Professional Documents
Culture Documents
Concrete Institute of Australia - Recomended Practice - Z40 Super Workable Concrete
Concrete Institute of Australia - Recomended Practice - Z40 Super Workable Concrete
Super-Workable Concrete
SWC
RECOMMENDED PRACTICE
Super-Workable Concrete
The Concrete Institute of Australia New South Wales
is a non-profit organisation which was formed to PO Box 848 Crows Nest NSW 1585
provide a forum for exchange of information between Tel [02] 9903 7770 Fax [02] 9437 9703
its members and others. Since the information
contained in its publications is intended for general Queensland
guidance only and in no way replaces the services Level 14, 348 Edward Street Brisbane QLD 4000
of professional consultants on particular projects, Tel [07] 3227 5204 Fax [07] 3839 6005
no legal liability for negligence or otherwise can be
South Australia
accepted by the Institute for the information contained
in this publication. PO Box 148 Kent Town SA 5071
No part of this publication may be reproduced Tel [08] 8300 0300 Fax [08] 8341 1591
Crows Nest NSW 1585 Australia Level 6, 504 Pacific Highway St Leonards NSW
Tel [02] 9903 7770 Fax [02] 9437 9703
Email: exec@coninst.com.au
Website: www.coninst.com.au
2
Super-Workable Concrete
Committee Members
3
Super-Workable Concrete
4.3 Placement, Finish, Curing and
Joint Control 14
Contents
4.3.1 General 14
4.3.2 Placing Distance 14
1 General 4.3.3 Flatwork 14
1.1 Purpose 5 4.3.4 Mass Concrete 15
1.2 Scope 5 4.3.5 Walls/Columns/Beams 15
1.3 Background 6 4.4 Formwork 15
1.4 Definitions (Terminology) 6 4.4.1 Structural Design 15
1.5 Flowing Concrete 6 4.4.2 Release Agents 15
1.6 Benefits and Characteristics 4.4.3 Strip Timing 15
of SWC 6
5 Performance Verification
2 Characteristic Performance of SWC
5.1 General 16
2.1 Introduction 8
5.2 Laboratory/Trial Verification 16
2.2 Ranking of Structures/Members
Incorporating SWC 8 5.3 Field Verification 16
2.3 Plastic Properties of SWC 8 5.4 Quality Control Verification 16
2.3.1 Flowability 8 5.5 Hardened Concrete
Inspection/Verification 16
2.3.2 Passing around
Reinforcement 8 Appendix A Test Methods
2.3.3 Segregation Resistance 8 A.1 Modification to AS 1012 Standard Test
2.3.4 Bleed 9 Methods 18
2.4 Hardened Concrete Properties A.1.1 Sampling 18
of SWC 9 A.1.2 Making Test Specimens 18
2.4.1 Compressive Strength 9 A.2 Slump Flow Test Method 18
2.4.2 Tensile Strength 9 A.2.1 Overview 18
2.4.3 Shrinkage 9 A.2.2 Equipment Required 18
2.4.4 Modulus of Elasticity 9 A.2.3 Test Procedure 19
2.4.5 Bond Strength 9 A.2.4 Interpretation of Result 19
2.4.6 Structural Performance 9 A.3 Slump Flow and J-Ring Test Method 20
2.4.7 Durability 9 A.3.1 Overview 20
3 Materials and Proportioning A.3.2 Equipment Required 20
3.1 General 10 A.3.3 Test Procedure 20
3.2 Materials 10 A.3.4 Interpretation of Result 21
3.2.1 Cementitious/Binder 10 A.4 L-Box Test Method 22
3.2.2 Admixtures – General 10 A.4.1 Overview 22
3.2.3 Superplasticisers (HWR) 10 A.4.2 Equipment Required 22
3.2.4 Viscosity Modifiers (VMA) 11 A.4.3 Test Procedure 22
3.3 Proportioning 11 A.4.4 Interpretation of Result 23
3.3.1 General 11 A.5 Orimet Test Method 24
3.3.2 Basics 11 A.5.1 Overview 24
3.3.3 Initial Design Methodology 12 A.5.2 Equipment Required 24
A.5.3 Test Procedure 24
4 Production Control
A.5.4 Interpretation of Result 25
4.1 Concrete Supplier Control 13
A.6 GTM Screen Stability Test Method 26
4.1.1 Plant Selection 13
A.6.1 Overview 26
4.1.2 Raw Material Storage 13
A.6.2 Equipment Required 26
4.1.3 Batching 13
A.6.3 Test Procedure 26
4.1.4 Mixing 13
A.6.4 Interpretation of Result 26
4.1.5 Delivery andTransportation 13
4.2 Transportation 14 Appendix B Specification Guide 27
4.2.1 Pumping 14 References 28
4.2.2 Other on-site methods 14 Bibliography 28
4
Super-Workable Concrete
1 some vibration – depending on the application of the
concrete, its mix design, methods of placement, the
General size and shape of each element of the structure, and
the layout and amount of reinforcement.
Typical binders, admixtures and modifiers used
1.1 Purpose to produce SWC are:
Binary/ternary system low-heat binder – a type
This Recommended Practice provides
■
5
Super-Workable Concrete
1.3 Background Workability – A measure of the ease by which
The development of superplasticising fresh concrete can be placed and compacted.
admixtures (high-range water reducers) allowed the This is a complex combination of the aspects
development of flowing concrete in the mid 1970s. of fluidity, cohesiveness, transportability,
The development of SWC began in Japan in the early compactability and stickiness.
1980s (see Hurd2). Many of these concretes were Mortar – The fraction of the concrete
called SCC (self compacting concrete) but may or comprising the binding paste plus those
may not be self compacting without additional effort aggregates passing a 4.75-mm sieve.
depending on many factors. This research work started Paste – The fraction of the concrete
because of the concerns about concrete durability, comprising powder plus water and air.
with researchers realising that poor compaction Powder (Fines) – A generic term for solid
of concrete was a major factor in the declining materials including cement with a particle size
quality of construction work. The first SCC mix was smaller than 0.125 mm in average diameter.
demonstrated in Japan in 1988. SWCs have now Fillability – The ability of SWC to flow into and
reached 40% of the total concrete placed in Japan. fill completely all spaces within the formwork.
This technology was transferred to Europe
during the 1990s with the development of a new 1.5 Flowing Concrete
polycarboxylate generation of high-range water- The main benefit of the use of flowing concrete
reducing admixtures (superplasticisers). is to allow easier and quicker placing without recourse
to higher water-cement ratios or high cement contents.
1.4 Definitions It is important to note that not all normal concretes
The definitions of terms (see EFNARC3 and typically supplied at an 80-mm slump can be modified
JSCE4 publications) used in this document are: to produce flowing concrete. A mix design should be
Self-Compacting Concrete – Concrete having used which gives workability without segregation and
the characteristics of self-compactability. bleeding. Flowing concrete must be compacted by
Self-Compactability – A property of concrete vibration.
related to its placeability, enabling it to
completely fill the formwork by its own weight 1.6 Benefits and Characteristics of SWC
without vibration and without any micro air The benefits of SWC can be summarised as:
voids being formed. ■ Reduced construction time2,3.
Resistance to Segregation – The ability of ■ Reduced manpower required for placing and
fresh concrete to maintain uniform distribution compacting2,3.
of its ingredients against segregating action ■ Lower equipment costs and less noise since
induced by gravity and external forces. fewer or no vibrators may be required2,3.
Passability – The capability of fresh concrete ■ Ability to fill complex forms and members with
to pass through narrow spaces (eg between congested reinforcement2,3.
reinforcing bars) by its own weight without ■ Elimination of rubbing and patching ordinarily
using vibrating procedures and without required to fill defects in poorly consolidated
causing segregation or blocking. surfaces2.
Placeability – A property of fresh concrete ■ Safer working environment3.
representing the relative ease of transporting, The principal benefits of SWC are the
placing, filling, compacting and finishing. characteristics of the fresh mix. It has easy flow with
Binder – The total combined cement and increased cohesion and resistance to segregation but
binding materials in a super-workable places particular demands on the mix design.
concrete.
6
Super-Workable Concrete
Important points to be noted about SWC can be
summarised as:
■ Slower strength gain if high proportions of fly
ash, or ground slag are incorporated2.
■ Because of the higher fines content and
viscosity, it exhibits little or no bleeding2,4.
■ Potential for increased plastic shrinkage
cracking. The curing procedures are therefore,
important, particularly on large, flat exposed
areas2,4.
■ Being more susceptible to quality fluctuations
and batching errors of raw materials, SWC
concretes require stricter quality control,
production control and construction control
than conventional concrete4.
■ Unless the mix design is thoroughly tested
to ensure easy pumpability, the pumping
resistance of SWC may be different to
conventional concrete and should be trialled
in similar conditions to the project prior to the
commencement of the project4.
7
Super-Workable Concrete
2 It is an important requirement to establish
the placeability for fresh concrete; the strength and
Characteristic Performance durability for hardened concrete. The placeability of
fresh concrete is a property required from the time
of SWC immediately after its production through to the end of
placement. Concrete having the required placeability
can be filled into forms uniformly without causing
segregation. This will produce a structure of the
required dimensions with the required accuracy under
2.1 Introduction
the planned construction conditions. The performances
The pre-setting performance of SWC should required of all hardened concrete include strength and
be adequately established to satisfy the permanent durability.
performance requirements of the structure in
consideration of the structural, constructional and
Table 2.1 Ranking of Super-Workable Concrete
other conditions. The concrete may or may not require
compaction by vibration depending on many factors. Rank of structure/member
If no vibration may be required, this concrete is called
Structural conditions 1 2 3
Self-Compacting Concrete.
The performance of SWC should be adequately Minimum space between <60 60–200 >200
established so that the structural performance required reinforcement (mm)
of the whole structure or individual members can be
attained and the requirements for construction can be Amount of steel per m3 >350 100–350 <100
of concrete (kg)
satisfied, in consideration of various conditions. These
conditions include the structural conditions (such as
shapes, dimensions and reinforcement layout) and
2.3 Plastic Properties of SWC
construction conditions (such as methods of concrete
transporting, placing, finishing and curing). The level of
2.3.1 Flowability5
self-compactability for super workable concrete can be
SWC flows under its own weight, filling
set based on its ranking.
formwork and flowing around recesses or embedded
objects without leaving voids. As it is very fluid, it can
2.2 Ranking of Structures/Members flow considerable distances horizontally and upwards
incorporating SWC to fill vertical elements from the bottom.
The ranking levels should be adequately
2.3.2 Passing Around Reinforcement5
established in regard to concrete mix design for SWC
The passability enables SWC, containing the
giving consideration to the shapes, dimensions and
appropriate aggregate size, to flow around congested
reinforcement conditions of the structure/member4.
reinforcement without blocking or affecting the
The three levels of ranking structures/members
homogeneity of the concrete.
incorporating SWC (which may be self-compacting) are
given in Table 2.1. 2.3.3 Segregation Resistance5
The ranking level of general reinforced concrete Segregation after placement can be observed
structures or members should be Rank 2. as surface bleed water and formation of surface mortar
In order to satisfy the performance requirements laitance. Excessive bleeding is as undesirable in SWC
of the structure and its construction requirements, it is as it is in normal concrete.
necessary to select other basic properties of normal Segregation resistance is the most difficult fresh
concrete as well as the special requirements of SWC. property to achieve in unset (plastic) SWC. The most
The latter relate mainly to the plastic state of the critical manifestation of segregation is the separation of
concrete. the mortar from the coarse aggregate fraction even
8
Super-Workable Concrete
though full compaction is achieved. This can cause 2.4.4 Modulus of Elasticity5
settlement of coarse aggregate in deep sections, The relationship between static modulus of
together with blocking around reinforcement, which can elasticity and compressive strength is similar for super-
prevent the free flow of concrete. The required cohesive workable mixes and normal concrete mixes.
nature of SWC in spite of its high fluidity is that there is
2.4.5 Bond Strength5,6
no internal settlement of coarse aggregate particles.
The bond between concrete and reinforcement
2.3.4 Bleed for both medium and high-strength grades of SWC is
Refer to Clause 4.3.3 Flatwork for comments as strong as that of the equivalent normal concrete
on bleeding. mixes.
2.4.3 Shrinkage5
Drying shrinkage has been shown to be similar
or lower than that of normal concrete of the same
grade. This is contrary to that expected from the lower
coarse aggregate content, but is partially explained
by the similar water content of SWC and normal
concrete. The high fines content and viscosity of the
SWC inhibit bleeding and, therefore, evaporation, so
the plastic settlement is reduced. Plastic shrinkage and
associated cracking may be increased as water lost (ie
by evaporation) is not replaced by bleed water. Careful
attention to curing procedures is most important,
especially on large flat exposed areas in highly
evaporative conditions.
The use of evaporation-control methods
(eg evaporative retardants, misting, windbreaks)
during finishing may need to be specified to limit the
occurrence of plastic cracking.
9
Super-Workable Concrete
3 500 and 600 kg/m3 of concrete. Other materials
commonly used for increasing the mortar volume of
Materials and Proportioning SWC are limestone and silica flour; availability, cost
and the influence they may have on the potential for
plastic shrinkage cracking should be considered prior
to project commencement.
10
Super-Workable Concrete
supplementary cementitious materials), apart from If SCMs are included in the mix, their effect
helping gain the desired ultimate strength, is extremely on the plastic properties of the SWC should be
important in maintaining a homogenous SWC that is considered. Research has shown that the addition
free from segregation yet still able to fill intricate voids. of fine pozzolans can make SWC very cohesive and
The binder contents as mentioned above are generally sticky, which may cause difficulties in placement.
in the range of 400–600 kg/m3. It may also be
3.3.2 Basics
advisable to use a viscosity modifying admixture (VMA),
The supplier’s main objective is to produce
especially when producing concrete with total binder
SWC that will flow under its own weight without
contents at the lower end of the scale, say 400 kg/m3.
blocking or segregation, while satisfying all the
3.2.4 Viscosity Modifiers (VMA) performance criteria applicable to the specification. In
Viscosity modifying admixtures are considered order to achieve this property, to ensure the aggregates
to be extremely beneficial in SWC to help maintain remain suspended in the concrete paste and to
a segregation-free concrete. These materials are guarantee a maximum degree of compaction, mix
designed specifically to aid in the production of good designs will differ considerably from those for standard
quality SWC; they will not, however, be beneficial if the or normal grade concretes. With this in mind, the
concrete has too high a water-binder ratio or uses low- proportion of total fines and the maximum aggregate
quality materials or poor proportioning. sizes have to be taken into consideration. Other
VMAs can be formulated from many sources, important considerations are:
the most common are cellulose, synthetic polymers ■ Size of materials – A suitable maximum size
and organic gums including Whelan, Guar and aggregate has been shown to be somewhere
Xanthate gum. They can have quite dramatic effects on between 10 and 20 mm.
SWC, for example if too much of the material is used it ■ Gap-graded mix designs – Mix designs that
can make the concrete extremely sticky and difficult to rely on gap-graded materials as part of their
place. It is recommended that trials be carried out prior mix constituents are likely to result in better
to the project commencing to ascertain the optimum flowing mixes than those using continuously-
dose rate. As previously mentioned these materials are graded materials.
particularly useful when producing SWC with relatively ■ Shape of fine materials – The use of sharp,
low binder contents. VMAs can be classified under angular fine particles as a portion of the mortar
AS 1478.17 as a special purpose admixture and may fall paste can result in a resistance of SWC to flow,
under the abbreviations SN, Sre or SAc depending on mainly due to mechanical interference. A high
the setting characteristics of the particular admixture. degree of sphericity is beneficial.
■ Mix designs that are too cohesive or too
3.3 Proportioning well graded (ie containing a large number
of fine graded aggregates) are not suitable
3.3.1 General in producing SWC as the particles finer than
The mix composition should satisfy all the typical 20 mm used for normal concrete
performance criteria specified for the concrete in both will tend to lock up the concrete’s flow by
the plastic and hardened states. In addition to these mechanical interference.
properties SWC must also possess the following key
characteristics:
■ Fillability – SWC must be able to flow into
all spaces within the formwork without the
addition of water or any other assistance.
■ Passability – SWC must flow through tight
opening between reinforcement without
assistance and without blocking.
■ Resistance to segregation – SWC must meet
the above properties without segregating.
11
Super-Workable Concrete
3.3.3 Initial design methodology
■ Mix design guidelines for SWC inevitably
differ in some respects from those for normal
concrete. Consideration of performance
criteria will influence the type of mix design,
which will be required. Listed in Table 3.1 are
a number of guidelines from various sources,
which have been shown to be beneficial when
designing SWC.
■ Adjustment of the initial mix design may be
necessary. Confirmatory laboratory trial mixes
should be undertaken to verify the plastic
properties of the SWC and used as a basis for
further modifications if required.
■ Water demand is critical. High water demand
often results in segregation and poor
performance.
Suggested
Property CPS 1235 EFNARC3 JSCE4 practical guidelines
Coarse aggregate 50% of bulk density 28%–40% by volume 28%–35% by volume 700–800 kg/m3
content
Sand (fine aggregate > 50% of total > 38% of the mortar To be determined Approximately half
content) aggregate content volume from other figures of total aggregate
content
Cementitious content Around 500 kg/m3 400–600 kg/m3 Not less than Higher than normal
0.16–0.19 m3 by cement contents are
volume usually required
Total water content < 200 litres/m3 < 200 litres/m3 < 185 litres/m3 Excess water
content often results
in uncontrolled
segregation
12
Super-Workable Concrete
4 4.1.3 Batching
At the beginning of a contract, and particularly if
Production Control there is limited experience with SWC, additional expert
personnel may be needed for the supervision of all
aspects of initial production.
The quality of fresh concrete may fluctuate
at the beginning of production, it is therefore
recommended that workability tests be conducted
on every load, until consistent and compliant results
4.1 Concrete Supplier Control
are obtained. Thereafter, every delivered batch should
be visually checked by an experienced and trained
4.1.1 Plant selection
operator before transportation to site. Routine testing
The production of SWC needs to be carried
should be carried out at the frequency recommended
out in plants where the equipment, operation and
in AS 13798.
materials are suitably controlled. Plants that have
production quality systems that conform to ISO 9000 4.1.4 Mixing
or similar quality systems are preferred. Production staff The efficient mixing of SWC is crucial to the end
involved in the manufacture of SWC should be trained product. Cement, aggregates and admixtures should
to understand the differences between SWC and be thoroughly dispersed throughout the concrete.
conventional concrete. This means that the mixing time for SWC needs to
Mixing plants suitable for the manufacture of be pre-determined in trials and applied throughout
SWC are: the production cycle. As stated in Clause 4.1.1
■ Drum, agitator or transit mixer above, mixing times will generally be longer than for
■ Pan mixer conventional concrete. It should be noted that AS 1379
■ Paddle mixer requires mixers to be fitted with an identification plate
Paddles, blades and flights should be in very that shows the agitation speed of the mixer.
good condition to facilitate the thorough mixing that
SWC requires. Generally, the mixing time needs to be 4.1.5 Delivery and Transportation
longer than for conventional concrete; it should be If SWC is to be transported in transit mixer
determined by practical trials. trucks there will need to be an assessment of load
size based on the high workability of the concrete.
4.1.2 Raw Material Storage Generally, because of the fluid nature of the product,
If possible, aggregates should be covered load sizes may need to be reduced in comparison
to minimise fluctuations in surface moisture. During to those for normal concrete. If SWC is transported
production of SWC, tests of aggregate gradings and in kibbles or buckets, the doors or gates on the
moisture contents should be carried out frequently, equipment should be in good condition for opening
since SWC is more sensitive than normal concrete to and closing. The doors or gates should not permit
variations. the loss of cementitious paste or mortar. Depending
A key element in producing SWC is the control on the size of the structure being built, production
of the water-cement ratio. The manufacturing plant capacity, journey time and placing capability need
should be fitted with calibrated and well maintained to be considered. SWC should be designed so that
moisture probes. In addition to these, aggregate workability is maintained to meet the requirements
and sand moisture contents should be tested in the of the contract. Generally, placing should be faster,
laboratory prior to the commencement of production especially if SWC is pumped, but it is essential to make
and at regular intervals throughout the pour. sure that delivery and placing can be completed within
the workability-retention (self-compactability) time of the
concrete.
13
Super-Workable Concrete
Concrete mixed at a remote concrete supply 4.3.3 Flatwork
plant should be transported to the point of discharge SWC, although not originally designed for
by truck-mounted drum mixers complying with the flatwork, has been successfully used in many parts of
requirements of AS 1379. the world in warehouse and workshop facilities.
On completion of mixing, the concrete should Formwork should be constructed to a tolerance
be continuously agitated until it is fully discharged. suitable to maintain the concrete within the forms whilst
The agitation speed should be specified by the minimizing leakage (see Clause 4.4).
manufacturer of the equipment, and should be at the SWC can be placed by chute, kibble or pump. If
ideal charging barrel speed after mixing. a kibble is used, its jaws should be tight enough so that
the SWC does not leak during transporting. In flatwork
14
Super-Workable Concrete
4.3.4 Mass Concrete conventional concrete, type of concrete placement and
SWC is well suited to mass concrete pours, rate, frictional resistance, etc. SWC may be expected
particularly where poor access makes it difficult to to result in reduced pressure on formwork due to the
consolidate the concrete by traditional means. It is, absence of vibration, and generally faster stiffening
however, important to maintain a continual supply after placement at a given concrete temperature. It is
of concrete as any long delays may result in a cold recommended that a detailed (local) testing programme
joint. Where delays have been experienced it may be carried out before (further) reduction factors to
be necessary to vibrate the subsequent concrete liquid/hydrostatic pressure be considered.
into the previous layer, this should be done with a When placing SWC in enclosed spaces
poker vibrator inserted at the appropriate centres. (particularly when pumping from the bottom), vent
Consideration should be given to the placement holes should be provided at appropriate positions in
method so as not to have a freefall of more than 5 m the top of forms to allow expulsion of air.
(see Clause 4.2). Curing requirements should be the
4.4.2 Release Agents
same as for traditional concrete and in line with project
Chemical release agents containing particular
specifications and relevant Australian Standards.
surfactants may put additional pressure on the
4.3.5 Walls/Columns/Beams formwork, by reducing frictional resistance between
This is probably the most appropriate the concrete and the form during concrete placement.
application for SWC. These elements are generally Reference should therefore be made to manufacturers’
heavily reinforced, thus making good compaction recommendations in regard to the selection of a
difficult because of the restricted access for poker suitable release agent. Care should be taken in the
vibrators. With good quality SWC the off-form selection and application of form release agents with
appearance is generally better than that of normal particular reference to the required off-form finishes11.
concrete. Formwork must be of good quality and
4.4.3 Strip Timing
able to withstand the internal pressures of the plastic
Strip timing should be verified with consideration
concrete (see Clause 4.4) with tight tolerances
given to the proposed mix design and applicable site
so that leakage is kept to a minimum. Again, it is
conditions.
extremely important to have continuity of supply
and ample manpower to cope with the size of the
pour. Placement can be by pump, kibble, chute or
tremie and consideration may be given to pumping
from the bottom up, particularly for columns. Curing
requirements are the same as for normal concrete and
in line with project specifications and relevant Australian
Standards.
4.4 Formwork
15
Super-Workable Concrete
5 For more-difficult structures or members where
no previous experience is available it may be necessary
Performance Verification to carry out full-scale field trials to verify the suitability
of the concrete.
16
Super-Workable Concrete
Table 5.1 Test Methods for Various Properties
Filling ability A.2 Slump Flow A.2 Slump Flow T500 and Dfinal can be measured
Passing ability A.3 Slump Flow and J-ring A.3 Slump Flow and J-ring T500 and Dfinal can be measured
A.4 L-box – –
Resistance to A.2 Slump Flow A.2 Slump Flow T500 and Dfinal can be measured.
segregation Can only give a visual indication of
sergegation; it is not a conclusive test
A.6 GTM Screen Stability – Suitable only for initial laboratory trials
at design stage
Note: Reference should also be made to Table B.1 (Appendix B) for guidance on specification
17
Super-Workable Concrete
A A.2 Slump Flow Test Method
18
Super-Workable Concrete
A.2.3 Test Procedure A.2.4 Interpretation of Result
■ Level and check that the board is on a stable ■ The Dfinal measurement is an indication of flow.
and horizontal surface. The greater the final diameter the greater the
■ Moisten the surfaces of the plate, sample fillability of the concrete.
bucket and cone, removing any excess water. ■ The T500 time is a secondary indication of flow.
■ Centre the slump cone on the board. A lower time indicates a greater ability to fill
■ Sample concrete representatively formwork under its own weight.
(approximately 8.5 litres). ■ In the case of severe segregation most
■ Remix samples prior to use by transferring coarse aggregate will remain in the centre
from initial sub-sample buckets into other of the pool of concrete and mortar paste at
buckets of equivalent size to ensure a the periphery. In case of minor segregation
homogenous sample. a border of mortar without coarse aggregate
■ Stand on cone bottom flange, fit a funnel to top can occur at the edge of the pool of concrete.
of cone aperture, and fill cone by pouring in This test method can give a visual indication of
concrete continuously until it reaches the top segregation, but it is not a conclusive test for
edge. Do not tamp. segregation of the concrete in the final form.
■ Remove the funnel, trowel off any excess
concrete from top, and clean the plate of spills.
■ Transfer and maintain hold-down pressure from ���
feet to hands on cone handles.
■ Simultaneously commence stop watch and
raise the cone vertically by a steady upward lift ���
without interruption, such that the cone is clear ������
of the concrete sample within 2 to 3 seconds.
■ Measure, record and report the time, to the ���
nearest 0.1 second, for the spreading concrete
�����������final
to reach the marked 500-mm circle (T500).
�����������500
■ Measure and record the final diameters of
the concrete spread in two perpendicular ������
directions. If the two measurements differ by ��������
more than 50 mm, then the test is deemed to
be invalid and must be repeated. Report the
final diameter of the concrete spread as the
average of two perpendicular diameters, to the
nearest 10 mm (Dfinal).
■ Review and report visually detectable Figure A.2.1
segregation. Flow Table and Modified Slump Cone
19
Super-Workable Concrete
A.3 Slump Flow And J-Ring Test Method A.3.3 Test Procedure
■ Level and check that the board is on a stable
A.3.1 Overview
and horizontal surface.
The test method is used to indirectly measure
Moisten the surfaces of the plate, sample
■
■
the ability of a concrete with a maximum
bucket, cone and J-Ring, removing any excess
coarse aggregate size of 20 mm or less, to
water.
flow into all spaces within the mould (fillability)
■ Centre the J-Ring and slump cone on the
and flow through tight spaces and openings
board.
(passability) under its own weight.
■ Sample concrete representatively
The test method is a simple, rapid test
(approximately 8.5 litres).
■
20
Super-Workable Concrete
A.3.4 Interpretation of Result
■ The Dfinal measurement is an indication of flow.
The greater the final diameter the greater the
fillability of the concrete.
■ The T500 time is a secondary indication of flow.
A lower time indicates a greater ability to fill
formwork under its own weight.
■ The J-Ring Passing Ability Difference is an
indication of segregation resistance. The
greater the value, the less the passability of the
concrete.
■ Blocking and/or segregation can also be
detected visually. In the case of severe
segregation most coarse aggregate will remain Figure A.3.2
in the centre of the ring and mortar paste at Typical Test Result
the periphery.
���
���
���
�����������final
�����������500
���
Figure A.3.1
Flow Table, J-Ring Assembly and Modified Slump
Cone
21
Super-Workable Concrete
A.4 L-Box Test Method A.4.3 Test Procedure
■ Set L-Box on a horizontal plane.
A.4.1 Overview
■ Moisten the surfaces of the L-Box and
The test method is used to indirectly measure
sampling buckets, removing any excess water.
■
22
Super-Workable Concrete
A.4.4 Interpretation of Result
■ The Filling Ratio is an indication of flow value.
The closer the value to 1, the higher the flow of
concrete.
■ The L-Box Passing Ability Difference is an
indication of segregation resistance. The
greater the value, the less the passability of the
concrete.
■ After 5 minutes of setting, segregation of
concrete will show a less continuous flow with
an increase in flow time.
■ Blocking and/or segregation can also be
detected visually. In the case of severe
segregation considerable coarse aggregate
will remain behind the reinforcement and
mortar paste only at the opposite end of the
box.
���
���
������������������
��������� Figure A.4.2
���
��� Typical L-Box
���
�1
�2
Figure A.4.1
L-Box Details and Application
23
Super-Workable Concrete
A.5 Orimet Test Method A.5.3 Test Procedure
■ Set funnel approximately vertical.
A.5 Overview
■ Moisten the surfaces of the funnel, removing
The test method is used to indirectly measure
any excess water.
■
24
Super-Workable Concrete
A.5.4 Interpretation of Result
■ The test measures the ease of flow of the
concrete through an orifice, shorter times
indicate greater flowability.
■ The inverted-cone shape at the orifice
restricts flow, and prolonged flow times or
discontinuous flow may give some indication of
the susceptibility of the mix to blocking and/or
segregation.
���
���
����
��
Figure A.5.2
Orimet Funnel Pipe
Figure A.5.1
Orimet Funnel Pipe Details
25
Super-Workable Concrete
A.6 GTM Screen Stability Test Method A.6.3 Test Procedure
■ About 10 litres of concrete is needed to
A.6.1 Overview
perform the test, sampled normally.
This test has been developed by the French
■ Allow the concrete in the bucket to stand
contractor, GTM, to assess segregation resistance
for 15 minutes covered with a lid to prevent
(stability). The test consists of taking a sample of
evaporation.
10 litres of concrete, allowing it to stand for a period to
■ Determine the mass of the empty sieve pan.
allow any internal segregation to occur, then pouring
■ Inspect the surface of the concrete; if there is
half of it onto a 5-mm sieve of 350-mm diameter which
any bleed water, note it.
stands on a sieve pan on a weigh scale. After two ■ Put the top 2 litres or approximately 4.8 kg
minutes, the mortar which passed through the sieve is ± 0.2 kg only of the concrete sample in the
weighed, and expressed as a percentage of the mass bucket, into a pouring container.
of the original sample on the sieve. ■ Determine the mass of the filled pouring
Practising engineers who have used this test container.
say it is a very effective way of assessing the stability ■ Determine the mass of the empty sieve pan.
of SWC. However, though simple, it is not a rapid test, ■ Pour all the concrete from the pouring
and requires an accurate weigh-scale, so the test may container onto the sieve from a height of
not be suitable for site use. 500 mm in one smooth, continuous movement.
The repeatability of results may be questionable. ■ Weigh the empty pouring container.
26
Super-Workable Concrete
B
Appendix B Specification
Guide
Table B.1 Evidence on Values of Properties Assessed by Test Methods Described in Appendix A
27
Super-Workable Concrete
References Bibliography
28
Super-Workable Concrete
Z40 Super-Workable Concrete RECOMMENDED PRACTICE
Super-Workable Concrete
SWC