Professional Documents
Culture Documents
TR-2-82 Connections For Precast Buildings
TR-2-82 Connections For Precast Buildings
I
CONNECTIONS FOR
I PRECAST PRESTRESSED
I CONCRETE BUILDINGS
including earthquake resistance
I
I L. D. Martin and W. J. Korkosz
I
I
I
I
I
I
I
I
I
I
Copyright 0 1982
I
I
By Prestressed Concrete Institute
All rights reserved. This book or any part thereof may not be
reproduced in any form without the’written permission of the
I
Prestressed Concrete Institute.
I
Library of Congress Catalog Card Number 82-81939
ISBN O-937040-20.7
I
I
Printed in U.S.A
I
I
I
I
I
I
I.
I
I
CONNECTIONS FOR
I PRECAST PRESTRESSED
I CONCRETE BUILDINGS
including earthquake resistance
I
I by
L. D. Martin and W. J. Korkosz
I
I
I A Research Investigation
I by
The Consulting Engineers Group, Inc.
I supported by
I
Washington, D.C.
and
I
I
I
March 1982
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
TABLE OF CONTENTS
I
1. INTRODUCTION AND OVERVIEW. . . . . . . . . . . . . . . . . . . . . . . . . . 1.1
I 1.1 Scope of This Study . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.2
1.2 Development of the Precast, Prestressed Concrete
I
1.2.3 Inhibitors to the Growth of the Industry . . . . . . . . 1.6
I
2.1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.1
2.2 Nature of Earthquake Forces on Buildings . . . . . . . . . . . . . 2.2
2.3 Predicting Structural Behavior . . . . . . . . . . . . . . . . . . . . . . . 2.4
2.3.1 Dynamic Analysis Procedures . . . . . . . . . . . . . . . . . 2.5
I
2.3.2 Seismic Building Design Codes . . . . . . . . . . . . . . . . 2.12
2.4 Design Philosophy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.19
2.4.1 Energy Principles . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.20
I
2.4.2 Displacement Ductility and Load Reduction
Factors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.20
2.4.3 Curvature Ductility . . . . . . . . . . . . . . . . . . . . . . . . . 2.24
2.5 Lateral Load Resisting Systems . . . . . . . . . . . . . . . . . . . . . . 2.27
I 2.5.1
2.5.2
2.5.3
Shear Wall Systems . . . . . . . . . . . . . . . . . . . . . . . . . . 2.28
Precast Frame Systems . . . . . . . . . . . . . . . . . . . . . . 2.37
Braced Frames . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.37
I
2.5.4 Floor and Roof Diaphragms . . . . . . . . . . . . . . . . . . . 2.39
2.6 Dynamic Characteristics of Precast Connections . . . . . . . 2.42
2.6.1 Shear Connections . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.42
I
2.6.2 Beam-Column Connections . . . . . . . . . . . . . . . . . . . 2.48
2.7 FutureTesting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.54
2.8 Performance of Precast Systems in Previous
Earthquakes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.57
I
2.9 Structural Integrity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.60
2.9.1 Definitions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.60
2.9.2 Philosophy of Design for Structural
I
Integrity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.61
2.9.3 Application to Severe Earthquake
Resistance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.63
2.9.4
I
Relationship to Service Load Design
Procedures.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.63
2.9.5 Current Design Provisions for Structural
Integrity.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.64
I
2.10 Hurricanes, Tornadoes and Other Wind Loadings . . . . . . . . 2.69
2.10.1 Comparison with Earthquake Loading . . . . . . . . . . 2.69
2.10.2 Building Code Requirements . . . . . . . . . . . . . . . . . . 2.69
I
2.10.3 Common Practice . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.70
2.10.4 Recommendations.. . . . . . . . . . . . . . . . . . . . . . . . . . 2.71
I i
I
I
3. SELECTION AND DESIGN OF CONNECTIONS.. , . . . . . . . . . . . . 3.1
I
3.1 Criteria for Connections of Precast Concrete
Members . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.1
I
3.1.1 Strength.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.1
3.1.2 Ductility . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.1.3 Volume Change Accommodation . . . . . . . . . . . . . . .
3.2
3.3 I
3.1.4 Durability . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.4
3.1.5 Fire Resistance . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.1.6 Fabrication Simplicity . . . . . . . . . . . . . . . . . . . . . . .
3.1.7 Erection Simplicity . . . . . . . . . . . . . . . . . . . . . . . . . .
3.5
“3.: I
3.1.8 Appearance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.io
3.2 COnCeptSOf COMedOn DeSign . . . . . . . . . . . . . . . . . . . . . .
3.2.1 LoadTransfer Paths . . . . . . . . . . . . . . . . . . . . . . . . .
3.11
3.11
I
I
3.2.2 Failure Modes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.12
3.2.3 Stability and Equilibrium . . . . . . . . . . . . . . . . . . . . . 3.13
3.2.4 Stress Relief Measures.. . . . . . . . . . . . . . . . . . . . . . 3.14
3.2.5 fbqansion.Joints . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.16
3.3 Designing Load Transfer Mechanisms . . . . . . . . . . . . . . . . .
3.3.1 Bearing ..................................................................
3.3.2 Shear Strength
3.16
i.tz
.
I
I
3.3.3 Tensile Strength . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.26
3.3.4 Anchorage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.26
3.3.5 Friction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.31
I
3.4 Load Transfer Devices . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.32
3.4.1 Bolts and Threaded Connectors . . . . . . . . . . . . . . . . 3.32
3.4.2 Inserts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.37
3.4.3 Welded Studs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.44
I
3.4.4 Welding . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.47
3.4.5 Reinforcing Steel . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.53
3.4.6 Dowels . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.55
I
3.4.7 Post-Tensioning Steel . . . . . . . . . . . . . . . . . . . . . . . . 3.56
3.4.8 Pads and Other Bearing Devices . . . . . . . . . . . . . . . 3.57
3.4.9 Cast-In-Place Concrete . . . . . . . . . . . . . . . . . . . . . . 3.59
I
3.4.10 Grout . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.59
3.4.11 Epoxy Resins . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.61
3.5 Special Designs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.62
3.5.1 Reinforced Concrete Corbels . . . . . . . . . . . . . . . . . 3.62
I
3 S.2 Structural Steel Haunches . . . . . . . . . . . . . . . . . . . . 3.64
3.5.3 Dapped-endBeams . . . . . . . . . . . . . . . . . . . . . . . . . . 3.79
3.5.4 Hanger Connections . . . . . . . . . . . . . . . . . . . . . . . . . 3.78
References - Part 3 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.84
I
TYPICAL CONNECTION DETAILS . . . . . . . . . . . . . . . . . . . . . . . . .
I
4. 4.1
4.1 Column to Foundation - CF . . . . . . . . . . . . . . . . . . . . . . . . . . 4.3
4.2 Column to Column - CC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . t.ti
I
4.3 Beam to Column - BC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.4 Slab to Beam - SB . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . i.Ei
4.5 Beam to Girder - BG . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
I
4.6 Beam to Beam - BB . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4:65
4.7 Slab to Slab - SS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4.69
ii
I
I
I 4.8
4.9
Wall to Foundation - WP . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Slab to Wall-SW . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.75
4.82
4.10 Beam to Wall-BW . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4.96
I 4.11 Wall to Wall-WW..................................4.10 1
Committee authored a draft report for that committee which was the basis for Section
I
2.5 of this report. D. P. Jenny, PC1 Technical Director was very helpful in digging up
I
I
resource material. Both he and G. D. Nasser, editor-in-chief of PC1 technical
Wiss, Janney, Elstner and Associates added their experience from failure investigations
and critique of Parts 3 and 4 of this report. With this help, the authors feel that this
I
document represents the latest state-of-the-art in precast concrete connection design
and detailing.
This material is based upon work supported by the National Science Foundation
I
I
under Grant No. PFR-7820900. Any opinions, findings, conclusions or recommendations
expressed in this publication are those of the authors and do not necessarily reflect the
I
views of the National Science Foundation or the Prestressed Concrete Institute.
I
I
This report is published and distributed by the Prestressed
Concrete Institute through agreement with The Consulting
Engineers Group, Inc., and with the forehowledge of National
Science Foundation. PC1 producer members, technical committees
and staff participated in the project as indicated in the
acknowledgements. However, the Prestressed Concrete Institute
cannot accept responsibility for incorrect engineering designs
I
I
resulting from errors or omissions in the report or misuse of
the matekal contained in the report.
I
iv
I
I
I
I
I
I
I
I P A R T 1
I INTRODUCTION
I
I
I
I
I
I
I
I
I
I
I
I
I 1. INTRODUCTION MD OVERVIEW
I an important method of framing for structures. Virtually all types of structures are
being built with this material-industrial buildings, parking garages, commercial build-
I
partly because the material is precast, partly because it is prestressed, and partly be-
cause it is concrete.
I
Precasting offers the opportunity of compressing construction time schedules.
For example, superstructure members can be cast and cured simultaneously with site
work and foundation construction. Erection of precast members takes less time compar-
I higher strength concrete, improved quality control and better opportunities for standard-
ization.
I
Compared with ordinary reinforced concrete, the use of prestressing allows
longer spans with shallower depths, more controllable performance in terms of cracking
I
and deflection, and less material usage.
The principal advantages of concrete over other materials such as timber and
steel are fire resistance and durability.
I ized:
The disadvantages of precast, prestressed concrete can be similarly categor-
I
facilities within a reasonable hauling distance of the project.
Prestressing places concrete under constant compression, thus creep strains
I
are greater than in non-prestressed concrete. Eccentric prestressing, the most advanta-
geous structurally, causes cambers which must be considered in the design.
Compared with timber and steel, concrete members are heavier and bulkier,
I which can be a disadvantage in seismically active areas, or on sites with poor soils.
It should be noted that costs are not listed in any of the advantages or disad-
I
I 1.1
I
tive for a given type of structure, depending on the design requirements, geographical
I
location, code restrictions, etc. It is to the advantage of the construction consumer to
have a choice of framing methods available, and to be assured that any method selected I
is designed and detailed in the most economical manner. It is axiomatic that the struc-
tures must be structurally able to resist loads that are likely to occur during the life of I
I
the structure.
1.1 Scope of this Study
I
This study represents the state-of-the-art, of precast concrete connection
technology. Special emphasis has been placed on the special considerations involved in
I
designing for earthquake resistance. However, the design methods of Part 3, and the
connection details shown in Part 4 apply to connections in general. It is intended that
I
those two parts serve as a general guide to improved design and construction of connec-
tions of precast and prestressed concrete. The special requirements for earthquakes and
other unusual loading such as hurricanes and tornadoes are contained in Part 2.
The team involved in this study has had extensive experience in the design and
construction of precast, prestressed concrete structures. Three consulting engineering I
I
firms were involved. These three firms have specialized in various aspects of the con-
struction method; design, detailing, field supervision and investigation of performance
I
and failures. The staff and members of the Prestressed Concrete Institute were also
deeply involved. Membership of PC1 includes companies and individuals who are actively
involved in the design, fabrication and construction of precast, prestressed concrete
buildings and bridges.
An extensive literature search and review was a major part of this study.
I
Bibliographies and references are given in each part. This report is a synthesis of the
pertinent information contained in the literature, supplemented by the hands-on exper- I
I
ience of the study team.
Interviews were conducted with people in the design and construction
I
community; building officials, engineers, architects, contractors and educators. Their
views as to the advantages, limitations and research needs were incorporated into the
study.
I
I
I
1.2
I
I
I 1.2 Development of the Precast, Prestressed Concrete Industry in
I 1.2.1
North America
History
I The basic concept of prestressed concrete was first patented in the United
States in 1886, but it was almost a half century later before the initial shortcomings
I plates bearing on the ends of the concrete member. Because shrinkage and creep can
cause about 0.1% shortening of the concrete, the initial stress in the steel diminished.
I
The bolts became loose and the concrete was no longer prestressed. Eugene Freyssinet, a
French engineer, demonstrated in the 1930’s that prestressing could be done successfully
I
if high strength steel were used. Thus if the concrete subsequently shrinks and creeps
0.1% of its length, the steel stress reduction (now called prestress losses) of 30,000 psi
could be accommodated, particularly if the initial steel stress was in the order of 150,000
I psi. Today most cold-drawn prestressing steels have an ultimate strength of at least
250,000 psi, and initial stresses of 175,000 to 190,000 psi are commonly used.
I After World War II, Europeans began to use prestressed concrete in their
rebuilding programs, principally because it afforded more efficient use of steel and
I
concrete. Most of the prestressed concrete used in Europe shortly after World War II was
post-tensioned rather than pre-tensioned, so it is not surprising that the first uses of
I
prestressed concrete in the United States employed post-tensioning. But shortly after
the first major project in the United States, the Walnut Lane Bridge in Philadelphia in
1951(l’l), Americans began to consider the advantages of plant-produced prestressed
I concrete.
In 1952 several prestressed concrete manufacturing plants, located mainly in
I
Several factors were responsible for the fact that plant-produced prestressed
concrete became popular in America before similar trends were apparent in Europe. Jn
I
America, good roads, a well developed trucking industry capable of hauling heavy bulky
loads, readily available mobile erection equipment, and high priced field construction
labor combined to make precast, prestressed concrete economical.
I From its modest start in the early 1950’s, the prestressed concrete industry
has grown steadily into a network of competing plants throughout the United States.
I
I 1.3
I
I
I
I
I
I
I
I
I
Fig. l-l - Estimates of dolkc sales of precast and prestresaed concrete
I
for the United States and Canada, 1950 through 1980
I
Fig. l-l shows the sales of precast and prestressed concrete in the United States and
Canada from 1951 through 1980(1*2). The growth rate between 1959 (sales of $100
million) and 1975 (sales $1.2 billion) averaged more than 16% annually. Since 1973 the
I
sales volume has fluctuated between about $1.1 and $1.8 billion annually, reflecting the
general volume of construction, excluding one- and two-story houses.
I
1.2.2 Development of standard products
I
profession had no standard sections, designers often developed sections that would best
solve a particular problem. In turn, the precaster purchased forms (often expensive steel
forms) to produce the product. That product then became a “standard” in the precaster’s
I area.
Some of the floor and roof slabs which were used on early projects included
I double tees, mono-wing tees, channels, single tees, quad-tees, solid flat slabs, and many
variations of these shapes. Through the years double tees proved to be the most econom-
I
ical for spans of 30 to 70 ft and have become standardized through industry efforts.
The earliest double tees were 4, 5, or 6 ft wide and were generally 12 to 18 in.
deep, with 14-in. deep by 4-ft wide double-tees gaining the widest usage. However, most
I double-tees made today are 8 ft wide and many are 9, 10, and 12 ft wide. Depths range
from about 12 in. to 40 in. The 24-in. deep by 8-ft wide section is the most widely used.
I
hollow-core slabs were developed in Germany during the 1940’s. (The first such machine
was brought to the United States in 1954 in such poor condition that it was classified as
I
scrap on the trams-Atlantic crossing!) The growth of hollow-core slab production in the
United States was slow at first, probably because of the high capital investment required,
but during the 1960% and 70’s the use of hollow-core slabs increased sharply and now is
I the most used single product in the precast, prestressed concrete industry.
Hollow-core slabs were initially made in 4, 6, and S-in. depths, but today most
I units are 8 in. deep and many are 10 and 12 in. deep. Most hollow-core units have widths,
depths, and core shapes dictated by the manufacturing process. Most are machine-made
I
or are made in highly automated plants. They are generally marketed by the trade name
of the manufacturing equipment licenser, such as Spancrete, Flexicore, Span-Deck,
I
Spiro& Dy-Core, etc. Although the depths of hollow-core slabs have been standardized,
the widths are established by the manufacturing equipment. For example, Spancrete is
generally 40 in. wide, essentially the same as the width of the original German product,
I one meter. Flexicore is generally 24 in. wide, Spiro& Dy-Core, and Span-Deck are
generally 48 in. wide, but many Span-Deck and some Dynaspan slabs are 96 in. wide.
I
I 1.5
I
Precast concrete wall panels also constitute a large segment of the industry.
I
These panels can be loadbearing or non-loadbearing, and can be architectural and/or
structural. Manufacture of precast concrete wall panels predates the prestressing indus- I
try. Precast concrete wall panels were used on many notable structures prior to World
War II, and were referred to as “cast stone”, I’art stone”, and other similar terms. Many I
I
of these panels are still in use and serve as a testimony to the craftsmanship of the
builders and the durability of concrete panels.
Most of the early uses of precast wall panels were attempts to imitate natural
stone (limestone, sandstone, granite, or marble). Such panels were usually non-loadbear-
ing and were rather small in comparison to current practice. Connection details were
I
adaptations of those used for natural stone.
With the growth of the industry in America, the use of larger precast wall I
I
panels became economical. Wall panels of a variety of shapes, patterns, and textures
could be produced. These included custom-made architectural panels and %tandardtf wall
I
panels made of structural shapes, such as double-tees and hollow-core panels. Many of
these panels serve both architectural and structural functions. In recent years an in-
creasing number of precast concrete wall panels have been made as sandwich panels
incorporating an insulating material to help reduce heat losses.
In addition to floor and roof slabs and wall panels, a wide variety of other I
I
precast building elements are made. These include beams, columns, fascia panels,
column covers (for steel columns), elevator shafts, piles, and balconies. These items
I
have not been standardized by the industry, but most precasting firms generally make
only a small number of different sizes of each item.
I
Through the years the PC1 Committee on Standardization has been able to
develop certain standards, most notably those for double-tees. In addition, standards for
depths of hollow-core units and single tees have also been successfully developed. The
publication of the first edition of the PC1 Design Handbook(l’*) in 1971 helped to speed
up the standardization process, not only for cross sectional dimensions, but for design I
I
procedures as well.
1.2.3 Inhibitors to the Prowth of the industry
The growth of the precast prestressed concrete industry did not proceed
without problems. Indeed, the industry grew because the technical soundness of pre-
I
stressed concrete out-weighed the unsolved problems. A great deal of research on pre-
stressed concrete was conducted in the early 1950’s. Much of the research involved I
I
flexural behavior, deflection and camber prediction, and bond and anchorage stresses.
1.6
I
I
I Later researchers studied end-block stresses, behavior under repeated loads, shear
strength and prestress losses. In the early 1960’s, systems studies were begun of fire
I resistance, long term durability, restrained shortening stresses, and certain connection
details. Research on some of these topics, most notably connections is still incomplete.
I One of the problems faced and solved by the industry in the 1950’s was the
lack of building code provisions. Prior to publication of the 1963 AC1 Building Code
I
1958(1’5), and in 1959, PC1 published building code provisions (1.6). However, many
building officials were reluctant to approve the use of prestressed concrete until the
I
local building codes adopted the 1963 AC1 Code(1’71.
Another problem faced by the young industry was that of fire resistance.
Because prestressed concrete is made with cold-drawn prestressing steel which is affect-
I ed more by high temperatures than other steels used in construction, questions about the
fire resistance arose. In 1957, PC1 organized a committee on fire resistance, and in 1958
I
the first full-scale standard fire tests were conducted at Underwriters Laboratories.
Through the years, the industry has sponsored both standard tests and comprehensive
I
research programs, to the point that more data exists on the behavior of prestressed
concrete exposed to fire than most other construction materials (1.8). In recent years, a
methodology for calculating fire endurance of prestressed concrete has been developed.
I The PC1 publication, “Design for Fire Resistance of Precast Prestressed Concrete t&9 ,
is accepted by most building officials as an alternate method to fire testing for deter-
I
in its simplicity. It is best usad in simple span, pin-ended beams and deck members. The
absence of continuity and redundancy has caused some designers to question stability
I
under high lateral loads.
Precast, prestressed concrete has been used in many areas throughout the
world which are subjected to high winds (hurricanes, typhoons, and tornadoes) and to
I earthquakes. Many thousands of buildings, bridges, stadiums and other structures have
been built of precast, prestressed concrete in hurricane-prone regions and in seismically
I active areas of the western United States, Alaska, Japan, New Zealand, Indonesia and
along the Mediterranean Coast, as well as in western South America. Many of the struc-
I
tures have successfully withstood hurricane forces and earthquake motions. Some
precast concrete structures have been damaged by earthquakes. Overall behavior of
I
precast concrete structures in earthquakes has been about the same as that for steel or
I 1.7
I
cast-in-place concrete structures. However, the number of precast concrete buildings I
that have been involved in serious earthquakes is relatively small, so it may be premature
to make any general conclusions. This aspect of precast, prestressed concrete construc-
tion is one of the primary purposes of this study. It is discussed in detail in Part 2.
I
Probably the most persistent problem facing the industry has been that of
adequate connections to withstand the variety of stresses and movements imposed by
I
gravity loads, repeated loads, creep and shrinkage forces, temperature changes and
intermittent lateral forces of wind and earthquake. Early attempts at developing ade- I
I
quate connections resulted in either go-no-go details or complex empirical expressions
that did not relate directly to imposed shears, moments, and direct forces. The relative-
I
ly recent concept of ‘shear-friction” has been of considerable help in developing rational
design methods to replace empirical relationships. But the problem of providing econom-
ical connections that will transmit the required forces without unduly restraining the
volume change movements which occur still persists. The other primary thrust of this
report is to synthesize available information on connections design and detailing. These
I
aspects are covered in Parts 3 and 4.
Despite these shortcomings, the prestressed concrete industry has had an I
I
impressive growth record. Failures which have occurred have been well publicized and
the industry has worked to prevent similar Occurrences by disseminating information to
I
designers.
I
I
I
I
I
I
I
1.8
I
I
I .
RJWERENCES - PART 1
I - Chicago)
(1) “Standard Prestressed Concrete Beams for Highway Bridge Spans 30 ft to
I
140 ft”.
(2) “Standard Presstressed Concrete Box Beams for Highway Bridge Spans to
103 Feet”.
I
(3) “Standard Prestressed Concrete Slabs for Highway Bridge Spans up to 55
Feet”.
(4) ‘Standard Prestressed Concrete Piles lo”, 12”, 14”, 16”, 18” 20”, 22”, and
24”“.
I
“Prestressed Concrete Cylinder Piles 36” - 48” - 54”“.
I:; “General Notes - Prestressed Concrete Piles”.
I
1.4 “PC1 Design Handbook - Precast and Prestressed Concrete”, First Edition, 1971,
Prestressed Concrete Institute, Chicago.
1.5 ACI-ASCE Joint Committee 323, “Tentative Recommendations for Prestressed
I 1.6
Concrete”, AC1 Journal, v.29, no. 7, Jan. 1958.
“PC1 Standard Building Code for Prestressed Concrete (Tentative)“, Std. llO-59T,
I
Prestressed Concrete Institute, Chicago.
1.7 “Building Code Requirements for Reinforced Concrete (AC1 318-63Y’, June, 1963,
I
American Concrete Institute, Detroit.
1.8 “Fire Resistance DirectoryI’, Jan, 1980, Underwriters Laboratories, Northbrook, IL.
I
1.9 Gustaferro, A. H., and Martin, L. D., “PC1 Design for Fire Resistance of Precast,
Prestressed Concrete”, 1977, Prestressed Concrete Institute, Chicago, IL
I
I
I
I
I 1.9
.
I
I
I
I
I
I
I
I
P A R T 2
I
KARTHQUAKIS AND OTHER EXTREME LOADING
I
I
I
I
I
I
I
I
I
I
I
I
I 2. EARTHQUAKE AND OTHER EXTREME LOADING
2.1 Introduction
I An earthquake is one of nature’s most unpredictable and devasting
I
forces. The energy release causes forces which often are greater than the structural
resistance of natural and man-made structures. Loss of life, structural collapse, or
I
excessive structural damage often occur unnecessarily in major earthquakes. The pre-
vention of these unfortunate events can only occur if proper design, detailing and quality
I
control are incorporated into the structural system. The present state of knowledge in
earthquake-resistant design has produced economical structures which have performed
safely in major earthquakes, but further research and advancement is still required. This
I is especially true when precast and prestressed concrete elements are used in earth-
quake-resistant structural systems.
I The major emphasis in earthquake resistant design has centered around the
use of steal and cast-in-place concrete as the major structural materials. Ductility,
I
energy dissipation, and the ease of producing monolithic redundant structures has made
these materials the forerunners in earthquake-resistant research and construction.
I
In the United States, the popular acceptance of prestressed and precast
concrete as a seismic lateral load resisting system has generally been limited to low rise
panel structures. Although this trend is changing, the U. S. is still conservative compar-
I ed with other seismic regions of the world such as Japan, Cuba, and Eastern Europe,
where multi-story construction of large precast panel buildings is widespread (2.33).
I
post-elastic behavior, and cyclic strength of connections are dark areas which lack
information. As a result, design provisions and code requirements are often ambiguous,
I
vague, or non-existent regarding precast construction. Consequently, building officials
and design engineers often interpret code requirements differently, which results in
costly delays or total rejection of the precast system. Knowing this, owners and design-
I ers tend to prefer cast-in-place concrete and steel in seismic areas, since design con-
cepts and code requirements are well established and clearly documented.
I
The major building codes such as AC1 318-77(2’25), or the Uniform Building
Code(2.15) , have special provisions for the seismic design of reinforced concrete struc-
I 2.1
I
I
tures. They do not, however, have corresponding provisions for prestressed or precast I
concrete structures. The present design codes generally require precast systems to
conform to the requirements of reinforced concrete even though these requirements I
were developed for cast-in-place concrete and in many instances do not apply to precast
systems. I
I
The remainder of this section discusses some basic engineering principles
associated with the code requirements for reinforced concrete. Emphasis is placed on
the requirements for connections and the validity of applying reinforced concrete re-
quirements to precast and prestressed systems. The section is intended to provide a
better understanding of connection design for the engineer with limited experience in
I
I
seismic or precast-prestress design. The section also describes what little data there is
available on precast seismic behavior, and areas in need of future research.
2.2 Nature of Earthquake Forces on Buildings
A map showing the location of major seismic activity is shown in Fig. 2-l.
I
Highest seismic regions include the coasts of the Pacific Ocean from Chile through
Central America, along the coasts of the United States, through the coastal islands of I
I
British Columbia, southern Alaska, the Aleutians, Japan, the Philippines, New Guinea,
and New Zealand. Other major areas of seismic activity include central and eastern
I
United States, the Mediterranean coast, central Asia, and most of Indonesia. These areas
and other areas with previous seismic activity are major areas of concern for earthquake
resistant structural design.
The most widely accepted explanation of the origin of earthquakes is the
“elastic rebound theory” proposed by H. P. Reid in 1906. Reid claimed the occurrence of
I
I
an earthquake is due to a sudden shear fracturing, or faulting along planes of weakness in
crustal rock. The exact forces which produce the internal fracturing strains is not fully
I
known, but viscous movement of crustal plates is believed to be a major source.
When crustal rock fractures, energy is released in the form of a dynamic
I
wave. The vibratory ground action produced by the passing of this wave is what consti-
tutes an earthquake. When fracturing occurs along a number of different planes the
dynamic waves interact in a complex random motion. The magnitude of ground oscilla-
tion associated with this motion will depend on the ground material, the medium through
which the wave traveled, and the distance the wave traveled. Thus, the ground motion I
for a given earthquake will vary with the structural site.
The ground motions produced during an earthquake are recorded in the I
I
form of ground accelerations. Accelerations in both the horizontal and vertical direc-
2.2
I
I .-. .,.
-
i -4% t
%- 2-l - Map shone global seismicity for the year 1966 (Ref. 2.2)
0.3r I,
0.2
01
:: 0
-01
-0.2
-0.3 Ground Acceleration, y
I
design.
Generally, the magnitude of horizontal ground acceleration in a major
earthquake will range from 0.2 to 0.5 g, while vertical ground accelerations hardly ever
exceed 0.1 g.
2.3 Predicting Structural Behavior
I
Two procedures are used to design structures to resist earthquakes. High I
I
rise or complex shaped buildings may be analyzed dynamically, using a predicted or
recorded ground motion. Most common, however, is to apply equivalent static loads
which are prescribed by building codes.
2.3.1 Dynamic Analysis Procedures
I
I
Dynamic analysis of a structure can be very complex and a detailed treat-
ment of the subject is beyond the scope of this report. There is even some disagreement
among design engineers as to the value of complex dynamic analyses, given the unpre-
dictable nature of earthquake movements and the necessity of making what may be
rather broad assumptions as to the response of foundation materials, the capacity for
I
damping, the post-elastic behavior of the structural components, etc.
Nevertheless, all modern methods of earthquake analysis are based on at I
I
least approximations of dynamic forces, so a brief overview of dynamic analysis proce-
dures is useful in understanding the various design techniques, including equivalent static
loads.
2.4
I
I
I The various dynamic analysis procedures determine the structural response
I of a system by solving the equations of motion for an acceleration applied at the base of
the structure. The design acceleration may be determined from an accelerogram record
of an actual earthquake, Fig. 2-2, or from a simulated motion generated from a geolog-
I ical study of a given site.
I
Three main methods are currently used for dynamic analysis. They are:
1. direct step-by-step integration of the equations of motion
I
2. normal mode analysis
3. response spectrum method
I
2.3.1.1 Direct Integration
Direct integration of the equations of motion is the most sophisticated
I
analysis method available for earthquake design. It is a step-by-step procedure which
determines forces and displacements by summing the response of the structure during
very short time increments. The structure is assumed to be linearly elastic during each
I increment of time, but between increments the properties of the structure are modified
in accordance with the current deformation condition.
I interval(2’4).
The following steps summarize the analysis procedure during each time
I
1. The stiffness of the structure for the time interval is evaluated,
based on the state of displacement existing at the beginning of the
I
interval.
2. Changes in displacements are computed, assuming the accelerations
to vary linearly during the interval.
I 4.
the end of the interval.
Stresses are computed from the total displacements, taking into
I
account non-linear material properties.
The accuracy of the direct integration procedure is dependent on the
I
analysis method, the ground motion, and the modeling of the non-linear properties. For
precast concrete, little information is available on the linear or non-linear dynamic
behavior of connections. Thus non-linear analysis by direct integration is not as common
I for precast structures as it is for steel or monolithic concrete structures. ‘lhe majority
of non-linear analyses that have been performed for precast concrete involve the behav-
I 2.5
I
I
I
I
I
First (fundamental)mode Second mode Third mode
I
I
2.3.1.2 Normal Mode Analysis
Normal mode analysis is more limited than direct integration analysis,
I
since non-linear behavior cannot be taken into account. Like direct integration, normal
mode analysis applies earthquake accelerograms to the structure and uses a stress history
to determine the structural response. However, unlike direct integration, the normal
mode analysis procedure uncouples the different modes of vibration for the structure.
The accuracy of the analysis is then affected by the number of modes which are superim-
I
posed.
A structure will generally have as many modes of vibration as it has signif- I
I
icant degrees of freedom. For the elastic response of multi-story buildings the first or
fundamental mode contributes about 80% of the total structural response, while the
I
second and third modes contribute about 15’%6(2*1). Thus sufficient accuracy can be
obtained with the superposition of the first few modes. Fig. 2-3 shows the first three
natural modes of vibration for a multi-story structure.
2.3.1.3 Response Spectrum I
I
The simplest of the dynamic analysis procedures uses a predetermined
a “response spectrum”. A response spectrum relates the maximum responses (acceleration,
velocity or displacement) of a structure to its natural frequency of vibration or period.
(Note: the velocities and accelerations shown in a response spectrum are not the actual
values, but values chosen for convenience in analysis. They are usually called ‘pseudo-
I
velocity” or “spectral velocity” and “pseudoacceleration” or “spectral acceleration”.)
Fig. 2-4 shows combined response spectra developed from the ground motion recorded
I
during the El Centro Earthquake. Fig. 2-S is an idealized version of the acceleration
response spectra for the same earthquake, which is more useful for design. I
I
The values shown in a response spectrum represent the maximum response
2.6
I
I
I
I
I
I
I
I
I
I
2-4 - Response spectra for El Centro Earthquake of May 19, 1940, N-S co
I
I
I
I
I
I
I Period ol vibration, T ( oec)
I
I 2.7
I
I
Mass
I
/////////i-t_.
t
I
‘x 1 Damper X- Ground displacement
I
Original
Position
:
7
A
D: Mass displacement I
I
:
‘7r///////////////////////////////////////// I
I
ness and damping characteristics change. The total reponse is obtained by applying a
“modal participation factor” and summing the responses, similar to the method used in
the nor ma1 mode analysis.
Pseudovelocity, V, and pseudoacceleration, A, are related to the displace-
ment D, of the system by the following equations:
I
A =W2D (2-la)
(2-lb)
I
I
V~=wD
Where w i,s the circular frequency of vibration for the system and is defin-
Q-2)
I
I
where K = stiffness of the system
m. = mass of the system
I
The natural frequency, f, and period, T, of the system are given by the
relationship:
To illustrate the use of the response spectrum technique, assume the frame
I
in Fig. 2-6 is to be analyzed for the motion produced by the El Centro Earthquake. If the
stiffness of the frame is 25 kip/in. and the mass is 0.6 kip-sec2/in., then the circular I
I
frequency and period of the frame are:
2.8
I
I
I
w = E= r& = 6 . 4 5 radlsec
I
f = k = !y = 1.03 cps
I
I
T = + = 0.97
I 9 ft/sec2.
I
D = if = -$~f = 0.22 ft = 2.6 in.
I
The maximum base shear can be computed in two ways:
I The response spectra for the El Centro earthquake and response spectra for
I
other dynamic motions usually have the following characteristics (2.3).
1. For very low frequencies the maximum response displacement, D, is
I
virtually constant and is equal to the maximum ground displacement.
2. For very high frequencies the maximum pseudoacceleration, A, of
the mass is virtually constant and is practically equal to the maxi-
I 3.
mum acceleration of the ground.
For intermediate frequencies, the maximum response displacements,
I velocities and accelerations are all amplified over the ground motion
maxima. For damping values in the range of 5 to 10 percent, the
I
amplification factors are approximately 1.0, 1.5 and 2.0 for dis-
placement, velocity and acceleration.
I
Fig. 2-5 shows that the largest accelerations, or forces for elastic response,
will occur in structures with natural periods of vibration around 0.5 seconds. Periods
greater than this produce much lower accelerations, white shorter periods tend to have
I
I
2.9
I
accelerations equal to or slightly less than the maximum.
I
The majority of low to medium rise precast concrete structures have
periods less than 0.3 secondsf2*10). This places them to the left and near the magnitude I
of maximum acceleration. If stiffness degradation occurs, the period of the structure
will increase but the accelerations will also increase. ‘Ihis is unlike structures with I
I
periods greater than 0.5 seconds where an increase in the structural period will decrease
the induced acceleration.
I
2.3.1.4 Damping
Figs. 2-4 and 2-5 show that damping has a major influence in determining
I
the structural response of a system. Reference 2.11 defines damping as “a measure of
the ability of a member or a structure to absorb the energy generated by the application
I
of an external repetitive type loading. ‘Ihis energy absorption reduces the oscillations
resulting from the loading and is expressed as a percentage of critical damping, which is
the minimum viscous damping that will allow a displaced system to return to its initial
position without oscillation”.
The exact value of damping for most structures cannot be determined since I
I
many structural and non-structural effects contribute to damping. Friction between
members, cracking of walls, yielding of members and connections, and soil conditions all
I
contribute to damping in the structure. Damping will also vary with the structural form
and the nature of vibration. Large amplitude post elastic vibration is more heavily
damped than small amplitude vibration (2.12) .
Damping values used for design are obtained through extrapolation of test
data for individual components and structures. Typical design values for various con-
I
struction types are given in Table 2-1f2.12). Generally, buildings with heavy shearwalls,
heavy cladding, or partitions, have greater damping values than lightly clad skeletal I
I
structures<2*12).
The high damping values given for concrete construction may not apply to
I
prestressed concrete since these values are dependent on the member behavior and the
connections between the members. Generally, the high damping values associated with
I
concrete are a result of tensile cracking in the member. For prestressed members,
cracking will not occur at working stress level, therefore the initial internal damping will
be lower than that produced by a reinforced concrete member. This can be seen from
the test results given in Table 2-2(2*27). Damping will increase as the member cracks,
but the connections between members must still withstand the structural deformations I
I
associated with the initial low damping values.
2.10
I
I
I ‘lhble 2-l Typical Damping Ratios
I
Steel frame, with concrete shear walls 7
I
I
I
Type of Member Damping
(percent of critical)
I
0.5 to .75
concrete
beam With tension cracks not
visible to naked eye 1.0 to 2.00
I Reinforced
concrete
Without tension cracks 1.0
I
beams With first tension crack 2.0
I by Newmark(2’3).
1. For low frequency systems, the total displacement for the inelastic
I
system is the same as for an elastic system having the same frequency.
I 2.11
I
I
I
I
I
I
I
I
I
Fig. 2-7 - Deformation spectra for elaeto-pleetic systems with 2%
eciticel damping subjected to IQ Centro Earthquake (Ref. 2.3)
I
source for the seismic design requirements of the Uniform Building Code, the most
commonly used code for earthquake design. It is not surprising that the SEAOC is a
major contributor to seismic design codes, since the majority of seismic activity and
earthquake resistant design in the U. S. is centered in California. The codes and prac-
I
I
2.12
I
I tices in California are highly regarded in the area of earthquake resistance design.
TherefOre, a brief review of early California design codes and the developments of these
I
life and damage occurred in San Francisco in 1906. Statistics regarding the earthquake
are questionable, but it is believed that 700 to 800 people died and over 400 million
I
dollars in damage occurred from the earthquake and the fires after the
earthquaket2*14). Surprisingly, the earthquake and the damage which ensued did not
produce any changes in the building codes. The city was rebuilt to a design code that
I and about 6 million dollars in structural damage (2.14) , structural engineers in California
began to give serious thought to earthquake resistant design. Research was started in
I
the United States and design procedures began to appear in engineering journals. How-
ever, there were still no mandatory earthquake design requirements in any building
I
codes. It was not until the Long Beach, California earthquake in 1933 that earthquake
design requirements appeared in building codes in the United States(2’g)
The first building code provisions in the U. S. regarding earthquake resistant
I design were similar to the provisions of Japanese codes which had been in existence for
almost ten years. The first codes specified a single seismic coefficient with the earth-
I
quake forces calculated by the following formula:
F=CW (2-J)
I
Where F is the earthquake force, C is the seismic coefficient and W is the total dead load
of the structure plus one half of the design vertical live load.
I
In the 1933 codes, C was a constant equal to 0.08 for ordinary buildings and
0.10 for school buildings. Factors such as construction type, building height, or structur-
al shape, did not affect the value of C. However, certain individual parts of buildings
I such as parapet walls, chimneys, tanks, and exterior ornamentation were designed for
higher earthquake forces since experience had shown these items to be susceptible to
I
count for the fact that the period of vibration for a building will increase with the num-
ber of stories, and smaller accelerations are obtained with large periods of vibration.
I 2.13
I
I
This can be seen from the acceleration spectra in Fig. 2-5. The new value of C was given
I
as:
I
60
’ = IN + 4.51100 (2-5)
I
where N is the number of stories above the one under consideration.
The value of C was revised again in 1957 after the City of Los Angeles re-
moved the 13 story height limitation which had been imposed on previous building con-
I
struction. The new equation for C was:
I
c = w+ 0.9”;?- S)J 100 (2-6)
where S is the total number of stories in the building. For buildings less than 13 stories,
I
the value of S was taken as 13 and the value of C remained unchanged from the previous
code value.
I
I
The new equation for C produced design forces which gave a better approxi-
mation to the forces determined by a dynamic analysis for buildings greater than 13
I
stories. It also was the first equation to approximate the triangular load distribution
predicted by dynamic analysts.
The first seismic committee of the Structural Engineers Association of Cali-
fornia was formed in 1957. The intent of the committee was to develop a seismic code
which would be in close agreement with the essential features of dynamic theory, and to
I
develop a uniform code which could replace the many different codes that existed at the
timet2sg) . I
I
The code developed by SEAOC was the first to incorporate the concept of
ductility into the design process. It was also the first to impose different requirements
I
for different construction types.
The base shear derived by the committee was given by the formula:
V=KCW (2-7)
I
In which V is the base shear, K is a ductility factor, W is the total weight of the building
above the first floor and C is the base shear coefficient defined by the equation: I
(2-E) I
I
2.14
I
I
I In this equation, T is the fundamental period of vibraton of the building. The committee
realized the calculation of the period of vibration for a building was complicated and
I time consuming. Therefore, they developed the following simple formula for calculating
T:
I T = 0.05H
6
(2-9)
I Here H is the height of the building in feet and D is the dimension of the building, in
feet, in the direction parallel to the applied forces. The code stipulated that T need not
I average values obtained by measuring periods of vibration for several hundred buildings.
However, it was felt that the errors in the period of vibration would not seriously affect
I
the calculated base shear value.
The ductility factor, K, accounted for the difference in resistance to seismic
I
loads for different types of construction. The values of K were based on the opinions of
the committee members and on the performance of each system in previous
earthquakes. Types of construction which had performed well in earthquakes were
I assigned low K values, while structures with poor performance records were given high K
values. The four K values given by the committee are listed below (2.9) .
I
K= 1.33 was established for the Wax Type” building structures which do not have
a complete space frame capable of resisting all vertical loads. Vertical and
I
lateral loads are carried by bearing walls and shear walls.
K= 1.00 was established for a building having a complete “vertical load space
frame” designed to carry all vertical loads. Shear walls or other bracing
I K=
systems are designed to resist the total lateral force.
0.80 was established for buildings with a complete horizontal bracing system
I capable of resisting all lateral forces, plus a ductile moment resisting space
frame which independently is capable of resisting a minimum of 25 percent of
I
the lateral force.
K= 0.67 was established for buildings in which the total lateral force is resisted
I
by a moment resisting frame which has the necessary ductility.
The code also developed the following formula for determining the shear
I
force at each story level:
(2-10)
I
I 2.15
I
where:
F, = lateral force at level x. I
v zz base shear
WX
= weight at level x I
hx = height in feet above the base to level x
cwtl = summation of the products of all wx h,‘s for the building I
For determining overturning moments the committee recommended the
forces at each floor level be reduced by a factor J. This accounted for the reduced base
moments produced during high modes of vibration when the floor shear forces are not
I
acting in the same direction. The factor was later dropped when damage from the 1967
Caracus, Venezuela earthquake showed results obtained with a J factor were unconserva- I
I
tive.
The code developed by the 1957 SEAOC committee was first published in
I
1959. Since that time the code has been changed to account for lessons learned in later
earthquakes. However, the major principles and the general approach to earthquake
I
design developed by the committee is basically the same in the current codes.
2.3.2.2 Present Code Requirements
I
The earthquake provisions of the 1979 Uniform Building Code represent the
current equivalent static design requirements. The base shear formula given by the UBC
I
has been revised to the following formula:
V = ZIKCSW (2-11)
I
The term I is an occupancy importance factor which establishes higher seis-
mic forces for structures essential to public safety during and after an earthquake.
Essential facilities have an I value of 1.5 and include hospitals, medical buildings with
surgical facilities or emergency treatment areas, fire and police stations, disaster oper-
ation facilities and communication stations. Any building with a primary occupancy of
I
I
more than 300 people in one room has an I value of 1.25, while other buildings have an I
value of 1.0.
I
K, the ductility coefficient, is basically the same as the values defined by the
2.16
I
I
I
I
I
I
I-
I
I
I
I
w. or n * L c
pis. 2-8 - Seismic zone map of the United States (Ref. 2.15)
I
The value of C is currently given by the formula:
I
c = & so.12 (2-12)
For buildings with a ductile moment-resisting space frame capable of resisting 100 per-
I cent of the lateral load, and without being enclosed or adjoined by more rigid elements
tending to prevent the frame from resisting lateral forces, the period can be found by the
I
formula:
T = O.lON (2-13)
I
Other buildings may use the formula given by the original committee:
o.05Hn
T=- (2-14)
I
6
1~ 2.17
I
For T/Ts = 1.0 or less: I
(2-15) I
For T/Ts greater than 1.0: I
S = 2.3 + 0.6 6 -0.3 & 2
S [IS I
If Ts, the characteristic site period, cannot be properly established, the value of S should
be taken as 1.5. The code also specifies S should always be greater than 1.0, and the I
I
product CS need not exceed 0.14.
The UBC also gives the following formula to determine the forces on parts or
I
portions of structures, non-structural components and their anchorage to the main struc-
tural system:
Fp = ZICpWp (2-17)
I
Fp is the force on the component, Wp is the weight of the component and Cp
is defined in Table 23-J of the UBC. For most precast concrete components and their I
I
connections, Cp = 0.3.
The body of a precast connection for non-bearing non-shear wall panels is
I
required to resist 4/3 Fp. Fasteners attaching the COMEXtOr to the panel or the StrUC-
ture such as bolts, inserts, welds, or dowels are required to resist 4Fp.
Connections and panel joints should also allow for a relative movement be-
tween stories of the greater of l/2 inch, two times the story drift caused by wind,
Or (y) times the calculated story displacement caused by seismic forces.
I
Braced frames in buildings located in Seismic Zones No. 3 and No. 4 and
buildings located in Seismic Zone No. 2 with an importance factor, I, greater than 1.0, I
I
are required to design their members and connections for 1.25 times the calculated
earthquake force.
I
2.3.2.3 Future Code Provisions
In 1878 the Applied Technology Council, in cooperation with the National
I
Bureau of Standards and the National Science Foundation published a comprehensive
report on the current state of knowledge in the fields of engineering seismology and
I
seismic design for construction of buildings. The report, commonly called ATC-3(2’16),
2.18
I
I
I was developed for the improvement of current building practices. ATC-3 has not been
formally adopted and present debate over some of the provisions will probably produce
I revisions in the report. However, if the majority of the existing report is adopted into
the major building codes, earthquake design requirements will change for a large portion
I of the country.
Many of the changes which ATC-3 will produce stem from the revision of the
I different seismic zones throughout the country. Seven zones are listed in ATC-3 instead
of the four found in UBC, and many areas are placed in new zones which have more
I stringent earthquake requirements than the present UBC requirements. This is especially
true for many midwestern and eastern areas where earthquake requirements currently
I
have an insignificant effect on the structural design. However, under ATC-3, earthquake
resistance would be a major factor in design, significantly affecting cost, material selec-
I
tion and construction methods(2’17).
.
Since the provisions of ATC-3 are still tentative, a detailed discussion of the
report will not be given. Relevant provisions concerning connection design will be dis-
I cussed in later sections. The significant factor is that the present UBC earthquake
provisions may be revised to incorporate higher design forces along with stricter ductility
I The major building codes consider the following criteria as a basis for struc-
tural performance:
I
3) Resist major catastrophic earthquakes without collapse. Essential
facilities are also expected to remain operational during and after a
major earthquake.
I The previous sections have shown that once the physical parameters of a
structure are known, approximate earthquake forces can be generated through a dynamic
I analysis or simplified code equations. The equivalent static forces prescribed in the
major building codes were developed with the assumption that inelastic structural re-
I
sponse will occur during a major earthquake. Structures which are designed for elastic
behavior with these static loads will be overstressed during a major earthquake. Suffi-
cient ductility is required to accommodate the deformations associated with inelastic
I
I 2.19
I
behavior without jeopardizing the integrity or stability of the structural system. Using a
I
dynamic analysis, the engineer has the option of assuming elastic or inelastic structual
behavior. For elastic behavior, the design forces approximate the maximum I
anticipated. Little damage will occur if strength degradation is prevented and structural
deformations are controlled. If the structure responds inelastically, lower design forces I
I
are used, resulting in smaller members, less weight and a more economical structure.
The energy principles discussed in the next section will describe ductility
requirements and inelastic behavior of simple structural systems.
2.4.1 Energy Principles I
I
The easiest way to Illustrate non-linear behavior in a structure ls through the
oscillations of a simple cantilever as shown in Fig. 2-9. Such an oscillator, responding
elastically, will have a load deflection relationship as shown in Fig. 2-9a.
The potential energy stored in the elastic system at the maximum deflection
point b, is equal to the area a-b-c under the curve. As the mass returns to its initial
I
position, the potential energy is converted into kinetic energy.
If the stress in the oscillator exceeds the yield strength of the material, a I
I
plastic hinge forms and the inelastic load-deflection will be as shown in Fig. 2-9b. At the
maximum response of this system, point e, the potential energy stored in the system Is
I
equal to the area a-d-e-f. When the mass returns to the zero position the area a-d-e-g
represents the energy dissipated by the plastic hinge. ‘lhe area e-f-g is the potential
energy converted into kinetic energy(2.18).
The energy dissipation capacity of the plastic hinge, or of any structural
component, dictates how the structure will respond to seismic ground motion. If the
I
energy dissipation is large, the vibrational amplitudes of the structural response will be
small. Conversely, if the energy dissipation is small, the vibrational amplitudes will I
I
increase as the absorbed energy is converted into kinetic or velocity energy (2.19) .
The load-deflection curve shown in Fig. 2-9b is called an elastoplastic re-
I
sponse, and is characterized by the flat plateau at the yield point (d-e). Generally,
structures wiIl not behave in a perfect elastoplastic manner. The exact behavior is
difficult to predict for structures, but it can be determined by tests for individual mem-
bers. Fig. 2-10 shows other common inelastic behavior patterns.
2.4.2 Displacement Ductility and Load Reduction Factors
I
Two methods are commonly used to equate the responses of elastic and I
I
elastoplastic systems. One method assumes equal maximum deformation, while the other
I
2.20
I
I
I
I
I
I
I
I
I (b)
I
Fig. 2-9 - I&spans of oecillntiorc3 to earthqueke motion
(a) Elastic responw. (b) Elestoplastic response. (Ref. 2.18)
I
I
1
I
I Py -- ------- 4’
1 Lc i
I i
I
4 Am.%
Fig. 2-10 - IdeaBed load deflection curves for common types of inelesticity
I
1
2.21
I
I
I
I
I
I
(a) (b)
Fig. 2-ll- Assumed responses of elastic and elastoplastic structures
(a) Equal maximum deflection response. (b) Equal maximum potential energy response.
method assumes equal maximum potential energy. Fig. 2-11 shows the responses for both
I
methods.
For both methods the ductility of the structure is measured by the displace-
I
I
ment ductility factor, u , defined as:
AU
I
v =*- (2-18)
Y
I
A, is the deformation at the end of the post elastic range, while A is the lateral
Y
deformation when yield is first reached.
The ratio of maximum inertia loads for the elastic to elastoplastic structures
is the load reduction factor R. For the assumption of equal maximum deformations, R is
defined as:
I
R=L
!J
(2-19) I
The SEAOC committee used this load reduction factor in determining appropriate code I
I
forces. They also indicated that typical values of u range from 3 to 5. As a result the
forces predicted by an elastic dynamic analysis will be 3 to 5 times larger than those
given by the code formula. Figure 2-12, shows this in graphical form (2.11) . ln theory, to
justify the lower design forces the structure must be capable of deflecting 3 to 5 times
the elastic deflection obtained with the code forces. I
I
Dynamic analyses conducted by Clough(2*20) have indicated the equal max-
imum deflection assumption is unconservative for degrading stiffness systems, such as
I
reinforced concrete. Fig. 2-13 developed by Clough suggests that for degrading systems
2.22
I
I
I
I
I
I
I
I
I
I I I / I
0 1.0 2.0 3.0 1.0 6.0
Pl)rl0d.T,**5
I
Fig. 2-12 - Comparison of equivalent static force method
to dynamic analyses procedures
the load factor defined by the equal potential energy assumption gives an upper bound to
I the system response. The load factor is obtained by making the area OCD, in Fig. Z-llb,
equal to the area OEFG. When these areas are equal the potential energy of each system
I
is equal and the load reduction factor becomes.
I
I
I
I
I
I Fig. 2-13 - Displacement ductility versus ratio of strength to elastic
demand for single degree of freedom oscillators responding to the 1940
I
El Centro N-S earthquake. (Ref. 2.18)
I
2.23
I
A comparison of lJ values obtained from the two methods is shown below for I
a range of R values.
I
lbble 2-3 Comparison of ductility factor, p
I
The comparison shows that for low strength levels the e&to-plastic system
will suffer larger displacements if it is to absorb the same energy as the elastic system.
It also shows that the difference between P values increases as the value of R
decreases. Thus for low values of R an exceptionally large amount of ductility may be
required. Although monolithically cast structures may be able to provide such ductility,
I
the capability of precast systems has yet to be established. Therefore, it may be appro-
priate to use conservative estimates of R and P in the design of precast structures. I
I
The ductility factors given in Table 2-3 illustrate how ductility requirements
vary with stiffness characteristics and the assumed elastic design loads. Generally in the
I
design of a structure, ductility requirements are implicitly satisfied by other provisions
such as reinforcement ratios and defIection limitations. Whether theses provisions are
adequate to satisfy the ductility demands of a given system is beyond the scope of this
report.
Until more specific provisions are developed, precast design should strive to
I
meet the ductility provisions of reinforced concrete. If the intent of these provisions
cannot be met, or if in the judgment of the designer a precast system has less ductility I
I
than a similar monolithic structure, a larger elastic design force may be appropriate for
the precast system.
I
2.4.3 Curvature Ductility
In obtaining structural ductility, separate ductility requirements are imposed
I
on the individual structural members. Since flexural deformations are dominant in most
members, member ductility is most commonly represented by a curvature ductility
I
factor, +u/$y , where @,, is the member curvature at the end of the post-elastic range
2.24
I
I
I and @y is the member curvature at first yield. ‘lhe magnitude of curvature ductility
required for a given member will vary with the structural shape, the location of the
I member, the plastic hinge length (i.e. the length over which inelastic behavior occurs)
and the yield mechanism of the structure.
I Shear and axial ductility factors can also be established, but inelastic behav-
ior is seldom justified for these deformational modes and elastic behavior is usually
I required throughout the total structural response.
For a frame structure, ductility can be obtained through inelastic column
I behavior, Fig. 2-14(a) or inelastic beam behavior, Fig. 2-14(b). Park and Paulay(2’18)
analyzed the frames of Fig. 2-14 and determined curvature ductility requirements for the
two mechanisms shown. ‘Iheir results indicated that for a ten story building with a
I displacement ductility factor of 4, the required curvature ductility factor with the
column sidesway mechanism was 122. For the beam sidesway mechanism the required
I curvature ductility was only 18.
This drastic difference, along with the impossibility of obtaining a curvature
I ductility of 122, illustrates why it is more desirable to form plastic hinges in the beams
and allow the columns to behave elastically. The beam-sidesway mechanism also results
I in a more stable structure with lower P-A moments and less permanent lateral deforma-
tion.
Fig. 2-15, developed by Parme(2.10) , also illustrates the effect of curvature
I ductility on inelastic structural response. Fig. 2-15(a) shows that formation of a hinge at
the first floor girder reduces the induced shear into the structure. Further reduction of
I the shear force requires formation of additional hinges and additional curvature ductility
from the first floor girder.
I
I ’/ Fi
I 0pc
w QPC
I
I E!a I
(a) (b)
Fig. 2-15 - helastic response of U-story building I
Fig. 2-15(b) shows how the ductility of the first floor girder wiI1 effect
required moment capacity of the base column. The figure shows if the beam behaves
the
I
elastically, +tI,/$ = 1 , the required moment capacity at the base would be four times
the elastic code value. However, if a curvature ductility of 14 is obtained, the capacity I
of the column need only be slightly greater than the code value.
These two examples of frame behavior illustrate the fact that there is a I
difference between structural displacement ductility and member curvature ductility. In
general, the curvature
resisting frames will
ductility
be from
demand for girders and connections of ductile
three to five times the required
moment-
displacement
I
ductililty(2’10).
For shear wall structures, ductility occurs with the formation of a plastic
I
hinge at the base of the shearwall,
curvature ductility ou/oy
as shown in Fig. 2-16.
, and displacement ductility
The relationship
Au/Ay , can theoretically
between
be I
calculated from the ratiofp/% (2.18). For example, for the structure in Fig. 2-16 the
following curvature ductility factors are required for a displacement ductility factor of I
four.
L,la
a$+,
0.05
20.5
0.1
10.5
0.15
7.2
0.20
5.6
0.25
4.6
0.30
3.9
0.35
3.5
I
For monolithic shearwalls I,, Is typically in the range of 0.5 to 1.0 times the
I
r
member depth.
connection
However, for low rise precast shear walls it ls not uncommon to have a
which does not develop the full flexural strength of the shear wall. If inelas- I
tic behavior is limited to the connection, the plastic hinge length is limited to the con-
I
2.26
I
I
I
I
I
I
Fig. 2-16 - Cantilever shear wall with lateral loading at ultimate moment
I nection length and considerably less than 0.5 times the wall depth.
Most precast concrete members, especially when they are prestressed, are
I factory-made products. Their economy stems from repetitive use of similar shapes and
construction details. A large project which can achieve repetition within itself may
I economically employ special products and details, but the vast majority
not fit this category. Thus, the designer of precast, prestressed concrete structures must
of buildings do
I learn to live within a discipline established by the manufacturing process. This concept,
as related to connections, is discussed in Sections 3.1.6 and 3.1.7.
I
I 2.27
I
3. Braced frames
I
4. Floor and roof diaphragms
The function and performance of precast concrete lateral load resisting I
systems are largely dependent on the type of connection used. The illustrations in this
section show different types of connections which are designated schematically as shown
in Table 2-4.
I
Table 2-4 Schematic Connection Symbols
I
iymbol
A
Connection Type
Fixed connection. Stresses in the components remain in the elastic I
range throughout the earthquake. No significant movement occurs.
0 Ductile connection. Will yield or otherwise behave inelastically at high I
force levels, allowing energy dissipation.
0 Pinned connection. Allows relative movement when subjected to latera: I
loads.
I be considered since a large number of load reversals will occur with the low periods
associated with short shear walls.
As the ratio of height to length increases, the deformation characteristics of
I the shear wall change from a deep beam to a cantilever beam. This reduces the influ-
ence of shear deformation and increases the contribution of flexural deformation. ln-
I elastic deformation is then obtainable through yielding of the flexural reinforcement and
plastic hinge formation as described in Sec. 2.4.3.
I gories:
Precast concrete shear wall systems can be divided into the following cate-
I 1.
2.
Single panel - isolated
Single panel - coupled
3. Stacked panel - isolated
I
I 2.29
I
4. Stacked panel - coupled
I
The type of joinery between the vertical and horizontal boundaries of the
individual wall elements will determine the type of system, and whether the elements I
should be designed as individual units standing; alone (isolated), or as part of a larger
shear element (coupled). These concepts are illustrated schematically in Figs. 2-17 I
through 2-22.
Connections are required to:
1. Transfer shear from the floor and roof diaphragms to the walls.
I
2.
3.
Transfer shear from the walls to the foundations.
In stacked panel systems, transfer horizontal shear between panels.
I
4. In coupled systems, transfer vertical shear between panels.
5. Transfer tension caused by overturning forces. I
2.5.1.1 Single panel systems (Figs. 2-17 and 2-18)
I
Here, there are no horizontal joints between precast panels. Lateral shears
are carried directly from the floor and roof diaphragms through the wall to the support-
ing foundation.
I
This type of wall is frequently used in single-story industrial buildings and low
to medium rise commercial and residential structures, most often as exterior walls. I
Panels are cast in long-line forms and are usually prestressed. They may be either
stemmed units, such as double tees, or flat panels and are often insulated as sandwich I
panels. The height of the panel is only limited by the transporting and handling consider-
ations. I
2.5.1.1.1 Single Panel-Isolated
When single panels are isolated, as shown in Fig. 2-17, there is no connection I
between units. The stiffness of the wall system is equal to the sum of the stiffnesses of
the individual panels and the lateral load distributed to each individual wall is propor- I
tional to its shear and flexural stiffness.
The base connection of an isolated shear wall panel can be designed for
elastic or inelastic behavior. If the connection is to behave elastically one of two condi-
I
tions must be satisfied. Either the connection must be designed for the maximum earth-
quake loads, which may be four or five times the equivalent static load, or the capacity
I
of the connection must be greater than the capacity of the wall. The latter case assumes
formation of a plastic hinge in the wall thereby limiting the loads induced into the con- I
nection. The performance of the system is then dependent on the ductility and energy
I
2.30
I
I
I
I Root --- I
I Floor
El
---
I n
I Floor ---
I Floor
1
--- ---
I
I Fig. 2-17 - Jsolated single panel shear wall system
I
I
I
I
I
I
---- --- ---
<~t,~L/L~=Az-~~ -- I
I
Fixed Coupling Ductile Coupling
I
Fig. 2-18 - Coupled shgle panel shear wall system
I 2.31
I
I
Illfill Ppr:3!,_lnfill
l--twall width wall
1 I
I
I
I
I
I
I
Fig. 2-19 - Jsolated stacked panel shear wall system I
I
I
I
I
I
I
I
W- 2-20 - Coupled stacked panel shear wall system 1. Fixed couplings.
I
I
2.32
I
I
I
I
I
I
I
I Fixed coupling
I pig. a-21- Coupled stacked panel shear wall system. Jntermittent ductile couplings.
I Panel length
I -
I Z=
rii
0”s
I
I
I
I
I.
. . * 4.
I rnt
II -
I
Fig. 2-22 - Coupled stacked panel shear wall system. Duetile coupli~.
I
I 2.33
I
absorption of the wall instead of the connection. I
If the connection can develop sufficient inelastic behavior, lower elastic
deskn forces, such as those predicted by an equivalent static method, may be used for I
Proportioning the connection components. The inelastic behavior of the connection
should ahow rotational ductility to develop at the base of the wall before a brittle shear
or concrete failure occurs in the wall or connection.
I
For example, consider the single story shear wall and base connection shown
in Fig. Z-23. The connection forces, C and T, are determined by the wall dimensions, the
I
lateral load, V, and the axial load, P. During an earthquake the magnitude of V will
increase until the maximum acceleration is reached, or until yielding occurs in the wall I
or connection.
For the connection shown in Fig. 2-23(a), the preferable inelastic behavior I
will occur with the yielding of the reinforcing bar. This will produce the longest plastic
hinge length and the greatest rotational ductility at the base of the wall. Yielding of the
connecting plate can also produce rotational ductility, but the short length of the plate
I
reduces the plastic hinge length and increases the ductility demand as described in
Sec. 2.4.3. Yielding of the embedded studs (Fig. 2-23(b)) is dependent on the brittle
I
fusion weld attaching the stud to the plate and therefore is not recommended.
If the reinforcing bar is to provide the ductility of the connection it should be I
the first component to yield. At yield the magnitude of the lateral force, V, will remain
constant until strain hardening initiates in the rebar as shown in Fig. Z-24. For grade 60
steel, strain hardening will allow the force in the bar to double the yield force. Conse-
I
quently, the maximum value of V may be twice the value which initiates yield in the
bar. If all the components of the connection, except the reinforcing bar, are designed
I
I
I
I
I
t i Ial lb) I
Fig. 2-23 - kolated shear wall and base connection
I
2.34
I
I
I
I
I
I
I 0
0 0.04 0.08 0.12 0.10
0.200
J
S,,d"
I elastically for two times the lateral force which initiates yield, the bar and connection
will obtain maximum ductility.
Diagonal steel bracing is often employed in structural steel frames for reduc-
2.37
I
I
I
I
I
Fig. 2-26 - Examples of combined precast beam/column mtion.q
I
Used in ductile moment+esktii frames.
ing lateral forces caused by wind or earthquake. Three types of framing bracing are I
shown in Fig. 2-27.
The K-brace and the X-brace systems are the two most familiar systems
which have been investigated and tested for earthquake loading. Both systems initially
I
offer considerable strength and stiffness, but inelastic lengthening and cyclic bucking
usually reduces the strength and stiffness of the bracing members. Thus for proper
I
inelastic cyclic analysis of braced frames, an accurate hysteretic model for individual
braces must be available(2’68). I
The eccentric brace system, shown in Fig. 2-27(c), is a relatively new system
which has shown promise in steel construction. The system is unique in that it has the I
strength and stiffness of a braced frame with the inelastic behavior and energy dissipa-
tion of a moment-resisting frame (2.30).
The only research available on eccentric bracing involves the behavior of a
I
steel system. The inelastic action observed in the frame was obtained through shear
I
I
I
I
a) x-erase b) K-Brace c) Eccentric
smc* I
Fig. 2-27 - Cross bracing used with steel frames
I
2.38
I
I
I yielding in the web of the “link beam” between the column and the brace. This type of
yielding cannot happen in precast concrete members, so additional analytical and labora-
I tory research would be required if such a system is to be used with precast concrete
frames.
I Little if any construction has been done using braced precast concrete frames
for earthquake-resistant structures. However, braced systems have been utilized to
I resist wind loads(2’31), usually with steel sections used for the bracing members.
The advantages of braced frames include:
I 1. Standard rectilinear sections can be used for the precast beams and
columns.
2. Economical “pinned” connections, which erect rapidly can be used at the
I beam column interface.
3. Volume change restraint forces are reduced.
I 4. Erection is not slowed by time-consuming moment connections or cast-
in-place infill shear walls.
I The UBC recognizes braced concrete frames and requires the connections of
the system to be designed for the capacity of the member or 1.25 times the equivalent
I static force.
For braced steel frames over two stories in height ATC-3 requires the mem-
bers to have a compressive strength equal to at least 50 percent of the required tensile
I strength. ‘This is due to the poor earthquake performance of braced frames which con-
tained only tension members. Compliance with this provision would be proper for con-
I crete frames utilizing steel bracing members.
2.5.4 Floor and Roof Diaphragms
I The diaphragm floor and roof systems of precast structures are composed of
carrying girders, beams, deck elements and often a cast-in-place concrete topping slab.
I These are designed initially to accommodate the vertical load requirements. ‘lhe con-
nection details are designed to transfer the vertical loads between the various elements
I and to account for the member induced effects of shrinkage, creep and temperature
variation.
I
I
I (a) Simple beam action, lateral suppoh at ends
I
I
I Y = .F, = d/? tF,l
R3=R,=dF./2h
I T=C=(M-wd,2/2)
h
I
0 Cantllever beam action, lateral suppwts at thref2 sides
I
I
I
I
I
I
I
I
I
topping must transfer these generated forces through mechanical con-
I
nections or continuous pour strips. Mechanical connections cause stress
concentrations which may result in local failure under the possible peak I
load conditions. This may be avoided by reducing the allowable stresses
used for design of the connections and to thus increase the elastic
capacity. Continuous pour strip connections result in a more uniform
I
6.
stress distribution, but are much more costly.
Interior bearing walls and slab openings tend to disrupt diaphragm
I
7.
continuity. Additional reinforcement may be required in these areas.
Earthquake loads may be induced into a diaphragm from any direction.
I
The diaphragm and its connections should be designed for the most
critical loading direction. For convenience ATC-3 requires 100 percent I
of the forces for one principal axis plus 30 percent of the forces for the
perpendicular axis. This combination is considered for both principal I
directions and the combination requiring the maximum component
strength is used. I
2.6 Dynamic Characteristics of Precast Connections
Part 3 of this report discusses various design principles and behavior char- I
acteristics for precast connections subjected to monotonic loading. During an earth-
quake, connections are subjected to monotonic gravity loads plus time-varying cyclic
lateral loads. The behavior of a connection during cyclic loading can be different than
I
for static loading and as the previous sections have shown, the behavior of the connec-
tions will influence the structural reponse and the loads induced into the structure.
I
Properties such as initial rigidity, ductility, inelastic deformation, strength and stiffness
degradation as well as the loading influence connection behavior and structural response
I
to earthquake loads.
This section describes some of the characteristics associated with typical I
precast connections. The limited dynamic experimental data which is available is pre-
sented and areas in need of future research are noted. Although design of precast con- I
nections for seismic loading is based on monotonic elastic behavior, knowledge of the
cyclic behavior of a connection is essential for preventing unwanted brittle failures and
for accurately predicting the seismic response of the precast system.
I
2.6.1 -Shear Connections I
Shear connections are classified as either “wet” or “dry”. Wet connections
I
2.42
I
I
I
I a) my Conn*cthm b) Wet Connection
I wet connections include the precast and cast-in-place concrete,the amount of transverse
and longitudinal steel, the tensile or compressive forces acting on the connection and the
surface preparation of the precast panels. Fig. 2-30 shows some of the typical edges
I presently used in precast construction.
Shear transfer in wet connections can occur through cohesion or bond, fric-
I tion, dowel action and direct bearing. However, the construction process, along with
creep and shrinkage effects, will often destroy the bond between precast and cast-in-
I place concrete thereby eliminating that transfer mechanism(2.32) .
Shear transfer through friction can only occur with a clamping force acting
I normal to the connection face. The clamping force can be supplied through external
compressive forces, post-tensioning, or transverse mild steeL When transverse mild steel
is used the shear friction principles discussed in Sec. 3.3.2.3 are used to determine the
I magnitude of shear transfer.
“Effective” shear-friction, as discussed in Sec. 3.3.2.3 was developed from the
I results of monotonic tests. During cyclic loading, tests have indicated that these princi-
ples may be unconservative and that a reduction in shear transfer will occur during
I successive load cycles. Mattock obtained this result in his cyclic shear transfer testing
I
I
I
Fig. 2-30 - Typii panel Bage prepsration
I
I 2.43
I
I
I
I
I
I
I
(a) cycles l-5 b) cycks 25-30
Fig. 2-31 - sheer-slip from Univ. of Washington teats (Ref. 2.33) I
at the University of Washington. Hawkins in his state-of-the-art report (2.33), provides a I
summary of Mattock’s work.
A typical load-deformation curve for one of Mattock’s test specimens is
shown in Fig. 2-31. Fig. 2-31(a) shows the reponse for the first five cycles at a load of
I
0.5 V”. During this loading the specimen was stable with little loss of stiffness or
strength occurring. However, as the load and number of cycles increased, the stiffness
I
and strength of the connection degraded. This is evident by the increase in slip between
cycles 25 and 30, Fig. 2-31(b). I
In comparing the cyclic results against monotonic load results, Mattock
observed a reduction in strength of about 20% in the cyclic tests for initial crack widths I
of 0.015 in. or less. The reduction increased with increasing initial crack width and was
more for lightweight concrete than for sand and gravel concrete (2.33).
The energy dissipation capacity of the connection, represented by the area
I
under the shear-slip curve, also degraded with cycling and increasing load. Tests on
shear wall structures(2*34) have indicated that under axial loads the hysteresis loops
I
become fuller, but in general shear transfer should not be relied on to dissipate much
energy. I
Development of transverse steel beyond both sides of the failure plane is
essential for wet connections. For some precast connections, such as the hollow-core I
connection shown in Fig. 2-32(a), this development is easily obtained.
I
2.44
I
I
I
I
I (b) (C)
I Fig.2-3%-slabtoslabcoMections
I seismic regions since the lap length is insufficient for most joint widths. Welding, me-
chanical connectors, or longitudinal steel through hooped bars, Fig. 2-32(c) are possible
I solutions.
2.6.1.2 Dry Connections
I The most common type of dry shear connectors are composed of embedded
steel shapes anchored into the precast members by studs or reinforcing bars. The con-
I Many tests have been conducted on the ultimate strength Of dry COMedOnS
under static or monotonic loading, but few tests have been conducted under cyclic or
alternating loads. Spencer and Neille(2’35) are two of the few who have conducted and
I reported on cyclic tests. Their work at the University of British Columbia involved the
cyclic testing of the six specimens shown in Fig. 2-34.
I Five of the test specimens were subjected to cyclic loading at frequencies in
I
I (b) (Cl
Fig.2-33-Dtysbefueonnecto~
I
I 2.45
I
CONNECTIOh I
DETAILS
PANEL
OF STUDS 8
REINFORCEMENT I
I
Al
I
A2.A3
I
I
81
I
B2
I
83 I
I
pig. 2-34 - Details of test connectiom
the range of 0.01 to 0.02 cycles per second. Connection Al was loaded monotonically to I
failure. The load was applied ‘l/8 inch from the face of the angle. This produced tensile
and compressive forces in the studs equal to 10 and 15 percent of the shear force for 12 I
and 10 inch long connection angles, respectively.
Test results for connections Al and A3 are shown in Fig. 2-35. Fig. 2-35(a)
shows that connection Al exhibited considerable ductility under monotonic load. The
I
yield strength of the connection was greater than the design strength of 27.2 kips, pre-
dicted by the PC1 Design Handbook(2.36) .
I
The cyclic test results for connection A3, depicted in Fig. 2-35(b), illustrates
the change in behavior between monotonic and cyclic loading of the same connection. I
The connection was loaded to yield after several initial cycles in the elastic range, and
then subjected to steadily increasing deflections. The results again show a decrease in I
stiffness and strength with cycling.
8pencer and Neille reported that failure of the connections were preceded by
progressive crushing and spalling of the concrete above and below the angle. They also
I
observed progressive tension cracking parallel to, but several inches away from the
angle. Connections Al and Bl failed when a large block of concrete surrounding the
I
I
2.46
I
I
I
I
I
I
I +I / “El0ENYELOFcy
1L30
Load-deflection curve bnnection Al) for
I monotonic load* to failure (b) Load-deflection loops (connection A3)
Fig. 2-35 - Load deflection curves for connections shown in Pi. 2-34 (Ref. 2.35)
I studs broke away. The other connections failed when one of the studs broke close to the
I fusion weld.
The following conclusions were reached by Spencer and Neille after the cyclic
I testing(2’35).
1. The PC1 procedures for calculating the ultimate design strength of
these connections under static loading give conservative results.
I 2. ‘lhe strength of the connections in the first cycles of loading up to yield
will be approximately the same as the strength in mon~otonicloading.
I 3. If cyclic loading is continued above the stability limit, the strength of
the connections will fall with an increasing number of cycles, and the
I 4.
yield strength envelope will tend to approach the stability limit.
The deflections reached before failure were from seven to twenty-four
I only gravity
to accommodate
loads. Their performance
the rotational
during an earthquake is dependent on their ability
deformations imposed by the structure. For simply
I deformation would depend on the structural shape, the lateral load resisting system, the
diaphragm stiffness and the physical properties of the frame. As a result of the lateral
I frame deformation, moments and shears are induced into the columns by P- Aeffects and
large rotations occur at the beam-column connection. The detailing of the pinned con-
nection must be able to accommodate these deformations and forces.
I Two common types of simply supported precast connections are shown in
Fig. Z-38. The connection shown in Fig. 2-38(a) has a large rotational capacity which
I could accommodate the deformations of a major earthquake with little distress.
See Part 4 for other features of these connections.)
(Note:
I In Fig. 2-38(b) an angle is added to the top of the beam for lateral support.
The connection is not designed to transmit moment, but rotation of the beam will induce
stress into the angle and the adjoining parts. Proper design of the connection requires a
I
I 2.49
I
I
I
I
I
I
(b)
I
Fig. 2-38 - Typical pinned amnections I
flexible angle at the top of the beam so that the angle will deform before large stresses
are induced into the connection. If the angle is too stiff, or welded along both sides,
large rotations which force the bottom of the beam to bear against the column could
I
produce failure in the top connection.
The consequences of local failures in pinned connections may seem minor, but
I
redistribution of load or damage to the column or beam could effect the structural
performance significantly. I
Rigid beam-column connections for ductile earthquake resistant moment
frames should conform to the following provisions: I
1. The sum of the moment strengths of columns at factored axial loads
should be greater than the sum of the moment strengths of the flexural
members along each principal plane. This results in the preferred
I
beamsidesway failure mechanism instead of the column-sidesway
mechanism as shown in Fig. Z-14.
I
The curvature ductility capacity of the connection must be sufficient to
2.
accommodate the ductility demands imposed by the inelastic structural I
response. Methods for determining the curvature ductility required of
members designed by an equivalent static method have yet to be estab- I
lished. This is a result of the complex nature of frame structures and
the many variables which influence the formation of the structural yield
mechanism. Generally, for ductile reinforced concrete frames a curva-
I
ture ductility of three times the lateral ductility is acceptable.
I
2.50
I
I
I 3. The shear capacity of the connection must be greater than the flexural
overcapacity of the beam. This ensures the formation of a plastic hinge
I and ductility in the connection before the occurrence of a shear failure.
2.6.2.1 “Dry” Beam-Column Connections
I Moment resisting connections utilizing precast members and mechanical
anchors are commonly used to resist wind or gravity loads. However their use in resist-
I ing lateral seismic loads has been limited by the lack of test data concerning cyclic
strength, stiffness and ductility. Without further testing the acceptance of these con-
I nections will be limited to areas of low seismic activity.
Pillia and Kirkt2’3g) are currently conducting a series of tests on the cyclic
I behavior of the precast connection shown in Fig. 2-39. The load history for the testing is
shown in Fig. 2-40 and the moment rotation curve for one specimen is given in Fig. 2-41.
I Failure in six out of seven test specimens occurred by fracture of the weld
connecting the bottom beam reinforcement to the angle. Inspection of these welds after
fracture showed that they were somewhat incomplete. Tnis emphasizes the importance
I of quality workmanship in welded connections and suggests that the connection can be
improved if a better transfer mechanism can be obtained between the reinforcing and the
I angle.
Failure of the precast connections oecured between the seventh and fifteenth
I cycle. Loading of one specimen was terminated in the fourteenth cycle when the capa-
city of the loading jack was reached. A similar monolithic connection was tested and
I
I
I
I
I
Fig. 2-39 - Test specimen we-d in FWia-Kirk tests (Ref. 2.39)
I
I 2.51
I
I
I
I
I
I
%- GO - Loade pattern used in Pillia-Kirk tests (Bf. 2.39) I
tests were conducted at the time the report was published. However, the initial test
results are encouraging and the performance of these specimens provides optimistic hope I
for the development of similar connections.
I 2. Lap splices should not be located (1) within beam column joints, (2)
within a distance of twice the member depth from the face of the joint,
I The Standards Association of New Zealand has drafted seismic design recom-
mendations for prestressed concrete (2.45, 2.46) which includes provisions for post-ten-
sioned beam-column joints. Park, in Reference 2.41, describes some of the code re-
I
2.53
I
I
quirements and the research which led to their development. Several provisions listed by I
Park are given below.
“22.6 Joints in Prestressed Frames I
22.6.1 - Anchorages for post-tensioned tendons shall not be placed within
beam-column joint cores.
22.6.2 - Except as provided by Section 22.6.3, the beam prestressing
I
tendons which pass through joint cores shall be placed at the face of the
columns so that at least one tendon is located at not more than 6 in. (150 mm)
I
from the beam top, at least one within the middle third of the beam depth
and at least one at not more than 6 in. (150 mm) from the beam bottom. I
22.6.3 - When partially prestressed beams are designed with mild steel
reinforcement providing at least 80% of the seismic resistance, prestress may I
be provided by one or more tendons passing through the joint core and located
within the middle third of the beam depth, at the face of the column. In such
cases post-tensioned tendons may be ungrouted, provided anchorages are
I
detailed to ensure that anchorage failure, or tendon detensioning, cannot
occur under seismic loads.
I
22.6.4 - Ducts for post-tensioned grouted tendons through beam-column
joints shall be corrugated, or provide equivalent bond characteristics. I
22.6.5 - Connections between precast members at beam-column joints
shall be acceptable brovided that the jointing material has sufficient strength I
to withstand the compressive and transverse forces to which it may be sub-
jected. The interfaces shall be roughened or keyed to ensure good shear
transfer and the retention of the jointing material after cracking.”
I
2.7 Future Testing I
A great deal more seismic testing of connections and components is probably
essential if precast prestressed concrete is to develop into a generally accepted safe I
system for earthquake-resistant design. Without additional research and testing to
determine appropriate dynamic characteristics, precast and prestressed systems will be
subjected to design uncertainties and strict code requirements.
I
If rapid advancement is to occur in the acceptance of precast systems proper
organization and standardization of test procedures will be required. Presently there is
I
uncertainty as to what constitutes an appropriate test, what demands are imposed On
connections and how to determine if a connection is acceptable for seismic loading. I
Although there are no general answers to these questions, guidelines could be established
I
2.54
I
I
I to eliminate much of the confusion which now exists.
In establishing the demands imposed on a system the following parameters are
I important(2’4g).
1. Maximum amplitude of deformation
I 2.
3.
Number of large-amplitude cycles of deformation
Sequence~oflarge-amplitude cycles of deformation
I 4. Associated maximum forces
Developing representative values for these parameters will allow easier evaluation of
I 2.
shown in Fig. 2-42.
Maximum shears corresponding to a particular combination of earth-
quake intensity, structure period and yield level may be estimated using
I charts such as shown in Fig. 2-43.
Dynamic analysis indicates that the critical shears shown in Fig.
I 2-43 are often produced by ground motions that are not the same as
those producing the critical ductility demand. Consequently, a conser-
I vatism beyond that associated with using the largest value for each
response quantity is obtained by assuming that they occur simul-
I taneously.
2.55
I
I
I
I
I
I
I
I
pip. !A-42 - Rotatlofml ductility vs. fundamental period
I
I
I
I
I
Fig. 2-43 -Critical
FuND*MENT*L PEWOD. T. SEC
I 5.
test with only one small inelastic cycle preceding it.
A suggested loading program is shown in Fig. 2-44. The value of maxi-
mum rotation in the hinging region, enex , and maximum shears corre-
I sponding to a particular earthquake intensity and combination of struc-
ture period and yield level can be obtained from charts such as shown in
I Figs. 2-42 and 2-43 respectively.
A specimen that sustains the applied loading without significant
I variables represented
earthquake intensity,
by the loading program.
structure
These variables include
period and yield level. Survival under
additional applications of the same loading history provides a measure
I of reserve capacity.
Satisfactory performance or survival in this context may be
I 6.
exceeding say, XI%, of it original strength.
A loading characterized by moments, shears and rotations all occurring
in phase, such as is commonly used in laboratory tests under slowly
I reversed loading, differs from dynamic inelastic reponse. Under dyna-
mic conditions, the shears are more sensitive to the higher modes of
I response. Consequently, they change direction much more rapidly than
do moment and rotation. For this reason, the commonly used test
I method of applying forces and deformations in phase represents a more
severe loading condition when compared to typical dynamic response.”
I precast panels to the main frame or diaphragm system. Welded embedded anchors show-
ed little ductility and failure often occurred in a brittle manner by pull out or weld
I fracture.
Other troublesome areas included lap splices, development of reinforcement
and unexpected torsional stresses. It was also speculated that shrinkage and temperature
I effects may have overstressed some connections before the earthquake occurred (2.51).
San Fernando, California, Earthquake
I Date:
Magnitude:
February 9, 1971
6.6 (200 aftershocks with a magnitude greater than 3.0 were recorded
I The largest fully precast structure built at the time of the earthquake was a
nine story bearing wall apartment building. The earthquake design of this and other
precast structures was developed through forced vibration testing of quarter-scale ten
I
I 2.59
I
story structures. The test specimens were typical of bearing wall construction with
I
horizontal and vertical connections composed of welded reinforcing bars or interlacing of
protruding reinforcing hoops(2’54). I
Finte1(2’54) suggests that the response of the large panel precast structures
was within their elastic range. If the structures were designed to perform elastically, I
there would be no signs of ductile behavior. The minimal amount of damage and repair
after the earthquake suggests that elastic response is an efficient way to design precast
structures.
I
2.9 Structural Integrity I
2.9.1 Definition
Structural integrity can be defined as that quality of a structure which allows I
stresses to be transferred from one component of a structure to another component. In
the event of the failure or removal of a structural component, the stresses carried by I
that component have to be redistributed away from the damaged area. This ‘alternate
path” philosophy of design requires that a structure be tied together to resist forces not
usually encountered under normal service loads.
I
The purpose of designing for structural integrity is to prevent a local failure
from producing a catastrophic collapse. Lack of structural integrity can be compared to
I
a row of dominoes or a house of cards, where the loss of one element precipitates the
collapse of the remaining elements. Providing an alternate path for the loads through I
the use of structural continuity will serve to bridge the local element failure, preventing
a collapse that would be entirely disproportionate to the initiating cause (known as
“progressive collapse?.
I
This philosophy of damage confinement can be illustrated in the design of
other types of structures. Bulkheads seal off compartments on ocean-going vessels to
I
prevent a single break below the water line from sinking the entire ship and party walLs
in apartment complexes localize damage due to fire or smoke.
I
Until recently most codes have not addressed the concept of adequate struc-
tural integrity directly. The reason is that most buildings contain a certain amount of I
“integrity” built-in.
Cast-in-place, reinforced concrete buildings contain numerous continuity I
enhancing features. These include minimum temperature reinforcement, 1% minimum
column reinforcement, #5 bars at openings, #3 bars at 12” to anchor floors to walls, wall
reinforcement in both directions, etc. These features enable reinforced concrete struc-
I
tures to withstand nearly all abnormal loadings without sustaining a total collapse.
I
2.60
I
I Such arbitrary, continuity-enhancing criteria also exist in structural steel
buildings. These factors include minimum force connection design, minimum weld size
I and length, slenderness limits, residual moment capacity in framed or seated connections
and other features of normal structural steel frame design.
I Non-structural components also play a major role in preventing a progressive
collapse. Such elements as concrete block partitions, window mullions, non-composite
I floor toppings, chimneys and fascia panels all contribute to post-abnormal loading stiff-
ness.
I maintain simplicity in details and erection procedure. The key advantage of precast
construction is its capability for a simple and speedy erection, with most of the compli-
cated details accomplished in the prestressing plant. As a consequence, the design
I efficiency brought about by this “building block” approach tends to eliminate the design
redundancies present in steel or concrete construction, which also eliminates many of the
I alternate load paths desired for abnormal loading response. Therefore, current research
is geared toward restoring some of these redundant load paths, thereby increasing struc-
I tural integrity, while also attempting to retain the simplicity of precast, prestressed
concrete connection details.
I instance when loads exceed ultimate to the point that a crucial support member, usually
a wall or a column, has yielded to the point where it can no longer transfer its assigned
loads effectively. These loads must then seek an alternate path for transfer to the
I ground.
I
2.61
I
I
I
I
I
I
(a) Immediate local damage (b) Progressive collapse
I
Fig. 2-45 - PaiIure modes of Roman Point collapse (Ref. 2.80)
I
The need for continuity of this type was demonstrated tragically in 1968 when
the 24 story Ronan Point apartment tower in London, England partially
explosion on the 18th floor caused an exterior
collapsed.
wall panel to be blown out, initiating
A gas
a
I
progressive collapse upward to the roof and then downward almost to the ground, due to
debris loading of the floors (See Fig. Z-45). As such, the initial damage was relatively
I
minor, but the resulting collapse was 23 times as damaging, demonstrating the structure%
inability to bridge over the local failure, i.e., its lack of integrity. I
Design forces at Ronan Point were resisted solely by the effects of bearing,
friction and bond, yet the building design fully complied with the then applicable building I
codes. After loss of the 18th floor wall panel, the structure was subjected to loads which
were unanticipated and, consequently, undesigned for, causing the collapse.
The Ronan Point disaster caused engineers and others to recognize that other
I
“abnormal”, unpredictable loadings can and sometimes do occur. This may include such
things as vehicle or airplane crashes, fires, floods, landslides, etc. In areas of low seis-
I
mic probability, earthquakes could be considered “abnormal loads”. This presents some-
thing of a dilemma: How does one design for loads which are, by nature, totally unpre- I
dictable? ‘lhe first approach, that of strengthening each element to resist any applied
abnormal load, is clearly uneconomical, as well as not totally attainable, given the un- I
predictable nature of these loads. A more logical approach would be to allow removal of
any structural element, at random, and designing the structure to transfer loads to the
other elements accordingly. ‘Ibis approach is still unrealistic in the sense that rarely
I
does an element simply Waporixe”
a yielded condition.
from the structure. It usually remains in place, but in
I
I
2.62
I
I
I Therefore, the most reasonable design approach would be to designate which
members are “allowed” to yield and which members are to be Wrong elements” (meant
I to stand firm at all cost). The member to be yielded is assumed to fail in a ductile
manner, allowing a semi-static type of load transfer. The post-yielded member also
I retains some of its original height, thereby limiting the deflection of the elements
above. This design approach is presented more completely in Reference 2.69.
I 2.9.3 Application to Severe Earthquake Resistance
Design for structural integrity is not meant to be a substitute for earthquake
I design. On the contrary, structural integrity provisions (as currently proposed) are bare
minimum requirements for 5 structure and any earthquake resistant design require-
I ments are in addition to the minimum integrity provisions.
This does not mean that design for integrity and continuity will not help in an
I earthquake situation. The ties used to hold elements together under abnormal loads will
also provide added ductility in the event of an earthquake. They are designed to sustain
large deflections without failure, which is precisely what is required to dampen severe
I earthquake vibrations in a prestressed building.
If the normal seismic provisions for a certain structure are exceeded and a
I member fails totally, structural integrity provisions will provide a secondary line of
defense. This is accomplished by shifting loads to other members, hopefully until the
I vibrations cease, allowing occupants time to evacuate the building.
2.9.4 Relationship to Service Load Design Procedures
I In general, design provisions for abnormal loads should be separated in func-
tion from the service load requirements for precast, prestressed construction.
I These load transfers should, in fact, be avoided under service conditions. The
additional member restraint added by these tie forces could cause unanticipated stresses
I explosion.
I 2.63
I
2.9.5 Current Design Provisions for Structural Integrity I
1. AC1 318-77
The American Concrete Institute Building Code for Reinforced I
Concrete(2.25) does not address the problem of structural integrity
directly, but does provide certain requirements for precast, prestressed I
construction in general:
14.2.9 Walls shall be anchored to floors, roofs, or to columns,
pilasters, buttresses and intersecting walls.
I
16.2.2 In precast construction that does not behave monolithically,
effects at all interconnected and adjoining details shall be
I
considered to assure proper performance of the structural
system. I
16.2.3 Effects of initial and long-time deflections shall be con-
sidered, including effects on interconnected elements.
Design of joints and bearings shall include effects of all
I
16.2.4
forces to be transmitted, including shrinkage, creep, temper-
ature, elastic deformation, wind and earthquake.
I
2. U. S, Department of Housing and Urban Development - “Minimum
Property Standards for Multi-family Housh@’
I
Recently, the Prestressed Concrete Institute has proposed addi-
tions to the above document regarding structural integrity. These I
additions listed below have been accepted in principle by HUD.
a. In Section 601-18: “All buildings shall maintain a level of strength
that will minimize the possibility of local damage being propagat-
I
b.
ed beyond the immediate vicinity of such damage.”
In Section 603-10: “The following provisions for bearing wall
I
construction will satisfy the requirements of Section 601-18:
. ..Unless analysis indicates that a greater amount of ties are I
required, the following minimum ties shall be provided:
(1) Reinforcement in the direction of the floor span, connecting I
floor or roof units which abut over internal bearing walls, or
connecting units to end bearing walls, shall be provided at a
spacing not to exceed 8 feet. Reinforcement shall be capable
I
of developing the design (factored) force required, but not
leas than 1500 pounds per linear foot of distance measured
I
parallel to the support wall. Reinforcement may be connect-
I
2.64
I
I
I ed by mechanical methods, or be of sufficient length to
I grity if the design does not require cross ties or continuity reinforce-
I 2.65
I
I
I
I
I
0 Recommended tie forces b) lppioal tie errangement
I
pig. 2-46 - Recommendations for nominal tie placement (Ref. 2.71)
ment of greater strength. I
Another requirement is that the structure withstand a lateral
design load equal to 2% of the building’s vertical service load. I
It is clear that tie requirements for earthquake resistance would
be more stringent than those presented above, but the locations of tie
placement would be similar.
I
Portland Cement Association Tests(2.69)
4.
The Portland Cement Association has conducted precast large
I
panel general structural integrity tests for the Department of Housing
and Urban Development and has presented methods for the design of I
structural ties to resist abnormal loads. The notation is the same as
that used by PC1 CT1through T4), so one can refer to Fig. 2-4’7 for tie
locations.
I
Fig. 2-47 presents a method of calculating the required capacity
of the transverse ties (Tl). Peripheral ties (T2) are to be designed as
I
transverse (T1) or longitudinal (T2) ties, depending on their orientation
(compared to the 16 kip arbitrary force for T2 recommended by PC& I
Longitudinal ties (T2) can be designed based upon the chart and table
presented in Fig. 2-48. Unstressed prestressing strand is recommended I
for Tq to prevent tie rupture and promote floor suspension action (See
Fig. 2-49). Vertical ties (T4) may be designed according to the chart in
Fig. 2-50 for horizontal shear. Tension force due to the possible loss of
I
a lower panel and subsequent suspension of upper panels should also be
accounted for in the final design of tie T4.
I
I
2.66
I
I
I
I
I
I
I
I
Fig. 2-47 - Design chart for transve.rse force at any story (T1) (Ref. 2.69)
I
I
I
I
I
I
I
I
I
I F&!&46-Deaignehartfor interior langitudinal ties (Ref. 2.69)
I
I 2.67
I
I
I
-Wall panels
I
I
I
Fig. 2-49 - suspension mechanism by means of longitudinal ties
I
I
I
I
I
I
I
I
N-IOVERTICAL CONNECTION / TIE
SHEAR FORCE “V,.” AT EACH STORY
I
C-I FOR ANY WiLL HEIGHT _
I
I
Fig. P-60 - Des&p chart for horizontal shear force at any story Wet. 2.69)
I
2.68
I
I
I 2.10 Hurricanes, Tornadoes and Other Wind Loadings
I quake load design. In both cases, dynamic loads are approximated by equivalent static
loads applied laterally to the structure. For earthquakes, this static load is a small
percentage of the actual earthquake load, while static wind loads are representative of
I the actual maximum wind force.
The source of these loads differ, however. Earthquake loads are generated by
I the mass of the building itself, larger masses creating larger lateral forces. Wind forces
are externally applied. Their magnitude is dependent on local climate, building shape,
I orientation, and surface texture. Therefore, while excessive mass is a detriment to the
earthquake resistance of a structure, it is an asset to the structure’s wind resistance.
I that the allowable wind pressure tables have been replaced by pressure formulas and
coefficients. ‘this was done to reflect the proliferation of hand calculators which make
calculations easier than table reading.
I Design wind pressures are a function of velocity pressure, q, a gust factor, C,
and a pressure coefficient, C. Velocity pressure, q, is also a function of exposure* Rx,
I Importance, I, Hurricane vulnerability, H, and air velocity, V. A procedure for estimat-
ing the dynamic effect of wind gusts is suggested in the document. Pressure on building
I components and cladding are given special attention, since these pressures can be much
higher than the average pressure on the building. Tornadoes are not considered, but
I references are suggested which deal with design for tornado forces. Wind tunnel tests
are recommended for unusual conditions or in lieu of the above analytical procedure.
I
2.69
I
I
BOCA BASIC BUILDING CODE/l978 I
The BOCA Code follows ANSI A58.1-1972 recommendations closely. How-
ever, BOCA’s arbitrary assumption of cladding pressure equal to l-1/2 times the overaU I
pressure is unconservative at building corners, where the component pressure can be as
high as three times the overall pressure. It is expected that this assumption will be
revised to follow the ANSI 1980 revision recommendations.
I
UNIFORM BUILDING CODE, 1979 EDITION
The Uniform Code only specifies wind pressures as lateral forces applied to
I
the vertical projection of a building. No mention is made of cladding pressures or wall
suction pressures. These deficiencies are partially compensated for by specifying lateral I
pressures which are much higher than ANSI recommendations. This approach is unduly
conservative for structural design, yet possibly unconservative for cladding at building I
corners, windows and for negative pressure resistance.
2.10.3 Common Practice I
As was shown in the previous section, most building codes address conven-
tional wind storms and hurricanes only. A design for these loads is concerned mainly I
with service load conditions such as lateral drift control and movement perception.
Ultimate strength becomes critical only for low-rise buildings or for suction pressures on I
ClEWMing. An aeroelastic analysis is required for structure types that tend to vibrate
under the dynamic action of wind gusts. Precast concrete structures fare better than
steel in this respect, since greater mass means less acceleration.
I
Hurricane loads are anticipated by designing for conventional maximum 58 or
199 year recurrence wind speeds and adding a hurricane factor, H, depending on the
I
proximity to the coastline (ANSI A58.1-1980). As in earthquake resistant design, it is
expected that a severe hurricane could stress the structure to near ultimate strength and I
also cause some non-structural damage. This can be tolerated since such storms are
extremely rare and to design for such a rare occurrence would be economically unjustifi-
able. Structural ductility therefore becomes necessary to prevent a brittle failure from
I
occurring during the hurricane passage.
Wind-borne objects become missiles that can penetrate a building’s skin.
I
Precast wall panels provide an effective barrier against these missiles, though large glass
openings could subvert this advantage. .
I
Design for tornado resistance is normally not done for conventional struc-
tures. The reason for this is that although tornadoes are the severest of the wind storm I
types, they are also small in scope, leaving damage paths normally less than a few hun-
I
2.70
I
I
I dred yards wide. This makes it impossible to predict where they will occur. Typical
recurrence rates for tornadoes range in the thousands of years. Only for critical installa-
I tions such as nuclear power plants are such remote risks given any consideration. How-
ever, recent studies of tornado paths reveal lower wind speeds (100 to 250 mph) and
I pressures than previously expected, bringing tornado resistant design into the realm of
plausibility.
I 2.10.4 Recommendations
For conventional winds, Reference 2.73 suggests limiting drift to h/1000 for
I prefabricated panel buildings. This value lies between the AC1 maximum of h/500 and
the CEB recommendations of h/2000 for the limit state of cracking.
I Precast concrete shear walls can be used to effectively reduce drift in high-
rise steel structures(2*74). These panels could also serve to limit non-structural damage
I caused by a wildly gyrating ductile steel frame in the event of an earthquake.
Partial fixity at wall-floor panel joints under service wind loads is recom-
I mended by Reference 2.75 as a means of limiting lateral deflections. Fig. 2-51 shows
how the lateral drift varies, depending on the fixity of the wall-floor connection. A 20%
fixity serves to cut the total drift in half for an average mid-rise precast large-panel
I building. If the joint is not reinforced, however, it could fracture under earthquake loads
and the joint fixity benefits would be lost. Building codes utilizing an equivalent static
I earthquake load tend to obscure this point.
I
I
I
I
I
I DEGREibF OFW-ALL -FiOOR
CONNECTION
I subjective assumptions and the results too often indicate a degree of precision that has
very little meaning.
What is more relevant is the increased cost an owner is willing to absorb to
I provide some degree of tornado resistance and to what extent building codes should
require consideration of tornado velocity winds.
I Most precast, prestressed concrete buildings would require very little modifi-
cation to withstand exceptionally high wind velocities (2.79), particularly if ultimate
I strength of the components and connections is considered, as is the case with earthquake
resistant design.
I
I
I
2.73
I
I
BRFERBNCES - PART 2 I
2.1 Derecho, A. T. and Fintel, M. “Chapter 12: Earthquake Resistant Structures”,
Handbook of Concrete Engineering (Fintel, M. ed.), Van Nostrand Reinhold Com-
I
pany, New York, 1974.
2.2 Bolt, B. A., “Chapter 2: Causes of Earthquakes”, Earthquake Engineering
I
(Wiegel, R. ed.), Prentice-Hall, Inc., Fnglewood Cliffs, NJ, 1970.
2.3 Newmark, N. M., “Chapter 16: Current Trends in the Seismic Analysis and Design I
of High-Rise Structures ‘I, Earthquake Engineering (Wiegel, R. ed.), Prentice-Hall,
2.4
Inc., Englewood Cliffs, NJ, 1970.
Clough, R. W., “Chapter 12: Earthquake Response of Structures”, Earthquake
I
Engineering (Wiegel, R. ed.), Prentice-Hall, Inc., Englewood, NJ, 1970.
2.5 Llorente, C., Becker, J. M. and Roesset, J. M., “Effect of Nonlinear Inelastic
I
Connection Behavior on Precast Panelized Shear Walls”, Reinforced Concrete
Structures Subjected to Wind and Earthquake Forces, Publication SP-63, American
Concrete Institute, Detroit, 1980. I
2.6 Powell, G. and Schricker, V., “Ductility Demands of Joints in Large Panel Struc-
tures”, ASCE Fall Convention, San Francisco, October, 1977, Preprint 3022. I
2.7 Brankov, G. and Sachanski, S., “Response of Large Panel Buildings for Earthquake
Excitation in Non-elastic Range I’, Proceedings of the Sixth World Conference on
Earthquake Engineering, New Delhi, India, 1977. I
2.8 Newmark, N. M. and Hall, W. J., “Dynamic Behavior of Reinforced and Prestress-
ed Concrete Buildings under Horizontal Forces and the Design of Joints”, Preli-
minary Publication, Eighth Congress of International Association for Bridge and
I
Structural Engineering, New York, 1968, pp. 586-613.
2.10 Parme, A. L., “American Practice in Seismic Design”, PC1 Journal, Vol. 17, No. 4, I
July/August, 1972, pp. 31-44.
2.11 Phillips, W. R. and Sheppard, D. A., “Plant Cast Precast and Prestressed Con-
crete”, the Prestressed Concrete Manufacturers Association of California, Inc.,
I
1980.
2.12 Dorwick, D. J., Earthquake Resistant Design, John Wiley d( Sons, New York, 1977.
I
2.13 Seismology Committee, SEAOC. “Recommended Lateral Force Requirements
Commentary”, Structural Engineers Association of California, 1974.
and
I
2.14 Steinbrugge, K. V., “Chapter 9: Earthquake Damage and Structural Performance
in the United States”, Earthquake Engineering (Wiegel, R. ed.), Prentice-Hall, Inc.,
Englewood Cliffs, NJ, 1970.
I
I
2.74
I
I
I 2.15 Uniform Building Code, International Conference of Building Officials,
Whittier, CA, 1979.
I 2.16 ATC-3 (Applied Technology Council), “Tentative Provisions for the Development
of Seismic Regulations for Buildings”, National Bureau of Standards, U. S. De-
partment of Commerce, Washington, DC, June, 1978.
I 2.17 Anonymous, “Tough Rules To Make Buildings Quake-resistant”, Business Week,
October 6, 1980, pp. 112E-F.
I 2.18 Park, R. and Paulay, T., Reinforced Concrete Structures, John Wiley & Sons,
New York, 1975, pp. 545-609.
I 2.19 Blume, J. A., Newmark, N. M. and Corning, L. H., Design of Multi-story Relnforc-
ed Concrete Buildings for Earthquake Motions, Portland Cement Association,
Chicago, IL, 1961.
I 2.20 Clough, R. W., ‘Effect of Stiffness Degradation on Earthquake Ductility Require-
ments”, Report No. 66-16, Structural Engineering Laboratory, Berkeley, Univer-
I 2.21
sity of California, October, 1966.
Fintel, M., “Quake Lessons from Managua: Revise Concrete Building Design?“,
Civil Engineering, Vol. 43, No. 8, August, 1973, pp. 60-63.
I 2.22 Paulay, T., “Earthquake-Resisting Shear Walls - New Zealand Design”, AC1 Jour-
nal, Vol. 77, No. 3, May-June, 1980, pp. 144-152.
I 2.23 Allen, C. M., Jaeger, L. G. and Fenton, V. C., “Ductility in Reinforced Concrete
Shear Walls”, AC1 Publication SP-36, Responseof Multi-story Concrete Structures
to Lateral Forces, American Concrete Institute, Detroit, MI, 1973, pp. 97-118.
I 2.24 Derecho, A. T., Ghosh, S. K., Iqbal, M. and Fintel, M., “Strength, Stiffness and
Ductility Required in Reinforced Concrete Structural Walls for Earthquake Resis-
I tance”, AC1 Journal, Vol. 76, No. 8, August, 1979, pp. 875-896.
2.25 AC1 Committee 318, “Building Code Requirements for Reinforced Concrete
I 2.26
(AC1 318-77)“, “American Concrete Institute, Detroit, MI.
Englekirk, R. E., “An Evaluation of the State of Art in the Design and Construc-
tion of Prefabricated Buildings in Seismically Active Areas of the United State”,
I Proceedings, Workshop on Earthquake Resistant Reinforced Concrete Building
Construction, University of California at Berkeley, July, 1977.
I
2.75
I
I
2.30 Roeder, C. W. and Popov, E. P., “Eccentrically Braced Steel Frames for Earth- I
quakes”, Journal of the Structural Division, ASCE, Vol. 104, No. ST3, March, 1978,
2.31
pp. 391-412.
Scott, N. L., “Developments in Precast Framing ‘I, Concrete International, Ameri-
I
can Concrete Institute, Vol. 2, No. 11, November, 1980, pp. 60-66.
2.32 Becker, J. M. and Lorente, C., Seismic Design of Precast Concrete Panel Build-
I
ings”, Proceedings, Workshop on Earthquake Resistant Reinforced Concrete Build-
2.33
ing Construction, University of California at Berkeley, July, 1977.
Hawkins, N. M., “Stateof-the-Art Report on Seismic Resistance of Prestressed
I
and Precast Concrete Structures: Part 2 - Precast Concrete”, PC1 Journal,
Vol. 23, No. 1, Jan-Feb, 1978, pp. 40-58. I
2.34 Fiorato, A. E. and Corley, W. G., “Laboratory Tests on Earthquake Resistant
Structural Wall Systems and Elements”, Proceedings, Workshop on Earthquake
Resistant Reinforced Concrete Building Construction, University of California at
I
Berkeley, July, 1977.
2.35 Spencer, R. A. and Nellie, D. S., “Cyclic Tests of Welded Headed Stud Connec-
tions”, PC1 Journal, Vol. 21, No. 3, May-June, 1976, pp. 70-83.
I
2.36 PC1 Design Handbook, Second Edition,
Chicago, IL, 1978.
Prestressed Concrete Institute, I
2.37 Venuti, W. J., “Diaphragm Shear Connectors Between Flanges of Prestressed
Concrete T-Beams”, PC1 Journal, Vol. 15, No. 1, February, 1970, pp. 67-78. I
2.38 Shemie, M., “Bolted Connections in Large Panel System Buildings”, PC1 Journal,
Vol. 18, No. 1, Jan-Peb, 1973, pp. 27-33. I
2.39 Pillai, S. U. and Kirk, D. W., ‘Ductile Moment Resisting Beam-Column Connec-
tions on Precast Concrete ‘I, Paper presented at AC1 Fall Convention, Washington,
DC, Oct. 28-NOV.2,1979.
I
2.40 Hawkins, N. M. and Mitchell, D., “Historical Perspective”, Reinforced Concrete
Structures in Seismic Zones, Publication SP-53, American Concrete Institute, I
Detroit, 1977.
2.41 Park, R., “Design of Prestressed Concrete Structures”, Proceedings, Workshop on
Earthquake Resistant Reinforced Concrete Building Construction, University of
I
California, Berkeley, July, 1977.
2.42 Thompson, K. J. and Park, R., “Ductility of Prestressed and Partially Prestressed
I
Concrete Beam Sections”, PCI Journal, Vol. 25, No. 2, March/April, 1980,
2.43
pp. 46-70.
Thompson, K. J. and Park, R., “Cyclic Load Tests on Prestressed and Partially
I
Prestressed Beam-Column Joints”, PC1 Journal, Vol. 22, No. 5, Sept/Oct, 1977,
pp. 84-110. I
I
2.76
I
I
I 2.44 Lin, T. Y., Kuika, F. and Tai, J., “Design of Earthquake-Resistant, Prestressed
Concrete Structures”, Proceedings, Workshop on Earthquake Resistant Reinforced
I 2.45
Concrete Building Construction, University of California at Berkeley, July, 1977.
Code of Practice for General Structural Design and Design Loadings for Buildings
(NZS 4203: 1976), Standards Association of New Zealand, 1976.
I 2.46 Draft Code of Practice for the Design of Concrete Structures (DZ 3101), Stan-
dards Association of New Zealand, 19’78.
I 2.47 Dowrick, D. J., Kulka, F. and Park, R., “Connections Between Precast Prestressed
Concrete Members in Buildings”, FIP Commission on Seismic Structures, Interim
Report by Working Group, April, 1979.
I 2.48 Uzumeri, S. M., “Strength and Ductility of Cast-In-Place Beam-Column Joints”,
Reinforced Concrete Structures in Seismic Zones, Publication SP-53, American
I Concrete Institute, Detroit, 1977, pp. 293-350.
2.49 Derecho, A. T., Iqbal, M., Pintel, M. and Corley, W. G., “Loading History for Use
I in Quasi-Static Simulated Earthquake Loading Tests‘I, Reinforced Concrete Struc-
tures Subjected to Wind and Earthquake Forces, Publication SP-63, American
Concrete Institute, Detroit, 1980.
I 2.50 Kunze, W. E., Sbarounis, J. A. and Amrhein, J. E., “The March 27 Alaskan Earth-
quake-Effects on Structures in Anchorage”, AC1 Journal, Vol. 62, No. 6, June,
1965, pp. 635-648.
I 2.51 Wood, F. J. (Editor-in-Chief), The Prince William Sound, Alaska, Earthquake of
1964 and Aftershocks, U. S. Department of Commerce Environmental Science
I 2.52
Services Administration, Publication 10-3, Vol. 2, 1967.
Lew, H. S., Leyendecker, E. V. and Dikkers, R. D., Engineering Aspects of the
1971 San Fernando Earthquake, United States Department of Commerce, Building
I Research Division, Building Science Series 40, December, 1971.
2.53 Sharpe, R. L., ‘the Earthquake Problem”, Reinforced Concrete Structures in
I 2.54
Seismic Zones, Publication SP-53, American Concrete Institute, Detroit, 1977.
Fintel, M., “Performance of Precast Concrete Structures During Rumanian Earth-
quake of March 4, 1977”, PC1 Journal, Vol. 22, No. 2, March-April, 1977, pp. lo-
I 15.
2.55 Kunze, W. E., Sbarounis, J. A. and Amrhein, J. E., “Behavior of Prestressed Con-
I crete Structures During the Alaskan Earthquake”, PC1 Journal, Vol. 10, No. 2,
April, 1965, pp. 80-91.
I 2.56 Hanson, N. W., %eismic Resistance of Concrete Frames With Grade 60 Rein-
forcement”, Journal of the Structural Division, ASCE, Vol. 97, No. ST6, June,
1971, pp. 1685-1700.
2.5Y
pp. 1567-1590.
2.60 Freeman, S. A., ‘Seismic Design Criteria for Multi-story Precast Prestressed
I
Buildings”, PC1 Journal, Vol. 24, No. 3, May/June, 1979, pp. 62-88.
Lewicki, B and Pauw, A., “Joints, Precast Panel Buildings - State of the Art
I
Report No. 2”, Planning and Design of Tall Buildings, Vol. III, American Society of
Civil Engineers, New York, 1972, pp. 171-190. I
2.63 Zeck, U. I., “Joints in Large Panel Precast Concrete Structures”, R 76-16, De-
2.64
partment of Civil Engineering, Massachusetts Institute of Technology, Jan, 1976.
Frank, R. A., “Dynamic Modeling of Large Precast Panel Buildings Using Finite
I
Elements With Substructuring”, R76-36, Department of Civil Engineering, Massa-
chusetts Institute of Technology, August, 1976. I
2.65 Hassan, F. M. and Hawkins, N. M., “Anchorage of Reinforcing Bars for Seismic
Forcesl’, Reinforced Concrete Structures in Seismic Zones, Publication SP-53,
American Concrete Institute, Detroit, 1977, pp. 387-416. I
2.66 Hassan, F. M. and Hawkins, N. M., “Prediction of the Seismic Loading Anchorage
Characteristics of Reinforced Bars ‘I, Reinforced Concrete Structures In Seismic
Zones, Publication SP-53, American Concrete Institute, Detroit, 1977, pp. 417-
I
438.
2.67 Aswad, A., %elected Precast Connections: Low-Cycle Behavior and Strength”, I
Proceedings of the 2nd U. S National Conference on Earthquake Engineering,
2.68
Stanford University, California, August 22-24, 1979.
Maison, B. F. and Popov, E. P., %yclic Response Prediction for Braced Steel
I
Frames”, Journal of the Structural Division, ASCE, Vol. 106, No. ST7, July, 1980,
pp. 1401-1416. I
2.69 Schultz, D. M., Burnett, E. F. P. and Fintel, M., “A Design Approach to General
Structural Integrity”, Design and Construction of Large-Panel Concrete Strue-
tures, Office of Policy Development and Research, Department of Housing and
I
Urban Development, Washington, DC, October, 1977.
2.70 Thompson, K. J. and Park, R., ‘Seismic Response of Partially Prestressed Con-
crete”, Journal of the Structural Division, ASCE, Vol. 106, No. ST8, Proceedings
I
Paper 15598, August, 1980, pp. 1755-1775.
I
I
2.78
I
I
I 2.71 Speyer, I. J., “Considerations for the Design of Precast Concrete Bearing Wall
Buildings to Withstand Abnormal Loads”, for PC1 Committee on Precast Concrete
I 2.72
Bearing Wall Buildings, PC1 Journal, Vol. 21, No. 2, Mar-Apr, 1976, pp. 18-51.
Mast, R. F., ‘Seismic Design of 24-Story Building with Precast Elements”,
PC1 Journal, Vol. 17, No. 4, July-Aug, 1972, pp. 45-59.
I 2.73 Levy, Matthys P. and Varga, Istvan S., “High-Rise Panel Structures”, Journal of
the Structural Division, ASCE, New York, NY, Vol. 98, No. ST5, May, 1972,
I pp. 975-988.
2.74 Weidlingern, Paul, “Shear Field Panel Bracing I’, Journal of the Structural Division,
I 2.75
ASCE, New York, NY, Vol. 99, No. ST7, July, 1973, pp. 1615-1631.
2.76 Minor, Joseph E., Mehta, Kishor C. and McDonald, James R., “Failures of Struc-
I tures Due to Extreme Winds”, Journal of the Structural Division, ASCE, New
York, NY, Vol. 98, No. STll, Nov, 1972, pp. 2455-2471.
2.77 Wen, Yi-Kwei and Chu, Shih-Lung, “Tornado Risks and Design Wind Speeds”,
I Journal of the Structural Division,
Dee, 1973, pp. 2409-2421.
ASCE, New York, NY, Vol. 99, No. ST12,
I 2.78 Garsono, Robert C., Catalan, Jose Morla and Cornell, C. Allin, “Tornado Design
Winds Based on Risk”, Journal of the Structural Division, ASCE, Vol. 101, No. ST9,
Sept, 1975, pp. 1883-1897.
I 2.79 Mehta, Kishor C., “A Proposal for Tornado Resistant Design of Versa-Space Build-
ings”, McDonald, Mehta and Minor, Consulting Engineers, Lubbock, TX, NOV, 1975.
I
I
I
I
I
I
I 2.79
I
I
I
I
I
I
I
I PART 3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
3. SELECTION AND DESIGN OF CONNECTIONS
I Satisfactory performance and economy of precast, prestressed concrete struc-
tures depends to a great extent on the proper selection and design of each connection.
I Several publications have addressed this subject (3.1-3.6). This section is based on infor-
mation from those and other publications, plus the experience of the study team. A
I great deal of input was received from designers and manufacturers
ed concrete, especially members of the Prestressed Concrete
of precast, prestress-
Institute Committee on
I Connection Details.
I of the structure.
3.1.1 Strength
I A connection must have the strength to resist the forces to which it will be
subjected during its lifetime. Some of these forces are apparent, caused by dead and live
I would not “fail” until it had deformed by a length b (assuming adequate bearing
strength). Under the above definition, it could, therefore, be considered “ductile”.
However, ductility in building frames is usually associated with moment resis-
I tance. This is particularly true in designing for earthquake forces, which is where con-
cerns over ductility are usually expressed. In concrete members with moment-resisting
I connections, the flexural tension is normally resisted by steel components, either rein-
forcing bars or structural steel members. First yield occurs in this steel component, and
I final failure may be from rupture of the steel, crushing of the concrete, or a failure of
the connection of the steel to the concrete.
I The above friction connection, while probably not reliable for use in earthquake
areas, may be satisfactory for some types of structures under some loading conditions,
such as wind. In that case the normal wind loading would be resisted by the friction. The
I “ductility”, assuming adequate bearing length, b, might be adequate for unusually strong
wind gusts, or other abnormal, very short duration loads.
I 3.1.3 Volume Change Accommodation
The combined shortening effects of creep, shrinkage and temperature drop can
I cause severe stresses on precast, prestressed concrete members and their supports, if the
end connections restrain movement. These stresses must be considered in the design, but
I it is usually far better if the connection will allow some movement to take place, thus
relieving the stresses.
I Section 4.4 of the PC1 Design Handbook(3’2) provides data and guidelines for
estimating the amount of volume change shortening that may take place.
I Most of the severe problems that have been caused by restraint of volume
change movements have appeared when relatively long members, usually stemmed deck
units, were welded to their supports at the bottom on both ends. When such members are
I connected only at the top, as shown in Fig. 3-2, experience has shown that VolUme
changes are adequately accommodated. On relatively short, heavily loaded members,
I such as beams, an unyielding top connection may attract negative moments if compres-
sion resistance is encountered at the bottom. This may be difficult to accommodate.
I Connections using cast-in-place concrete, similar to Fig. 3-3 have exhibited few
volume change problems. This is probably because micro-cracking and creep in the cast-
I
I 3.3
I
I
I
I
I
I
pig. 3-3 - Compoaite connection
Fig. 3-2 - Tppical double tee to beam connection
I
3.1.4 Durability
Evidence of poor durability is usually exhibited by corrosion
elements, or by cracking and spalling of concrete. Connections which will be exposed to
of exposed steel I
weather should have steel elements adequately covered with concrete, or should be
painted or galvanized. All exposed connections should be periodically inspected and
I
maintained.
Most precast, prestressed concrete is of high quality, and flexural cracking is
I
seldom a serious problem, provided tensile stresses are kept within code limits. How-
ever, local cracking or spalling can occur when improper details result ,in restraint of I
movement or stress concentrations.
I E II
I
I (c) Wiled refractory anchor
I
recessed plates and similar elements, connections such as those shown in Fig. 3-4 can be
I used.
I example, an exposed steel bracket supporting a beam may be weakened enough by a fire
to cause the beam to collapse. Such a bracket should be protected. The amount of
protection depends on (a) the stress-strength ratio in the steel at the time of the fire and
I (b) the intensity and duration of the fire. Also many connections are simply stability
devices and are under little or no stress in service. A fire could substantially reduce the
I strength of such a connection but it would still perform effectively.
I
I 3.5
I
Connections which require a fire resistance rating will usually have exposed
I
steel elements encased in concrete
include enclosing with gypsum wallboard,
(See X1.4.1).
coating
Other methods of fire protection
with intumestic mastic, or spraying
I
with fire protection material.
There is evidence that exposed steel hardware used in connections is less sus- I
ceptible to fire-related strength reduction than other exposed steel members. This is
because the concrete elements provide a “heat sink”, which draws off the heat and re-
duces the temperature of the steel, Research on this subject Is recommended.
I
Additional
Reference 3.52.
information on fire protection of connections Is given in
I
3.1.6 Fabrication Simplicity I
Maximum economy of precast, prestressed concrete construction is achieved
when connection details are kept as simple as possible, consistent with adequate perfor-
mance and ease of erection. Furthermore, complex connections are more difficult to
I
control and will often result in poor fitting
erection and less satisfactory performance.
in the field. This can contribute to slow
I
Following is a list of items to consider in order to improve fabrication simplic-
ity. In many cases, some of these items must be compromised in order for the connec- I
tion to serve its intended function.
3.1.6.1 Avoid congestion. The area of the member in which the connection is made I
frequently requires large amounts of additional reinforcing steel, embedded plates,
inserts, blockouts, etc. It is not unusual for so many items to be concentrated into one I
area that there is very little room for concrete. It should be remembered that precast,
prestressed
top accessible.
concrete members are usually cast in permanent steel forms with only the
Placement of the reinforcement and hardware can often be likened to
I
“building a ship in a bottle”. If one item must be threaded in and around other items, for
example, labor costs can be significantly increased. Reinforcing bars and prestressing
I
strands, which appear as lines on drawings, have real cross-sectional dimensions (which
are larger than the nominal dimension because of the deformations); a fact to be consi- I
dered in the design phase. Reinforcing bar bends require minimum radii, which can cause
fit problems and leave some regions unreinforced.
to draw large scale details of the area in question.
If congestion is suspected, it is helpful I
In some cases, it may be economical to increase the member sizes just to avoid
congestion. Also, such details as dapped or recessed ends should be avoided unless neces-
I
sary. They require special reinforcement in a smaller space and are always congested.
I
3.6
I
I
I 3.1.6.2 Avoid penetration of forms. Since most precast, prestressed concrete members
3.1.6.3 Minimize embedded items. Items which are embedded in the member, such as
I inserts, plates, reglets, etc., require plant labor to locate precisely and attach securely.
Therefore, these items should be kept. to a minimum.
I 3.1.6.4 Reduce post-stripping work. A plant casting operation is most efficient when
the product can be taken directly to the storage area immediately after it is stripped
I from the form. Any operations which are required after stripping and before placement
at the job site, such as special cleaning or finishing, or welding on projecting hardware,
I should be avoided, whenever possible. These operations require additional
work space, and added labor, often with skilled trades.
handling, extra
I The trade-off
times need to be evaluated.
between penetration of forms and post-stripping work will some-
An example of this is the embedded steel haunch shown in
I Fig. 3-5.
In Fig. 3-5(a), the operations that are required are:
(1) Cut hole in steel form with cutting torch.
I (2) Smooth rough cut edges.
(3) Place and secure steel haunch (requires a special device to suspend the
I (4)
steel and hold rigidly in place).
Caulk opening around the steel haunch.
I (5)
(6)
After all casts are made, patch the hole by welding.
Grind welded surface smooth.
In (b) the required operations are:
I (1) Weld plate to haunch at A in steel fabrication shop.
(2) Place and secure to form (easier than in (a) because it does not have to be
I suspended).
(3) After stripping the product, remove to special work area.
I (4)
(5)
Turn member on side to avoid overhead weld.
Weld on exterior portion at B.
I 3.1.6.5
(6) Remove member to storage.
I be more rigid than industry standards, are difficult to achieve. Connections which re-
I 3.1
I
I
Steel
ham-h
----
==Tzc=
I
Form
p.n.tmed I
fEk
(a) I
Fig. 3-5 - Alternate methods of casting column with
embedded steel haunch
I
quire close-fitting parts without provision for adjustment should be avoided. Standard
I
tolerances are given in PC1 and AC1 documents.
3.1.6.6 Use standard items. Wherever possible hardware items such as inserts, studs,
I
steel shapes, etc., should be standard items that are readily available, preferably from
more than one supplier. Custom fabricated or very specialized proprietary items add I
cost and may cause delays.
It also simplifies fabrication if similar items on a product or project are stan- I
dardized as to size and shape. For example, if half of the inserts are required to receive
3/4 in. diameter bolts, and the other half 1 in. diameter, use of all 1 in. bolts will be
simpler. There is also less chance of error. The same principle applies to reinforcing
I
bars, embedded plates, studs, etc.
3.1.6.7 Use repetitious details. It is very desirable to repeat details as much as pos-
I
sible. Similar details should be identical,
Once workmen are familiar with a detail,
even if it may result in a slight overdesign.
it is easier to repeat it than to learn a new
I
one. Also, it will require fewer form set-ups and improve scheduling.
3.1.6.8 l3e aware of material limitations. Examples of this are the radius requirements
I
for bending reinforcing
I 3.1.7.1 Plan for the shortest possible hoist hook-up time. Hoisting the precast pieces is
usually the most expensive and time-critical process of the erection. Connections should
I be designed so that the unit can be lifted,
time.
set, and unhooked in the shortest possible
Before the hoist can be unhooked, the precast piece must be stable and in its final
I position.
inherently
Some shapes of precast units such as double tees and hollow-core
stable and require no additional connections before releasing
slabs are
the crane.
I Others, such as columns, deep beams, wall panels and single tees usually require some
supplemental shoring, guying, or fastening before the hoist can be unhooked. Preplanning
for the fewest, quickest, and safest possible operations that must be performed before
I releasing the hoist will greatly facilitate erection. Bearing pads, shims, or other devices
upon which the piece is to be set should be placed ahead of hoisting. Loose hardware
I that is requited for the connection should be immediately available for quick attachment.
In some cases, it may be necessary to provide temporary fasteners or leveling
I devices, with the permanent connection made after the hoist is released. For example, if
the permanent connection requires field welding, grouting, dry packing, or cast-in-place
concrete, erection bolts, pins, or shims can be used. These temporary devices must be
I given careful attention to assure that they will hold the piece in its proper position
during the placement of all pieces that are erected before the final connection is made.
I 3.1.7.2 Provide for adjustment. A certain amount of field adjustment at the connec-
tions is always necessary. Normal fabrication tolerances preclude the possibility of a
I perfect fit in the field. This is true not only when the precast pieces join to each other,
but, usually even more so, when the precast units must interface with other materials.
I Adjustment in the field is accomplished
holes for bolts and dowels, field welding, shims and grout.
through the use of slotted or oversize
I 3.1.7.3 Provide accessibility. Connections should be planned so that they are accessible
to the workman from a stable deck or platform. The type of equipment necessary to
I perform
sidered.
such operations as welding, post-tensioning, or pressure grouting should be con-
Operations which require working under a deck in an overhead position should be
I
I 3.9
I
avoided, especially for welding. Alternatives to anything that requires temporary scaf-
I
folding should be considered.Room to place wrenches on nuts and swing them in a large
arc should be provided for bolts. Dry-packing column or wall panel bases in a narrow I
excavation is difficult.
3.1.7.4 Standardize connection types. All connections which serve similar functions I
within the building should be standardized as much as possible. As workmen become
familiar with the procedures required to make the connection, productivity is enhanced, I
and there is less chance for error.
Some types of connections
ple, welding and post-tensioning.
require skilled craftsmen to accomplish,
The fewer of these skilled trades required, the more
for exam- I
economical the connection will be.
I
3.1.7.5 Standardize sizes of components. Whenever possible, such things as field bolts,
loose angles, etc., should be of common size for all connections.
for error, and the time required to search for the proper item.
This reduces the chance I
3.1.7.6 Use connections
pack, cast-in-place
that are not weathersensitive.
concrete,
Such materials as grout, dry-
and epoxies need special provisions to be placed in cold
I
weather. Welding is slower when the ambient temperature is low. If the connections are
designed so that these processes must be completed before erection can continue, costly
I
delays may result.
I and erection
ance.
simplicity, and hence, increase the cost, to provide a satisfactory appear-
I
I
I >-T
I
I
I
Fig. 3-6 - md patha on connection
I
I 3.11
I
(3) Haunch to steel plate through shear and flexural strength of steel shape.
I
(4)
(5)
Through the plate via welds.
From embedded steel shape to column concrete through bearing. I
The tensile force (caused by volume change shortening) follows these paths.
(6) Concrete beam to reinforcing bars by bond. I
(7) Reinforcing bars to bearing angle through weld.
(8) Bearing angle to steel haunch through friction on top and bottom of the
bearing pad. Most of this volume change force is then relieved through
I
(9)
deformation of the pad.
There is still a minor amount of tensile force transmitted through the
I
(10)
welds to the steel plate, and then to the embedded shape.
This is then resisted by bearing on the projecting studs and by bond be- I
tween the embedded shape and the column concrete.
Each of these load transfers establishes the forces to be used in designing the
I
connection. It is obvious that the fewer the number of load transfers, the less chance for
error. Load transfer mechanisms and load transfer devices are discussed in Sections 3.3 I
and 3.4, respectively.
3.2.2 Failure modes I
In a manner similar to following load paths, the connection designer must exa-
mine each possible mode of failure in the connection and its component parts. In some of
I
the simple connections, the critical failure mode will be quite apparent. In others, it is
not as obvious, and the behavior often has only been determined by laboratory testing. I
An example of a component of a connection that has several possible failure
modes occurs when it is necessary to recess the connection
requires what is called a “dapped-end” beam and is illustrated
into the beam depth.
in Fig. 3-7.
This I
I
0
c
%- I
I
I
Fig. 3-7 - Possible failure modes in dnpped+nd beam
I
3.12
I
I
I The PC1 Design Handbook(3*2) lists five potential failure modes which should be
investigated in designing the dapped-end of a beam:
I (1) Flexure (cantilever bending) and axial tension in the extended end.
(2) Diagonal tension emanating from the reentrant corner.
I (3) Direct shear at the junction of the dap and the main body of the member.
(4) Diagonal tension in the extended end.
I
I
I
I Support
I
I
I 3.13
I
In some structures, restraint against torsional rotation in the completed struc- I
ture is only provided by in-situ concrete which is placed after the precast members are in
place. Jn these cases, temporary restraint must be provided during erection. This is I
frequently very difficult and costly to do. It is better if connections are designed which
will make the members torsionally
the final condition.
stable during all phases of construction, as well as in I
In most precast, prestressed concrete structures, it is desirable that permanent
lateral stability be provided by shear walls or cross-bracing, rather than by moment
I
resistant frames. Moment-resisting connections are complex, congested and expensive.
Also, volume change restraint forces build up severely in continuous multi-bay and multi- I
story frames.
Lateral forces are distributed to the stabilizing assemblies through diaphragm I
action of the floor and roof decks. Since the structural frame must be placed before the
decks, temporary stability must be provided and constantly
buildings this may require a detailed
maintained. In multi-story
analysis and careful planning for all construction
I
phases. Sometimes connections are designed which will provide some temporary moment
resistance during erection, and then “released” (by removing bolts, or cutting welds loose)
I
when the permanent
encouraged, because
lateral stability
it is too easy for
assemblies sre in place.
the constructor
This practice
to forget to release
is not
the I
mechanism, and unplanned stresses could result.
I torsional rotation but would yield enough under gravity loads so that substantial negative
moments would not be attracted, even if compression is developed at the bottom.
I 3.2.4.3
allowed
s Stresses can also be relieved if certain portions of the connections
to slip under movements caused by volume changes, or in some cases, earth-
are
I quakes.
Some types of bearing devices are designed to provide slip characteristics. The
most common are thin plastic or hardboard bearing strips used under hollow-core slabs.
I Tetrafluorethylene (TFE - trade name Teflon) bearing devices are also used where very
low friction is desired.
I It is common practice to use slotted holes in clip angles as shown in Fig. 3-10.
When properly placed, this will allow some horizontal slip, but will restrain torsional
I rotation. However, the slot is also used for field adjustment, and all too often the bolt
ends up in the end of the slot, preventing further movement. There is also a tendency for
I workmen to tighten the bolt too much. If the purpose of the slot is to relieve restraint,
erection instructions should be clearly indicated and carefully inspected.
I
I 3.15
I
3.2.5 Expansion joints. The term “expansion joint” is applied to joints which extend
I
completely
dering lateral
through the building, effectively separating it into two structures
The PC1 Design Handbook (3.2) , Sect. 4.3, contains a discus-
movements.
when consi-
I
sion of expansion joints in precast, prestressed structures.
A true “expansion joint” is only required if the movements resulting from tem- I
perature rise are greater than the shortening caused by creep and shrinkage. ln precast,
prestressed concrete
contraction are needed
buildings, this rarely, if ever, happens.
to relieve the strains
Instead, joints that permit
caused by the additive effects of
I
temperature drop, creep, and shrinkage.
There are conflicting opinions regarding the spacing of expansion joints. These
I
joints are frequent sources of problems and often require maintenance, so it is desirable
to have as few expansion joints as possible. I
The National Academy of Science’s publication, “Expansion Joints in
Buildings”(3*10) provides guidelines for determining expansion joint spacing and designing I
the joints. ‘lhe recommendations in that report are based on a study of government
buildings and analytical study of the effects of uniform temperature change on typical I
two-dimensional elastic frames. This study found the need for expansion joints to be a
function of the following parameters (in addition to the length of the building).
1) Framing material (concrete or steel)
I
2)
3)
Configuration of the building-rectangular, L-shaped, T-shaped, etc.
Whether or not the building is heated and/or air conditioned
I
4) The base fixity condition of the columns
5) The relative stiffness against lateral displacement along the length of the I
building.
The above report did not address precast concrete buildings with “soft” connec- I
tions, i.e., those which use bearing pads or other restraint relieving measures discussed
previously. Experience of others has shown that if all or most connections are “soft”, the
distance between joints can be substantially increased over those recommended in Refer-
I
ence 3.10 and 3.2.
I with another. Thus, this report will use unit stresses in the design equations when it is
considered appropriate.
I 3.3.1 Bearing
Nearly all connections of precast, prestressed concrete involve the bearing
I strength of concrete. The AC1 Building Code(3’11) limits the unit design bearing stress
to:
fbu = 0.85 +f;$& (3-l)
I where:
fbu = limiting design bearing stress, psi
I
4 = 0.70
I f; = specified 29 day compressive strength of
concrete, psi (based on cylinder tests)
I
I 3.17
I
= maximum area of the portion of the supporting
I
surface that is geometrically similar to and
concentric with the loaded area, sq in. I
Rese&,(3.1fL, 3.13)
I
has established that bearing failures of plain concrete are
usually characterized by a splitting of the concrete perpendicular to the applied load.
Thus, the limit on bearing stress was determined to be a function of the splitting tensile
I
strength, rather than the compressive strength of concrete. The splitting tensile
strength has, in turn, been established to be a function of the square root of the compres-
I
sive strength.
Further, the AC1 equation does not consider the effects of a tensile force I
perpendicular to the applied load. This was found to substantially reduce the bearing
strength of the member. I
Kriz and Rathsc3’12), in a series of tests on column heads, mostly with lateral
reinforcement, suggested the following equation: I
Nu’vu
fbu = (69a y;, x (1 + C1,&%(Cr/80) (3-2) I
where (See Fig. 3-11):
S = distance from center of load to free edge of member, in.
I
w = width of bearing, in.
Cl = Owhens (2 in.; 2.5 when s? 2 in. I
Avf = area of reinforcement perpendicular to splitting crack, in.
b = length of bearing, in. I
c, = the product of SW,but not more than 9.0, sq in.
I
I
I
I
Fig. 3-U- Bearing on plain concrete
I
3.18
I
I
I N, = factored tensile force parallel to plane of bearing, lb.
I
fbu =
I This equation was also published in the PC1 Design Handbook(3Sz)and has been
used successfully by the precast, prestressed concrete industry in the U. S. since about
I 1971.
References 3.2 and 3.3 also suggests that when the limits prescribed above are
I exceeded, reinforcement can be designed by shear-friction (see Sect. 3.3.2.1).
In a much more comprehensive study, Williams (3.13) compared the results of
I some 15 research studies, including those of Kriz and Raths, and also conducted some
very extensive testing. A plot of all the data from Williams’ tests and the other studies
% -0.47 (3-4)
fbu = 6.92 fct (-)
I %
where:
I f,t = splitting tensile strength of concrete, psi.
ACl(3.11) suggests that when values of fct are not determined from test, the
I quantity 6.7X&A may be substituted for f,,, where i is a coefficient used with light-
weight concrete. Thus a suggested design equation based on Williams data would be:
I fbu
= $45x -f22
l- A1 (3-5)
tion of v%&
The data from Reference 3.13 indicates that if Eq. 3-7 is used, the AC1 limita-
s 2 does not apply. However, because of the limits of values tested, Fq.
I
3-l should be used as an upper limit.
fbu hex) = (0.85 $f;) 2 = 1.2 f;
Thus:
I
(3-S)
I caused by diagonal tension failure. Thus, while classic reinforced concrete design as-
sumes that concrete has no tensile strength, the “shear strength” of concrete is, in fact,
dependent on the tensile strength.
I Most of the formulas that limit shear stress in AC1 318-77(3*11) and other
building codes are derived from the principal stress equation:
I
ft (max) = l/2 ft +Aft/2)2 + v2 (3-9)
I where:
I “punching shear” in concrete members. In connection design, ‘beam shear” is the mech-
anism that transfers loads from flexural members to connections. For full-depth mem-
bers, the shear design procedure is well defined by AC1 318-77 and other building codes.
I For special end conditions, such as the dapped end described in Sect. 3.2.2, special de-
signs are necessary.
I In the codes, fpunching shear” is used in the design of slabs and footings to
describe the shear failure mode of a concentrated load or reaction that bears on the
I lab. AC1 318 limits the l’punching shear” stress on an unreinforced section to 4fi;
The surface area to which this limiting stress is applied has been somewhat arbitrarily
.
I chosen as the perimeter of an area at a distance of d/2 from the load area, times the
effective depth of the slab. (See Fig. 3-12). The British Code(3.18) prescribes a larger
perimeter, but uses a correspondingly lower shear stress. ‘Ihis has been defended, be-
I cause tests have shown that the “punched-out” surface is nearly always considerably
larger than the 45’ failure plane that is the basis for the AC1 definition.
I A phenomenon similar to punching shear occurs in precast concrete connections
when inserts, studs, etc. are subjected to a tension force. Design procedures for these
I items are discussed in Sect. 3.3.4.
I 3.21
I
I
I
I
I
I
I
Fig. 2-12 - Comparison of ACI and British criteria
for pullching shear I
In the 1962 Joint Committee report (3.14) the following statement is made: I
II. .. the goals of a complete understanding and of a fully rational solution to
the problem of computing diagonal tension strength have not been attain- I
ed. In view of these circumstances, it appears necessary at this time to
abandon the classical procedures in favor of a logical, though empirical
approach which takes into account the major variables affecting diagonal
I
tension strength as shown by test results.”
In 1980, the “goal of complete understanding” does not seem to be any closer.
I
Thus, the design of connections which depend on the strength of concrete in shear and
tension to transfer loads should be verified by test data. Unfortunately, well-document-
I
ed test data in this area are scarce.
3.3.2.2 Shear strength of steel
I
The shear yield stress of structural steel has been variously estimated as be-
tween l/2 and 5/8 of the tensile yield stress(3.20). However, the AISC
I
Specification(3*1s) allows a value equal to 2/3 the recommended basic allowable tensile
stress, substantially the same as it has been since the first edition published in 1923.
I
‘This apparent reduction in factor of safety is justified by the minor consequences of
shear yielding and by the effect of strain hardening, as well as the experience of over 50 I
years.
I
3.22
I
I
I Shear strengths of fastening devices, such as bolts and welds, are given in
I Reference 3.19. The design of these fasteners, as they apply to connections of precast,
prestressed concrete structures is discussed in Sect. 3.4.
I 3.3.2.3 Shear-friction
The shear friction hypothesis was introduced by Mast in 1968(321). The con-
I cept provides a rational approach for the design of reinforcement across a plane that is
subjected to shearing forces. This plane can be a crack, (real or potential), or an inter-
face between two materials, such as steel and concrete, or concrete cast on previously
I hardened concrete.
Simply stated, the shear friction concept states that slip along the plane is
I prevented by “friction” in a manner analogous to the classic friction formula:
I F =pN (3-10)
In this case P is the design shear strength, Vn, that can be resisted,u is the shear-fric-
I tion coefficient and N, the “normal force”, is the strength of the reinforcement, Avf,
across the crack. In order for the two surfaces of the interface to part and slip, the rein-
forcement crossing the plane must yield. Substituting AC1 notation into Rq. 3-10, yields:
I
Vn=u A f 3 vU
- (3-11)
I VfY $
I found that for many cases, the amount of reinforcement required to satisfy the equation
was very high, and appeared to add unnecessary costs to precast, prestressed members.
Both Mattock(3’22s 3.44) and Raths(3’23) observed that the shear resistance was a func-
I
I 3.23
I
tion of not only the force in the reinforcement, Av f and the interface condition,u ,
I
fY
but also the area of the interface. For monolithic concrete, Mattock suggested an
approach he called “modified shear friction”, in which:
I
V, = 0.8Avffy + AcrK
where:
o-12)
I
A”f = Area of reinforcement nominally perpendicular to the assumed crack
plane, in2 I
fy = Yield strength of Avf, psi (equal to or less than 60,000 psi)
A cr = area of the crack interface (varies depending on the type of connection) sq
in.
I
K = 400 psi for normal weight concrete, 200 psi for “all lightweight” concrete,
and 250 psi for “sand-lightweight” concrete.
I
In Rq. 3-12, the fit term represents the contribution of friction to shear- I
transfer resistance, and the second represents the contribution of the resistance to
shearing off of protrusions on the crack faces and dowel action of the reinforcement. I
The Raths(3’23) approach was to vary the shear-friction coefficient with the
area of the interface. The Prestressed Concrete Institute Committee on Connection
Details assigned the task of investigating the different approaches to committee member
I
A. P. Shaikh of the University of Wisconsin-Milwaukee.
In his study, Shaikh also included some earlier work by Birkeland (3.24). He I
found the three different approaches to produce almost the same results(3’25) and rec-
ommended, with the concurrence of the PC1 Connection Committee, the Raths “effec- I
tive shear-friction coefficient”, because of its similarity to the by-now established shear
friction method. I
The second edition of the PC1 Design Randbook(3’2) used the Connections
Committee’s recommendations, changing only the form to make them consistent with
AC1 318-77 in terminology. The equations as shown in Ref. 3.2 are reprinted here:
I
where %f = $i+
I
e
$ = 0.85 I
v = Applied factored shear force, parallel to the assumed crack plane, lb
up
1000 i2Acru I
‘e= V (3-13a)
up
I
3.24
I
I
I lbble 3-l - Shear-friction coefficients
Crack interface Recommended Maximum Vup, lb
I condition !J
1 Concrete to concrete,
I cast monolithically
2 Concrete to hardened concrete
1.4 0.30X2 f; AcrS1000X2 A0
When a tensile load is transferred between concrete and a steel device, the
I
steel must be anchored to the concrete.
device-reinforcing bar, stud, bolt, etc.
The method of anchorage depends on the type of
I
Anchorage failures are usually sudden and brittle in nature. It is therefore
usually recommended that anchorage strength be sufficient to force failure of the steel I
connecting device.
concrete.
Reinforcing bars and prestressing strand are usually anchored by bonding to the
Required lengths for anchorage are specified in AC1 318(3’11). Very often,
I
there is insufficient bond length available to anchor the bars, and supplemental mechan-
ical anchorage is required. This can be accomplished by bar hooks or welded cross-bars
I
as shown in Fig. 3-13. Most other types of steel devices depend on mechanical anchor-
age.
I
3.3.4.1 Anchorage of bolts, studs and inserts
Studs and bolts depend on the head to engage a concrete area that causes a
I
cone-type pull-out failure as shown in Fig. 3-14. Similarly, inserts which receive bolts or
I
3.26
I
I
I
I
I
I
I
I Fig. 3-14 - Assumed failure surface for
Fig. 3-13 - Mechtmlcel anchorage of reinforcement headed studs and bolts
I threaded rods employ various types of anchorage devices to try to force this cone type of
failure (Pig. 3-15). The PC1 Design Handbookf3”) and other publications (3.27, 3.28, 3.29)
I show design methods for this type of cone failure that assumes a shearing surface and
applies a unit shearing strength to that surface area.
I In these design methods, it is assumed that the pull-out cone makes an angle of
45’ with the surface of the member, and the unit shearing strength applied Is 4$ Jf;!,
I the same used for punching shear in slabs. This value has apparently been verified by
tests which are cited in references 3.27 through 3.29. In most direct pull-out tests, a
somewhat flatter shear cone has usually been observed, although the ultimate strength
I agrees closely with strength calculated using a 45’ cone and a unit stress 4 q . As in
punching shear, this suggests that a more precise design could be based on the flatter
I shear cone (more surface area) and a lesser unit stress. Nevertheless the presently used
criteria has had good experience for over 10 years.
I
I
I
I
F&3-15-shear-cone
I
I 3.27
I
When embedded steel devices are placed near the edge of a member, or when
I
two or more are used together, and spaced so that the full shear cone cannot develop,
special procedures are necessary for design. In this case, reference 3.2 recommends that I
the shearing surface area be assumed to be a truncated pyramid as shown in Fig. 3-16.
Reference 3.8 cautions that embedded devices in thin members can develop an even I
smaller shearing surface which extends through the member as shown in Fig. 3-1’7.
While these references are illustrated for steel studs, they apply also to other
types of devices that depend on mechanical anchorage.
I
An area that has apparently not been explored is the effect of steel reinforce-
ment passing through the assumed shear surface as shown in Fig. 3-18. It appears that
I
I
I
I
I
I
I
I
I
I
I
I
l’@.3-16-Pull-autsurfaceainstudgroups
I
3.28
I
I
Rd”tCWC-“l
II I
= = = = ,.:::,:: i zzz==
;; <’ ,:
--- Jo...::.
::.. ,i. = zrz==
0
II II F.YIIYle sm.ce
G
TENSION MOMENT
F@. 3-17 - Stud groups in thin sectiorrs Fig. 3-18 - Reinforcement placed
the principles of shear-friction (Sect. 3.3.2.3) apply, but this has not been verified by
I test. Such reinforcement would almost certainly improve ductility.
Studs, inserts and embedded bolts are frequently subjected to shearing forces
some tests on studs have indicated that concrete strength may be more critical (3.30).
I This is particularly so in concrete with strengths below 5000 psi, and when lightweight
aggregate is used. Reference 3.29, based on the data from Reference 3.30 suggests the
I shear strength be limited to:
I
I
I
\ h
I
E&3-lS-Shcxwloadingonastud
I
I 3.29
I
where I
v, =shear strength of the concrete in lbs.
4
Ab =
=0.85
area of the stud, sq in.
I
f;
E, =
= compressive strength of the concrete, psi
modulus of elasticity of the concrete, psi
I
A review of the data from Ref. 3.30 suggests that the following equation could
also be used: I
@Vc= 900 l$A q (3-17) I
where
x =
1.0 for normal weight concrete
I
=
0.85 for sand-lightweight concrete
=
0.75 for all-lightweight concrete
I
When the shear load is in the direction of a free edge, the shear strength of the
concrete becomes more critical. References 3.2 and 3.28 specify the following limita- I
tion:
$V, = 3250 C$(de - 1) J- -f;5000 (3-18) I
Ref. 3.29 recommends that the shear strength calculated from equation (3-16)
be multiplied by the factor:
I
d -1
e (3-19)
I
8dS
I combination
be used:
of shear and tensile force is applied. For desk&an interaction equation can
I (3-21)
I where:
= applied factored tensile and shear forces, respectively
I P”, Vu
@PC, +vc = design tensile and shear strengths, respectively
(based on concrete strength)
I A minor controversy exists over the value of the exponent, K. References 3.3,
I 3.29, and 3.31 use K = 5/3. ln references 3.1, 3.2 and 3.28, K = 4/3. Both are based on
the research at Lehigh University (3.31). Examination of the data indicates that 5/3
I exponent represents more or less average values of test results, while the 4/3 exponent
produces a lower bound curve(3*8).
Note that all of the design equations in this section are based on the limitations
I of the concrete. Design strengths of the various steel devices are given in Section 3.4.
For combined tensile and shear strength, all of the above cited references agree on the
I interaction equation:
I (3-22)
where
I 4%) eVs are the design strengths based on steel capacity
I 3.3.5 Friction
I are threaded into receptacles cast into the concrete (See Sect. 3.4.2, “Inserts”). Occa-
sionally a precast concrete member will be cast with a threaded connector projecting
from the face. This is usually an undesirable practice because such items are vulnerable
I to damage during handling. Also, unless the projection is from the top of the member as
cast, stripping from forms is extremely difficult-impossible with some types of forms.
I The types of threaded connectors that are most commonly used include: 1)
standard bolts; 2) high-strength bolts; 3) threaded steel rods; 4) coil bolts and coil rods.
I Standard bolts as defined here are those meeting ASTM A307. Threads are
“Coarse Thread Series” as specified in ANSI B1.l, and shown in Table 3-3.
I Design of standard bolts is in accordance with the AISC Specifications (3.19),
which requires working stress design using unfactored loads. The allowable stresses are
I connections between structural steel members. They have more than twice the tensile
stress capacity of A307 bolts. Their application requires controlled tensioning of the
fastener to develop sufficient force to prevent slipping of the connected parts. To take
I full advantage of high strength bolts in friction-type connections they must be tightened
using calibrated torque wrenches or load indicating washers.
I Because of creep and minor crushing, it is questionable as to whether a high
strength bolt will hold its tension when tightened against concrete. Thus, high strength
I bolts are used infrequently in precast concrete connections. Some applications and
limitations are shown in Fig. 3-20.
I
I 3.33
Table 3-3 - Screw thread, bolt head and nut standards
I
I
I
I
01 Bolt Width Width Height Width Width Height Width Widfh high,
F
I”.
c
I”.
H
I”.
I
~
716 1 5116
1.1116 1.114 7116 I
1-l/4 l-7116 112
I
I
I
N”, Wi;th Wt$h He;ght WY Wph Height Wl;th Wph t+e$ht Wiph WFh Heip
size
I”. I”. I”. I”. I”. I”.
N
I”. tn. I”. I”. I”. tn. I”. I
I
I
Diameter 1 Ama
I
Th’dn
1%
”
MINtMUM LENGTH OF THREAD ON BOLTS
ANSI 816.2.1 - 1966
I
I
Diameter of Bolt. D, Inches
112 .4w ,196 ,126 ,142 13 Length 01 Bolt
112 516 34 716 I lW4
11
3.4 ,626 ,442 ,302 334 10 To 6 in. Inc. l-l,4 I-112 I.314 2 2-l/4 2414
718
1
516
I.114
.731
,836
507
.Wl
,765
307
,419
,551
,202
,462
.w
,226 1
9
6
over 6 I”. 1.112 ICY4 2 2.114 2.112 3
I
I.064 1.227 ,690 ,969 7
I
3.34
I
I
‘hble 3-4 - Allowable workiw stresses on threaded fasteners
I
I
BOLT AREA STRES: Fy = 36 A 307 A 325F A 325N A 325X
SIZE AREA I I I I I I I I
F, ( F, 1 F, 1 F, 1 Fv 1 F, 1 Fv I F, 1 Fv
I 4
in. I”.’ ill.’
THREAD GROSS
PART AREA
BEAR.
ING
TYPE
GROSS
AREA
THREAC ,
I MA
in.
ALLOWABLE FORCES = kios
-
I l/2”
(0.40)
(I.196 0.142 3.12 4.31 2.1 2.64
I (0.507)
314” I I.4416 0.3345 7.36 9.72 4.6 6.69 13.25
(0.620)
I1
(0.731)
1” ( I.7654 0.6057 13.33 17.26 a.5 12.11 23.56
I (0.636)
1.114”
(1.064)
11.2272 0.9691 21.32 30.00 13.3 19.36 36.62
- - i
I F = Friction
N = Bearing
type connection
type connection with threads included in shear plane
I
I
I
I
I
I
I
I 3.35
I
3.4.1.4 Coil bolts and rods
I
The threads on coil bolts and continuously threaded coil rods are extremely
coarse (Fig. 3-21). They are designed to fit the contour and diameter of the helically
I
wound coil of wire used in some inserts (See Sect. 3.4.2).
Coil bolts were originally designed for use in temporary connections, usually in
I
lifting devices for site cast (tilt-up) or plant cast concrete members. They are ideal for
use in and around concrete, because the thread is not easily clogged or damaged. Coil I
bolts are frequently used in permanent connections in precast, prestressed concrete
construction. The coarse thread allows fast action, and does not require extremely close I
tolerance in placement of the insert. This helps to speed up erection.
Continuously threaded coil rods (Fig. 3-21) are available in lengths up to 10 ft.
They have many useful applications in precast concrete connections. For example, the
I
connection between a cast-in-place slab or topping and a precast beam or wall panel.
One end can be threaded into a coil insert in the precast piece. The threads serve the
I
same function as deformations on reinforcing bars to bond into the cast-in-place con-
crete. This bond development length of coil rods is assumed the same as deformed I
reinforcing bars but this has not been verified by test.
Coil bolts and rods are available from several concrete accessory suppliers, but I
are not covered by standard specifications. Manufacturer’s catalogs give
recommended ultimate and working strengths. References 3.1 and 3.2 have tabulated
typical values, which are shown in Table 3-5. These values are based on static loads.
I
The performance of coarse threaded coil bolts under cyclic loading is suspect.
Experience with bolts used in lifting inserts shows that they wear after several reuses.
I
This may indicate that the bolts could loosen after several repeated load cycles.
I
Table 3-5 - Capacity of Coil Bolts and Threaded Coil Rods
I
Bdt Diameter Min. Coil
Penetration lid
Tensile
Strength IPJ
I Shear
Strength W,)
I I
1
l/2
314
1 l/2
2
2 l/2
13,500
18,470
37,870
8,100
11.080
22,720
I
1 II4 2 l/2 54.960 32.980
1112 3 83.340 50,000
I
I
3.36
I
I
I
I
I
I
I COIL BOLT
I F&.3-5x-coilboltsandcoilrods
I 3.4.2 Inserts
I Cc) “Ferrule” or “Weld nut”. This is for use with standard bolts or rods with
standard threads. The nuts are of sufficient length and proper chemical
composition to be welded to the wires which form the anchoring
I element. Design strengths are shown in Table 3-6.
I
I 3.37
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
(a) Standard coil (b)Tapped coil (c) Weld nut (Ferrule)
I
Fig. 3-23 - Receptacles used in concrete inserts
I
3.38
I
I
I
I -
I
3.39
I
Table 3-6 - Design Strength of Machine Bolts in “Ferrules” or “Weld Nuts”
I
Bolt Dia.,
(in.1 Bolt Grade
Tensile
strength
Shear
strength Femle Data
I
(ASTM) P, (lb.1 V, (lb.1 Threads/in. Bolt Length
l/2
5t8
A307
A307
4820
7680
3330
5220
13
11
1
1-118
I
3t4 A307 11,360 7510 10 l-l/8
1 A307 20.600 13,350 8 l-l/4
I
3.4.2.2 Anchorage of inserts
I
Fig. 3-15 shows typical types of anchorage failures with inserts. The inserts
shown in Fig. 3-24 depend on bond with the concrete for anchorage. Those in Fig. 3-22
depend on mechanical anchorage and a shear cone type failure mechanism as discussed in
I
sect. 3.3.4.
3.4.2.3 Mechanical strength of inserts
I
If the insert is adequately anchored into the concrete, and the anchorage wires I
are properly welded to the receptacle, the strength of the insert is dependent on the
number and strength of wires or the connector capacity. It is most desirable to have the
bolt or the wires govern the connection strength, because they are more predictable and
I
ductile. Strengths of wires typically used in inserts are shown in Table 3-7.
3.4.2.4 Expansion inserts
I
Expansion inserts are devices placed into predrilled holes in hardened
concrete. The anchor develops a tension load-carrying capacity when expanding parts of
I
I
Table 3-7 - Capacity of Round Wire Used in Concrete Inserts
Yield
I
Leg Wire Wire strength,
Dia., in.
0.216
Grade
Cl008
lb
2000
I
0.223 Cl038 3900
0.225
0.240
0.260
Cl038
Cl008
Cl008
3700
2900
3550
I
0.281 Cl035 6000
0.306
0.340
0.375
Cl035
Cl035
Cl008
6900
7500
7450
I
0.440 Cl035 12.000
I
3.40
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I Fig. 3-26 - ‘Qpical expansion inserts
I
I 3.41
I
the insert exert lateral pressure against the sides of the hole. This is usually done by
I
tightening the connector bolt into the insert.
All expansion inserts ere proprietary. Examples are shown in Fig. 3-26. Each I
manufacturer has established the tensile and shear strengths of his devices by testing.
Typical ranges of tensile and shear strengths, taken from manufacturer’s catalogs are I
shown in Table 3-8. At the minimum recommended embedment depth, the tensile ca-
pacity agrees quite well with the “shear cone” concept described in Sect. 3.3.4
(Fig. 3-27). However, because of slip of the anchor in the hole, deeper embedment does
I
not proportionally increase the capacity. The upper limit of the capacity of the devices
is the strength of the connector bolt. Standard bolts (Sect. 3.4.1.1) are usually used as
I
connectors.
Edge distances for expansion inserts are more critical than for cast-in inserts. I
Expanding the insert in the direction of the edge should be avoided (Fig. 3-28). The
minimum edge distance should be at least five times the diameter of the connector bolt. I
The advantage of expansion inserts is that they can be placed in exactly the
right position after the precast members are in place.
measures when cast-in inserts are misplaced or left out.
They are often used as corrective
Proper performance of the
I
inserts is largely dependent on field workmanship. The holes must be drilled straight,
deep enough and the proper diameter. ‘lhe bolts must be tightened to sufficient torque,
I
sometimes requiring pneumatic impact wrenches. For these reasons, most manufacturers
318
1500 - 3600
3200 -6000
1200-3500
2500 -8500
I
Ii2 4200 -11,600 7300 -15,200 I
518 7000 - 19,500 11,000 - 17,000
34.000
-33,000
-40,000
26,000
40,000
-39,000
- 63.000
I
(1) Strengths vary with concrete strength. Concrete strengths range from 3500 to
5500 psi.
I
(2) All values sre at minimum recommended embedment.
I
3.42
I
I
I
I
I
I
I
I
I
I
I Fig. 3-27 - Comparison of expansion bolt manufacturing
streqth with %heer cone” concept
catalog pullout
I recommend that the working strength of the insert not exceed one-fourth of the catalog
ultimate strength values.
I The performance of expansion inserts under stress reversals, vibrations or
earthquake is not sufficiently known. Further research on this aspect is recommended.
I
I
I
I
I
pig. 3-28 - Direction of expansion
I
3.43
I
I
3.4.3 Welded studs I
Stud welding is a semi-automatic process that can be used to weld fasteners of
many sizes and configurations. It is a fast, economical method of anchoring steel plates I
to precast concrete members. The process is described in Fig. 3-29. Most precast co-
ncrete manufacturing
Fig. 3-30.
plants have stud welding capability.
The most common stud configuration
Typical equipment is shown in
used in connections of precast concrete
I
are headed studs (Fig. 3-31) and deformed bar anchors (Fig. 3-32).
I Table 3-S gives standard dimensions of readily available headed studs. The
plate thickness to which the stud is welded should be at least 2/3 of the stud diameter.
I The quality of a stud weld may be evaluated by bending the stud to an angle of
30° from the original axis and striking it with a hammer. If the equipment is not proper-
I ly adjusted, the weld will fracture. This test is performed at the start of the work or
after any change in working conditions.
I
I
I
I
I
I
pip. 3-31- Applications of headed sh&
I
I 3.45
I
table 3-9 - Dimensions of headed studs, in. (mm)
I
I
I
Shank Heed Head Stock lengths’
(Nominal dimensions)
I
diameter diameter thickness
ds
l/4 (6)
dh
l/2 03)
th
3116 (5) 1, 2-l/2,4
(25, 64, 102)
I
3fa (10) 3/4 (19) 9132 (7) 3,4, 6
(76, 102, 152) I
l/Z (13) 1 (25) 5116 (8) 2, 3, 4, 5, 6, a
2,4, 6, a
(51,102,152, 203)
I
3/4 (19) l-114 (32) 3/a (10) 3, 3-l/2, 4, 4-112, 5, 6, 7. a
(76, 89, 102,114,127,152, 178, 2031 I
718 w2) l-3/8 (351 318 w0 3-l/2,4,5,6,7.6
* Other lengt
(89,102,127,152,1’/8,203)
I
I
I
I
I
I
I
I
Fig. 2-22 - AppllcJltions of deformed bar anchors
I
3.46
I
I
I 3.4.3.2 Deformed bar anchors
I Deformed bar anchors (Pig. 3-32) are anchored in the concrete by bond. The
deformations are indentations rather than projections as on reinforcing bars. While they
do not meet the ASTM specifications, tests have shown bond properties to be similar.
I Reference 3.2 suggests the following equation for development length of deformed bar
anchors:
I
I Ed - ";">'y
C
% 12 in. (3-24)
where:
I x
= as defined for Rq. 3-13a
= diameter of bar, in.
I db
fY
d 60,000 psi
for fy greater than 60,000 psi, the above value should be multiplied by:
I 60.000
2- f
I Y
As with reinforcing bars, when the deformed bar anchors are placed with more
than 12 in. of concrete below the bar (top bars), the above ~valuesshould be multiplied
I by 1.4.
Deformed bar anchors are available in diameters of l/4 in. to .5/S in., and
I lengths of 12 in. to 30 in.
3.4.4 Welding
I Loads are frequently transferred within a connection by welding. Welded con-
nections are efficient and performance depends on reliable workmanship and the compat-
I ibility of welding materials with the metals to be joined. Detailed discussion of welding
of connections in precast concrete is given in Ref. 3.3.
I Weld material is specified by an electrode classification number, e.g., E60, E70,
etc. The number represents the minimum ultimate tensile strength, F,, of the electrode,
I in ksi (e.g., E60 electrodes, F, = 60 ksi). The ultimate shearing strength of weld material
is assumed by the American Welding Society to be 0.60 Fu(3’33).
I Full penetration welds such as the V-groove welds shown in Figs. 3-33 and 3-34
transfer loads in direct tension or compression. If the electrodes recommended by the
I American Welding Society(3’32s 3*33) for various steels are used, and the welds are
I 3.47
I
properly made, full penetration welds will be stronger than the base metal, and can be so
I
assumed in design. Fillet welds and others which transfer loads through shear in the weld
must be designed for the actual applied loads.
I
3.4.4.1 Structural steel welding
Welding of steel plates, angles and other shapes should follow AWS D1.1(3*32).
I
Nearly all structural steel used in precast concrete connections is ASTM A-36. Thus it is
readily weldable with standard equipment.
I
Design procedures for structural steel welding have been established with steel
construction in mind, so are based on working stress methods. In precast concrete con-
I
nections, it is often more convenient to use factored loads and strength design proce-
dures. Two publications have suggested values to be used for welds in shear with I
strength (or “load factor”) design: the AWS Reinforcing Steel Welding Code(3’33) and the
AASHTO Bridge Specifications(3’34). In the former the nominal (ultimate) shear strength I
of welds to be used with factored loads is equal to the assumed ultimate shear strength,
0.6Fu. It implies that the capacity reduction factors, 4 , used in reinforced concrete
construction should be applied to this value. In the AASHTO Specification, the nominal
I
shear strength is specified as 0.45Fu, but does not use a $ -factor. Note that the
AASHTO Bridge Specifications allows only 0.2?Fu for working stress design, compared I
with 0.30Fu specified by AISC for building design(3.19). The comparisons are shown
below: I
Allowable
working stress
Allowable
design strength
I
AWS(3.33) 0.3Fu 0.6Fu x $I I
1.70 ( 4, = 0.85)
AASHTO(3.34) 0.27Fu 0.45Fu 1.67 I
For simplicity, it seems reasonable and conservative to assign a constant value
of 1.67 times the allowable working stress to the design strength, as is done in the
I
AASHTO Bridge Specifications. This is the basis of Table 3-10.
In welded connections, combined tensile and shear loadings are frequently
I
encountered. Design procedures using working stresses are given in the AISC Steel
Manual(3’35). By using the values in Table 3-10, these procedures can also be used for I
strength design.
I
3.48
I
I
I Various types of welds are shown in Fig. 3-33. The most commonly used are
I Electrode Allowable
Working Stress (ksi)
Designc2)
Strength (ksi)
I I E60 18 I 30
I E80 24 40
I E90
El00
27
30
45
50
I Based on AISC Spec. for buildings. For bridges, use 90% of values.
Use factored loads and @ = 1 .O with these values.
I
I
I
I
I
l/2 6.36 10.61 7.42 12.37
I 9/16 7.16 11.93 8.35 13.92
I 518
(1)
7.95 13.26
I
I SingleV-groove weld
118”
Double-V-groove weld
I Full penetration welds
I
I
Fillet welds
I
-
t, = d,/5
d
I
I
I Flare-V-groove welds
I
I
I
I
I Flare-bevel-groove welds
I 3.51
I
?
Table 3-12 - Size of fillet weM required to develop full strength of bar I
I I 1
I
Bar perpendicular to plate,
welded one side
I
Plate fy = 36 ksi I
I
Bar
Gr. 40 bar, E 70 Electrode
Nominal weld Min Plate
Gr. 60 bar, E90 Electrode
Nommal weld Mm plate
I
size size in. I thickness, in. size, in. thickness, in.
where
I
fW = unit design strength from Table 3-10
= length of weld (Fig. 3-34)
I
ft.4
tW
= thickness of weld (Fig. 3-34)
Tables 3-12 through 3-15 show welding required to develop the full strength of I
reinforcing bars.
I
3.52
I
I
I Table 3-13 - Siie of fillet weld required to develop full strength of bar
I Plate fy = 36 ksi
I
I I Gr. 40 bar, E 70 Elec~trode I Gr. 60 bar, E90 Electrode
BW Nominal weld Min Plate Nominal weld Min plate
size size in. thickness, in. size, in. thickness, in.
I 3 I/8 5/16 118 3/a
I 4
511/S
118
1
5/16
5116 I
l/8
3/16 I
318
l/2
I 9
10
l/4
l/4
9/16
9/16
l/4
5116
11/16
718
bl
12
\ #3
2.5
#4
3.3
#5
4.1
#6 #7 #a #9 #lO #ll
I
7.7
3.3 4.4 5.5
I
-
-. 4.1 5.5 6.9 ::: a.2
4.9 6.6 a.2 9.9 Il.2 Ia.Y
9.6 f 11.5 13.5 1 15.4 1 ;;:i 1 19.6 1
11.0
I
-It Grade 60 Reinforcing bars; E90 weld electrodes
I
I
#5 #6 #7 #a #9 #lO #11
I
5.3
7.1
6.4
a.5 9.9
I
a.8 10.6 12.4 14.1
10.6
12.4
14.1
12.7
14.8
17.0
14 .a
17.3
19.8
17.0
19.8
22.6
19.1
22.3
25.5
25.1
28.7 31.9
I
19.1 22.3 25.5 28.8 32.4 36.0
I
I
I
3.54
I
I
I Table 3-15 - Minimum length of weld to develop full strength of bar.
Weld parallel to bar length.
I
I
I
I Gr. 40 bar, E70 Electrode
Min Plate
Gr. 60 bar,
Minimum weld
E90 Electrode
Min plate
Bar Minimum weld
I size
3
length, in.
718
thickness, in.
3/16
length, in. thickness, in.
3116
4 l-1/8 3116 1-',,8 l/4
I 5
6
l-l/Z
l-314
/
:,;6 l-314
2f3,8
5/16
318
7 2 5/16 'i/16
I 8
9
10
2-114
2-5/a
2-718
3/8
7116
7116
2-518
3&
:,i/
9/16
devices are based on test data. Some are recommended for compression splices only,
I while others can be used for tension splices. Design should be based on the manufac-
turer’s recommendations. AC1 318(3*11) requires mechanical couplers to be capable of
I cally and used only for alignment, or to resist horizontal loads from wind or earthquake.
Thus anchorage is normally not a problem.
Occasionally, a dowel will be required to resist tension. In this case, the bar
I must be sufficiently embedded to develop its design strength. However, the bond of the
grout to the concrete may be more critical. Tests(3.38) have shown that ordinary sand-
I cement grout in drilled holes is unreliable under direct tension loads. Anderson(3’3g)
reported on pull-out tests of dowels in holes which were preformed using a flexible
I
I 3.55
I
I
I
I
I
I
I
I
I
I
I
I
Fig. 3-35 - Proprietary mechanical couplers
metallic conduit (the type used for post-tensioning conduit). With bars up to #8, the full
I
strength of the bar was developed.
3.4.7 Post-tensioning steel
I
Post-tensioning is often used in connections when high ultimate tensile strength I
is desired, for example, in moment connections. Either ‘I-wire strands meeting ASTM
A416(3’40) or bars meeting ASTM A722(3*41) are used. The ultimate strength of strand is
either 250,000 or 270,000 psi. The ultimate strength of bars ranges from 145,000 to
I
160,000 psi.
In order to reliably measure the prestressing force, the tendon must be at least
I
15 or 20 ft long. Thus the prestressing feature of post-tensioned connections is normally
I
3.56
I
I
I only relied upon when long continuous tendons can be employed. Examples of this use
include vertical continuous post tensioning of columns and bearing walls and continuous
I frames in which the tendons also serve as all or part of the flexural reinforcement in the
beams. When shorter tendons are used, the primary value is in the high ultimate strength
I and ductility provided.
3.4.8 Pads ahd other bearing devices
I Bearing pads are used to distribute vertical loads over the bearing area. Some
types of pads also reduce force build-up at the connection by permitting small displace-
I ments and rotations. Their use is encouraged wherever applicable.
The performance of most bearing pads is a function of their deformation char-
I acteristics under service loads. Hence, these pads are designed using unfactored (ser-
vice) loads.
I There are a number of suitable materials and combinations of materials that
can be used for bearing pads. A few are described below with some design recommenda-
I tions. In some cases, various grades of bearing pads can satisfy these descriptions, but
exhibit widely different properties and behavior.
1. Commercial grade elastomeric (neoprene) pads are readily available and inex-
I pensive. However, these pads exhibit wide variations in shear deformation
characteristics and bearing strength, so they should not be used unless satisfac-
I 2.
tory performance test data is available.
Structural grade neoprene pads are those which meet the requirements of
I Section 25, Division 2 of the AASHTO Bridge Specifications (3.34). For optimum
economy, their use should be limited to places where uniform bearing is impor-
I 3. Laminated fabric bearing pads composed of multiple layers of 8-oz cotton duck
with a high quality natural rubber binder can sustain unfactored compressive
stresses up to 2000 psi. They are designed in a manner similar to elastomeric
I
3.57
I
I
pads except the shape factor need not be considered. These pads do not deform
I
as readily as elastomeric pads, so do not provide the same stress reducing
characteristics. The shear modulus, G, may be assumed to be 550 psi, unless I
more specific data is available.
4. Preformed pads composed of synthetic fibers and a rubber body are designed as
in (3) above, except that unfactored compression should be limited to 1500 psi.
I
The shear modulus can be assumed equal to 525 - 4v/3 unless more specific data
I
I
I
I
I
I
I
I
I
I
I
I
I
Fig. 3-36 - Design of structural gnde elastomeric beer- peds
I
3.58
I
I
I is available (v - unit unfactored shear stress). This type pad should meet the
requirement of Section 2.10.3 (L) of the AASHTO Bridge Specification (3.34).
I 5. Tetrafluorethylene (TFE) bearing pads reduce horizontal stresses because of
their low coefficients of friction. The unfactored bearing stress should not
I exceed 1000 psi when unreinforced or 2000 psi when reinforced with glass fibers
or similar material. TFE pads are sometimes used in combination with elast-
I Tempered hardboard strips are also used with slabs to prevent concrete to
concrete bearing.
I used in connections. Very often, connection areas will be heavily congested with rein-
forcement, so it is advisable to use small coarse aggregate, and to design concrete mixes
for relatively high slump.
I 3.4.10 Grout
I Many connections require the use of grout. Sometimes this grout is required
only for fire or corrosion protection, or for cosmetics. Other times, it is required to
I
3.59
I
I
in the field, or cast into the precast member. They are used within connections that are
I
heavily congested but not confined thus requiring some formwork. When such grouts are
used, the water-cement ratio is usually about 0.50. This is a relatively high value, result- I
ing in low strength and high shrinkage. These mortars also exhibit a tendency for the
solids to settle, leaving a layer of water on the top. Special ingredients or treatments I
can improve these characteristics, but add to the cost.
When very small spaces in confined areas are to be grouted, they are some-
times pumped or pressure injected. The confinement must be of sufficient strength to
I
resist the pressure. Rxamples are ducts for post-tensioning tendons or dowels. Some-
what less water is used than in flowable grouts, hence there is less shrinkage and higher
I
strength.
“Dry pack” is the common name used for very stiff sand-cement mixes. They I
are used when forming or other confinement is impractical, for example under column
base plates. Compaction is attained by hand tamping, using a rod or stick. I
3.4.10.2 Non-shrink grout
The shrinkage of sand-cement grout can be reduced-or compensated for-by
I
using proprietary non-shrink mixes, or by adding aluminum powder to the mix. Charac-
teristics and methods of testing non-shrink grouts are given by a Corps of Engineers I
specification(3’53).
Non-shrink grouts are designed to expand sufficiently during initial hardening I
and curing to offset subsequent shrinkage of the grout. Reference 3.53 classifies non-
shrink grouts by the method this expansion is accomplished.
1. Gas-liberating
I
2. Metal-oxidizing
3. Gypsum-forming
I
4. Expansive cement.
Some expansive ingredients may cause undesireable effects in some applica- I
tions, so manufacturer’s recommendations should be followed.
Proprietary grouts are prepared mixtures of cement, fine aggregate and the I
expansive ingredient. Aluminum powder added to ordinary sand-cement grout forms a
gas-liberating type of mixture. Extremely small amounts of aluminum powder are re-
quired - 50 to 60 millionths of the weight of cement used - about a teaspoonful per bag
I
of cement. ‘Ihe performance of the aluminum powder mixes are thus very sensitive and
not always predictable. Trial mixes should always be made with the particular cement
I
and sand that are to be used in the aluminum powder mixes.
I
3.60
I
I
I 3.4.10.3 Epoxy grouts
I aggregate-resin ratio, thus it is more economical. It is also easier to mix, place and
clean up, and has a coefficient of thermal expansion that is more compatible, although
still about twice that of concrete.
I 3.4.11 Epoxy Resins
I
I 3.61
I
Epoxies are often suggested, but seldom used in precast concrete connections,
I
except for grouting anchor bolts or dowels into pre-drilled holes. They have also been
used for repair or modification of connections in the field. I
Several types of connections suggest the application of epoxy bonding com-
pounds. For example, a precast corbel could be attached to a precast column. The I
strength and ductility are questionable, however, and additional research is suggested.
3.5 Special Designs I
The special connection elements described in this section have become stan-
dard in the industry. They usually involve combinations of load transfer mechanisms and I
devices. ‘Ibe design procedures have been developed from tests and analysis.
3.5.1 Reinforced concrete corbels I
One of the most common elements in beam-to+olumn connections is the
reinforced concrete corbel (sometimes called a bracket” or “haunch% Corbels have I
been extensively researched(3.43-3.451. The first major research work was done by Kriz
and Raths at the Portland Cement Association (3s43). A total of 195 corbels were tested, I
of which 124 were subjected to vertical load only and 71 to combined vertical and hori-
zontal load. This research resulted in the empirical design equation: I
(l/3 + 0.4Nu/Vu’
wn = 6.5bd 2/T (1 - 0.5d’a) (‘Ooo p)o.8N ,v
10 u” I
(3.27) I
This equation appeared in the PC1 Manual for Design of Connections (3.11 and in
the fist edition of the PC1 Design Handbook, along with design aids to assist in solving
I
it.
Equation 3-27 was approximated and simplified for inclusion in the 1971 ver- I
sion of the AC1 Building Code as Rq. 3-28 and was retained in the 1977 Code(“%
I The other major research on reinforced concrete corbels was done at the
University of Washington under the direction of Prof. Alan II. Mattock(3.44s3-45). Tnis
study included the testing of 28 corbel specimens, plus a review of the Kriz-Raths data.
I Mattock showed that the strength of a reinforced concrete corbel could be safely pre-
dicted by considering @-seFig. 3-37):
I (1) a moment equal to Vua + N,(h - d)
(2) a simultaneous horizontal tensile force, N,
I (3) shear resisted by shear friction as discussed in Sect. 3.3.2.3.
This approach resulted in the design equations suggested in the second edition
I of the PC1 Design Handbook(3’z). Referring to Fig. 3-3’7, the main tensile reinforcement,
As + An, is the greater of that determined by Rqs. 3-29 and 3-30:
I (3-29)
I (3-30)
I
I
I
I
I
I
I
I
concrete corbels
I Fig. 3-37 - Dfsign of
I 3.63
I
vu I
A (3-31)
vh = q
In these equations:
I
$
fy
=
=
0.85
yield strength of As + An
I
fyv
‘k
=
=
yield strength of Avh
effective shear-friction coefficient, as calculated in I
Sect. 3.3.2.3
vu = applied factored vertical force, limited to values shown in I
Table 3-l.
A review of reference 3.44 indicates that Bq. 3-31 misinterpreted the Mattock
and Kriz-Raths reports. The recommendations were that Avh should be equal to 0.5 A,,
I
regardless of whether the moment or shear-friction steel requirements are critical.
Thus, when used with Eqs. 3-29 and 3-30, a more proper equation would be:
I
Avh = 0.5
1
‘As + A,,’ - Nu/f Y (3-31a) I
This steel is provided to prevent a premature diagonal tension failure. I
Reference 3.2 also requires that:
(11 The minimum reinforcement requirements of Sect. 3.3.2.3 should be met.
(21 The horizontal reinforcement, Avh, should be distributed over a depth of
I
d/2 from the flexural reinforcement, A,.
(31 All reinforcement should be adequately anchored by welding, hooks, or
I
development length.
The above design approach is being considered for inclusion in future versions I
of the AC1 Building Code.
3.5.2 Structural steel haunches
I
Structural steel is often embedded in a precast concrete column or wall panel
to serve as a haunch or corbel. Numerous examples are shown in Part 4. They are often
I
easier and less expensive to fabricate than reinforced concrete corbels, and can be
designed to be stronger and more ductile. I
Design procedures are given in the PC1 Design IIandbook(3’2), based on a paper
by Raths(3’46). The method is a conservative approach, based on statical analysis, with I
the approximate assumptions shown in Fig. 3-38.
I
3.64
I
I
I
I
I
I
I Fig. 3-38 - Assumptions used in design of embedded
steel haunch by Reference 3.2
0.85f; bke
(3-32)
I “c = 3.67 + 4a/Re
I b
The effective
= effective width of the compression block (See Fig. 3-39)
width of the compression block for double flanged members are
assumed as shown in Fig. 3-39(a), provided steps are taken to assure good compaction of
I
I -?-l-
1 \
z
- Reinforcement
welded to tube
I I--i
L
‘b=2w’
I
I
I
I
Fig. 3-39 - Effective width of embedded
I
I 3.65
I
the concrete and/or confinement of the concrete around the section. Holes in the em-
I
bedded part of the member (more than 1 in. diameter) aid compaction.
It should be noted that there must be adequate concrete and/or superimposed I
axial dead load above and below the haunch to develop the compressive forces indicated
in Fig. 3-39 in order for Eq. 3-32 to be valid. If not, it may be possible to develop the I
force couple by using reinforcing bars in tension, in a manner similar to that shown
below. I
Additional capacity can be obtained by welding vertical reinforcing bars to the
steel section, as shown in Fig. 3-39(b). The additional capacity is calculated by conserva-
tively assuming that the reinforcement acts at the centers of compression, and that
I
reinforcement nearest to the applied load is balanced by reinforcement near the end of
the steel member. Thus:
I
3 Asf
v, = 3.67 + 4a/g,, (3-33) I
As (12a + 2k,)
I
A;; = (3-34)
12a + llf,,
where:
I
vr = additional nominal strength of the section provided by rein-
forcement
I
A, = area of vertical reinforcement nearest to the applied load
(assumed to be located at a,/6 from face) I
A; = area of vertical reinforcement near the end of the steel
section I
(assumed to be located at 11 9.,/12 from face)
fy = yield strength of the reinforcement I
The total design strength of the section is thus:
lpn = L$‘vc + Vr’ (3-35)
I
r$ = 0.85 I
The design strength of the steel section can be determined by:
Flexural design strength: I
I
3.66
I
I
I
0” 2% (3-36)
I n a
I +V, = @CO.55fy h w)
where:
(3-37)
I z,
fy
=
=
plastic section modulus of the steel section (see Table 3-16)
yield strength of the steel
I h,w
$ =
= depth and thickness of steel web, respectively
0.90
I Note: Plastic design criteria for structural steel does not require the use of
a +-factor . However, the load factors used are 1.7 (D + L). Therefore, when using
I steel plastic design with concrete load factors (1.4 D + 1.7 L), the use of $ = 0.90 is
recommended by the PC1 Connections Committee in order to provide approximately the
I same overall factor of safety.
For steel shapes projecting equally from each side of the member, with ap-
I proximately symmetrical loading, the design strength on each side as governed by the
capacity of the concrete can be calculated by:
I 0.85 ff bt,
bv, = 4 3 (3-38)
I Horizontal forces, Nut are resisted by bond on the perimeter of the section. If
the bond stress resulting from factored loads exceeds 250 psi, headed studs or reinforcing
I bars can be welded to the section.
In a study by Marcakis and Mitchell(3’47) the approximations of Fig. 3-38 were
I refined using the accepted strain and stress distribution assumptions in Fig. 3-40. The
resulting equations, listed below, were verified by testing 25 specimens.
I 0.85 f; b’l,
‘c = 1 + 3.6e/!le
(3-39)
I
I
I 3.67
Table 3-16 - Plastic section moduli and shape factors
1.12 Lapprox)
E 1.70
6
bh'
h 12 2
@ b
2As f
(3-40)
6e/xe
’ + 4.8s/Le - 1
3.68
I
I
I
I
I
I IdPure sll*ar (b)Pura
I (1) In a column with closely spaced ties above and below the haunch, the
effective width, b, can be assumed as the width of the confined region, or
2.5 times the width of the steel section, whichever is less.
I (2) For thin-walled members, such as the tube shown in Fig. 3-41, the inside
should be filled with concrete to prevent local buckling.
I (3) When the supplemental reinforcement, As and A; is anchored both above
and below the members, as in Fig. 3-41, it can be counted twice.
I (4) The critical section for bending of the steel member is located a distance
V,,/(O.SS f;? b) in from the face of the column.
I
I
I
I
I
I
Fig. 3-41 - Assumptions used in design of embedded steel haunch by Ref. 3.47
I
I 3.69
I
It can be seen that if the steel section projects from both sides, with equal
I
load on each side as in Fig. 3-40(a), Eqs. 3-39 and 3-40 are still applicable, with ae =
column width and e = 0. Because of the chance of unbalanced loads, a minimum eccen- I
tricity should be used. If a minimum value of e/!Ze = 0.5 is used, Eq. 3-39 becomes very
close to the PC1equation (Fq. 3-38). I
Further comparison of the PC1 Handbook equations (Eqs. 3-32 through 3-34)
with the comparable Marcakis and Mitchell recommendations @.q. 3-39 and 3-40) show
reasonable agreement when similar assumptions of embedment and reinforcement place-
I
ment are used. The PC1 equations are generally more conservative.
Using recommendation (4) above, the flexural design of the steel section would
I
be:
$Zsf
I
$‘n = a + VU’( O.i5f;bI
I schematically in Fig. 3-42(a). The forces for which this reinforcement is designed can be
determined by considering the simple truss analogy shown in Fig. 3-42(b), plus reinforcing
I for the axial tension, N,. It can be seen that the most critical reinforcement is the
horizontal bars A, + An, and the vertical ‘hanger” bars Ash. However, the tests showed
I that when these two possible failure modes are adequately covered, other modes develop
as discussed in Section 3.2.2.
I The following equations are from the PC1 Design Handbook, modified as indi-
cated by more recent data. The failure modes investigated are as shown in Fig. 3-7.
I reinforcement must resist the direct axial tension and the small moment caused by the
horizontal reinforcement being placed eccentrically to the applied axial force, N,. Thus:
I As =
Vua + Nu (h - d)
Qfy j,,d
(3-42)
I NU
(3-43)
An = r
Y
I
I 3.71
I
where:
I
4
a
=
=
0.90
shear span, in. I
h = depth of the member above the dap, in.
d = distance from top to center of the reinforcement, A,, in. I
fy = yield strength of the flexural reinforcement, psi
JU
= distance from the centroid of the compression block to center
of (As + A,,,
I
The PC1 Design Handbook
equating $ ju = 0.85 in order to simplify calculations.
uses a conservative approximation
When this is done, Rq. 3-42 and 3-
of
I
43 can be combined and simplified to:
I
(3-44)
I
The Handbook illustrations show the shear span, a, measured from the point of
load to the end of the deep portion
measured to the centroid
of the beam.
of the hanger reinforcement,
Reference 3-9 required that it be
Ash. Examination of Fig. 3-42(b)
I
shows the latter
condition
assumption to be correct. (Note: The Handbook approximated
by suggesting the load be assumed at 3/4 of the extended end, and specified the
this
I
hanger reinforcement
beam.)
start at a maximum of l-l/Z in. from the end of the full depth
I
3.5.3.2 Tensile Cracking at the Reentrant Corner
A tensile crack will emanate from the reentrant corner of a dapped-end beam
I
at a very low load. The Raths test, some of which were conducted on unreinforced
members, showed that this crack starts at a principal tensile stress of about 4fic for
I
normal weight concrete. Once the crack starts, the failure is very sudden and brittle in
an unreinforced member. The limited number of sand-lightweight specimens tested by I
Raths failed at a principal tensile stress of about 2.75 .&, and were less predictable.
The principal tensile stress is calculated by: I
(3-45) I
where:
fp = principal tensile stress, psi
I
I
3.72
I
I
I ft
= flexural tensile stress plus axial tension
I = Va + M/2
bh2/6
N 6Va
+i3i=b7;z+ni
4N
I v =
=
vertical load, lb
N axial load, lb
V
I f,
a
=
=
shear stress = m, psi
shear span, measured from point of load to reentrant corner,
I b =
in.
member width, in.
h = depth of the extended end, in.
I Because of the brittleness of the failure the unpredictability of other para-
meters (such as load placement and magnitude of axial load), and the possibility of cracks
I developing during handling, the concrete tensile strength should not be relied upon in
narrow members such as beams and joists.
I Thus in dapped-end beams the hanger reinforcement, Ash, must take the total
vertical shear:
I where
$ = 0.85
I vu = applied factored load, lb
Ash = vertical bars across potential re-entrant corner crack, sq in.
I fy = yield strength of Ash, psi
3.5.3.3 Direct Shear at the Extended End
I This reinforcement is determined by shear friction. The requirements are not
additive to the flexure requirements above. The PC1 Design Handbook recommends that
I 2/3 of the shear-friction steel requirements be supplied at the bottom of the extended
end (As in Fig. 3-42a), and l/3 be distributed in the bottom 2/3 of the extended end (AVh
I in Fig. 3-42a). The design equations then become:
2vu Nu (3-47)
I ‘s’ An = 3q +q
I Mattock-Chan specimens, the horizontal bars had more positive anchorage and were
better distributed. They also had perimeter “framing bars” which were not included in
the design. In the Raths specimens, the low placement of the Avh bars and the load
I placement permitted the cracks to bypass the bars and proceed uninterrupted to the load
point. While the Mattock-Chan tests did not indicate a need for the vertical reinforce-
I ment, their report recommended such reinforcement be used if the ratio of a/d exceeds
one.
I 3.5.3.5 Diagonal Cracking in the Undapped Portion
In the Mattock-Ghan tests, another possible failure mode was observed, diago-
I nal cracking in the lower part of the undapped portion. These cracks assumed an angle of
approximately 45O. To reinforce against this possible failure mode, the report recom-
I mends that the primary horizontal reinforcement be extended a full development length
beyond this potential crack (see Fig. 3-42a).
I 3.5.3.6 Bearing in the Extended End
As in all connections, the bearing should be checked as discussed in
I Section 3.3.1. Normally, the reinforcement required for the other failure modes will be
adequate to confine the bearing area.
I 3.5.3.7 Detailing Considerations
Anchorage of reinforcement in dapped-end connections is very important.
I Examination of the Mattock-Chan and the Raths tests suggest the following detailing
recommendations (see Fig. 3-44).
I 1. ‘lhe main reinforcement, As + An, should be positively anchored at the end
of the beam. Welding to a plate or confinement angle at the end of the
I beam is recommended.
2. ‘lhe hanger bars, Ash, should be placed as close to the end of the full-
I
I 3.75
I
I
I
-z-4+3 ClW.d sllrrupl
I
I
I
I
I
I
2-n3,3-t3 or Z-*0
I
I
I
0 Mattock-than teata
I
I
I
I Fig. 3-44 - Reinforcement for Dapped-lhd
I 4. The horizontal bars, As + A,, should extend into the beam a distance equal
to (H -d + kd ) past the end of the beam, where H is the depth of the
I undapped portion. This assures that the bars will be developed beyond a
45’ crack which starts from the bottom corner of the undapped portion.
Note that in most applications, the As + An and the Avh bars will be more
I than 12 in. above the bottom of the beam. Thus they are classified as “top
bars” by the AC1 Code13’11), and increased development length,Ild , is
I required.
In addition to the above, the PC1 Design Handbook recommends that the depth
I of the extended end should be at least one-half the full depth of the member. If a great-
er dap is required, hanger connections of the type discussed in Section 3.5.4 are recom-
I mended.
3.5.3.8 Alternate Placement of Reinforcement
I In some applications, the primary reinforcement is placed diagonally as shown
schematically in Fig. 45(a). In this case the forces are resolved as shown in Fig. 45(b).
I The reinforcement requirements are thus:
VuLF-Z
I Ash = I# fy“U cosa z
4 fy d
I (3-54)
I
3.77
I
I
I
I
I
I
I
(a) sehemetic of reinforcement 0 Force resisti system for verticel reaction
I
Fig. 3-45 - Alternate design for dapped-ends
The shear-friction (Sect. 3.5.3.3) and bearing requirements (Sect. 3.5.3.6) must
I
also be satisfied.
Anchorage of the bars is, again, very important, It is sometimes difficult to
I
get proper anchorage of the diagonal bars, Ash, especially in the extended end. Careful
consideration of bend radii, hook diameters and other details is necessary. Welding to I
cross bars or confinement angles may be required.
3.5.4 Hanger Connections I
Hangers are similar to dapped ends, except that the extended, or bearing end is
steel instead of concrete. They are used when it is desired to keep the structural depth
I
very shallow. Hangers are exceptionally stable during erection.
3.5.4.1 Cazaly Hangers
I
The basic Cazaly hanger, developed by Lawrence Cazaly of Ontario, Canada,
has three basic components (Fig. 3-46ah
I
1. A cantilevered bar which supports the unit containing the hanger. The bar
is kept in equilibrium by pressure from the concrete at its interior end and I
by tension in the strap.
2. A strap which transfers the vertical load to the bottom of the unit. (In I
prestressed members it also serves as anchorage zone reinforcement.)
3. Dowels.
Design assumptions and recommendations for Cazaly hangers are given in the
I
I
3.16
I
I
I
I
I
I (a) Basic components cb) Designasumptions
Fig.3-46-cazalyhanger
I Canadian Prestressed Concrete Institute (CPCI) Handbook(3’4g) as follows (see
Pip. 3-46b).
I 1. The cantilevered bar is usually proportioned so that the interior reaction
from the concrete is 0.33 Vu. The hanger strap should then be proportion-
I ed to yield under a tension of 1.33 Vu
I (3-55)
where:
I fy
4
=
=
yield strength of the strap material
0.90
I When the strap yields, it applies a uniform load to the bar. The point of
zero shear is then 0.75s from the front face.
3. Vu may be assumed to be applied 0.5 in. from the face of the seat. The
I remaining part of the moment arm is the width of the joint, g. It is there-
fore important that the joint width used in analysis is not exceeded in the
I field.
4. ‘lhe moment in the cantilevered bar is then given by:
I I$ = Vu (0.5 + g + 0.375s) = 0 fy bd2/6 (3-56)
where
I fy = yield strength of the bar material
0.90
0 =
I Other notation as shown in Fig. 3-46b.
If the bar is proportioned to take this moment at the yield stress, but
I using elastic section properties, the shear and tensile forces can usually be
neglected.
5. ‘lhe bearing pressure creating the interior reaction may be assumed to be
I
I 3.79
I
T,. The bearing length Qb is then given by:
I
I
The exterior cantilever should have a minimum length of (g + 1) in. Most I
hangers in practice have cantilever lengths of 2-l/2 to 3-l/2 in.
6. TO maintain the conditions
must have a length:
of equilibrium assumed, the interior cantilever I
7.
(1.5 + 3g + s + O.!iQb) in.
The minimum total length of bar is then:
I
8.
(2.5 + 4g + 2s + 0.5Qb) in.
The weld connecting the strap to the cantilevered bar should be designed I
to a higher factor of safety than the rest of the strap. A weld throat
stress (at the hanger design load) of 20 ksi, based on the gross length of I
weld (ignoring end effects) has proved satisfactory.
9. Longitudinal dowels, An, should be welded to the cantilevered
transmit the axial force, NU:
bar to I
An = q
NU
(3-57)
I
where I
fy = yield strength of the dowel
$ = 0.90 I
In a series of 52 tests performed at the University of Toronto (3.50) , it was
found that nearly all failures were a result of shearing of the concrete at the inside edge
of the strap (see Fig. 3-46b). A review of the test data indicates that the lower dowel
I
and the area confined witbin~the strap can be conservatively proportioned using effective
shear-friction described in Sect. 3.3.2.3:
I
I
where I
$ = 0.85
fy = yield strength of lower dowels, psi I
I
3.80
I
I
I 1400 X2 bh
ue= v
I U
I
I
I
I
I
I 3.81
I
I
Ash v” (3-60)
= Bfys cosa
I
where
@
fys
=
=
0.85
yield strength of Ash
I
N”
A, = “f;l (I + dh--a$ (3-61)
I
where
I
4 = 0.90
fy = yield strength of An I
The steel bar is proportioned so that the bearing strength of the concrete is
not exceeded, and to provide sufficient weld length to develop the diagonal bars. Bearing I
strength is discussed in Sect. 3.3.1. thus, from Eqs. 3-5 and 3-8, and referring to
Fig. 3-47a: I
fbu = 4 45 x
(3-62) I
where
$ = 0.70
I
x = 1.0 for normal weight concrete
= 0.85 for sand-lightweight concrete I
= 0.75 for all lightweight concrete
b2 = member width I
bl = width of the steel bar
The connection should be detailed so that the reaction, the center of compres-
sion and the center of the diagonal bars meet at a common point, as shown in Fig. 3-47.
I
The compressive force, C, is assumed to act at a distance a/2 from the top of the bearing
plate. Thus:
I
(3-63) I
where
Nu (h - d)
(3-64)
I
C = Vu tsna + d - a/2
I
3.82
I
I
I For most designs, the horizontal bars, An, are placed very close to the plane of
I bearing. Thus the term (h - d) can be assumed equal to zero, simplifying Pqs. 3-61 and 3-
64.
In the Loov tests(3’51) specimens in which beam shear was designed in accord-
I ance with ACI-318(3’1’), shear failure occurred before full capacity of the section was
reached and at loads significantly below the calculated ultimate. Thus, Loov recom-
I mended that stirrups in the beam end be designed to carry the total shear.
3.5.4.3 Variations
I Several variations of the Cazaly and Loov hangers have been used
successfully. Some of these variations are shown in Part 4.
I
I
I
I
I
I
I
I
I
I
I
I
I 3.83
I
RRFRRRNCES - PART 3
I
3.1 “PC1 Manual on Design of Connections for Precast, Prestressed Concrete”, First
I
3.2
Edition, 1973, Prestressed Concrete Institute, Chicago, IL.
3.3 “PC1 Manual for Structural Design of Architectural Precast Concrete”, First I
Edition, 1977. Prestressed Concrete Institute, Chicago, IL.
3.4 “Connection Details for Precast, Prestressed Concrete” by the Australian Pre-
stressed Concrete Group. Published by Cement and Concrete Association of
I
Australia about 1965.
3.13
Bulletin D73.
Williams, A., “The Bearing Capacity of Concrete Loaded over a Limited Area”,
I
3.14
Technical Report 526, (Aug, 19791, Cement and Concrete Association, London.
ACI-ASCE Committee 326 (now 426), “Shear and Diagonal Tension”, AC1 Journal,
I
v. 59, no. 1, Jan, 1962, and no. 3, Mar, 1962.
I
3.84
I
I
I 3.15 AC1 ASCE Committee 426, “‘lhe Shear Strength of Reinforced Concrete
Members”, Chapter 1-4, Proceedings, ASCE, v. 99, no. ST6, June, 1973; Chapter 5,
I Proceedings, ASCE, v. 100, no. ST8, August, 1974.
3.16 “Shear in Reinforced Concrete”, vols. 1 and 2, AC1 Publication SP-42, American
I 3.17
Concrete Institute, Detroit, MI.
3.24 Birkeland, H. W., Class Notes for Course on “Precast and Prestressed Concrete”,
I University of British Columbia, Spring, 1968.
I 3.26
v. 23, no. 2, March-April, 1978.
Mattock, A. H. and Martin, L. D., Discussion of Ref. 3.8, PC1 Journal, v. 25, no. 6,
Nov-Dee, 1980.
I 3.27 “Superior Precast Concrete Handbook”, Superior Concrete Accessories, Inc., San
Diego, CA.
I 3.28 “KSM Structural Engineering Aspects of Headed Concrete Anchors and Deformed
Bar Anchors in the Concrete Construction Industry”, KSM Fastening Systems
I 3.29
Division of Omark Industries, Moorestown, NJ.
I 3.30 Ollgaard, J. G., Slutter, R. G., and Fisher, J. W., “Shear Strength of Stud Con-
nectors in Lightweight and Normal Weight Concrete”, AISC Engineering Journal,
v. 8, no. 2, April, 1971.
I 3.31 McMackin, P. J., Slutter, R. G. and Fisher, 3. W., “Headed Steel Anchors under
Combined Loading”, AISC Engineering Journal, Second Quarter, 1973.
I 3.32 “Structural Welding Code, Dl.l-79”, American Welding Society, Miami, FL, 1979.
I 3.85
I
3.33 “Structural Welding Code/Reinforcing Steel”, D1.4-79”, American Welding Soci-
I
ety, Miami, FL, 1979.
3.34 “Standard Specifications for Highway Bridges‘I, Twelfth Edition, 1977, American I
Association of State Highway and Transportation Officials, Washington, DC.
3.35 “Manual of Steel Construction”, Seventh Edition, American Institute of Steel
Construction, Chicago, IL.
I
3.36 “Standard Specification for Deformed and Plain Billet-Steel Bars for Concrete
Reinforcement”, (ASTM A615-781, American Society for Testing and Materials,
I
Philadelphia, PA.
3.37 “Standard Specification for Low-Alloy Steel Deformed Bars for Concrete Rein-
forcement” (ASTM A706-761, American Society for Testing and Materials, Phila-
I
3.38
delphia, PA.
Conrad, R. F., “Tests of Grouted Anchor Bolts in Tension and Shear”, AC1 Journal,
I
v. 66, no. 9, Sept, 1969.
3.39 Anderson, A. R., ‘Composite Designs in Precast and Cast-in-Place Concretes, I
Progressive Architecture, v. 41, no. 9, Sept, 1960.
3.40 “Standard Specification for Uncoated Seven-Wire Stress-Relieved Strand for
Prestressed Concrete”, (ASTM A416-74), American Society for Testing and Mater-
I
ials, Philadelphia, PA.
3.41 “Standard Specification for Uncoated High-Strength Steel Bars for Prestressing
I
Concrete”, (ASTM A722-75), American Society for Testing and Materials, Phila-
delphia, PA.
I
3.42 “Standard Specification for Epoxy-Resin-Base Bonding Systems for Concrete”,
ANSI/ASTM C881-78, American Society for Testing and Materials, Philadelphia,
PA. I
3.43 Kriz, L.B. and Raths, C. H., “Connections in Precast Concrete Structures -
Strength of Corbels”, PC1 Journal, v. 10, no. l,Feb, 1965. I
3.44 Mattock, A. H., Chen, K. C. and Soongswang, K., “The Behavior of Reinforced
3.45
Concrete Corbels”, PC1 Journal, v. 21, no. 2, March-April, 1976.
Mattock, Alan H., “Design Proposals for Reinforced Concrete Corbels”, PC1
I
Journal, v. 21, no. 3, May-June, 1976.
3.46 Raths, Charles H., “Embedded Structural Steel Connections”, PC1 Journal, v. 19,
I
no. 3, May-June, 1974.
3.47 Marcakis, K. and Mitchell, D., “Precast Concrete Connections with Embedded
I
Steel Members”, PC1Journal, v. 25, no. 4, July-August, 1980.
3.48 Chan, Timothy, “A study of the Behavior of Reinforced Concrete Dapped-End
Beams”, Master of Science Thesis, University of Washington, 1979.
I
I
3.86
I
I
I 3.49 Cazaly, L., and Huggins, M., “Canadian Prestressed Concrete Institute Handbook”,
Canadian Prestressed Concrete Institute, 1964.
I 3.50 Ife, J., Uzumeri, S. and Huggins, M., “Behavior of the ‘Cazaly Hanger’ Subjected to
Vertical Loads”, PC1Journal, v. 13, no. 6, Dec., 1968.
I 3.51 Loov, Robert, “A Precast Beam Connection Designed for Shear and Axial Loads”,
PC1 Journal, v. 13, no. 3, June, 1968.
I 3.52 Gustaferro, A. II., and Martin, L. D., “PC1 Design for Fire Resistance of Precast,
Prestressed Concrete”, Prestreased Concrete Institute, Chicago, 1977.
3.54 AC1 Committee 503, IUse of Epoxy Compounds with Concrete”, AC1 Journal,
I v. 70, no. 9, Sept, 1973.
3.55 Mattock, A. II. and Gaafar, G. H., “‘Ihe Strength of Embedded Steel Sections as
I Brackets”, University of Washington, March, 1981. Presented at the 1981 Annual
Convention, American Concrete Institute, Dallas, TX, Feb, 1981.
I
I
I
I
I
I
I
I
I
I 3.87
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I PART 4
I
I
I
I
I
I
I
I
I
I
I
I 4. TYPICAL CONNECTION DETAILS
I The connection details shown in this section were selected from over 300 which
were initially reviewed. Some of these details are based on details shown in the
publications listed at the end of the section. Others were supplied by those who design
I and manufacture precast, prestressed concrete products.
Classification of Connections
I The connections have been classified by the types of members which are connected
as follows:
I 4.1
4.2
Column to foundation -
Column to column -
-
CF
cc
4.3 Beam to column BC
I 4.4
4.5
4.6
Slab to beam
Beam to girder
Beam to beam
-
-
-
SB
BG
BB
4.7 Slab to slab - ss
I 4.8
4.9
Wall to foundation
Slab to wall
-
-
WF
SW
4.10 Beam to wall - BW
I 4.11 Wall to wall - ww
Evaluation of Connections
I The more than 300 initial connection details were reviewed by approximately 40
professional, producer and associate members of the Prestressed Concrete Institute.
Each was initially evaluated on the basis of the criteria discussed in Section 3.1. This
I initial evaluation led to the selection of the details shown and the comments on each
detail.
I The final evaluation rating given for each connection is a composite, subjective
judgment based on the comments of the reviewers.
The first symbol in the “evaluation” rating refers to the extent of use in North
I America:
1- Common usage
I 2- Not common usage
The second symbol refers to the acceptability of each connection. Jn general, when
I applying this rating, it was assumed that the connection could be designed satisfactorily
to resist the loads imposed. Thus the evaluation was based more on simplicity, durability
and volume change accommodation than on inherent strength and ductility. The ratings
are as follows:
I Good solution
; - Acceptable
I AS
cs
-
-
Good solution for special design situations
Acceptable for special design situations
AM - Good solution when moment resistance is required
4.1
I
I
I
Initially, there was also an “F” category for connections which, in the opinion of the
evaluators, had little merit. This accounts for the elimination of many of the initial
300. Others were combined with those shown, either by smaller inset drawings, or by
I
reference in the comments.
There was not universal agreement as to the merits of the details shown and there I
are probably many ‘good” and “acceptable” details not shown. As the state-of-the-art of
precast, prestressed construction continues to develop, other good connection ideas will
undoubtedly develop. I
I
I
I
I
I
I
I
I
I
I
I
I
I
4.2 I
I
I
I
I
I
I
I
I 4.1 Column to Foundation - CF
I
I
I
I
I
I
I
I
I
I
I 4.3
I
I
COLUMN TO FOUNDATION - CPl
The column is cast with four corner pockets and a base plate the same size as the
column. It is erected over anchor bolts protruding from the foundation. The space
I
between the column and foundation is filled with a dry-pack or non-shrink grout.
Temporary support and levelling are accomplished by tightening down on the nuts
I
with the column resting on a center stack of shims or by a doubIe nut (levelling nut)
arrangement as illustrated in the insets.
Features:
I
...Corner pockets allow easy wrench access and effective placement of
anchor bolts.
...Holes in base plate are oversized lo reduce tolerance problems.
. ..Column size base plate does not require form penetration and
I
permits the thinnest possible plates.
. ..Conne&ion is concealed and protected from corrosion after
patching.
I
. ..Bolting allows quick, easy erection in any weather.
I Features: . ..Side pockets allow corner bars to be welded to base plate, if desired.
. ..Oversized holes in base plate usually reduce tolerance problems.
. ..Column size base plate does not require form penetration and
I
I
I
I
I
I
I
I
I
I
I
I 4.5
I
COLUMN TO FOUNDATION - CP3
I
The base plate is larger than the size of the column and can be cast into the end as
shown or welded on as illustrated in the inset.
I
Refer to CFl for discussion and insets concerning erection and temporary support.
I
Features: ...No restrictions on wrench movement.
. ..Column corner reinforcing bars can be welded to plate for anchorage
if desired.
...Larger base plate increases effective bearing area if needed.
I
. ..Oversized holes usually reduce tolerance problems.
...Bolting allows quick, easy erection in any weather. I
Disadvantages: . ..Usually requires thicker base plate.
...Connection is not concealed or protected from corrosion.
. ..Large base plate may interfere with existing or future wall located I
near column line.
...Plate has to penetrate column form or be beyond end of form when
cast with column. Connection is not usually used with prestressed
columns cast in long line forms.
I
Evaluation: . ..lC I
I
I
I
I
I
I
I
I
I
4.6 I
I
I COLUMN TO FOUNDATION - CF4
I This is a variation of connection CF3. The base plate is wider than the column on
only two sides and can be attached in the same ways as CF3.
I Refer to CFl for discussion and insets concerning erection and temporary support.
Features: ...Savings on base plate material over CF3.
I . ..No restrictions on wrench movement.
...Main reinforcement can be welded to base plate if desired.
. ..Oversized holes usually eliminte tolerance problems.
. ..Larger base plate increases effective bearing area.
I . ..Bolting allows quick, easy erection in any weather.
I Evaluation: . ..lC
prestressed columns cast in long line forms.
I
I
I
I
I
I
I
I
I
I
I
I
COLUMN TO FOUNDATION - CF5
I
This connection is similar in basic principle to CFl but uses two angles instead of a
base plate. Anchorage of angles in the column is provided by stiffeners and welded bars.
I
Refer to CF1 for discussion and insets concerning erection and temporary support. I
Features: ...Long pocket allows easy wrench access.
. ..Oversizad holes for bolts reduce tolerance problems.
...Angles are within dimensions of column which allows easy casting.
. ..Connection is concealed and protected from corrosion after
I
patching.
...Bolting allows quick, easy erection in any weather. I
Disadvantages: . ..Limitad by available angle thicknesses.
. ..More patching required.
. ..Eliminates possibility of welding main corner bar reinforcement to I
base angles.
Evaluation: . ..ZC I
I
I
I
I
I
I
I
I
I
I
4.8 I
I
I COLUMN TO FOUNDATION - CP6
I This is a variation of CF4 and is used when added base plate stiffness is needed.
The base plate is stiffened in the projecting direction. Anchorage is provided by
reinforcement welded to the stiffeners.
I Refer toCF1 for discussion and inset concerning erection and temporary support.
I Evaluation: . ..2cs
I
I
I
I
I
I
I
I
I
I
I 4.9
I
I
COLUMN TO FOUNDATION - CP7
Shims and wedges are used as shown for temporary support and alignment.
I
Features: . ..Quick. easy erection in any weather.
. ..Moment resistance at column base.
. ..Minimum tolerance problems.
I
Disadvantages:
. ..Simplifies column casting.
. ..Foundation work is expensive.
I
...Difficult to assure good grouting under column.
Evaluation: . ..lAM I
I
I
I
I
I
I
I
I
I
I
I
4.10 I
I
I COLUMN TO FOUNDATION - Cl’8
I Disadvantages: ...Requires special form at column base, so is not suitable for long-line
casting.
...Possible tolerance problems with sleeves.
I Evaluation:
. ..Bolts not concealed or protected from corrosion.
. ..ZCM
I
I
I
I
I
I
I
I
I
I
I
I
I
I
COLUMN TO FOUNDATION - CP9
I The foundation has grout sleeves cast in which accept projecting reinforcement
from the column. The sleeves are filled just before the column is set. Dry-pack grout is
later worked under the column the same as the previous connections.
I The angles and bolts shown are one way of providing temporary support and
levelling until the grout sets. The angles can be reused or left in place.
I Evaluation: . ..2CM
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
4.2 Column to Column - CC
I
(Column splices)
I
I
I
I
I
I
I
I
I
I
4.14 I
I
I COLUMN TO COLUMN - CC1
I The column is cast with four corner pockets and a base plate usually somewhat
smaller than the column. It is erected over anchor bolts protruding from the column
below. The space between columns is filled with a dry-pack or non-shrink grout.
I Temporary support and levelling are accomplished by tightening down on the nuts
with the column resting on a center stack of shims or by a double nut (levelling nut).
(See CFl insets).
I Features: ...Corner pockets allow easy wrench access.
. ..Holes in the base plate are oversized to reduce tolerance problems.
I . ..Connection is concealed and protected from corrosion after
patching.
. ..Bolting allows quick, easy erection in any weather.
Evaluation: . ..lA
I
I
I
I
I
I
I
I
I
I
I 4.15
I
COLUMN TO COLUMN - CC2
I
This is a variation
of temporary support.
of connection Ccl. Refer to CC1 for description and discussion I
Features: ...Side pockets allow corner bars to be welded to base plate.
. ..Connection is concealed and protected from corrosion after
patching.
I
Disadvantages:
...Bolting allows quick, easy erection in any weather.
I This connection is similar in basic principle to CC1 but uses two angles instead of a
base plate. Anchorage of angles in the columns is provided by stiffeners and welded bars.
Features:
support.
I Evaluation: . ..2c
I
I
I
I
I
I
I
I
I
I
I 4.17
I
I
COLUMN TO COLUMN - CC4
This connection is commonly used when a moment transfer splice is desired. The
columns are match cast with top and bottom plates and then welded together when
I
erected.
Evaluation: . ..lCM I
I
I
I
I
I
I
I
I
I
I
4.18 I
I
I COLUMN TO COLUMN - CC5
I The lower column has grout sleeves cast in which accept projecting reinforcement
from the upper column. The sleeves are filled as the column is erected. When set, it
affects a lap splice. Dry-pack grout is later worked under the column.
I Temporary support and levelling must be accomplished by guying or other means of
bracing until the sleeves are grouted and cured.
I Evaluation: . ..lCM
I
I
I
I
I
I
I
I
I
I
I
COLUMN TO COLUMN - CC6
I
“ihii is a proprietary mechanical bar splicing system that is gaining popularity
world-wide. Special installation devices are provided by the manufacturer to aid install-
ation.
I
In the preferred installation, bars project from the lower column and the sleeves fit
over the top. Leveling is accomplished by shims. Grout is pumped into the bottom tube
I
until it comes out the top. In the alternate shown in the inset, the bars project from the
upper column section. Grout may be placed in the sleeves and the shim space in the
same operation, prior to placing the top section. I
Features: . ..Moment resistance at connection.
. ..Special installation devices reduce tolerance problems.
. ..No patching required.
I
. ..Column bars need not be bent.
. ..Effectiveness of proprietary sleeves have been verified by test. I
Disadvantages: . ..Additional means of bracing must be provided until grout in sleeves
has set.
. ..Requires a proprietary mechanical sleeve. I
. ..2A
Evaluation:
I
I
I
I
I
I
I
I
I
I
4.20
I
I
I COLUMN TO COLUMN - CC7
I The upper column has grout sleeves cast in which fit over reinforcement protruding
from the lower column. The sleeves are then grouted to affect a lap splice. The space
between column sections is filled with a dry-pack grout.
I Temporary support and levelling must be accomplished by guying or other means of
bracing until the grout in the sleeves is cured.
I Evaluation: . ..2CM
I
I
I
I
I
I
I
I
I
I
I 4.21
I
COLUMN TO COLUMN - CC8
I
This connection is only used when full moment transfer is desired in large, heavily
reinforced columns. Both column sections are cast with reinforcement protruding from
I
the ends which is welded together when erected.
I This connection may be used when fully continuous, composite ductile frames are
required. It allows the placement of column ties for confinement. Beam reinforcement
is placed through the joint and the assembly is completed with cast-in-place concrete.
I Temporary support is provided by a sleeve-in-sleeve connection. A structural pipe
or tube protruding from the upper section fits into a slightly larger pipe or tube in the
I lower section. A small weld holds the assembly in place. No weld is required if the fit is
tight enough.
Evaluation: . ..2CM
I
I
I
I
I
I
I
I
I
I
I 4.23
I
COLUMN M COLUMN - CC10
I
‘This system uses vertical post-tensioning for the column reinforcement and for
splicing the column sections. Sleeves are cast in the columns at the plant. The tendons I
knmally bars) are attached to an anchor (at the bottom floor) or a coupler (at intermed-
iate floors). The upper column is then “threaded” over the bars. The bars are tensioned
and anchored, leaving enough projection to attach a coupler to receive the bars for the
next level.
I
Features: . ..Ductile moment resisting connection.
. ..Post-tensioning reduces drift in high-rise buildings.
I
Disadvantages: . ..Complex erection procedure.
. ..Post-tensioning is an added operation.
. ..Alignment of sleeves is critical.
I
...Requires supplemental reinforcement or pretensioning for handling.
Evaluation: . ..2CM
I
I
I
I
I
I
I
I
I
I
I
I
4.24
I
4.3 Beam to Column - BC
4.25
I
BEAM TO COLUMN - BCl
I
The beam sits on a bearing pad (usually neoprene or laminated fabric) which pro-
vides even bearing and permits slight movements caused by shrinkage, creep and temper-
I
ature change. The top connection transfers horizontal shear forces between the beam
and column, provides erection stability and braces the column, but does not provide
rotational restraint. I
The top connection should allow some slight rotation to avoid attracting unintended
negative moments. Thus
welded. The inset on the
when the angle connection is used, only the outer ends are
left shows an alternate top connection which permits rotation
I
about the horizontal bar. The inset on the right illustrates a dapped-end alternate.
Refer to Sect. 3.5.1 for column corbel design and 3.5.3 for dapped-end beam design. I
Features: . ..Quick. easy erection.
. ..Few tolerance problems.
. ..Minimum volume-change restraint.
I
Disadvantages: ...No moment capacity.
. ..No torsional restraint.
I
Evaluation: . ..lA
I
I
I
I
I
I
I
I
I
I
4.26
I
I
I BMM WI COLUMN - BC2
I A sleeve in the end of the beam fits over a dowel which is threaded into either an
insert in the support or a ferrule welded to the underside of a bearing plate. To prevent
damage in handling, the dowel is put in just prior to erection. The sleeve should be 3 or 4
I times the size of the dowel to minimize field tolerance problems.
In order to prevent restraint, the bottom few inches of the sleeve should be filled
with a compressible material such as sand, vermiculite, or asphalt. The remainder is
I filled with grout.
The inset shows an alternate threaded dowel with a plate washer and nut when
I torsion or uplift resistance is desired. It also illustrates use with a dapped-end beam.
Features: . ..Quick. easy erection if properly detailed.
. ..Volume change restraint is minimized.
I . ..Provides shear resistance and some torsional restraint after
grouting.
I
I
I
I
I
I
I
I
I
I
I
BEAM TO COLUMN - BC3
I
This is a variation of connection BC2. The dowels are shown as cast in and
protruding from the top of the column. Inserts or ferrules, as described in BC2, can also
I
be used.
The inset shows two dowels with threaded ends for each beam when increased
I
torsional resistance is required. The nuts and washers can be recessed and patched if
desired.
Separate bearing pads under each beam are required and beam bearing plates may
I
be necessary.
I A wide flange, tube or other structural steel section is embedded in the top of the
column and fits in vertical slots in the ends of the beams. Plates are welded to the top
of the steel section and to plates or angles in each beam that can be recessed and
I patched as shown. See BCl for comments on design of top connection.
Separate bearing pads under each beam are required and beam bearing plates may
I be necessary.
I
I
I
I
I
I
I
I
I
I
I
I 4.29
I
BEAM TO COLUMN - BC5
I
BC5 through BClO show several variations of connections which use structural steel
members projecting from the column to support the beams. Design of these connections
is discussed in Sect. 3.5.2.
I
In this version, the exposed steel haunch usually requires encasement in concrete,
or other protection (See Sect. 3.1.4 - 3.1.5).
I
The h-metshows attachment of the projecting member by welding to avoid penetra-
tion of molds. This is discussed in Sect. 3.1.6. I
See BCl for top connection
Features: . ..High load carrying capacity.
I
. ..Reduced structural depth compared with concrete corbel.
. ..Minimum forming.
. ..Volume change restraint minimized.
I
Disadvantages: . ..Requires encasement for fire and corrosion protection.
. ..Alignment during casting is critical. I
Evaluation: . ..lA
c
I
I BEAM TO COLUMN - BC6
I (See BC5). In this version the haunch is recessed to reduce the depth and the
amount of patching required for fire and corrosion protection.
I Features:
Disadvantages:
. ..Clean looking, concealed connection (See BC5).
I
I
I
I
I
I
I
I
I
I
I
I
I
I 4.31
I
BEAM TO COLUMN - BC?
I
This connection employs two angles which form a “cradle” making the beam
immediately stable when erected. Bearing pads and a top connection as discussed in BCl
I
are required. The angles can be recessed and patched if required.
Evaluation:
. ..Requires form penetration.
. ..2A
I
I
I
I
I
I
I
I
I
I
I
I
4.32
I
I
I BEAM TO COLUMN - BC8
I Features:
Disadvantages:
...(See BC5).
. ..Built-up steel section requires additional labor.
. ..Patching to conceal connection may be difficult.
I . ..Requires dapped-end beam design.
Evaluation: . ..2A
I
I
I
I
I
I
I
I
I
I
I
I
I 4.33
I
BEAM TO COLUMN - BC9
I
See BC5. This connection employs two steel channels separated for a bolt to go
through. A sleeve is cast in the beam and recessed pockets allow the connection to be I
completely concealed after patching.
The bolt and sleeve offer a weldless top connection which provides lateral stability
when grouted. A bearing pad is also required.
I
Features: ...Quick. easy erection.
. ..No welding required.
I
. ..Concealed connection.
I (See BC5). An angle is welded to a plate cast in the column. For light loads, the
plate can be attached to the column with headed studs. Stiffeners on the angle, as
illustrated in the inset, can increase the capacity, but for the most part, the connection
I is limited to light loads.
I Evaluation: . ..zc
I
I
I
I
I
I
I
I
I
I
I
I
I
BEAM TO COLUMN - BCll
I
This connection is especially suitable for repair or remodeling. It is not commonly
used for conventional precast construction. Holes are drilled or sleeves are cast in the
I
column through which bolts pass. An epoxy grout is injected to completely fill the
sleeves or drilled holes. Oversized or plate washers are used at each end.
I BC12 through BC14 show several variations of hanger connections. Design of these
connections is discussed in Sect. 3.5.4. Hanger connections are immediately stable
during erection, although without a bottom stopper, may “roll” when loaded eccentri-
I cally. Main drawing shows beam framing along the centerline of columns and inset shows
beam framing into the side of the columns.
Other variations of steel haunches are shown in BC5 through BClO and design is
I discussed in Sect. 3.5.2.
Features: ...Quick. easy erection.
I . ..Erection stability.
. ..Concealed connection
Disadvantages: . ..Connection hardware is expensive.
I . ..Welding of reinforcement is critical.
. ..Alignment of the embedded haunch is critical.
I Evaluation: . ..2c
I
I
I
I
I
I
I
I
I
I
I
I
BEAM TO COLUMN - BC13
I
This connection is similar to BC 12, except the long tube haunch fitting in the beam
slot provides torsional stability. It is especially suitable for eccentrically loaded I,- I
shaped beams.
4.38
I
I BEAM TO COLUMN - BC14
I This is an acceptable beam to column connection for special situations such as for
shallow beams where headroom is a problem. It is not commonly used for conventional
precast construction.
I Features: . ..Quick. easy erection.
. ..Good field adjustment.
. ..No volume change restraint problems.
I . ..Connection is concealed and protected
is poured.
from corrosion after topping
I Evaluation: . ..2cs
I
I
I
I
I
I
I
I
I
I
I
4.39
I
I
I
BEAM TO COLUMN - BC15
I welded reinforcement. The tension steel is placed and the composite topping is cast.
After the topping has cured, the next column is erected over the projecting reinforcing
bars.
I Disadvantages: ...Slow erection, as composite pour must cure before next column is
placed.
. ..Overhead welding is difficult.
I Evaluation: . ..lAM
I
I
I
I
I
Ii
I
I 7
I
I
I
I
BEAM TO COLUMN - BC17
This is similar to BC16 except the column corbels are omitted. Temporary shoring
of the precast beam is required. Bottom reinforcement continuity is attained by lapping,
I
welding, or hooking (See BC16 inset) projecting reinforcement, depending on dimensions
available. I
Features: . ..Clean connection with no projecting corbels.
. ..No exposed steel.
. ..(See also BC16).
I
Disadvantages: ...Requires temporary
. ..(See also BC16).
shoring during erection.
I
Evaluation: . ..lAM
I
I
I
I
I
I
I
I
I
I
I
I
4.42
I
I
I BEAM TO COLUMN - BC18
I Evaluation: . ..lAM
I
I
I
I
I
I
I
I
I
I
I 4.43
I
BEAM TO COLUMN - BC19
I
This is a moment connection using precast beams and cast-in-place columns. The
beams have reinforcement projecting from the ends, which is lapped with horizontal
reinforcement in the connection. The beams require shoring. Each pour typically ends at
I
the top of the finished floor.
Disadvantages:
. ..Lapped splices on reinforcement easier than welding.
. ..ZCM
I
I
I
I
I
I
I
I
I
I
I
I
4.44
I
I
I BEAM TO COLUMN - BC20
I A post-tensioning tendon is fed through a duct in the beam and an oversized sleeve
in the column. An anchorage plate is attached at the anchorage pocket and the tendon is
tensioned from the other end and locked off in the recessed pocket provided. Prior to
I tensioning, the space between the beam and column is filled with a dry-pack grout.
The inset illustrates the connection with a beam from both sides. The column can
. ..lAM
I
I
I
I
I
I
I
I
I
I
I
4.45
I
I
BEAM TO COLUMN - BC21 I
This shows a connection at the top of a column. Unlike BC20, the main
reinforcement for the beam and column is the post-tensioning.
As with BC20, the post-tensioning tendons are fed through embedded ducts
I
(oversized sleeves when passing through a second member) and are tensioned after the
grout between members has set. I
This connection can be designed to provide full moment resistance for lateral
loads. For earthquakes, the tendons can be positioned to establish hinging at a pre-
determined location (See Sect. 2). I
Features: ...Moment resistance at connection.
. ..Connection is concealed. I
Disadvantages: . ..No positive connection until tendons are jacked unless additional
means are provided.
. ..Without supplemental reinforcement or pretensioning, the beams
I
must be shored.
Evaluation: . ..lAM I
I
I
I
I
I
I
I
I
I
4.46
I
I
I
I BEAM TO COLUMN - BC22
I This connection is usually used with L-beams in parking structures. The beams set
on bearing pads in a pocket in the column, or on a corbel. They are bolted through
sleeves in the column into inserts in the beams. The bolts are located near the top or
I bottom of the beams depending on the direction of torsional rotation from eccentric
loads. The other (top or bottom) usually has a compression pad or shim between the
beam and column.
I Evaluation: ...lAS
I
I
I
I
I
I
I
I
I
I
I
4.47
I
I
BEAM TO COLUMN - BC23
I
This is a commonly used connection for spandrel beams. The beams sit on an
embedded steel haunch and are bolted into the column, top and bottom. The clip angles
I
have a vertical slot ins one leg and a horizontal slot in the other for adjustment,
A bearing pad as discussed in BCl is required.
and patched.
The angles may be set in recesses I
Features: . ..Torsional resistance provided.
. ..No welding required.
I
Disadvantages: ...Connections are exposed and may require fire or corrosion
protection. I
. ..Alignment of inserts is critical.
. ..To avoid volume change restraint, there must be some slot remaining
after adjustment and bolts should not be overtightened. I
Evaluation: . ..lCS
I
I
I
I
I
I
I
I
I
I
I
4.48
I
I
I BEAM TO COLUMN - BC24
I Evaluation:
. ..Possible alignment problems with conduits.
. ..2cs
I
I
I
I
I
I
I
I
I
I
I
4.49
I
I
I
BEAM TO COLUMN - BC25
This is an acceptable
cantilevers. The columns
beam to column connection for special situations such as
have pockets and plates similar to connection Ccl. After the
I
beam is erected on shims,
Enough rod is left sticking
as described in connection
the threaded rods are inserted and the sleeves are grouted.
up so that the next column can be erected in the usual manner
Ccl.
I
Features: . ..Quick. easy erection.
. ..Cantilevered beam passes through uninterrupted.
I
...Connection is concealed and protected from corrosion after
patching.
...Usually no tolerance problems. I
. ..Alignment of sleeves is critical.
Disadvantages:
. ..Projecting bolts are easily damaged. I
Evaluation: . ..lCS
I
I
I
I
I
I
I
I
I
I
I
4.50
I
I
I
I
I
I
I
I
I 4.4 Slab to Beam - SB
I
I
I
I
I
I
I
I
I
I
I 4.51
I
SLAB TO BEAM - SBl
I
Standard connection when no mechanical tie to the support is required. Slabs bear
on high density plastic or hardboard bearing strips. Composite topping often used with
I
this connection.
Disadvantages:
. ..Volume change restraint minimized.
I This connection provides a positive integral floor system without welding or cast-
in-place topping. With projecting stirrups as shown, the cast-in-place top portion of the
beam acts compositely with the precast section, providing added structural capacity.
I Features: ...Positive connection to beam.
. ..No hardware cast into slabs.
I Disadvantages:
. ..Allows adequate tolerance.
I Evaluation: . ..lA
I
I
I
I
I
I
I
I
I
I
I
4.53
I
I
SLAB TO BEAM - SB3
I
This is a standard connection for double tee roofs. The stems set on bearing pads
td a top connection is made as shown. Although one top connection per tee will usually
I
rffice for erection and diaphragm forces, two may be desirable. Experience has shown
tat in most stemmed members, a welded top connection will not cause volume change
?staint problems if the bottom of the stem is not restrained.
I
Features: ...Quick. easy erection.
. ..Allows adequate tolerance.
...Usually. no volume change restraint problems.
I
. ..Positive connection for erection and lateral forces.
Evaluation: . ..lA
I
I
I
I
I
I
I
I
I
I
I
I
I
4.54
I
I
I SLAB TO BEAM - SB4
I Precast slabs sit on a high density plastic or hardboard bearing strip. A loose plate
is welded to embedded plates in the slab and beam. A roof spandrel condition is
illustrated here.
I Features: ...Quick. easy erection from top.
. ..Positive connection to beam for erection and lateral forces.
I Disadvantages:
. ..Allows adequate tolerance.
I Evaluation: . ..lA
I
I
I
I
I
I
I
I
I
I
I
I
4.55
I
I
SLABTOBEAM-SB5
I
This connection is used to transfer lateral diaphragm loads and to provide bracing
for the compression flange of steel beams. The inset shows a connection used when
I
maximum clearance is needed below the slabs. (Top flange bracing not provided in this
case.)
Evaluation: . ..lC I
I
I
I
I
I
I
I
I
I
I
I
I
4.56
I
I
I SLABTOBEAM-SB6
I As with SBI,
hardboard bearing
precast slabs, generally voided, sit on a high density plastic or
strip. Steel plates with deformed bar anchors lay in the grout joints
and are welded to angles in the beam. The connection is completed as the joints are
I normally grouted. Usually, no topping used with this detail.
Evaluation: . ..2c
I
I
I
I
I
I
I
I
I
I
I
I
I 4.57
I
SLAB TO BEAM - SB7
I
This connection used when a positive tie across the beam is desired, but there is no
grout key for embedment of reinforcing bars. Continuity for live loads (and dead loads if
I
slabs are shored before welding and grouting) can be provided if end joint is grouted.
Disadvantages:
. ..Can provide continuity.
I Evaluation: . ..ZCS
I
I
I
I
I
I
I
I
I
I
I
I
4.59
I
I
I
I
I
I
I
I
4.5 Beam to Girder - BG I
I
I
I
I
I
I
I
I
I
I
4.60
I
I
I BEAM M GIRDER - BGl
I The beam or joist sits on a bearing pad in a pocket in the girder. Depending on the
relative depths of the beam and girder, the~beam may need to be dapped to allow
adequate depth under the pocket.
I The beams and girders are often used in conjunction with a floor system having a
composite topping. If there is no topping, a top connection may be required.
. ..2c
I
I
I
I
I
I
I
I
I
I
I
4.61
I
I
BEAM To GIRDER - BG2
I
The hanger connection shown is similar in concept to BC12 - BC14. Design of
hangers is discussed in Sect. 3.5.4.
I
Features: . ..Quick. easy erection.
...Minimum reduction of girder section. I
. ..No dust-collecting ledges.
. ..2A
I
I
I
I
I
I
I
I
I
I
I
I
I
4.62
I
I
I BEAM TO GIRDER - BG3
I . ..Positive connection.
. ..Full section of girder is effective.
I
I
I
I
I
I
I
I
I
I
I
I
4.63
I
I
BRAM TO GIRDER - BG4
I
This drawing shows a composite system using precast beams or joists on a soffit
beam. As shown, removable forming is required between beams, but a similar system
I
using hollow-core, flat slab or stemmed deck members is also used.
Features: ...Quick. easy erection. I
. ..Shallow structural depth.
Disadvantages:
. ..Totally integrated structural framing system.
Evaluation: . ..lA
I
I
I
I
I
I
I
I
I
I
I
I
I
4.64
I
4.6 Beam to Beam - BB
4.65
I
BEAMTOBEAM-BBl
I
BBl through BB3 are used in continuous frames, where it is desired to have the
connection away from the column. Examples are “tree” columns with “drop-in” beams,
I
cruciform beam-columns with connections at mid-span, or systems which use story-high
columns and continuous beams.
This connection requires dapped-end designs on both segments (See Sect. 3.5.3).
I
Modification of hanger connections shown in BC12 - BC14 can also be used. The top
connection should be detailed as discussed in BCl. I
Features: . ..Quick. easy erection.
Evaluation: . ..2c I
I
I
I
I
I
I
I
I
I
I
I
4.66
I
I
I BEAM TO BEAM - BB2
I ‘IT& connection is usually used in composite systems when “drop-in” beam sections
are suspended from two cantilevers. The connector is attached to the drop-in section.
Features: . ..Quick. easy erection.
I . ..Concealed connection.
Disadvantages: . ..Limited capacity.
I Evaluation: . ..X
I
I
I
I
I
I
I
I
I
I
I
I
I 4.67
I
I
BEAM TO BEAM - BB3
I
This connection is similar to BC6 with two embedded angles forming a “cradle”. An
alternate with a weld-on haunch is shown in the inset. Bearing pad(s) and top connections
I
are required and the haunches can be recessed and patched if desired.
4.69
I
sLABTosLAB-SSI I
This is the standard connection used between hollow-core and sohd slabs. The size
and shape of the key vary with the method of manufacture. The key is usually filled with
a sand-cement grout.
I
This connection distributes vertical loads and provides horizontal shear transfer for
moderate loads when the deck is used as a diaphragm. This is discussed in Sect. 2.
I
Features: ...Quick. easy erection.
...No embedded items in slabs.
I
Disadvantages:
. ..No hardware to corrode.
. ..Susceptible to freezing.
I
. ..Underside may have to be caulked if exposed.
Evaluation: . ..lA I
I
I
I
I
I
I
I
I
I
I
I
4.70
I
I
I SLAB TO SLAB - SS2
I An angle with deformed bar anchors and studs is embedded in the slab. A loose
plate is welded to the angles.
I The connection can be recessed slightly if the slab is thick enough to accommodate
the vertical leg of the angle or the angle can be inverted as shown in the inset.
I Evaluation: . ..lA
I
I
I
I
I
I
I
I
I
I
I
I
I
SLAB TO SLAB - 553
I
A plate with deformed bar anchors is embedded in the edge of the slab. A bar is
welded to the edges of the plate. If there is no topping and the slab or flange is thick
enough, the connections can be recessed and caulked as shown.
I
Features: ...Quick. easy erection.
. ..Properly spaced connections distribute loading and transfer
I
diaphragm forces.
. ..Helps even out differential camber.
I
Disadvantages: ...Bar may not fit if joint is too wide.
Evaluation: . ..lA I
I
I
I
I
I
I
I
I
I
I
I
I
4.72
I
I
I SLAB TO SLAB - SS4
I A plate with reinforcing bars welded at 45’ angles is recessed slightly and
embedded in the slab. This provides the proper reinforcement cover and keeps the
connection from projecting above the top of the slab. A loose plate is welded at each
I end.
...Quick. easy erection.
Features:
Evaluation: . ..lC
I
I
I
I
I
I
I
I
I
I
I
I
4.73
I
I
SLAB To SLAB - SS5
I
A narrow plate with deformed bar anchors is embedded at about a 20’ angle. A
short piece of reinforcing bar is welded to the steel plates. I
Features: . ..Quick. easy erection.
. ..Properly spaced connections distribute
diaphragm forces.
loading and transfer I
...Helps even out differential camber.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I 4.8 Wall to Foundation - WF
I
I
I
I
I
I
I
I
I
I
4.75
I
I
WALL TO FOUNDATION - WPl I
The wall panel is set on shims under each stem located at the centroid. Loose
angles are welded to plates embedded in the wall panel and foundation. Generally, two
connections per panel are provided. The space under the wall is usually filled with a dry-
I
pack grout.
Features: . ..Quick. easy erection.
I
...Pew tolerance problems.
Disadvantages: ...When placed below grade, may be awkward for welding. I
Evaluation: . ..lA
I
I
I
I
I
I
I
I
I
I
I
I
I
4.76
I
I
I WALL TO FOUNDATION - WP2
I Instead of being welded to a plate in the foundation, the angle is bolted; using
drilled-in expansion bolts. This eliminates the need for any hardware to be accurately
located in the foundation.
I The space under the wall is usually filled with a dry-pack grout.
I Evaluation: . ..lA
I
1
I
I
I
I
I
I
I
I
I
I
I
I
WALLTOFOUNDATION-WWF3
I
As with WFl and WF2, the wall panel is set on shims under each stem located at
the centroid. A loose angle is welded to plates embedded in the panel and foundation.
I
The bottom leg of the angle is usually turned under the stem when the footing isn’t wide
enough.
I
Features: ...Quick. easy erection.
. ..Allows access to connection when non-bearing panels are to be
removed and reused. I
Disadvantages: . ..Connection is away from main bcdy of panel (especially critical for
shear walls).
. ..Exterior connection is susceptible to moisture damage.
I
Evaluation: . ..2c
I
I
I
I
I
I
I
I
I
I
I
I
4.78
I
I
I WALL TO FOUNDATION - WF4
I This connection is used when the wall panel sets on a grade beam or wall. The wall
panel is set on shims under each stem located as near the centroid as possible. Loose
plates are welded to embedded plates on the face of the foundation wall and bolted into
I inserts in the wall panel. The gap under the wall is then filled with a dry-pack grout.
. ..2c
I
I
I
I
I
I
I
I
I
I
I
I
4.79
I
I
WALL TO FOUNDATION - WP5
I
This connection is used when cantilever moments must be resisted. The connection
at the base of the precast panel can be any of those shown in WFl - WF4. Coil rods are
threaded into inserts and cast into the floor slabs. Inset shows how strand lifting loops
I
can be used in conjunction with bent rebars to accomplish tie to floor slab.
Features: . ..Cantilever moment resistance provided.
I
Disadvantages: . ..Insert location (vertically) is critical.
...Slab construction requires care to assure that the bars are properly I
embedded.
Evaluation: ...2AS I
I
I
I
I
I
I
I
I
I
I
I
I
4.80
I
I
I WALLTOPOUNDATION-WWP6
I The foundation is cast with a slot to receive the wall panel. The wall panel is set
on shims as required and the shear key, which is 2 to 4 inches wider than the wall, is
filled in with grout. No other connection is made.
I Features: . ..Quick. easy erection.
. ..No tolerance problems.
I . ..Shear resistance perpendicular to wall.
I Evaluation:
...No connection for wall panel during erection.
. ..lA
I
:
I ,,. .I...:”..+sa:..‘.
...:‘., . : :,
:..
I : :‘,
.,:i:_
.;;: :
,.,,&:‘:‘:’
9‘.
I
I
I
I
I
I
I
I
I
I 4.81
I
I
I
I
I
I
I
I
4.9 Slab to Wall - SW
I
I
I
I
I
I
I
I
I
I
4.82 I
I
I SLABTOWALL-SW1
I Precast slabs are set on high density plastic or hardboard bearing strips; leaving a
2 - 3 inch gap, end to end. If the wall is concrete masonry as shown, the cores are filled
in the last 2 - 3 courses and rebars are embedded at approximately 32” ox. Longitudinal
I reinforcement is added in the joint to tie the connection together. A composite topping,
reinforced with welded wire fabric, is poured and the next level of walI is constructed.
I Disadvantages: . ..Good weather required to pour concrete topping which may delay
wall construction.
Evaluation: . ..lA
I
I
I
I
I
I
I
I
I
I
I
I
I
Precast slabs are erected on
SLAB TO WALL - SW2
high density plastic or hardboard bearing strips, simi-
I
lar to SWl; but leaving only about 1 inch tolerance gap, end to end. A bond beam is
shown as an alternate to the filled
level wall is constructed and later
cores in SWl. No vertical dowels are used. The next
a composite topping is poured; locking in the base of
I
the wall.
I This connection is used when a composite topping is not provided. Precast slabs are
erected the same as for SWI. Vertical reinforcement can be dowels as in SW1 or
continuous bars as shown here. Reinforcing bars are grouted into the keyways between
I slabs to provide structural integrity. Longitudinal bars assist in tying the structure
together and act as shear friction reinforcement for the slab grout keys.
Features:
with a cast-in-place
Disadvantages: ...Space over the wall tends to become conjested with reinforcement.
I Evaluation: . ..lA
I
I
I
I
I
I
I
I
I
I
I
4.85
I
I
SLAB To WALL - SW4 I
Precast slabs are set on a continuous steel angle which is welded to embedded
plates in the wall. Some positive connection should be provided. Several alternates are
as illustrated in SB2, SB5 or SB6. Production restrictions or other conditions as discussed
I
for each, may determine the connection used.
This connection is generally only good for light loads. I
Features: ...Quick. easy erection.
. ..Wall can be continuous.
. ..No vertical tolerance problems.
I
Disadvantages: ...Connection may require fireproofing.
. ..Difficult to hold angle in place while welding.
I
. ..Little adjustment for tolerances normal to plane of wall, especially
Evaluation: . ..lC
when used with narrow wall panels.
I
I
I
I
I
I
I
I
I
I
I
4.86
I
I
I
I SLAB TO WALL - SW5
I This connection is usad when slabs cantilever over the wall. Dowels are grouted in
or embedded in the wall below at each slab joint. Precast slabs, with a notch at each
dowel location are erected on high density plastic or hardboard bearing strips. The
I notches are grouted with the keyways.
The dowels extend above the slab if there is a wall above or stop short of the top,
. ..lCS
I
I
I
I
I
I
I
I
I
I
I
4.87
I
I
SLABTOWALL-SW6
I
The wall panel has either a continuous reinforced concrete corbel or a “buttorP
haunch, as shown in the inset. The tee sits on a bearing pad (typically neoprene or
I
laminated fabric) and has a top connection usually over each stem which can take a
variety of configurations as discussed in BCl.
Features:
I
. ..Quick. easy erection.
. ..Braces wall panel.
...Connection is protected when roofing is placed or topping is poured. I
Disadvantages: . ..Special forming required for corbel.
Evaluation: . ..lA
I
I
I
I
I
I
I
I
I
I
I
I
I
4.88
I
I
I SLABMWALL-SW7
I This connection is used for the special situation when the double tee frames into
the stem side of a precast wall panel. The double tee rests on a bearing pad on a weld-
on steel haunch attached to a plate in the stem. A top connection, similar to that of SW6
I is also required.
Note that the stem of the double tee is blocked back and the flange is notched
around the stem of the wall panel.
I Features: ...Relatively easy erection.
. ..Bolves special condition without overly complicating casting of units.
I Disadvantages:
. ..Braces wall panel.
. ..Connaction is exposed and may require protection.
. ..Tolerances are critical because of stresses caused by eccentricities.
I Evaluation: . ..2cs
I
I
I
I
I
I
I
I
I
I
I
4.89
I
I
SLABTOWALL-SW8
I
This connection may be used when roof slabs cantilever over the wall panels. Here,
the stem of the wall panel is blocked back and the flange notched instead of the double I
tee. The double tee rests on a bearing pad on the top of the stems and cantilevers out.
A plate cast in the bottom of the stem of the roof member is welded to the angle at the
support. This connection should only be used when the wall is flexible enough to avoid
volume change restraint problems.
I
Features: . ..No haunch is required.
. ..Provides desired cantilever.
I
. ..Braces wall panel.
Disadvantages: . ..Overhead weld is difficult; especially on high walls. I
. ..Connection may require fireproofing.
Evaluation: . ..2c I
I
I
I
I
I
I
I
I
I
I
I
4.90
I
I
I SLABTO WALL-SW9
I A loose angle with a vertical slot is bolted into an insert in the panel and welded to
a plate in the slab. The slot takes care of vertical adjustments made necessary by
camber or fabrication or erection tolerances. In the case of a roof, it also allows the
I slab to move with temperature changes.
The inset illustrates a welded alternate. Experience and calculations have shown
I that sufficient welded connections (typical spacing in most cases) can resist movements
due to temperature changes with no adverse effects.
Evaluation: ...lC
I
I
I
I
I
I
I
I
I
I
I
4.91
I
I
SLABTOWALL-SW10
I
This is a variation of connection SW1 for use with stemmed deck units. Precast
tees are set on neoprene bearing pads with the flanges blocked back to the face of the
I
wall. If the wall is concrete masonry as shown, the cores are filled in the last 2 - 3
courses and rebars are placed at approximately 32” OX. Longitudinal reinforcement is
added in the joint to tie the connection together. A composite topping, reinforced with
welded wire fabric, is poured along with the connection and the next level of wall is
I
constructed.
I
I
I
I
I
I
I
I
I
I
I
I
4.93
I
I
I
SLABTOWALL-SW12 I
A common connection of a roof to a masonry wall. The last course is usually a
bond beam containing reinforcement. The flanges of the tees are not cut back and the
area between the stems can be left open, infilled The
withtees
masonry or closed end
are connected off to
withend as
I
precast, asbestos cement or translucent panels.
shown.
I
Design conditions such as significant shear force transfer may dictate the need for
an additional connection to the wall.
Features: ...No tolerance problems.
I
. ..No forming and pouring of connection required.
I This is a variation of connection SW4for stemmed units. The tees are set on a
continuous steel angle welded to embedded plates in the wall. Stiffeners are usually
required in the angle at the stem locations. An alternate to the continuous angle is
shown in the inset.
I A top connection is required as in SW6and discussed in BCl.
I Evaluation: . ..lA
I
I
I
I
I
I
I
I
I
,
I
4.97
I
BEAMTOWALL-BW2 I
A pocket is cast into the wall to receive the beam. The beam sits on a bearing pad
and the pocket is later grouted, preferably after dead loads are in place. A top connec-
tion, as discussed in BCl could also be provided. Axial shortening of beam due to volume
I
change should be considered when designing depth of recess.
This connection @ more commonly used with cast-in-place walls, but can also be
I
used with precast panels.
Features: . ..Minimum of embedded hardware. I
. ..Clean. concealed connections.
Disadvantages: . ..Pocket dimensions must be planned so that beam can “swing” into
place-especially critical if this connection is used at both ends.
I
Evaluation: ...lC I
I
I
I
I
I
I
I
I
I
I
I
4.98
I
I BEAMTOWALL-BW3
I A dowel is placed in a bond beam or grouted masonry cores. See BC2 for other
features.
Evaluation: . ..2c
I
1
I
4.99
I
BEAM TO WALL - BW4
I
This connection is used when the beam is required to provide lateral restraint to
the wall. The bearing plate is installed on a mortar bed immediately after the concrete I
is placed in the bond beam.
I
I
I
I
I
I
I
I
I
I
I 4.101
I
WALLTO WALL--WI
I
A plate is cast into the upper wall, anchored with deformed stud bars which lap
with vertical reinforcement in the panel. A threaded rod or coil rod projects from the
I
lower panel and bolts through an oversized hole in the plate. This rod also laps with
vertical reinforcement to provide a continuous vertical tension tie through the system.
The formed pocket is later patched to conceal the connection. Proper vertical elevation I
is obtained with shims or a leveling nut under the plate.
Evaluation: . ..lA I
I
I
I
I
I
I
I
I
I
I
I
I
I
I WALL TO WALL - WW2
I A section of structural steel tube is east into the upper panel. Continuous steel
rods which project from the lower panel are bolted to the top and bottom of the tube.
With high strength bars and a heavy steel tube, a high ultimate resistance to uplift can be
I attained.
Evaluation: . ..2C
I
I
I
I
I
I
I
I
I
I
I
I 4.103
I
WALLTO WALL--W3
I
The upper wall is cast with an embedded plate in a recessed pocket. The lower wall
is cast with a plate projecting from the top which fits up against and is welded to the
I
plate in the upper wall. The pocket is later patched to conceal the connection. During
erection, the panel is shimmed to the proper elevation and later dry packed.
I
The lower plate fits in the joint between the slab and the notched wall or between
the two slabs at a typical interior connection. The reinforcement on the plates can be
lapped with vertical reinforcement in the panels, providing continuity through the
connection.
I
Features: ...Positive connection between walls.
. ..Connection is concealed and protected from fire after patching.
I
. ..Continuous vertical reinforcement through the connection.
Disadvantages: . ..Plate alignment in the wall is critical. I
Evaluation: ...2c
I
I
I
I
I
I
I
I
I
I
I
I
I WALLMWALL-WW4
I The sleeve connectors shown here receive reinforcing bars from each end and are
later filled with an expansive grout to form a continuous connection. The device is
proprietary and tests have shown they are capable of developing the full strength of the
I bar. (See also CC%.)
The sleeve connector can be placed in any of positions shown, but placement in the
. ..2A
I
I
I
I
I
I
I
I
I
I
I
4.105
I
I
WALLTO WALL--W5
I
This connection uses vertical post-tensioning to connect the walls. Sleeves are cast
in the wall panels at the plant. In most applications, the tensioning is done one floor at a
I
time. The tendons (usually bars) are attached to an anchor (at the bottom floor) or a
coupler (at intermediate floors). The panels are then “threaded” over the bars. The bars
are tensioned and anchored, leaving enough projection to attach a coupler to receive the
bar for the next level.
I
Features: . ..Fully continuous tension tie.
. ..Connection is totally concealed and protected.
I
...High tensile strength.
. ..Post-tensioning reduces drift in high rise buildings.
I
Disadvantages: ...Complex erection procedure.
. ..Post-tensioning is an added operation.
. ..Alignment of sleeves is critical.
. ..Hardware is expensive.
I
Evaluation: . ..lC I
I
I
I
I
I
I
I
I
I
I
4.106
I
I
I WALLTOWALL-WW6
I Plates are cast in the wall panel and anchored with studs and/or welded reinforcing
bars. A loose plate is welded across the joint. In the corner condition shown in the inset,
a loose steel angle is used instead of the loose plate.
I Features: ...Ample adjustment allowance.
. ..When recessed, connection is concealed and protected.
I Disadvantages:
...Good shear transfer.
. ..Rigid connection.
...Possible volume change problems.
I Evaluation: . ..lA
I
I
I
I
I
I
I
I
I
I
I
I
I 4.107
I
WALLTOWALL-WW'I
I
Inserts or bolts welded to steel plates are cast into the panels. The loose plate has
slots in opposite direction on each side to allow both vertical and horizontal adjustment.
I
If properly placed, the slots will also allow some movement for volume changes. If a
rigid connection is desired, the plates can be later welded.
. ..Quick erection.
I
Features:
. ..Volume change strain relief.
. ..When recessed, connection is concealed and protected.
...No welding required.
I
Disadvantages: . ..Less field adjustment than WW6.
...Shear transfer between panels unreliable without welding.
I
Evaluation: . ..lA
I
I
I
I
I
I
I
I
I
I
I
I
4.108
I
I
I
WALLTOWALL-WW8
I angle.
Steel angles are cast into the panels. A bar spans the joint and is welded to each
I Evaluation: . ..2c
I
I
I
I
I
I
I
I
I
I
I
I
I 4.109
I
I
REFERENCES - PART 4
I
4.1 “Connection Details for Precast-Prestressed Concrete Buildings”, Prestressed
Concrete Institute, 1963.
I
4.2 “Connection Details for Precast, Prestressed Concrete”, by the Australian
Prestressed Concrete Group. Published by Cement and Concrete Association of
4.3
Australia about 1965.
4.5 “PC1 Manual on Design of Connectins for Precast, Prestressed Concrete”, First
I
Edition. PC& Chicago, IL 1973.
I
I
I
I
I
I
I
I
I
4.110
I
I METRIC CONVERSION
I SI Base units
I Quantity
length
Name
meter
Symbol
Ill
mass kilogram kg
I electric
time
current
second
ampere
s
A
thermodynamic temperature
I amount
luminous
of substance
intensity
mole ,llOl
I SI Supplementary Units
I
I SI Derived Units
force newton N - m l kg l s2
pressure, stress Pascal Pa N/m2 ,,-I. kg. s-2
I en$g;;,uk,
power
quantity
jOUk
watt
J
w
Nom
J/s
m’
m2
l
l
kg
kg
l
l
s-*
s3
I SI Derived Units
In Terms In Terms
I Quantity Description of
Other Units
Of
Base Units
I specific volume
meter
cubic meter par
kilogram
- ml/kg
I moment of force
heat capacity
specific heat capacity
newton meter
joule per kelvin
joule par kilogram
N-m
J/K
J/kg-K
mr.kg*s-z
,,,‘.kg.s-Z.K-’
,,,‘.s-2.K-1
kelvin
I thermal conductivity watt per meter
kelvin
Wlm*K m*kg*s-3 K-l
I
I
METRIC CONVERSION I
I
Quantity
Other Units to Use with SI
mass
degree
Celsius
tonne
“C
t
1 “C (interval) = 1 K
0°C = 273.15 K
1 t = 1000 kg
I
I
Conversion Factors I
U.S. Customary to SI
I
To convert from to multiply by
I inch-pound
foot-pound
newton-meter
newton-meter
(Nom)
(N*m)
0.1130
1~.356
foot-kip newton-meter (Nom) 1356
I
I MXS
I
I pound (avdp)
ton (short, 2000 lb)
kilogram
kilogram
(kg)
(kg)
0.4536
907.2
ton (short, 2000 lb) tonne (t) i 0.9072
I I
I Temperature
I Other
I section
moment
modulus
of inertia
in.l
in:
mm3
mm’
16,387
416,231
Coefficient of heat transfer,
I Btulft’ hr ‘F
Modulus of elasticity, psi
W/m’* “C
MPa
5.678
0.006895
Thermal conductivity,
I Btu/in./ft’ hr “F
Thermal expansion in.lin. ‘F
W/m* “C
mm/mm* “C
0.1442
1.800
fc = mf’,, psi MPa 0.063036 J
I
I
I
-
I
I
I
I
.-
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Prestressed Concrete Institute
201 North Wells Street
I
Chicago, Illinois 60606
Telephone 3121346-4071 I
Printedin U.S.R
I