Professional Documents
Culture Documents
App (C) - Scope & Responsibility Matrix (06.12.2022)
App (C) - Scope & Responsibility Matrix (06.12.2022)
The following scope of works to be carried out by Sub-Contract is not exhaustive. Sub-Contractor shall price within the unit
rates their obligation in compliance with this requirement and deemed to have satisfied themselves as to the correctness and
sufficiency of the offer which shall be deemed to cover all his obligation under the Sub-Contract and all matters and things
necessary for the proper construction and completion of the Sub-Contract Works.
6 Cable detection works including trial trenches / X All Sub-Contractors shall include for their
holes, NCE / NCD submission and Authority own cable detection(s), NCE
fees. submission(s) and trial trenches prior to
any excavation work.
B) Programme
1 Submission of detailed working programme X The format of the working programme
within 14 days upon award of Sub-Contract for shall be based on Main Contractor's
Main Contractor's approval. requirement
Page 1 of 10
S/N Description Main Sub- Remark
Contractor Contractor
3 The works shall be carried out in phases and X
sections as required by the Main Contractor /
Client. Sub-Contractor shall familiarise the
phases and sections of works in accordance to
the Main Contractor's programme. No claims
on stoppage or downtime shall be entertained
and Sub-Contractor's price is deemed to have
taken this into consideration.
2 Submission of Test Report and Certificates X The Test Report and Certificates & any
issued by accredited lab and approved test results shall be kept confidential and
agencies, for Sub-Contract material / works. not allowed to be disclosed to any other
parties without prior consent from the Main
Contractor
6 Submission of Shop Drawings and As-Built X Main Contractor has the right to make any
Drawings in format as specified (ie. amendments, copy and use of the
Microstation and/or AutoCAD format) for Main softcopy submitted by Sub-Contractor.
Contractor / Client's approval.
Format used subject to Main Contractor /
Client's approval.
Page 2 of 10
S/N Description Main Sub- Remark
Contractor Contractor
9 Submission of daily report, weekly report and X
monthly report
6 Set up, maintenance and subsequent removal X The Sub-Contractor shall pay for water
for required utilities, including water, electrical / consumption without administration charge
power, lighting, lightning protection and etc. for and provide generator for their own
temporary site building(s) and sub-contract temporary power supply.
works.
The Sub-Contractor shall provide sufficient
water tank(s) on-site for storage, taking
into consideration the space constraint on
site.
Page 3 of 10
S/N Description Main Sub- Remark
Contractor Contractor
E) Site Management and Manpower
1 Provision of competent and full time Site X Detailed Site Organization Chart and CV
Management and Manpower, consist of but not of key personnel and manpower
limited to the following, for the proper and deployment plan shall be submitted as per
satisfactory execution and completion of Sub- Main Contractor's request.
Contract Works:
6 Provision of site transport to ferry workers from X no workers are allowed to roam freely
gate to work area. outside the site.
Page 4 of 10
S/N Description Main Sub- Remark
Contractor Contractor
F) Plant, Equipment & Material
1 Mobilization, multiple internal shiftings and X Sub-Contractor to get clearance from Main
demobilization of machinery, plant & equipment Contractor prior to mobilisation and
demobilisation
4 All plants and equipment necessary for the Sub- X Replacement of all plant/ equipment shall
Contract works, complying with all safety be within 48 hours upon instructed by the
requirement and approved by the Main Main Contractor if:
Contractor. a) breaks down frequently, or
b) unable to repair within 48 hours.
G) Survey Works
1 Survey & Survey Control for temporary X # X - Only TBMs are provided by the Main
benchmark (TBM) Contractor.
# - All setting out from the TBM &
transfering survey references by Sub-
Contractor
4 Provision of cleaning, washing and preparation X To ensure used water not to flow beyond
works prior to commencement of the Sub- the Sub-Contract work zone and properly
Contract Works discharge.
Page 5 of 10
S/N Description Main Sub- Remark
Contractor Contractor
5 Protective and maintenance of safety barricade X
to Sub-Contract Works, including protective
barrier, netting, signages, temporary works and
etc., in compliance to Main Contractor and
Authority's requirement
13 All hand tools must be 110V and comply to X Monthly LEW check for all electrical tools
Client and all other Authorities requirement
15 Any fine or penalties charged by Authority due X The Sub-Contractor shall be liable for their
to untreated conditions generated from the Sub- own or any relevant infringements/ fines
Contract works imposed by Authorities.
Page 6 of 10
S/N Description Main Sub- Remark
Contractor Contractor
17 Protection & diligence to adjacent structure X Cost of repair/ replacement of damaged
items/works shall be borne by the Sub-
Contractor.
Page 7 of 10
S/N Description Main Sub- Remark
Contractor Contractor
5 Overcome site constraint, including obstruction X
/ unforeseen ground condition whatsoever for
the completion of Sub-Contract Works
11 Daily co-ordination on behalf of Main X Sub-Contractor shall receive & compile all
Contractor with appointed rebar Supplier(s) for material Delivery Orders and submit to
fabrication and delivery schedule. Main Contractor on the next day after
receipt. All Delivery Orders are required to
12 Weekly planning and requisition to Main X be properly recorded for works, sealed &
Contractor for ready-mixed concrete supply signed by Sub-Contractor's authorized Site
with ready-mix concrete batching plants. Rep.
Page 8 of 10
S/N Description Main Sub- Remark
Contractor Contractor
15 Provision of Professional Engineer (PE) X
services
Traffic Diversion
17 Excavation for road and related work to X
required level, including but not limited to,
excavation, backfill & disposal off-site.
17 IRI testing X
Page 9 of 10
S/N Description Main Sub- Remark
Contractor Contractor
Drainage Works
19 Excavation for drain and related work to X
required level with working space including but
not limited to, excavation, backfill & disposal off-
site, etc.
Page 10 of 10