ID Task Task Name Duration Start Finish Half 2, 2566 Half 1, 2567 Half 2, 2

Mode มิ.ย. ก.ค. ส.ค. ก.ย. ต.ค. พ.ย. ธ.ค. ม.ค. ก.พ. มี.ค. เม.ย. พ.ค. มิ.ย. ก.ค.
1 1 Construction of Check Point 231 days 1/9/66 27/5/67
2 1.1 Stainless Steel of Little Marquees 201 days 1/9/66 22/4/67
3 1.1.1 Shop Drawings 10 days 1/9/66 12/9/66 10 days

4 1.1.2 Shop Drawings Approval 5 days 13/9/66 18/9/66


5 1.1.3 Purchasing and Delivery Materials 60 days 18/9/66 25/11/66
6 1.1.3.1 Stainless steel Pipe 60 days 18/9/66 25/11/66 60 days

7 1.1.3.2 Stainless steel Sheets 10 days 18/9/66 28/9/66 10 days

8 1.1.3.3 Stainless steel Casting works 14 days 18/9/66 3/10/66 14 days

9 1.1.4 Fabrication At Shop Thapanin 177 days 29/9/66 22/4/67


10 1.1.4.1 Check Point 2 Lage CP 1-1 =1 (H=9.5) 112 days 29/9/66 6/2/67
11 1.1.4.1.1 LEAF CANOPY 89 days 29/9/66 10/1/67
12 1.1.4.1.2 TRUNK 20 days 27/11/66 19/12/66
13 1.1.4.1.3 TOP TRUNK +BRANCH 36 days 9/12/66 19/1/67
14 1.1.4.1.4 Bright Annealed (BA) Surface Finishing 15 days 20/1/67 6/2/67
15 1.1.4.2 Check Point 2 Lage CP 1 =1 (H=7.6) 107 days 20/12/66 22/4/67
16 1.1.4.2.1 LEAF CANOPY 89 days 10/1/67 22/4/67 89 days

17 1.1.4.2.2 TRUNK 20 days 20/12/66 11/1/67 20 days

18 1.1.4.2.3 TOP TRUNK +BRANCH 36 days 20/1/67 1/3/67 36 days

19 1.1.4.2.4 Bright Annealed (BA) Surface Finishing 15 days 2/3/67 19/3/67 15 days

20 1.2 Foundation 2ต้นx4เข็ม=8 เข็ม 37 days 18/9/66 30/10/66


21 1.2.1 Bored pile 30 days 18/9/66 21/10/66 30 days

22 1.2.2 Footing 25 days 2/10/66 30/10/66 25 days

23 1.3 Checkpoint 2 Erection 128 days 30/12/66 27/5/67


24 1.3.1 TRUNK CP1 Lage CP 2 =1 (H=7.6) 6 days 30/12/66 5/1/67 6 days

25 1.3.2 INSTALL SCAFFOLDING 6 days 10/1/67 16/1/67


26 1.3.3 LARGE ERECTION TOP TRUNK+ BRANCH +NODE +LEAF 30 days 17/1/67 20/2/67 30 days

27 1.3.4 TRUNK CP2 Lage CP 1-1 =1 (H=9.5) 6 days 6/1/67 12/1/67


28 1.3.5 INSTALL SCAFFOLDING 6 days 16/1/67 22/1/67
29 1.3.6 LARGE ERECTION TOP TRUNK+ BRANCH +NODE +LEAF 30 days 23/4/67 27/5/67
Task Project Summary Inactive Milestone Manual Summary Rollup Deadline
Project: Little Marquee
Split External Tasks Inactive Summary Manual Summary Progress
Date: 25/8/66 REV.00
Prepared by K.Phornwit Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only