FORM NO - QAP/QCF/RATAPANI/08

National Highways Authority of India


Project - :- Four Lanning Of Ratapani Stretch From Kms. 8+300 To Kms.20+680 (Length 12+380 Kms.) Of Obedullaganj- Itarsi Section
Of Nh-46 (Old Nh-69) In The State Of Madhya Pradesh.

EPC CONTRACTOR AUTHORITY ENGINEER CLINT

M/s Bansal Construction Work Pvt Ltd Lion Engineering Consultant Pvt Ltd National Highways Authority of India

CALIBRATION OF SAND POURING CYLINDER


(As Per IS : 2720, Part-28)
Date of Calibration : Cylinder No. :
Source Of Density Sand
: Calibrating Container No. :

Size of Sand Used : Calibrated By :

A. Determination of the weight of sand in Cone.

Determination No. 1 2 3

Weight of cylinder + Sand (Before Pouring) W1 (gm)

Weight of cylinder + Sand (After Pouring) W2 (gm)

Weight of sand in Cone W3= (W1-W2) (gm)

Average weight of sand in Cone (gm)

B. Determination of Bulk Density of Sand.

Determination No. 1 2 3

Weight of cylinder + Sand (Before Pouring) W1 (gm)

Weight of cylinder + Sand


W4 (gm)
(After Pouring in Calibrating Container)

Average weight of sand in Cone W3 (gm)

Weight of sand in Calibrating Container W5=(W1-W4)-W3 (gm)

Volume of calibrating Container V CC

Bulk Density Of Sand W5 / V (gm/cc)

Average Bulk Density Of Sand (gm/cc)

Remarks :

Tested By ( EPC Contractor ) Checked By (Authority Engineer)


Signature Signature
Date Date