous Glenn Ballard (http://www.leanconstruction.org).
improvement (kaizen). It has proven impossible to simply imitate many of the
Downloaded by [171.67.216.21] at 13:12 23 January 2015
(2) project phases are conceptualized as interlinked Another limitation in the applicability of lean methods is
triads, and development within phases is under- also apparent as regards automated processes. Process
stood to occur through a kind of ‘conversation’, plants may benefit from lean in their design and construc-
consistent with the fundamental lean principle to tion, but there appears to be little place for lean methods in
do work only on request, discussed in the next their operation. Perhaps the underlying issue is the human
section, role in operation––or rather the lack of such a role—and
(3) decisions regarding product and process design are the existence of a continuous flow process to start with.
to be made together, and If humans need not cooperate in order to produce some-
(4) work structuring (process design at every system thing, the applicability of lean methods appears to be
level) and production control are the primary reduced. When product flows continuously, there is no
management methods for governing project deliv- need for the rule ‘Do work only on request’. Conformance
ery through all its phases. to the rule is built into the process flow itself and is gov-
erned by automated controls. The lean ideal can still be
pursued in the designing of automated production
systems, and there is very likely need for lean methods in
From repetitive manufacturing to projects
maintenance, but operations appear to be off-limits. We
Figure 2 obtained from Schmenner (1993), who adapted return to this interesting question of limitations and con-
it from Hayes and Wheelwright’s (1979) typology of pro- textualization of lean in the fifth section.
duction systems, shows the range of systems for making Although many of Toyota’s manufacturing methods
things, from those in which the product flows continu- are applicable to construction, Toyota’s product devel-
ously (liquids and gases) to job shops and projects. opment system is the true counterpart to construction.
Product mix varies from standard products in very high Everything that is mass-produced is first produced in a
volumes to one of a kind or few. Process pattern varies product development system, which stops when repeti-
from rigid, automated flows to very jumbled flows, with tive manufacturing begins. Construction projects have
process segments loosely linked. Brink and Ballard the same scope; use of the product begins after con-
(2005) noted that lean manufacturing has been success- struction ends.
ful in converting batch flows into line flows, whether The difference between manufacturing’s product
worker paced or machine paced, and explored the development and construction projects is that the
limits to applying manufacturing cells, a specific lean former develop the means for producing multiple
method, to job shops and projects, based on the size copies of a product, while the latter produce only the
and temporal duration of product families.2 prototype and do not produce copies.
Lean Management Methods 89
Downloaded by [171.67.216.21] at 13:12 23 January 2015
Construction’s products are rooted in location and In the U.S., and broadly in the international commu-
are highly impacted by their physical, social, environ- nity, lean construction has been taken up with the
mental and aesthetic contexts. Automobiles, refriger- idea that the project is a more fundamental form of
ators and wrist watches may be used anywhere on the production system than the factory. For the author,
planet, regardless of where they are made. Buildings, construction is one of many types of projects for
bridges, factories, highways, tunnels and dams must which theorists and practitioners are developing
be adapted to their locations. Differences in meteorolo- theory and tools, alongside air and sea shipbuilding,
gical and seismic conditions alone demand adaptations performing arts productions, software development,
of otherwise standard designs. Differences in regu- product development, fabrication (job) shops, oil
lations and codes, in the demand for aesthetic field development, health care delivery and work
harmony and in the availability and cost of (local and order systems such as plant maintenance.
distantly sourced) materials and many more differences
further increase the demand for adaptations to context. The argument for the project being the most funda-
mental form of production system is that all products,
mass-produced or custom, are first designed and
made in a project, specifically in a type of product devel-
Competing approaches to bringing lean into
opment system. Construction is one type of product
construction
development system, dedicated to designing and
Some attempts to bring lean into the construction making (producing) engineered-to-order (aka
industry have proposed to make construction into ‘custom’) products that are rooted in the earth. Some
repetitive manufacturing. Standardization of product products, traditionally understood as products of con-
design is expected to enable application of repetitive struction, such as fabricated housing, may be subject
manufacturing methods. This seems to be a particularly to repetitive manufacturing methods in offsite fabrica-
strong view in the UK, reflecting the influence of the tion shops, as are many of the components that are
Egan Report (Egan, 1998). assembled into custom facilities; consider basic
This has not been the dominant view among lean materials such as wallboard, lumber and nails and also
construction proponents, who are better represented more complex components such as motors and
in the following excerpt from ‘Construction: One pumps. Other components, such as turbines and com-
Type of Project Production System’ (Ballard, 2005): pressors, are typically engineered-to-order, but can be
90 Ballard and Tommelein
built in one place and used elsewhere. It is the design of avoid overproduction’ and principle #4 ‘Level out the
the whole that makes a product engineered-to-order, workload (heijunka) – work like the tortoise, not the
not the design from scratch of every component. hare’. We return to this issue of the limitations on appli-
For those who see construction in terms of engin- cation of the lean philosophy in the fifth section.
eered-to-order products, the larger challenge of lean
construction is to learn how to manage all types of
project production systems. What principles and Last planner: a lean project management
methods apply to all? Which principles and methods method
require adaptation to differences in the work being per-
formed in each type of project production system? This section describes one key lean project management
To take one example, lean has been applied very suc- method, the Last Planner System. The development of
cessfully to oil field production, conceptualizing each the Last Planner illustrates the adaptation of lean prin-
well as a project moving through a multi-project proces- ciples and methods from their origin in repetitive man-
sing system. The approach taken was to reduce variation ufacturing to the project domain.
in work flow as wells moved through a series of pro- Last Planner originated in 1992, in the discovery that
cesses from the design of the well by engineering to only 54% of tasks on weekly work plans were com-
putting oil and gas in pipelines where they add to sell- pleted, on average, on numerous projects of seven
able product inventories (Ballard, 2007). The reduction highly regarded construction companies (Ballard and
Downloaded by [171.67.216.21] at 13:12 23 January 2015
in workflow variation allowed resources to be reduced Howell, 1998). In most cases, labour capacity was
to match the lower workload peaks, resulting in a diverted to other tasks, making this phenomenon invis-
saving of 25% in development costs and a reduction ible to those focusing only on productivity and on pro-
of 32% in cycle time (Figure 3), not to mention the gress. Tasks may have been done out of sequence, but
additional profits from increased capital turns. Each the rework penalty for doing so would be felt later.
point in the graphic shown in Figure 3 represents the This was discovery of an underlying determinant of his-
cycle time of a well from the start of drilling to torical norms, so the corresponding unit rates and unit
product flowing into the pipeline. Although there costs did not signal the need or opportunity to
remain a few outliers, the reduction in variation after improve performance.
implementation of lean methods is evident. The research findings were initially interpreted within
Adaptation was needed to the oil field environment, the conceptual framework of productivity improvement
but the lean ideal was held constant, as were many of to explain the low productivity of crews and design
the lean principles already found in the Toyota Way; squads that had to shift from one task to another.
for example, principle #3: ‘Use “pull” systems to Once introduced to the lean manufacturing literature,
it became apparent that the major impact on perform- With this insight, the disruptive character of the Last
ance was from poor work flow reliability. Work plans Planner System and lean, in general, began to become
made within one week of execution were very poor pre- apparent. Construction projects had previously been
dictors of work released to following ‘trades’ one week practised largely through command and control, with
later. At 54% percent plan complete (PPC), the tasks assigned as orders, reinforced by contractual
chance that the current plan will accurately predict the penalties. Commitments were neither requested nor
work available to be done next week was almost that given (Howell and Ballard, 1994a). Understanding of
of a coin toss. Given this fact, it would be no surprise the extent to which fundamental change is required in
if design squad bosses and construction foremen were industry practice has continued to grow from this orig-
to give up extensive preparation for performing specific inal insight.
tasks and rather be satisfied to do whatever work hap-
pened to be available. It became apparent that the invisi-
The lookahead (make-ready) process
bility and low reliability of work flow were major
contributors to the poor productivity in construction Improving PPC was expected to improve productivity
compared with other industries. by increasing certainty of work available the following
week and hence preparation for performing those
tasks. However, it was understood that PPC could be
Weekly work plans
100% and the project could still fail to progress on sche-
Downloaded by [171.67.216.21] at 13:12 23 January 2015
The Last Planner System was designed in stages, dule. Progressing on schedule is rather a function of
working from bottom (weekly work plans) to top making the right tasks ready to be performed at the
(project schedules). The first problem was as to how right time. A new and improved lookahead process
to improve PPC, the percentage of planned tasks com- was proposed to perform this function, principally
pleted as planned. Four quality criteria for assignments through meticulous identification and removal of con-
on weekly work plans were proposed to improve the straints on tasks scheduled to be performed in the
PPC of these plans: definition, soundness, sequence next six weeks (Howell and Ballard, 1994b). On reflec-
and size. These were rules for selection and formation tion, a name different from ‘lookahead’ might have
of task assignments intended to shield direct production avoided confusion with traditional lookahead processes
from upstream variation (Ballard and Howell, 1994a). in construction, which have not made transparent the
status of future work, but rather have functioned as
(1) Definition: An assignment is adequately defined early warnings of mobilization: ‘You will be ready to
when those who are to perform the assigned task form the interior basement walls two weeks from now,
can determine if and how to perform it and what right?’. These are not requests for commitments, but
instructions, materials, special tools, special thinly disguised commands to which the expected
skills, access, equipment, etc. are needed. response is ‘Aye aye, sir’.
(2) Soundness: An assignment is sound if all con- Typical constraints for tasks were identified and
straints that can be removed prior to the plan spreadsheets, like the one given in Table 1, were used
period have been removed, and if those who for status constraint removal and the soundness of
are to perform the task are confident, the scheduled tasks.3
remaining constraints can be removed during In weekly Last Planner meetings, managed usually by
the plan period. the superintendent (construction) or the design
(3) Sequence: An assigned task is in the proper manager (design), the supervisors of the various special-
sequence when it is critical, in critical path ists review tasks scheduled to be performed in the next
method (CPM) terms, when its immediate cus- three to six weeks and accept responsibility for removing
tomers will be ready to work on its product at constraints. The rule is to notify the team immediately if
release and when performing the task now does one loses confidence that constraints can be removed in
not incur a later rework penalty. time to start the task when scheduled. Note the differ-
(4) Size: Tasks are assigned within the capabilities of ence from waiting until you are sure you cannot
those who are to perform the tasks. remove a constraint to notify the team. A early
warning provides more time and resources for removing
Once the importance of work flow reliability was the constraint or, if this is not possible, for replanning
understood, this led naturally to the realization that per- around the constrained task.
sonal commitments were needed between interdepen- As shown in Figure 4, the design of work methods has
dent front-line supervisors, aka ‘last planners’, been considered part of the lookahead planning process
followed quickly by a second realization, namely that since the initial design of the Last Planner System
you cannot make a promise if you cannot say ‘no’. (Ballard and Howell, 1994b). The current thinking is
92
Table 1 Constraint analysis in the lookahead process
Contract/
Activity Planned Responsible change Design Prerequisite
ID Activity description start date party orders Materials Labour Equipment work Space Sound? Comments
Requests for
Drawings Information
complete Submittals (RFIs)
11 Rebar erection for first- 15 January Rebar sub X X X X Delivery Monday X X X X
floor columns 5–8 2007 am
12 Electrical inserts/rough- 15 January Electrical sub X X X X X X X X X
Downloaded by [171.67.216.21] at 13:12 23 January 2015
yourself in their shoes, subject to the same competing definitively specified, with no risk of major change,
objectives, unclear information, delayed feedback, etc. then traditional management methods can be success-
For a number of reasons, the second type of accident ful. Such methods include sequential processing,
investigation is very difficult to do. For one thing, in a fixed-price contracting, reductionist work breakdown
short time after events, we begin reconstructing our structuring and reactive project control.
experience. But perhaps the biggest obstacle is the Sequential processing comes with a rework penalty,
desire to avoid blame and hence to withhold infor- in consequence of failing to consider all relevant
mation that is argued by Dekker to be critical in prevent- design criteria when forming, evaluating and selecting
ing reoccurrence of the accident. There is a tension from design alternatives. For example, reviewing
between the desire to learn and the desire to hold designs for constructability after they are fully devel-
people accountable for their actions—a tension which oped often reveals deficiencies in the designs. Rework
is exacerbated by cultures that prize knowing over is needed to correct these deficiencies. The risk of incur-
learning. ring the rework penalty, and the amount of rework to be
A number of different methods of root cause analysis done, increases directly with the extent of design inno-
have been proposed, but none have been systematically vation. If an existing design needs to be adapted only
employed in practice. The problem appears rather to be slightly to differences in location or capacity, the prob-
in behaviour than in methodology. Although it seems ability that the currently accepted ‘means and
quite clear that individuals have benefited enormously methods’ will prove to be inadequate is reduced.
Downloaded by [171.67.216.21] at 13:12 23 January 2015
from the rigorous testing of their ‘hypotheses’ about Fixed-price contracting, when based on nominally
reality, complete implementation of the learning com- complete design documents, is at risk for changes in
ponent of the Last Planner System remains elusive. the design, which provokes change orders, providing
contractors an opportunity to increase their profitabil-
ity. When competitive bidding is used as the basis for
Conclusion
contract award, bidders may rely on change orders for
The Last Planner System of production planning and all their profits or simply make them whole. This puts
control is disruptive to current project management the parties to the contract in an adversarial, zero sum
practices, if for no other reason, because requests game. To the extent that the scope is firm and design
replace commands. It has proven effective in stabilizing is complete, the risk of exploitation is reduced.
work processes, which is a prerequisite for substantial However, note that this does not reduce the risk to the
investments in optimization. Its principles include project of the difference in commercial interests of the
‘Plan in greater detail as the time for action approaches’ parties.
and ‘Produce plans collaboratively with those who will Work breakdown structuring is traditionally done to
do the work’ (Ballard, 2009a). The first conflicts with assure that all work scopes are assigned with no over-
the traditional practice of highly detailed master sche- laps or omissions. Subsequently, the created structure
dules. The second conflicts with imposing these sche- is used as the basis for contract management and
dules unilaterally on those who are to do the work. managerial control, which acts as if each contract
As projects become more complex and uncertain, the and node in the work breakdown structure was inde-
extent to which pre-programming is effective is pendent and hence could be optimized for duration
reduced, and dependence on proactive and opportunis- and cost as a means for optimizing the project. To
tic steering during project execution increases. Last the extent that the assumption holds, namely that
Planner is a method that facilitates steering in rough the parts of the whole are independent (i.e. the
seas. project is less complex), traditional work structuring
and the associated management practice can be
successful.
The limits of lean project management Traditional project control starts with the identifi-
cation of negative variances between SHOULD and
Lean project management is especially critical for suc- DID. This signals the need for management attention,
cessful performance of complex and uncertain projects. a scarce resource, which is to be expended on analysis
Traditional project management assumes a high degree and corrective action. This might be likened to driving
of certainty and levels of complexity sufficiently low that a car while looking in the rear view mirror. Maintaining
they can be buffered by adding time to schedules and the analogy, a more proactive concept of control is steer-
money to budgets and still keep projects economically ing the car towards its destination, which implies a man-
viable. The fundamental requirement for successful agement focus on the plan to complete rather than a
application of traditional, non-lean project management focus on how well you are performing relative to your
methods is scope stability. If what is wanted can be original plan. Obviously, traditional project control is
Lean Management Methods 95
the more appropriate choice when both project ends traditional methods. The greater the complexity, the
and means are fixed and definitive. more the lean methods are needed.
We have also identified a need for future research to
develop means for more accurately assessing the com-
A research challenge plexity of projects before they are started. Examination
of current risk management practices is a good starting
Deciding when to use lean or traditional methods of
point, because risk assessment is the current means for
project management is currently inhibited by inability
determining project challenge. If successful, this
to adequately evaluate project complexity and uncer-
research would enable designing project delivery pro-
tainty before project execution. There is little or no
cesses tailored to the challenge posed by each project.
empirically based knowledge on the distribution of pro-
Closely related to this research is the quantification of
jects along the continuum between simple and certain,
penalties imposed on users of traditional management
on the one extreme, and complex and uncertain, on
methods relative to the risks of project failure, where
the other extreme.6 Indeed, the relevant variables may
failure is not achieving business objectives within con-
not have been accurately identified.
ditions of satisfaction. Once we better understand
Project management research has focused its efforts
where a project lies on the continuum between simple
on reducing uncertainty (though with less focus on
and complex, more information will be needed in
complexity), with much less attention to managing in
order to make trade-off decisions.
conditions of uncertainty and complexity. If industry
Downloaded by [171.67.216.21] at 13:12 23 January 2015
struction: stabilizing wok flow. Proceedings of the 2nd Koskela, L. (1992) Application of the New Production Philosophy
Annual Meeting of the International Group for Lean to Construction, Center for Integrated Facilities Engineering
Construction, Santiago, Chile, (Available in Lean Technical Report #72, Stanford University, CA,
Construction, A.A. Balkema Publishers, Rotterdam, September 2002.
Netherlands, 1997). Koskela, L. (2000) An Exploration Toward a Production Theory
Ballard, G. and Howell, G. (1994b) Implementing lean con- and its Application to Construction, VTT Publications, Espoo,
struction: improving performance behind the shield. Finland.
Proceedings of the 2nd Annual Meeting of the International Koskela, L. (2011) Fifty years of irrelevance: the wild goose
Group for Lean Construction, Santiago, Chile, , (Available chase of management science. Proceedings of the 19th
in Lean Construction, A.A. Balkema Publishers, Annual Conference of the International Group for Lean
Rotterdam, Netherlands, 1997.). Construction, Lima, Peru, pp. 85–96.
Ballard, G. and Howell, G. (1998) Shielding production: Krafcik, J.F. (1988) Triumph of the lean production system.
essential step in production control. Journal of Construction Sloan Management Review, 30(1), pp. 41–52.
Engineering and Management, 124(1), 11–7. Levitt, R.E. (2011) Towards project management 2.0.
Barley, S.R. and Kunda, G. (2001) Bringing work back in. Engineering Project Organization Journal, 1(3), 197–210.
Organization Science, 12(1), 76–95. Liker, J. (2003) The Toyota Way, McGraw-Hill, New York.
Berggren, C. (1992) Alternatives to Lean Production, ILR Press, Nahmias, S. (1997) Production and Operations Analysis, Irwin,
Ithaca, NY. Chicago, IL.
Brink, T. and Ballard, G. (2005) SLAM––a case study in apply- Ohno, T. (1988) Toyota Production System: Beyond Large Scale
ing lean to job shops. Proceedings of the ASCE 2005 Construction Production, Productivity Press, Portland, Oregon.
Research Congress, April 2005, San Diego, CA, pp. 1–6. Schmenner, R.W. (1993) Production/Operations Management:
Clark, K.B. and Fujimoto, T. (1991) Product Development From the Inside Out, 5th edn. Prentice-Hall Inc,
Performance, Harvard Business Review Press, Cambridge, Englewood Cliffs, NJ.
MA. Schonberger, R.J. (1986) World Class Manufacturing, Free
Dekker, S. (2006) The Field Guide to Understanding Human Press, New York, NY.
Error, Aldershot, Ashgate, UK. Sobek, D.K.II, Ward, A.C. and Liker, J.K. (1999) Toyota’s
Dinero, D.A. (2005) Training Within Industry: The Foundation principles of set-based concurrent engineering. Sloan
of Lean, Productivity Press, New York. Management Review, 40(2), pp. 67–83.
Egan, S.J. (1998) Rethinking Construction, Report of the Ward, A., Liker, J.K., Cristiano, J.J. and Durward, K.S.II
Construction Task Force to the Deputy Prime Minister, (1995) The second Toyota Paradox: how delaying
John Prescott, on the Scope for Improving the Quality decisions can make better cars faster. Sloan Management
and Efficiency of UK Construction, Dept. of Trade & Review, 36(3), Spring 1995, pp. 43–61.
Industry. Womack, J. and Jones, D. (1996) Lean Thinking, Simon &
Elfving, J., Ballard, G. and Talvitie, U. (2010) Standardizing Schuster, New York, 350 p.
logistics at the corporate level––towards lean logistics in Womack, J., Jones, D. and Roos, D. (1990) The Machine That
construction. Proceedings of the 18th Annual Conference of Changed the World, MacMillan Publishing, New York.