0002 - 703 - Electrical Load Planning and Connection-Disconnection
0002 - 703 - Electrical Load Planning and Connection-Disconnection
Number APPROVED
2.703
GENERAL INSTRUCTION MANUAL
ISSUE DATE REPLACES
ISSUING ORG. POWER SYSTEMS PLANNING DEPARTMENT
1/21/2018 08/17/2015
ELECTRICAL LOAD PLANNING AND CONNECTION/ APPROVAL PAGE NO.
SUBJECT AAG 1 OF 14
DISCONNECTION
CONTENT
This instruction outlines the rules and regulations governing the proposed electrical connections or
disconnection to or from Saudi Aramco's power transmission and distribution facilities. This instruction also is
applicable to any modifications to the existing electrical connections. The text includes:
1.1 Definitions
Electrical Connections: Any connection or planned future load additions or power generation facilities
to the existing or new underground, overhead, substation, transformer or service equipment of the
power system network for the purpose of importing (additional) respectively exporting electrical power.
Electrical Disconnection: Any disconnection or removal of a load from Saudi Aramco's distribution
facilities. This includes mothballing of facilities.
Proponent of Power Source Facility: This is the proponent organization that owns the electrical
distribution network to which the electrical connection is to be made. Normally for industrial facilities,
it is the proponent owning the plant facilities where as, for communities and installations with a
nominal voltage of 69 kV or higher it is the Power Systems Admin Area.
1.2 Abbreviations
2.2 Alternatively, for projects planned under Capital initially managed by FPD, the requirement
for electrical connections or additional power capacity requirements for existing facilities
can be communicated by letter to the Manager of PSPD2.
*2.3 Power requirement information shall consist of the amount of the power required in kVA,
diversity factor, power demand schedule, load list (if available), voltage level at which the
power is required, location and the date by which the power will be required.
2.4 The entity processing the request shall be the responsible agency for
approval/determination of the most viable and cost effective power source connection for
all new projects or expansion of existing facilities planned under corporate
major capital outlay, BI-19, NDE, and Non- capital. The entity processing the
request will closely coordinate with FPD for power connections for all new projects or
expansion of existing facilities planned under corporate major capital outlay.
**2.5 Off-grid renewable solution shall be pursued in-lieu of medium voltage distribution lines if
the following conditions are met:
2.5.1 The facility total name plate rating of the connected load is less than 200 KVA.
2.5.2 The expected distribution lines required length to power the new load is 1 km or
longer.
**2.6 For the case of replacing existing distribution lines, the economic analysis stipulated in
paragraph 2.5 applies.
**2.7 The economic analysis comparing new or replaced transmission/distribution lines versus
off-grid renewable solution shall be reviewed by PSRD and approved by FPD.
**2.8 The detailed design shall be reviewed and approved by PSRD for all off-grid renewable
solutions.
__________________________________________________________________________________________________________________________________________________________
1
The end-user submitting the request can track the status of the Electrical Power Connection / Disconnection requests online through CRM.
2 Refer to Attachment II.
2.9 Nothing in this Instruction shall be interpreted as prohibiting the attachment of portable
electric tools equipped with approved attachment plugs to the convenience outlets
provided at the unit or facility. The user of such tools shall be responsible for the
satisfactory and safe operating condition of his equipment.
2.10 In addition to meeting the requirements of the Saudi Aramco Drafting Manual, the requester
of the connection shall have the responsibility to assure that "As Built" drawings are
furnished to PSED together with completed and updated drawings of new installations.
3.2 Prior to making any electrical connection, the Department, Division, Section or Unit
Head desiring to make the connection shall comply with the following:
3.2.1 Proposed electrical connections without drawings or project proposal shall require
the preparation of an engineering package consisting of a work order (with
preliminary sketches) or memorandum setting forth the proposed connection to
be made, the type of connection required, i.e. permanent or temporary, and the
kind and type of load for which the service is desired.
3.2.2 This engineering package shall be reviewed and approved by the competent
authority within the proponent organization prior to being uploaded in CRM.
3.2.3 Subsequent design changes in electrical connections after the project proposal
review shall be resubmitted via CRM.
3.2.5 It must be recognized that switching operations that are necessary to make the
proposed electrical connections require notification to various operating
organizations, and that it is the responsibility of the organization requesting the
connection to provide sufficient prior notice to the concerned Superintendent of
POD, who will schedule these operations accordingly. The responsible
inspection authority shall notify POD that the facility has been installed
according to Saudi Aramco standards and is ready to be energized.
* CHANGE ** ADDITION NEW INSTRUCTION COMPLETE REVISION x
SAUDI ARABIAN OIL COMPANY (Saudi Aramco) G. I. Number APPROVED
2.703
GENERAL INSTRUCTION MANUAL
ISSUE DATE REPLACES
ISSUING ORG. POWER SYSTEMS PLANNING DEPARTMENT
1/21/2018 08/17/2015
ELECTRICAL LOAD PLANNING AND CONNECTION/ APPROVAL PAGE NO.
SUBJECT AAG 4 OF 14
DISCONNECTION
3.2.6 Circuit energization request form shall be completed and forwarded to the
concerned Superintendent of proponent organization.
4.1 The procedure to be followed for electrical disconnection is the same as for an electrical
connection requirement.
**5.2 The project execution agency shall coordinate through Corporate Affairs for any
Saudi Aramco distribution network electrical connection request s of below 69 kV
to SEC or National Grid. The project execution agency shall provide project
information, proposed connection location, connection specification and demand
requirements as part of the request.
5.3 The project execution agency shall coordinate and sign the Power Supply
Implementation Agreement (PSIA) with SEC or National Grid to implement the
project for the power supply plan as defined in the signed Memorandum of
Understanding (MOU).
5.4 Initial requests for energization on a project shall come from the project execution
agency or the Proponent by letter to SEC/National Grid. PSPD and Northern Area
Power Operations Department - Power Operations & Control Division shall be
copied on such a request.
5.5 Energization requirements by SEC or National Grid for Saudi Aramco facilities
shall be coordinated through the Northern Area Power Operations Department -
Power Operations & Control Division.
5.6 Corporate Affairs shall be the liaison agency for SEC's or National Grid ’s request
for power connections to Saudi Aramco power distribution network and
coordination of all such requests between the two corporations including the Land
Use Permit requests for SEC's or National Grid’s underground cables or overhead
power lines as per GI2.716.
Recommended: Date:
Manager, Power System Planning Department
Concurred: Date:
Manager, Facilities Planning Department
Concurred: Date:
Vice President, Project Management
Approved: Date:
Executive Director, Power Systems
EXCEPTIONS/REMARKS
ALL PROPONENT OPERATIONS SIGNATORIES COMPLETED THE QUALITY CHECK-LIST
1
Copies of the Energization Form can be downloaded via intranet link
https://sharek.aramco.com.sa/orgs/30002444/home/POD%20eforms/POD-04%20ENERGIZATION%20FORM.doc
* CHANGE ** ADDITION NEW INSTRUCTION COMPLETE REVISION x
SAUDI ARABIAN OIL COMPANY (Saudi Aramco) G. I. Number APPROVED
2.703
GENERAL INSTRUCTION MANUAL
ISSUE DATE REPLACES
ISSUING ORG. POWER SYSTEMS PLANNING DEPARTMENT
1/21/2018 08/17/2015
ELECTRICAL LOAD PLANNING AND CONNECTION/ APPROVAL PAGE NO.
SUBJECT AAG 7 OF 14
DISCONNECTION
Workflow notes:
DBSP = Design Basis Scoping Paper
FEL = Front End Loading
IPT = Integrated Project Team
LUP = Land Use Permit
MoA = Manual of Authorities
MoU = Memorandum of Understanding
NG = National Grid Saudi Arabia
POMA = Engineering, Procurement, Construction, Operation and Maintenance Agreement
POMA Template Custodian = committee comprising Contracting, Project Management, Law, Financial Risk
Management Department, Contract Review & Cost Compliance Department, Facilities Planning Department and
Power Systems representatives issuing templates for electrical interconnection agreements between Saudi
Aramco and SEC or National Grid
PS MoU Custodian = assigned representative of Power Systems Planning Department - Integrated Resources
Supply Planning Division which interfaces with SEC and National Grid on a regular basis2
PSP = Project Scoping Paper
PS-Rep IPT = Power Systems representative assigned to Integrated Project Team
Timing of the phases shown on the left hand side of the diagram are indicative only
Several sub processes triggered by the workflow are controlled by the applicable General Instructions,
Contracting Manual, (Department specific) Internal control Procedures, etc.
Workflow outlines principle; re-iterations required for example for design, location, SEC/National Grid
agreement on MoU content, approval of LUP requests or project timing changes are not explicitly shown
PS-Rep IPT decision step “LUP initiator” is guided as follows:
o Project execution agency submits LUP requests for Maintain Potential projects and for Temporary
Construction Facilities
o Otherwise the Organization owning the Business Initiative acts as Proponent in the context of a GI2.716
and submits LUP requests
LUP requests are submitted on-line along with shape file (file containing coordinates in UTM format) and
location map (PDF file for proposed route overlaid on satellite image required to verify wheter the given
coordinates match the proposed route) attached to it
Delay in approval of MoU and LUP delays the issuance of DBSP
Workflow does not preclude adherence to other General Instructions, such as GI887.000 and GI887.001
2
Regular interfacing enables the review step that the Integrated Resources Supply Planning Division performs to assess whether the
SEC proposal for power transfer facilities and/or required strengthening our their electrical network is most cost effective and
delivers optimum value both from a Saudi Aramco and Kingdom economics perspective.
* CHANGE ** ADDITION NEW INSTRUCTION COMPLETE REVISION x
SAUDI ARABIAN OIL COMPANY (Saudi Aramco) G. I. Number APPROVED
2.703
GENERAL INSTRUCTION MANUAL
ISSUE DATE REPLACES
ISSUING ORG. POWER SYSTEMS PLANNING DEPARTMENT
1/21/2018 08/17/2015
ELECTRICAL LOAD PLANNING AND CONNECTION/ APPROVAL PAGE NO.
SUBJECT AAG 9 OF 14
DISCONNECTION
* CHANGE
Workflow Engineering, Procurement, Construction, Operation and Maintenance Agreement (POMA) for Power Transmission Facilities with operating voltage ≥ 69 kV
ISSUING ORG.
IPT
Execution POMA Template
SEC/NG PMT (FEL1-2: FPD led; PS-Rep IPT Proponent PS MoU Custodian Law Contracting
Agency Custodian
FEL-3: PMT led)
** ADDITION
DBSP Issue first draft of
DISCONNECTION
Review/
comment,
concur
SAUDI ARABIAN OIL COMPANY (Saudi Aramco)
Review/comment, concur
POWER SYSTEMS PLANNING DEPARTMENT
NEW INSTRUCTION
ELECTRICAL LOAD PLANNING AND CONNECTION/
Review/
comment,
concur
Concurrence
MoU (unsigned)
signature MoU (unsigned)
(as per MoA)
Obtain
signature
Sign
(as per
MoA)
AAG
G. I. Number
APPROVAL
1/21/2018
ISSUE DATE
2.703
Phase:
COMPLETE REVISION x
APPROVED
PAGE NO.
REPLACES
10 OF 14
08/17/2015
SUBJECT
* CHANGE
Workflow Engineering, Procurement, Construction, Operation and Maintenance Agreement (POMA) for Power Transmission Facilities with operating voltage ≥ 69 kV
ISSUING ORG.
Execution IPT
POMA Template
SEC/NG PMT (FEL1-2: FPD led; PS-Rep IPT Proponent PS MoU Custodian Law Contracting
Agency Custodian
FEL-3: PMT led)
** ADDITION
DISCONNECTION
Store in project
MoU MoU
folder of POMA
Archive
Site
survey
results LUP initiator
FEL2 – DBSP
(shape file ?
SAUDI ARABIAN OIL COMPANY (Saudi Aramco)
& location
GENERAL INSTRUCTION MANUAL
map)
or or or
LUP (initiated three months before DBSP issue; processed as per GI2.716)
POWER SYSTEMS PLANNING DEPARTMENT
NEW INSTRUCTION
Scope of Work/
ELECTRICAL LOAD PLANNING AND CONNECTION/
Review/comment, concur
AAG
G. I. Number
APPROVAL
1/21/2018
ISSUE DATE
2.703
Phase:
COMPLETE REVISION x
APPROVED
PAGE NO.
REPLACES
11 OF 14
08/17/2015
SUBJECT
* CHANGE
Workflow Engineering, Procurement, Construction, Operation and Maintenance Agreement (POMA) for Power Transmission Facilities with operating voltage ≥ 69 kV
ISSUING ORG.
IPT
Execution POMA Template
SEC/NG PMT (FEL1-2: FPD led; PS-Rep IPT Proponent PS MoU Custodian Law Contracting
Agency Custodian
FEL-3: PMT led)
Revised PMOD
project cost Scope as per
no
estimate MOU ?
** ADDITION
DISCONNECTION
Bid Authorization to
evaluation Bid Letter yes
results
SAUDI ARABIAN OIL COMPANY (Saudi Aramco)
GENERAL INSTRUCTION MANUAL
no
Project
economics
re-
NEW INSTRUCTION
ELECTRICAL LOAD PLANNING AND CONNECTION/
evaluation
no
Project ERA
obtained ? Provide
Advise, support,
SEC/NG
attend SEC/NG
endorsed
yes meetings jointly
POMA
with PS-Rep IPT
Template
Obtain SRC Issue first draft of
approval for bid POMA based on
results and POMA Template
funding
AAG
G. I. Number
APPROVAL
1/21/2018
ISSUE DATE
2.703
Phase:
COMPLETE REVISION x
APPROVED
PAGE NO.
REPLACES
12 OF 14
08/17/2015
SAUDI ARABIAN OIL COMPANY (Saudi Aramco) G. I. Number APPROVED
2.703
GENERAL INSTRUCTION MANUAL
ISSUE DATE REPLACES
ISSUING ORG. POWER SYSTEMS PLANNING DEPARTMENT
1/21/2018 08/17/2015
ELECTRICAL LOAD PLANNING AND CONNECTION/ APPROVAL PAGE NO.
SUBJECT AAG 13 OF 14
DISCONNECTION
Execution IPT
POMA Template
SUBJECT
SEC/NG PMT (FEL1-2: FPD led; PS-Rep IPT Proponent PS MoU Custodian Law Contracting
* CHANGE
Agency Custodian
FEL-3: PMT led)
ISSUING ORG.
EXECUTION
Manage
construction,
Confirm scope of work complete and power quality within acceptable ranges
commissioning,
energization
** ADDITION
Letter to PMT
DISCONNECTION
OPERATION
De-energizing of Notice of POMA
power transmission termination
SAUDI ARABIAN OIL COMPANY (Saudi Aramco)
facilities
ABANDON
GENERAL INSTRUCTION MANUAL
POWER SYSTEMS PLANNING DEPARTMENT
NEW INSTRUCTION
ELECTRICAL LOAD PLANNING AND CONNECTION/
AAG
Phase:
G. I. Number
APPROVAL
1/21/2018
ISSUE DATE
2.703
COMPLETE REVISION x
APPROVED
PAGE NO.
REPLACES
14 OF 14
08/17/2015