Professional Documents
Culture Documents
DC Cable Laying
DC Cable Laying
DC Cable Laying
Project Name: -
Client: -
Document No: - MSPL-OE-US-EL-27-002
Revision No: - 2
History of Revisions: -
The contents of this document are the sole property of Mahindra EPC Services Pvt. Ltd.
and any copying/reproduction of this document is strictly prohibited without prior
permission from MEPC in writing.
Copyright © 2017 Mahindra Susten Pvt Ltd. All rights reserved Page 1 of 8
MAHINDRA SUSTEN PVT. LTD SOP - DC Cable Laying (Underground & Tray)
Contents
Copyright © 2017 Mahindra Susten Pvt Ltd. All rights reserved Page 2 of 8
MAHINDRA SUSTEN PVT. LTD SOP - DC Cable Laying (Underground & Tray)
1. Purpose
To document a procedure for cable laying and termination at project site.
2. Scope
This Standard operating procedure will be applicable to all projects handled by Mahindra Susten Pvt Ltd.
across the demography of the country.
4. Responsibility
It is the primary responsibility of the Lead Electrical for Cable Laying as per the procedure ensuring
quality, health and safety as per the norms of the company with Site Engineers team.
It is primary responsibility of Lead Electrical to verify that requisite PPEs are being used & area
barricaded before allowing work & site HSE supervisor will monitor that correct PPEs are being used
& area barricaded. Record of these shall be maintained in FQP checklist.
After the completion of each stage (Cable laying, Termination, Earthing, Testing, Commissioning),
Lead Electrical shall arrange to get FQP filled up after verification. Site QC Electrical shall use this FQP
record for verification of correctness of job using FQP checklist records as mentioned above and
identify the pieces/item actually inspected.
Copyright © 2017 Mahindra Susten Pvt Ltd. All rights reserved Page 3 of 8
MAHINDRA SUSTEN PVT. LTD SOP - DC Cable Laying (Underground & Tray)
5. Methodology
Copyright © 2017 Mahindra Susten Pvt Ltd. All rights reserved Page 4 of 8
MAHINDRA SUSTEN PVT. LTD SOP - DC Cable Laying (Underground & Tray)
1. IR value of the cable drum must be checked before loading/transporting the cable drum to site.
2. With the help of lifting hydra crane, the drum should be carried to the site of execution. It must be
placed at from where it can be easily accessible. Once more, the IR value should be checked after getting
the cable drum to site of execution.
The above are Pre-requiste which has to be followed on both, cable laying on under ground and on tray.
Copyright © 2017 Mahindra Susten Pvt Ltd. All rights reserved Page 5 of 8
MAHINDRA SUSTEN PVT. LTD SOP - DC Cable Laying (Underground & Tray)
5. Check the cable shall be pulled over on rollers in the trench steadily and uniformly without jerks and
strain. The entire cable length shall as far as possible be laid off in one stretch.
Power cable to power cable: Clearance not necessary however, larger the clearance, better would be
current carrying capacity.
Copyright © 2017 Mahindra Susten Pvt Ltd. All rights reserved Page 6 of 8
MAHINDRA SUSTEN PVT. LTD SOP - DC Cable Laying (Underground & Tray)
6. Check cables are dressed properly and gap b/w the cables are maintained as per drawing.
7. Check 75mm sand bedding done above the cables.
8. Check laying of earth strips & communication cables as per the drawing.
9. Check Hume pipes are done at road crossing as per drawing
10. Check for warning tapes laid & back fill it up to ground level with natural soil. No heaps should be
created.
1. Ensure that the pre-requisite has been followed before starting the cable laying activity.
2. Check that the tray structures & trays were erected as per drawing.
3. Check that the cables were laid on the tray & dressed properly as in Fig-A.
Fig-A
4. Ensure that the cable ends were sealed and cable identifications were provided.
Copyright © 2017 Mahindra Susten Pvt Ltd. All rights reserved Page 7 of 8
MAHINDRA SUSTEN PVT. LTD SOP - DC Cable Laying (Underground & Tray)
Copyright © 2017 Mahindra Susten Pvt Ltd. All rights reserved Page 8 of 8