Professional Documents
Culture Documents
CE Law Quiz - Group8
CE Law Quiz - Group8
COLLEGE OF ENGINEERING
I. Multiple Choice
1. What is the typical responsibility of the Civil Engineer regarding legal, land,
administration, staffing, and financial costs in a construction project?
A) Always increased
B) Always decreased
C) Increased as the project progresses
D) Decreased as the project progresses
5. Why might larger or more complex construction projects require higher contingency
allowances?
7. According to the information provided, should engineers revise the estimate of the
probable total project cost as the design progresses?
8. Who is typically responsible for estimating costs related to legal, land, administrative,
and financial aspects of a construction project?
A) Civil Engineer
B) Project manager
C) Construction workers
D) Client
Answer: D) Client
A) Labor costs
B) Material costs
C) Audits
D) Land acquisition costs
Answer: C) Audits
II. Identification
2. Cost of issuing bonds: In project cost estimation, what does the term "cost of
issuing bonds" refer to, and why is it considered a part of the project cost?
3. Land costs: How are land costs calculated in project cost estimation, and why
are they important to consider?
6. Intangible costs: What are intangible costs in project cost estimation, and why
should they be considered?
7. Client's responsibility: What is the typical role of the client in providing cost
estimates for certain aspects of a construction project, and why is it necessary?
9. Complex projects: Why might larger or more complex projects require higher
contingency allowances in their cost estimates?
10. Final project cost: At what point in a construction project does the final project
cost become a known quantity, and what factors influence this knowledge?
III. Enumeration
1 – 3) List three examples of costs that are part of the probable total project cost.
Answers:
Audits
The cost of issuing bonds
Land costs
Interest for borrowed money during construction
Administrative costs
4 – 6) Name three project phases mentioned in the text through which the project
progresses.
Answers:
Study and report phase
Final design phase
Construction award phase
7 – 10) List four areas where the client is normally responsible for providing cost
estimates.
Answers:
Legal costs
Land costs
Administrative costs
Financial costs
IV. True or False
1. True or False: Legal, land, administration, staffing, and financial costs are
typically within the control of Civil Engineers during a construction project.
Answer: False. These costs are usually outside the knowledge and control of
Civil Engineers.
3. True or False: Contingency allowances are meant to account for intangible costs
that may arise during a construction project.
Answer: False. Larger or more complex projects may require higher contingency
allowances due to increased uncertainties.
6. True or False: The final project cost is known at the start of a construction
project.
Answer: False. The final project cost becomes known only at the completion of
the project.
7. True or False: Civil engineers should not revise the estimate of the probable total
project cost as the design progresses.
8. True or False: Clients are typically responsible for estimating costs related to
legal, land, administrative, and financial aspects of a project.
10. True or False: Contingency allowances are only added once, at the beginning of
a project, and are not adjusted throughout its duration.