INTRODUCTION TO CONSTRUCTION COST INCLUDING
ITS TYPES, PRELIMINARY ESTIMATES AND UNIT PRICES
Construction Cost
Construction Cost means the total cost of the work to the owner of all elements of
the project designed or specified by the design professional including the cost at
current market rates of labor and materials furnished by the owner and equipment
designed, specified or specifically provided by the design professional. Construction
costs shall include the costs of management or supervision of construction or
installation provided by a separate construction manager or contractor, plus a
reasonable allowance for each construction manager’s or contractor’s overhead and
profit.
INTRODUCTION TO CONSTRUCTION COST INCLUDING
ITS TYPES, PRELIMINARY ESTIMATES AND UNIT PRICES
Types of Construction Project Cost
1. Fixed Cost
This is defined as the cost spent once for a particular point of time. The purchase
of equipment, machinery etc comes under fixed cost assets.
2. Time-Related Cost
Time-related cost is the cost spend for a particular activity for a given duration. The
cost spent on wages, equipment and building rents etc comes under this category.
3. Quantity -Proportional Cost
This type of cost will vary based on the quantities. Materials costs are examples of
quantity-proportional costs. Major classification of construction projects costs
are:
1.Project direct costs
2.Project Indirect Costs
Total Project Cost = Project Direct cost and Project Indirect Cost
INTRODUCTION TO CONSTRUCTION COST INCLUDING
ITS TYPES, PRELIMINARY ESTIMATES AND UNIT PRICES
Preliminary Estimates
Preliminary Estimates
Depending upon the type of infrastructure, the estimation technique and units
may change.
1.For buildings: The rate per square foot/per cubic foot/per room/per
occupant is given
2.For Roads and Highways: The rate per Km is provided depending upon
the thickness of layers and the type of construction material.
3.For Irrigation channels: The cost per Km is given. It can also be based on
a per hectare basis (area irrigation by the canal/water channel)
INTRODUCTION TO CONSTRUCTION COST INCLUDING
ITS TYPES, PRELIMINARY ESTIMATES AND UNIT PRICES
Preliminary Estimates
The preliminary cost estimate of buildings is based on areas and length measurements of various
elements of the structure. Moreover, the total square footage of the plot is also considered to get the
approximate cost for building the house, plaza, or multi-story building. Most of the clients require the
preliminary budget estimate from contractors and It helps to get a rough idea about the total
expenses for the completion of the project. So we can say that it is based on:
•Total square footage of building
•Linear Measurements (walls etc.)
•Area Measurements (Rooms, Floors, etc)
This is followed by a detailed estimate that includes a list of all the construction materials along with
the specifications. The detailed BOQ can be priced based on the cost of each line item
including masonry estimate, concrete estimate, etc. and the total budget amount for the construction
can be estimated precisely in this way. The quantity takeoff sheet can be priced easily by putting the
unit cost and most of the clients require such cost filled BOQ’s from contractors.
INTRODUCTION TO CONSTRUCTION COST INCLUDING
ITS TYPES, PRELIMINARY ESTIMATES AND UNIT PRICES
Preliminary Estimates
Thank you!