Project Schedule - Caustic Dilution
Project Schedule - Caustic Dilution
5
ID Task Name Duration Start Finish Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
1 Engineering 70 days Mon 2/24/20 Fri 5/29/20
2 Basic Engineering 4 wks Mon 2/24/20 Fri 3/20/20
3 MCD Development 4 wks Mon 3/23/20 Fri 4/17/20
4 MCD Review & Approval 4 wks Mon 4/20/20 Fri 5/15/20
5 Bid Documents 2 wks Mon 5/18/20 Fri 5/29/20
6
7 Procurement 200 days Mon 3/23/20 Fri 12/25/20
8 Budget Appropriation 20 days Mon 3/23/20 Fri 4/17/20
9 Advice of Approval for CAPEX 2 wks Mon 3/23/20 Fri 4/3/20
10 AACE Approval 1 wk Mon 4/6/20 Fri 4/10/20
11 IO & AMU No. Issuance 1 wk Mon 4/13/20 Fri 4/17/20
12 Material Procurement 200 days Mon 3/23/20 Fri 12/25/20
13 Shopping Cart No. Creation 1 day Mon 4/20/20 Mon 4/20/20
14 Shopping Cart Approval 1 day Tue 4/21/20 Tue 4/21/20
15 Bidding 4 wks Mon 3/23/20 Fri 4/17/20
16 Technical Evaluation 2 wks Mon 4/20/20 Fri 5/1/20
17 Award of PO 2 wks Mon 5/4/20 Fri 5/15/20
18 Equipment Fabrication/Delivery 8 mons Mon 5/18/20 Fri 12/25/20
19 Service Contract 118 days Mon 6/1/20 Wed 11/11/20
20 WOR & Memo to Procurement 3 days Mon 6/1/20 Wed 6/3/20
21 Shopping Cart Creation 3 days Mon 6/1/20 Wed 6/3/20
22 Shopping Cart Approval 1 wk Thu 6/4/20 Wed 6/10/20
23 Pre-bid Meeting 1 wk Thu 6/4/20 Wed 6/10/20
24 Bid Submission 8 wks Thu 6/11/20 Wed 8/5/20
25 Evaluation of Technical Bid 4 wks Thu 8/6/20 Wed 9/2/20
26 Approval of Technical Evaluation 2 wks Thu 9/3/20 Wed 9/16/20
27 Evaluation & Approval of Commercial Bid 4 wks Thu 9/17/20 Wed 10/14/20
28 Award Endorsement 2 wks Thu 10/15/20 Wed 10/28/20
29 PO & NTP Issuance 2 wks Thu 10/29/20 Wed 11/11/20
30
31 Construction 97 days Thu 11/12/20 Fri 3/26/21
32 Pre-Construction & Kickoff 1 wk Thu 11/12/20 Wed 11/18/20
33 Mobilization & Temfacil 1 wk Thu 11/12/20 Wed 11/18/20
34 Construction 3 mons Mon 12/28/20 Fri 3/19/21
35 Testing & Commissioning 1 wk Mon 3/22/21 Fri 3/26/21
Normal Case