Task 2
Implement program governance
BSBPMG622
◻ I declare that this task and any attached document related to the task is all my own work and I have not
cheated or plagiarised the work or colluded with any other student(s)
◻ I understand that if I am found to have plagiarised, cheated or colluded, action will be taken against me ac-
cording to the process explained to me
◻ I have correctly referenced all resources and reference texts throughout these assessment tasks.
◻ I have read and understood the assessment requirements for this unit
Unit Title
Unit Code
Student ID 39434
number
Task Number 2
Student Name:
Assessor Name:
Assessor Signature:
Date:
Table of Content
Procedures
1. Review the assessment scenario, the business documentation, including policies and proce-
dures and the templates provided:
o Templates:
▪ 1 – Program Governance Support Plan in Task 2. 1
▪ 2 - Email in Task 2.2
3. Discuss and negotiate approval for the governance support plan with the Program Board
played by a group of classmates in simulated work conditions (Role-Play).
4. Record the feedback received and apply changes to the governance support plan as re-
quired.
The trainer and assessor will check that the feedback is applied to the plan.
Develop a program governance plan to facilitate decision making, establish effective systems and
methods, ensure program compliance, identify and plan for program support services.
A planning template is provided (Template 1), follow the instructions and complete all parts.
· Outline the process that was followed to develop the program governance model
(40-80 words)
· Develop the program governance structure/model for the program (chart) and document it in the space provided below.
Project governance is a framework that includes guidelines, processes, decision models, and
project execution tools. Each organisation should adjust this general framework in accordance
with its existing policies and governance models. The project is carried out within the organi-
sation and must be consistent with the decision-making method and the business culture of
the project.
The project manager and team must review the project governance framework throughout
the life cycle and, at times, must adjust the model based on environment, evolution, and ex-
perience.
ment.
Communication plan
Develop a communication plan to communicate the governance structure, roles responsibilities, authorities, the decision-making process,
and updates to all stakeholders. Include the following:
o Stakeholders
o Purpose of the communication
o Methods and frequency of communication
o Communication content
(6 communication needs)
Program personnel
Address the following:
o Outline how roles, responsibilities and authorities for the program were identified and allocated (30-50 words)
o Develop a program personnel matrix (10 roles) to document decisions and accountability relevant to the program objectives using
the table provided (include key decision-making roles).
o Outline how the program personnel matrix will be made available to all relevant stakeholders. Specify what stakeholders. (30-50
words)
Example: Mark White Example: HR Dept Example: HR Manager Example: HR manage- Example: Decision on
ment for the program. recruitment and selec-
tion planning and de-
livery; guidance with
HR disputes
Felipe Event planner project manager Staff social ac- Responsible for
tivities providing em-
ployee appreci-
ation activities
within the orga-
nization.
Planning and coordination define the day-to-day development of the project and its gover -
nance. Although all his tasks lead him to one goal: to achieve the agreed conditions, his tasks
are many. To do this, you should pay attention to the following points:
• Identify risks, assess risks and mitigate them if they cannot be avoided.
Clarify the organization's value proposition. The value proposition is the driving force behind
the organization.
(40-80 words)
Resources may include human resources, services, physical resources and information systems.
(30-50 words)
Aurnia O'Sullivan CEO of the project was asked for the following resources for the develop-
ment of the project:
Physical resources:
Meeting office.
Computer equipment.
software.
Qualified human resources for the development of its activities provided with training.
Asset Register
Complete an asset register to record office space and equipment needed by the project (add additional rows if needed).
*If the system has been purchased for the program, indicate when it will be implemented.
o If the system has been developed specifically for the program or if it is an existing organisational system or process
o The departments/projects that will be utilising the system/process
o The use of the system/process in the program
o The reason why the system/process is important for the program and how it aligns with program objectives
Example: Review Example: Y Example: Fi- Example: Moni- Example: keeps the
of financial state- nance Depart- tor financial ex- program within fi-
ments and in- ment; Program penses; adher- nancial constraints,
voices Team ence to budget signal issues (vari-
and variations; ances in expenses)
alignment with
financial author-
ity as stipulated
in the gover-
nance model
Program Audit
Identify the following:
· Four (4) audit activities that will be performed in the program (internal and external)
Audit documentation:
The information will be compiled in reports.also by email when some change it is made for
faster deliver.
Program Policies
The Program Management Office establishes process efficiency and supports it with suitable program policy.
o Identify and list what organisational policies will be used in the program. (4)
o Identify what program specific policies need to be created and why. (2)
Organisational policies:
Inspections must be made more often to keep the audit more precise and organised
Improve and train personnel knowledge with skills required in the project
The achievement of goals is the main Policy ,with this one all the important aspect has been
take into consideration to hit the target .
Develop a high-level draft of a program-specific policy for your program. Attach it to your submission in a separate file or copy and paste in
the space provided below.
Suggested format:
▪ Policy Title
▪ Purpose of the policy (briefly describe purpose and scope of the policy)
▪ Policy (summarise the content of the policy including relevant procedures -step by step)
To review and evaluate the planned process and procedures, we have adopted a policy of continu-
ous improvement, which will help to fine-tune our working methods to make them as effective and
efficient as possible.
o Identify and describe both organisational and external compliance requirements relevant to the program (5)
Compliance Re- Internal (I) Reporting Re- Data collection re- Strategies to rectify
quirement quirements quirements non-compliance
External (E)
Example: Example: I,E Example: Yearly inter- Example: Trainer and Example: External and in-
nal audit and external Assessor’s: ternal training
Trainer and assessor audit from ASQA
requirements · Qualification Improve recruitment prac-
· Evidence of indus- tices
try Currency
· Evidence of Pro-
fessional Develop-
ment
· Current resume
· Trainer’s matrix
· Risk Response Plan: Several options and actions are formulated to increase opportuni-
ties and reduce threats to project objectives.
· Risk management plan: in which it is decided how to proceed, plan and implement the
project's risk management activities.
· Risk identification: it is possible to determine which risks may affect the project and
record their characteristics.
Project Manager. · Organized and efficient in plan- · Develop the project plan.
ning. · Set priorities.
· A leader. · To coordinate.
· A team leader.
· Motivator
· A good negotiator.
(50-100 words)
· The training will provide new skills and knowledge on how to improve customer ser-
vice before, during and after sales.
· Training will be provided when all project teams are complete and need consultation.
Knowledge Management
Develop a program knowledge management strategy. Address the following:
(50-100 words)
In the meeting schedule, the project manager should meet with all the project managers to
update the information and plan the performance, and one minute of the meeting is to hear
the opinions of the project manager and this is necessary for your project .
Task 2.2 Present, discuss and negotiate the governance support plan for approval
Schedule a time with the trainer and assessor in week 4 of class and present, discuss and negotiate
approval for the governance support plan with the Program Board played by a group of classmates in
simulated work conditions (Role-Play).
The trainer and assessor will evaluate your performance during the meeting.
If you are absent from class, it is your responsibility to make alternative arrangements with the trainer
and assessor to perform the Role-Play.
Before the meeting
· Record the feedback received and apply changes to the governance support plan as required.
The trainer and assessor will check that the feedback is applied to the plan.
Every step of the project was accurate with goals of the company ,also the supply chain was ar-
range to be more efficient and faster.
Advise them to pay particular attention to roles and responsibilities, decision-making process and
support services.
Use Template 2 to write the email. The text of the email should be in grammatically correct Eng-
lish, written in an appropriate (polite, business-like) style.
(40-80 words)
Template 2 -Email
Dear Team.
In this Email you will find attached the governance plan in which you will find a description of the
roles , responsibilities and decision making process within the company if you have any doubt do
not hesitate asking.
Best Regards,
Andres Garcia