GRIDCo STATEMENT-System Disturbance - Final Version - 8!9!2023
GRIDCo STATEMENT-System Disturbance - Final Version - 8!9!2023
The Ghana Grid Company Ltd., (GRIDCo), the “Operator” of the National Interconnected
Transmission System (NITS) informs the public that a system disturbance occurred at 19:03GMT
affecting parts of the country.
Restoration commenced immediately and three quarters of customers received supply as of 21:00
GMT. Power restoration efforts continue as generation is restored.
GRIDCo apologises for the inconvenience caused and appreciates your patience as we continue
to restore power to all affected customers.
Signed
Note to Editors:
Ghana Grid Company Limited (GRIDCo) was incorporated in December 2006 to carry out the economic
dispatching and transmission of electricity from facilities of wholesale suppliers (Independent Power Producers
[IPPs] to bulk customers and distribution utilities in Ghana and West Africa. GRIDCo operates the National
Interconnected Transmission System (NITS). The Utilities from eleven (11) Wholesale Suppliers, including the
Volta River Authority (VRA).