M.S For Cement Mill Building Foundation - RV01
M.S For Cement Mill Building Foundation - RV01
1 of 4 Prepared by
2 of 4 Approved by SINOMA
3 of 4 Be approved by PEG
4 of 4 Approved by YCC
SINOMA 1 / 22
Table Of Contents
1. Introduction ........................................................................................................ 3
2. Scope ..................................................................................................................... 3
3. References, Drawings and Standards ............................................................ 3
4. Roles/Responsibilities/Competence ............................................................. 4
5. The management & supervisor....................................................................... 5
6. Resource including manpower, materials and equipment ....................... 5
a) Materials .................................................................................................................. 5
b) Equipment ............................................................................................................... 6
7. Sequencing................................................................................................................ 7
8. Methodology............................................................................................................. 7
8.1 Pre Work ...................................................................................................................... 7
8.2 Work ............................................................................................................................ 8
8.2.1 Setting Out .............................................................................................................. 8
8.2.2 Construction for formwork ...................................................................................... 8
8.2.3 Concreting ..............................................................................................................10
SINOMA 2 / 22
1. Introduction
This Method Statement is intended to ensure the execution of all works during construction
of the Reinforcement concrete for Cement mill Building foundation including, formwork,
reinforcement and concrete works shall be executed safely and performed in accordance
with contract requirement and that all quality assurance/ control activities are in a systematic
manner, works are inspected and conformance is verified and documented.
2. Scope
This method statement covers the practice of the Reinforcement concrete of Cement mill
+ contract requirments
SINOMA 3 / 22
4. Roles/Responsibilities/Competence
SINOMA 4 / 22
Please nominate
casting
superintendent
to be responsible
for all casting
coordination
5. The management & supervisor (area engineer)
Mr. Li is not on
Table 01 management & supervisor list site ?!!
Civil
3 Eng. Mahmoud QC Quality control of civil work
department
a) Materials
SINOMA 5 / 22
Serial NO. Material Name Size Unit Quantity
NOTE:All materials must comply with relative standards and approved specifications
b) Equipment
Al Hanaki 50
100 m3/h
Helicopter/
Surface
8 4
troweling machine Finishing
SINOMA 6 / 22
7. Sequencing
8. Methodology
8.1 Pre-Work
The Project shall use ALhenaki and Sinoma batch plants located in YCC project with
Construction joints:
- Construction joint materials will be submitted and approval for work sequence
SINOMA 7 / 22
8.2 Work
setting of all works shall be undertaking in accordance with the method statement and
be derived from the main grid and benchmarks established at the commencement of
the project and which shall be maintained throughout construction works by the
surveyors, a certain shift from element axis will be setting out to be used for adjusting
Formwork will be adequately supported to prevent loss of grout and to ensure the correct
profile within the limits of the dimensional tolerances specified. The design and execution of
formworks will follow the requirements of Contract documentation and relevant European
Plywood supported by the timber will be used as a form-work, and tie rod system with double
1- the backing of the fixed temple will be galvanized steel pipe Φ50×3.4mm.
SINOMA 8 / 22
2- it is very important that the formwork is well supported and strong enough to bear all
3-formwork must be aligned and braced well from all sides to keep its original shape.
5- form-work material should not be damaged or rusted, which affects the quality of
concrete finishing.
7- steel pipe will be used to secure the system to prevent the lateral movement and
therefore to seal the top part of the foundation. As per fig below.
plan view
SINOMA 9 / 22
Section A-A
8.2.3 Concreting
SINOMA 10 / 22
❖ Field inspection for approval by YCC/PEG for formwork, rebars, cleaning and
8.2.3.2 Preparatory work before concrete pouring please refer to table 1 page 5 to identify
this role?!!
❖ Site coordinator in QC department, who’s main responsibility is to inspect,
SINOMA 11 / 22
laboratory technician, the technician is in charge of checking the concrete
❖ Slump test will be conducted as per relevant local standard and adjusted according
❖ The value of the slump is 12.5 ± 2.5 cm, and the concrete temperature not exceed
❖ All raw materials used to make concrete shall be measured accurately in batching
plant, and the measure system shall be checked regularly according to relevant
❖ Enough aggregate, sand, stone, water + admixtures shall be prepared before work
casting.
❖ Inspect and observe concrete uniformity and slump as per standard requirement,
take concrete testing sample on site and conduct curing in curing room. The testing
SINOMA 12 / 22
❖ Inspections and checks at various stages of the concrete works will be performed
using the pre- and post-concrete form attached and will be filled by the production
❖ The two Concrete batch plants capacity is ≥150m³/h, enough (aggregate, sand,
❖ Concrete mixer trucks are applied for horizontal concrete transportation: There are
8 vehicles at site, with 10 m3 capacity can be delivered each time for each one,
the transportation time from batching plant to work site is about 10 minutes. For
pumps to pour the concrete. “see the fig 4 for the location of the pump”
❖ Make detailed execution specification about overall concrete pouring and vibrating
order, the way of concrete transport, construction joint location, discharge and
vibrating method and key point and difficulty of quality control for the foreman and
labors.
be poured in two stage but before the concrete setting time between the stage.
SINOMA 13 / 22
So, assume 6 hours for the completion of the concrete delivery, plus 4 hours for
Rejected, casting to
toweling and curing protection. start early in the
morning (around 6 am)
❖ Pouring is scheduled to start at 17:00 pm and finish at 11:00 pm.
maintain and repair related machinery equipment in time for keeping them in
good working order. Making plan for manpower distribution, material supply,
❖ Self-inspection shall be carried out very carefully and strictly according to the
approved drawing and relevant local standard before requesting consultant for
inspection.
❖ The form shall be well cleaned to be free of detritus, sawdust, standing water or
other sundries. In order to prevent concrete leakage, the joints between forms
shall be completely tight, any big gaps or holes found shall be well sealed
instantly. The forms shall be wetted to a damp condition before concrete pouring.
if admixture is needed.
Concrete pouring shall be started after the owner/ consultant gives the orders and concrete
delivery list. We will have two pumps for casting, each pump will start opposite to the other,
SINOMA 14 / 22
the sequence of casting will be from the nearest edge adjusted to the pump towards the far
foundations edge. Eventually the two pumps will meet in the middle of the foundation by the
completion of each layer. By this method will minimize the concrete pressure on the one side
of the shuttering and distribute the concrete evenly on the foundation area without causing
any kind of segregation or cold joint. “See the attached layout”. Three vibrators are arranged
for each pump, at the front, middle and back of each concrete pouring band. The foundation
will be casted in two stage “see the section A-A “. firstly 0.8 m thickness will be poured in 3
layers. Then we will have time gab between the two stage which will not be more than the
initial setting time in order to make the base of the stage two stiff enough to carry the concrete
above. Secondly 1.2 m from the foundation will be poured in 4 layers. The concrete is poured
in layers, advancing horizontally layer by layer. The thickness of each layer is not more than
300mm and strictly controlled by calipers on site. The interval time of each layer of concrete
pouring shall not exceed the initial-set time of the previous layer of concrete (the initial-set
time of concrete is generally (3h), and the pouring shall be carried out after the second
vibration of the previous layer of concrete. Each layer of pouring shall be closed and vibrated
in place at the pouring joint. Date and time should be announced 24 hours prior to casting to
get all parties ready. vibration of the concrete shall be applied using either petrol or electrical
The number of workers and the number of pumps needed according to the volume of
SINOMA 15 / 22
A group of concrete casting:
1 Civil Engineers 2
2 Electric Engineer 1
4 Safety Engineer 1
10 Carpenters 4
11 Rebar Fixers 2
12 Cleaner 2
TOTAL 34
SINOMA 16 / 22
The Communication List for YCC line 3 Project
Foundation Layout
SINOMA 17 / 22
Section A-A
out”. The vibration depth must be no more than 30cm. The vibrator must be used
vertically only and the inserting vibrator’s moving radius should be not more than
1.5 time of vibrator’s effective radius, under the normal condition, the vibration
between vibrator and side formwork should be kept 5 to 10cm and be aware of
avoiding to touch steel bar and embedded parts. The concrete pouring in upper
layer must be conducted after the vibration work of concrete in down layer finish,
the vibrator must insert the concrete in down layer about 5 to 10cm when vibrating
SINOMA 18 / 22
concrete in upper layer, the vibration period of each point is 10s, the time must
ii. In the process of pouring and vibrating concrete, the foreman shall arrange a
carpenter for checking concrete cover, embedded items to ensure they would not
be reduced or moved. The forms and supporting system shall also be checked
The top of the concrete will be covered with plastic sheets to avoid evaporation of the
water the outer concrete, water spray below and above the plastic sheet will be applied.
Above this sheet Geotextile will be placed to keep the surface moist for a long period of
time. We are going to keep the form-work all around the foundation for 7 days as a curing
method therefore the form-work will prevent the evaporation of the water from the
1) Safety education
SINOMA 19 / 22
Safety regulations (BS EN 1004-2004) must be carried out to improve consciousness of
safety production and civilized construction. The concept of safety first has to be embedded
into all. At the same time, the following measures will be continually insisted: safety
education for construction workers before they enter into site, request for license of special
The safety officer shall inspect the execution of safety measures with the cooperation of
civil engineers and foremen every day. Any hidden danger found will be dealt with
immediately. Every working group will attend a safety meeting on each Monday, which
aimed at summarizing possible hidden danger of past week and try to improve it in the
future. At the same time, precautions will be taken and hidden danger will be recorded.
1) Before the scaffolding construction, work team is required to take safety training, and
safety engineer shall state the safety issues during work. With safety engineer’s field
survey to obtain authorization to start the scaffolding work. If any unsafe factors appear
in construction process, the safety engineer or site coordinator must stop and correct it.
Safety Engineer must inspect access and safe passage to the scaffolding before using
them. All scaffolds must be inspected by foreman prior to use-after erection and each
day. (Before used every working day) All scaffolds must be inspected by safety engineer
prior to use every seven days and made in a scaffold register. And also it shall be
SINOMA 20 / 22
inspected when there is impact, damage or modification of any scaffold by safety
engineer.
2) All workers in construction site shall wear helmet, working clothes, safety shoes.
Workers working high above the ground shall wear safety belts;
3) Labors with high blood pressure, heart disease or other conditions which are not suited
for the work high above the ground shall not participate in the work high above the
ground;
4) The construction area shall be closed with warning tape as a safety area, and workers
5) It’s prohibited to throw materials and litter from high, all items shall be transferred to the
and anti-rain measures have to be checked before use. Leakage of electricity protector
has to be installed into power-driven instrument and circuit. Emergency light shall be
SINOMA 21 / 22
wind-force over Beaufort scale 6.The safe engineer has to learn the weather forecast
officers before use. The driver shall hold work license of special equipment.
10) Temporary lighting receptor shall be installed on the top of operation platform and tower
crane, which the light can cover all scope of operation platform.
11) The scaffold shall be re-checked after strong wind or heavy rain. It shall be repaired
SINOMA 22 / 22