TS No.

047
SITE TESTING Page 1 of 6
SCHEDULE Revision 1

SITE TESTING SCHEDULE – FREQUENCY RELAY MiCOM P941, P942 & P943
Client: Site:
Client Ref:
Client Rep:
Circuit: Contract Number:
Test Engineer: Date Tested:

Panel

CCT Diagram no Rev.

Relay Serial No

Relay Model No
Vdc
Rated Voltage

Auxiliary Voltage

ELECTROSTATIC DISCHARGE (ESD)


The relay incorporates CMOS static sensitive devices, which may be damaged by static electricity discharged from
the body. When handling care should be taken to avoid contact with components and electrical connections. If the
relay is removed from its case for any period of time, it should be placed in an electrically conducting anti-static
bag. If making measurements on the internal electronic circuitry, it is preferable you are earthed to the case with a
conductive strap having a resistance to ground between 500kΩ - 10MΩ

WARNING
The use of equipment out of calibration is strictly prohibited. Prior to the
commencement of any activity on this STS, confirmation that all requiring
calibration carries a current calibration label.

NOTE: This document to be used in conjunction with Argus 4 manual

Pre-Commissioning Precautions

ALL circuit breaker closing, tripping and alarm circuits isolated. (Where practicable)

Before testing commences, the relay should be isolated from voltage transformers in line with local site procedures

Kirby 2019 TS 047 (Micom P941,P942 & P943) Rev 1


TS No. 047
SITE TESTING Page 2 of 6
SCHEDULE Revision 1

Preliminary Checks
Remove any packing material from relay and check for transit damage

Confirm the equipment corresponds to the relevant drawings

Where necessary, measure insulation resistance of all wiring

Carry out wire checks to relevant diagrams

Supply Checks

Confirm that the relay supply voltage and polarity is correct

Confirm that the relay auxiliary voltage and polarity is correct

Watchdog Contacts
Confirm that with the relay de-energised, contacts 11 & 12 are closed, 13 & 14 open

Confirm that with the relay energised, contacts 11 & 12 are open, 13 & 14 closed

Date & Time Settings


With an IRIG-B Signal

With IRIG-B signal active, adjust the time offset of the universal co-ordinated time (satellite
clock time) on the satellite clock equipment so that local time is displayed and the correct
year has been manually set

Remove the IRIG-B signal and auxiliary supply from the relay. Leave de-energised for
approximately 30 seconds. Re-energise, re-connect IRIG-B signal and confirm date & time
correct

Without an IRIG-B Signal

Confirm the cell {0804: DATE and TIME, IRGI-B Sync} is set to ‘Disabled’

Set the date and time using cell {0801:DATE and TIME, Date/Time}

Remove the auxiliary supply from the relay. Leave de-energised for approximately 30
seconds. Re-energise and confirm date & time correct

Kirby 2019 TS 047 (Micom P941,P942 & P943) Rev 1


TS No. 047
SITE TESTING Page 3 of 6
SCHEDULE Revision 1

LED Checks

Confirm the following LED’s function correctly with the relay energised

LED FUNCTION COLOUR STATE

Relay Healthy Green Lit

Alarm Yellow Flashing

Out of Service Yellow Lit


Lit (During setting
Trip Red
checks)
Lit (During setting
Programmable (8 off)
checks)

Field Supply Voltage

Confirm Field Supply voltage Polarity correct. Value measured between terminals 7/9 and Vdc
8/10 (40V – 60V with no load)

OPTO INPUTS

Connect the field supply voltage to the appropriate terminals for each input in turn. Confirm correct operation of each

OPTO INPUT OPTO INPUT


Correct Function Correct Function
NUMBER NUMBER
1 9 (P943 only)

2 10 (P943 only)

3 11 (P943 only)

4 12 (P943 only)

5 13 (P943 only)

6 14 (P943 only)

7 15 (P943 only)

8 16 (P943 only)

Kirby 2019 TS 047 (Micom P941,P942 & P943) Rev 1


TS No. 047
SITE TESTING Page 4 of 6
SCHEDULE Revision 1

Output Relays

With the MiCOM relay in test mode, energise each output relay in turn confirming correct operation

Output Relay Output Relay


Correct Function Correct Function
(All Models) (P942 & P943)
1 8

2 9

3 10

4 11

5 12

6 13

7 14

Voltage Inputs

Apply rated voltage to each transformer input in turn and record voltage displayed on the relay

Displayed Voltage Displayed Voltage


Input VT Voltage Applied
(Primary) (Secondary) ±1%
Va (C19 – C22)

Vb (C20 – C22)

Vc (C21 – C22)

Note: The Primary value displayed should be equal to the applied voltage multiplied by the corresponding voltage
transformer ratio set in the ‘VT and CT RATIOS’ menu column.

Setting Checks
Under/Over Frequency Level Detectors

Kirby 2019 TS 047 (Micom P941,P942 & P943) Rev 1


TS No. 047
SITE TESTING Page 5 of 6
SCHEDULE Revision 1

Check the pick up value of each frequency elements.


Vary the applied frequency for each of the frequency elements in use and record the pick up values in the table
below. (The RED starter LED will give indication of the elements picking up and dropping off.)
Also record the operating time for the element, to check the time delay has been set correctly

f+t SETTING OUTPUT TRIP


ELEMENT PU VALUE TIME DELAY
f+df/dt (Hz) RELAY LED
STAGE1
STAGE2
STAGE3
STAGE4
STAGE5
STAGE6

Final Checks Before Commissioning

Test wiring removed


Disturbed customer wiring re-checked:-
Relay event records reset
Relay fault record reset
Relay disturbance records reset
Relay alarms reset
Relay LEDs reset
Relay secondary front cover replaced

On Load Checks
Perform the On Load tests in accordance with section 6 of the Operation Guide (OG8611B)

Displayed Voltage
(Primary)
Displayed Voltage
(Secondary)
Main VT Ratio

Applied Value Displayed Value


Voltages
Va
Vb
Vc

REMARKS & TEST EQUIPMENT USED (Include Asset/Plant No’s.)

Kirby 2019 TS 047 (Micom P941,P942 & P943) Rev 1


TS No. 047
SITE TESTING Page 6 of 6
SCHEDULE Revision 1

SIGNED ____________________ FOR KIRBY DATE ____________________

____________________ FOR CLIENT DATE ____________________

Kirby 2019 TS 047 (Micom P941,P942 & P943) Rev 1