WEEKLY PROGRESS REPORT

ELECTRICAL CONTRACTOR
PROJECT : GROVE RESIDENCY
National engineers co
DATE: Tuesday, August 8, 2023
MONTHLY PROGRESS OF JULY (from3-07-23 to 31-7-23 )
TOWER A
ACTIVITIES LOCATION FLOORS REMARKS
Sr# Description 28TH 27TH 26TH 25TH 24TH 23TH 22TH 21TH 20TH 19TH 18TH 17TH 16TH 15TH 14TH 13TH 12TH 11TH 10TH 09TH 08TH 07TH 06TH 05TH 04TH 03TH 02TH 01TH GF
All Washrooms wiring was pull backed as per client
1 Light circuit wiring / light point wiring Tower A 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% instrustions and for futher floors all washrooms are hold till
the completion of back box installation works by paragon.
2 Power circuit wiring / point wiring Tower A 95% 95% 95% 95% 95% 95% 95% 95% 95% 95%
All the Ac unit Conduits Are laid from DB To outer. Only 2.0
3 AC power wiring Tower A 95% 95% 95% 95% 95% 95% 95% 95% 95% 25%
Ton AC wiring have been done .
4 Conduting for Audio video intercome Tower A
5 Group control light wiring Tower A 80% 95%
6 Data voice wiring Tower A
7 Audio Video intercom wiring Tower A
8 Co-axial wiring Tower A
9 2-C fiber wiring Tower A
10 CCTV Wiring Tower A
11 Fire Alarm Wiring Tower A
12 CCVT Conduiting and Holes
TOWER B
ACTIVITIES LOCATION 33TH 32TH 31TH 30TH 29TH 28TH 27TH 26TH 25TH 24TH 23TH 22TH 21TH 20TH 19TH 18TH 17TH 16TH 15TH 14TH 13TH 12TH 11TH 10TH 09TH 08TH 07TH 06TH 05TH 04TH 03TH 02TH 01TH GF
All Washrooms wiring was pull backed as per client
1 Light circuit wiring / light point wiring Tower B 95% 95% 95% 95% 95% 95% 95% 95% 95% instrustions and for futher floors all washrooms are hold till
the completion of back box installation works by paragon.
2 Power circuit wiring / point wiring Tower B 95% 95% 95% 95% 95% 95% 95% 95% 95%
3 AC power wiring Tower B 95% 95% 95% 95% 95% 95% 95% 0% 0%
4 Conduting for Audio video intercome Tower B 50% 50% 50% 50% 50% 50% 50% 50% 50% 50% 50% 50%
5 Group control light wiring Tower B 80% 95%
6 Data voice wiring Tower B
7 Audio Video intercom wiring Tower B
8 Co-axial wiring Tower B
9 2-C fiber wiring Tower B
10 CCTV Wiring Tower B
11 Fire Alarm Wiring Tower B
12 CCVT Conduiting and Holes
TOWER C
ACTIVITIES LOCATION 25TH 24TH 23TH 22TH 21TH 20TH 19TH 18TH 17TH 16TH 15TH 14TH 13TH 12TH 11TH 10TH 09TH 08TH 07TH 06TH 05TH 04TH 03TH 02TH 01TH GF
All Washrooms wiring was pull backed as per client
1 Light circuit wiring / light point wiring Tower C 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% instrustions and for futher floors all washrooms are hold till
the completion of back box installation works by paragon.
2 Power circuit wiring / point wiring Tower C 90% 90% 90% 90% 90% 90% 90% 90% 95% 95% Sand in the bed room on 23th and 22th floor
All the Ac unit Conduits Are laid from DB To outer. Only 2.0
3 AC power wiring Tower C 95% 95% 95% 95% 95% 95% 95% 95% 10% 10%
Ton AC wiring have been done .
4 Conduting for Audio video intercome Tower C 100% 100% 100% 100% 50% 50% 50% 50% 50% 50% 50% 50% 50% 50% 50% 50% 50% 95% 50% 50% 50%
5 Group control light wiring Tower C 80% 95%
6 Data voice wiring Tower C
7 Audio Video intercom wiring Tower C
8 Co-axial wiring Tower C
9 2-C fiber wiring Tower C
10 CCTV Wiring Tower C
11 Fire Alarm Wiring Tower C
12 CCVT Conduiting and Holes
LOBBY AREA
TOWER A
ACTIVITIES LOCATION FLOORS REMARKS
Sr# Description 28TH 27TH 26TH 25TH 24TH 23TH 22TH 21TH 20TH 19TH 18TH 17TH 16TH 15TH 14TH 13TH 12TH 11TH 10TH 09TH 08TH 07TH 06TH 05TH 04TH 03TH 02TH 01TH
1 Light circuit wiring / light point wiring Tower A 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 50% 50%
2 Power circuit wiring / point wiring Tower A 70% 70% 70% 70% 70% 70% 70% 70% 70% 70% 70% 70% 70% 70% 70% 70% 70% 70% 70% 70% 70% 70% 70% 70%
3 Conduiting For CCTV Tower A
TOWER B
ACTIVITIES LOCATION 33TH 32TH 31TH 30TH 29TH 28TH 27TH 26TH 25TH 24TH 23TH 22TH 21TH 20TH 19TH 18TH 17TH 16TH 15TH 14TH 13TH 12TH 11TH 10TH 09TH 08TH 07TH 06TH 05TH 04TH 03TH 02TH 01TH
1 Light circuit wiring / light point wiring Tower B 90% 90% 90% 90% 90% 90% 90% 90% 90% 90% 90% 90% 90% 90% 90% 90% 90% 90% 50% 50%
2 Power circuit wiring / point wiring Tower B
3 Conduiting For CCTV Tower B
TOWER C
ACTIVITIES LOCATION 25TH 24TH 23TH 22TH 21TH 20TH 19TH 18TH 17TH 16TH 15TH 14TH 13TH 12TH 11TH 10TH 09TH 08TH 07TH 06TH 05TH 04TH 03TH 02TH 01TH
1 Light circuit wiring / light point wiring Tower C 95% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 90% 90% 90% 90% 90%
2 Power circuit wiring / point wiring Tower C 70% 70% 70% 70% 70% 70% 70% 70% 70% 70% 70% 70% 70% 70% 70% 70% 70% 70% 70% 70% 70%
3 Conduiting For CCTV Tower C