Professional Documents
Culture Documents
Ground Slab Tutorial Solutions-1
Ground Slab Tutorial Solutions-1
Semester 1 -2022
Tutorial 04 – Ground Slab (Pour Layouts and Detailing)
You are required to propose the pour layout of the ground slab at a distribution centre
with dimensions of 100m x 50m as shown in Figure T2. Assume that the walls and roof
have been completed, and your task is now to work out the method and sequence for the
casting of the ground slab given the following constraints. The ground slab is 200mm thick
with a layer of F92 mesh placed 50mm from the top surface. Access is only via the two
roller doors shown at the bottom right of the plan.
Determine the size of each pour, and indicate the position of all construction joints, saw
cuts, and isolation joints. Estimate the widths of each joint after shrinkage of concrete.
Page 17
ABPL30046 Steel and Concrete Structural Systems
Semester 1 -2022
1. LONG STRIP CONSTRUCTION
• Long strip max pour is about 400 sq.m. Usually about
50m long and 6-8m wide.
• Concrete Will be poured from the back of the truck
• Panel length (L ) of 10-15m is recommended
• A transverse pour joint (BLACK line) is therefore
required at grid F.
1 7
• There will be isolation joint all around the columns.
1 4 POUR PLAN
• There will be 6 pours and will be done using hit and
miss method for pours 1-3 and will take 3 days.
• For pours 4-6 this will take 6 days to do with a day
delay for preparing each strip after pouring.
3
5
Shrinkage calculations (same for long strip in the
longitudinal direction
Students assume 400um(microstrain) for RC slab which is
4mm per 10m length of slab. Therefore, for 50m length,
total shrinkage is 20mm.
2 6 1 Pour joints at each ends takes up 50% of total
shrinkage: ie 10mm total with 5mm at each end.
For pour 1, this will be taken up at grids A and F
(Typical for all pours)
1. For the remaining 10mm, 50% will be taken up at
the centre. I will therefore put two centre saw cuts
joints at grids C and D (in BLUE). 50% of 10 =
5mm distributed between this two @ 2.5mm each.
2. The remaining 50% (5mm) will go to the saw cut
joints at grids B and E (in RED). Ie 2.5mm each.
3. NOTE: The portals are about 10m bays along
length and 8.33 spacing of columns along width.
Therefore the concrete panels of 10x8.33m OK.
With a saw cut in middle.
4. Also note with the 16.66m width, the shrinkage is
1.666x4=6.66mm. 50% (ie 3.33mm) will be taken
up by the pour joints on either sides. There will
need to be a saw cut joint (in dotted purple) in the
middle along grid line 2 to take up the other 50%
of 3.33mm.
Page 19
ABPL30046 Steel and Concrete Structural Systems
Semester 1 -2022
3. LARGE AREA CONSTRUCTION
POUR PLAN
1 4 2 • There will be 6 pours and will be done sequentially
Shrinkage calculations
Students assume 400um(microstrain) for RC slab which is
4mm per 10m length of slab. Therefore, for 30m length,
total shrinkage is 12mm and across width of about 25m it
is about 10mm.
For wider panel of 40x25, total shrinkage is 16mm.
5. All Pour joints at each end takes up 50% of total
3 shrinkage: For the 30m wide side, 6mm into two
5 6
pour joints and the remaining 6mm into the saw
cut joints (in RED) with 3mm in each.
6. Students can distribute the rest using same
concept.
Page 20