RBR-TSRA

15 Boundary Pillar
Reinforced cement concrete M15 grade boundary
RBR- pillars/local stone of standard design as per IRC:25,
TSR fixed in position including finishing and lettering but
A-15 excluding painting as per drawing and Technical
Specification Clause 1704 MORD / 806 MORTH

Unit = each
Taking output = 57 Nos.
a) M-15 grade of concrete or Demarcation Stones Each 57 85.7 4884.90
( 900 x 150 x 150 mm) MAT-00419
c) Excavation in soil for foundation
As per item No. 1 of Chapter 11 cum 10.72
d) lettering, each 10 cm high
As per Item No. 1 of Chapter 10 per 2280.00
letter
per
cm
high
Transportation and fixing
f) Labour
Mate day -
Mazdoor (Unskilled) day 14.82
g) Machinery
Tractor with trolley hour 6.00
h) Material
Stone spall cum 11.97
i&j) Overheads & Contractors Profit
k) Cost for 57 Nos. boundary pillar =
a+b+c+d+e+f+g+h+i+j

Rate for each boundary pillar = k/57


Note : 1. In case of soft ground, a proper foundation may be provided as per
approved design. In case foundation is required to be provided, the items of
excavation and foundation concrete are required to be measured and paid
separately.
2. In case local stone is to be used in place of precast RCC stones, then rate of
cement concrete and steel reinforcement may be deleted.

16 G.I Barbed Wire Fencing 1.2 m high


i Providing and fixing 1.2 m high GI barbed wire fencing
with 1.8 m RCC posts 150 mm x 150 mm placed every
3 m centre-to-centre founded in M15 grade cement
concrete, 0.6 m below ground level, every 15th post,
RBR- last but one end post and corner post shall be strutted
TSR on both sides and end post on one side only and
A-16 provided with 9 horizontal lines and 2 diagonals
interwoven with horizontal wires, fixed with GI staples,
turn buckles etc., complete as per Clause 1705
MORD.

Unit = per running m


Taking output = 30 m
a) Labour
Mate day -
Blacksmith day 0.25
Mazdoor (Unskilled) day 2.09
b) Machinery
Barbed wire 335 m length @ 9.38 kg per 100 m kg 31.42
R.C.C. Post 150 mm x 150 mm x 1.80 m M15 Grade
concrete 13 x 150 mm x 150 mm x 1.8 m
As per item No. 5 (i) or (ii) of Chapter 12 cum 0.526
Add 5 per cent extra cost for formwork of M-15
Supply of HYSD Bars including cutting, bending, tying
& placing in position.
10 mm dia HYSD bars for posts
13 x 4 x 1.8 = 93.6 m @ 0.62 kg/mt = 43.60 kg
8 mm dia HYSD bars for rings
13 x 10 x 0.6 = 78 m @ 0.39 kg/mt = 30.42 kg

441
RBR-TSRA

Total = 74.02 Kgs


As per item No. 6 of Chapter 12 t 0.074
Add for GI staple binding wire, drilling holes, etc. @ 2
per cent of the cost of material
c) Painting
Applying two coats of painting including primer coat on
exposed surface of RCC posts
As per item No. 6 of this Chapter sqm 8.14
d&e) Overheads & Contractors Profit
Cost for 30 m fencing = a+b+c+d+e
Rate per m = (a+b+c+d+e)/30
Note : Cost of excavation for foundation and foundation concrete to be added separately
in the cost estimate as per approved design. The rate for these items may be taken from
respective Chapters.