Daily Activity Report (Subcontractor)

Project : RDMP JO RU V Contractor No : RDMP-H-SC-SC-003 Work Work stop


Working
Discipline : SC Date : 06-Sep-23 From To Hour Reason
Time (H)
Subcontractor : PT. DAEAH E&C Report No : 26411-SS-SC003-JO-DP-00643 7:00 18:00 0.00
Work Activity : Common Scaffolding Today Work 10.00 Hour
1. Work Description
TODAY / DONE TOMORROW / PLAN
Install Scaffolding at Kariangau 37 Install Scaffolding at Kariangau 37
Install Scaffolding at PR-084-01 Install Scaffolding at PR-084-01
Install Scaffolding at R83 Install Scaffolding at R83
Install Scaffolding at R16 Install Scaffolding at R16
Install Scaffolding at R60 Install Scaffolding at R60

2. DIRECT MANPOWER (MD)


Local Non-
Korea Foreigner Previ. Today Accum.
No Direct BPN Local No Work Group Work Package Previ. Today Accum.
M F M F M F M F M F M F M F
1 Supervisor - - - - 1 - - - 273 - 1 - 274 -
2 Inspector - - - - 1 - - - 535 - 1 - 536 -
3 Foreman - - - - 6 - - - 1,521 - 6 - 1,527 -
4 Scaffolder - - 1 - 70 - - - 21,060 - 71 - 21,131 -
5 Helper - - 22 - - - - 4,561 - 22 - 4,583 -
6 Paramedic - - - 3 - - - - - 750 - 3 - 753
7 Rigger - - - - - - - - 168 - - - 168 -
8 Operator TMC - - - - - - - - 45 - - - 45 -
9 Safetyman - - 4 - 1 - - - 1,141 13 5 - 1,146 13
10 Material Control - - 1 - - - - - 530 13 1 - 531 13
11 Permit Holder - - - 2 - - - - - 79 - 2 - 81
12
13
14
15
16
Sub-Total 0 0 28 5 79 0 0 0 29,834 855 107 5 29,941 860
Total 0 33 79 0 30,689 112 30,801 Total - - -
3. INDIRECTION MANPOWER (MD)
Local Non-
Korea Foreigner Previ. Today Accum.
No Indirect BPN Local
M F M F M F M F M F M F M F
1 Common Labor - - - - - - - - - - - - - -
2 Staff 1 - 2 - 1 - - - 2,498 437 4 - 2,502 437
3 Others - - 3 - - - - - 1,177 25 3 - 1,180 25 Sub-Total 1 - 5 - 1 - - - 3,675 462 7 - 3,682 462
4 Total 1 5 1 - 4,137 7 4,144
4. EQUIPMENT (ED)
No Item Capacity Unit Previ. Today Accum. 18
1 Shackle 6.5 TON 221 - 221 19
2 TMC 15 TON 39 - 39 20
3 Crane 50 TON 66 - 66 21
4 Trailer 40 TON 40 - 40 22
5 Webbing Sling 2 TON 236 - 236 23
6 Webbing Sling 3 TON 198 - 198 24
7 Webbing Sling 4 TON 112 - 112
8 Webbing Sling 5 TON 98 - 98
9 Truck 7 TON 550 1 551
10
11
12
13
14
15
16
17 Total 1,560 1 1,561
Prepared by Subcontractor Reviewed by Contractor
Name : Joung Seok Ha Signature : Name : Resaldy Signature :

Date : 6-Sep-23 Date : 6-Sep-23

EPC ISBL and OSBL for the RDMP PROJECT


RDMP RU V – BALIKPAPAN

DAILY QUANTITY REPORT


[RDMP] EPC ISBL and OSBL for the RDMP PROJECT Date: 6-Sep-23

Quantity
No Description Heigth Level UOM Total Quantity C-Space Activity ID Remarks
Acum Last Day Today Acum Plan Tomorrow %

1 Install Scaffolding M² 94,610.93 76,744.92 286.00 77,030.92 - 81.42%

Area PR-052-02

Pipe Rack Erection 0-10 M M² 2,150.10 2,150.10 - 2,150.10 - 100.00% CA052SS50005-A301 DONE
Pipe Rack Erection 10-20 M M² 3,354.30 3,354.30 - 3,354.30 - 100.00% CA052SS50005-A305 DONE

Pipe Rack Erection 20-30 M M² 5,759.80 5,759.80 - 5,759.80 - 100.00% CA052SS50005-A309 DONE

Area PR-052-05

Pipe Rack Erection 0-10 M M² - - - - - 0.00% N/A

Pipe Rack Erection 10-20 M M² - - - - - 0.00% N/A

Pipe Rack Erection 20-30 M M² 1,931.30 1,931.30 - 1,931.30 - 100.00% CA052SS50005-A401 DONE

Area STR-052-04

Pipe Rack Erection 0-10 M M² 88.00 88.00 - 88.00 - 100.00% CA052SS500010 DONE

Pipe Rack Erection 10-20 M M² 1,847.65 1,847.65 - 1,847.65 - 100.00% CA052SS500010 DONE

Pipe Rack Erection 20-30 M M² 3,783.30 3,783.30 - 3,783.30 - 100.00% CA052SS500010 DONE

Area STR-052-05

Pipe Rack Erection 0-10 M M² 1,077.40 1,077.40 - 1,077.40 - 100.00% CA052SS50015 DONE

Pipe Rack Erection 10-20 M M² 83.40 83.40 - 83.40 - 100.00% CA052SS50015 DONE

Pipe Rack Erection 20-30 M M² - - - - - 0.00% N/A

Area STR-052-07

Pipe Rack Erection 0-10 M M² 560.00 560.00 - 560.00 - 100.00% CA052SS50020 DONE

Pipe Rack Erection 10-20 M M² 1,110.70 1,110.70 - 1,110.70 - 100.00% CA052SS50020 DONE

Pipe Rack Erection 20-30 M M² 950.3 950.25 - 950.3 - 100.00% CA052SS50020 DONE

Area PR-321-14 (R70)

Pipe Rack Erection 0-10 M M² 411.00 411.00 - 411.00 - 100.00% CB321SS50155 DONE

Pipe Rack Erection 10-20 M M² 1,498.40 1,498.40 - 1,498.40 - 100.00% CB321SS50155 DONE

Pipe Rack Erection 20-30 M M² 330.00 330.00 - 330.00 - 100.00% CB321SS50155 DONE

Area PR-321-15

Pipe Rack Erection 0-10 M M² 70.00 70.00 - 70.00 - 100.00% CB321SS50160 DONE

Pipe Rack Erection 10-20 M M² 84.00 84.00 - 84.00 - 100.00% CB321SS50160 DONE

Pipe Rack Erection 20-30 M M² - - - - - 0.00% CB321SS50160 N/A

Area HRSG UNIT A/B/C/D


HRSG 0-10 M M² - - - - - 0.00% N/A

HRSG 10-20 M M² 144.00 144.00 - 144.00 - 100.00% DONE

HRSG 20-30 M M² - - - - - 0.00% N/A

Area PR-160-01

Pipe Rack Erection 0-10 M M² 489.60 489.60 - 489.60 - 100.00% CA160SS30007-A101 DONE

Pipe Rack Erection 10-20 M M² 318.00 318.00 - 318.00 - 100.00% CA160SS30007-A101 DONE

Pipe Rack Erection 20-30 M M² 123.00 123.00 - 123.00 - 100.00% CA160SS30007-A101 DONE

Area PR-001 R01 ~ R05

Pipe Rack Erection 0-10 M M² 597.60 597.60 - 597.60 - 100.00% CA001SS30010-A105 DONE

Pipe Rack Erection 10-20 M M² - - - - - 0.00% CA001SS30010-A105 N/A

Pipe Rack Erection 20-30 M M² - - - - - 0.00% CA001SS30010-A105 N/A

Area PR-331-06

Pipe Rack Erection 0-10 M M² 66.00 66.00 - 66.00 - 100.00% CB331SS50100 DONE

Pipe Rack Erection 10-20 M M² - - - - - 0.00% N/A

Pipe Rack Erection 20-30 M M² 144.00 144.00 - 144.00 - 100.00% CB331SS50100 DONE

Area PR-321-09 ( R 41 )

Pipe Rack Erection 0-10 M M² - - - - - 0.00% CB321SS50115 N/A

Pipe Rack Erection 10-20 M M² 621.00 621.00 - 621.00 - 100.00% CB321SS50115 DONE

Pipe Rack Erection 20-30 M M² 189.00 189.00 - 189.00 - 100.00% CB321SS50115 DONE

Area PR-052-06

Pipe Rack Erection 0-10 M M² 882.00 882.00 - 882.00 - 100.00% CA052SS50005-A403 DONE

Pipe Rack Erection 10-20 M M² - - - - - 0.00% CA052SS50005-A403 N/A

Area PR-002-01 (VDU)

Pipe Rack Erection 0-10 M M² 80.00 80.00 - 80.00 - 100.00% CA002SS50005 DONE

Pipe Rack Erection 10-20 M M² 179.40 179.40 - 179.40 - 100.00% CA002SS50005 DONE

Area PR-002-02 (VDU )

Pipe Rack Erection 0-10 M M² 135.00 135.00 - 135.00 - 100.00% CA002SS50010 DONE

Pipe Rack Erection 10-20 M M² 180.80 180.80 - 180.80 - 100.00% CA002SS50010 DONE
Area PR-002-03 (VDU )

Pipe Rack Erection 0-10 M M² 167.60 167.60 - 167.60 - 100.00% CA002SS50015 DONE

Pipe Rack Erection 10-20 M M² - - - - 0.00% CA002SS50015 N/A

Area PR-002-04 (VDU )

Pipe Rack Erection 0-10 M M² 25.80 25.80 - 25.80 - 100.00% CA002SS50020 DONE

Area STR-052-09

Pipe Rack Erection 0-10 M M² 180.00 180.00 - 180.00 - 100.00% CA052SS50025 DONE

Pipe Rack Erection 10-20 M M² 1,053.00 1,053.00 - 1,053.00 - 100.00% CA052SS50025 DONE

Pipe Rack Erection 20-30 M M² - - - - 0.00% CA052SS50025 N/A

Area PR-321-06 ( r17)

Pipe Rack Erection 0-10 M M² - - - - 0.00% N/A

Pipe Rack Erection 10-20 M M² 160.00 160.00 - 160.00 100.00% CB321SS50145 DONE

Area STR-052-03

Pipe Rack Erection 0-10 M M² 1,352.40 1,352.40 - 1,352.40 100.00% CA052SS50030 DONE

Pipe Rack Erection 10-20 M M² 402.60 402.60 - 402.60 100.00% CA052SS50030 DONE

Area PR-321-07 ( LPG )

Pipe Rack Erection 0-10 M M² 96.00 96.00 - 96.00 100.00% CB321SS50145 DONE

Area PR-084-01

Pipe Rack Erection 0-10 M M² 4,058.70 3,848.70 - 3,848.70 94.83% CA084SS50010-A103 ON GOING

Pipe Rack Erection 10-20 M M² 3,756.95 3,274.95 80.00 3,354.95 89.30% CA084SS50010-A103 ON GOING

Pipe Rack Erection 20-30 M M² 485.80 485.80 - 485.80 100.00% CA084SS50010-A103 DONE

Area PR-001 01R ~ 05R (CDU)

Pipe Rack Erection 0-10 M M² 36.00 36.00 - 36.00 100.00% CA001SS30010-A103 DONE

Pipe Rack Erection 10-20 M M² 368.00 368.00 - 368.00 100.00% CA001SS30010-A103 DONE

Area PR-321-18B (R81)

Pipe Rack Erection 0-10 M M² 2,322.00 2,322.00 - 2,322.00 100.00% CB321SS50130 DONE

Pipe Rack Erection 10-20 M M² 1,279.20 1,279.20 - 1,279.20 100.00% CB321SS50130 DONE

Area PR-334-01

Pipe Rack Erection 0-10 M M² 2,140.83 2,030.83 - 2,030.83 94.86% CB334SS50100 ON GOING

Pipe Rack Erection 10-20 M M² 770.90 770.90 - 770.90 100.00% CB334SS50100 DONE

Area STR-052-011

Pipe Rack Erection 0-10 M M² 198.00 198.00 - 198.00 100.00% CA052SS50040 DONE

Pipe Rack Erection 10-20 M M² 117.00 117.00 - 117.00 100.00% CA052SS50040 DONE

Area PR-059-02
Pipe Rack Erection 0-10 M M² 2,377.62 2,377.62 - 2,377.62 100.00% CA059SS50005-A201 DONE

Pipe Rack Erection 10-20 M M² 792.54 792.54 - 792.54 100.00% CA059SS50005-A201 DONE

Area STR-052-02

Pipe Rack Erection 0-10 M M² 325.38 325.38 - 325.38 100.00% CA052SS50035 DONE

Pipe Rack Erection 10-20 M M² 449.75 449.75 - 449.75 100.00% CA052SS50035 DONE

Pipe Rack Erection 20-30 M M² 933.75 487.45 - 487.45 52.20% CA052SS50035 ON GOING

Pipe Rack Erection 30 M - ~ M² 287.55 287.55 - 287.55 100.00% CA052SS50035 DONE

Area STR-052-04

Pipe Rack Erection 0-10 M M² 172.50 172.50 - 172.50 100.00% CA052SS500010 DONE

Area PR-052-03

Pipe Rack Erection 0-10 M M² 338.00 338.00 - 338.00 100.00% CA052SS50005-A201 DONE

Area PR-334-V03

Pipe Rack Erection 0-10 M M² 624.00 624.00 - 624.00 100.00% CB334SS50120 DONE

Pipe Rack Erection 10-20 M M² 766.00 766.00 - 766.00 100.00% CB334SS50120 DONE

Area PR-321-02 ( R11)

Pipe Rack Erection 0-10 M M² 972.00 972.00 - 972.00 100.00% CB321SS50105 DONE

Pipe Rack Erection 10-20 M M² 1,782.00 1,782.00 - 1,782.00 100.00% CB321SS50105 DONE

Pipe Rack Erection 20-30 M M² 300.00 300.00 - 300.00 100.00% CB321SS50105 DONE

Area PR-321-03 ( R12)

Pipe Rack Erection 0-10 M M² 2,225.90 2,204.40 - 2,204.40 99.03% CB321SS50110 ON GOING

Pipe Rack Erection 10-20 M M² 5,254.67 4,360.45 - 4,360.45 82.98% CB321SS50110 ON GOING

Area STR-052-01

Pipe Rack Erection 0-10 M M² 236.00 236.00 - 236.00 100.00% CA052SS50045 DONE

Area PR-321-11

Pipe Rack Erection 0-10 M M² 8,100.00 3,791.00 100.00 3,891.00 48.04% CB321SS50180 ON GOING

Pipe Rack Erection 10-20 M M² 5,700.00 1,596.00 - 1,596.00 28.00% CB321SS50180 ON GOING

Area PR-321-06

Pipe Rack Erection 0-10 M M² 764.00 764.00 - 764.00 100.00% CB321SS50145 DONE

Area PR-321-19 (R82)

Pipe Rack Erection 0-10 M M² 1,596.00 1,596.00 - 1,596.00 100.00% CB321SS50135 DONE

Pipe Rack Erection 10-20 M M² 798.00 798.00 - 798.00 100.00% CB321SS50135 DONE

Area PR-321-20 (R83)

Pipe Rack Erection 0-10 M M² 840.00 720.00 36.00 756.00 90.00% ON GOING

Pipe Rack Erection 10-20 M M² 360.00 360.00 - 360.00 100.00% DONE

Area VDU-BPP2

Pipe Rack Erection 0-10 M M² 450.00 450.00 450.00 100.00% DONE

Area PR-334-V02

Pipe Rack Erection 0-10 M M² 556.00 510.00 - 510.00 91.73% ON GOING

Pipe Rack Erection 10-20 M M² 296.00 260.00 - 260.00 87.84% ON GOING

Area PR-321-13 (R62)

Pipe Rack Erection 0-10 M M² 1,050.00 750.00 - 750.00 71.43% ON GOING


Pipe Rack Erection 0-10 M M² 525.00 200.00 - 200.00 38.10% ON GOING

Area PR-052-12

Pipe Rack Erection 0-10 M M² 346.50 346.50 - 346.50 100.00% DONE

Area PR-321-12 (R61)

Pipe Rack Erection 0-10 M M² 7,182.00 720.00 70.00 790.00 11.00% ON GOING
Quantity
No Description Heigth Level UOM Total Quantity Remarks
Acum Last Day Today Acum Plan Tomorrow %
3
2 Acces Tower M 4,816.30 4,492.30 60.00 4,552.30 - 94.52%

Area STR-052-04

Acces Tower Erection 30 M - ~ M3 1,296.30 1,296.30 - 1,296.30 100.00% DONE

Area PR-052-02
3
Acces Tower Erection 0-10 M M 180.00 180.00 - 180.00 100.00% DONE

Acces Tower Erection 10-20 M M3 360.00 360.00 - 360.00 100.00% DONE

Area PR-321-14 R70


3
Acces Tower Erection 0-10 M M 180.00 180.00 - 180.00 100.00% DONE

3
Acces Tower Erection 10-20 M M 198.00 198.00 - 198.00 100.00% DONE

Area K-052-01~03

Acces Tower Erection 0-10 M M3 790.40 790.40 - 790.40 100.00% DONE

3
Acces Tower Erection 10-20 M M 118.60 118.60 - 118.60 100.00% DONE

Area PR-002-03 (VDU )


3
Acces Tower Erection 0-10 M M 316.00 316.00 - 316.00 - 100.00% CA002SS50015 DONE

Acces Tower Erection 10-20 M M3 - - - - - 0.00% CA002SS50015 N/A

Area PR-321-09 ( R 41 )
3
Acces Tower Erection 0-10 M M - - - - - 0.00% CB321SS50115 N/A

3
Acces Tower Erection 10-20 M M 171.00 171.00 - 171.00 - 100.00% CB321SS50115 DONE

Area PR-331-06 ( R 42 )

Acces Tower Erection 0-10 M M3 - - - - - 0.00% CB331SS50100 N/A

3
Acces Tower Erection 10-20 M M 54.00 54.00 - 54.00 - 100.00% CB331SS50100 DONE

Area PR-002-04 (VDU)


3
Acces Tower Erection 0-10 M M 144.00 144.00 - 144.00 - 100.00% CA002SS50020 DONE

Area PR-002-01 (VDU)


Acces Tower Erection 0-10 M M3 168.00 168.00 - 168.00 - 100.00% CA002SS50005 DONE

Area PR-321-18A & 18B (R81)


Acces Tower Erection 0-10 M M3 48.00 48.00 - 48.00 - 100.00% CA002SS50005 DONE
Area PR-059-02)
Acces Tower Erection 0-20 M M3 270.00 270.00 - 270.00 - 100.00% CA002SS50005 DONE
Area PR-321-20 ( r83 )
3
Acces Tower Erection 0-20 M M 198.00 198.00 - 198.00 - 100.00% CA002SS50005 DONE
Area PR-321-06 (R16)
3
Acces Tower Erection 0-20 M M 324.00 - 60.00 60.00 - 18.52% CA002SS50005 ON GOING
Quantity
No Description Heigth Level UOM Total Quantity Remarks
Acum Last Day Today Acum Plan Tomorrow %
3 Dismantle M² 1,201.00 1,201.00 - 1,201.00 100.00%
Area STR-052-05
Pipe Rack Dismantle 0-10 M M² 544.70 544.70 - 544.70 100.00% DONE
Area STR-052-07
Pipe Rack Dismantle 20-30 M M² 416.30 416.30 - 416.30 100.00% DONE
Area HRSG A
Pipe Rack Dismantle 20-30 M M² 36.00 36.00 - 36.00 100.00% DONE
Area HRSG B
Pipe Rack Dismantle 20-30 M M² 36.00 36.00 - 36.00 100.00% DONE
Area HRSG C
Pipe Rack Dismantle 20-30 M M² 36.00 36.00 - 36.00 100.00% DONE
Area HRSG D
Pipe Rack Dismantle 20-30 M M² 36.00 36.00 - 36.00 100.00% DONE
Area PR-321-07
Pipe Rack Dismantle 20-30 M M² 96.00 96.00 - 96.00 100.00% DONE
Quantity
No Description Heigth Level UOM Total Quantity Remarks
Acum Last Day Today Acum Plan Tomorrow %
4 Dismantle M3 - - - - - 0.00%

Prepared By Checked & Review by JO


PT. Daeah E & C RDMP JO

Joung Seok Ha Resaldy Hasyim


Construction Manager JO Scaffolding SPV

PROJECT ; RDMP JO RU V
CONTRACT. NO ; RDMP-H-SC-SC-003
DATE ; Wednesday, September 6, 2023
PHOTOGRAPH DAILY REPORT

Tool Box Meeting Daily Check Up

Install Scaffolding at PR-321-11 Install Scaffolding at PR-321-11


Install Scaffolding at PR-321-20 Install Scaffolding at PR-321-20

SI Area Kariangau 75 SI Area Kariangau 75

Prepared by : Joung Seok Ha Date : 6-Sep-23