Jumlah Harga

No Nama Bahan / Upah / Alat Sat Harga Koef. JUMLAH


Upah Bahan Alat
Pasang dinding Double Kalsiboard
1 Pekerja OH 120,000.00 0.2000 Rp 24,000.00 Rp 24,000.00
2 Tukang OH 180,000.00 0.6000 Rp 108,000.00 Rp 108,000.00
3 Kepala Tukang OH 225,000.00 - Rp - Rp -
4 Mandor OH 225,000.00 0.0100 Rp 2,250.00 Rp 2,250.00
5 Balok Kayu m3 50,000.00 0.0250 Rp 1,250.00 Rp 1,250.00
6 Paku Kayu kg 28,175.00 0.3000 Rp 8,452.50 Rp 8,452.50
7 Skrup allumunium bh 500.00 8.0000 Rp 4,000.00 Rp 4,000.00
8 Kalsiboard lbr 140,000.00 0.7500 Rp 105,000.00 Rp 105,000.00
9 Compound zak 55,200.00 0.1200 Rp 6,624.00 Rp 6,624.00
10 Skrup Kalsiboard bh 500.00 32.0000 Rp 16,000.00 Rp 16,000.00
11 Amplas lbr 5,000.00 0.5000 Rp 2,500.00 Rp 2,500.00
Jumlah Rp 278,076.50
Jumlah Harga
No Nama Bahan / Upah / Alat Sat Harga Koef. JUMLAH
Upah Bahan Alat
Plasteran tembok
1 Pekerja OH 120,000.00 0.30 Rp 36,000.00 Rp 36,000.00
2 Tukang OH 180,000.00 0.15 Rp 27,000.00 Rp 27,000.00
3 Kepala Tukang OH 225,000.00 0.02 Rp 4,500.00 Rp 4,500.00
4 Mandor OH 225,000.00 0.01 Rp 2,250.00 Rp 2,250.00
5 Semen Portland Zak 0.13 60,000.00 Rp 7,740.00 Rp 7,740.00
6 Pasir Pasang m3 0.02 1,200,000.00 Rp 22,800.00 Rp 22,800.00
7 Alat Bantu ls 1.00 2,000.00 Rp 2,000.00 Rp 2,000.00
Jumlah Rp 102,290.00
Jumlah Harga
No Nama Bahan / Upah / Alat Sat Harga Koef. JUMLAH
Upah Bahan Alat
Acian tembok
1 Pekerja OH 120,000.00 0.30 Rp 36,000.00 Rp 36,000.00
2 Tukang OH 180,000.00 0.15 Rp 27,000.00 Rp 27,000.00
3 Kepala Tukang OH 225,000.00 0.02 Rp 4,500.00 Rp 4,500.00
4 Mandor OH 225,000.00 0.01 Rp 2,250.00 Rp 2,250.00
5 Semen Portland Zak 0.13 60,000.00 Rp 7,740.00 Rp 7,740.00
6 Pasir Pasang m3 0.02 1,200,000.00 Rp 22,800.00 Rp 22,800.00
7 Alat Bantu ls 215.00 100.00 Rp 21,500.00 Rp 21,500.00
Jumlah Rp 121,790.00
Jumlah Harga
No Nama Bahan / Upah / Alat Sat Harga Koef. JUMLAH
Upah Bahan Alat
Pasang Dinding dengan Seng Lama
1 Pekerja OH 120,000.00 0.2000 Rp 24,000.00 Rp 24,000.00
2 Tukang OH 180,000.00 0.4000 Rp 72,000.00 Rp 72,000.00
3 Kepala Tukang OH 225,000.00 0.0200 Rp 4,500.00 Rp 4,500.00
4 Mandor OH 225,000.00 0.0200 Rp 4,500.00 Rp 4,500.00
5 Kanal C- 75 m' 13,000.00 1.3000 Rp 16,900.00 Rp 16,900.00
6 Alat Bantu LS 1,000.00 1.0000 Rp 1,000.00 Rp 1,000.00
Jumlah Rp 122,900.00
Jumlah Harga
No Nama Bahan / Upah / Alat Sat Harga Koef. JUMLAH
Upah Bahan Alat
Pembuatan Lantai Beton
1 Pekerja OH 120,000.0 1.65 Rp 198,000.00 Rp 198,000.00
2 Tukang OH 180,000.0 0.25 Rp 45,000.00 Rp 45,000.00
3 Kepala Tukang OH 225,000.0 0.03 Rp 5,625.00 Rp 5,625.00
4 Mandor OH 225,000.0 0.08 Rp 18,000.00 Rp 18,000.00
5 Semen Portland Zak 60,000.0 4.36 Rp 261,600.00 Rp 261,600.00
6 Pasir Pasang m3 1,200,000.0 0.52 Rp 624,000.00 Rp 624,000.00
7 Alat Bantu ls 100.0 215.00 Rp 21,500.00 Rp 21,500.00
Jumlah Rp 1,173,725.00
Jumlah Harga
No Nama Bahan / Upah / Alat Sat Harga Koef. JUMLAH
Upah Bahan Alat
Cat Dinding Kalsiboard
1 Pekerja OH 120,000.00 0.0200 Rp 2,400.00 Rp 2,400.00
2 Tukang OH 180,000.00 0.0630 Rp 11,340.00 Rp 11,340.00
3 Kepala Tukang OH 225,000.00 0.0063 Rp 1,417.50 Rp 1,417.50
4 Mandor OH 225,000.00 0.0020 Rp 450.00 Rp 450.00
5 Cat Dasar kg 37,800.00 0.3700 Rp 13,986.00 Rp 13,986.00
6 Alat Bantu ls 2,500.00 1.0000 Rp 2,500.00 Rp 2,500.00
Jumlah Rp 32,093.50
Jumlah Harga
No Nama Bahan / Upah / Alat Sat Harga Koef. JUMLAH
Upah Bahan Alat
Pasang Rangka & Atap Baja Ringan
1 Pekerja OH 120,000.00 0.2470 Rp 29,640.00 Rp 29,640.00
2 Tukang OH 180,000.00 0.1760 Rp 31,680.00 Rp 31,680.00
3 Kepala Tukang OH 225,000.00 0.1170 Rp 26,325.00 Rp 26,325.00
4 Mandor OH 225,000.00 0.0800 Rp 18,000.00 Rp 18,000.00
4 Talang Jurai m' 35,000.00 0.1100 Rp 3,850.00 Rp 3,850.00 Rp 7,700.00
4 Kanal C- 75 m' 13,000.00 1.2200 Rp 15,860.00 Rp 15,860.00
4 Spandek 6x0,25 m' 35,833.33 2.8000 Rp 100,333.33 Rp 100,333.33
4 Reng Kencana m' 14,500.00 5.1000 Rp 73,950.00 Rp 73,950.00
4 Drilling Pendek bh 866.67 25.0000 Rp 21,666.67 Rp 21,666.67
4 Drilling Panjang bh 750.00 35.0000 Rp 26,250.00 Rp 26,250.00
4 Dynabolt dia 12x120mm bh 1,500.00 1.0000 Rp 1,500.00 Rp 1,500.00
Jumlah Rp 352,905.00
RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN : PERBAIKAN RUMAH DINAS


LOKASI : BANDAR UDARA H. ASAN SAMPIT
TAHUN : 2023

HARGA JUMLAH HARGA


NO URAIAN JENIS PEKERJAAN VOLUME SATUAN SATUAN
Rp Rp
1 2 3 4 5 6

1 Pekerjaan Bongkaran
- Pembongkaran Dinding Bata 1.00 Ls Rp 350,000.00 350,000.00
- Pembongkaran Atap Seng 1.00 Ls Rp 400,000.00 400,000.00
- Pembongkaran Closet Duduk 1.00 Ls Rp 350,000.00 350,000.00

2 Pekerjaan Dinding
- Pasang dinding Double Kalsiboard 19.76 m2 Rp 278,076.50 5,495,737.10
- Plasteran tembok 23.79 m2 Rp 102,290.00 2,433,479.10
- Acian Tembok 23.79 m2 Rp 121,790.00 2,897,384.10
- Pasang Dinding dengan Seng Lama 22.90 m2 Rp 122,900.00 2,814,655.80
- Pengadaan & Pemasangan Kaca Jendela 1.00 Ls Rp 150,000.00 150,000.00

3 Pekerjaan Lantai
- Pembuatan Lantai Beton 3.13 m3 Rp 1,173,725.00 3,674,580.86
- Nat Keramik 1.00 Ls Rp 250,000.00 250,000.00

4 Pekerjaan Pengecatan
- Cat Dinding Kalsiboard 33.05 m2 Rp 32,093.50 1,060,719.06
- Cat Daun Pintu & Dinding Seng 1.00 Ls Rp 1,000,000.00 1,000,000.00

5 Pekerjaan Pintu & Atap


- Pengadaan & Pasang Engsel Pintu 5.00 Set Rp 45,000.00 225,000.00
- Pasang Rangka & Atap Baja Ringan 34.18 m2 Rp 352,905.00 12,061,234.19

6 Pekerjaan Sanitasi
- Instalasi Air Baru 1.00 Ls Rp 350,000.00 350,000.00
- Instalasi Pipa Pembuangan Air Kotor 1.00 Ls Rp 750,000.00 750,000.00
- Pembuatan Penampungan Air Kotor 1.00 Ls Rp 250,000.00 250,000.00
- Pengadaan & Pemasangan Closet Duduk 2.00 bh Rp 1,700,000.00 3,400,000.00

JUMLAH 37,912,790.20
PPN 11% 4,170,406.92
JUMLAH TOTAL 42,083,197.12
PEMBULATAN 42,090,000.00