VxRail Appliance - VxRail Appliance Power Control Procedures-Power Down A Running VxRail Cluster
VxRail Appliance - VxRail Appliance Power Control Procedures-Power Down A Running VxRail Cluster
Topic
VxRail Appliance Power Control Procedures
Selections
Select Your Power Control Activity: Power Down a Running VxRail Cluster
What VxRail Software Version is the Cluster running?: v7.0.320
REPORT PROBLEMS
If you find any errors in this procedure or have comments regarding this application, send email to
SolVeFeedback@dell.com
Copyright © 2023 Dell Inc. or its subsidiaries. All Rights Reserved. Dell Technologies, Dell, EMC, Dell
EMC and other trademarks are trademarks of Dell Inc. or its subsidiaries. Other trademarks may be
trademarks of their respective owners.
The information in this publication is provided “as is.” Dell Inc. makes no representations or warranties of
any kind with respect to the information in this publication, and specifically disclaims implied warranties of
merchantability or fitness for a particular purpose.
Use, copying, and distribution of any software described in this publication requires an applicable
software license.
This document may contain certain words that are not consistent with Dell's current language guidelines.
Dell plans to update the document over subsequent future releases to revise these words accordingly.
This document may contain language from third party content that is not under Dell's control and is not
consistent with Dell's current guidelines for Dell's own content. When such third party content is updated
by the relevant third parties, this document will be revised accordingly.
Page 1 of 6
Contents
Preliminary Activity Tasks .......................................................................................................3
Read, understand, and perform these tasks.................................................................................................3
Page 2 of 6
Preliminary Activity Tasks
This section may contain tasks that you must complete before performing this procedure.
Table 1 List of cautions, warnings, notes, and/or KB solutions related to this activity
000196884: Dell EMC VxRail: Ensure vCLS VMs are deleted before VxRail cluster shutdown
490875: VxRail: Enter/exit Maintenance Mode and VxRail shutdown/startup with Horizon Air Hybrid-
Mode deployed
• VxRail 7.0.320 and later releases contain resolutions for two of the VMware vSAN issues detailed in
VMware Proactive Customer Advisory issued in June 2022: KB 88870
https://kb.vmware.com/s/article/88870. One issue is not yet resolved by VMware and requires the
workaround described in KB 88870. The Dell VxRail: VxRail Response to VMware Proactive
Customer Advisory for June 2022 contains more information https://www.dell.com/support/kbdoc/EN-
US/000201082.
2. This is a link to the top trending service topics. These topics may or not be related to this activity.
This is merely a proactive attempt to make you aware of any KB articles that may be associated with
this product.
Note: There may not be any top trending service topics for this product at any given time.
IMPORTANT: Please take our survey! VxRail Appliance Procedure Quality Survey
Page 3 of 6
Cluster Shutdown Procedure
Note: If DNS is hosted on VxRail, shutdown of DNS should be performed manually before shutting down
the cluster.
Description:
The VxRail Manager Shut Down Cluster feature provides users a graceful shutdown for the entire cluster
with just a few clicks. During the shutdown procedure, VxRail Manager provides detailed error messages
with links to appropriate knowledgebase articles if there are any problems.
Note: You are responsible for properly shutting down all client VMs. VxRail Manager will shut down all
VMs in the cluster. Dell highly recommends that you gracefully shutdown all client VMs before performing
this procedure.
1. [ ] Open a supported browser and go to the < IP of vSphere vCenter > using HTML5 Client
with administrative privileges.
2. [ ] Go to Home > Hosts and Clusters > VxRail-Cluster.
3. [ ] Right-click the cluster, select VxRail, and then click Shut down….
Page 4 of 6
Figure 2 Shut down confirmation page.
Note: If any of the pre-shutdown heath checks fail, the shutdown script will not complete. To bypass
known issues, you can select Ignore to bypass any task that is in an Error status. Only use this option
if you know the reason for the failure.
Note: If the time between the current hosts is not synchronized, you will see a warning message
during the cluster shutdown validation process and VXM will automatically synchronize the time
between the hosts.
Page 5 of 6
Figure 4 Confirm Operation
7. [ ] [Optional] If you are running on a Standard License and have VMs running on VSAN cluster with
the system, clicking confirm displays “Pre-check failed, please resolve the issue(s)
and retry”. Power off the VMs from the VMware vCenter manually, and then click retry to perform
the shutdown.
8. [ ] Click FINISH.
9. [ ] After the appliance has been shut down correctly, a message shows that the appliance shutdown
operation has started. Check the physical node power state after 15 minutes.
10. [ ] Wait for all the LEDs on the appliance to turn off. The locator LED of Node 1 will remain lit after
shutdown completed.
Page 6 of 6