OSHE-F-10 Lifting Operations Permit

You might also like

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 2

 

 Document ID:
OSHE-F-010
Project: AL DAHRA 1.8MW Solar PV
 Rev : 0 
Panel Installation
 Issue Date
  20 AUG 2023
Lifting Operations Permit  Date: 20/8/2023

Project details Permit No PTW/L/0001


Project Name AL DAHRA 1.8MW Solar PV Number 1
Panel Installation
Specific location or area 4 locations:
where lifting will be  Front side warehouses1- 21-24/8/2023
conducted
2(plant loading trailers
area)
 Silo Building (Back side of
Date
the building (last right and
last left)

Company details
Company conducting the lift SME Company managing the GFTS-CES
(Subcontractor) lifting operation
Crane owner ___ Other companies involved __

People Involved (Names & Numbers)


Appointed Crane Supervisor
(Foreman/ Engineer) Ahmed / Renjith
___ 3rd party __
Crane driver competency and
expiry date __
___ 3rd party
Rigger competency and __
expiry date

Crane Involved
Maximum lift
____ capable in Tonnes
Make / Model
supplied
configuration (consult Load Chart)
Boom length to
Registration / Plant number Metres
be used
Yes Yes No
Is the Load chart available in Is SWL indicator
the crane calibrated
No
___/____/20__
3rd party Certification- last Certification due
inspection date ____/____/20___ date ____/____/20___
Last major ___/____/20__
Certificate Number
service
Yes / No Known defects
Monthly crane inspection sighted
with crane, if any

Complete a separate form if more than one hook or configuration is used.

Lifting gear
Item ID Number SWLL Date thoroughly
examined
- - - ____/____/20__
- - - ____/____/20__
   Document ID:
OSHE-F-010
Project: AL DAHRA 1.8MW Solar PV
 Rev : 0 
Panel Installation
 Issue Date
  20 AUG 2023
Lifting Operations Permit  Date: 20/8/2023

- - - ____/____/20__
Visual check made
by (Rigger)
The Lift
What is to be lifted
Place more detail on back of form
Solar PV Panels – Mounting Structures – Cables Trayes -Dc Cables Drums - Inverters
if req.
What is the weight of lifting
equipment used (Hook, spreader bar Tonnes Kgs
etc.)
What is the weight of the items to be
Are other cranes
lifted – include more info on back of
Tonnes involved Yes / No
form if required

Site Conditions
What is the ground
Obstructions in lifting location NO angle at the lifting
location 0 degrees
0 degrees if level ground
Is the area concealing Check ground
underground hazards i.e. Pipes, NO conditions for Solid
recently back-filled etc. outriggers
Wind 38 Km/h or 20.5
Could weather condition effect
Yes / No If yes, give details of Knots
this operation
the point where the Heavy Rain/Low
operation will cease visibility
Area barricaded off to prevent
unauthorised access Yes / No
Other __________

Information
Pre-start toolbox talk conducted 22-30 Aug 2023 Name supervisor who Esmat- Renjith
Underground services gave the toolbox talk
documentation held Yes / No

Approvals
I have checked the above information as indicated and confirm that to the best of my
knowledge, the information is accurate and therefore this form is valid until the prescribed
date, providing that conditions and provided information has not changed.

Name: HOSSAM Date


Deputy Project Manager HAMOUDA
Phone No. 0502258098
Signature:
22-30 Aug / 9 AM Prescribed ____________AM/PM
Prescribed start
date/Time
date/Time 22-30 Aug/ 9 AM ____/____/20__
Valid until
Date
Name: Rnjith
Lifting Supervisor
Signature: Phone No.
0562208135

Date
Name: Esmat
OSHE Representative
Signature: Phone No.
0501316752