Professional Documents
Culture Documents
R1116010 Toss 09 001
R1116010 Toss 09 001
Standard Specification
R1116010-TOSS-09-001
ENTP-6
Equipment Spacing
Amendment Record
Issue/revision Date Remarks Signature
0 01/06/16 First issue CFPA/ADSC (Narongsak)
Note: This CFP Project Specific Standard/Specification has been developed from original
Corporate Standard TOSS-09-001 Revision 2/A, Dated 24/04/96
This document is confidential. Neither the whole nor any part of this document may be disclosed to any third party without the
prior written consent of Thai Oil Company Limited Thailand.
The copyright of this document is vested in Thai Oil Company Limited
All rights reserved. Neither the whole nor any part of this document may be reproduced, stored in any retrieval system or
transmitted in any form or by any means without the prior written consent of the copyright owner.
INDEX
1. GENERAL 4
1.1 SCOPE 4
1.2 OBJECTIVE 4
1.3 GENERAL CONSIDERATIONS 4
1.4 DEFINITIONS 4
1.4.1 FLASH POINT 4
1.4.2 AUTO IGNITION TEMPERATURE (A.I.T.) 5
1.4.3 SOURCES OF IGNITION 5
1.5 APPLICABLE STANDARDS AND GUIDES 5
3. ON-SITE SPACING 10
4. OFFSITE SPACING 17
5. TANKAGE 21
6. ATTACHMENTS 31
GENERAL
SCOPE
This standard is intended as a guide to minimum safe spacing of plant and equipment for Oil
Refineries, Petro-chemical Complexes and similar installations.
The spacing recommended will apply in the absence of Client’s standards or supplement such
standards where necessary. The recommendations are based on current practice in the industry and
are intended, as a minimum, to satisfy the requirements of all relevant Government recommendations.
OBJECTIVE
The objective of the spacing recommendations is to ensure that maximum economical use is made of
available plot areas, compatible with the safety of personnel and vulnerability of plant.
GENERAL CONSIDERATIONS
Circumstances will arise where it will be difficult to adhere to the minimum spacing requirements, e.g.
where there are severe limitations on plot availability. In such cases relaxation of minimum spacing
may be permitted by providing additional safety features such as sprinklers, supplementary fire fighting
equipment, emergency shut-down facilities, additional fireproofing, inert gas blanketing, etc. Such
relaxations will generally require the sanction of Statutory Authorities, Plant Insurers and CLIENT.
Other factors may require spacing greater than the minimum recommendation of this Standard. In this
category consideration should be given to:-
(a) proximity of adjacent property and the consequential environmental and public relations
effects.
(b) special process hazards which may justify increased spacing.
(c) special plant maintenance/installation considerations,that may necessitate increased spacing.
(d) future development plans, both inside and outside the boundary fence.
(e) topographical features of site and direction of prevailing winds.
(f) political security factors.
DEFINITIONS
The following definitions are used throughout the standard.
Flash Point
The flash point is the lowest temperature at which a product gives off sufficient vapour to form a
mixture with air that can be ignited by a flame or spark.
Sources of Ignition
Possible sources of ignition include the following:-
Electrical
Sparks/arcs may occur when current-carrying contacts are separated or by static electricity discharge.
Naked Lights
E.g. fired heaters, fires, smoking, hot work, gas welding, etc.
Engines
Spark ignition systems, exhaust hot spots.
Spontaneous Combustion
Prophoric materials, vapour leakages at temperatures above A.I.T.
Frictional Ignition
Grit blasting, power tool grinding, mechanical failure of rotating machinery.
Process Unit
A process complex consists of a combination of plants, each carrying out a specific processing duty.
these plants are defined as PROCESS UNITS.
Equipment items within the process unit limits are referred to as “on-site equipment”. On site Spacing
Chart, Attachment 1 gives the recommended spacing between these items of equipment.
Equipment limits are determined by an imaginary line drawn around the outer edge of equipment
within the Process Unit.
Process Area
Several process units may be combined to form a PROCESS AREA. These units may be intregrated,
i.e. no spacing between units other than basic equipment spacing, or may be laid out as separate units
with spacing between equipment limits (as defined above) based on fire fighting access, process
hazard or separate shut-down requirements; depending on overall plant philosophy.
Process block
A number of process areas may be combined to form a PROCESS BLOCK.
Fig. 2 indicates an example of a Process Block showing the arrangement of a Process Unit (integrated
and separate) and Process Areas within the block. The basic minimum spacing between Units and
Areas are given on Fig. 2. For process blocks which may be independently shutdown the minimum
spacing requirement is 30m to the adjoining process block.
ON-SITE SPACING
For the commended spacing of on-site equipment refer to the “On-site Spacing Chart”, Attachment 1
The information on this chart is supplemented by explanatory notes which are contained in Section 7.1
“On-Site Spacing Guide”, it is essential that reference is made to this section.
Against each type a basic spacing dimension is quoted. This basic spacing is the recommended
distance between the item and other general process equipment. The recommended spacing
between different items is given at the intersection of the horizontal line for one item and the vertical
line from another. In general, this shall be the greater of the basic spacing dimensions for the two
items, Explanatory notes can be found in section 7.1.
Reactors may be grouped together, in which case operational and maintenance access of 1.5 metres
between shells is satisfactory.
Reactors operating below A.I.T. may be regarded as drums, i.e. drum spacing recommendations will
apply, see Ref. (D)
Spacing from Ref. (F) is an excess of the greater basic dimension as the Reactor is regarded as high
risk equipment.
Since the Reactor is operating above A.I.T., other sources of ignition are not a spacing consideration
and basic reactor spacing of 4.5 metres will apply, e.g. items Refs. (J) and (O).
The basic spacing of 7.5 metres provides access for fire fighting minimises damage to other
equipment is event of reactor fire, and protects exposed shell.
N.B. Internally lined reactor shells are more susceptible to fire damage than unlined vessels.
Reactors may be grouped together, in which case operational and maintenance access of 1.5 metres
between shells is satisfactory.
Reactors operating below A.I.T. may be regarded as drums, i.e. drum spacing recommendations will
apply, see Ref. (D).
Spacing from (F) is in excess of the reactor after basic dimension as the reactor is regarded a high
risk equipment.
Since the reactor is operating above A.I.T. , other sources of ignition are not a spacing consideration,
basic reactor spacing of 7.5 metres will apply, e.g. items (J) / (O).
Spacing from Refs. (P), (T), (U) - These items are not regarded as fire-hazardous - the spacing of 4.5
metres will give these items protection in the event of reactor fires.
For pressure storage vessels, in the same service provide a minimum of one diametre between shells
for operational and maintenance access.
Spacing form (U) pipe racks is not considered as fire hazardous - spacing of 4.5 metres affords
protection to these items in the event of storage vessel fire.
For high risk equipment the spacing should be increased to 15 metres. High risk equipment includes
reactors, exchangers and pumps operating above A.I.T., fired heaters, gas compressors, and
expanders, and their drivers, e.g. items Refs. (B), (C), (G), (L), (N), (O).
Spacing from Ref. (U) - Pipe racks are not regarded as fire hazardous - spacing of 4.5 metres affords
protection to the pipe rack in the event of blowdown drum fire.
Exchanger above A.I.T. in the same service, i.e. connected by a common process stream, may be
spaced 1.0 metre apart; for other exchangers basic spacing of 4.5 metres should apply.
Spacing from Ref. (J) - Since the fluid in the exchanger is already above its A.I.T., the fired heater, in
this case, does not represent a source of ignition. However, a heater fire is considered likely to be
more severe than other plant fires, so spacing greater than basic is applied to minimise damage to the
exchanger in the event of a heater fire.
Spacing form Ref. (O) - Since the fluid in the exchangers is above its A.I.T., the Compressor driver
does not represent a source of ignition. Therefore, exchanger basic spacing of 4.5 metres applies.
Spacing from ref. (F) is in excess of the greater basic dimension as the exchanger (above A.I.T.) is
regarded as a high risk item.
Spacing form ref. (P) protects equipment from a high fire risk item.
For this reason grade mounted units isolated from other equipment are preferred. However, because
of restrictions on area availability, it is common practice to mount air fin coolers on top of the pipe rack.
In such cases consideration must be given to the following:-
(a) Air fin coolers must not be mounted over pumps, compressors, drums or heat exchangers,
containing flammable materials.
(b) There must be no flanges or valves in any hydrocarbon lines on the rack beneath an air fin
cooler.
(c) Horizontal spacing requirements of “on-site” spacing Chart, Attachment 1, must be met.
(d) Support legs for the air fin cooler must be fireproofed.
(e) Access must be provided for tube bundle removal by mobile equipment.
The basic spacing of 3.0 metres (horizontal) minimises exposure to fire hazard-air fins are more
vulnerable to fire damage than shell and tube exchangers.
Ref. (U) - The basic spacing of 3.0 metres is applicable to grade mounted air fin coolers only.
Where such restrictions are not applied, the heater location should be selected on the windward side
of the unit with reference to the prevailing wind, close to the battery limit and as far as practicable from
other equipment. Consideration must also be given to the proximity of plant and equipment outside
the unit battery limit.
When the heater has an individual stack, the top of the stack should be at least 3 metres higher than
equipment within a horizontal distance of 15 metres and at least 3 metres higher than any operating
platform within a horizontal distance of 65 metres.
Ref. (J)
If all heaters in a group shut-down together at plant turnaround spacing between shells can be for
normal maintenance only. If heaters are required to shut-down individually, spacing of 7.5 metres
between shells is required for L.P. operation (less than 7 kg/cm 2g) and 15 metres between shells for
H.P. operation (7 kg./cm2g and above).
Ref. (B), (C), (G), (L) are items operating above their A.I.T. and in these cases the fired heater is not
considered to be primary source of ignition, spacing is based on affording protection in the event of
heater fire.
For reformer heater/reactor installations, where vapour only is present in heater tubes and reactors,
spacing may be further reduced to 3 metres and in the case of Ref. (B) and 3 metres in the case of
Ref. (C).
Ref. (N) - The compressor area is regarded as a special risk area in view of the potential release of
large vapour quantities. Spacing greater than the basic dimensions is required.
Ref. (O) - The compressor driver is not considered a source of ignition in this case. The spacing of 7.5
metres minimises damage to the compressor driver in the event of heater fire.
Ref. (P) - A spacing of 4.5 metres minimises damage in the event of the heater fire. For equipment
higher than 3 metres, spacing should be increased to 7.5 metres from heaters with liquid in their
tubes. Reduced spacing is permitted because there is no flammable material release in the event of
damage.
Ref. (U) - Because of severity of heater fire, spacing to pipe racks is greater than basic.
The cooling tower becomes a source of hazard in the event of tube failure in a water cooler. Basic
spacing provides for dispersion of hazardous vapours, minimises corrosive effects of spray
impingement and visibility problems from exhaust plume.
The cooling towers should be located on the leeward side of a process unit with reference to the
prevailing wind.
Ref. (U) - The factors above are not considerations in the case of a pipe rack. Pipe rack basic spacing
will apply.
Ref. (F) - Because of the high fire risk, spacing greater than basic should be provided from this item.
Ref. (J) - The fired heater is not considered a source of ignition in this case. Spacing of 7.5 metres is
provided between two high risk items.
Ref. (L) - Pumps in the same service may be spaced at 1.5 metres. For pumps in different services
basic spacing of 4.5 metres applies.
Ref. (O) - The compressor driver is not considered a source of ignition in this case. Basic spacing for
pump applies.
Ref. (P) - A spacing of 4.5 metres minimises damage in the event of a pump fire.
Ref. (U) - Spacing is horizontal from edge of rack to pump stuffing box.
Ref. (U) - Spacing is horizontal from edge of rack to pump stuffing box.
Compressors are costly items so basic spacing is greater to allow additional protection in the event of
a fire.
Small compressors (200.P and less) may be treated as pumps for spacing purposes.
Ref. (F) and (J) - Spacing greater than basic is provided because of the high risk nature of these
items.
Ref. (U) is not a hazard producing items. The basic spacing of 4.5 metres provides protection in the
event of compressor fire.
For items (B), (C), (G), (L), which are operating above A>I.T. the driver is not considered to be the
primary source of ignition. The basic spacing for these items therefore applies.
Ref. (J) - Spacing of 7.5 metres protects driver in event of heater fire.
Ref. (F) - Spacing greater than basic provides additional protection to critical item.
Ref. (U) - The pipe rack is not at hazard-rack basic spacing applies.
Refs. (B), (c), (G), (L) - Spacing of 4.5 metres provides protection to equipment in the
event of fire at likely sources of ignition.
Non blast-proof building should be considered as Ref. (B) Buildings on the off-site spacing chart.
Ref. (U) - On-site pipe racks should not generally be nearer than 30 metres to the Control Building.
Provided lines are all welded with no valves or flanges, a pipe rack may be brought to 7.5 metres from
one side only of a Main Control Building.
Ref. (U) - Pipe rack basic spacing applies provided all welded pipe racks without valves or flanges.
Ref. (U) - Pipe racks do no present a major hazard . Basic rack spacing applies.
Item Ref. (J) - Fired Heater is a possible source of a major fire. Spacing greater than basic is required
in this case.
NB. This limitation does not apply to the pipe rack serving the heater area.
The pipe rack in itself is not considered highly hazardous. In general equipment which is not
hazardous may be located on access and operability considerations relative to the pipe rack. Items
Ref. (A), (D), (H), (I),(grade mounted) are in this category.
In special cases where the hazard from the pipe rack must be minimised, fittings and flanges, which
could be sources of leakage, should be eliminated from the pipe rack in the vicinity, e.g. from pipe
racks under air fin exchangers and from pipe racks in the vicinity of control houses. i.e. items (I), (Q)
and (R).
Pumps are also considered as a special case as, for layout purposes, access and operability, it is
usual to have pumps in close proximity to the pipe rack e.g. Items Refs. (L) and (M) - spacing in
horizontal distance from pump stuffing box to edge of pipe rack.
Refs. (E) and (J) are exceptionally hazardous items. The basic spacing for these items therefore
applies.
Where it is necessary for reasons of plant layout to locate emergency shut-off valve manifolds closer
to a heater than 15 metres, a fire wall shall be provide between the manifold and the heater at a
minimum distance of 7.5 metres from the heater.
OFFSITE SPACING
Facilities outside the confines of a Process Block, e.g. boiler house and power stations, administration
offices, workshops, effluent treatment, flare stacks, jetty & rail loading, blending facilities etc. are
referred to as “off-site facilities”.
It is customary to combine the utility type facilities, e.g. steam generation, water treatment, plant air,
etc. within a utility area or block.
Effluent treatment, flare and similar high hazard off-site facilities are generally located remote from
process facilities, utility areas and administration areas.
Spacing of flare stacks requires special consideration based on relief loads and thermal radiation
levels. Reference must be made to the Process Engineer.
The recommended spacing off-site equipment is indicated in “Off-site Spacing Chart”, Attachment 2.
The information on this chart is supplemented by explanatory notes contained in Section 8.1 “Off-site
Spacing Guide”.
It is essential that reference is made to Section 8.1 when using “Off-site Spacing Chart”. Attachment 2.
Against each item a basic spacing dimension is quoted. This basic spacing is the recommended
distance between the item and other equipment/facilities. The recommended spacing between different
items is given at the intersection of the horizontal line from one item and the vertical line from another.
In general, this shall be the greater of the basic spacing dimensions for the two items, otherwise
explanatory notes can be found in Section 8.1.
The spacing between similar equipment/facilities is given in the first box adjacent to the item.
Ref. (B) - Buildings are not considered hazardous to boilers and generating plant and vice versa.
Therefore, spacing less than basic for buildings is acceptable. Ref. (K) - Spacing protects pipe track
from possible fire in boiler house.
Ref. (O) - Railway main lines are not at risk from facilities and do not present a risk to facilities. Boiler
basic spacing applies.
Ref. (P) - Rail sidings present a minimum risk to facilities. Siding basic spacing applies.
Note that steam generators forming an integral part of a process unit are considered as fired heaters.
In such cases, on-site basic spacing will apply.
The lower basic spacing is for equipment that is lower than the cooling tower.
The higher basic spacing is for equipment that is taller than the cooling tower and where it is
necessary to minimise the corrosion, visibility and ice formation problems, resulting form the
impingement of the cooling tower exhaust plume.
A cooling tower can become a source of hazard due to release at atmosphere of flammable vapours,
caused by tube failure in water cooled exchangers. The higher basic spacing distance is considered
adequate for dispersal of these vapours.
Spacing greater than cooling tower basic is applied form highly hazardous sources, e.g. items Refs.
(D) and (H).
Items Refs. (F), (G) and (O) do not present a hazard to these cooling tower. Cooling tower basic
spacing is therefore applied.
Items Refs. (J) and (L) are possible sources of fire. Higher cooling tower basic spacing is applied to
these items.
Items Refs. (M) and (O) do not present a hazard to the cooling tower.
Item Ref. (K) - The cooling tower is considered to be at risk from the pipe track. Pipe track basic
spacing is applied.
Items Ref. (N), (P), (Q) are not considered as sources of hazard. Basic spacing for these items will
apply.
Items Refs. (K), (O), (P) are not considered major sources of hazard.
TANKAGE
This section gives guidance for the spacing and bund capacities of storage tanks, storage spheres
and cylinders.
Other types of bulk storage, e.g. underground caverns, are not covered by this standard.
Flammable Liquids
Petroleum products by their nature are potentially hazardous, the degree of hazard being directly
related to their volatility and flash point.
They are classified :
Types of Tankage
The type of tank used to store a particular produce is generally specified by Client’s requirements. In
the absence of such requirements, type selection should be referred to the Process Design
Coordinator.
The following types are generally used :
Table 1
This table gives typical examples.
Definitions
Bund or Firewall
A wall of appropriate height constructed of concrete, earth or any other suitable material and design to
confine spillage of tank contents.
Bunded Area
An area bounded by bund walls to confine spillage.
Bund Capacity
The volume in cubic metres that can be contained within the exposed.
Tank Group
A number of tanks contained within a common bund.
Small Tanks
A tank of 10 metres diametre or less and capacity of 8,000 cubic metres of water or less is deemed to
be a small tank.
It is desirable to group tanks for the storage of the same products in one group within a bund area,
subject to the limitations of the bunded capacity.
It is desirable that LPG or other liquefied flammable gases should be stored remote from other
products.
Intermediate and component tankage should be located in areas local to their respective units
where possible so that lines can be kept to a minimum length.
Account should be taken of the possibility of storing more than one class of material in certain
tanks or of changing the tank service at some future date. Where future changes of service of the
storage tanks are anticipated, the layout and spacing should be for the most stringent case.
Wherever possible storage tanks should not be located on high ground overlooking the facilities.
This prevents spillage of flammable liquid flowing downhill and endangering operating plant.
For fire fighting reasons there should be no more than two rows of tanks between adjacent access
roads.
Intermediate walls of less height than their main fire walls may be provided to divide the tankage
into groups of a convenient size so as to contain small spillage and act as firebreaks.
For Class III (1) and Unclassified petroleum stocks spacing of tanks is governed only by
construction and operational convenience.
Note that the spacing of Class III (1) tankage from Class, II or III (2) tankage is governed by the
atter.
Example 1, Cone Roof Tanks (CR) Tanks > 10metres. Class II & III Storage
Spacing
‘A’ To suit construction and operating conditions but not less than half tank height.
‘B’ 1/2 dia of largest tank but not less than 10 metres and need not be greater than 15 metres.
‘C’ & ‘D’ See Table ‘2’.
Spacing
‘A’ to suit construction and operating conditions but not less than half of tank height.
‘B’ 0.3 dia of largest tank but not less than 10 metres and need not be greater than 15 metres.
‘C’ & ‘D’ See Table ‘2’
Example 3, Cone Roof (CR) & Floating Roof (FR) in a Common Bund
Class I & II
Spacing
‘A’ Distance equal to not less than 1/2 height of tank.
‘B’ The least of 9I) 10 metres (iii) 1/2 dia of largest tank.
‘C’ & ‘D’ See Table ‘2’
Example 4, Cone & Floating Roof Tanks, Not exceeding 10 metres dia,
Class I & II
Fixed or floating roof tanks not exceeding 10 metres diametre may be grouped together up to a total of
8000m3 and treated as one tank if grouped with other tanks, total overall tank capacity including other
tanks in common bund not to exceed 60000m 3 if other tanks are fixed roof type, or 120000m 3 if other
tanks are floating roof type..
Spacing
‘A’ to suit construction or operating requirements
‘B’ 1/2 dia of larger tank but not less than 10 metres and need not be more than 15 metres.
Spacing
‘A’ Minimum 30 metres
‘B’ (Dia of large tank + dia of small tank) divided by two
‘C’ & ‘D’ See Table ‘2’
Maximum capacity of all vessels within one group = 3 items capacity of largest vessel in group.
maximum number of vessels in any one group 6. Any tank in one group to be at least 8 metres from
any tank in another group.
Spacing
‘A’ = 1/4 sum of dia. of 3 adjacent tanks but not less than 2 metres.
‘D’ See Table ‘2’
Dimension ‘C’ is dimension from facility/equipment reference line to inside top of tank bund.
Dimension ‘D’ is dimensions from facility/equipment reference line to tank shell
Attachments
Attachment 1 “On Site” Equipment Spacing Chart
Attachment 2 “Off Site” Equipment Spacing Chart
Basic
ITEM REF.
Spacing
Distance in meters
1.5 TOWERS A 3 4.5 7.5 1.5 22.5 7.5 4.5 1.5 3 15 15 4.5 3 7.5 10.5 X 30 15 15 X 3 7.5
1.5 DRUMS D 1.5 4.5 7.5 1.5 22.5 7.5 4.5 1.5 3 15 15 4.5 3 7.5 10.5 X 30 15 15 X 1.5 7.5
7.5 Blowdown and Disengaging DRUMS F 7.5 15 15 7.5 22.5 X 15 7.5 7.5 15 15 15 7.5 15 15 X 30 15 15 X 4.5 7.5
3 AIRFIN COOLERS I 3 4.5 7.5 3 22.5 7.5 4.5 3 X 15 15 4.5 3 7.5 10.5 X 30 15 15 X 3 N.A.
15 FIRED HEATERS J 15 4.5 1.5 15 22.5 15 7.5 15 15 1 30 7.5 15 22.5 7.5 4.5 30 15 15 15 6 15
N.A. MAIN EQUIPMENT STRUCTURES T X 4.5 4.5 X 22.5 X 4.5 X X 15 15 4.5 3 7.5 X X 30 15 15 X X 7.5
4.5 ON SITE PIPE RACKS U 3 4.5 4.5 1.5 4.5 4.5 4.5 1.5 3 6 4.5 3 1.5 4.5 4.5 X 7.5 4.5 4.5 X X X
REF. A B C D E F G H I J K L M N O P Q R S T U V
COMPRESSORS & Expanders, For Flammable Gasses
REACTORS, Above Auto Ignition, Externally Insulated
Notes :
REACTORS, Above Auto Ignition, Internally Insulated
access.
EXCHANGERS, Operating Above Auto Ignition
process-
Blowdown and Disengaging DRUMS
ing equipment.
3) See notes in section 7.
ITEM
SUBSTATIONS (Electrical)
FIRED HEATERS
TOWERS
DRUMS
Standard Specification
Equipment Spacing.
45 Major offsites pipe tracks K 6 15 4.5 X 7.5 4.5 4.5 45 15 N.A. 4.5 4.5 4.5 7.5 4.5 4.5 4.5
60 Railway main lines O 30 7.5 30 60 7.5 7.5 7.5 60 45 7.5 60 N.A. 45 N.A. N.A. 60 60
15 Plant Rail Facilities P 15 7.5 15 15 7.5 7.5 7.5 45 N.A. 4.5 45 N.A. 15 N.A. N.A. 30 15
30 Facilities for Heat Sensitive Materials E.G. TEL. and TML R 30 45 30 60 45 45 45 45 45 4.5 45 45 30 60 15 30 N.A.
REF. A B C D E F G H J K L M N O P Q R
Notes :
1) X = provide spacing based on
access.
ing equipment.
Boundary Fence
Cooling Towers
Process area
Fire Station
Mainfold)
products
Stations
TML
etc.