Professional Documents
Culture Documents
Sandro Corsi 2
Sandro Corsi 2
Sandro Corsi 2
Abstract—The hierarchical voltage control system, currently with a dominant time constant of about 5 min, automatically
fully exploited in the Italian transmission grid and presented in updating all the pilot nodes voltage set-points. TVR aims to
Part I, improves voltage quality, network security and operation both minimize network losses and improve operation voltage
efficiency. This coordinated automatic system, operated by the
Italian ISO (GRTN), is subdivided into three hierarchical control security.
levels, requiring unconventional regulation apparatuses. They The activities involved in practical application of the multi-
are the Voltage and Reactive Power Regulator (REPORT) at the level hierarchical control system in the Italian transmission grid
power plant level, the Regional Voltage Regulator (RVR) at the are very advanced and are expected to be completed shortly.
regional dispatcher level, and the National Voltage Regulator
They include field commissioning of about 35 plant regulators
(NVR) at the ISO control center. This survey paper provides a
general description of the characteristics of these new automatic (REPORT) [5], [6] and three regional regulators (RVR) [7], the
control apparatuses and of the interventions required on existing majority of which (32 REPORTs and two RVRs) are already
equipment for their installation, activation and operation. A brief in operation. The Italian power plants involved are the largest
presentation of the main dynamic performance of the hierarchical hydraulic, thermal and combined-cycle plants, having in total
control system, from the inner to the outer control loops, is also
more than 150 generators with an overall capability of about
given with reference to laboratory, commissioning and field tests.
20 000 MVAR. The NVR control apparatus [8] is a combi-
Index Terms—Automatic control, coordinated voltage control,
nation of a Tertiary Voltage Regulator (TVR), optimizing and
multi-variable hierarchical control, optimal reactive power flow,
reactive power, reactive power coordination, secondary and ter- controlling RVR voltage set-points in real-time, and a Losses
tiary voltage regulation, stability margins, transmission losses, Minimization Controller (LMC), forecasting by an Optimal Re-
voltage, voltage ancillary service. active Power Flow (ORPF) the network voltage, and reactive
plan used by TVR as a reference input. NVR is under devel-
opment for the ISO national control center and will be ready
I. INTRODUCTION
within 2004.
Authorized licensed use limited to: TU Ilmenau. Downloaded on May 06,2022 at 06:33:49 UTC from IEEE Xplore. Restrictions apply.
1734 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 19, NO. 4, NOVEMBER 2004
Authorized licensed use limited to: TU Ilmenau. Downloaded on May 06,2022 at 06:33:49 UTC from IEEE Xplore. Restrictions apply.
CORSI et al.: COORDINATED AUTOMATIC VOLTAGE CONTROL OF THE ITALIAN TRANSMISSION GRID—PART II 1735
orized EHV bus voltage daily trends, etc.) and synthetic com- local reference) or the stored profiles (automatic local
mands through a functional keyboard. All the control parame- reference). Otherwise it is received by remote from
ters, as well as the EHV bus voltage daily trends, can be modi- TVR. Tracking functions among pilot node voltage
fied directly using a friendly editor. calibrators and corresponding controlled magnitudes
enable switching between the RVR’s different oper-
B. Installation and Interfacing Requirements ation modes at any time without causing noise for
Putting REPORT apparatuses in service is the first, but also controlled variables.
the most onerous of the activities involved in practical applica- For each area, one or two vicarious pilot nodes can be chosen
tion of the hierarchical voltage control system. In fact, the large to deal with possible tele-measurement equipment failures at
number of power plants involved demands significant efforts, the main pilot node. The configuration of the control system
costs and organization, in particular for managing plant modi- in the region can be also modified taking into account network
fications (often requiring short unit out of services) and instal- changes and in response to requests coming from TVR. The
lation activities (mainly involving interfaces with the excitation regulation areas can be configured on-line in terms of control
systems and the plant control room). The AVR modifications plants (participating in pilot node voltage control), peripheral
concern the static high-precision calibrator and the adoption of plants (performing local high side voltage control), stations re-
static relays, with optical insulated up/down commands. In op- active reserves under SVR control and control law parameters.
eration, REPORT also requires automatic restraint of control In particular network configurations, some control plants may
room AVR up/ down commands, opening of the AVR com- gravitate to an area close to that they electrically belong to, due
pound feedback and signaling of allowed rotor overloading to to their geographic position. These boundary plants, considered
REPORT. peripheral ones in the initial configuration, can either participate
in tele-control of their pilot nodes or of the neighboring ones, as
III. THE RVR APPARATUS: FUNCTIONAL DESIGN AND the grid configuration varies.
TECHNOLOGICAL ISSUES In the automatic operation mode, based on local reference,
the set-point value of each pilot node voltage is automatically
RVR [7] is installed at the regional control centers of the updated on the basis of a voltage profile associated with the cur-
Italian ISO (GRTN). It is implemented in a workstation inte- rent day and stored in the RVR. The voltage daily generic profile
grated with the local EMS for achieving plant data acquisition consists of 96 values corresponding to the set-point values to put
and communications. RVR software architecture basically con- into operation every quarter of an hour. During such an interval,
sists of a real-time cycle with control functions executed within the reference of the pilot node voltage is automatically updated
a time interval of 500 ms. The RVR software has been devel- every minute, on the basis of a tracking ramp, from the current
oped to permit easy adaptability of the control apparatus to the reference value to that foreseen for the start of the subsequent
features of the regional grid it is applied to. quarter of an hour.
A suitable simulation function permits RVR operation sim-
A. Control and Protection Requirements
ilar to an actual case without requiring activation of its inter-
RVR regulates at the same time, but with independent and faces with the plants. This function is a very useful tool, both
parallel operation, the voltages of its pilot nodes through real- during the RVR functional test phase and factory setting up and
time remote control of the reactive power productions of those for operator training. The simulated region is described with
power plants with the greatest impact on pilot node voltages. a model taking significant aspects into account, useful for the
For this purpose, RVR defines and updates the value of its area reconstruction of phenomena connected with network voltage
reactive power levels through a separate voltage regulator for regulation. Specific operator commands permit load variations,
each pilot node in the region, whose main characteristics are: network perturbations, failure signals from the plants or from
– the regulation law is of the proportional-integral type, the tele-operation equipment, incorrect values of tele-measure-
with an adaptive control algorithm which keeps loop ments, interfacing with TVR, etc.
dynamics unchanged in real-time, taking into account The RVR has two types of automatic acquisition and storage
the number and actual capabilities of the plants partic- functions for transient phenomena. The first type concerns tran-
ipating in pilot node voltage regulation, as well as the sient trends in ordinary operation and records all the measure-
equivalent external reactance experienced by the pilot ments and signals related to the RVR operation every 5 min,
node; adequately filtered. These acquisitions are always active and do
– full dynamic de-coupling among different pilot node not require any triggering, since they document RVR operation
voltage control loops within the same region, to avoid over the last ten days. The second type concerns fast transients,
oscillations of reactive power between neighboring and keeps a high density record (one sample every 500 ms for
areas: for this purpose it is also possible to select a 5 min) of perturbations significantly affecting RVR dynamics:
positive, null or negative static droop for pilot node this acquisition is enabled by appropriate triggers, which recog-
voltage regulation; nize a heavily disturbed situation in the network and also include
– each pilot node voltage regulator can be started pre-trigger features.
without any preliminary manual alignment of control RVR apparatus is provided with auto-diagnostic functions for
generator voltages, and its set point value can be deter- detection of possible failures inside itself or at the EMS inter-
mined locally by either the manual calibrator (manual face. RVR also includes diagnostics tests to acknowledge and
Authorized licensed use limited to: TU Ilmenau. Downloaded on May 06,2022 at 06:33:49 UTC from IEEE Xplore. Restrictions apply.
1736 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 19, NO. 4, NOVEMBER 2004
Fig. 3. RVR graphical interface: Lombardy regional topographic and Milan1 area regulation block diagram.
signal the principal failure conditions which can be attributed IV. THE NVR APPARATUS FUNCTIONAL DESIGN AND
to apparatuses interconnected with RVR (anomalous input sig- TECHNOLOGICAL ISSUES
nals, failed execution of commands sent outside, etc.). More NVR [8] includes the real-time regulator TVR and the op-
precisely, the RVR verifies I/O magnitudes, detects particular timal forecasting controller LMC: the description below mainly
operating conditions in the controlled region (area in island op- refers to the real-time regulator. TVR software architecture basi-
erating condition, area close to the voltage instability limit) and cally consists in a computing cycle, with control functions exe-
checks the effect of control actions undertaken, so as to allow cuted every 500 ms, and in a set of MMI facilities allowing easy
failure diagnosis on RVR-interfaced devices. configuration of the TVR control system based on the subdivi-
sion of the network into regions, regulation areas, pilot nodes,
B. Graphical User Interface Requirements
and control plants.
All RVR graphic interfaces are implemented in X-Window TVR has two main objectives: minimizing network losses and
Motif environment (see Fig. 3). MMI pages are shared into var- increasing load margins in the transmission network in response
ious sets, the main of which is the real-time operation. Each set to heavy operating conditions (critical from the voltage stability
is organized in levels, allowing easy, organic navigation starting viewpoint). These goals are basically achieved by proper coor-
from a basic topographical map. Pages associated with subse- dination between the TVR and the SVR: TVR establishes net-
quent levels concern narrower portions of the controlled region work voltages by updating the voltage set-points optimization
and show a more detailed information content through area top- of the pilot nodes, at any cycle. The TVR uses the last avail-
ographical maps, area and power plant functional block dia- able minimum losses ORPF as the voltages-reactive powers ref-
grams and tables. Each page enables RVR commands to con- erence and achieves minimum feasible losses by minimizing a
trol the displayed regulated environment and shows the relevant real-time control function OF (see Part I).
alarms and signals. According to the Motif standard, all com- The load margin is maximized by the automatic and real-time
mands can be given with the mouse. Further MMI pages are coordinated control contemporarily exercised by SVR on all the
organized in the following environments: power system’s reactive resources, according to the SVR’s con-
– control configuration, inside which the parameters trol philosophy. In terms of stability, TVR and RVR’s operate
defining the regulating system structure and dynamic to prevent units from reaching their over-excitation limits: in
performance can be displayed, modified and stored; the presence of the TVR, this condition is in fact related to the
– voltage profiles, where the daily trends of pilot node tap-changer reverse action which normally anticipates the trig-
reference voltages are managed; gering of the voltage collapse mechanism. Whenever the reac-
– stored transients, where traces of recordings previ- tive power control margins made available to SVR are strongly
ously made can be displayed; reduced as a result of severe perturbations or abnormal load pat-
– chronological events, showing the sequence of relevant terns, the TVR attends the grid voltage reduction to the min-
events in the area (alarms, signals, etc.); imum allowed by the operating conditions, progressively re-
– test perturbations, allowing the canonical stimulation nouncing the not applicable optimal forecasted grid voltage pro-
to perform tests on real system dynamics; file. The TVR will therefore avoid the risk of instability by al-
– simulation, in which specific commands define the op- lowing the power plants under SVR to operate at their capa-
erating condition of the network-plants and reconstruct bility limits only when transmission network voltages are very
different failures on measurements and signals; low even though all the network’s reactive power resources are
– historical file, where disk files (regulation parameters, engaged for voltage support. In this way there is a reduced risk
control configurations, stored voltage profiles, tran- of the triggering of a voltage collapse in response to interven-
sient records, etc.) can be displayed, analyzed, and tion of over-excitation limits, and the overall loadability of the
maintained. transmission system is increased.
Authorized licensed use limited to: TU Ilmenau. Downloaded on May 06,2022 at 06:33:49 UTC from IEEE Xplore. Restrictions apply.
CORSI et al.: COORDINATED AUTOMATIC VOLTAGE CONTROL OF THE ITALIAN TRANSMISSION GRID—PART II 1737
Fig. 4. TVR graphical interface: Italy national topographic and Milan2 area regulation block diagram.
A. TVR Control and Protection Requirements and used by the TVR. If the TVR recognizes significant differ-
TVR design is based on a dedicated workstation interfaced ences between expected and real system operating conditions,
with GRTN communication subsystems for the exchange of in- it requires the LMC to compute the updated optimal forecasted
formation with the field data and basically with the RVR’s. De- voltage plan based on the last system state estimation (which, in
velopment of the TVR involves configuration of the information the best case, could refer to about five minutes before). This de-
exchange and the design of the software code for monitoring layed ORPF will be continuously computed by LMC every state
and control functions, centralized services, real-time data-base estimation update and sent to the TVR until the stored and new
and the man-machine interface. In particular, TVR data-base re- optimal forecasted voltage plans resemble each other. In addi-
quirements regard stored data types, required refreshing times tion, the LMC shows and compares, for each area, on-progress
and access violation problems. TVR has two classes of tran- daily traces of the pilot node voltage and required set-point, the
sient acquisition for normal and perturbed operation of signif- reactive power levels operating on the plants and the optimal
icant area control variables. Long sampling traces throughout forecasted references used by the TVR.
the day for each pilot node voltage, voltage set-point and reac-
tive level give a clear view of control system performance. On V. FIELD PERFORMANCE OF THE ITALIAN NETWORK
the other hand, fast sampling traces lasting a few minutes, with
VOLTAGE CONTROL SYSTEM
a pre-trigger mechanism, offer strong support for correct recon-
struction of dynamic phenomena. The main dynamic performance results, checked during com-
missioning field tests, are described in brief below for each sub-
B. TVR Graphical User Interface Requirements system under Italian coordinated voltage control:
All graphic interfaces are implemented by the X-Window – Power Plant Reactive Power Regulator (REPORT);
Motif environment (see Fig. 4). The MMI pages are shared in – Pilot Node Regional Voltage Regulator (RVR).
different environments, very similar to those conceived for the Some information is also given on the expected performance of
RVR, to achieve a common look and use. They are organized in the National Tertiary Voltage Regulator (TVR).
levels to allow an easy and friendly navigation, starting from a
Basically, commissioning activities can be subdivided be-
basic topographical map. Pages associated to subsequent levels
tween tasks at the power plant level (involving REPORT) and
concern narrower portions of the controlled nation and show in-
tasks at the regional control center level (involving RVR).
formation in greater detail through topographical regional maps
and area block diagrams and tables. Each page enables TVR
commands for controlling the displayed regulated environment A. REPORT Commissioning
and shows relevant alarms and signals. In the laboratory, REPORT type tests were fully carried out
in a closed loop through the use of the turbine-generator-net-
C. LMC Forecasting Optimization Requirements work real-time simulator [10]. Detailed acceptance and func-
The second NVR main function is achieved by the LMC con- tional tests were also carried out during the commissioning and
troller, which defines the optimal forecast voltage plan required monitoring phases on each of the REPORT apparatuses now in
as input by the TVR. This very slow off-line ORPF computing operation in the Italian power system, with very satisfactory re-
is the main LMC activity, taking into account the estimation of sults. In particular, in the plant, after verifying the coherency
system state and the constraints determined by the hierarchical between AVR and REPORT limit settings and the adequacy of
structure of the SVR and its control ties (pilot nodes and con- control parameters (for instance the external reactance seen by
trol power plants). On the basis of a forecasted state estima- the power station), defined dynamic transients were carried out,
tion, LMC computes in advance (i.e., the day before) the provi- following step perturbations of the respective set-points. The re-
sional optimal voltage and reactive power plan, which is stored sults shown in Figs. 5 and 6 refer to the Edolo hydraulic power
Authorized licensed use limited to: TU Ilmenau. Downloaded on May 06,2022 at 06:33:49 UTC from IEEE Xplore. Restrictions apply.
1738 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 19, NO. 4, NOVEMBER 2004
Fig. 6. Generating unit step response of REPORT bus bar voltage control.
plant, equipped with eight generating/pumping units (160 MVA active power, the unit terminal voltage, the local EHV
each). They are related to two different basic test groups: bus-bar voltage);
– single unit test under REPORT reactive power control: – multiple units tests under REPORT’s automatic con-
the dynamic response following the step variation in trol of the local bus-bar EHV level: the dynamic re-
reactive level corresponds to a proper time constant of sponse following the step variation in bus-bar voltage
5 s (Fig. 5 from the top: the reactive level, the unit re- set-point corresponds to a proper time constant of 50 s
Authorized licensed use limited to: TU Ilmenau. Downloaded on May 06,2022 at 06:33:49 UTC from IEEE Xplore. Restrictions apply.
CORSI et al.: COORDINATED AUTOMATIC VOLTAGE CONTROL OF THE ITALIAN TRANSMISSION GRID—PART II 1739
B. RVR Commissioning reactive power. They are due to the telecommunication chan-
All the I/O signals exchanged by the RVR require hard- nels delaying in sending/receiving controls/measurements sig-
ware/software intervention by the Regional Dispatcher SCADA nals. The transients show the coordinated and timely reaction
system to generate the new data-base variables to be provided of the peripheral power plants following RVR control (from the
or received by the RVR, managing either errors in communica- top: pilot node voltage, reactive power level sent by RVR, reac-
tion, system out of services or peripheral devices maintenance. tive power and voltage of one controlled generator at La Casella
Moreover, the refreshing time on the control loop measure- thermal power plant). At the activation time, the other thermal
ments operated by the telecommunication equipment has to be power plants in the same area (Piacenza, Tavazzano, Turbigo)
kept below 2 s. were already in service under RVR control. Their daily behavior
The results shown in Figs. 7 and 8 refer to RVR commis- is shown in Figs. 9 and 10, respectively representing the pilot
sioning activities carried out at the regional dispatcher in Milan, node voltage, tracking its set-point, and the area reactive level,
during the activation of La Casella thermal power plant. Dy- as well as the reactive powers generated by the controlled plants.
namic transients have been recorded at both the power plant and
control center levels. The transients in Fig. 7 (RVR step variation C. TVR Expected Performance
of the area reactive power level) and in Fig. 8 (RVR step vari- The transients shown in Figs. 11 and 12 (TVR step variation
ation of the pilot node voltage set-point) reveal delays between of three optimal forecasted pilot nodes voltages and area reac-
the area reactive level and the power plant’s unit voltage and tive power levels) reveal the coordination exercised by the ter-
Authorized licensed use limited to: TU Ilmenau. Downloaded on May 06,2022 at 06:33:49 UTC from IEEE Xplore. Restrictions apply.
1740 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 19, NO. 4, NOVEMBER 2004
Authorized licensed use limited to: TU Ilmenau. Downloaded on May 06,2022 at 06:33:49 UTC from IEEE Xplore. Restrictions apply.
CORSI et al.: COORDINATED AUTOMATIC VOLTAGE CONTROL OF THE ITALIAN TRANSMISSION GRID—PART II 1741
[8] C. Brasca, R. Chinnici, M. Pozzi, and M. Zaramella, “Practical imple- Massimo Pozzi received the Doctorate degree in electronics (automatic sys-
mentation aspects of a multilevel control solution for voltages and re- tems) from the Polytechnic of Milan, Milan, Italy, in 1987.
active regulation in electrical power systems,” in Proc. Process Control In 1989, he joined the Control System and Voltage Regulation Department,
and Instrumentation Conf., Glasgow, 2000. Automatica Research Center, where his main interests were simulation and real-
[9] S. Bittanti, S. Corsi, M. Pozzi, and M. Zaramella, “The power plant time design, turbine and generator regulation, and wind and photovoltaic unit
voltage/reactive power regulator with an adaptive control solution,” in control. He became a Senior Researcher with ENEL S.p.A Ricerca in 1997,
Proc. Powertech Conf., Bologna, Italy, 2003. working in the framework of grid voltage control and power electronics appli-
[10] S. Corsi, M. Pozzi, and G. Tagliabue, “A new real-time digital simu- cation. He has been with CESI, Milan, since 2000 as a Product Leader in the
lator of the turbine-alternator-grid system (STAR) for control apparatus T&D Networks B.U., in the field of grid control and supervision. He is the au-
closed-loop tests,” in Proc. IEEE/PES Summer Meeting, Berlin, Ger- thor of about 20 papers on power system control.
many, 1997.
[11] S. Corsi, M. Pozzi, U. Bazzi, M. Mocenigo, and P. Marannino, “A simple
real-time and on-line voltage stability index under test in Italian sec-
ondary voltage regulation,” in Proc. CIGRE Conf., 2000.
[12] S. Corsi, V. Arcidiacono, M. Cambi, and L. Salvaderi, “Impact of the
restructuring process at enel on the network voltage control service,” in Marino Sforna received the Doctorate degree in electrical engineering from the
IREP, Santorini, Greece, Aug. 24–28, 1998. University of Rome, Rome, Italy, in 1985.
[13] A. Berizzi, S. Sardella, F. Tortello, P. Marannino, M. Pozzi, and G. He joined ENEL in 1982 as a MV Network Designer. From 1987 to 1997, he
Dell’Olio, “The hierarchical voltage control to face market uncertain- was with the Research and Development Department of ENEL, where he gained
ties,” in Proc. Bulk Power Systems Dynamics and Control V Conf., experience in artificial intelligence applied to power system operation. From
Onomichi, Japan, 2001. 1997 to 2000, he was Deputy Manager of the Gestore della Rete di Trasmis-
[14] S. Corsi, M. Pozzi, V. Biscaglia, and G. Dell’Olio, “Fiscal measure of sione Nazionale SpA (GRTN) Area Control Center, Milan, Italy, and then in
the generators support to the network voltage and frequency control in 2001, was given the same position in Venice. He is now in charge of defense
the ancillary service market environment,” in Proc. CIGRE Conf., Paris, plans, restoration strategies, protection strategies, system studies, and voltage
France, 2002. regulations for the GRTN.
Authorized licensed use limited to: TU Ilmenau. Downloaded on May 06,2022 at 06:33:49 UTC from IEEE Xplore. Restrictions apply.