Professional Documents
Culture Documents
Morsi 1985
Morsi 1985
Morsi 1985
SPE
-Of PeWdeurnEngineer%
SPE 13743
In nearly every case, a blow out of a The Thamama Zone “C” sour gas reservoir was
producing well is caused by a combination of completelydevelopedin 19S4.
factors, including:
This sour gas field produces from a limestone
An act of God (earthquake,etc.). formation in the lower Cretaceous horizon,
The failure of a surface control equipment. with an average gas production rate of 30
A fire or explosion which causes the failure MMSCF/D per well and an average H2S and
of surface control equipment. C02 contents in the range of (0.7-S.0 Mole
Sabotage. %) and (3.9-8.0 Mole %) respectively. These
Human error: wells are located in a roughly U-shaped
Lack of proper safety equipment. pattern.
“n,
. SURFACEAND DOWNHOLE
PRODUCTIONSAFETY -smS FOR WJROIL ANDGAS WELLS SPE 1374;
The original reservoir pressure is 4300 psig (Fig. 2 shows a typical chemical injection
at 8500 ft. SS and the bottomhole temperature valve in the side mfi~~-+
r------ w,a-a.fil~
‘J”.=A, .
(BHT) is 260”F.
All items below the side pocket mandrel,
The gas wells are connected to four trunk which is set as deep as possible, are made of
lines (legs) which tie into tbe production 25% Cr duplex stainless steel since they do
facilitiesthrough four gathering lines. not receive any corrosioninhibition.
Equipment design and completion suitable for The tubing string is furnished with another
these wells is a complex undertakingin which SPM for D/K valve installation. The D/K
many aspects must be considered. The valve is a 1.1/2” O.D. wireline retrievable
following highlights the equipment and which is used to provide a means of
procedures used to provide safe and secure circulation between the casing and tubing.
operations:- This valve is normally closed. The
differential D/K valve acts initially as a
I. Downhole Completion dummy valve to prevent communicationbetween
the annulus and the tubing. The design of
In general, the Thamama C gas wells are cased the valve in use includes a moveable piston
with a 9.5/8” casing from the surface to a which, when in the closed position, blocks
depth of about 8500 ft. SS followed by a off the circulatingports and prevents fluid
short 7“ liner to the total depth movement through the valve. This piston is
approximately9000 ft. SS. held in place by shear screws, the number and
combination of which establish the shear
(Fig. 1 shows a typical completiondesign) pressure for the valve. Many different shear
pressures are obtainable by varing the shear
The tubing consists of a 7“ OD, 29 lb/ft. to screw combination. The D/K valve opens when
about 300 ft. below surface followed by a the required differential pressure between
4.1/2” O.D. 12:6 lb/ft. string to the packer the annulus and tubing is obtained.
setting depth at about 8100 ft. SS.
(Fig. 3 shows a D/K valve in the side pocket
The tubing string is provided with a landing mandrel).
nipple to accommodate a 7’ ball type surface
controlled - sub-surface safety valve A 7“ permanent production packer is normally
(SC-SSSV)which is installedat 300 ft. below set using electric wireline at about 150 ft.
surface. A 10 ft. length of alloy flow above the top of perforation. This type is
coupling is run above the SC-SSSV in order to selected due to the sour gas environment and
provide anti- turbulenceprotection. the high differential pressure generated
during stimulationoperations.
A continuous downhole open chemical injection
system is provided; it utilizes the The landing nipples in the tail pipe section
casing/tubing annulus as the injection are used to pressure test the tubing, packer
conduit. The annulus between the tubing and seals and to set Amerada pressure gauges. The
casing is filled with corrosion inhibitor bottom of the tail pipe is kept some 60 feet
mixed with diesel oil. The injection above the top of the pay.
chemical enters the Side Pocket Mandrel (SPM)
directly from the casing annulus, then flows Three of the Thamama Zone C wells have
through the chemical injection valve latched different downhole completion,being provided
into the mandre1 pocket. The chemical with duplex stainless steel tubing and no
volumes and the injection pressure are downhole chemical inhibition.
regulated at the surface by a chemical pump
and associatedcontrol equipment. II. Surface Equipment
I
K 13743 yin$alir
Also, the control system provides five To monitor corrosion rates, Magna
(5) command as follows: resistance probes and weight loss disc
coupons are installed near wellheads and
1. Well close. at the station manifold.
4
Eight (8) storm chokes were installed in The development of a solar energy
different wells to evaluate their system has provided a conversable
performance. These valves were supplied form of energy which in certain
by four differentmanufacturers. areas of the world, including most
desert areas, is available at
These valves were tested forty (40) practicallyall times of the year.
separate times by tripping and then
re-opening, on seventeen (17) occasions (See the attached figure No. 5)
an unsuccessfultest was recorded:
The ultimate objective is to employ
This gave an average estimated failure solar units on all oil producing
rate of 43%, which was considered too wells remote from existing power
high. sources:
Several problems were encountered while For remote and low associated gas
testing these storm chokes e.g. frequent production oil wells solar powered
valve malfunction, equalizing problems, units may provide an attractive and
loss of wireline tools in hole, etc. eConQrniCally j,dg~if~ca~~~
These problems were due to many alternativeto other methods.
different reasons.
b. Associated (Scrubbed)Gas
Two modified DC-SSSV’S were purchased
from each of the most promising two For high GLR wells the associated
suppliers for long term testing. These (scrubbed) gas is used as a power
are being tested for possible use in source to operate the hydraulic
suitable wells since their application control unit for SC-SSSVO
will yield a substantialcost saving.
The gas scrubber is used as a
So far the results on these DC-SSSV9S separator to remove the condensate
indicate that they are more reliable and water and produce the dry gas
than those used in previous test. required to operate the control
system.
II. Power Source to Operate the Wellhead
HydraulicUnits The gas scrubber vessel, valves,
controllers and piping should be
The types of power source to operate the designed for sour service.
surface hydraulic control units to
actuate Sc-sssv’s are a photovoltaic This power supply system requires
solar, associated (scrubbed) gas, more frequent field operator
bottled Nitrogen and self- contained attention.
integratedhydraulicpower systems.
(see the attached figure No. 6)
a. PhotovoltaicSolar System
c. Bottled Nitrogen
The testing and evaluation of a
solar system as a power supply to The amount of energy required at
operate the hydraulic control unit each wellsite to operate the SC-SSSV
for SC-SSSV has been successfully is small. So Nitrogen bottles can
completed. Two solar powered air also operate the hydraulic control
supply units were tested for more system. However, this requires
than one year in ADCO fields: frequent operator attention and the
risk of inadvertent well ‘shut-ins”
The solar supply system consisted due to pressure drops caused by
essentiallyof a solar panel, charge system leakage.
controller, storage batteries,
electric motor controller, electric Handling a large number of Nitrogen
motor/air compressor and air storage bottles is very difficult and it is
(tank). preferable te Me the= 2s afi extra
back up for other primary systems.
The photovoltaic system energizes a
D.C. battery cel1 which supplies d. Self-contained (Integrated)
power to an electrical air HydraulicPower System
compressor. This charges a low
pressure air tank that supplies the At present the testing and
end user (safety system) with evaluation of a self-contained
compressed air regulated to the (integrated) hydraulic power system
appropriate pressure. The as a power supply for the hydraulic
compressor is capable to charging control unit is being carried out.
the tank to about 120 psig which can Two units from different
provide the required amount of manufacturers are under test. If
useable air to the safety system.
4
L SURFACEANDDOWNHOLE
PRODUCTIONSAFETY S ITEMSFOR SOUROIL AND GAS WELLS SPE 13742
they prove successful, this system Pigging to remove condensate from the
may be consideredwhen an associated gathering system is being carried out using solid
gas supply is not available due to polyurethane pigs. The metal bodied pigs should
low GOR of the producingoil wells. not be used for running through sour gas pipelines.
.? ;
T
Tubi!
Control Lina
43 3/e”A P
—— 4 $/2”’ Tubing
S. P. M. For
D/)( Valw
Seat
—S. P.M. FOr C. I.V.
Side pocket
Mandrel
—- 9 5A3” Permtmont Packer
Check Valve
— Lher Hang.r
9 5/6 “
A
- Landing Nipple
Par fOrcfted Tube __
1
‘NO 90 Lending NiPP18
Nm -rfOmtd TUtW ——
%odl
FIOI
T(biw Shoe— —
POrfOratkms __
7’ b
I
j COMMAND
E---------
(5)
J
‘—-— Shear Screws WELL WEN
kiiii---
VALVE
OPEN
FTWMTIC WING
/s~ETY VALjIE”-
—
h!i!iiz
1 —— I
I
CHDKE
1
~g(a SAFETY
.
,... - CWTFOL FANEL MDRAWIC MASTER
CHEMICALlNJECTm AFETY VALVE
I // ‘i”~”
gQ@ SYSTEM
‘reduction 1~ r
Flow
Annululs
b
SURFACECDNTRC)LLIII w
. f S118SURFACESAFETY VALVE
w
*
FIQ. 3-TYplcal D/K valve in SPM
w
Fig. 4—Wellhead controland chemicalinjectionsystems,
FLLSISLE RM LOOP ( IOI,Vpre~ur.g)
ESD STATION
kl
SPE 13743
ESD STATfON
H
I I 1) -
I 1
Ehct.
Motor +
Hyd Pu~
I J
DIESEL GENERATOR