Change Order Feb 06, 2020
Change Order Feb 06, 2020
BOQ ACTUAL
REMARKS
QTY Unit ADDITIONAL QTY
1 20mm REINFORCEMENT BARS 85 pcs 109 pcs ₱ 50,685.00 Change layout of reinforcement
2 10mm REINFORCEMENT BARS 10 pcs 175 PCS ₱ 20,650.00 bars on post and footing
6 3 x 3 x 6mm ANGLE BAR 28 pcs 22 PCS ₱ 40,700.00
7 3 X 3 X 9MM / 8MM ANGLE BAR 48 pcs 43 PCS ₱ 113,950.00 For Single Strut to Double
9 2 X 2 X 4.5MM ANGLE BAR 33 pcs 7 PCS ₱ 5,740.00 Strut on Girder and Trusses
10 3 x 3 x 8mm Angle bar 48 pcs 19 ₱ 47,500.00
For removing of Boulder for
11 BACK HOE 1 lot 1 LOT ₱ 25,400.00 footing layout
cost of materials
on additional ₱ 304,625.00
additional cost of
materials and labor ₱ 441,706.25
profit ₱ 66,255.94
overhead ₱ 66,255.94