UEBQ3523 Tutorial 2qa
UEBQ3523 Tutorial 2qa
QUESTION 1
By referring to section A-A, plan, and the major unit rates given, estimate the
construction cost for a small factory guard house using the approximate quantities
method.
Grade 30
3.000
Timber flush door
3.000
150
Half brickwall in
mortar (1:3) with
plaster finishes
2.500
150
(80 marks)
QUESTION 2
Classify the objectives of creating a pre-tender estimate and analyse the variables that
affect the accuracy of cost estimation for construction projects.
(20 marks)