Document No.

OM-SKD-WI01
Standard Operation Procedure for safety inspection (SKD) Version No. 19A
Page 1 / 5
Product Range General Refrigerator From Homa
Procedure Inspection Steps Operation Content Quality characteristic requirements
1. check security instrument twice a day, before
Inspection security the start of the working, the method of
1 instrument inspection detailed in the "six-in-one safety
inspection instrument operating procedures
",and keep record。
2. The safety performance parameters of the
Inspection the parameters of test data are in accordance with the specified
the security instrument requirements。
3. Check the computer screen normal display,
2 comprehensive test software normal
operation, scan code voice broadcast system
Check computer screen
normal operation, scan code gun normal
display ," comprehensive tester
operation, etc.
software "and" voice broadcast
4. After finishing inspection,fill in the check
software ", scan gun display, etc
list,if finding problem,immediately
feedback to team leader or technician

Fill in the Checklist

Editor Countersignature Auditor Approver Date


Document No. OM-SKD-WI01
Standard Operation Procedure for safety inspection (SKD) Version No. 19A
Page 2 / 5
Product Range General Refrigerator From Homa
Procedure Inspection Steps Operation Content Quality characteristic requirements
1.The water tray can not be inclined to the left
1.Inspection of water tray assembly (PTC box direction),the distance between the
water tray and basehouse is more than 5mm,the
distance between the compressor and the pipe is
2.Inspection the compressor and TPC more than 10mm。
box 2.PTC box, terminal box assembly in place, no
loose, broken, charred and other phenomena
3. Wires (ground wires, power cord, etc.)
3.Inspection the wire and screws
assembled in place, no wrong connection,
damage, burning and other phenomena
4. Screws and nuts are fixed in place according to
4.Inspection the painting pipe、welding the process operation requirements, no loose,
joint 、pipe space。 lack of screws, lack of nuts and other
phenomena。
5. The distance between the pipe and the pipe ≥5
1
mm, each pipe can not collide with each other
5.Inspection the electric control panel
and other parts, and each pipe can not exceed the
cover、 compressor back cover。
box body
2 4 6. Flat pipe, pipe folding requirements: after
3
deformation diameter ≥85% original diameter;
iron pipe and pipe welding joints require
protective paint, no lack of painting

Editor Countersignature Auditor Approver Date


Document No. OM-SKD-WI01
Standard Operation Procedure for safety inspection (SKD) Version No. 19A
Page 3 / 5
Product Range General Refrigerator From Homa
Procedure Inspection Steps Operation Content Quality characteristic requirements
1、Before the start of step 2,Check that the
“pass'”stamp is complete such as the stamp of
inspection room、the stamp of refrigeration
1、Select Test Mode test,If "pass" stamp is not complete, do not
1
inspection, must be returned to the assembly
group to be inspected again。
2.Select the test mode according to the rated
voltage of the tested fridge,220V~240 V rated
voltage select test mode with a voltage of 1800
2、Plug power cord
V,100V~170 V rated voltage select test mode
with a voltage of 1500 V ,Rated voltage can be
identified in compressor label 。
3.Before starting the auto-test button, use the
clamps to clamp the pipe until all test items are
3、Start Automatic
completed to release the clamps ,such as
Test Button
2 below:

3
4. To prevent electric shock, the inspector needs to
wear insulated gloves to contact the power cord

Editor Countersignature Auditor Approver Date


Document No. OM-SKD-WI01
Standard Operation Procedure for safety inspection (SKD) Version No. 19A
Page 4 / 5
Product Range General Refrigerator From Homa
Procedure Inspection Steps Operation Content Quality characteristic requirement
1、 Test numbers accord with safety performance
parameters。
2、 When the safety performance is not qualified,
the security instrument will automatically
alarm, then the refrigeration is judged to be
1. safety performance test
unqualified.
(automatic completion of
security instrument)
1 (yellow light )in
testing
1 2 3

(Green light)
Listen to the alarm warning of the (alarm)
qualified light
security instrument to determine unqualified
whether the safety performance is
2 qualified。

Editor Countersignature Auditor Approver Date


Document No. OM-SKD-WI01
Standard Operation Procedure for safety inspection (SKD) Version No. 19A
Page 5 / 5
Product Range General Refrigerator From Homa
Procedure Inspection Steps Operation Content Quality characteristic requirements
tested the qualified refrigerator on the tracking
sheet with a qualified stamp, the unqualified box
can not be stamped,such as follow figture:

1
Unplug the power cord

Put the power cord on the


line or in compressor
room

Editor Countersignature Auditor Approver Date