LICENSING PROCESS

New Application

Licensing Secretariat and Engineering

Engineering Division and Finance


Examine application for completeness
Examine for further technical information (Engineering) – 1 Licensing Secretariat
day Prepare Schedule and Calculation
START Request and prepare file -Prepare draft Licence
Sheet
*Request security clearance -submit for verification
Acknowledge receipt and *request additional information (as
necessary)
Request Schedule and Calculation Sheet 3 Days
2 Days
2 Days
Manager
Administration
Director, Legal Affairs Licensing Secretariat Engineering Division
Review draft Licence
Approved for signing Receive and amend draft Licence Verify draft Licence
where necessary (frequency Schedule)

2 Days
2 Days 1 Day 1 Day
Licensing Secretariat Technical Operations Managing Director/
Committee Minister
Licensing Secretariat Finance
Prepare document for (every two weeks)
submission to Technical
Operations Committee Approval/or ratification Prepare original Licence FINISH
Submit for signature Invoicing
2 Days
10 days 30 Days
1 Day 3 Days 2 Days

* Stop the Clock Private Radio, VSAT, Amateur and Aeronautical