Professional Documents
Culture Documents
Concrete Institute of Australia - Recomended Practice - Z36 Formwork Handbook
Concrete Institute of Australia - Recomended Practice - Z36 Formwork Handbook
Concrete Institute of Australia - Recomended Practice - Z36 Formwork Handbook
CONCRETE INSTITUTE
of AUSTRALIA
RECOMMENDED PRACTICE
Z36
Formwork Handbook
RECOMMENDED PRACTICE
Z36
Formwork Handbook
Z36
Z36
Formwork
Handbook
i
Formwork Handbook
Ramsetreid
ii
Formwork Handbook
Warning
This publication should not be used without the services of a competent professional person with expert knowledge
in the field, and under no circumstances should this publication be relied upon to replace any or all of the
knowledge and expertise of such a person.
iii
Formwork Handbook
iv
Formwork Handbook
The motivation for creating this Handbook In 2002, the Standing Committee on Structural
comes from a strong belief that the health and safety of Safety (SCOSS) in the UK warned that there is a need
construction workers should not be put at greater risk to carefully consider the means by which falsework
from structural failure than other workers. Unfortunately, is currently procured, designed, constructed and
in Australia and elsewhere, this is not the case. In supervised. Furthermore, that judging from the
practice, the frequency of structural failure and the evidence, it is only a matter of time before a serious
general risk of death is much higher during construction event occurs. As recently as 2010, SCOSS reported
than, later, during the service life of the completed that these concerns remain pertinent.
In the past, a higher frequency of structural issues identified in the UK apply to Australia”. However,
failure may have been tolerated because of an the frequency of formwork and falsework collapse over
underlying tacit attitude in the design and construction recent years support this view.
industry that temporary structures, such as formwork, To address the shortcomings identified, SCOSS
are less important than permanent structures and recommended compiling courses that include elements
therefore greater risks are acceptable. However, this is on procurement, statutory responsibility and managing
no longer the case. the supply chain, as well as the technical issues
failure agree procedural inadequacies enable To this end, this text may help by providing
flaws in the design and/or construction to go guidance on procedures, requirements and methods for
the design and construction of formwork and falsework
undetected. Examples of procedural inadequacies
to comply with Australian Standards and Work Health
include: communication difficulties and confusion of
and Safety Regulations.
responsibilities among participants; inadequate briefing
of designers; the lack of design drawings; inadequate
checking of designs (particularly those containing novel ACKNOWLEDGEMENTS
features); unapproved modifications of the initial design; I would like to acknowledge the contribution
or failure to inspect work prior to loading. Although this and thank: the staff at Syntect Consulting Engineers
research was carried out 30 to 40 years ago, formwork (Simon Johnson, David Webster and Nicholas Ho) for
collapse and failure continues to occur all too often and all their help in putting this Handbook together; Harry
the findings are just as applicable today as then. Backes and John Woodside for their comments; and
Implicitly, the higher frequency of structural Ian Gilbert for his help with Chapters 9 and 10. I also
failure also casts doubt on the competence of those wish to acknowledge the contribution and counsel of
involved in the design and construction of formwork and my co-author Douglas Crawford (Chairman of Australian
falsework. This premise is supported by researchers Standards Committee BD-043 responsible for AS 3610)
who interviewed those responsible for the design and and the work of all BD-043 committee members.
construction of the majority of falsework in the UK. The Special thanks must go to Eur Ing Peter F. Pallet
researchers found that: who kept me up-to-date with changes happening to
(a) At all levels of the industry there is a lack of the Euro and British Standards, and freely shared his
understanding of the fundamentals and basic expert knowledge and the wealth of information he has
principles involved in achieving the stability of published.
falsework; Stephen Ferguson
(b) The contracting sector does not appreciate
v
Formwork Handbook
vi
Formwork Handbook
vii
Formwork Handbook
viii
Formwork Handbook
ix
Formwork Handbook
x
Formwork Handbook
xi
Formwork Handbook
xii
Formwork Handbook
Figure 1.1: Soffit formwork includes soffit forms and supporting falsework
1:1
Formwork Handbook
1:2
Formwork Handbook
1:3
Formwork Handbook
1:4
Formwork Handbook
1:5
Formwork Handbook
1:6
Formwork Handbook
1:7
Formwork Handbook
1:8
Formwork Handbook
1:9
Formwork Handbook
2:1
Formwork Handbook
For example: situations where formwork is not disposal of the structure; and
fabricated off-site. ■ At or in the vicinity of a workplace are exposed
to the structure or whose health and safety may
2.1.2 Scope be affected by an activity related to the structure.
This Chapter sets out the procedures, roles, To fulfil these obligations, the project designer
responsibilities and requirements consistent with safe must communicate, consult, and work together with
formwork design and construction for each participant, those involved in the construction about potential risks
namely: project designer (see Section 2.2), construction and solutions.
contractor and formwork coordinator (see Section 2.3), The project designer must provide information
formwork supplier (see Section 2.4), formwork designer in relation to the formwork, which AS 3610.1:2010 (SA
(see Section 2.5), formwork checker (see Section 2010) calls “project documentation”, that:
2.6), formwork contractor (see Section 2.7), formwork (a) Specifies the requirements associated with
supervisor (see Section 2.8); and formwork inspector the design and construction of the concrete
(see Section 2.9). structure and its elements (SA 2010); and
Section 2.10 provides guidance on obligation (b) Provides information in relation to hazards and
and competency for those involved in design, checking risks at or in the vicinity of the construction
and inspecting formwork. site, including specifying the hazards relating to
the design of the structure that create a risk to
2.2 PROJECT DESIGNER the health and safety of those carrying out the
The project designer has an obligation to construction work.
be aware of and ensure the design is achievable Where the project documentation is incomplete
using current construction practice, methods and or unclear, the project designer must respond in writing
workmanship (SA 1996). to requests from the construction contractor for missing
Work Health and Safety Regulations (SWA 2011) information or clarification.
also place obligations on project designers to ensure,
so far as is reasonably practicable, that the structure is 2.2.1 Project documentation
designed to be without risks to the health and safety of The project documentation must communicate
persons who: specific requirements associated with the design
■ At a workplace, construct the structure; and construction of the concrete structure and its
■ At a workplace, carry out any reasonably elements; including, where appropriate, instructions and
foreseeable activity in relation to the information relating to concrete surface finish.
manufacture, assembly, use, demolition and Guidance is provided in AS 3610.1:2010 that the
2:2
Formwork Handbook
2:3
Formwork Handbook
2:4
Formwork Handbook
2:5
Formwork Handbook
2:6
Formwork Handbook
1 Registration of prefabricated formwork is not required if the design was started before 1 January 2012 and completed prior to 1 January 2014;
otherwise, unregistered prefabricated formwork must not be supplied. This requirement may not apply in all States.
2:7
Formwork Handbook
2:8
Formwork Handbook
2:9
Formwork Handbook
2:10
Formwork Handbook
2:11
Formwork Handbook
2:12
Formwork Handbook
conditions are all in accordance with the formwork removal of any part of the formwork or multistorey
design documentation, the person inspecting the shoring may be hazardous and may have detrimental
formwork construction shall certify in writing that the effects on the surface finish, serviceability, strength or
formwork construction complies with the design, stability of the concrete structure.
including stating: Chapter 9 provides general guidance on criteria
■ Their name(s) and qualifications; for stripping formwork and multistorey shoring.
■ Whether they were or were not involved in the
design or checking; 2.10 OBLIGATION AND COMPETENCE
■ The details of formwork construction that has The concept of Formwork Risk Level provides
been inspected; a useful framework for specifying appropriate levels of
2:13
Formwork Handbook
Level Formwork design and Formwork design check and Formwork inspection and
of documentation certification certification
Risk
Obligation Competence Obligation Competence Obligation Competence
Low Mandatory Experienced Optional Experienced Mandatory Experienced
obligation and competence for situations with different organisation not involved in the original design.
levels of risk. In practice, most formwork is designed by
For formwork design, documentation, checking “experienced” persons who may not possess formal
and certification, as well as inspecting the formwork qualifications. Some authorities (WorkCover NSW 1998)
construction, Table 2.2 sets out appropriate levels of do not require the formwork design be checked and
obligation and competence for situations with different certified, but rather, require a qualified person to inspect
levels of risk. A method for selecting the appropriate and certify the formwork construction prior to concrete
level of risk for different situations is set in Appendix A. placement where the level of risk is moderate or high.
The level of competency required in Table Unfortunately, inspections are often called
2.2 increases with risk. Accordingly, the levels of the at the last minute at a time when the formwork may
competence are, or the approved equivalent of: be incomplete. It may be difficult to access all parts
Experienced – A person who has a minimum of of the formwork. Inspectors may be unfamiliar with
4 years site experience in construction of the particular project requirements, the formwork brief and design.
type of work. Furthermore, construction cost and time pressures
Qualified – A professional engineer who has may sway inspectors to haste or to compromise and
qualified as a member of Engineers Australia (MIEAust) approve formwork or modifications thereto, which
and who has a minimum of 4 years’ experience in the in other circumstances would not have happened
design and construction of the particular type of work. and may have delayed concrete placement. Where
Chartered – A professional engineer who is inspections are the only form of checking, especially in
a member of Engineers Australia with the status of less than ideal circumstances, there is a higher risk that
Chartered Professional Engineer (CPEng) or a person flaws in the design or construction will go undetected.
registered on the National Professional Engineers For the majority of formwork (with a moderate
Register (NPER), or if there is a law that provides for level of risk), Table 2.1 requires the design be checked
registration of professional engineers, is a registered by a qualified person prior to construction commencing.
professional engineer, and who has a minimum of 4 In this way, design flaws should be detected prior
years’ experience in the design and construction of the to construction and subsequent inspection, thereby
particular type of work. reducing the onus on inspectors and reducing risk.
Independent – A professional engineer who
is a member of Engineers Australia with the status of
Chartered Professional Engineer (CPEng) or a person
registered on the National Professional Engineers
Register (NPER), or if there is a law that provides for
registration of professional engineers, is a registered
professional engineer, and who has a minimum of
4 years’ experience in the design and construction
of the particular type of work, and employed by an
2:14
Formwork Handbook
2:15
Formwork Handbook
3.1 INTRODUCTION
3.2 STABILITY, STRENGTH
Formwork should satisfy the requirements set AND SERVICEABILITY
out in the relevant Work Health and Safety Regulations,
Australian Standards and Codes of Practice. To do
3.2.1 Limit states design
so, formwork should satisfy fundamental structural
In the context of structural design, the word
requirements to: be safe, be fit for its purpose and
“state” means “the condition of a structure”.
consistently perform as intended through-out its design
The fundamental concept of limit states is that
working life.
a structure can be classified as either satisfactory
As a minimum, the formwork design should:
1. Identify hazards and assess the risks; (serviceable, safe) or unsatisfactory (unserviceable,
2. Eliminate the hazards, or if not reasonably unsafe) (Gulvanessian and Holicky 1996). Thus, if the
practicable, control the risk of injury; condition of a structure exceeds any limit state, a limit
3. Satisfy stability, strength and serviceability limit state violation is said to have occurred as it no longer
states; and satisfies the fundamental performance requirements.
4. Possess structural integrity; i.e. have a minimum Often people make statements such as “I’ve
level of connectivity, robustness and resist done it this way thousands of times before and never
progressive collapse. had a problem”. What does this really mean? It means
The first two points are discussed at length that, on each past occasion, the load on the structure
in Chapter 2. This Chapter provides guidance was less than its capacity. How much less or whether it
on requirements to satisfy stability, strength and will be less on the next occasion are all unknowns. The
serviceability limit states specific to formwork. General structure may have been serviceable, but was it safe?
issues regarding structural integrity and the concept of If it was possible to test structures to failure a
design working life are also discussed. sufficient number of times, it would be possible to use
The philosophy and principles of structural the data collected to verify the reliability of a structure
design presented herein are consistent with those set using purely probabilistic techniques.
out in ISO 2394:1998 General principles on reliability for Figure 3.1 expresses a simplistic relationship
structures (ISO 1998), and AS/NZS 1170.0 Structural between the distribution of action effects E and
Figure 3.1: Probability distributions for design action effects and design resistance
3:1
Formwork Handbook
In Equation 3.2, En is the nominal action effect, should not be disproportionate to the original cause.
Rn is the nominal resistance, γ is a partial load factor, A practicable approach is to design the
and φ is a capacity reduction factor. The values for formwork for ordinary use in ordinary circumstances
the partial factors and methods of determining the and take the following additional measures:
nominal action effect and resistance are specified in the (a) Design the structure with minimum levels of
applicable structural Standard. They are carefully chosen structural integrity and to avoid progressive
to take account of uncertainties about the probability collapse, see Section 3.4;
distributions of the action effects and resistance, as well (b) Take protective measures against foreseeable
as the mode and consequence of failure. actions. For example, safeguard against impact
Factors affecting the probability of failure and by providing additional protection such as
therefore influencing the choice of partial factors bollards; and
include: choice of the values of actions; degree of (c) Reduce the probability of gross design and
structural integrity; accuracy of structural models used; construction errors by appropriate quality
quality and durability of materials and equipment; assurance and/or quality control measures; e.g.
site conditions; environmental conditions; quality of follow the procedures set out in Chapter 2.
workmanship; and measures taken to reduce the risk of
gross human, design and construction errors. 3.2.2 Stability (limit states)
In some situations, the choice of partial factors Formwork must be stable (i.e. resist sliding,
should ensure an even lower probability of failure. For overturning and uplift) under extreme and/or frequently
example where: repeated actions.
(a) The risk of injury, economic, social and Stability limit states are concerned with the
environmental losses is greater; or loss of equilibrium of the formwork or any part of it,
(b) Collapse occurs suddenly and without warning, considered as a rigid body, due to overturning, uplift
rather than where collapse is preceded by some and sliding. For example, the possibility of suspended
kind of warning in such way that measures can slab formwork and falsework overturning, lifting or
be taken to limit the consequences. sliding under extreme wind actions or a cantilever
However, satisfying Equation 3.2 does not bearer subject to overturning if only the cantilever is
guarantee that a structure or part of it will not fail. Failure loaded. It is good practice to check stability limit states
may occur due to: first.
where
Ed = design action effect (see Section 4.3.2); and
Rd = design resistance or capacity (φRn).
The partial load factors and action combinations
for strength limit states are set out in Section 4.3.2.2.
3:3
Formwork Handbook
In addition to member deflection, variant the visual quality is not important. Class 4 has good
formwork material and fabrication compounded by general alignment, while for Class 5 even alignment is
imprecise erection will also detract from the formwork not important.
quality and consequently the concrete surface. For Guidance on the design and detailing of
example, deformations in the concrete surface will arise formwork to achieve colour control is beyond the
from variations due to: scope of this text, (refer to CS 1999; CCAA 2006; ACI
■ permitted dimensional tolerances of graded 2013). However, guidance is provided herein on the
timber; appropriate serviceability deflection limits to use in
■ welding heat deformations during fabrication design.
steel formwork; or The stiffness of formwork is important because
■ the presence of small gaps between framing it affects both the quality of the surface finish and
members. dimensional accuracy of the concrete. Formwork
deformations should not exceed the limits specified
AS 3610 in AS 3610.1:2010 Clause 3.3.4 and Table 3.3.2. The
AS 3610.1:2010 (SA 2010) classifies and acceptable surface finish deformation caused by form
specifies the requirements for the physical quality and face deflection and concrete surface undulations given
colour control of the concrete surface finish. There in AS 3610.1:2010 Table 3.3.2 are repeated here in
are five classes (1 to 5) of surface finish. Where colour Table 3.1.
control is incorporated it is denoted by the suffix C The format for the acceptable deformation for
following the surface finish number, e.g. Class 2C. surface undulations is useful for assessing the physical
Class 1 is the highest attainable quality and quality of the concrete surface (see AS 3610.1:2010
should only be specified for use in very special Clause 5.2.2(b) and Figure 3.3). However, it is not
cases. Class 2 has uniform quality and texture and is convenient for the purpose of formwork design and
commonly specified for architectural work. Class 3 is AS 3610.1:2010 does not provide guidance on the
specified with the intention that the concrete is to be acceptable limits for surface undulations for a given
viewed as a whole. Classes 4 and 5 are specified when span.
3:4
Formwork Handbook
In this case it is useful to consider the limits for sectional dimension of 1/200 times the specified
surface undulations expressed in terms of straightedge dimension or 5 mm, whichever is the greater;
length (l) as span to deflection ratios, see Table 3.2. and
The values expressed in Table 3.2 are intended ■ deviation from surface alignment, in that the
to result in a concrete surface finish that will comply deviation of any point on a surface of a member,
with the requirements of Table 3.1, but may be more from a straight line joining any two points on the
stringent. surface, shall not exceed 1/250 times the length
For example, consider using a straightedge that of the line.
is 1500 mm long to check undulations for a Class 2 Recommended serviceability limits for
surface. Assume readings a and b are taken only member deflection
600 mm apart (l = 2 x 600 = 1200 mm) such that (a – b) Serviceability limits for deflection must satisfy
= 3 mm and satisfies both the 90 and 100 percentage the more severe of the requirements set out in AS
limits of Table 3.1. When expressed as a span to 3610.1:2010 and AS 3600.
deflection ratio, l/(a – b) = 1200/3 = 400, which could be
Form face deflection and surface undulations
interpreted to mean Table 3.1 permits undulations of up
will run parallel with the members primarily responsible
to l/400 rather than the more stringent criteria of l/500
for the deformation. Therefore, measurements of form
specified in Table 3.2.
face deflection and surface undulations should be taken
By observation, for short spans the requirements
in the direction of the undulation; i.e. with straight-edge
for form face deflection are more severe than surface
parallel to the member span (form face, secondary
undulation limits for a similar length straightedge (i.e.
or primary member). Thus, these deformations are
where l = 300 mm) and will govern design. For longer
primarily the result of the deflection of a single member.
spans, where the deflection of secondary and primary
However, measurements for surface alignment
members plays a major role, the limits for surface
to AS 3600 may be taken in any direction and therefore
undulation will govern serviceability limit states for the
may take account of the accumulated deflection of
deflection of secondary and primary members.
two or more members. Thus, to satisfy the AS 3600
AS 3600 surface alignment limit of 1/250 times the length of the
In addition, formwork must also satisfy the line (span), the total deflection (secondary plus primary
tolerances specified in AS 3600 Concrete structures member deflection) must be less than span/250.
(SA 2009), which provides permitted tolerances for Table 3.3 shows recommended serviceability
plumb, dimensions and surface alignment of concrete limits for deflection for use in the design of formwork
structures and members. In particular, consideration members. They are intentionally more stringent than
should be given to the: the acceptable concrete surface deformations and
■ floor-to-floor plumb tolerance for columns and alignment tolerances permitted in AS 3610.1:2010 and
walls of 1/200 or 10 mm, whichever is the AS 3600 because they are intended to make allowance
greater; for variant formwork material and fabrication, as well
■ deviation from specified height, plan or cross- as deflection, and satisfy both AS 3610.1:2010 and AS
3:5
Formwork Handbook
3:6
Formwork Handbook
fy = yield stress of steel ply. φRn = strength limit states design resistance or
Satisfying this requirement should limit hole capacity;
deformations to 2% of hole diameter. LSD = limit states divisor that satisfies LSD ≥
1.5, unless a lessor value is justified by a
3.2.5 Working load limit (WLL) rigorous statistical analysis of load and
AS 3610.1:2010 requires suppliers of proprietary capacity data using probability methods
formwork to publish the strength and serviceability (SA 2003)1; and
limit states capacities and working load capacity of Es.max = maximum action effect satisfying
proprietary formwork, as calculated in accordance serviceability limit states.
with AS 3610:1995 (SA 1995). The requirement to
publish both limit states and working load capacities is 3.3 STRUCTURAL INTEGRITY
intended to minimise the risk of misunderstanding and Formwork must satisfy minimum structural
possible “overloading” of the formwork up to its limit integrity requirements so that the formwork is not
states capacity, if only the limit states capacities were damaged disproportionally as a consequence of impact
published. or due to human error. In addition, formwork must resist
The working load limit (WLL) should satisfy the progressive collapse.
following conditions for strength and serviceability:
I5Q 3.3.1 Robustness
:// d (3.8)
/6' Formwork should be designed so that any
and damage due to impact or occurring as a consequence
://(VPD[ (3.9) of human error is not disproportionate to the original
where cause. Figure 3.4 shows an example of a robust
1 Prior to the publication of SA (2003). Amendment No. 1 to AS 3610:1995 Formwork for concrete. Sydney, Standards Australia, AS 3610:1995
Clause A4.4.4 permitted working load capacities to be derived from the limit state capacity using a divisor of less than 1.5 (based on the load
factors given in AS 3610:1995 Table 5.1); however, calculating the working load capacity using this method was unreliable.
3:7
Formwork Handbook
3:8
Formwork Handbook
3:9
Formwork Handbook
with little or no modification or cutting. Project steel formwork shores. Master of Engineering (Honours),
designers might realise these savings by judicious University of Western Sydney.
selection of building dimensions. Gulvanessian, H. and M. Holicky (1996).
Where the quality of the concrete surface finish Designers’ Handbook to Eurocode 1: Part 1 Basis of
is important, false economies arise when short cuts in design. London, Thomas Telford.
design and construction of formwork result in non-
Hadipriono, F. C. and H.-K. Wang (1986).
conformance and costly remedial work.
“Analysis of causes of formwork failures in concrete
Economies may also be achieved in formwork
structures.” Journal of Construction Engineering and
material handling. This happens where mechanical
Management 112: 112-121.
and automated machines can increase productivity by
ISO (1998). ISO 2394:1998 General principles
handling large formwork assemblies, negating the need
on reliability for structures. Geneve, International
for them to be dismantled and re-assembled after each
Organization for Standardization.
use.
McAdam, P. S. (1993). Formwork: A practical
REFERENCES approach. Brisbane, Stuart Publications.
ACI (2013). Guide to Formed Concrete Surfaces. SA (1990). AS 3610:1990 Formwork for concrete.
Farmington Hills, American Concrete Institute. Sydney, Standards Australia.
Bragg, S. L. (1975). Final report of the Advisory SA (1995). AS 3610:1995 Formwork for concrete.
Committee on Falsework. London, Her Majesty’s Sydney, Standards Australia.
Stationery Office: 151. SA (1995). AS 3610 Supplement 1 – 1995
Bridge, R. Q., T. Sukkar, I. G. Hayward and Formwork for concrete – Blowhole and colour
M. Van Ommen (2002). “The behaviour and design of evaluation charts. Sydney, Standards Australia.
structural steel pins.” SA (1996). AS 3610 Supplement 2 – 1996
CCAA (2006). Guide to Off-form Concrete Formwork for concrete – Commentary. Sydney,
Finishes. Sydney, Cement and Concrete Association of Standards Australia.
Australia. SA (1998). AS 4100:1998 Steel Structures.
CS (1999). Technical Report 52: Plain formed Sydney, Standards Australia.
concrete finishes. Berkshire, The Concrete Society. SA (1999). DR99481 Formwork for concrete
Ferguson, S. A. (2003). Limit states design of (Draft Australian Standard – Revision of AS 3610:1995).
3:10
Formwork Handbook
SA (2003). AS/NZS 1170.3: Structural design SAA (1974a). AS 1509:1974 SAA Formwork
actions Part 3: Snow and Ice actions. Sydney, Code. Sydney, Standards Association of Australia.
Standards Australia. SAA (1974b). AS 1510 Part 1 – 1974 Control of
SA (2005). DR05029 Formwork for concrete Concrete Surfaces – Formwork. Sydney, Standards
(Draft Australian Standard – Revision of AS 3610:1995). Association of Australia.
Sydney, Standards Australia. SAA (1975). AS 1793:1975 Limit State Design
Method. Sydney, Standards Australia.
3:11
Formwork Handbook
4:1
Formwork Handbook
4:2
Formwork Handbook
4:3
Formwork Handbook
4:4
Formwork Handbook
Recommendations for stacked materials in AS act concurrently; i.e. the formwork design should take
3610:1995 account of Quv + M; i.e.
AS 3610:1995 requires the project designer to Stage 1: Quv1 + M1 = 5.0 kPa;
place limits on the timing, magnitude and location of Stage 2: Quv2 + M2 = 1.0 kPa (i.e. materials are not
stacked materials. In the absence of specified limits stacked on wet concrete); and
on stacked materials, AS 3610:1995 recommends the Stage 3: Quv3 + M3 = 5.0 kPa.
design load for stacked materials to be: Recommendations for stacked
Stage 1: M1 = 4.0 kPa; materials in the literature
Stage 2: M2 = 0 kPa (i.e. materials are not stacked Guidance on the appropriate magnitude of
on wet concrete); and stacked materials can be found in literature that analysed
Stage 3: M3 = 4.0 kPa. data collected from site surveys that weighed every
piece of material and mapped its location (Ayoub and
AS 3610:1995 also considers the load from
Karshenas 1994; Karshenas and Ayoub 1994). Ayoub
workers and equipment (Quv) and stacked materials (M)
4:5
Formwork Handbook
4:6
Formwork Handbook
Figure 4.5: Horizontal actions from construction activity acting on formwork of a 20 m × 10 m concrete slab
4:7
Formwork Handbook
Table 4.3: Ultimate limit states regional wind speeds, m/s wind, snow and earthquake events
Level Region
of Risk A (1 to 7) W B C D
Low 37 43 39 47 53
Ordinary 41 47 48 59 73
High 45 51 57 69 88
1 The working design wind speed represents the 3 second gust wind speed for permissable
stress design, which is greater than the mean wind speed measured on site.
4:8
Formwork Handbook
In this text, the notation S replaces Xw used in overhead or mobile cranes operate, there is some
AS 3610:1995. risk of impact from crane loads landing on top of the
Where formwork is erected in water, take formwork. In this situation, in addition to the weight of
account of actions by river currents, tides, waves and the lifted load, an allowance of not less than 25% of
flooding. These actions may include: the dynamic the weight of the lifted load should be applied to the
pressure of the water; impact from floating objects; the formwork.
effects of increased frontal area and head of water due
to trapped debris; buoyancy and uplift. 4.2.5.2 Horizontal impact (Ah)
When formwork is erected on sites where
4.2.4.4 Earthquake (Eu) overhead or mobile cranes operate, there is some risk
It would be unusual to design formwork or of impact from crane loads, as shown in Figures 4.6
falsework to resist earthquakes. Inherently, satisfying and 4.7. For example, in the situation depicted in Figure
robustness requirements set out in Chapter 3 provides 4.6, the impact of a 2700 kg kibble of concrete travelling
a sufficient resistance. at 3 km/h and coming to rest in a distance of 25 mm is
If it were necessary to design formwork to resist equivalent to 40 kN (SA 1996).
4:9
Formwork Handbook
Figure 4.7: Impact from moving crane load (McAdam and Lee 1997)
When formwork is erected adjacent to or notional actions to determine the combined effect of all
bridges access for vehicles, there is some risk of impact other concurrent actions factored in accordance with
from those vehicles, as shown in Figure 4.8. the relevant combination under consideration. Thus,
When formwork assemblies are crane handled, the magnitude of the notional load and its effects will
there is risk of collision with another object during lifting. vary depending on the combination of actions under
consideration, see Section 4.3.
4.2.6 Notional actions (N1, N2 and N3)
Notional actions are applied to idealised 4.2.6.1 Notional horizontal forces for initial
out-of-plumb erection (N1)
“perfect” structural models to take account of permitted
structural imperfections that have a significant influence AS 3610:1995 permits falsework, intended to be
on the structural behaviour; otherwise, the strength and vertical, to be erected out-of-plumb up to an inclination
stability of the structure may be overestimated; e.g. N1 of 1 in 200 or a maximum horizontal displacement of
for initial out-of-plumb and N2 for bracing forces. 40 mm. This may be taken into account by analysing a
As structural imperfections are present at all structural model of the formwork, incorporating:
times, notional actions should be considered to act (a) out-of-plumb members; or
concurrently and in combination with other actions. (b) vertical members and notional horizontal
Notional actions are also used to achieve forces equal to 0.01 times the sum of the
minimum levels of structural integrity; e.g. N2 for bracing vertical design actions acting at each point of
stiffness and N3 for minimum levels of robustness. application, see Figure 4.9.
In Figures 4.9, 4.10 and 4.11, the forces F1 to The value of 0.01 is consistent with the
F8 represent vertical actions acting on the falsework at requirements of other national standards; e.g. (ECS
each location. The magnitude of each force F1 to F8 is 2004; Tayakorn and Rasmussen 2009). It also reflects
calculated by first analysing the structure without any the results of research that measured the effects of
4:10
Formwork Handbook
Figure 4.10: Notional forces to ensure braces have the minimum brace strength and stiffness
permitted out-of-plumb tolerances in steel structures Notional forces (N2) are intended to ensure
and recommends a value for the notional force of twice the members that brace compression members to
the permitted out-of-plumb tolerance, i.e. reduce their effective length have sufficient strength to
resist the forces arising in the bracing due to permitted
u
out-of-straightness and to achieve the minimum brace
The notional force should be considered to act, stiffness needed to be effective in reducing member
in either direction, in combination with direct actions effective length.
for serviceability, stability and strength limit states, see Notional forces (N2) should be applied at each
Section 4.3. bracing point in a manner that minimises the residual
4.2.6.2 Notional forces for braces that reduce the forces accumulating at points of restraint. For example,
effective length of compression members in the arrangement shown in Figure 4.10, within each
(N2) structure, the forces on each level of bracing are
For free standing falsework, notional forces (N2) applied in opposing directions, and the forces on the
do not apply, because the effect of applying notional same level in adjacent structures are considered to act
horizontal loads to ensure structural integrity (N3) is in opposite directions. The forces in falsework bracing
sufficient to ensure the bracing is adequate. are real and some residual forces can be expected at
Notional forces (N2) apply to the design of points of restraint, see Section 8.3.3.3.
falsework that has a top or intermediate restraint. The recommended magnitude of the notional
Refer to Section 8.3.1 for the difference between top- horizontal force at each bracing point is equivalent to
restrained and freestanding falsework. 2.5% of the axial force in the compression member.
4:11
Formwork Handbook
Figure 4.11: Notional horizontal actions to ensure minimum levels of structural integrity
4:12
Formwork Handbook
4:13
Formwork Handbook
4.3.2 Action combinations for ultimate limit states Permanent and accidental actions,
– strength and stability (GYGVW >*I*F$Y@DQG(GKGVW >$K@ (4.9)
For strength and stability limit states, the most where
adverse combinations of actions that occur during Edv.dst = net destabilising effect of the combined
Stages 1, 2 and 3 must be considered. vertical actions;
During Stage 1, Gc may be zero or represent the Edh.dst = net destabilising effect of the combined
weight of reinforcement. At this Stage, the destabilising horizontal actions;
effects (uplift, sliding and overturning) of wind are Wuv = vertical ultimate limit states wind action;
significant in comparison to subsequent Stages. Wuh = horizontal ultimate limit states wind action;
Over half of all formwork collapses occur Av = vertical actions from accidental impact;
during Stage 2. Thus, it is necessary to consider the and
concrete placement sequence (e.g. the possibility of Ah = horizontal actions from accidental impact.
concrete placed only on a single span or cantilever). It The above combinations should only
is unlikely that concrete placement would commence include actions that act concurrently and produce a
or continue during storm winds, so Stage 2 action destabilising effect. They should not include any actions
combinations including Wu can be neglected. However, that produce a stabilising effect.
as the primary cause of failure is inadequate bracing, Where applicable, action combinations including
the effect of snow, ice and earthquake actions should
the combinations of vertical and horizontal actions need
be taken into account (SA 2002).
careful consideration.
For combinations of vertical actions that
The design of primary members (shores and
produce net stabilising effects (Edv,stb)
primary beams) is often governed by the effects of
Permanent actions only,
stacked materials present during Stage 3.
Consideration should be given to the possibility
(GYVWE >*I*F@ (4.10)
4:14
Formwork Handbook
4:15
Formwork Handbook
From Table 4.4, for each action, the effective duration of peak load and
duration of load factor for bearers are:
Taking account of the duration of load factor, the most adverse combination for the limit states strength
design of the timber bearers will be the greater of the following:
Stage 3
* I *F 4P * I *F
or
6WDJH RU
Any risk of underestimation due to the negligible effect short term variable actions (e.g. workers and
equipment) with a high load duration factor or which might be omitted is avoided by considering combinations for
permanent actions only, as well as combinations for permanent and variable actions.
4:16
Formwork Handbook
4:17
Formwork Handbook
Figure 5.1: Comparison between measured and calculated pressures (Clear and Harrison 1985)
5:1
Formwork Handbook
5:2
Formwork Handbook
Concrete Admixtures
Aggregate shape, size, grading and density
Cementitious materials
Mix proportions
Temperature at placing
Wet density
Workability
Formwork Permeability/watertightness
Plan shape and area of the cast section
Roughness of the sheeting material
Slope of the form
Stiffness of the form
Vertical form height
Placing Impact of concrete discharge
In air or underwater
Placing method (e.g. lift height or rate of rise)
Vibration
more than 1.0 m. In these cases, formwork pressures hf = vertical height of form, m.
are likely to be higher. Figures 5.3 to 5.8 are included to demonstrate
In the case of self-compacting concrete, DIN the sensitivity of concrete pressure to each of these
18218 “Pressure of fresh concrete on vertical formwork” factors, for pours up to 6 m high. In each case, only
(DIN 2010) provides guidance based on research by one variable changed. Otherwise, each figure depicts a
Proske (2002). scenario where concrete with a wet density of 24 kN/m3
Anecdotal evidence suggests that the maximum is discharged from the top of formwork that is nominally
concrete pressure ever measured is 150 kPa. 200 mm higher than the pour. The nominal rate of
concrete rise in the formwork is 5 m/hr. The nominal
5.2.1 Factors influencing concrete pressure coefficient for concrete materials C2 is taken to be equal
From casual inspection of Equation 5.1, it is clear to 0.45 and the concrete temperature is assumed to
that concrete density and vertical pour height have be 20 °C. Except for Figure 5.4, where C1 = 1.5 (e.g.
a direct (linear) bearing on the hydrostatic concrete columns), the nominal value for coefficient C1 = 1.0 (e.g.
pressure. In Equations 5.2 and 5.3, some of the factors walls).
that influence the rate of hydration and therefore
concrete pressure are less obvious and discussed 5.2.2 Plan shape and area of cast section
herein. Form height and the height at which the A common misconception is that deep elements
concrete is discharged are also discussed as these can with a large plan area (e.g. 3 m deep raft foundations)
affect the maximum concrete pressure. have high concrete pressures. To the contrary, in
Factors that affect the maximum concrete elements with small plan cross-section shape or area
pressure are listed in Table 5.2. vibration can be sufficient to mobilise all the concrete;
Some of these factors are taken into account in however, in elements with a large plan section or area,
Equations 5.1 to 5.3, namely: all of the concrete is not mobilised at the same time and
ρ = wet density of concrete, kg/m3; less energy is transmitted into the formwork.
hc = vertical pour height, m; The effect is that the maximum pressures in
C1 = coefficient dependent on the size and shape walls are lower than in columns. For the purposes
of formwork; of Equation 5.3, a “column” is defined as a section
Rc = vertical rate of concrete rise up the form, m/hr; where both the width and breadth are equal to or less
C2 = coefficient for the effect concrete cement and than 2 m; otherwise, the section is considered to be
admixtures have on setting time, see Table 5.1; a “wall”. The difference in pressure between “walls”
Tc = concrete temperature at placement, ° C; and and “columns” is addressed in Equation 5.3 by the
5:3
Formwork Handbook
5:4
Formwork Handbook
coefficient C1, which is equal to 1.0 for “walls” and 1.5 should be increased for admixtures that effectively act
for “columns”. as retarders, such as retarding water reducers and
The effect of plan shape and area can be seen any admixture that is used above the recommended
by comparing the pressures plotted in Figures 5.3 and dosage.
5.4, which plot the concrete pressure for a range of The effects of different values of coefficient C2
rates of concrete rise. can be seen in Figure 5.5, which plots the maximum
Clearly the pressure in columns (Figure 5.4) is concrete pressure for concrete placed in wall formwork.
greater than walls (Figure 5.3) and hydrostatic pressure Figure 5.5 demonstrates that concrete pressure
governs the design of columns more so than for walls. increases with increasing the values of C2.
5:5
Formwork Handbook
therefore the maximum pressure. previously discussed it has less of an effect on the
The form height may also dictate the minimum maximum concrete pressure.
discharge height, which is important because the
impact of falling concrete increases concrete pressure. 5.2.7 Other factors
Figure 5.7 demonstrates how the factor hf should be Other factors that affect the maximum concrete
measured. pressure include m`ethod of vibration and formwork
Figure 5.8 demonstrates the influence of a range permeability. In addition, when concrete is placed
of vertical form heights expressed in terms of height underwater, concrete pressure is affected.
above the top of the pour.
Concrete may be placed by a static hopper with 5.2.7.1 Method of vibration
a tremie pipe, directly to the base of the form. In this Equations 5.1 and 5.2 do not cover situations
case, the height of the concrete shall be measured from where:
the base of the form to the top of the hopper (Pallett 1. Concrete is pumped from below;
2009). 2. External vibrators are attached to the formwork;
Although, the maximum concrete pressure and
increases with increasing form height or concrete 3. The concrete is revibrated by immersing internal
discharge height, when compared with the factors vibrators more than 1.0 m.
5:6
Formwork Handbook
§ K & & ·
5.3 RATE OF RISE
5K K t ¨¨ ¸
¸ (5.5)
The rate concrete rises up the form has a &
© ¹
significant effect on concrete pressure. In selecting
If the difference in height is significant, the
an appropriate rate of rise upon which to base the
equation is much more complex, as shown in
formwork design, consideration must be given to many
Equation 5.6 (below).
factors including: the proposed method and rate of
concrete delivery, the proposed method and sequence
5.3.2 Proposed method of concrete placement
of concrete placement, the duration of concrete
placement, formwork economy, formwork shape and Concrete may be placed in many ways. The
most common methods are: discharging directly out
plan area, and any limitations on formwork strength or
of the truck into the formwork; discharging out the
serviceability. In any case, the formwork design should
truck into a concrete kibble (or skip), which is lifted by
be based on a realistic estimate of the maximum rate of
a crane and emptied into the formwork; or discharging
rise that could be expected.
out of the truck into the hopper of a concrete pump
For concrete elements with parallel side
and pumped along a pipeline and/or boom into the
formwork, the rate of rise (Rc ) can be calculated as
formwork.
follows:
A concrete truck is capable of discharging its
9F contents directly into formwork at approximately 30
5F (5.4)
$F m3/hr. The rate at which concrete can be delivered
where by crane is approximately 20 to 25 m3/hr. If concrete
Vc = rate of concrete delivery, m3/hr; and pumps are used, concrete may be delivered at rates
Ac = plan area of the concrete element of 50 to 75 m3/hr. If concrete is delivered concurrently
to be cast, m2. from more than one source (e.g. two pumps) the rates
§ & & K & & K K & & K ·
I ¸
5K K t ¨¨
(5.6)
¨ & ¸¸
© ¹
5:7
Formwork Handbook
Figure 5.10: Vertical construction joints introduced to reduce the area of concrete to be placed
of delivery will potentially increase proportionally. of the concrete. Common practice is to ensure each layer
On the other hand: is placed within in 0.5 hrs. This has a direct relationship
(a) The rate of rise chosen should also be consistent on the minimum permitted rate of rise, specifically:
with practical minimum concrete delivery rates.
GO
If the rate of rise is too slow, previously placed 5F t (5.7)
WF
concrete may start to set causing cold joints to
form, or concrete yet to be placed may start to where
set causing blockages; and dl = thickness of the layer, m; and
(b) When chutes are used to place concrete and tc = setting time of the concrete, hrs.
avoid segregation the rate of rise may also be Based on typical values of dl = 0.5 m and tc =
slower than expected. 0.5 hrs, substituting into Equation 5.7 establishes a
practical minimum rate of concrete rise:
5.3.3 Proposed sequence of concrete placement
It is good practice to place and vibrate concrete, 5F t t PKU (5.8)
progressively, in layers (typically 300 to 500 mm thick). and Equation 5.4 becomes:
A layer is placed over the whole plan area of the form,
9F
before commencing the subsequent layer. Each layer is 5F t PKU (5.9)
$F
placed following the same sequence or path, starting
Similarly, a useful expression for the minimum
and finishing at the same location, see Figure 5.9.
rate of concrete delivery is given by:
To avoid cold joints (where a layer of concrete
sets before the subsequent layer is placed), the time to 9F t $F PKU (5.10)
place a single layer should be less than the setting time
5:8
Formwork Handbook
On large pours (e.g. raft foundations) it may not “tapered” walls and columns whose plan area varies
be possible to deliver concrete at a rate that satisfies with height.
the inequality in Equation 5.10. In this case, two options
are available: 5.3.6 Economy
(a) Divide the concrete element into two or more The direct relationship between rate of rise and
parts that each satisfy Equation 5.10, and the required formwork stiffness and strength provides
which are poured on separate days. This can an apparent opportunity for economy by choosing a
be achieved by introducing vertical construction lower rate of rise. This must be balanced to achieve
joints, see Figure 5.10; or an overall cost-effective solution. Potential formwork
(b) Place the concrete in layers, which are the full savings may be offset by additional costs for labour
width of the concrete element, but reach full
to place the concrete and to deliver concrete in small
height in a shorter distance, such that Equation
quantities.
5.10 is satisfied. In this way, the concrete is
progressively placed from one end of the pour to
5.3.7 Limitations on formwork strength
the other in layers, which might be considered or serviceability
like parallelograms in elevation, see Figure 5.11.
It may be necessary to restrict the rate of
In the latter case, the angle and length of the
concrete rise to avoid overloading formwork with a
slope as well as the layer thickness is dictated by the
limited capacity. This is often necessary when using
properties and behaviour of the concrete mix, including
proprietary column and wall panel formwork systems.
the internal shear friction (φ c).
5:9
Formwork Handbook
(a) (b)
Figure 5.13: Hydrostatic concrete pressure distribution on an inclined soffit or lower surface
concrete pressure distribution acting at the centre of Equations 5.16 and 5.17 can be considered
pressure at a height hp above the bottom of the form, is generic expressions for all values of α.
given by either:
(a) If α = 1.0, the maximum concrete pressure is 5.4.2 Inclined side or sloping soffit formwork
hydrostatic, see Figure 5.12(a), and: The situation is slightly more complex with
inclined formwork.
3F PD[ KF
)S N1PDQG (5.14)
5.4.2.1 Hydrostatic concrete pressure
KF
KS P (5.15) Soffit or lower form
First consider the distribution of hydrostatic
(b) If α ≤ 1.0, the concrete pressure may be limited
concrete pressure on an inclined surface AB, shown
by concrete setting, see Figure 5.12(b), and:
in Figure 5.13(a). In accordance with Pascals Law, the
> @
concrete pressure distribution is as shown in Figure
3F PD[ KF
D N1PDQG
)S (5.16) 5.13(b).
However, the distribution of hydrostatic pressure
5:10
Formwork Handbook
(a) (b)
Figure 5.15: Hydrostatic concrete pressure distribution on an inclined top or upper surface
Figure 5.16: Vector components of hydrostatic Figure 5.17: Incorrect concrete pressure distribution
concrete pressure distribution on an inclined top or (limited by setting) on an inclined soffit or lower
upper surface surface
5:11
Formwork Handbook
5.4.2.2 Concrete pressure limited by setting of concrete pressure normal to the bottom of the
inclined form (Pcx’) is given by the expression:
Soffit or lower form
First assume that the maximum concrete 3F[
3F PD[ D VLQ T FRV T (5.19)
pressure shown in Figure 15.13(a) is limited by concrete
Furthermore, the magnitude of the component
setting. Intuitively, the pressure diagram might be
of concrete pressure in the plane of the inclined form
expected to be as shown in Figure 5.17, which is often
Pcy’ increases from zero at a depth of hh = αhc to a
how it is presented in the literature.
maximum value at the full depth of the concrete at point
However, by considering the vector sum of the
A given by the expression:
orthogonal pressure components shown in Figure 5.18
it can be shown that the distribution in Figure 5.17 is 3F\
3F PD[ VLQ T FRV T D (5.20)
incorrect. The distribution shown in Figure 5.17 does The latter is significant as it results in an axial
not take into account that the vertical component of tension/compression force in the form, which is often
concrete pressure is not limited by setting. neglected in the literature and as a consequence may
The correct concrete pressure distribution is as cause underestimation.
shown in Figure 5.19. The validity of this solution can be seen by
In Figure 5.19, the magnitude of the component considering as θ approaches 90 degrees (closer to a
5:12
Formwork Handbook
5:13
Formwork Handbook
Figure 6.2: Wall formwork with secondary vertical Figure 6.3: Load distribution through side formwork
studs and primary horizontal walers (McAdam and Lee 1997)
6:1
Formwork Handbook
Figure 6.5: Single-sided wall formwork Figure 6.6: Common types of form ties
6:2
Formwork Handbook
distinguish between non-reusable and reusable (b) By a further 20%, except for members whose
sections, nor mode of failure (ductile or brittle), nor capacity has been reduced to take account of
6:3
Formwork Handbook
that they are acceptable. Extremely ductile materials to shear and bending.
may be unsuitable for use as formwork ties. Due to the chemical properties of high tensile
Guidance on ensuring elastic behaviour of steel form ties, welding is not recommended. Unless
multiple-use equipment is provided in Chapter 3. A special procedures are followed, the strength and
simple and more conservative approach may be to ductility of the form tie bar may be impaired by welding.
ensure elastic behaviour at ultimate limits states, which In addition, high tensile form ties should not be
negates the need to check serviceability limit states. hot dip galvanised due to the risk of brittle fracture.
Similarly, the risk of brittle fracture increases when high
6.2.4 Form tie identification tensile steel under load comes into contact with wet
A potential problem arises when form tie concrete. Accordingly, some suppliers of high tensile
components from different manufacturers are mixed, fasteners do not recommend using steel with a tensile
i.e. nuts from manufacturer A used with threaded bar strength greater than 800 MPa when cast in concrete.
from manufacturer B.
Purchasing stock from one source or marking 6.3 DOUBLE-SIDED WALL FORMWORK
matching components may reduce the risk of
unintentional mixing. 6.3.1 Balanced concrete pressure
Instances of two nuts being used to “increase” The most common and economical method of
the capacity of suspect form ties are also cause for wall formwork is double-sided. The concrete pressure
concern. When two nuts are locked together, the 2nd on each face is balanced by form ties, as shown in
nut carries the load. This practice does not increase Figure 6.7.
capacity and is not recommended. If the loaded nut In the situation depicted in Figure 6.8, the
fails, the load will be transferred to the other nut which pressure on the lower face is greater than on the upper
may also fail. The purpose of lock nuts is to prevent face. The form ties balance the horizontal concrete
unintentional loosening. In this case, the lock nut is pressure on the upper face leaving an imbalance on the
placed on the bolt first followed by the full nut, not vice lower face, which must be resisted by the formwork,
versa as is common practice. bracing and their connections to avoid instability.
6.2.5 Precautions when using form ties 6.3.2 Limit states design of wall form
Form ties are intended to be used in tension. face and framing members
The tensile capacity of form ties is eroded when subject A concrete pressure envelope can be
6:4
Formwork Handbook
For timber
formwork, often
bearing capacity
perpendicular to
the grain will govern
design. For example, the
characteristic bearing capacity
of LVL products is of the order of 12 MPa;
therefore, twin LVL soldiers (50 mm apart) have a
limit states bearing capacity of approximately 50% of
the limit states tensile capacity of commonly used high
Figure 6.9: Out-of-balance effects when opposing tensile form ties, when exerted by a bearing plate 130
side forms are not parallel mm wide by 100 mm high.
For cold-form steel formwork members, often
web buckling or web crippling will govern design.
determined using Equations 5.1 to 5.3. For serviceability
limit states the action combination given in Equations
6.3.3 Unbalanced concrete pressure
4.3 to 4.5 apply. For stability limit states, the action
combinations given in Equation 4.7 applies. For strength Figure 6.9 shows a plan of side formwork.
limit states, the action combinations in Equations 4.12a Where the opposing sides are not parallel, out-of-
and 4.13 apply. balance effects arise. Axial forces are generated in the
The deformations and action effects in form plane of the formwork. Instability might be avoided by
face and framing members can be determined from the creating a shear connection between adjacent sides, as
pressure at the appropriate height intervals. For stability shown in Detail 1.
and strength limit states, the action effects in primary Figure 6.10 shows various arrangements of
beam (e.g. vertical soldiers or horizontal walers), braces inclined and tapered formwork with out-of-balance
and form ties should be multiplied by factor γd = 1.25 to effects. In each case, there is an imbalance of concrete
take account of unanticipated load redistribution. pressure that results in an unbalanced vertical action.
Form ties are often capable of exerting much Often the vertical action can be balanced by a restraint
higher forces on soldiers and walers than they can (tie or support) at the base of the formwork. In addition,
resist in bearing, web yielding or web buckling. significant axial forces are generated in the formwork
6:5
Formwork Handbook
(b)
(c)
Figure 6.10: Out-of-balance effects on inclined and tapered wall formwork
6:6
Formwork Handbook
and it is necessary to ensure that the formwork the bracing is a function of the formwork stiffness,
members are capable of resisting the combined effects straightness and continuity.
of bending, shear and axial tension or compression, as Formwork may have sufficient stiffness to satisfy
appropriate. strength and serviceability requirements across the
short span between form ties, but along its length it
6.4 SINGLE-SIDED WALL FORMWORK may be slender and require bracing at regular intervals.
In some situations, it is not possible to use In addition, horizontal framing members may not
form ties to balance concrete pressure. However, be straight and bracing may be required to straighten
considerable additional work (cost) is involved in bracing the formwork. The sides of column formwork are
single-sided formwork. So much so, it is recommended often slightly twisted or prone to twisting under load.
that single-sided formwork should only be adopted after Therefore, bracing is required to hold the formwork
careful consideration. square.
The action effects of pouring concrete in the Larger concrete elements, with long sides,
single side formwork in Figure 6.5 are depicted in may be formed by joining a series of formwork panels
Figure 6.11. A common mistake is to underestimate together. Without bracing, the joints may be misaligned
the magnitude of uplift to be resisted at the base of the causing steps and/or angular misalignment in the
formwork. The connections anchor the formwork and concrete face.
brace should be designed for the appropriate forces.
6.5.2 Bracing for stability
6.5 BRACING
Side formwork nearly always requires bracing to 6.5.2.1 Robustness
provide stability and alignment. Bracing may also be necessary to ensure a
minimum level of stability. This can be achieved by
6.5.1 Bracing for alignment designing the bracing members and connections to
Bracing is required at intervals along the length resist 2.5% of the weight of the formwork and concrete,
of side formwork to ensure transverse alignment, in as well as imposed actions, see action Combinations
particular at the top of the formwork. The spacing of 4.11b and 4.12b in Section 4.3.2.2.
6:7
Formwork Handbook
6:8
Formwork Handbook
6:9
Formwork Handbook
Figure 7.1: Simple suspended slab formwork Figure 7.2: Load distribution through soffit formwork
(McAdam and Lee 1997) (when viewed from underneath)
7:1
Formwork Handbook
OVERLOAD
BEARER LIFTS
AND PROP
FALLS OVER
Figure 7.3: Line or point loads that arise from stacked Figure 7.4: Adverse partial loading of multiple span
materials during Stage 1 (SA 1996) bearer (McAdam and Lee 1997)
PROGRESS OF POUR
the strength and stability of formwork members, as well
as the assembly as a whole. In particular, in the case of
cantilever formwork failing to prevent uplift may cause
STABLE overturning, see Figure 7.5.
7:2
Formwork Handbook
(such as stacked materials) need only be taken into approximately 2 or less; e.g. common LVL sections
account in the design of primary members and their 95 x 47, 95 x 65, 130 x 77 and 150 x 77. Although less
supports; i.e. need not be taken into account in the efficient as beams, these members are less likely to roll
design of conventional form face and secondary or fall over and are less susceptible to lateral buckling
members. However, this assumption may not be valid than are narrow members, see Figure 7.7.
in all situations and must be verified, in particular, for In most situations, it is assumed the form face
longer spanning members, e.g. long span permanent and secondary beams provide effective lateral restraint
formwork. to the secondary and primary beams, respectively.
Consequently, in most conventional formwork design
7.4 ANALYSIS OF SOFFIT FORM MEMBERS
situations the lateral buckling of beams need not be
considered. However, connection details between
7.4.1 Point loads vs UDL members should be checked to ensure they are
Soffit form primary beams (bearers) are subject consistent with this assumption. In particular, lateral
to a series of point loads from each secondary beam buckling should be considered when using slender
(joist), see Figure 7.6. members (whose height to width ratio exceeds 2) and
A comparison of the effect of point loads versus when channel sections are used.
an equivalent uniformly distributed load on a continuous
primary beam (Ikäheimonen 1997) shows: 7.4.3 Simply supported beams
(a) When calculating beam reactions (shore loads),
Often the action effects in beams can be based
in most cases, point loads can be replaced by
on one of three simple beam load cases, namely: a
a uniformly distributed load without large errors;
simply supported beam with a uniformly distributed load
and
on one, two or three or more spans. In this case, the
(b) Deflections, bending moments and shear
stresses due to point loads could be higher than action effects for the maximum beam reaction, bending
7:3
Formwork Handbook
7:4
Formwork Handbook
§ ·
film faced plywood,Q ¨ ¸ ≤ 3.0°; and for softwood
© ¹
§ ·
timber, α ≤ arctan ¨ ¸ ≤ 9.0°
© ¹
For slopes greater than 3.0°, the fasteners
holding the plywood to the joists would have to resist
sliding. Similarly for slopes greater than 9.0°, to resist
sliding the joists would have to be fixed to the bearers
and, likewise, the bearers would have to be fixed to the
wedges.
7:5
Formwork Handbook
7:6
Formwork Handbook
Figure 7.14: Examples of horizontal forces being transferred to falsework, when concrete is cast on formwork
adjacent to but not connected to an existing structure (CS 1995)
7:7
Formwork Handbook
8:1
Formwork Handbook
8:2
Formwork Handbook
8:3
Formwork Handbook
(a) (b)
8:4
Formwork Handbook
(a) (b)
8:5
Formwork Handbook
8:6
Formwork Handbook
(d)
(a) (b)
(c) (d)
8:7
Formwork Handbook
8:8
Formwork Handbook
Figures 8.7, 8.8 and 8.9 depict freestanding shown in Figure 8.10; otherwise bending moments are
falsework. To avoid sway members in falsework that introduced, which must be taken into account. Failure
is top restrained, it is also necessary to brace the to do so may result in overestimating the capacity of the
top and bottom screw jacks in manner similar to that falsework.
8:9
Formwork Handbook
8:10
Formwork Handbook
8:11
Formwork Handbook
bracing force criteria suggested by Trahair, factored by k = minimum axial brace stiffness for a single
1000/500, would fall between from 0.008Nd to 0.025Nd. column, see Equation 8.2
In practice, all braces would have to satisfy the
Multiple columns with single line of braces
maximum value of kn.
A more common situation in falsework is when
Of concern is that the current criteria, to design
multiple parallel columns are connected by a line of
braces to resist a design force is based on the brace
bracing, as modelled in Figure 8.13.
stiffness required for a single column, does not take
Guidance provided in Clause 6.6 of AS 4100 and
into account the non-linear increase in brace stiffness
Clause 4.4.6 of AS 3610:1995 suggests that the first
required for braces that connect multiple columns.
brace should be designed to transfer a force of 0.025Nd
and all subsequent braces, up to a maximum of seven, Single column with multiple braces
be designed to transfer a force of 0.0125Nd. Another variation on the single column with a
Thus in Figure 8.13, the design force central brace is when a column is braced at multiple
accumulates along the line of bracing reaching a
maximum of 0.025 + (4 x 0.0125) = 0.075Nd. There
appears no justification for this rule in the literature,
other than it is reasonable to assume that the
imperfections are not uniform.
An analysis of the arrangement in Figure 8.13
demonstrates that, if the imperfections are uniform,
then:
(a) the force in the bracing increases proportionally
to the number of columns; and
(b) to be effective the brace stiffness increases non-
linearly, see Figure 8.14.
Figure 8.14 depicts the brace stiffness multiplier
(α) such that:
N Q t DQ N (8.4)
where
Figure 8.14: Brace stiffness multiplier for a series
kn = minimum axial stiffness of brace number n of parallel 48.3CHS4.0 columns 3 metres long and
αn = brace stiffness multiplier given in Figure 8.14 restrained by a line of bracing at mid point
8:12
Formwork Handbook
points along its length, as shown in Figure 8.15. design braces to resist a design force of 2.5% of the
From first principles it can be shown axial force in the column will result in braces whose
(Timoshenko and Gere 1961) that the required brace axial stiffness is sufficient to provide required axial
stiffness for a single column with multiple braces is stiffness to adequate brace columns at more than one
given by the expression point along their length.
P1 RPE
Nt (8.5)
DO 8.3.3.4 Brace connection behaviour
in which m is the number of spans and α is The capacity and behaviour of connections of
a numerical factor which depends on the number of horizontal and diagonal braces vary from one falsework
spans, see Table 8.1. For more spans, the magnitude of system to the next.
the factor a asymptotes to 0.250. Depending on the falsework, the connection
For practical purposes, the brace stiffness of horizontal and diagonal braces to vertical shores is
required to reduce the effective length of a column considered to behave as either: a “pin”, which is free to
increases with the number of spans along the column rotate; or a semi-rigid joint. Rarely are falsework brace
length. For example, the brace stiffness required to connections rigid.
ensure a 6 metre high column has an effective length of It would be conservative to neglect the rotational
2 metres is 1.5 times the brace stiffness required if the stiffness of brace connections and model them as pin-
same column is 4 metres high with effective length of 2 ended:
metres. (a) If the falsework was intended to behave as a fully
Again concerns arise as to whether the current braced frame; or
criteria, for a single column with a central brace, to (b) In the absence of any published technical data
m 2 3 4 5 6 7 9 11
α 0.500 0.333 0.293 0.276 0.268 0.263 0.258 0.255
8:13
Formwork Handbook
8:14
Formwork Handbook
(a) Swivel coupler (forged) (SOURCED FROM HTTP:// (b) Scaffold tube diagonal brace connection using
WWW.DOUGHTY-ENGINEERING.CO.UK /CGI-BIN /TROLLEYED _ PUBLIC. a swivel coupler (pressed steel) (SOURCED FROM HTTP://
CGI?ACTION=SHOWPROD _ T24801) WWW.DOUGHTY-ENGINEERING.CO.UK /SHOP/22/INDEX.HTM)
8.3.3.5 Brace axial stiffness Braces connected with scaffold tube and couplers
If horizontal and diagonal braces connect to a Figures 8.18 and 8.19 show scaffold couplers
vertical member in the same plane and their centre lines and how they are used to connect scaffold tube lacing
intersect at the same point (without any eccentricity), and bracing to vertical scaffold tube compression
their axial stiffness can be expressed as: members.
When scaffold tube connected by scaffold
($
6 (8.6) couplers is used as horizontal lacing or diagonal
O
bracing, its effective axial stiffness is reduced. This can
where
be dealt with in the following way (ECS 2004):
S = member axial stiffness;
E = modulus of elasticity; ($
A = member cross-sectional area; and 6 (8.7)
EO
l = member length.
8:15
Formwork Handbook
8:16
Formwork Handbook
Proprietary diagonal bracing increased requirement for brace stiffness that could be
In addition to the semi-rigid properties of expected in falsework structures that typically consist
proprietary brace connections, Godley and Beale of a series of parallel columns braced at multiple points
determined the effective axial stiffness of proprietary along their length.
diagonal bracing. This was necessary because the
eccentricity and construction of the end connections 8.3.3.6 Plan bracing (diagonal bracing
significantly reduced the axial stiffness of the bracing in the horizontal plane)
member, see Figure 8.20. In addition to horizontal and diagonal bracing in
For example, the effective axial stiffness of a vertical planes, for tall slender falsework structures, it
48.3 mm diameter tube proprietary diagonal brace 3.2 may be necessary to provide plan bracing to maintain
m long with an cross sectional area of approximately the orthogonal arrangement of the falsework and
460 mm2 was equivalent to a member with a cross prevent buckling about a non-orthogonal axis.
sectional area of 10.4 mm2. In terms of reduction Plan bracing may also be required to provide a
factors, this would be equivalent to β = 44. load path for horizontal loads to points of restraint.
Where it may be conservative to neglect the
rotational stiffness of member connections and model 8.3.4 Falsework base plates and screw jacks
them as pin-ended, it is not conservative to neglect
the reduction in axial stiffness of lacing and bracing 8.3.4.1 Eccentricity
members. The stability and capacity of falsework may
Due to the nature and conditions of working
be over-estimated if the design of proprietary brace
on construction sites, accidental or unintentional end
connections reduces the axial stiffness of bracing
eccentricities occur at the base and head of falsework
members. It is especially important to take account
shores. For example:
of the effect of reduced brace axial stiffness given the ■ Despite the best intentions, bearers may be
8:17
Formwork Handbook
Figure 8.24: Column strength curves for eccentrically loaded shore in “new” condition
8:18
Formwork Handbook
8:19
Formwork Handbook
Figure 8.28: Examples of good and bad practice in locating connections in compression members
8:20
Formwork Handbook
member above and below the connection, as shown in prop inners) that have inbuilt clearances for assembly,
Figure 8.28(b). angular imperfections may occur, see Figure 8.30.
Figure 8.28(c) is an example of bad practice. The The effects of this imperfection can be minimised by
connections are located in a position and in a manner increasing the lap or detailing close fitting collars and
that permits and accentuates the detrimental effects spacers to reduce the diametral clearance.
of angular change, as well as where bending moments The angular imperfection can be calculated
may arise. using Equation 8.8 (ECS 2004)
§ G G RG ·
8.3.5.1 Eccentricity WDQ IR ¨ LG ¸ (8.8)
¨ O ¸
Tolerances at joints in shores are also a potential © ODS ¹
source of eccentricities, see Figure 8.29. where,
d1id = internal diameter of outer member, mm;
8.3.5.2 Angular change at joints d2od = external diameter of inner member, mm; and
l2lap = length the inner member laps inside the outer
When tubular members such as the vertical
member, mm.
falsework members are joined using telescoping
components (e.g. spigots, base plates, screw jacks and
8:21
Formwork Handbook
8:22
Formwork Handbook
the shores are equally spaced and could be expected expected difference in settlement must be explicitly
to carry approximately the same load. However, due taken into account. Where the location of differential
to differential settlement, the shore resting on the rigid settlement is not fixed, it should be considered to occur
concrete foundation will carry a greater share of the where it would have the most detrimental effect.
load than the adjacent shore bearing on an “elastic” soil For the situations depicted in Figures 8.34 and
foundation. 8.35, differential settlement can be taken into account
Similarly, in Figure 8.35, due to differential by analysing models of the structure with:
settlement, load will be redistributed from the shores (a) For Figure 8.34, vertical spring restraints whose
at the centre of the beam (where the beam deflection stiffness models the behaviour of the foundation
is greatest) to the shores closer to the beams supports material; or
(where the beam deflection is the least). (b) For Figure 8.35, the falsework supported by the
On uniformly compacted soil, it would be beam.
reasonable to expect the effects of differential
settlement to be minor and therefore taken into account 8.3.7.2 Differential axial shortening
by the strength load factor for primary members γd = Where the axial stiffness of adjacent shores
1.25, see Section 4.3.2.3. differs and the stiffness of the primary beam permits,
Where uniform settlement does not occur, any load redistribution may occur such that a shore with a
8:23
Formwork Handbook
greater axial stiffness will carry a greater share of the In the case shown in Figure 8.38, where hinges
load than an adjacent shore that is less stiff and would develop between the bearer and screw jack, the
otherwise shorten. capacity of the falsework is less than for falsework with
In the example depicted in Figure 8.36, part of top restraint.
the falsework is supported by a previously poured slab Knee buckling arises because the modulus
that acts as a rigid foundation. As a result, the adjacent of elasticity of timber varies with angle and direction
shores that differ significantly in length carry differing of the annular growth ring gradient. Consequently,
loads. The shorter shore, which is more heavily loaded, when a timber is loaded perpendicular to the grain, the
is three to four times as stiff as the tall lightly loaded deformation is non-uniform and the surface is distorted,
shore. A significant share of the load is redistributed see Figure 8.39.
from the less stiff tall shore to stiffer short shore. Importantly, tests show that knee buckling
can occur at bearing stresses less than permitted in
8.3.8 Knee buckling design standards. Thus, merely ensuring that a limit
Research (Ikäheimonen 1997) has shown that states bearing violation will not occur is insufficient to
knee buckling can occur when compressive stresses prevent knee buckling. In addition, timber that is out-of-
between the top of the shore and the underside of square may cause an initial set or out-of-straightness,
the bearer are high and the bearer is not adequately which makes the formwork prone to knee buckling.
restrained to prevent overturning, see Figures 8.37 and Furthermore, eccentric loading may also increase the
8.38. risk of knee buckling.
In Figure 8.37, the buckling load of shore and Knee buckling may be prevented by restraining
bearer acting together may be considerably lower than the bearer from overturning; e.g. where the bearer is
that of the shore itself. a close fit inside a “U-head” screw jack. Alternatively,
8:24
Formwork Handbook
Figure 8.39: Non-uniform deformation of timber Figure 8.40: Models for Euler and knee buckling
loaded at right angles to the grain (Ikäheimonen 1997) (Ikäheimonen 1997)
knee buckling may be prevented by laterally bracing the and detrimental second-order effects. Second order
top of the shore. effects arise from loads acting on the falsework and its
In the absence of any preventative measures, members in their displaced and deformed configuration.
account should be taken of the lower buckling load A plastic analysis takes into account material
arising from knee buckling, see Figure 8.37. In Figure non-linearity, which is not appropriate for falsework. It is
8.40, to take account of knee buckling, an elastic hinge more appropriate for sway structures with high bending
is introduced to model the non-uniform deformation of moments and small axial loads. An elastic analysis is
the bearer. appropriate for falsework structures that are intended to
be braced frames, primarily subject to axial loads and to
8.4 ANALYSING FALSEWORK STRUCTURES behave elastically at all times.
Falsework is often a heavily loaded structure A first-order elastic analysis that ignores second-
with slender members. For a slender member subject order effects will underestimate the action effects in the
to an axial load, deformations increase instability structure and over-estimate stability. Accordingly, AS
8:25
Formwork Handbook
8:26
Formwork Handbook
8:27
Formwork Handbook
8:28
Formwork Handbook
Figure 8.43: Effective length of members in top restrained frames with pinned bracing at the base
Figure 8.44: Effective length of members in freestanding frames with central pinned bracing
Figure 8.45: Effective length of members in freestanding frames with pinned bracing at the base
8:29
Formwork Handbook
§ 1 RPE ·
¦ ¨© O ¹
¸
OPV (8.17)
§1 ·
¦ ¨© O G ¸¹
For example, Equation 8.17 would be used to
calculate the elastic buckling load factor of the top and
bottom row of screw jacks shown in Figure 8.46.
Using Equations 8.16 and 8.17, an estimate of
the elastic buckling load factor for the whole frame can
be determined based on initial estimates of column
effective length, using guidance similar to shown in
Section 8.4.3.1.
It is useful to compare the expected elastic
Figure 8.46: Effective length of members in
freestanding frames with pinned bracing buckling load factor for the whole frame (λc) (calculated
in accordance with Equations 8.15 and 8.16) with the
elastic buckling load factor determined by a rational
Top restrained falsework buckling analysis. The elastic buckling load factor
For a top restrained frame with central pinned determined by a rational analysis (λc) should be greater
bracing, as shown in Figure 8.42, the effective length of than or equal to the lowest elastic buckling load of
the compression member ke l = l. all the braced members (λm) and the lowest elastic
For a top restrained frame with pinned bracing at buckling load factor for each storey (λms), as applicable.
the base, as shown in Figure 8.43, the effective length When the elastic buckling load factor determined
of the compression member ke l = 0.85[l – (x/2)]. by a rational buckling analysis is less than the expected
elastic buckling load factor, it is indicative of one of the
Freestanding falsework
following:
For a freestanding frame with central pinned
(a) Underestimating member effective lengths;
bracing, as shown in Figure 8.44, the effective length of
(b) A previously unidentified member buckling first;
the compression member ke l = l – (x/2).
(c) The whole frame buckling in an unexpected
For a freestanding frame with pinned bracing at
manner; or
the base, as shown in Figure 8.45, the effective length
(d) Errors in the structural model.
of the compression member ke l = 2l – x.
For a freestanding frame with pinned bracing,
as shown in Figure 8.46, the effective length of the
compression member is the greater of, ke l12 = l2 + 2 l1;
ke l3 = l3; or ke l45 = l4 + 2 l5.
8:30
Formwork Handbook
8:31
Formwork Handbook
surface finish, contribute to non uniformity of colour and In single-stage stripping the forms and shores
impede hydration. Structurally, early stripping may lead are removed over large areas, allowing the concrete to
to cracking, increased long term deformations, overload span between the permanent supports in the manner
and possibly collapse. intended in the project design, see Figure 9.1. Once the
For practical and economic reasons, stripping forms and shores are removed, the concrete will carry
times need to be as short as possible. Therefore, this its own weight and any superimposed construction
Chapter focuses on minimum stripping times that loads; e.g. workman and equipment, stacked materials,
satisfy structural requirements. The guidance in this etc.
Chapter may be inappropriate for architectural concrete
and does not fully address or take account of all 9.2.2 Two-stage stripping
matters relating to curing or protection of the exposed For economic reasons, some formwork systems
concrete surface. allow the forms to be removed before the shores (two-
The Chapter starts by explaining different stage stripping), see Figure 9.2.
9:1
Formwork Handbook
Alternatively, a similar result can be achieved by Post-tensioned concrete is often initially partially
“backpropping”. The term “backpropping” refers to the stressed after 2 or 3 days; however, it should not be
procedure of installing additional shores (backprops) stripped until fully stressed.
prior to removing small areas of the formwork, thereby Where colour control is specified, it is advisable
preventing the concrete from carrying load, as shown in to strip forms on different elements at the same age
Figure 9.3. and as early as is permissible.
Either way, the benefit of two-stage stripping
is the early recovery of formwork without letting the 9.3.1 Development of concrete strength with age
concrete carry its own weight or any construction load, The development of concrete strength with age
because until the formwork shores or backprops are varies with the type of cement, grade specified and
eventually removed the weight of the concrete and ambient temperature, see Figures 9.4 and 9.5, as well
any superimposed construction load is carried by the as Table 9.1.
shores. Compared to normal-class concrete, the rate of
strength gain is reduced in concrete that incorporates
9.3 MINIMUM STRIPPING TIMES higher contents of supplementary cementitious material
For economic and practical purposes, stripping such as fly ash; e.g. “Green Star” products.
times need to be as short as possible.
The project designer should specify the 9.3.2 Minimum stripping times for vertical forms
minimum stripping times. The minimum stripping times for vertical forms
In the absence of any specified stripping times, (side forms for footings, walls, columns slabs and
AS 3600 and AS 3610 provide guidance on minimum beams) may be based on achieving the minimum
stripping times. However, much of the guidance in AS average concrete compressive strength specified in
3610 is impractical and out-of-date. Table 9.2. Extra care is needed if vertical formwork is
Structurally, formwork should not be stripped stripped within 18 hours after casting.
until the concrete has attained sufficient strength
Table 9.1: Early-age mean strengths for normal-class
and stiffness to support its own weight and any concrete (SA 1997)
superimposed loads, safely and without damage or
Average 7-day
detriment to its intended use (SA 2009). Grade designation compressive strength
The minimum stripping time is usually (MPa)
determined by calculating the minimum early-age N25 12
characteristic concrete strength the in-situ concrete N32 16
is required to attain taking into account the pace of
N40 20
construction, imposed loads, ambient temperatures
N50 25
and early-age strength gain characteristics of concrete.
9:2
Formwork Handbook
Table 9.3: Minimum strength and curing requirements for concrete (SA 2009)
Exposure Minimum Minimum initial Minimum average compressive
classification f’c curing requirement strength at time of stripping forms or
(MPa) removal from moulds
(MPa)
A1 20 Cure continuously for
15
A2 25 at least 3 days
B1 32 20
B2 40 Cure continuously 25
C1 50 for at least 7 days
32
C2 50
9:3
Formwork Handbook
12 ≥ T > 5 8 20 ≥ T > 12 18
12 ≥ T > 5 24
average strength of control samples taken, greater than that which would occur if the
cured, see Sections 9.4 and 9.5. design serviceability load were applied to the
(b) For stripping soffit forms between undisturbed member when the concrete has attained its
shores under normal class reinforced concrete required design strength, see Section 9.4; or
slabs: (ii) In the absence of early-age strength data,
The minimum period of time after casting and the period of time after casting the concrete
before commencement of stripping forms only is not less than that given in Table 9.5.
(i.e. leaving the shores undisturbed) should not The values in Table 9.5 only apply providing
be less than specified in Table 9.4. the imposed construction load is not greater
The values in Table 9.4 only apply providing both than 2.0 kPa.
the following criteria are satisfied: The periods in Table 9.5 shall be increased
if the average temperature over the period is
O
d less than 5° C. Increase the periods by half a
GF G F day for each day the daily temperature was
A
where between 2° C and 5° C; or by a whole day
for each day the daily average temperature
l = span between formwork shores,
was below 2° C.
in mm; and
(d) For removal of multistorey shoring under slabs
dc = overall depth of the concrete and beams:
section, in mm. (i) Calculations that demonstrate that the
B the imposed construction load is not magnitude of cracks and deflections in
greater than 2.0 kPa. all supported and supporting floors and
The periods in Table 9.4 shall be increased if the beams, under the current and subsequent
average temperature over the period is less than imposed loads, will not impair the strength or
5° C. Increase the periods by half a day for each serviceability of the completed structure; and
day the daily temperature was between 2° C and (ii) A minimum elapsed time of 2 days after
5° C; or by a whole day for each day the daily placing of concrete before removal of any
average temperature was below 2° C. shores directly or indirectly supporting the
(c) For removing formwork supports under slabs or concrete.
beams not supporting structures above: (e) For removal of forms and formwork shores under
(i) Calculations based on known or specified prestressed concrete slabs and beams:
early-age strengths that demonstrate the The strength of the concrete in the member and
concrete has gained sufficient strength so the number of tendons stressed are such as to:
that the degree of cracking or deformation (i) Provide the necessary strength to carry
that will occur, then or subsequently, is not its own weight and any currently or
9:4
Formwork Handbook
(b) Stacked materials applied directly to the Therefore, Equation 9.7 can be written in terms
concrete surface, Qm; and of the characteristic compressive strength f’c as
(c) Other vertical loads, Qx.
§: · § O ·
If construction for a subsequent level has If t ¨ G ¸
F
¨¨ ¸¸ 03D
(9.9)
commenced prior to formwork removal, an allowance © ¹ © GF ¹
9:5
Formwork Handbook
For flat reinforced concrete slabs, formwork on the slab exceeding the unfactored design service
may be stripped providing the following inequalities are load. Equation 9.12 limits the extent of cracking to that
satisfied: implicit in the concrete design. In doing so, they satisfy
9:6
Formwork Handbook
© F ¹
design capacity.
:G
Importantly, Equations 9.11, 9.12, 9.15 and 9.16 d 2.
are not applicable to the first stage of “two stage” :XOW
stripping, where only the forms are removed leaving all
the formwork supports undisturbed and supported on a 9.4.3 Stripping formwork supports under
rigid foundation. prestressed concrete
Strength rather than cracking may govern
Design Example
the minimum early-age concrete strength required
What is the maximum construction load a
before stripping formwork supports under prestressed
N32 flat reinforced concrete suspended slab could
concrete slabs. In this case, only Equations 9.11, 9.15
support if stripped when the characteristic early age
and 9.16 need be satisfied.
strength reaches 20 MPa? The slab is 250 mm thick
and designed for an imposed floor live load of 3.0 kPa
9.5 ASSESSMENT OF CONCRETE
and dead load of 1.5 kPa for services, partitions and STRENGTH AT EARLY AGE
ceilings.
The early-age characteristic compressive
Assume the density of reinforced concrete is 25
strength f’ce is determined by sampling, curing and
kN/m3.
testing concrete from which a lower bound 95%
: § I
·
d ¨¨ FH ¸¸ confidence limit is chosen as the nominal characteristic
:VHU © I
F ¹ strength.
u 4Y § ·
d¨ ¸ 9.5.1 AS 3600
u © ¹ Clause 17.6.2.8 of AS 3600 requires:
(a) Taking control test-samples of each concrete
4Y
d grade placed on any one day at a minimum
frequency of one sample for each 50 m3, or part
Therefore, thereof;
4Y d u (b) Storing and curing the samples under conditions
similar to those of the concrete in the work;
4Y d d N3D (c) Testing at least two samples from each grade for
strength at the desired time of stripping; and
By observation the unfactored load inequality
(d) Assessing the early-age strength of the concrete
:
d 1.0 is also satisfied. on the basis of the average strength of the
:VHU samples tested at that age.
Check the strength limit states inequality Where control samples have been taken, cured
and tested in accordance with AS 3600, the mean
:G
≤ 1.0 is satisfied compressive strength of the specimens at that age can
:XOW
be determined. In order to obtain an estimate of the
:G u u
characteristic compressive strength at that age, the
:XOW u u
mean strength must be reduced to take account of the
variability and uncertainty of the test methods.
:G
d 2. For example, AS 1379 (SA 1997) requires when
:XOW
assessing production control that:
Check the strength limit states inequality If FP t I
F N F V (9.19)
:G I5XH
d is satisfied, by assuming strength where,
:XOW I5X
9:7
Formwork Handbook
9:8
Formwork Handbook
Figure 10.1: Example of multistorey shoring with one floor of formwork and three floors of shores
10:1
Formwork Handbook
10:2
Formwork Handbook
on lower levels, the consequential reduction in axial 10.1.3.2 Recent guidance predicting
stiffness of the shoring will increase the share of the load distribution
load carried by, and may contribute to the overload of, There is evidence and guidance in the literature
the floors above. (Beeby 2001; Moss 2003; Park et al. 2011) that a
reasonable estimate of the share of the construction
Conclusions
load carried by each floor connected by multistorey
Based on these findings, the share of the load
shores can be determined by taking account of the:
carried by the uppermost slab supporting the formwork
(a) Method and sequence of stripping and shoring;
will be larger than previously thought and such that
(b) Flexural stiffness of each floor at time of loading;
it may often be significantly overloaded in particular,
(c) Effective axial stiffness and layout of the
when:
formwork and multistorey shores on each floor;
(i) Multistorey shoring is sparse and heavily loaded;
and
(ii) Floor to floor heights vary, as shore stiffness is
(d) Preload in multistorey shores.
directly proportional to length; or
There is also guidance on assessing the ability of
(iii) Shores are made from less stiff materials; e.g.
slabs and beams to carry the construction loads (Beeby
aluminium is approximately one third the stiffness
2001) by considering the:
of steel, but some alloys have a comparable
(a) Magnitude and location of the construction
strength to steel.
10:3
Formwork Handbook
loads, including loads from multistorey shoring; for “reshoring” and “undisturbed” shoring. Special
(b) Magnitude and location of the in-service design situations that need to be addressed are highlighted
loads; and and the Chapter concludes with a discussion on
(c) Floor construction cycle time relative to early-age assessing the capacity of slabs to carry loads at an
concrete strength gain. early-age.
Other factors that influence the multistorey load
distribution include concrete shrinkage, creep and 10.2 FACTORS INFLUENCING THE DESIGN
ambient temperature change (McAdam and Behan OF MULTISTOREY SHORING
1990).
The ACI Guide for Shoring/Reshoring of 10.2.1 Method and sequence of
Concrete Multistorey Buildings (ACI 2005) also provides stripping and shoring
useful information. There are two methods of multistorey shoring:
reshoring or undisturbed shoring.
10.1.4 Guidance provided herein In Figure 10.1, it is not apparent, without more
This Chapter explains the factors that influence information, whether the project designer intended
the design of multistorey shoring, and introduces and specifying reshoring or undisturbed shoring.
discusses several methods for estimating the load
distribution between the floors connected by multistorey 10.2.1.1 Reshoring
shoring and the load in the multistorey shores Reshoring is the most common method adopted
themselves. In addition, explanations are provided on for multistorey shoring; primarily, because it minimises
the different methods to determine the load distribution the load distributed to the lower floors and therefore
10:4
Formwork Handbook
1
The term “backpropping” is often used to describe any type of multistorey shoring. Herein
“backpropping” refers to only the shores installed as shown in Figure 9.3. It does not refer to reshores.
10:5
Formwork Handbook
10.2.2.2 Concrete modulus of elasticity For one-way slabs, beams and simple two-way
slabs, it is possible to develop simple expressions for ξ lc
The concrete modulus of elasticity increases
for use in Equation 10.1. However, this is not practical
with age. Unless determined by testing in accordance
for more complex slab and beam arrangements.
with AS 1012.17, the mean modulus of elasticity (within a
range of ±20%) is specified in AS 3600 as:
10.2.3 Effective axial stiffness of shores
10:6
Formwork Handbook
packing or other material between the top and/ Ef = modulus of elasticity of the forms or other
or bottom of the shore and the concrete; and material between the top and/or bottom of the
(b) The reduction in stiffness caused by the shore and the concrete;
inclination and other shore imperfections. The range of the mean modulus of elasticity
IS perpendicular to the grain falls between (BS
6S 2008), for:
(10.5) (i) Softwood timber, 230 MPa
6V 6I
to 530 MPa; and
(ii) Hardwood timber, 630 MPa
to 1330 MPa.
Af = bearing area of the forms or other material; and
lf = thickness of the form or other material.
The presence of softwood forms between the
shores and concrete can reduce the effective axial
stiffness of a steel shore to approximately 30% of its
axial stiffness based on the shore section only
(Fang et al. 2001).
In addition, Fang et al. found the presence
of imperfections, such as inclination, reduces the
theoretical shore stiffness and also needs to be
taken into account. Failure to do so may lead to
underestimation of the load carried by the uppermost
slabs.
Figure 10.6: Idealised model of one floor of formwork The effective axial stiffness of shores will also be
(not shown) and two floors of multistorey shoring less where there is high-strutting to the floor above; e.g.
10:7
Formwork Handbook
entrance foyers, plant rooms, etc. Aluminium and timber 3.25m tall steel shores are spaced evenly at 1.2 m in
shores may have significantly less axial stiffness than one direction and 1.8 m in the other. Each shore has
steel shores. a cross-sectional area of 574 mm2. The shores are in
direct contact with the 250 mm thick concrete slabs,
10.2.3.2 Multiple shores which are continuous on all four sides and span 8 m
On any one level, the effective axial stiffness in both directions. The characteristic compressive
of the multistorey shores as a group is a function of strength of the concrete in each slab at the time of
the axial stiffness of each shore and the shore layout. loading is, from top to bottom, 20 MPa, 25 MPa, 32
This can be demonstrated by observing the change in MPa and 32 MPa.
load distribution in the following four design examples; Neglecting cracking and assuming infinite
in particular, the share of the load carried by the shore stiffness, an analysis of this arrangement shows
uppermost slab, see Table 10.1. the share of the load (applied to the top floor) carried
by each floor is 0.236, 0.251, 0.257 and 0.257, top to
Design Example 1 – Multistorey load distribution
bottom.
assuming infinite shore stiffness
This design example calculates the load Design Example 2 – Effect of axial shore stiffness
on multistorey load distribution
distribution assuming infinite shore stiffness.
Consider the load distribution for the situation This design example calculates the load
depicted in Figure 10.7. In this situation, 35 number distribution taking account of the actual shore stiffness.
In the absence of any specific guidance on the
Table 10.1: Load distribution in multistorey shoring effective axial stiffness of the shores, it is possible to
taking account of shore axial stiffness and layout take account of shore imperfections by adopting a
Design Example reduced cross-sectional area for each shore (as per
Load
Ratio Equation 10.5); i.e. the effective cross-sectional area of
1 2 3 4
each shore, Ase = φp × 574 mm2 = 0.80 × 574 mm2 =
Wc1/W1 0.236 0.404 0.423 0.496
459 mm2.
Wc2/W1 0.251 0.250 0.273 0.278 Thus, neglecting cracking and taking account of
Wc3/W1 0.257 0.188 0.173 0.140 the shore stiffness, reanalysing shows the share of load
(applied to the top floor) carried by each floor is 0.404,
Wc4/W1 0.257 0.159 0.131 0.087
0.250, 0.188 and 0.159, top to bottom.
10:8
Formwork Handbook
The share of load carried by the uppermost slab effective bearing area calculated at the centre of each
increased by a factor of 1.71 (0.404/0.236). member assuming a 45° load distribution, the effective
compressive axial stiffness of the formwork, considering
Design Example 3 – Effect of a “thinned” shore
layout on multistorey load distribution the stiffness of the plywood, joist and bearer, is given by
the formula shown above.
This design example compares the effect on
Using Equation 10.5, the effective axial stiffness
load distribution of taking account of the shore stiffness
of a single formwork shore taking into account the
and “thinned” shore layout.
presence of the formwork is:
On the lower two levels, the shores are “thinned”
out from a grid of 5 x 7 to a grid of 5 x 4, as shown
6S
in Figure 10.8. Reanalysing the arrangement shows
the share of the load (applied to the top floor) carried
by each floor is 0.423, 0.273, 0.173 and 0.131, top to Taking account of the presence of formwork
bottom. between the top of the shores, the share of the load
The share of load carried by the uppermost slab (applied to the top floor) carried by each floor is 0.496,
increased by a factor of 1.79 (0.423/0.236). 0.278, 0.140 and 0.087.
The increase in load carried by the uppermost The share of load carried by the uppermost slab
slab depends on revised shore layout because increased by a factor of 2.10 (0.496/0.236).
removing shores near the centre of the slab increases It is useful to represent the effective axial
the load on the uppermost slab more so than removing stiffness of a level of shores as a multiple of the elastic
those near the slab’s supports. flexural stiffness of the 28-day slab flexural stiffness, see
Design Example 4 – Effect of the presence of soft Section 10.3.1.
wood formwork on load distribution For example, the results from Design Examples
This design example takes account of softwood 1 to 4 have been calibrated using the relative stiffness
timber formwork remaining in place between the top of method presented in Section 10.3.1.3 and the effective
the shores and the concrete slab; i.e. the shores were axial stiffness each level of shores relative to the 28-day
relaxed allowing the slab to deflect before being reset slab flexural stiffness presented in Table 10.2.
without removing the formwork. In the worst case, neglecting the effective axial
Consider the formwork is constructed from F14 shore stiffness could underestimate the load carried by
17 mm plywood, 95 x 65 LVL joist at 400 mm centres the uppermost slab by 50%.
and 150 x 77 LVL bearers spanning 1.2m between and
bearing on shores with a 150 x 150 end plate. 10.2.4 Preload in multistorey shores
Using Equation 10.6, the axial stiffness of a It is normally assumed that shores (reshores and
single formwork shore is: backprops) are installed with zero preload. The effect
of excessive, or predetermined, tightening of the shores
is beneficial as it increases the load in slab below and
6V
decreases the load in the slab above; i.e. move load
from the slab above to the slabs below.
6V N1PP When reshoring, preloading will result in a more
Based on a mean modulus of elasticity even distribution of the share of load between the
perpendicular to the grain of 400 MPa (BS 2008) and an supporting slabs (BRE 2004). Accordingly, there may be
10:9
Formwork Handbook
account of:
■ 0.25 kPa for all other slabs carrying
a share of the load.
(a) The self-weight of concrete floors, Gc (see
The weight of construction material or
Section 4.2.1.2);
equipment stacked on soffit formwork or on any of the
(b) The imposed construction loads on each floor,
slabs carrying a share of the load is likely to increase
Qv; and
the number of floors of shoring and must be taken
(c) The load transferred to each floor through the
into account. This may be achieved economically
multistorey shores.
by limiting the magnitude of the load from stacked
materials and locations where stacking material is
10.2.5.1 Imposed construction load permitted.
The imposed construction load on any floor may Additional multistorey shoring may be required
include: to share the load imposed by construction equipment,
10:10
Formwork Handbook
10:11
Formwork Handbook
10.3 METHODS FOR CALCULATING LOAD (a) It is appropriate for one-way and two-way
DISTRIBUTION IN MULTISTOREY reinforced concrete slabs with beams, as well as
SHORING
beams that behave elastically; e.g. slabs up to
There are several methods recommended in the 350 mm thick and not heavy stiff beams.
literature for calculating the load distribution in multistorey (b) It is useful for reshoring, but less so for
shoring. Three methods are discussed herein, namely: undisturbed shores;
1. Relative stiffness method; (c) If the effective axial stiffness of each floor of
2. Slab shore interaction method; and shores is not known, which is usually the case,
3. Finite element analysis. application of this method relies on making an
All the methods are suitable for both reshores accurate assumption or estimate of the effective
and undisturbed shores. axial stiffness of each level of shores relative to
the flexural stiffness of the slabs; e.g. in terms
10.3.1 Relative stiffness method of a multiple of the flexural stiffness of the slabs
The Guide to Flat Slab Formwork and Falsework at 28 days; e.g. as per the example in Section
(CSG 2003) presents simplified formulae to calculate 10.2.3.2 where Sp = 0.8Sc28; and
the load in each level of shoring based on the flexural (d) The actual load in individual shores is not known,
stiffness of the slabs and effective axial stiffness of the only the total load in the level of shores, which
level of shores. may lead to underestimating the load in the
Unfortunately, the use of this method has heaviest loaded shores.
limitations: For the purposes of simplifying the formulae
10:12
Formwork Handbook
provided in Guide to Flat Slab Formwork and Falsework, The share of W1 transferred to the top slab is
it is useful to define a “relative stiffness term” for slab 1 given by:
to 2, K12, and for slab 2 to 3, K23, and so on as: :F : :S (10.13)
6F 6F The share of W1 transferred to the second
. (10.8)
6F 6S (bottom) slab is given by:
:F :S (10.14)
6F 6F
. (10.9)
6F 6S
10.3.1.2 Two levels of multistorey shores
6F 6F For systems with two levels of multistorey
. (10.10)
6F 6S shoring (see Figure 10.11), the load in the top level of
6F 6F multistorey shoring, Wp1, and the load in the second
. (10.11) level of multistorey shoring, Wp2, is given by:
6F 6S
:
:S
6 F
10.3.1.1 One level of multistorey shores
6 F (10.15)
For systems with a single level of multistorey .
.
shoring (see Figure 10.10), the load in the multistorey
:S
shoring, Wp1 is given by: :S (10.16)
: .
:S (10.12)
. The share of W1 transferred to the top slab is
on the top slab to be shared by the multistorey shoring. The share of W1 transferred to the second slab
is given by:
W1 will be the sum of the construction load from the
formwork shores and any imposed construction load :F :S :S (10.17)
acting on the top slab. The share of W1 transferred to the third (bottom)
10:13
Formwork Handbook
slab is given by: the second slab is given by Equation 10.17. The share of
:F :S (10.18) W1 transferred to the third slab is given by:
:F :S :S (10.22)
10.3.1.3 Three levels of multistorey shores The share of W1 transferred to the fourth
Based on the same theory, for systems with (bottom) slab is given by:
three levels of multistorey shoring (see Figure 10.12), the
loads in the respective level of multistorey shoring, Wp1, :F :S (10.23)
Wp2, and Wp3, are given by:
10.3.1.4 Four levels of multistorey shores
:
:S Based on the same theory, for systems with four
6 F
levels of multistorey shoring (see Figure 10.13), the loads
6 F
. in the respective level of multistorey shoring, Wp1, Wp2,
6 F (10.19) Wp3, and Wp4, are given by:
6 F
. :
. :S
6 F
:S
:S 6 F
6 F .
6 F (10.24)
(10.20)
6 F
. 6 F
. .
6 F
:S 6 F
:S (10.21) .
. .
The share of W1 transferred to the top slab is
given by Equation 10.13. The share of W1 transferred to
10:14
Formwork Handbook
:S arise from the point load from each individual formwork
:S or multistorey shore on the level above and any other
6 F
(10.26) construction loads acting downward on the top of the
6 F
. supported slab, less the reduction in deflection that
. arises from the sum of the effects of the point load from
:S each individual multistorey shore on the same level as
:S (10.27) the shore in question, acting upward on the underside
.
of the supported slab.
The share of W1 transferred to the top slab is
The deflection at the bottom of each shore
given by Equation 10.13.
(δB) is equal to the sum of the deflections in the slab
The share of W1 transferred to the second slab
supporting the shore that arise from the point load from
is given by Equation 10.17.
each individual multistorey shore on the same level
The share of W1 transferred to by the third slab
as the shore in question and any other construction
is given by Equation 10.22.
loads acting downward on the slab supporting the
The share of W1 transferred to the fourth slab is
shore, less the reduction in deflection that arises from
given by:
the sum of the effects of the point load from each
:F :S :S (10 .28) individual multistorey shore on the level below the shore
The share of W1 transferred to the fifth (bottom) in question (where present), acting upward on the
slab is given by: underside of the slab supporting the shore in question.
Considering the axial load in every shore on
:F :S (10.29) each level of multistorey shoring results in a series of
complex simultaneous equations that can be solved
10.3.2 Slab shore interaction method using matrix methods.
The Guide to Flat Slab Formwork and Falsework The accuracy of this method depends on the
(CSG 2003) includes a spreadsheet for calculating suitability of the deflection coefficients used to calculate
the loads in multistorey shoring and the connected the slab deflection at each shore location. For two-
flat plate slabs. The spreadsheet takes account of the way slabs, using simple methods for estimating slab
interaction of slab flexural stiffness, shore axial stiffness deflections (e.g. Scanlon and Suprenant 2011) may
and preload based on methods for estimating load result in inaccurate estimates of load distribution,
distribution that have been previously investigated because although these methods may provide a
(Liu et al. 1985; El-Shahhat et al. 1992) and refined by reasonable estimate of the maximum deflection
Beeby (2001). Useful commentary on its use can be for a two-way slab, without adjustment, they can
found in Early age construction loading (BRE 2004). underestimate the deflection near the slab edges and
Using this method, for a given multistorey shore therefore the load in those shores.
layout, the axial load in each multistorey shore (Np) can The advantages of this method are that it is
be expressed as: suitable for:
1S 6S G$ G% (10.30)
1. Situations where the layout of formwork shores
and/or multistorey shores differs from floor to
In Equation 10.30,
floor, see Figure 10.14; and
Sp = Effective axial stiffness of each individual
2. One-way slabs and beams, as well as simple
multistorey shore, see Equation 10.5;
rectangular two-way flat slabs; and
δA = Deflection of the slab at the top of the
10:15
Formwork Handbook
10:16
Formwork Handbook
Figure 10.16: Idealised model with both the top and intermediate floor loadings
relative stiffness of the floors and shores at the time of slab. The load distribution for W2 must be determined
each event. based on the time the load was installed and before
Loads may be applied to any floor connected considering the distribution of W1.
by multistorey shoring, the most common case is Thus, it is necessary to sequentially determine
when loads are applied to the top floor and the load the distribution from each load event using the stiffness
is shared between the floors below, see Figure 10.6. of the concrete and shore layout at the time of loading.
This may occur on any day of the floor cycle. However,
if an intermediate floor is loaded (e.g. with stacked 10.4.1.1 Floor numbering
materials), the distribution of this load will change the Note on Day 1 of any floor cycle, the newly
share of load carried by the slabs above and below the poured slab has some stiffness and is identified as
floor. slab 1 in the multistorey arrangement (e.g. as shown
In Figure 10.16, the intermediate floor is shown Figure 10.7) and the floors below are renumbered.
carrying an additional construction load (W2) from The numbering applies for all load events up to and
material stacked on the floor prior to pouring the next including the casting of the next floor. The day after the
10:17
Formwork Handbook
next floor is poured, what was slab 1 becomes slab 2 Typically, multistorey shores carry compression
the loads are distributed and accumulate, until the than the lowest level, is significantly stiffer than
formwork shores are removed after pouring the next the floors below (e.g. a floor with a thicker slab
slab. or shorter spans).
This is not a problem providing the tension does
10.4.3 Undisturbed shoring not exceed the accumulated compression or preload
in the shores. The latter case may be indicative of how
When analysing undisturbed multistorey shoring,
shoring beneath very stiff slabs may be ineffective.
it is necessary to determine the load distribution in
Nevertheless, it is good practice to install
the slabs and multistorey shoring that accumulates
multistorey shores with a minimum preload to minimise
from each loading event throughout the time each
slab participates as part of the multistorey shoring the risk of unloaded shores falling.
connected by multistorey shoring and the multistorey During construction, at some point, in slabs
shores it supports are removed. sharing multistorey loading subject to increasing
For a multistorey structure, it is necessary loads, cracking will take place and reduce the flexural
to sum the calculated load distribution from each stiffness of the slab. It may be prudent to be aware of
load event slabs connected by multistorey shoring the magnitude of the load that will cause the onset of
10:18
Formwork Handbook
10:19
Formwork Handbook
:G :FN3D (10.34) Fang, D.-P., H.-Y. Zhu, C.-D. Geng and X.-L. Liu
(2001). “On-Site Measurement of Load Distribution in
Reinforced Concrete Buildings during Construction.”
10.6.4 Acceptable overload
ACI Structural Journal 98 (No. 2): 157-163.
The acceptance or otherwise of the magnitude
Ferguson, S. A. (2000). “A 2-day cycle using
of construction load from multistorey shoring is the
timber formwork.” Concrete Vol. 34 (No. 3, March): 22-26.
responsibility of the project designer.
Grundy, P. and A. Kabaila (1963). “Construction
A discussion and guidance on issues associated
Loads on Slabs with Shored Formwork in Multistorey
with loading a slab to above the design service load in
Buildings.” ACI Journal Proceedings V 60 (No. 12 Dec):
the UK is presented in Appendix E of the Guide to Flat
1729-1738.
Slab Formwork and Falsework (CSG 2003).
Liu, X. L., W. F. Chen and M. D. Bowman (1985).
“Construction loads on supporting floors.” Construction
REFERENCES International (December): 21-26.
ACI (2005). ACI 347.2R-05 Guide for Shoring/ McAdam, P. S. and J. E. Behan (1990). Multi-
Reshoring of Concrete Multistorey Buildings. storey Formwork Loading (Technical Paper 7). Sydney,
Farmington Hills, American Concrete Institute. Concrete Institute of Australia: 18 pages.
Beeby, A. W. (2000). ECBP Task 4 Report – Moss, R. M. (2003). Best practice in concrete
Early Striking and Backpropping (Report BR 394). frame construction: Practical application at St George
London, BRE. Wharf. London, BRE Centre for Concrete Construction.
Beeby, A. W. (2001). “Criteria for the loading of Park, H.-G., H.-J. Hwang, G.-H. Hong, Kim,
slabs during construction.” Structures & Buildings 146 Yong-Nam and J.-Y. Kim (2011). “Slab Construction
May 2001(2): 195:202. Load Affected by Shore Stiffness and Concrete
Beeby, A. W. (2001). “The forces in backprops Cracking.” ACI Structural Journal 108 (No. 6): 679-688.
during construction of flat slab structures.” Structures SA (1995). AS 3610:1995 Formwork for concrete.
& Buildings 146 August 2001(3): 307-317. Sydney, Standards Australia.
Bischoff, P. and A. Scanlon (2007). “Effective SA (1996). AS 3610 Supplement 2 – 1996
Moment of Inertia for Calculating Deflections of Formwork for concrete – Commentary. Sydney,
Concrete Members Containing Steel Reinforcement Standards Australia.
and Fiber-Reinforced Polymer Reinforcement.” ACI SA (2009). AS 3600:2009 Concrete Structures.
Structural Journal 104 (No. 1): 68-75. Sydney, Standards Australia.
BRE (2004). Early age construction loading. SA (2010). AS 3610.1:2010 Formwork for
London, The Concrete Centre. concrete Part 1: Documentation and surface finish.
BS (2008). BS EN 338:2008 Structural timber: Sydney, Standards Australia.
Strength classes. London, British Standards. Scanlon, A. and B. A. Suprenant (2011).
CSG (2003). Guide to Flat Slab Formwork and “Estimating two-way slab deflections.” Concrete
Falsework. Berkshire, Concrete Society on behalf of International (July): 29-34.
Concrete Structures Group.
10:20
Formwork Handbook
11:1
Formwork Handbook
11:2
Formwork Handbook
of blowholes, which then may fall outside the range 11.4 HONEYCOMBING
permitted for the specified finish Class, or exposed Areas of concrete surface that are coarse and
aggregate, which may be unacceptable if colour control stony are described as honeycombing. Honeycomb
is specified. Little or no effort has been made to colour- defects often are initially blamed on poorly sealed
match the mortar used to repair the form tie holes in formwork joints. However, insufficient fine material in
Figure 11.2. the mix or incorrect aggregate grading, as well as poor
Repair of face steps when carried out properly practices during mixing, placement and compaction
can result in an acceptable surface finish when the of the concrete can result in surface problems. The
concrete surface is new and when aged can be almost photograph in Figure 11.6 shows honeycombing,
impossible to detect. The photographs in Figures 11.3 which could be the result of either: grout leakage from
the formwork joint; or concrete that has not been
and 11.4 are examples of face step repairs that were
adequately mixed when delivered to the formwork and
considered acceptable for Class 2; i.e. without colour
poorly compacted. The absence of darker concrete
control.
around the edges (typical of loss of water or grout)
Face steps of less than 5 mm can be difficult
would suggest the latter. Apart from the surface
to measure with any degree of accuracy on the job.
appearance there has to be concern of the extent of
A simple means is to use widow packers that have
the voids in the concrete and the detrimental effect on
stated thickness of 1.5 mm and 3.2 mm. An example durability regardless of a satisfactory surface repair.
of measuring a rebate in a concrete surface is shown Placing and compaction problems with textured
in Figure 11.5. Here the blue packers used are marked forms can be difficult if not impossible to repair.
with a thickness of 1.5 mm. Some face steps can be The photograph in Figure 11.7 is the result of poor
so large that repair to fit within the limits for Class 3 is compaction where repairing the surface to replicate the
difficult if not impossible. sawn board finish will be very difficult.
11:3
Formwork Handbook
Figure 11.9: Rust stains left on the forms before the concrete is placed. However, there is another
possible problem even when the form surface has been
cleaned of all debris. This results from debris such as
scraps of tie wire being left on a soffit form for some
period of time before being removed. The photograph in
Figure 11.9 shows rust staining of the form surface that
has subsequently imprinted on to the concrete surface.
In addition, the concrete shows shading resulting
from reinforcing mesh also being left on the form for
a period of time. These stain and shading marks are
of no consequence if the soffit is to be covered by a
Figure 11.10: Concrete surface damaged after suspended ceiling, plastered or painted; however, if
removal of the forms the soffit is to be left bare (i.e. colour control specified)
then such marking can be objectionable. Similar tie wire
stain marks can be seen in the earlier photograph that
showed rubbish left in the trough of the beam form.
11:4
Formwork Handbook
The photograph in Figure 11.11 shows a consuming and costly to effectively remove. Where a
concrete surface that has been contaminated after the wall is specified as an exposed wall, care must be taken
forms have been removed. This is the result of poor to ensure that the forms are adequately cleaned before
construction practices at higher levels of the building. being erected.
Depending on the type of contamination a repair of The final photograph in Figure 11.14 shows the
the surface can be difficult or it may be impossible to result of inadequate erection procedures, in particular
completely clean the marking resulting in a need to inadequate sealing between the soffit form and
paint the concrete as the only effective remedy. concrete wall, accepting that the stair soffit off form
Other stains can adversely mark a wall surface finish was generally Class 2.
and repair can present some problems. If the intended
finished surface is to have some form of texture that REFERENCES
may not be a problem. The photograph in Figure 11.12 SA (1995). AS 3610 Supplement 1 – 1995
shows unsightly white staining of the textured surface Formwork for concrete – Blowhole and colour
which can be repaired by water blasting, if that does not evaluation charts (Supplement to AS 3610:1995).
change the specified finish. Sydney, Standards Australia
Dirty faces of wall forms will result in SA (2010). AS 3610:2010 Formwork for concrete
objectionable appearance of the concrete following Part 1: Documentation and surface finish. Sydney,
removal of the forms. Problems such as the marking Standards Australia.
in the photograph in Figure 11.13 can be very time
11:5
Formwork Handbook
A:1
Formwork Handbook
A:2
Formwork Handbook
B:1
Formwork Handbook
Formwork Handbook
SURFACE 1
Steel Alum. Timber Plywood Concrete
Plain Plain Galv. Prop. Prop. Soft wood Hard wood Proprietary Good one Combi ply Film faced Film faced Cast
SURFACE 2
Unrusted rusted painted waling Parallel Perp Parallel Perp beam side faced Finnish quality face
Plain unrusted 0.25 0.3 0.2 0.25 0.2 0.25 0.3 0.35 0.35 0.4 0.25 – – 0.05 –
Plain rusted 0.3 0.35 0.2 0.45 0.35 – – 0.4 – 0.35 0.25 0.15 0.15 0.15 –
Steel
Galvanised 0.2 0.2 0.2 0.25 0.2 0.3 0.35 0.35 0.35 0.3 0.15 – – 0.05 –
Proprietary painted 0.25 0.45 0.25 0.55 0.3 0.35 0.35 0.3 0.4 0.4 0.3 0.15 0.15 0.15 –
Aluminium Proprietary waling 0.2 0.35 0.2 0.3 0.25 0.3 0.3 0.3 0.3 0.2 0.2 0.2 0.2 0.05 –
Parallel 0.25 – 0.30 0.35 0.3 0.45 0.4 0.3 0.35 0.35 0.2 0.2 0.2 0.15 0.55
Softwood
Perpendicular 0.3 – 0.35 0.35 0.3 0.4 – 0.3 – 0.3 0.2 0.15 0.2 0.1 0.5
Timber Parallel 0.35 0.4 0.35 0.3 0.3 0.3 0.3 0.35 0.35 0.3 0.2 – – 0.15 0.4
Hardwood
Perpendicular 0.35 – 0.35 0.4 0.3 0.35 – 0.35 – 0.3 0.25 – – 0.15 0.5
Proprietary beam 0.4 0.35 0.3 0.4 0.2 0.35 0.3 0.3 0.3 0.35 0.2 – – 0.15 –
Good one side 0.25 0.25 0.15 0.3 0.2 0.2 0.2 0.2 0.3 0.2 0.3 0.2 0.2 0.15 0.25
Combi ply faced – 0.15 – 0.15 0.2 0.2 0.15 – – – 0.2 – – – 0.2
Plywood
Film faced Finnish – 0.15 – 0.15 0.2 0.2 0.2 – – – 0.2 – – – 0.2
Film faced quality 0.05 0.15 0.05 0.15 0.05 0.15 0.1 0.15 0.15 0.15 0.15 – – 0.1 0.15
Hardened Cast face – – – – – 0.55 0.5 0.4 0.5 – 0.25 0.2 0.2 0.15 –
Concrete
Trowelled face 0.4 0.55 0.2 0.45 0.35 0.75 0.55 0.5 0.5 0.45 0.25 – – – –
Soil Granular – – – – – – – – – – – – – – –
12/09/2016 7:36 am
C European
5. BS 5975:2008. Code of practice for temporary
works procedures and the permissible stress
Recommended Reading
design of falsework. London, British Standards
Institution.
6. CS (1999). Checklist for Erecting and
C.1 INTRODUCTION Dismantling Falsework. Berkshire, The Concrete
To obtain a comprehensive understanding of Society.
formwork design, in addition to the references cited 7. CS (2003). Checklist for Assembly, Use and
at the end of each Chapter, the following references Striking of Formwork. Berkshire, The Concrete
are recommended reading (sorted geographically, Society.
alphabetically and chronologically). 8. CS (2012). Formwork – A guide to good
practice. Berkshire, The Concrete Society.
REFERENCES 9. CSG (2003). Guide to Flat Slab Formwork and
Falsework. Berkshire, The Concrete Society on
American
behalf of Concrete Structures Group
1. Hurd, M. K. (1995). Formwork for Concrete.
10. DIN (2010). DIN 18218 Pressure of fresh
Farmington Hills, American Concrete Institute.
concrete on vertical formwork. Berlin, German
Australian Standards.
2. CCAA (2006). Guide to Off-form Concrete 11. ECS (2004). BS EN 12812 Falsework –
Finishes. Sydney, Cement and Concrete Performance requirements and general
Association of Australia. design. Brussels, European Committee for
3. McAdam, P. S. and G. Lee (1997). Formwork – Standardization.
A practical approach. London, E & EF Spon.
4. EWPAA (1993). Plywood in Concrete Formwork
Manual. Brisbane, Engineered Wood Products
Association of Australasia.
C:1
Formwork Handbook
RECOMMENDED PRACTICE
Z36
Formwork Handbook
RECOMMENDED PRACTICE
Z36
Formwork Handbook
Z36