UNIT RATE ANALYSIS (BASED ON PREVAILING MARKET RATES

(AGGREGATE-BASE)

Providing, laying and spreading graded aggregate base course material upto any thickness in base course in
required grade and camber and compacted to the required density by approved mechanical means (vibratory
roller, road packer and smooth wheel rollers

Rate Analysis for: 50.00 Cu.M


RATE AMOUNT
BREA DOWN OF ITEM UNIT QUANTITY
(Rs.) (Rs.)

A- MATERIAL

Graded Crush Aggregrate i/c haulage CM 63 725.00 45,312.50

B- LABOUR

Forman Hour 1 60.00 60.00

Labour Hour 3 43.75 131.25

C- MACHINERY i/c Fuel

Water Tanker i/c cost of water, diesel, driver, etc. Hour 2 500.00 1,000.00

Grader i/c cost of diesel, driver, etc Hour 2 1,750.00 3,500.00

Vibratory Roller i/c cost of diesel, driver, etc Hour 4 800.00 3,200.00

TOTAL Rs. 53,203.75


Add Contractor's Overheads Profit & Taxes 20.00% 10,640.75
Total 63,844.50
Cost for 50 Cu.M 63,844.50
Cost for 1 Cu.M 1,276.89
Cost for 1 Cft 36.16
Say Rs. 36.00