Agreement (Dosc (Rev.) )
Agreement (Dosc (Rev.) )
OSMEÑA
BRGY. OSMEÑA, DAPA, SIARGAO, SURIGAO DEL NORTE
This Contract/Agreement made and entered into this 25th day of January 2018, by and between
ECCON DEVELOPMENT CORPORATION, with official address at Garing, Consolascion, Cebu, Philippines
herein represented by the Operation Manager, Engr. DON CAJILOG, hereinafter called “the
Owner/Contractor” (the first party).
And
Whereas, the Client needs the services of the Sub-Contractor to execute the works describes in
the table below.
Page1 of 2
COMPLETION OF SPORT COMPLEX, BRGY. OSMEÑA
BRGY. OSMEÑA, DAPA, SIARGAO, SURIGAO DEL NORTE
1. That the Contractor Cost (Cash) for Labor Work is Five Hundred Fifty Thousand Pesos Only
(Php 550,000.00)
2. That the Client/Contractor shall pay the Sub-Contractor for billing is weekly bases according to
its work accomplishment and acceptance of the work in accordance to plans and specifications.
The details of the work accomplishment shall be reflected in the Statement of Work
Accomplishment (SWA), verified by the Client’s/Contractor’s representative.
3. The Sub-Contractor commits to complete all the works within Ninety nine (90) Calendar
Days(CD).
4. The 10% of the contract amount should be paid by the Client/Contractor for mobilization fee
before commencement of the project.
5. Occupational Safety and Health Program, Bunk house and Materials needed for the completion
of the Project stated herewith will be provided by the Client/Contractor.
6. The Sub-contractor is exclusively responsible for all labors and any incidents that will happen
within the project site.
In WITNESS WHEREOF, the parties hereto have caused this Agreement to be executed this
_25_day of January_2018.
WITNESS:
Page2 of 2
COMPLETION OF SPORT COMPLEX, BRGY. OSMEÑA
BRGY. OSMEÑA, DAPA, SIARGAO, SURIGAO DEL NORTE
Page3 of 2