Professional Documents
Culture Documents
Legal Covid19 Solar Industry 040320
Legal Covid19 Solar Industry 040320
pwc.com.au
Introduction
The outbreak of the novel coronavirus (COVID-19),
and the possibility of prolonged quarantine and
mitigation responses, will impact manufacturing and
supply of key equipment and materials used in the
construction of solar energy facilities in Australia.
classifying them as Delay Events, which enables the Consider the following list of events or circumstances
EPC Contractor to claim an extension of time to expressed as an exhaustive list of Force Majeure
extend the Date for Commercial Operation and avoid Events:
a liability for Delay Liquidated Damages is avoided; a. riot, war, invasion, act of foreign enemies,
suspending both parties’ performance obligations hostilities (whether war be declared or not), acts
until the impact of the Force Majeure Event has of terrorism, civil war, rebellion, revolution,
ceased; and insurrection of military or usurped power,
requisition or compulsory acquisition by any
providing a right to terminate the contract if the governmental or competent authority;
Force Majeure Event continues for an extended
period of time. b. ionising radiation or contamination, radioactivity
from any nuclear fuel or nuclear waste from the
On first impression, the COVID-19 outbreak and its combustion of nuclear fuel, radioactive toxic
consequential disruptions to solar equipment supply explosive or other hazardous properties of any
chains look like a classic Force Majeure Event, i.e. an explosive assembly or nuclear component;
event beyond the reasonable control of the EPC c. pressure waves caused by aircraft or other aerial
Contractor which will significantly impact the EPC devices travelling at sonic or supersonic speeds;
Contractor’s ability to meet its obligations under the EPC
Contract, particularly its obligation to complete by the d. earthquakes, flood, fire or other physical natural
Date for Commercial Operation. disaster, but excluding weather conditions
regardless of severity; or
The question for the Project Owner and EPC Contractor e. strikes or industrial disputes at a national level, or
is, does the supply chain disruption caused by COVID-19 strikes or industrial disputes by labour not
qualify as a Force Majeure Event under the terms of the employed by the affected party, its subcontractors
EPC Contract? or its suppliers, and which affect an essential
portion of the works, but excluding any industrial
Definition of Force Majeure Event dispute which is specific to the performance of the
works or this contract.
The definition of Force Majeure Event differs from
agreement to agreement. However, three qualifying
requirements are uniformly accepted as the basis of most
definitions:
In the above example, the interpretation of ‘Law’ will be If the supply chain disruption caused by COVID-19 falls
critical. EPC Contracts usually adopt a definition which within the definition of Force Majeure Event under the
sets out an exhaustive list of categories of law, including EPC Contract and provided that a Force Majeure Event
for example, ‘statutes’, ‘regulations’ and ‘subordinate constitutes a Delay Event, the EPC Contractor will be
legislation’. This list of categories may not extend to entitled to claim an extension of time to the Date for
‘orders’, ‘directives’, ‘by-laws’ and ‘approvals’ of bodies or Commercial Operation.
authorities other than State or Commonwealth
legislatures. If an extension of time is granted, the original Date for
Commercial Operation will be extended and the EPC
Contractor will not be liable to pay Delay Liquidated
Damages for that extended period.
As with the EPC Contract, a Force Majeure Event under A Connection Agreement has two distinct sets of
the PPA will typically entitle the Project Owner to claim an obligations (and often the agreement may be split into
extension of time to the Date for Commercial Operation multiple contracts).
and therefore avoid liability for Delay Liquidated
First, the transmission network service provider
Damages.
(TNSP) undertakes to construct the connection
assets for the solar facility by a fixed Date for
However, it is insufficient to simply point to force majeure
Practical Completion.
under the EPC Contract as evidence of an Force Majeure
Event under the PPA. Rather, the Project Owner will need Second, the TNSP undertakes to maintain those
to demonstrate that a Force Majeure Event has occurred connection assets and provide connection services
under the definition in the PPA. Some PPAs expressly over the life of the solar facility.
provide that a failure of another supplier or contractor to
Although these obligations may be viewed as separate
the Project Owner is excluded from the definition of Force
work streams, the TNSP typically recoups the costs of
Majeure Event unless that failure is, or would be,
constructing the connection assets through the annual fee
considered a Force Majeure Event affecting that supplier
charged to the Project Owner for the ongoing
or contractor under the PPA itself (had the supplier or
maintenance and connection services. This complicates
contractor been a party to the PPA).
how each obligation (or separate agreement) can
ultimately be terminated.
It is critical to understand any inconsistencies between the
definitions of Force Majeure Event under the PPA and the
EPC Contract. The differences may be significant given
the strong negotiating power of Offtakers in the current
PPA market. But if the definition of Force Majeure Event
3 Treat – Implement actions to reduce the impact of add an additional condition precedent specifying that
COVID-19 on your business and mitigate (to the the EPC Contractor must make enquiries as to the
extent possible) the risks where you can. This may availability of solar panels from the intended supplier
involve seeking external legal advice to determine the to inform the construction program and next steps;
risk under the various project agreements and expand the definition of Force Majeure Event to
conducting commercial discussions with other parties explicitly include any of the following terms:
or subcontractors.
– a ‘health crisis within Australia’;
4 Stay informed – The ramifications of COVID-19 are
– an ‘epidemic’;
yet to be fully seen or understood. It is important to
stay informed of any developments with respect to – a ‘health crisis declared to be a Public Health
COVID-19 (e.g. supply chain issues, visa restrictions Emergency of International Concern by the World
and/or trade restrictions that may be implemented by Health Organisation occurring within Australia or
government authorities). The situation is in a state of internationally’; or
flux and parties are encouraged to continually assess
– a ‘pandemic’; and
and triage the various impacts of COVID-19 on their
business. expand the definition of Force Majeure Event to
explicitly include Australian authority directives which
Endnotes
1 International Energy Agency, National Survey Report of PV Power Applications in China (2013): http://www.iea-
pvps.org/index.php?id=443&eID=dam_frontend_push&docID=2195
2 V Magazine Australia, Coronavirus could cause solar panel price spike (5 February 2020): https://www.pv-magazine-australia.com/2020/02/05/coronavirus-
could-cause-solar-panel-price-spike/
3 Ibid.
4 Ibid.
5 Smart Energy International, Coronavirus will impact global solar supply chain – Wood Mackenzie (11 February 2020): https://www.smart-
energy.com/industry-sectors/business-finance-regulation/coronavirus-will-impact-global-solar-supply-chain-wood-mackenzie/
6 Ibid.
7 PV Magazine Australia, Coronavirus could cause solar panel price spike (5 February 2020): https://www.pv-magazine-
australia.com/2020/02/05/coronavirus-could-cause-solar-panel-price-spike/
8 World Health Organisation, Statement on the second meeting of the International Health Regulations (2005) Emergency Committee regarding the outbreak
of novel coronavirus (2019-nCoV) (30 January 2020): https://www.who.int/news-room/detail/30-01-2020-statement-on-the-second-meeting-of-the-
international-health-regulations-(2005)-emergency-committee-regarding-the-outbreak-of-novel-coronavirus-(2019-ncov)
9 Centers for Disease Control and Prevention, SARS Basic Factsheet (6 December 2017): https://www.cdc.gov/sars/about/fs-sars.html
www.pwc.com.au
© 2020 PricewaterhouseCoopers. All rights reserved. PwC refers to the Australian member firm, and may sometimes refer to the PwC
network. Each member firm is a separate legal entity. Please see www.pwc.com/structure for further details. This content is for general
information purposes only, and should not be used as a substitute for consultation with professional advisors. Liability limited by a scheme
approved under Professional Standards Legislation. At PwC Australia our purpose is to build trust in society and solve important problems.
We’re a network of firms in 158 countries with more than 250,000 people who are committed to delivering quality in assurance, tax and
advisory services. Find out more and tell us what matters to you by visiting us at www.pwc.com.au.
TAG127076110