Design of Pipe Line Source 1 (CHANGU) for Budang WTP

HW Formulae
Pipe Start Pt Pipe end pt Q Pipe Pipe Pipe velocity Head loss Length Total loss in Total RL of start RL at Head at Remarks
design dia OD dia ID materia Head specials Head pt end end pt
l C loss @ 20% Loss pt
Pressure
LPS
m/sec m/ m m m m m m m m kg/cm2
Source BPT1 1.5 17.38 160.00 125 HDPE 120 1.42 0.0207 2500 51.84 10.37 62.21 3250 3053 134.79 13.47944 FEASIBLE
BPT1 BPT2 1.5 17.38 160.00 125 HDPE 120 1.42 0.0207 2850 59.10 11.82 70.91 3051 2893 87.09 8.708567 FEASIBLE
BPT2 BPT3 1.5 17.38 160.00 125 HDPE 120 1.42 0.0207 4300 89.16 17.83 106.99 2891 2690 94.01 9.400645 FEASIBLE
BPT3 BPT4 1.5 17.38 160.00 125 HDPE 120 1.42 0.0207 2420 50.18 10.04 60.21 2688 2538 89.79 8.978502 FEASIBLE
BPT4 BPT5 1.5 17.38 160.00 125 HDPE 120 1.42 0.0207 1200 24.88 4.98 29.86 2536 2390 116.14 11.61413 FEASIBLE
BPT5 BPT6 1.5 17.38 160.00 125 HDPE 120 1.42 0.0207 3350 69.46 13.89 83.36 2388 2234 70.64 7.064456 FEASIBLE
BPT6 Pakyong 1.5 17.38 150 API 100 0.98 0.0120 12300 147.10 29.42 176.52 2232 1345 710.48 71.04839 FEASIBLE
Pakyong Higest Point 1.5 17.38 200 API 100 0.55 0.0029 9500 27.98 5.60 33.58 2055.48 1890 131.90 13.19021 FEASIBLE
Higest Point Dhap Budang 1.5 17.38 150 API 100 0.98 0.0120 2150 25.71 5.14 30.85 2021.90 1875 116.05 11.60477 FEASIBLE
HDPE 16620
API 23950
Total 40570
Design of Pipe Line Source 1 (CHANGU) Parallel line for Pachak WTP
HW Formulae
Pipe Start Pt Pipe end pt Q Pipe Pipe Pipe velocity Head loss Length Total loss in Total RL of start RL at Head at Remarks
design dia OD dia ID materia Head specials Head pt end end pt
l C loss @ 20% Loss pt
Pressure
LPS
m/sec m/ m m m m m m m m kg/cm2
Source BPT1 1 11.59 140.00 110 HDPE 120 1.22 0.0182 2500 45.60 9.12 54.72 3250 3053 142.28 14.22828 FEASIBLE
BPT1 BPT2 1 11.59 140.00 110 HDPE 120 1.22 0.0182 2850 51.98 10.40 62.38 3051 2893 95.62 9.562235 FEASIBLE
BPT2 BPT3 1 11.59 140.00 110 HDPE 120 1.22 0.0182 4300 78.43 15.69 94.11 2891 2690 106.89 10.68863 FEASIBLE
BPT3 BPT4 1 11.59 140.00 110 HDPE 120 1.22 0.0182 2420 44.14 8.83 52.97 2688 2538 97.03 9.703371 FEASIBLE
BPT4 BPT5 1 11.59 140.00 110 HDPE 120 1.22 0.0182 1200 21.89 4.38 26.26 2536 2390 119.74 11.97357 FEASIBLE
BPT5 BPT6 1 11.59 140.00 110 HDPE 120 1.22 0.0182 3350 61.10 12.22 73.32 2388 2234 80.68 8.06789 FEASIBLE
BPT6 BPT 7 1 11.59 140.00 110 HDPE 120 1.22 0.0182 8400 153.21 30.64 183.85 2232 1718 330.15 33.01501 FEASIBLE
25020

Design of Pipe Line Source 2 (TAKCHAMCHU) for Pachak WTP


Source BPT 7 1.3 15.07 125 DI 140 1.23 0.0120 9500 113.60 22.72 136.32 1900 1718 45.68 4.568348 FEASIBLE
BPT7 pachak 1.3 15.07 125 DI 140 1.23 0.0120 16000 191.32 38.26 229.59 1716 1400 86.41 8.641428 FEASIBLE
25500

125 HDPE 16620 From Changu upto BPT 6


110 HDPE 25020 From Changu upto BPT 7 Parallel Line
125 DI 25500 From Takchamchu to Pachak WTP
150 API 12300 From BPT 6 to Pakyong Bazaar
200 API 9500 From Changu upto BPT 10
150 API 2150 From higest point to Budang
91090
WS PHE DEPARTMENT
RL Pressure
0 3250 0.00
2500 3053 13.48
5350 2893 8.71
9650 2690 9.40
12070 2538 8.98 Wate r Pres s ure wit h Le ngth and Reduce Le vel/Elevati on
13270 2390 11.61
16620 2234 7.06 3500 80.00
28920 1345 71.05
38420 1890 13.19 3053 71.05 70.00
3000
40570 1875 11.60 2893
2690 60.00
2500 2538
2390 1875
2234 50.00
elevation

2000

pressure
1890
40.00
1500
1345 30.00
1000
11.60 20.00
13.48 11.61 13.19
500 10.00
8.71 9.40 8.98
7.06
0 0.00

Water Flow and Pressure Chart


RL Pressure
Design of Sedimentation Tank

2.500 MLD
For Demand
104.17 cum/hr

Detention Time 6 hours

Capacity Required 625.00 m3

Height of Tank Proposed 4.00 m

Area of Tank required 156.25 m2

Length width ratio 3

Width 7.22 m

Provide Width 7.20 m

Length 21.7 m

Provide Length 21.70 m

Sludge depth 0.5 m

free Board 0.3 m

Total Height 4.80 m

Surface loading 16.00 m3/m2/day

Surface loading less than 30-40 m3/m2/day so OK

Check for Weir loading 347.22 SO OK

As such provide Double entry trough 2.00 NA

Surface loading 173.61 Ok

Limit being 300 m3/m2/day, Hence OK


749.95
Design of Sedimentation Tank

1.300 MLD
For Demand
54.17 cum/hr

Detention Time 6 hours

Capacity Required 325.00 m3

Height of Tank Proposed 4.00 m

Area of Tank required 81.25 m2

Length width ratio 3

Width 5.20 m

Provide Width 5.20 m

Length 15.6 m

Provide Length 15.60 m

Sludge depth 0.5 m

free Board 0.3 m

Total Height 4.80 m

Surface loading 16.03 m3/m2/day

Surface loading less than 30-40 m3/m2/day so OK

Check for Weir loading 250.00 SO OK

As such provide Sigle entry trough 1.00 NA

Surface loading 250.00 Ok

Limit being 300 m3/m2/day, Hence OK


389.38
Design of BPT1 - BPT6

2.500 MLD
For Demand
104.17 cum/hr

storage Time 1/4 hours

Capacity Required 26.04 m3

Height of Tank Proposed 2.00 m

Area of Tank required 13.02 m2

Length width ratio 2

Width 2.55 m

Provide Width 2.50 m

Length 5.2 m

Provide Length 5.20 m

free Board 0.3 m

Sludge depth 0.5

Total Height 2.80 m


Design of BPT7

1.300 MLD
For Demand
54.17 cum/hr

storage Time 1/4 hours

Capacity Required 13.54 m3

Height of Tank Proposed 2.00 m

Area of Tank required 6.77 m2

Length width ratio 2

Width 1.84 m

Provide Width 2.00 m

Length 3.4 m

Provide Length 3.40 m

free Board 0.3 m

Sludge depth 0.5

Total Height 2.80 m


Design of Main Clear Water Reservoir at WTP

1.50 MLD
For Demand
62.50 cum/hr

Reserved Time 12 hours

Capacity Required 750.00 m3

Provided capacity 750.00 m3

Height of Tank Proposed 4.00 m

Area of Tank required 187.50 m2

Length width ratio 3

Width 7.91 m

Provide Width 8.00 m

Length caculated 23.4 m

Provide Length 23.50 m

free Board 0.3 m

Total Height 4.30 m


808.40
Design of Main Clear Water Reservoir at WTP

1.30 MLD
For Demand
54.17 cum/hr

Reserved Time 12 hours

Capacity Required 650.00 m3

Provided capacity 650.00 m3

Height of Tank Proposed 4.00 m

Area of Tank required 162.50 m2

Length width ratio 3

Width 7.36 m

Provide Width 7.50 m

Length caculated 21.7 m

Provide Length 21.70 m

free Board 0.3 m

Total Height 4.30 m


699.83
Design of Zonal Tank

0.500 MLD
For Demand
20.83 cum/hr

storage Time 8 hours

Capacity Required 166.67 m3

Height of Tank Proposed 3.70 m

Area of Tank required 45.05 m2

Length width ratio 2

Width 4.75 m

Provide Width 4.75 m

Length 9.5 m

Provide Length 9.50 m

free Board 0.3 m

Total Height 4.00 m


WATER STRUCTURES SUMMARY

SL. TANK DETAILS Length Width Height CAPACITY

1 Intake/Head work Structure1

2 Intake/Head work Structure2

3 Sedimentation Tank AT CHANGU 21.70 7.20 4.80 749,952.00 Ltr.

4 Sedimentation Tank TAKCHAMCHU 15.60 5.20 4.80 389,376.00 Ltr.

5 WTP 1 AT DHAP BUDANG 1.50 MLD

6 WTP 2 AT PACHAK 1.30 MLD

7 Main Clear Water Reservoir1 23.50 8.00 4.30 808,400.00 Ltr.

8 Main Clear Water Reservoir2 21.70 7.50 4.30 699,825.00 Ltr.

9 Zonal Tank Ltr.

10 Distribution tank (Steel Tank)


LOCATION RL.

at CHANGU SOURCE 3260

at TAKCHAMCHU SOURCE 1910

at CHANGU SOURCE 3250

at TAKCHAMCHU SOURCE 1900

at BUDANG DHAP 1875

at PACHAK 1400

at DHAP 1870

at PACHAK 1395

as required