Professional Documents
Culture Documents
Ground Improvement, Principles
Ground Improvement, Principles
The US practice of ground improvement is divided into six I-es pratiques amrlricaines d'am6lioration du sol se classent
main categod"", {gEileation, 1o_!!s-91 idegon, Jqi$gfSe: en six cat6gories principales: densification, consolidation,
tr_eit4gent, t!e44i!-9te!d!4gg1 and blq' renforcement, traitement chimie, stabilisation thermique et
!elt, chemical
.fechnicaT
stabili.zation. Densification, which applies stabilisation biotechnique- La densification, qui s'applique
'----i"fy to- g.r.;il;ls, includes vibrocompactiory jly: prineipalement aux sols granuleux, comPrend les m6th-
r4glc compaction, blasting and compaction grouting. odes de vibrocompaction, de compaction dynamique,
rsoliffi[i6n-Ji--basically achieved through Preloading d'abattage et d'injection de compaction. La consolidation
ar,d the use of vertical drains. SoiI reinforcement is consiste en gros i effectuer une pr6charge at i utiliser des
dir.ided into two groups:-th-ose involving compacted fill canaux de drainage verticaux. Le renforcernent se comPose
such as mechanical)f-stabilized backfill systemg and those de deux groupes de m6thodes: celles qui consistent en un
applied in situ such as soil nailing: element walls, micro- remblayage compact6 corrune les systEmes de rernblayage
piles and stone columns. The chemical treatment methods stabilis6 de maniEre mdcanique et celles qui sont appli-
discussed are those applied at depth such as perneation qu6es iz sifz comme le cloutage du sol, le rnur i 6l6ments,
gxouting jet grouting, deep soil mixing and lime columns. les micropiles et les col-onnes de pierre. Les m6thodes de
Thermal stabilization is covered through ground freezing kaitement chimique sont appliqu6es en profondeur
and its use in urban construction. Finally, biotechnical cornme l'injection impr6gnante, I'injection par !et, le
stabilization, which is one of the latest developments in m6lange du sol en.profondeur et les colonnes du chaux. La
the field, is'briefl.y presented. Discussed in the PaPer are stabilisation thermique, effectur5e en gelant le sol, est
the applications, advantages, limitations, design and con- utilis6e dans la construction urbaine. Enfin, la stabilisation
struction aspects of each ground improvemi:nt method as biotechnique, qui repr6sente I'un des derniers d6veloppe-
well as the durability and long-terrn perforurance of the ments dans ce dornaine, fera I'objet d'une corte pr6senta-
improved ground. The use of ground improvemqnt in tion. Dans cet exposti, nous exarninons les applications, les
enwironmental engineering is briefly highlighted" av&ntages, les limites, la conception et I'6laboration de
chaque m6thode d'am6lioration des sols ainsi que la
. Keywords: .dnchors & anchorages; chemical grout- durabilit6 et la performance i long terme des sois am6li-
,1.'r.g; compaction groutinB; contaminated ground; deep orr6s. Nous dr-icrivons rapidement l'utilisation des techni-
- ooii mixing; field testing & monitoring; treezing; ques d'am6lioration dans le g6nie environnemental.
rsynihetic reinforcemen! heating; jet grouting
r"^rre; r.ricro piles; plant & equipmen! preloading
retaini.ng walls; slurry; soil nails; steel reinforce-
ments; testing stone columns; vibro compaction
the paPer.
C.t"goty l' Duntifitdion
metLg$
imProvemenl mgthocls
-
round imProvement
Ground Granular materials are normally
stabilizedly densi.fication'
prooce
Ground improveme"t metiods in
US
Table !. Used for'
lmprovement method Btffi"-ni'ag ccr'Pc'ut
Sand, collaPsing silt Lu\\t!f6\d)
Chemical B, St, Sw, Cc' Pr
Admixture (cement) Plasdc claY, swelling claY
Chemicai B, Sq Se
Admixiure (lime) Coarse soils' rock
Chemical B, St, Se
Cement groudng Fine sand
Chemical U, Se, L, Sq En
Chemical grouting All soils
B,
Chemical / reiaforcem ent St, E, Ss, En
Jet SfoutinB Fine-grained soils
Chemical Se, En, St
Deep soil mixing Saturated claY
Chemical B, Sq En
Lime columns Saturated claY
Consoiidation B, St, En
Pr:eloading/drains Saturated claY
Consolidation B, St, L
Electro-osmosis Sand and gravel
Densification B, St, L, En
VibrocomPaction Granular soils' fills
Densification B,SqL
Dynamic comPaction Sarurated sand
Densification Sq Ex
Blasting Loose soil with voids
Densffication St
Compaction grouting Granular soil
B, Sl
Reinforcement
MechanicallY stabilized backfi ll Gmnular soil
Sl, Ex
Reinforcement U, Sl, En, B, St
Soil nailing Granular soil
'MicroPiles Reinforcement St, St, E, L
Clay, liquefiable soil
Reinforcement Sl, Ex
Stone columns Fertile granular soil
Reinforcement Sl, B, En, Cc
Biotechnical stabilization Loose, collaPsible silts
Thermal Ex, Se, En
Heating Underwater sand
Thermal
ft"*U,'- - , :: , """"' porc L, liquefacrion resisance; Pr, plasticity
reducdon'; se, seepage
if':
. "
collapsing control; En,.environmenEl
ti"ll,"l'_T;
B, h,:-; i: r.,r:ciq6 cc, ::::::,:",",tt \-..
control; Sl, slope stability; s,, J;;'"nt controli Sw' swelling reduction; U' underpinning I
SteP 1 Step 2
194
and the soil particles are moved to new packing arrange-
100
Equipment lprocedures
The most corunon pieces of equipment in vibrocompac- t
'E
tion are the vibroflot, Terra probe, vibrorod, vibrowing, 80
vibrating I-beam, flexiprobe and vibrocomposer' Depending Eo
o
on the tlpe of equiprnent employed, vibrating frequencies--of =6
15-50 Fil can be used; the vibration is applied vertically, o
o
horizontally or in both directions'
d
' Compaction can be accomplished with or without the use
of a witer jet or compressed air, and with or without the o_
r8O
.s',
o
3
!60
c
E
q
940
tr
o iange aciordin{ to Thorburn (1 975)
o
o
0-
20
E
E
N 400
o
C
o
E
o
=o
-
q
o
l'
d
o
'ic
o3 zoo
o
E
_q
Equipment lprocedures
The weights used in dynamic compaction may consist of
concrete blocks, steel plates, or thick steel shells filled with
CPT cone resistance: tons/tt2 or kgr/cm2 concrete or sand, They normaily range from 6 to 35 t, but
d0 80 120 160 200 heavier weights up to 200 t have been used. They are usually
CPT-12
square or circular in plan and can be quite large i4r-,
dimensions (up to a few metres). Special, streamlined shapel*--;
have been used for dynamic compaction rmderwater. l
The drop heights usually range from 12 to 24 m (40 t-
80 ft), but heights up to 40 m (130 ft) have been used. Several
repetitions may be required and the drops are made at
points spaced several mekes apart in a grid pattern. A
typical treaknent will result in an average of 2 to 3 biows
c.
per square metre of treated area (Mitchell, 1981).
to The ground surface is usually levelled between repeti-
E-5 tions. Sometimes, the craters formed by compaction are
o CPT.4 _
[-6 filled with select granular material. To ensure uniformity
and high density in the near-surface zone. surface 'ironing'
is done by small weight drops over the entire surface of the
treated area.
Suitable soils
Dynamic compaction was developed and successfully
used for densification of loose, saturated, cohesionless soils.
Liquefaction is induced in these soils, and the densification
* CPT in sand lill prior to compaction process is similar to that of vibrocompaction. Although used
_ post_compaction CpT, trial 2, also in fine cohesive soils, its success in these soils is
single GKN vibroflot uncertain and may require special attention to the genera-
----- Post'compaction CPT, trial 3,
twin GKN vibroflots tion and dissipation of excess pore water pressures. This can
be facilitated by the formation of drainage channels in the
Fig. 5. CPT testing of vibrocompacrion, Kismayo Pon (Castelli, 199 I ) fine-grained soil, by fissuring or by the use of vertical drains.
796
On occasions, other ground improvement techniques such P elfo r m anc e su aluat ion
as stone columns are used in conjunction with dlmamic The effectiveness of dymamic compaction is usually
compacfion (Bayuk and Walker, 1994). assessed by a tesi prograrune that establishes the produc-
of loose natural
Although developed for densification tion parameters and by a monitoring programme that checks
. soils, the majority of the dynamic compaction work in the actual performance throughout the site. Among the perform-
US has recently been performed at sites of sotrid waste, mine ance indicators monitored are tamper penetraLion rate, crater
spoils and questionable or uncontrolled old fills. Another expansion, volume of ground heave, ground subsidence,
corrunon application in recent years has been for stabilia- vibration monitoring and depth of improvement. An impor-
tion of coliapsible soils which are stiff and dry in their tant concem of this method of ground improvement which
natu-ral state, but lose strength and experience significant should be monitored during construction is the impact of
settlement when they become wet (Rollins and Kim, 1994). heavy tamping on nearby facilities such as existing founda-
tions and utilities.
Design issues
The design of a dynamic compaction project involves Blasting
determination of tamper weights, grid pattems, drop heights
and depths of influence. Lukas (1995) proposed the follow- Deep compaclion by detonation of buried explosives is a
ing formula for determining the depth of influence: rapid, Iow-cost method of ground improvement. The shock
wave Benerated by the blast breaks down the ini'tial
D: n(wH)05 (1) structure of the soii and creates a liquefaction condition for a
sufficient period to enabie the soil particles to rearrange
where D is the maximum depth of influence in metres, W is themseives irr a denser packing, The advantage of this
7^.the drop weight in metric tons, H is the drop height in
_
technique is that it allows treakn6nt of isolated deposits at
l*- -netres and n is an empirical coefficient that depends on the depth without having to deal with overlying denser soils.
:e of soil. It varies between 0'3 and 0.8 (Van Impe and Also, it has a relariveiy larger sphere of influence (5-7 m)
rladhav, 1995).
than that of other densification techniques, thus requiring
In addition to the impact energy, the depth of influence is
fewer densification points.
dependent on other factors such as the soil stratification, the in the USA. Iis first
Biast densification is relatively new
degree of saturation and the method of load application. A application on a US highway project was in '1992-93 for
crane drop, for instance, is less efficient than a free drop. construction of an embankment and bridge foundations at
The presence of soft cohesive layers or peat has a damping the Mount St Heien National Volcanic Monument in Wash-
influence on the dymamic forces penetrating the soil, and ington State (Badger, 1996).
tJlus the depth of influence is reduced.
The grid spacing is related to the impact energy by the Equipment /procedures
equation
A borehole is drilled, or a pipe is installed in the ground
E. :
La- NW=HP (z)
by jetting, impact or vibration; a charge is piaced in the hole
sz at the required depth; the hole is backfilled; and the charge
is detonated. A number of charges are sometimes placed at
where Eu is the average applied energ'y over the treated different elevations in the same hole.
area, N is the number of drops, W is the drop weight, H is -A hydro-biasting technique can also be used to densify
the drop height, P is the number of passes and S is the grid coilapsibie soils. Lr this iechnique, water is pumped into the
spacing. Lukas (1995) gives typical impact energy values per soil deposit through wells for a few days, then the saturated
a--,unit volume of treated soils. These values can be mulfiplied soil is forced to collapse by detonation of small charges
(_.Uy the thickness of the treated soil to estimate the required inserted down tubes installed in a grid pattern.
-oplied energy (E") at the surface. The estimated E" value is The type and amount of explosives used are influenced
. ien used with Equation (2) to determine either the number by a number of factors reiated to operation, storage and
of drops for a specified spacing or the minimum spacing for safety (Van Impe, 1989). Typically, 15-25 g of explosives per
a particular number of drops. The grid spacing usually used cubic metre of treated soil are used, The level of densifica-
is aboui 1.5 to 2-5 times the dimension of the tamper (Lukas, tion achieved is infiuenced by the size and depth of the
19es). charges, the reiative density of the soil, and the time and
The number of drops at a grid point is limited by the sequencing of detonation. Field trials are usually used prior
depth of the inifial crater. That depth should be limited to to production blasting.
the height of the tamper plus 300 mm (1 ft). if the design
impact energy cannot be achieved by this limiting require- Suitable soils
ment, multiple passes are usually used. Saturated clean sands are best suited for densification by
' The amount of gror:nd improvement achieved is depen- . blasting. The premise of densification is that the excess pore
dent on the type of soil, the groundwater condition and the pressure must be dissipated rapidly so that the soil particles
impact energy per unit area. Mitchell (1981) reports the can assurne a more iightly packed configuration. Therefore,
, foilowing maximum ground improvement values achieved open-drained soils are the most suitable. In granular soils
for clean sand, based on evaluation of actual case histories: with finer materials that delay their internal drainage,
cone penetration resistance 180 kglcmz, standard penetra- vertical drains located equidistant from the blast holes may
tion resistance IV :45 biows, pressuremeter Iimit pressure be used to accelerate dissipation of the excess pore pressure.
_
3 MPa and pressuremeter modulus 25 MPa. Finer-grained
soils may. have maximum values less than half of these. Design issues
Within a homogeneous soil layer, the level of densification Significant ground settiement and dewatering of the soil
decreases with depth from the maximum values near the mass typically occur immediately after blasting, as well as
ground surface to the original in situ values at the maximum after a period of several weeks; the latter is called 'ageing',
depth of penetration. and is a littie-known phenomenon. Van Impe and Madhav
197
G. A. Munfakh
by the size of the charge, the depth of the charge, the relative
density of the soil, the charge distribution with depth and
the spacing and sequencing of detonation- The degree of
imptovement achieved is inversely related to ihe relative
densiry of the soil to be densified; ihe method becomes
essentially ineffective with a material of in situ relative
density of 60 or more. The achievable level of improvement
is usually determined during the field trials prior to actual
production.
P erformance eaaluation
Densification by the dynamic shear stresses generated by
biasting can be effective, if ti-re excess Pore Pressures Sener-
ated by detonation can dissipate rapidly. The initialiy high
values of these skessed induce liquefaction and increase the
possibility of readjustment of the grains' mass sfructure'
The performance evaiuation methods used include meas-
,."*".,t of pore Pressure by piezometers, of vertical and Fig. 7. Compaction grouting applications
horizontal ground movements by deep settlement indicators
arid inclinometers, and of relative density of the soil by the initial grout front. Soils which are dry of optimum can
standard penetration or cone penetration tests' The measure- be pre-wetted to assist grout take.
ments are taken before and irnmediately after detonation, as
well as after the long-term'ageing' period. Design issues
Tie design of a compaction grouting Programme involves
iocating the areas requiring compaction, defining the degree
Compaction grouting of densification needed, estimating the required grout
ln this displacement method of grouting, a stiff groui volume and selecting grouting layout and programme' The
mixture is injected in the ground to densify loose soil .compaction grouting
design is heavily dependent on experi-
'ence.
formations. The Brout generaliy does not enter the soil pores, A test programme may be needed'
but remains in I |,L-mogeneous mass 'ttrat dispiaces and
compresses tire .';-irounding soii. Compaction grouting is f quality assutance
os"d to correct differentiat settlements or to provide under- - Sluripcontrol
Quality
tests are takin routinely at the pump and at ti
--')
piruring and ground strengthening adiacent to oPen excava- end of the discharge line. Cylinders of the compaction gro\'*-/
tions or tunnelling actiVities (Fig. 7). It can be consiciered are tested if strength is a iactor. CPT or SPT tests car. :
*o6ot ui&oiEffio-*ethod than a chemical stabilization. performed at the giouted zone if access is available'
The system is also used to fill voids created by sink hole
activities.
Categony ll. Consolidation
Materials
A very stiff 'zero-siumP' mortar grout is usuaily iniected The engineering characterishics (strength, density, com-
under relatively high Pressures' The grout composition is pressibilit|, etc.) oI a soft cohesive soil improve markedly as
usualiy as follows: silty sand (with 10-30% fines), cement ihe soil consolidates under a iustained static load' Unfortu-
(sometimes with fly ash), additives (fluidifiers and accelera- nately, this improvement is accompanied by a volume
tors) and water. Coarse aggregates are sometimes used, but decrease which may result in unacceptable ground deforma-
they require larger pumps and grout lines' tions. To safeguard against that, the soil is often forced to
consolidate under loads higher than the design loads so that
*E quipment the required deformations take place prior to the installation
'The f pr o cedur es
compaction grouting equiPment includes a mixing of the ;kucture or the permanent fill. This method of ground
plant, force-feed piston pumPs, hoses and grout pipes. improvement is referred to as Preconsolidation, preloading
t omp a @ ie?sf -oi-6-uliiiirEEiE aIe d or surcharging.
under foundations or adjacent to excavations to densify the
ground and arrest potential ground and structural move-
ments. Single or staggered bulbs are created through vertical
Freloading and ventica! drains
or inclined grout PiPes. Preloading is often used to consolidate a weak compres-
The grout pipes have a minimum inside diameter of sible soil. It ls one of the most conventional and least costly
50 mm (4 in) and are flush iointed to avoid leakage. They methods of ground improvement. When the anticipated time
should be pre-wetted to avoid excessive moisture loss from for compresiion of the soil under the applied preload is
198
State of US practice: part 7
EquiPment lProcedures
'Preioading
is usuaiiy accomplished by placing surcharge
6lls to elevltions higher than those corresponding to the
design loads. The surcharge fill is often placed in stages to
safe[-uard against stability failure, with each lift placed only
after- the soil hus gained sufficient strength uncier the
previous lift to sustain the additiot-ral load
Conkolled filiing of tanks or lined poncis, and creahon of
vacuum by pumping groundrvater from beneath an imper-
vious membrane placed over the ground have aiso been
{ ,sed for preloading. Consolidation b1' eiccLro-csmosis is the
tme in manlr asPects as consolidahon under externally
applied stresses, except that the driving force for drainage is
induced intemaliy by an eiectric field Con'sciidation b1'
vacuuln, water-tabie lorvering and elecko-osmosis offer the
advantages that there are no stabiiitl problems, and iarge
volrrmes of surcharge filis are not required' On the other
hand, they are more complex in execution than ihe other
methods.
Prefabricated wick drains are often used with a preload-
ing programme. The drain strip is n'rade up of a plasiic of
Fig. 8. Wick drains installation, Jourdan Road Terminal' Port New
ariinage core, about 100 rnm (4 in) rvide, on most occasions Orleans
wrapped in a non-woven geotextile filter r'1aterial' It is
placed in the ground through a mandrel in one continuous
push. An anchor plate is placed at the tip of the drain to . the increase in the shear strength under the suPerimPosed
hold it in the ground rvhile the mandrel is r'vithdrawn' load at each stage of surcharge Placement.
The prefabricated wick drains are easy to Lnstall and fairly
inexpensive. An installation rate of 90 s for a 20 m (65 ft) The ciassical one-dimensional consolidation theory is used
drain was achiei,ed at the )ourdan Road Terminal of the Port in the anaiysis. To determine the time required for preload-
of New Orlea:rs (Fig. S). The raie of insiaiiation, however, ing, &e hme-settiement curves under both the design ioad
u.rd th" preload are plotted concurrently. The estimated total
,1--'maY be a(fected. by any obstructions or miscelianeous fill
settlement on the time-settlement curye of the design load
'.- -.Lnri may be preient below the ground surface' These
taterials, on the other hand, are quite often close to the is then proiected to the preload curve to predict the time of
surface and can be removed prior to drain installation' A preloading'which would result in the same amount of
maior advantage of wick drains over sand drains is their settlement.
flexibility and ability to sustain large soil deformations If the time required for preloading is excessive, or if the
which may otherwise shear and clog the sand drains, rate of strength gain is too slow to permit fill placement
rendering them inef fective. according to schedule, vertical drains are usually used to
After instailation of ihe drains, a 600 mm (2 ft) tHck accelerati consolidation- In this case, both radial and vertical
permeable sand blanket is piaced over the drains area' A drainage consolidation are considered in establishing the
drainage ditch is provided to carry ihe rn"ater collected in the time-settlement curve of the preload' Figure 9 illustrates
drainage blanket off site. time-settlement curves used in the design of a preloading
and wick drains programme for construction of retaining
walls at Bridge 8-538 of the I4&1 Berkley lnterchange in
Suitabte soils
The soils best suited foP improvement by preioading are
Virginia. As shown in this figure, a maximum preloading
saturated soft clays, compressible silts, organic silty clays
p"rioa of 7 months (200 days) would be required to achieve
. the estimated long-term settlement under the design load'
and peats. The vertical drains are of greatest effectiveness in
inorganic clays and silts ihat exhibit little secondary con-
with the addition of a 1'5 m (5 ft) surcharge only'
The theory of consolidation by radial and vertical drah-
solidation. (Barron, 1948)' Hansbo (1979) outlines
age is weli
"ttublithud
piocedures for the design of prefabricated wick drains' and
Design issues
gives horizontal to vertical consolidation (Cr,/C") rahios for
The design of a preloading Programme involves estabiish-
iifferent soiis. It should be noted that the drain spacing is a
i.g far more significant Parameter in the design ihan is the drain
o the time-settlement curve under the design load diameter. A t'S * ft) .".,t."-to-centre spacing in a trian-
[5
t the fime-settlement curve under the preload gular array is frequently used in wick drain design An
199
C. A. Munfakh
500
100 200 300 400 soo
Time: days
P erformance eualuation
A geotechnical instrumentation prograrnme is usually
implemented to monitor the ground deformations and the
build-up and dissipation of pore water pressures with tim€.
These measurementr can be used to schedule the stageci
placement and removal of the preload. Among the instru-
ments used are piezometers, settlement plates, inclinometers
and deep settlement indicators.
Toble 2. Mechonicolly stobilized bocknll sfstems used in the USA' buiid-up of excessive hydrostatic pressure behind the facing.
ln the interests of economy, however, on-site materiais of
lesser quality have been used with certain systems.
Reinforced eamh Steel strips Concrete panels
VSL recained eamh Steel grid Concrete panels
Plastic strips T-shaped concrete Design issucs
WebsoI reinforced
soil system panels The mechanically stabilized bacKill system is analysed for
Welded wire wall Welded wire mesh Wrapped'around both external and intemal stabiiity. For'externai stabiliry, the
wire mesh soil and the reinforcement are considered as one coherent
Reinforced soil Welded wire grid Concrete panels body. The reinforced-soil block is then analysed against
embankment sliding, overturning, bearing capacity failure and circular
Eureka reinforced soil Welded wire mesh Cast-in-place concrete shear failure using conventional stabiiity analysis methods
Hilfiker stabilized Welded wire mesh Large, smooth
for gravity-type structures. For internal stability, the maxi-
embankment concrete panels
mum tension developed in the reinforcement is calculated
Tensar geogrid system Geosynthetic grid Wrapped grid,
shotcrete, blocks
and compared to the tensional strength of the reinforcement,
Genesis HDPE geogrid Concrete modular and the bond between soil and reinforcement (Pull-out
blocks resistance).
Matrix geogrid wall Geogrid mats Wire mesh and The tension in the reinforcement is calculated assuming
geotexdle horizontal equilibrium of the correSponding soii iayer. The
USFS geotextile wall Geocextile sheet Wrapped sheets, iateral earth pressure in the reinforced soil layer is calculated
shotcrete by multiplying the vertical earth pressure by a coefficient K,
CTI wall Geosynthetic grid Timber ranging from at-rest to active depending on the degree of
-..-l"lodular block Geotexdle shees Stacked concrete
reskaint imposed on the soil by the reinforcing elements. ln
( geotextile wall blocks
systems that ailow substantial yield of the soil, such as
hanically stabilized Steel bar mats Precast concrete units
cmbankment l geotextile walls, active earth pressures may be appropriate.
Georgia stabilized Steel bar mats Concrete panels kr fully restrained systems, at-rest earth pressures usually
embankment develop at the top, but they drop to lower values as the
Miragrid system Geosynthetie grid Precast concrete units reinforcement and the soil yield. In the Reinforced Earth
Geocell wall Geosynthetic grid Cellular confinement system, for instance, K. ranges from Ko at the surface to Ko
system at a depth of 6 m (20 ft) below the surface. ln systems using
Pyramid modular Steel strips, Concrete blocks metal bar mats, K. ranges from 2.5 Ku at the surface to 1'1
block system geostriPs K" at a depth of 6 m (20 ft) below the surface (Table 3). The
Maccaferri terramesh Steel wire Rock-filled
vertical and horizontal slresses from extemai loadings
system mesh sheets wire baskets
(surcharge and point loads) are added to the earth pressures
Anchored eamh wall Steel rods Concrete panels
Tyre faced wall Geotextile sheets Stacked
in estimating the maximum tensile stresses in the reinforce-
ment.
' This mble is by no means complete. Many of the above wall designations The tensional strength (allowable tension capacity) of the
are registered trademarks.
reinforcement is equal to the allowable tensile stress of the
material forming the reinforcement, multiplied by its cross-
section. The bond between soil and reinforcement has two
components: a frictional component calculated along the
soil-reinforcement interface in the resisting zone, and a
passive resistance component calculated along the raised
{,-'
\*.. portions of the reinforcing strip, the transverse sections of
the reinforcement in a grid system or the anchor head at the
end of the reinforcing element in a multi-anchor system.
The resisting zone in the mechanically stabilized backfill
system is determined by the maximum tensile forces line
(the locus of the points of maximum tension in the reinforce-
ments). With inextensible reinforcements/ the maximum
tensile forces line can be modelled by a bilinear failure
surface which is vertical in the upper half of the reinforced-
soil zone (Fig. 13(a)). With extensible reinforcements, that
line coincides with the Coulomb or Rankine active failure
plane (Fig. 13(b)).
Fig. 12. Soil-reinforcement interaction The design and construction of mechanicaliy stabilized
bacKill systems are discussed in detail in Mitchell and Villet
(1987), British Standards institution (1.991), Wu (1994) and
r friction along the soil-reinforcement interface Elias and Christopher (1.996).
. passive soii resistance along the kansverse members of
the reinforcement, if any. Durability and long-term perforfiafice
The service life of an MSB system depends to a great
Suitable soils extent on the durability of the reinforcement and, to a lesser
Since the soil-reinforcement interaction depends to a extent, on that of the facing elements. The durability of
great extent on the friction along the soil-reinforcement metallic reinforcements is usually measured by their resis-
interface, soils with high Frictional characteristics, such as tance to corrosion. That of geosynthetics is assessed b1i the
angular sands and gravels, are preferred for use as backfill resistance to hydrolysis, oxidation and ultraviolet light
materiais. These soils are also well drained, preventing the exPosure.
201
t
o o.3H tan 6
co U - UL
rrr-rrr
t-o.3tanB
U
C
G
o
.?
c o
E
I
o
o-
a
o
.;
u
o
I
s
o (a)
c
'o Y Zone of maximum
or potential {ailure
o
o
@
@
& q{
e I
u
"t
d
o o
,c aaa
!l to
@
o
f c (b)
'E
u =6C
d,
Fig. 13. Poncential hilure surhce in MSB systems (points of maximum
.E ? tension in the reinforcement): (a) inextensible reinforcemenq (b) extensible
.L o reinforcement
o E
c
E o
tr
z
0 rJ
E
o
Soil nailing
o
aa
Used primarily for support of excavations and reinfor-'
.g
o :o ment of slopes, the concept of soil nailing is to place closely
spaced reinforcing elements in situ to increase *re shear
strength of the soil arrd to resirain its displacements during
!
o and after excavafion.
tr d.
The construction process involves tlrree repetitive stages:
(1) excavation of a iirnited depth. (2) installation of nails and
a @ drainage and (3) placing a facing' The reinforcing elements
o
€a tr
E (soil nails) are in the form of metal bars, tubes or rods. The
0
t E facing can either be built on site (shotcrete or cast-in-place
.N o
€E g
p concrete) or consist of prefabricated steel or concrete panels.
o
c
u The main advantages of soil nailing are that it allows top-
5 o
o n down excavation, and can be used in areas of limited space
q
a and low headroom. It is also price competitive with other
o methods of excavation support. The main limitations of the
E q
o
system are its intoierance to iong-term creeP, which may be
'- excessive in some soils, and the corrosion potential of the
.e metallic inclusions in aggressive environments.
E s
o ts
€
E
tr SE
!oi Equipment f procedures
o:
5 oAS
\J
The top-down excavation and support Process is accom-
-; , c , o o; E plished in 1-3 m (3-10 ft) deep incremental steps using
€
&9I3;
-
202
')
State of IJS Practice: Part
Project CLOUTERRE'
on the French National Research
*T,l,l?J'
"J::,Ti;l,i : H: ;;;;;"; ";d distributed bY FHwA (1ee3)'
: [i
in,,
p ro iec r
:-*l;,sa
: mass is dependent on the
The stabitity of u t'Jii"altoil
.a :,
and grouting' jet as their 1""g1' spacing and
::;r";:iil* ;[:|;"":-u|-l'i"i"g' drixing
'srouting or firing O"*t'rttgt temp"orarv facing
(wire capacity of the nails ^t'*"iL
it ilirrutio.t. fnctinut'on
"oi
ti't" *utt facing also affects the
"'i's' 'Le
piJt"a.':""i:',":'ll,,Jt;}r"r"iil ;;il,v :iI *;
iresh and shotc'et";
lift, and
;i"|; ilffi'#,'. i i;:'#}ff
tr::ff'jl"#ll'.ili'J*t if; :".:1"
"*".*utio" 1 i""j^,:""ili,tTilt*" ffi"., in a higher sarerv ractor Barig
"r.u,rting
and / oi the
ap piop.a te v erticar parameters that affect
;fi:f HJ ;ui
;l"i..T# "
"'is installed O::tU the perma- et at. (1992) discuss rn ietalittre
horizontal drainage ;ti;'"
-iii'-t'*utut o( performance of soil nailing the
the construction itages system involves analysing
nent facing' Fiprre ti The desiSn ot u 'o"^^uf;ing
the nail' the soil between
stability with respect to fuitt'"'"'of
soil nailing' The intemal stability of a
the nails, and their l"t"""tio'''
il;il; subiect of extensive stud-
t13?':it?fr willr-ircl soil-nailing structure 'h"over the Past h"/o decades'
is mostlv suitable ror soils {i:9"1 ies, tests, discussions
l"O'*t
sands' It is difficult to use rn ^"i
methods;il;'ri, *j1' emerged and
resistance, such as unsaturated
creep can affect d"19q:
Four main l'":
ft: ?u": method (original
clavev soils where '"*tlicl" ""d extensively used in # ;;;ih'
the advantages' of the system
o*u of
rs
and modified), th" C;;"
ti"tft"a' the French multicriteria
;.f';;;;,.tt' ;il:"ry;: method' In the first three
trre ,uitity to update
-:-"i t:ff.**S;$i method and the t*"t""'it"f assumed and the are
surfaces
iil,?:f,':,*l;;'""i"i-E*s--"r'-:'"c"1::*:1.1 .. methods, potential failure
analyses are modified to account
conventionai slope stabiliry
excavarlon
for the forces in
-i.r"'"lt" tio"*g these surfaces' The
difficult and considers kine-
kinematical upptouJ't *"re
C"T-ifJ jffi,,, interaction invorves two
tundamental me-
and (2) matically admissible
of failure in a iimit
doPi;"it^111des
ftittl;" "ft1n" 'oit-ttuil'interface $uran et al'' 7990)'
-nanisms: (1) tigid nails' The soil ""r#;;;;i p'"it method is the one mostlv used in
"""iutiJrt"*"work the
lateral soil otu"t"'" "i"?"i'"""rY tY friction is much and luran (1991)
United States at th"";;;;t
to'g"""t"e. i:
-i"at'? time'
-tr-t'' Elias.
deformation '"q'it"l original Davis
smaller than that to mobilize the passive earth proposed design ti-t^iit
modi{y the
may generate bending the ultimate-pull-out resistance
";il-;t;"tt *hith
pressure. fr'i' *ouiii'utiott'
only .ii a shear zone has
method, taklng rnto account
;ultiple nail'lengths' inclined
and shear in the The behaviour of soil
in the soil-nail ;;; uuot'" the cuts' etc' These charts
developed in the n"'i"O-J
*ass'' facings, ,lop"
of mechanicallv "*buJ*u:ni' soil nailing design' Figure 15
nailing has often #;;;;;J, {*.,t" and differences Dresent a simple Pt;;;;;for
stabilized Uucitfiff' il" ba'sic the modified Davis desiSn.charts'
slmilarities
tt""" been documented in a rePort [;;;;;i" "t to soii design has been
between the two
'y'i"*t Recently, u ia:t*i
""*'u"pp-t-*h eleven-step design procedure'
proposed by ruwii The role of the facing' is
which takes i"t
utto'"i-it'" 'tt'"t"tuf
detailed in BYme et al' (1996)'
Excavate
unsuPPorted cul Durabitity and long-t erm Performan ce
Parhcu-
t-2 m (3-S ft) high Durability is an important issue.with service
:-ol-1"'^''
life of more
iarlv for Permanent :';;*t"t with a
are built using steel
than 30 years' Since "t"tt t""t*res
Step 2. Drill hole lor nail iltit ;i;'"* iuti"gt' the durability of these structures
materials'
Step 1. Excavate small cul of
is impacted by the ";;;; characteristics with ,these
by providing
is dealt
Corrosion of *'" 't"5iliil;;t a sleeve aroun{--the
safiif-ggl-thitto*gg*t"t * g- ot
"trns
1ail. Corrosion-prtt#;;fu"s of clment are used in ihe
and
Steo 4. Place drainage striPs
Step 3. lnstall and grout nail ln][ri snot"rete layer and install
bearing Plates/nuts
1'75
itrr
tz
1.50
?- //) |
2
///
I *i==--
6 -t.l-_{_
Top wall
Precast panel
Aliva drain
Shotcrete Porous backfill
Concrete looting
Structural bacKitl
\* Reinforced concrete Tieback
Drain pipe
Front view
Cross-sectlonT:
Eig. 16, Element wall at Rogers pass
204 uQ-'
State of US practice: part 7
Micrapile testing
Since the micropile design depends to a Sreat extent on
intuition and experience, pile testing is almost essential to
verify the adequacy of the design and the installation
procedure. Both compression and tension tests are normally
used. Figure 18 illustrates the results of compression and
tension testing of micropiles at the Coney Island Main
Repair Fqcifity in Brooklyn, New York' The micropiles were
inslalled in a very congested space without intermption of
the shop operation (Soliman and Munfakh, 1988)-
Fig. 17. Micropile applicacions (not to scale) (Lizi' 1983)
Stone colurnns
micropiie with expanded base and the fly-ash-micropile Atthough constructed using the same equipment and
svste;. In ali of these procedures, the equiPment used is procedure as vibrocompaction, stone columns frrnction as
reinforcement rather than densification' They are appiied to
/-itati"ety small, lightweight and mobile, and capable of
\ -reration in remote areas and under low headroom' soft cohesive soils in order to (1) increase bearing capacity,
(2) reduce settlement and accelerate consolidation, (3) im-
Reinforcem e n I mech an is m prove slope stability and (4) control liquefaction. About 10-
When used as in situ reinforcement, the micropiles are 35% of the soil is replaced with stone (or sand) in the form
spaced closer than in conventional pile foundations, and the of columns.
loads are supported by a complex soil-pile structure Typical column diameters are between 0'75 and 1'0 m
analogous to reinforced concrete, where the ground repre- (2.5-3.5 ft) and the column spacings are between 2 and 3 m
sents the concrete and the micropiles correspond to the steel (7-10 f0. Munfakh (1984) describes some novel applications
reinforcement. ln order for the piies and the soil to act as a of stone columns, including one application using a combi-
unit, it is necessary to assume that the stresses are distrib- nation of stone columns and mechanically stabilized backfill
uted to both the soil and the piles, rather than the piles alone as an integtal part of a wharf structure at the ]ourdan Road
as is usually considered in conventional pile foi:ndation Terminal of the Port of New Orleans (Fig. 19).
design. To achieve this, a 'knot effect' is assumed, by which
the stress acting on the pile is partially transfeued to nearby Equipmrnt lprocedures
piles, owing to the interaction between the piles and the Stone columns are usually installed by vibro-replacement
ground generated by the high bond between them (Lizzi, (wet method) or vibro-displacement (dry method). Figure 20
1978; Plumelle, 1'984). illustrates an environmentally-sensitive bottom-feed method
of installation. Other methods (rammed columns, vibrocom-
, Suitable soils poser, dynamic replacement, etc.) have also brien used but to
,ry11 Since the micropile deveiops its capacity mainly by a lesser extent. The latest addition to the field is concreted
i stone columns. The equipment/procedures used in the
f,* "i"tio.,, is mostly suitable for soils with high frictional
it
such as ang'ular sands and gravels' construction of stone columns.are described by Munfakh ef
"aracteristics aL (7987).
Design issues
ryVhen used in a reticulated fastrion to reinforce slopes and
support excavations, the basic approach would be to
calculate the contribution offered by the piies to the
resistance of the natural soil. This approach, however, is
considered conseryative as it does not take into account the
knot effect between the soii and the piles. Once that effect is
assured, the soil-piles system behaves as a coherent body .\'-.- \\ \. //_
and is analysed as a rigid structure. \ '-..- -.1-)x-
'----J \ \.
\-\.\ -. ,-1OD
The design of an individual micropile involves determin- \\
ing both the intemal (structurat) and extemal (gror-lnd- tta
related) load-carrying capacities' The internal capacity is ---
. calculated according to conventional structural design Proce- 15 ton tension - -- \
pile ----- \,
durei. For external capacity, tlvo aPProaches are used: one \
treats the micropile as a displacement pile (Lizzi, 1980), and 8AS: 15 ton compression with - -- -l
the other treats it as a grouted soil anchor (Xanthakos ef aI',
1,ss4). 7Dl10D: 15 ton compression pile with pile cap
kr Lizzi's approach, the required pile length is calculated 1 in = 25'4 mm
using the formula 1 ton = 0.9 metric ton
205
G. A. Munfakh
o. : +3
t)
(4)
206
ice: part 1
and lower compressl- experience and are usually adjusted in the field on the basis
+^sether, resuiting in higher strength
l:::;'; time st"auilizuEor,, utt ion exchange reduces the of initial grouting Performance.
its workability' The ion The grouting configuration (layout, spacing, inclination
II# putt.ity and improves by a chemical..reaction that and depth of grout holes) is dependent on the stratigraphy
l-"Jr"!" i, tien followed
and propertiei of the ground, the grout characteristics, the
surface stabilization' the
'iri.*ut!t the shear strength'-In
*re soil and an appropriate injection parameters and the desired efficienry' In general,
lr-,"r"i.a, are mixed with ttre groui permeates through the ground under pressure,
I*o,*, of water, and then compacted using conventional
depth' the dispi'acing iater and air from the voids at a rate dictated by
.o*p".tior, equipment and procedures' When at tf,e grouna permeability- In homogeneous, - isotroPic, uni-
J-r"ti.rft a.e appiitd by injection' or by deep mixing
treatrnent-methods will be (ornisoils, a spherical flow of grout takes place' Normally,
i",tt.at. Otiy U,t" ae"p chemical
following' however, the ground is non-uniform and the penekation
discrrrsed in tiris paper. They include the
depth is affected by stratigraphy. Detailed discussions on
groutlng Pattems and grout penetration are included in
Xanthakos et aI. (1994) and AFTES (1991)'
Permeation grouting
(silicates'
In ihis method, cement, lime or chemical grouts P erformance eualuation
etc.) fi1I the voids in the soil, resulting essentially
in
fhe drilling and grouting parameters should be carefully
ir,.i"ur"a strength and cohesion and reduced permeability' monitored during any test Prograrnme and production
Utf, .ro chang:e in volume or structure of the original works. The monitoring should include grout volume and
sround. Neat cement, clay/bentonite/cement' sodium silj- composition, injection Pressure and time, piezometric varia-
[ate, calcium ch]oride and others are used in permeation tions, ground heave, and grout interconnections' Both in silu
-*srouting.
-
Organic compounds or resins are also used for and hloratory testing are performed to verify the strength,
"apnli"cations.
ir\' r.cial Microfine cement grout is the iatest permeabiliry and other engineering characteristics of the
lition io p".*"ution grouting' Grout additives may be grouted ground. Special types of monitoring, such as colour-
used to enhance penetrability and strength and to control Lg the grout or aPPlying chemical indicators to the ground,
setting time. .ui b" to trace the location of the grout within the
Perineation grouting is mainly used in construction o{ ground."tttptoyed
tunnels and dams, in s-trengthening of natural slopes' and
in
special applications such as treatment of swelling clays' The
prop"tties the treated ground, particularly its void space' Jet grouting
i url tnu "f
major influence on the selection of appropriate This technique uses high-pressure fluids, appiied through
grouting materials and procedures' a nozzfe at the base of a drill pipe, to erode the soil particles
and mix them with cement Srout as the drill bit is rotated
Equipment lProcedures and withdrawn, forming hard, impervious columns' Excess
'Permeation grouting is performed by driJling holes in-the
soil cuttings are carried to the surface in the form of a waste
ground and inj-ection of .ttt.ry grouts' The drilling procedure slurry. The grouted columns can be formed vertically,
iarive drilling, extemal flush, rotary duplex, percussion' horizontally or at an angle. A row of overlapping columns
double head,- etc') is heavily dependent on t\e type of forms a wali. Jet grouting has been successfully applied to
ground. Grout iniection is performea through the'end of the nurnerous proiects in Japan and Europe and recently in the
fasir,g o. tluough specialized equipment- such as a valve USA for underpinning, tururelling and groundwater cut-off'
"system
tube ortr fiU, a Manchette' Details of drilling and Figure 22 shows jet grouting applied fsr constructiol of an
are discussed in Xanthakos et al' (1994)' excavation suPPort system at the 63rd Street Tunnel Connec-
--injection
( tion Project in New York CitY.
\''quitable ground The main advantage of jet grouting is that it works in all
'C"*"rit grouting is usually used in fissured roSks and types of soii since the initial soil shucture is broken down
.ourru-gr"ili"d soili (less than 15% fines)' Chemical grouts and replaced with a composite mass of soil and grout,
(silicatei, etc.) can be used with finer soils' sometimes called 'soilcrete'. Also, the iet grouting operation
can be directed from a rernote point and can be terminated
Design issues at any elevation, thus providing keafinent in isolated zones'
aesign of a permeation grouting Prograrnme involves The main limitations of the system are that the construction
ftie
seiecting ** tlp" of grout, grout mix properties'
iniection process may result in heave or excess lateral gtound move-
configuration' ments, and the ultra-high pressure used may fracfure
Parameters and grouting
The type of grout used and the make-up of the grout mix surrounding ground or force the grout into adjacent vaults,
are dependeni on the properties of the grqund' When sumps or blJements. In soils containing peat or high-level
grouting rock masses, botlt t}te overall permeability of the otgurric material, the humic acid in the soil may delay or
,'o.k mis" and that of the fusures in the rock affect perform- prevent the hardening of the soil-grout rnix.
- ance (cement grouts usually Penetrate fissures of width at
least three timis the largesi particle size in the grout mix)' Equipmmt
'There lprocedures
For granular soils, the principal parameter affecting Perrnea- are basically three systems of jet groutingl the
tion is the size of the intergranular voids, usually repre- single-fluid system, the double-fluid system and the triple-
sented by the soil's coefficient of permeability' fluid system. In the first system, the fluid is the grout and
The iniection Parameters (volume, Pressure and rate of the jet simultaneously erodes and binds the soil particles' In
injection) are alio dependent on the soil porosity' lt. is the double-fluid system, a second fluid is used in addition to
important to note thai the Pressure and rate of iniection the grout to enhance the cutting abilify of the system' The
should be kept below limiting values to avoid hydrofracture .".ottd fluid can be either compressed air or water' In the
of the ground or disturbance to adiacent structures or triple-fluid system, both air and water are used' The central
utilities. The injection Parameters are greatly dependent on coie of the diilling rod and monitor conveys the grout while
G. A. Munfakh
Design issues
The design of a jet-grouted column involves the deiermi-
nation of the column diameter, slrength and permeability
that wouid satisfy the project's requirements. These factors
are, in tum, inl']uenced by a number of interdependent
variables reiated to in situ conditions, materials used and
operating parameters. Although ihe Soil type is less impor_
tant in jet grouting than it is in permeation grouting, the
characteristicsof the ir sifr material are still importint as
they affect the strength and permeability of the jet-grouted
coiumn. Miki and Nakanishi (19M) published empiricaily
derived data relaling the jet-grouted column diameter to the
SPT value of the grouted soil.
Both the strength and the permeabitity of the grouted
mass are influenced by the cement content in the grout mix.
Plo-ts reiating strength to cement content are preiented by
Caliavresi (1992). These plots can be used rn the design of
the grout mix.
The diameter of the constructed coiumn is a function of a
number of operaling parameters such as injeciion pressure,
grout flow, and rod wiihdrawal and rotation rates. For a
given soil fype, the slower the withdrawal and rotation rates-" .,
Equipment lprocedures
'Hollow-stem
multiple augers equipped with mixing pad-
dles penekate the gtound to the required depth' During
penetration and withdrawal, cement grout is pumped
ihrough the auger stem. The auger flights and mixing
paddles mix the soil and the grout in place to fgrm
iontinuous, overiapping soil-cement columns. If needed,
steel reinforcement is inserted in the colurnn to provide
bending resistance (Fig. 2a)' Fig. 25. DSM for liquefaction control flaki and Yang, I 99 I )
A typical DSM consLruction system consists of a mixing
plant ind a drillinglmixing unit. A separate pump supplies
the grout from the mixing plant to each of the injecting soil types. For all pracLical purposes, one-third of the
urrgeis. A computer is used for controi of mixing and grout unconlined compressive strength of the soil-cement can be
flow, considered as its shear strength.
/--'" 4 series of multi-shaft eiements, each of which consists of For a well mixed soil-cement, the coefficient of per-
\- " -ee or more overlapped coiumns, is constructed in a series meability ranges from 10-s to 10-7 cm/s. ln general, the
-^ in a stepped sequence. ln extremely dense soils, holes are permeability decreases with increasing cement ratio in the
predrilled to loosen up the ground along the DSM alignment mix. These permeabilities, however, are those of the soil-
using a powerfui single-shaft auger. AI1 obstructions in the .cement mix and do not necessarily represent the in situ
soil are removed, if possible, and replaced with good-quality permeabiliry of the DSM wall. That permeability would be
filI prior to DSM instaliation. dependent on the tightness of the wall, the overlapping of
the columns and the potential presence of 'window' caused
Design issues by boulders or other anomalies. The actual wall permeability
The DSM design is influenced to a certain extent by the can best be determined by performtng in situ permeabiliry
plarmed function of the system- lAlhen building a cut-off tests.
wail, for instance, the soil-cement is considered a Porous
material from a microscopic viewpoint, and the wall is Quality controlf quality assurance (QC/QA)
designed to provide a required impermeability. A DSM wall The success of a DSM application depends to a great
used for excavation supPort usually has reinforcing mem- extent on the QC/QA procedures implemented- Basically,
bers designed to resist bending moments and shear stress two materials are tested: the cement grout and the soil-
along the longitudinal direction of the wall, and the soil- cement product.
cement between the reinforcement is designed to resist and Unconfined comprebsive strength and permeability tests
redistribute the horizontal sbress to neighbouring reinforcing are normally performed. Three tlpes of samples are tested:
members. When used for liquefaction control, the DSM is (1 ) laboratory-mixeci soil-cement-water specimens, (2) field
r.-=performed in a block or lattice Pattern to resist the stress wet samples extracted from the DSM column at different
(;j"* embankment or surcharge loadings when loose co- depths immediateiy after instaliation and (3) core samples
' sionless soils liquefy during seismic ground shaking obtained after the column has hardened.
1. rg. 25). Field monitoring of the installation process is an integral
The strength, permeability and modulus of elasticity of part of the QC/QA programme. The operation parameters
the soil-cement are the primary engineering properties of monitored in the field include the driliing time for each
concem for the DSM design. These properties are affected panel and the grout injection rate. The iniection rate is
by the soil rype, the composition of the mixing agent adjusted constantly to accommodate varying driiiing speeds
(cement and additives), the degree of mixing and compac- in different soii strata so that the design voiume of grout per
'tion, the curing environment and the age. unit volume of soil is maintained.
Taki and Yang (1991) present correlations between the 28-
day unconfined compressive strength and the cement con-
tent for both granuiar and cohesive soils. The 28-day Lime columns
strength is approximately harice the 7-day strength for both This method is a variaLion of deep soil mixing, in which
unslaked quicklime is used in lieu of, or mixed with, the
cement. Used extensively in Scandinavia and the Far East,
and introduced recently in the US, this ground improvement
method is mostly suitable for stabiiization of deep, soft,
sensitive clay deposits. A pozzolanic reaction takes place
Reinforcing member between the lime and the ciay minerals resulting in substan-
tial increase in the strength and reduction in the plasticity of
the native material. The heat generated by hydration also
reduces the water content of the clayey soils, resultin5i in
accelerated consolidation and strength gain- Lime columns
can be used for load support, stabilization of natural and cut
Fig. 24. Steel reinforcement in DSM columns slopes, and as an excavation support system.
209
G. A. Munfalch
Equipment lprocedures (a) water content reduction due to the heat generated by
The original lime columns were constructed by mixing the
slaking and hydration of the quicklime
soil at depth with quicklirne using a tool shapeci Iike a (b) lateral consolidation of surounding soii due to expan-
fiant
dough mixer (Fig. 26). The mixing tool penetrates the grJund
sion of the column as slaking takes place
to the required depth, then is slowly withdrawn as the lime is (c) acceleration of consolidatiJn due to the increase in
forced into the soil by compresied air via holes iocated perrneability generated by the flocculated nature of the
immediately above the blades of the mixing tool. As the tool is .
lime-treated soil
withdrawn, the inclined blades compact the soil_lime mix_ (d)
ture,_resulting in columns of 0.5-0.6 m (1.65_2 ft) in diameter,
increase in shength and density due to the pozzolanic
reaction between the lime and the silica and itu*ir,u ir.,
whi$ is approximately the diameter of the mixing tool. Ir:r the clay mineral, which binds the soil particles together
another method of installation, unslaked lime is pliced and (e) pore pressure reduction in the surrounding soil*due to
c-ompacted in pre-.driiled holes. Lime columns of 1 m (3.3 ft)
in the net flow of water from the soil voids towards the
diameter have been installed in Japan using this technique.
Iime column due to the slaking reaction in the column
A uniform mixing of the soil and the itabilizing agent is which, in tum, increases the shear strength of the
essential. This is done by sp"rchronizing the rate of fleaing
surrounding soil.
to that of rotation of the mixing tool_ A iecorder registers th!
1*oyrt of lime injected per metre of coiumn. The operator The shear strength of the soil increases several_fold with
checks this recorder constantly and adjusts the rates and
the addition of lime. The ultimate strength of the column,
quantifies accordingly. Compressed air is used to transport
however, is influenced by the ,nuu. ,#".,gth of the sur_
the lime from the metering unit to the mixing tool, and then
rounding soil. Failure of the surrounding soii would reduce
into the soil. the confining piessure, which, in turn," reduces the shear _-
strength of the lime column. The long_term strength ')
Suitable soiis of the
coiumn can also be reduced owin! to creep (ZO-35"r.
Lime columns are used to stabfize cohesive soils. For reduction).
inorganic soils with iow to medium piasticity, the iime
The permeability of the column is usually hugher than
cor.rt:lt used-is_usually 6-8% of the dry ui.lt weight of the . that
of the native soil. ehanges in the coefficient olpermeabiirty
stabilized soil. Lr highly plastic soils, more iime is added.
of one to two decimal exponents are possible with the
Gypsum is sometimes mixed with unslaked lirne to stabilize addition of lime. This permeability, however, is still on
soils with high water content. In low_reactive clays, the
:rganlc lower side (generally, k:19-o to i0*7 cm/s).
fly ash or kiln dust may be added to er*rance the soil_lime
pozzolariic reaction. Lime-cement mixes of equai propor_
Durability and long-term perfonnance
tions are used when higher skength is required.
.Although the strength of the lime_treated soil increases
with time until a certain age, the longterm behaviour of the
Design issues
lime column structure is influenced Ly weathering, particu_
- Ynslaled quicklime stabilizes soils through one or more larly if the structure is continuously exposed to weithering
of the following mechanisms:
elements such as water, wind or temperature. Test results
on
the subject show that the lime-keated soiis absorb
less water
with time than do untreated soils - they also dry faster.
lo:rtrary to cement stabilization, tne frost f,Jr,r" *-ti*"_
stabilized soils is more than that in untreated soils, particu_
larly if the soils are frozen within one month after ctmpac_
tion. The resistance against frost-thaw effects, ho*.rer.il.,
Unslaked lime
incl-e-1ses- rapidly with curing time as the strength of tt"*J
siabilized soil is increased. Giinerally, .fte depth Ind
spee
of frost penetration are reduced wiitr the ujdido., of lime
b.ecause the larger void ratio, generated by flocculation,
allows less heat conduction throufh the soil.
Rotary table
Quality assurance f quality control
Quality assurance of lime column construction is usually
accomplished in two main stages: during construction
ani
after completion. During instafiadon, the"depth of penetra_
tion.and quantities of admixtures and water
iwhen slurry is
used) are recorded for every column. The quality 'the
of
completed column can be tested in situ by static
cone
penetration or standard penetration tests. A modified
pene_
Maximum 15 m was developed in Sweden for the specific prr.por"
Injection of ":,*:r:.
of testing lime columns. About 3% of the .o*pl"t"d
columns
l.urt" projects, the bearing capaciry of rhe
i:," ju*ud 3their creep
timits are usuaily itreclea in situ by
Soft clay :?l:T:
plate loadf"d
or screw plate tests.
4r.!
.,uiua sites. Following are brief detaiis on both methods' N2 lo
atmosph€re
Ground heating
Lr this method, a bumer is placed in a plug at the top of a
sealed borehole. Compressed air and fuel are iniected under
pressure, and the temPerarure and comb.ustion products are
controlled. Several boreholes are usually connected to a
o-central apparatus and fired simultaneously' Ao altemative
(. nethod ,.rse, electric heaters rather than combustion' The ICc' ]
:ctric heaters can be either piaced at the top of ihe
borehole or inserted in ihe borehole' Eight to ten days are
usually needed to treat a soil column with a diameter of
1'5-2'5 m (5-8 ft) to a depth of B-10 m (26-33 ft)'
Design issues Fig.27. Ground freezing medrods (Donohoe' 1993): (a) circulatory brine
Hfat flow analyses can be done irl the same general way cooling; (b) expendable refrigerant
Ground freezing
:' Ground freezing has two main functions: (1) to prevent Ego
qroundwater t"epig" into excavations and (2) to increase 0
Design issues binding agent that gives sirength to the frozen ground' The
Mirked increases in the soil's strength occur upon freez- .o*p.Jrril,r" streng"ths of both the ice itself and the soil
ing. Fig. 28 shows unconfined compressive strengths of containing ice increase as the temperature is lowered further
frozen ground in relation to temPerature' The ice acts as a beiow the freezing Point.
211
G. A. Munfakh
Soil-vegetation interaction
In the brush layering system of biotechnical reinforce_ Ground improvement in
ment, the soil and the rregetation interact in three
follows.
ways as environmental ensineerino
o Friction is developed along the interface
between the soil applications, ground improvement techniques are
and the live stems and brushes, in a manner similar also used
to to deal with environmental challengu, ,.r.i as groundwater
212
and containment of solid
References
nrotection and the safe disPosal (1988)'Three examples of
wastes' sorne of the environmental
aPPlica-
AeRAi,{soN L. W' and HaNsnarxr W H' on Casc
5nJ r,rru.a"us innovative retainmg *uii
6ons include
'o"ttt"tti?i ?"-O
Ensinecing' st lttuis' Missourt'
^Y!.:^.'!,nt''
to
;;;;;;l; C'ii'ni'ot oi g-o'ting for underground
t^t^:f::':^compaction) AFTES (1991) n".o**"nJutl%ns 6' No' 4'
(a) densification- (surface' .vibro: works. Trlrnei i,g onai'i"'ground"space Technology'
Iandfill capacity and conskuct caps
iror"u."
i; mit'lmi'" tu*tu settlements and avoid densifies volcanic debris Ciuil Engineer-
(b) ;;;;; u^rlliint. (1996) Blasting
York, Mar'' 8A-12A'
hrr^. Neu
";;;il; of soil
(c) 3[H3:"::t#J to remove
contaminants' inject remedia- u^*:''d., n i'' "'a s"u" c' K' (1ee2) -Analvsis
s' iy*p' o''' Earth Reinforcemml Pructicc'
io. ,uug".,tt an{ create flow barriersfor in situ treatnnent nailins svstem Proc'-I'nt'
Kvusliu iniaersity, I ukuokn' I
apan'
(d) ;; ;;;;"*r"g or deep.-soil
mixing construction of
'and".r"utio-n of cut-off walls Baxx#ere R. D' and B^;;ri''C (tsss)
-pes'3" 'a'nd
-83 / 026' Federal
-^..!^'--
^r contam- v"i'
r'"n"p"tt ricl' fffW4Tno
oJ stone columns,
(e) ;; freezing for temporary c?ntalnm:nt
Y -' r r---:6^ ,*^oi"-.^hl"
flffi:ffi3i"itt't*'p.I*'"ir' uu"l"" by ice crvstals
barriers bv crystals
o^#i;;; ii"n. "'J-ct'""-"u* us' n'"'q' (1984) Settlement perform-
ln-iitu Sioil and Rock Reinforce'
in the soil voids ance of sto.," toi'''mtt"sIii"
construction of iiners and barriers' Con1"'n'c' Paris' pp 105-110 r. -
1/; ;J;th";;J;t ^-*t R. A. (1948) Con'solidation of fine
BanxoN -^i^^. soils by drain
grained
which are used strictiy walls' T r ans' ASCE' 178' 7"18-7 il'
Other ground treatment methods' D1'namic compaction: two
D' (1994)'techniques'
control' include Bevux A. a. und Warxrn A' ln'situ deE soil
fo. case histories utiiizing'it'"ouu'iuu
".tri.Jn*ental Publication No' 45' American
volatile and semi-
(a) hot air/steam iniection to remove
improuement,Ctot"tr'"ituiSpecjal
So'.i"ty of Civil Engineers' oo'
55-67 '
code of practice for
volatiie contaminants
and immobilize contamr- Bnrrrsn Sr.tNoanps *ttt"ttJ"i "'^olt' tr991) .BS 8006' British Standards
1) i, -.it, ,it ifitation to melt soil strertgthenedf reinlo"') ind other flls'
nants. Institution, London'
Ground improaement (ed' M' P'
Bnor.as B. (1993) Lime stabilization' ln
"^'" Professional' Giasgow'
Someofthesetechniques,however,arestillinthe nitr.f"ii 6lackie Academic and
Bvxr.rr F. J-, Corron ;:-'ij;;*"rn J''.worccxrac C' and
develoPment stage' iry conskuction
Uenracxrt c (19;; Mant'al fo-r {e. ^andFederal High-
moniioring or t'lir *"rit Erwa-SA-'6-069'
"ol Washington' DC'
*u, ea*ittltu'ation' of underwater ill' f
.^#:1, t:i]ffiiinil';*v-dZup'o^pu'tion design'
SumrnarY In ASTM STP i08; 6eep loundaiion .improaements:
Sociery for Testing and
construction t,.iiir.g' 'd*"tlt'n
Ground improvement is the fastest-deveiTlg:.^1111 "a
Materials, PP' ?79 -79 6'
G' A' (1983) Ground
,1i""
highlY comPetihve imaginative field of geotechni- Cesrnru R- i', Sanren il'r' u"a MuNrnxu
""J-*"" of a wharf structure'
=.^iif; ti i'
:.i^;'l#'.*e reatment in the design and construction
tt'" geotechnical :iclT:^'.,::::"'fl Thomas
in pitin-{ ola grotund treatment lor fouadatians'
f :.i:ffi il;;;'ild'rnground-t*p:l-"-",1-"li:,,11 \n Aduances
Telford' London'
*1 .T:.J :'':"i';,,::::';
i'd:H' t;::;'*1I^iEs?"""d l" state'
;'."J;ir;r".*g- "atural*h:, *:::'ij:-::::t# *':;;;;'
DrPaon -,h; C' and
B., S:rnr-a Peurr-r Crrt'o A' (1991) A monitoring
assessment of iet groutins Process
;- lualiw
[T,\;" ?"1:';i.'; *":: r:i,11::1i1i':::'1:"*:
. throush an energy up/'o"ttt' t"ot '
4th Int' Cont'' on Piling and
..:'-},
i. .,1
'',!..!/
21,4
if ound lriProz:emmt {tS9D }, zlW.
are
of the foundation
weicome in environmentally sensiti"u soils (Munfakh, 1984).
land. Methods that ailow construction
u;;u;-r;"h as park_ Surface compaction by heavy vibratory
of embankments with rollers, dynamic
vertical faces (mechanicaiiy srabilized prelo.ading with borrow fill and vibrocompac-
at or near wetland.
b;.Glt';.e preferred llTYlllli:
*:i:, amon8 the. ground improvement methods
:11
Ereu.
consid_
The. durabilify of the materials
used in ground improve_ . vtorocompaction was selected on the basis of
a strong governing factor, particularly considerations of ground conditions, construction
l"na 3.is exposed
ground where the nons, srte constraints and cost-
condi_
to heavy weathering elements. The
use of Vibrocompaction was performed using
metal reinforcements, for instance,
fI ,r"u. undqr
two to six probes
currents or in highly corosive ""Ua"a
soils. When "r.uy
geosymthetics
are 1acl.r
required.relative
footing, aepTaing o., itr'rir" (Fig. 1).
The
require protecrion from the "uff".*, density of g0yo was monitored Ui perform_
Iff1,^ll:y
cnemrrals and_ exposure to ultraviolet of heat, tng cone penetration tests before and after
light. The effects of compaction.
wet-dry and freeze_thalcyeles ,r" revealed the p..r".ce oi-r- rort compres_
pu.i."furly important _1*::^::^:*ings
srole layer of cohesive material 1.5_3.0 m (5_10
in chemical stabilization. Extreme
*..itfr". .."aidons did not respond to vibrocompaction. fo ft) thick that
as dry heat or ice may nu,o" au*ugi"g'.;r"qu"ncessuch aeaf with this
biotechnical stabilization. on material, it was decided to support the
loads on stone
Contractual requirements play columns (soil reinforcement) rather than
- a rore in the selecrion the soil, particularly since ttre ,urr,"
attempt to densify
usea in the
i::i:i1li National
contractor.
;.,slT
^=;n: politics, traderil",:TlP,,* ;*,Tii;
p,rocess. Vibro-replacement stone "qrip*eniis
columns rvere economic_
ally installed under the footings. Actual settlements
birriers and,poiitical influ- footings instalied over the sbnJcolumn,
of the
ences sometirnes affect the selection,
as cloes tidition. Some_
*"r" .,.gfigiUlu.
Another successful densification project *"" ut Kismayo
216
IJS practice: Part 2
q
q E
tooting footing
footing
I
I
eon*-J-
mtil +-'t--4
E0'75 m
ro
o! I i I O
$-ffi
-i
E\
6- Pile caP
15'2 m /
I- Elevation F4'2 m (+13 8lt)
Slope 1% V- Concrele Pavement / (7 MHWS
\7 MHWS
=
1 llll ilrt
l* Existing surface
/ I Sheet Pile bulkhead
E*itting 7'
rock /
I J+- *J,,^)rirter raver
\
[..-il \
dike
-
'uno'"'
\__---
l.'
-L--z
I
L Excavation and backtill
of soft silt and clay
in vicinitY of berlhs 2 and
3
34 m wharf
Sott clay
Loos6 sand
218
expensive and required
surcharge retaining strucYes were more
'-ropotreintorced
ToD of
of bridge deck andint='t*i."j..:"^:*J:
'l:;.in'o*"" fffJ."il: ;j ffift 'r,"- (Fiq' n.;T:h yf Ty*
removal the
",;,!ii{ HllT::3,1'#ll?
YxTff"Hl"**,t::$T:i1"""::"'ff;-construction ."ti.rlu. sir"" u''uiro*ental
'l*'ling
structure'
restrictions precluded
increases.-To allow cohesive material could not
be re-
accommodate traffic volume
trrffi. or, th" tridge deck P;;g*g' "i;J";;;;;,e,,,,ing
and the
to the potential
of the new lane while maintaining from *itrri" ttr" cetls owing
ieihod was serected, using *;;-;"#;ry
above, a top_down;;;k;" earth
soil nailing fo' "x'uuutio" suPPort'
co"""tio"ul '*:ld'.t"ffi::il ;:ni**Z'T*:1'#tf::i: ffi:?
-_)
; ;" #, d; ;Til::il:.#.LT..il:,
*x,::,;;
oetow the groundwate #
*.m.:,m.{tr1}':'t't"#i'",#'ff T'".ffit"i
dritu iluned;;,;; ;""1"""*truction callgd f67 ,
;illi
and usine nir ,,-i^*:-* ttu "*oti.; il:X'f":"::
support the eisting o -- lvrrr'rqur concrete walls tha
st --'*' *tute protecting
proteching the
openings.
operungs. conhoi;
Frg. 8. Celfular containment
To conrroi
*",.,.i"," ".# ;:"J,fj.H-":::Y: ,while minec
mineo
*.u ui ti o,,,,r,,,,1
i::1" :,i::p,
u
saruc&re for dredged
material disposal hcility
[1H ffi:#l"Ji:fl
keyed into .*k;;;t;.:],:
cr';r
:"n : $,.i
ulrp€rlrleable
;:'ilX':h:l;:]
srde of the box srru*'re,
[o move. The stone al'
under
. .it"
al. owing to
uno er existing
"""tj,T
.ii"..."I:,::iv TP"::eable
.o.r"ti".' Lquscu glaciat
slacial
by lnadeouate
Dy inad"equa
till *ut"ril
uu materi-
evatuadng Jiir.r"ii=rf?iumns scheme was selected existin* ufuvuie;:"o
ro.1*rl1:1Lt:d te headroom
after stu*y
sturry walr
wall .";,"o".il,i
"1.,r, ubor" the site, the
corisrrucro- *,?il,
,^:"1Tt: Tu"f .
Efr,:t::".H:tl;'T;
"fl:J H #""'.:r**i_i;.ff1'H:#E?Ffi
l:l
u,,a.o*t.,.i;;fiL..J*11y$f""if
fl:
n"*."";,;:;J;i
ehen rica! stabilization
projects
_ The hvin 5.5 m (18 f tururels
Market Secrion * urrntllili*r of the Lexingron
compressecj air 'Io.Iu Yuho were driv
rrned B&o railroad ;;;'" fi:::-"]ffi"f
shield
*"T-l'hof:'
l:rm*: ;fh,#:,+ t,l:["#:ff til,r.[,,fj
:tace conditions at
Steel Grout
ihe intersection liner pipes
s"ur"t---fioft
Fig. 9. Stone column layout
inside a cellular sructure
0 1 Z 3m
a1n Fig. I0. Chemical grouting
for protection of
the B&O Railroad runnel