Professional Documents
Culture Documents
SOP For Work Permit
SOP For Work Permit
SOP For Work Permit
Purpose: -
1. To ensure execution of construction activities as per legal & technical requirement
2. Ensure worker safety before starting the activities
Applicability: -
1. Height Work (Above 2 meter)
2. Hot Work
3. Excavation Work
4. Night Work
5. Holiday Work
6. Confined Space Entry
7. Electrical Work
8. Blasting Work
9. Piling Work
10. Demolition Work
Procedure: -
1. Contractor Engineer or supervisor will inspect the work area and fill the permit form
2. Contractor safety representative will verify the work requirement as per points given in
permit form
3. Contractor Engineer will fill the permit register and take the unique permit number
4. HCZ Engineer or Area incharge will approve the permit if work requirements are fulfilled
in satisfactory manner
5. HCZ safety representative will acknowledge the permit
6. After completion of shift or work; permit will be closed by contractor Engineer and
specify the closing time on form
Output: -
1. Hazard and risk minimization before starting construction activities
2. Better work communication between HCZ & Contractor
Note:-
1. Work without permit reflects that HCZ Engineer has not authorized the activity
2. Penalty will be imposed to contractor in case of work execution without authorized
permit