Sept~2023

Project Name : Triple bay Primary Infrastructure Development AMAALA SA SU M TU W TH FR SA SU M TU W TH FR SA SU M TU W TH FR SA SU M TU W TH FR


C
el Report Type : 3 Weeks look ahead (Infra)

10-Sep-23
11-Sep-23
12-Sep-23
13-Sep-23
14-Sep-23
15-Sep-23
16-Sep-23
17-Sep-23
18-Sep-23
19-Sep-23
20-Sep-23
21-Sep-23
22-Sep-23
23-Sep-23
24-Sep-23
25-Sep-23
26-Sep-23
27-Sep-23
28-Sep-23
29-Sep-23
2-Sep-23
3-Sep-23
4-Sep-23
5-Sep-23
6-Sep-23
7-Sep-23
8-Sep-23
9-Sep-23
ls Data Date : 09-Sept-2023
I5
T
hi Activity Name D
Start Finish
A
ELECTRICAL
Materials delivery
Thermal Sand 3-Jun-23 29-Sep-23
110mm with 7-29mm sub duct ICT Conduits 15-Jul-23 28-Sep-23
Construction at Road-01 (MV Cable at Right side Shoulder 1+860 to 2+360)
Pulling of 3Cx400 mm² XLPE Aluminum Cable 33 kv and Splicing 14-Sep-23 16-Sep-23
Installation of HDPE Duct For Fiber Optic Cable 16-Sep-23 17-Sep-23
Testing and splicing for Installed Cables 18-Sep-23 18-Sep-23
2nd Layer Thermal sand bedding above Cables 18-Sep-23 19-Sep-23
Backfilling up to subgrade first layer level and compaction 20-Sep-23 21-Sep-23
Construction at Road-01 (MV Cable at Right side Shoulder 1+360 to 1+860)

Installation of HDPE Duct For Fiber Optic Cable 20-Sep-23 21-Sep-23


Testing and splicing for Installed Cables 23-Sep-23 23-Sep-23
2nd Layer Thermal sand bedding above Cables 23-Sep-23 24-Sep-23
Backfilling up to subgrade first layer level and compaction 25-Sep-23 26-Sep-23
Construction at Road-01 (MV Cable at right side Shoulder 0+860 to 2+320)
Trenches Excavation for MV Cables 19-Sep-23 21-Sep-23
Bedding Preparation for MV Cables 23-Sep-23 24-Sep-23
Pulling of 3Cx400 mm² XLPE Aluminum Cable 33 kv and Splicing 24-Sep-23 25-Sep-23
Installation of HDPE Duct For Fiber Optic Cable 26-Sep-23 27-Sep-23
Testing and splicing for Installed Cables 28-Sep-23 28-Sep-23
Construction at Road-01 (MV Cable at right side carriage way 1+320 to 1+820)
Backfilling up to subgrade first layer level and compaction 2-Sep-23 4-Sep-23
Construction at Road-03 (MV Cable at carriage way 0+000 to 0+500)
Pulling of 3Cx400 mm² XLPE Aluminum Cable 33 kv and Splicing 2-Sep-23 3-Sep-23
Installation of HDPE Duct For Fiber Optic Cable 4-Sep-23 5-Sep-23
Testing and splicing for Installed Cables 6-Sep-23 7-Sep-23
2nd Layer Thermal sand bedding above Cables 7-Sep-23 9-Sep-23
Backfilling up to subgrade first layer level and compaction 10-Sep-23 11-Sep-23
Construction at Road-03 (MV Cable at Right side carriage way 0+500 to 1+000)
Trenches Excavation for MV Cables 31-Aug-23 3-Sep-23
Bedding Preparation for MV Cables 9-Sep-23 10-Sep-23
Pulling of 3Cx400 mm² XLPE Aluminum Cable 33 kv and Splicing 10-Sep-23 11-Sep-23
Installation of HDPE Duct For Fiber Optic Cable 11-Sep-23 12-Sep-23
Testing and splicing for Installed Cables 13-Sep-23 13-Sep-23
2nd Layer Thermal sand bedding above Cables 13-Sep-23 14-Sep-23
Backfilling up to subgrade first layer level and compaction 16-Sep-23 17-Sep-23
Construction at Road-03 (MV Cable at Left Shoulder 1+050 to 1+550)
Trenches Excavation for MV Cables 31-Aug-23 2-Sep-23
Bedding Preparation for MV Cables 2-Sep-23 2-Sep-23
Pulling of 3Cx400 mm² XLPE Aluminum Cable 33 kv and Splicing 2-Sep-23 3-Sep-23
Installation of HDPE Duct For Fiber Optic Cable 4-Sep-23 5-Sep-23
Testing and splicing for Installed Cables 6-Sep-23 7-Sep-23
2nd Layer Thermal sand bedding above Cables 9-Sep-23 10-Sep-23
Backfilling up to subgrade first layer level and compaction 11-Sep-23 12-Sep-23
Construction at Road-03 (MV Cable at Right side Shoulder 0+000 to 0+500)
Trenches Excavation for MV Cables 5-Sep-23 7-Sep-23
Bedding Preparation for MV Cables 7-Sep-23 9-Sep-23
Pulling of 3Cx400 mm² XLPE Aluminum Cable 33 kv and Splicing 10-Sep-23 11-Sep-23
Page 1 of 7
Sept~2023
Project Name : Triple bay Primary Infrastructure Development AMAALA SA SU M TU W TH FR SA SU M TU W TH FR SA SU M TU W TH FR SA SU M TU W TH FR
C
el Report Type : 3 Weeks look ahead (Infra)

10-Sep-23
11-Sep-23
12-Sep-23
13-Sep-23
14-Sep-23
15-Sep-23
16-Sep-23
17-Sep-23
18-Sep-23
19-Sep-23
20-Sep-23
21-Sep-23
22-Sep-23
23-Sep-23
24-Sep-23
25-Sep-23
26-Sep-23
27-Sep-23
28-Sep-23
29-Sep-23
2-Sep-23
3-Sep-23
4-Sep-23
5-Sep-23
6-Sep-23
7-Sep-23
8-Sep-23
9-Sep-23
ls Data Date : 09-Sept-2023
I5
T
hi Activity Name D
Start Finish
A
Installation of HDPE Duct For Fiber Optic Cable 12-Sep-23 13-Sep-23
Testing and splicing for Installed Cables 14-Sep-23 16-Sep-23
2nd Layer Thermal sand bedding above Cables 16-Sep-23 17-Sep-23
Backfilling up to subgrade first layer level and compaction 18-Sep-23 19-Sep-23
Construction at Road-01 (MV Cable at Right side carriage way 1+000 to 1+500)
Trenches Excavation for MV Cables 10-Sep-23 12-Sep-23
Bedding Preparation for MV Cables 12-Sep-23 13-Sep-23
Pulling of 3Cx400 mm² XLPE Aluminum Cable 33 kv and Splicing 13-Sep-23 14-Sep-23
Installation of HDPE Duct For Fiber Optic Cable 16-Sep-23 17-Sep-23
Testing and splicing for Installed Cables 18-Sep-23 18-Sep-23
2nd Layer Thermal sand bedding above Cables 18-Sep-23 19-Sep-23
Backfilling up to subgrade first layer level and compaction 20-Sep-23 21-Sep-23
Construction at Road-02 (MV Cable at carriage way 6+000 to 6+500)
Trenches Excavation for MV Cables 23-Sep-23 25-Sep-23
Bedding Preparation for MV Cables 25-Sep-23 26-Sep-23
Pulling of 3Cx400 mm² XLPE Aluminum Cable 33 kv and Splicing 27-Sep-23 28-Sep-23
Construction at Road-01 (MV Cable at right side Shoulder 1+360 to 1+860)
Trenches Excavation for MV Cables 6-Sep-23 9-Sep-23
Bedding Preparation for MV Cables 9-Sep-23 10-Sep-23
Pulling of 3Cx400 mm² XLPE Aluminum Cable 33 kv and Splicing 10-Sep-23 11-Sep-23
Installation of HDPE Duct For Fiber Optic Cable 11-Sep-23 12-Sep-23
Testing and splicing for Installed Cables 13-Sep-23 14-Sep-23
2nd Layer Thermal sand bedding above Cables 16-Sep-23 17-Sep-23
Backfilling up to subgrade first layer level and compaction 18-Sep-23 19-Sep-23
Construction at Road-01 (MV Cable at right side Shoulder 1+860 to 2+360)
Trenches Excavation for MV Cables 10-Sep-23 12-Sep-23
Bedding Preparation for MV Cables 13-Sep-23 14-Sep-23
Pulling of 3Cx400 mm² XLPE Aluminum Cable 33 kv and Splicing 16-Sep-23 17-Sep-23
Installation of HDPE Duct For Fiber Optic Cable 18-Sep-23 19-Sep-23
Testing and splicing for Installed Cables 20-Sep-23 21-Sep-23
2nd Layer Thermal sand bedding above Cables 23-Sep-23 24-Sep-23
Backfilling up to subgrade first layer level and compaction 25-Sep-23 26-Sep-23
Construction at Road-10 (MV Cable at carriage way 1+700 to 2+200)
Trenches Excavation for MV Cables 7-Sep-23 10-Sep-23
Bedding Preparation for MV Cables 11-Sep-23 12-Sep-23
Pulling of 3Cx400 mm² XLPE Aluminum Cable 33 kv and Splicing 13-Sep-23 14-Sep-23
Installation of HDPE Duct For Fiber Optic Cable 16-Sep-23 17-Sep-23
Testing and splicing for Installed Cables 17-Sep-23 18-Sep-23
2nd Layer Thermal sand bedding above Cables 18-Sep-23 19-Sep-23
Backfilling up to subgrade first layer level and compaction 20-Sep-23 21-Sep-23
ICT
Construction at Left side Road-01 (1+000 to 2+000)
Trenches Excavation for ICT duct along with secondary irrigation trench 31-Aug-23 3-Sep-23
Compaction and leveling trench 4-Sep-23 6-Sep-23
Installation of ICT CD duct 7-Sep-23 10-Sep-23
Soft sand sorounding 11-Sep-23 12-Sep-23
1st Layer backfilling 13-Sep-23 14-Sep-23
2nd Layer backfilling with warrning tape 16-Sep-23 17-Sep-23
Construction at Right side Road-01 (1+000 to 2+000)
Trenches Excavation for ICT duct along with secondary irrigation trench 4-Sep-23 7-Sep-23
Compaction and leveling trench 7-Sep-23 10-Sep-23
Page 2 of 7
Sept~2023
Project Name : Triple bay Primary Infrastructure Development AMAALA SA SU M TU W TH FR SA SU M TU W TH FR SA SU M TU W TH FR SA SU M TU W TH FR
C
el Report Type : 3 Weeks look ahead (Infra)

10-Sep-23
11-Sep-23
12-Sep-23
13-Sep-23
14-Sep-23
15-Sep-23
16-Sep-23
17-Sep-23
18-Sep-23
19-Sep-23
20-Sep-23
21-Sep-23
22-Sep-23
23-Sep-23
24-Sep-23
25-Sep-23
26-Sep-23
27-Sep-23
28-Sep-23
29-Sep-23
2-Sep-23
3-Sep-23
4-Sep-23
5-Sep-23
6-Sep-23
7-Sep-23
8-Sep-23
9-Sep-23
ls Data Date : 09-Sept-2023
I5
T
hi Activity Name D
Start Finish
A
Installation of ICT CD duct 11-Sep-23 12-Sep-23
Soft sand sorounding 13-Sep-23 14-Sep-23
1st Layer backfilling 16-Sep-23 17-Sep-23
2nd Layer backfilling with warrning tape 18-Sep-23 19-Sep-23
Construction at Road-02 (1+000 to 2+000)
Installation of ICT CD duct 2-Sep-23 4-Sep-23
Soft sand sorounding 4-Sep-23 6-Sep-23
1st Layer backfilling 7-Sep-23 10-Sep-23
2nd Layer backfilling with warrning tape 11-Sep-23 13-Sep-23
Construction at Road-02 (2+000 to 3+000)
Compaction and leveling trench 23-Aug-23 24-Aug-23
Installation of ICT CD duct 2-Sep-23 4-Sep-23
Soft sand sorounding 4-Sep-23 6-Sep-23
1st Layer backfilling 7-Sep-23 10-Sep-23
2nd Layer backfilling with warrning tape 11-Sep-23 13-Sep-23
Construction at Road-02 (3+000 to 4+500)
Soft sand sorounding 12-Sep-23 13-Sep-23
1st Layer backfilling 14-Sep-23 16-Sep-23
2nd Layer backfilling 17-Sep-23 18-Sep-23
Construction at Road-02 (4+500 to 6+000)
Installation of ICT CD duct 13-Sep-23 14-Sep-23
Soft sand sorounding 16-Sep-23 17-Sep-23
1st Layer backfilling 18-Sep-23 19-Sep-23
2nd Layer backfilling 20-Sep-23 21-Sep-23
Construction at Road-10 (0+000 to 1+000)
Trenches Excavation for ICT duct along 16-Sep-23 17-Sep-23
Compaction and leveling trench 18-Sep-23 19-Sep-23
Installation of ICT CD duct 20-Sep-23 21-Sep-23
Soft sand sorounding 23-Sep-23 24-Sep-23
1st Layer backfilling 25-Sep-23 26-Sep-23
2nd Layer backfilling 27-Sep-23 28-Sep-23
Road crossing ducts at Road-2 ( 6+000 to 6+500)
LV Ducts Excavation 12-Sep-23 14-Sep-23
LV Ducts Lean Concrete 16-Sep-23 17-Sep-23
LV Ducts installation 18-Sep-23 19-Sep-23
LV Ducts Backfilling 20-Sep-23 21-Sep-23
ICT Ducts Excavation 12-Sep-23 14-Sep-23
ICT Ducts Form work and pipe installation 16-Sep-23 17-Sep-23
ICT Ducts Concrete 18-Sep-23 19-Sep-23
ICT Ducts Bitumen and Backfilling 20-Sep-23 21-Sep-23
MV Ducts Excavation 12-Sep-23 14-Sep-23
MV Ducts Lean Concrete 16-Sep-23 17-Sep-23
MV Ducts installation 18-Sep-23 19-Sep-23
MV Ducts Backfilling 20-Sep-23 21-Sep-23
Road crossing ducts at Road-10 ( 1+000 to 2+000)
LV Ducts Excavation 10-Sep-23 12-Sep-23
LV Ducts Lean Concrete 12-Sep-23 13-Sep-23
LV Ducts installation 14-Sep-23 16-Sep-23
LV Ducts Backfilling 17-Sep-23 18-Sep-23
ICT Ducts Excavation 10-Sep-23 12-Sep-23
Page 3 of 7
Sept~2023
Project Name : Triple bay Primary Infrastructure Development AMAALA SA SU M TU W TH FR SA SU M TU W TH FR SA SU M TU W TH FR SA SU M TU W TH FR
C
el Report Type : 3 Weeks look ahead (Infra)

10-Sep-23
11-Sep-23
12-Sep-23
13-Sep-23
14-Sep-23
15-Sep-23
16-Sep-23
17-Sep-23
18-Sep-23
19-Sep-23
20-Sep-23
21-Sep-23
22-Sep-23
23-Sep-23
24-Sep-23
25-Sep-23
26-Sep-23
27-Sep-23
28-Sep-23
29-Sep-23
2-Sep-23
3-Sep-23
4-Sep-23
5-Sep-23
6-Sep-23
7-Sep-23
8-Sep-23
9-Sep-23
ls Data Date : 09-Sept-2023
I5
T
hi Activity Name D
Start Finish
A
ICT Ducts Form work and pipe installation 12-Sep-23 13-Sep-23
ICT Ducts Concrete 14-Sep-23 16-Sep-23
ICT Ducts Bitumen and Backfilling 17-Sep-23 18-Sep-23
MV Ducts Excavation 10-Sep-23 12-Sep-23
MV Ducts Lean Concrete 12-Sep-23 13-Sep-23
MV Ducts installation 14-Sep-23 16-Sep-23
MV Ducts Backfilling 17-Sep-23 18-Sep-23
Road crossing ducts at Road-10 ( 0+000 to 1+000)
LV Ducts Excavation 19-Sep-23 21-Sep-23
LV Ducts Lean Concrete 23-Sep-23 24-Sep-23
LV Ducts installation 25-Sep-23 26-Sep-23
LV Ducts Backfilling 27-Sep-23 28-Sep-23
ICT Ducts Excavation 19-Sep-23 21-Sep-23
ICT Ducts Form work and pipe installation 23-Sep-23 24-Sep-23
ICT Ducts Concrete 25-Sep-23 26-Sep-23
ICT Ducts Bitumen and Backfilling 27-Sep-23 28-Sep-23
MV Ducts Excavation 19-Sep-23 21-Sep-23
MV Ducts Lean Concrete 23-Sep-23 24-Sep-23
MV Ducts installation 25-Sep-23 26-Sep-23
MV Ducts Backfilling 27-Sep-23 28-Sep-23
Road crossing ducts at Road-15 ( 0+000 to 1+000)
LV Ducts Excavation 9-Sep-23 11-Sep-23
LV Ducts Lean Concrete 12-Sep-23 14-Sep-23
LV Ducts installation 16-Sep-23 19-Sep-23
LV Ducts Backfilling 20-Sep-23 23-Sep-23
ICT Ducts Excavation 9-Sep-23 11-Sep-23
ICT Ducts Form work and pipe installation 12-Sep-23 14-Sep-23
ICT Ducts Concrete 16-Sep-23 19-Sep-23
ICT Ducts Bitumen and Backfilling 20-Sep-23 23-Sep-23
MV Ducts Excavation 9-Sep-23 11-Sep-23
MV Ducts Lean Concrete 12-Sep-23 14-Sep-23
MV Ducts installation 16-Sep-23 19-Sep-23
MV Ducts Backfilling 20-Sep-23 23-Sep-23
MECHANICAL
Materials Submittals
Technical submission of Air conditioners. 9-Sep-23 22-Sep-23
Technical submission of Ventilation fans. 9-Sep-23 22-Sep-23
ITP and Method Statement
Method of statement submission of Crane Installation. 9-Sep-23 22-Sep-23
Method of statement submission of Flushing and Disinfection of the utilities. 9-Sep-23 22-Sep-23
Method of statement submission of Fire Hydrant. 9-Sep-23 22-Sep-23
Inspection Test Plan submission of Plumbing Sanitary Fixture Installation system. 9-Sep-23 15-Sep-23
Materials delivery
Ongoing receiving of HDPE materials 9-Sep-23 29-Sep-23
Ongoing receiving Sewer manhole bases and rings 9-Sep-23 29-Sep-23
Ongoing receiving materials of GRP pipes 9-Sep-23 29-Sep-23
Shop drawings:
Submission of All network shop drawings R09 9-Sep-23 15-Sep-23
Submission of All network shop drawings R04 9-Sep-23 15-Sep-23
Submission of All network shop drawings R08 16-Sep-23 22-Sep-23
Submission of All network shop drawings R14 16-Sep-23 22-Sep-23
Page 4 of 7
Sept~2023
Project Name : Triple bay Primary Infrastructure Development AMAALA SA SU M TU W TH FR SA SU M TU W TH FR SA SU M TU W TH FR SA SU M TU W TH FR
C
el Report Type : 3 Weeks look ahead (Infra)

10-Sep-23
11-Sep-23
12-Sep-23
13-Sep-23
14-Sep-23
15-Sep-23
16-Sep-23
17-Sep-23
18-Sep-23
19-Sep-23
20-Sep-23
21-Sep-23
22-Sep-23
23-Sep-23
24-Sep-23
25-Sep-23
26-Sep-23
27-Sep-23
28-Sep-23
29-Sep-23
2-Sep-23
3-Sep-23
4-Sep-23
5-Sep-23
6-Sep-23
7-Sep-23
8-Sep-23
9-Sep-23
ls Data Date : 09-Sept-2023
I5
T
hi Activity Name D
Start Finish
A
Construction
Ongoing excavation of gravity sewer lines in R02 9-Sep-23 29-Sep-23
Ongoing Installation of GRP sewer line of R02 9-Sep-23 29-Sep-23
Ongoing Installation of secondary irrigation lines in R02 9-Sep-23 22-Sep-23
Ongoing Excavation of primary irrigation lines in R02 9-Sep-23 29-Sep-23
Ongoing Installation of primary irrigation lines in R02 9-Sep-23 29-Sep-23
Ongoing excavation of Secondary irrigation lines in R01 9-Sep-23 22-Sep-23
Ongoing Installation of secondary irrigation lines in R01 9-Sep-23 29-Sep-23
Excavation of gravity GRP sewer lines in R03 9-Sep-23 29-Sep-23
Installation of gravity GRP sewer line of R03 9-Sep-23 29-Sep-23
Ongoing Installation of secondary irrigation R03 9-Sep-23 22-Sep-23
Ongoing Excavation of primary irrigation lines in R03 9-Sep-23 29-Sep-23
Ongoing Installation of primary irrigation lines in R03 9-Sep-23 29-Sep-23
Ongoing Excavation of Potable water network of R10 9-Sep-23 29-Sep-23
Ongoing Installation of Potable water network lines of R10 9-Sep-23 29-Sep-23
Ongoing Excavation of Secondary irrigation network of R10 9-Sep-23 29-Sep-23
Ongoing Installation of Secondary irrigation network of R10 9-Sep-23 29-Sep-23
Ongoing Excavation of primary irrigation lines in R10 9-Sep-23 29-Sep-23
Ongoing Installation of primary irrigation lines in R10 9-Sep-23 29-Sep-23
Excavation of gravity sewer lines in R09 9-Sep-23 29-Sep-23
Installation of GRP sewer line of R09 9-Sep-23 29-Sep-23
Excavation of Potable water network of R09 9-Sep-23 29-Sep-23
Installation of Potable water network lines of R09 9-Sep-23 29-Sep-23
Excavation of Secondary irrigation network of R09 9-Sep-23 29-Sep-23
Installation of Secondary irrigation network of R09 9-Sep-23 29-Sep-23
Excavation of primary irrigation lines in R09 9-Sep-23 29-Sep-23
Installation of primary irrigation lines in R09 9-Sep-23 29-Sep-23
PUPM STATION
Construction
PIPS water proofing for wall 19-Aug-23 12-Sep-23
PIPS back filling for wall 27-Aug-23 20-Sep-23
PIPS MEP Building surface prepartion 21-Sep-23 22-Sep-23
sips 1 wall Pump room and water tank steel fixing 22-Jul-23 9-Sep-23
sips 1 wall Pump room and water tank Form work 10-Sep-23 24-Sep-23
SIPS 2 Pump room surface preparation 20-Aug-23 9-Sep-23
SIPS 2 Pump room water proofing 26-Aug-23 13-Sep-23
SIPS 2 Pump room back filling 28-Aug-23 17-Sep-23
SIPS 2 Pump room top slab form work 5-Sep-23 15-Sep-23
SIPS 2 Pump room top slab steel fixing 16-Sep-23 26-Sep-23
SIPS 2 Pump room top slab concrete pouring 26-Sep-23 28-Sep-23
SIPS 2 MEP Building surface prepartion 5-Sep-23 6-Sep-23
SIPS 2 MEP Building termite control 7-Sep-23 8-Sep-23
SIPS 2 MEP Building Lean concrete 7-Sep-23 8-Sep-23
SIPS 2 MEP Building water proofing 9-Sep-23 12-Sep-23
SIPS 2 MEP Building screed 13-Sep-23 14-Sep-23
SIPS 2 MEP Building Raft steel fixing 15-Sep-23 19-Sep-23
SIPS 2 MEP Building Raft Form work and concrete pouring 20-Sep-23 24-Sep-23
SIPS 3 Pump room and water tank wall steel fixing 13-Aug-23 12-Sep-23
SIPS 3 Pump room and water tank wall form work 28-Aug-23 17-Sep-23
SIPS 3 Pump room and water tank wall concrete pouring and de shuttering 2-Sep-23 22-Sep-23
SIPS 4 Pump room and water tank wall steel fixing 20-Aug-23 19-Sep-23
Page 5 of 7
Sept~2023
Project Name : Triple bay Primary Infrastructure Development AMAALA SA SU M TU W TH FR SA SU M TU W TH FR SA SU M TU W TH FR SA SU M TU W TH FR
C
el Report Type : 3 Weeks look ahead (Infra)

10-Sep-23
11-Sep-23
12-Sep-23
13-Sep-23
14-Sep-23
15-Sep-23
16-Sep-23
17-Sep-23
18-Sep-23
19-Sep-23
20-Sep-23
21-Sep-23
22-Sep-23
23-Sep-23
24-Sep-23
25-Sep-23
26-Sep-23
27-Sep-23
28-Sep-23
29-Sep-23
2-Sep-23
3-Sep-23
4-Sep-23
5-Sep-23
6-Sep-23
7-Sep-23
8-Sep-23
9-Sep-23
ls Data Date : 09-Sept-2023
I5
T
hi Activity Name D
Start Finish
A
SIPS 4 Pump room and water tank wall form work 25-Aug-23 24-Sep-23
SIPS 4 Pump room and water tank wall concrete pouring and de shuttering 30-Aug-23 29-Sep-23
SIPS 5 Pump room wall external surface preparation 1-Sep-23 2-Sep-23
SIPS 5 Pump room wall water proofing 3-Sep-23 7-Sep-23
SIPS 5 Pump room wall backfilling 8-Sep-23 13-Sep-23
SIPS 5 Pump room and water tank wall steel fixing 1-Sep-23 11-Sep-23
SIPS 5 Pump room and water tank wall form work 6-Sep-23 16-Sep-23
SIPS 5 Pump room and water tank wall concrete pouring and de shuttering 11-Sep-23 21-Sep-23
SIPS 6 Pump room top slab form work 28-Aug-23 7-Sep-23
SIPS 6 Pump room top slab steel fixing 8-Sep-23 18-Sep-23
SIPS 6 Pump room top slab concrete pouring 18-Sep-23 20-Sep-23
SIPS 6 Pump room back filling 29-Aug-23 8-Sep-23
SIPS 6 MEP Building surface prepartion 9-Sep-23 10-Sep-23
SIPS 6 MEP Building termite control 11-Sep-23 12-Sep-23
SIPS 6 MEP Building Lean concrete 11-Sep-23 12-Sep-23
SIPS 6 MEP Building water proofing 13-Sep-23 16-Sep-23
SIPS 6 MEP Building screed 17-Sep-23 18-Sep-23
SIPS 6 MEP Building Raft steel fixing 19-Sep-23 23-Sep-23
PWPS Pump room and water Tank wall concrete pouring and DE shuttering 27-Aug-23 7-Sep-23
PWPS Pump room and water Tank Formwork topslab 8-Sep-23 15-Sep-23
PWPS Pump room and water Tank steel topslab 15-Sep-23 19-Sep-23
PWPS Pump room and water Tank concrete topslab 19-Sep-23 20-Sep-23
PWPS Pump room surface preparation 21-Sep-23 1-Oct-23
SPS 4 Wet well & Screen till bottom water proofing 9-Aug-23 4-Sep-23
SPS 4 Back filling for Screen & wet well 5-Sep-23 10-Sep-23
SPS 4 MEP Building surface prepartion 11-Sep-23 12-Sep-23
SPS 4 MEP Building termite control 13-Sep-23 14-Sep-23
SPS 4 MEP Building Lean concrete 13-Sep-23 14-Sep-23
SPS 4 MEP Building water proofing 15-Sep-23 18-Sep-23
SPS 4 MEP Building screed 19-Sep-23 20-Sep-23
SPS 4 MEP Building Raft steel fixing 21-Sep-23 25-Sep-23
Sps 3 Dewatering operation 17-Jul-23 15-Oct-23
SPS 3 Wet well and screen wall steel fixing 2-Sep-23 12-Sep-23
SPS 3 Wet well and screen wall form work 13-Sep-23 21-Sep-23
SPS 3 Wet well and screen wall concrete pouring 22-Sep-23 23-Sep-23
Sps 2 Dewatering operation 8-Aug-23 6-Nov-23
SPS 2 Back filling till Screen bottom raft 4-Sep-23 9-Sep-23
SPS 2 Wet well and screen wall surface preparation 9-Sep-23 10-Sep-23
SPS 2 Wet well and screen termite 9-Sep-23 10-Sep-23
SPS 2 Wet well and screen wall water proofing 11-Sep-23 13-Sep-23
SPS 2 Wet well and screen wall Lean concrete 14-Sep-23 16-Sep-23
SPS 2 Wet well and screen raft steel fixing 16-Sep-23 18-Sep-23
SPS 2 Wet well and screen raft form work 19-Sep-23 21-Sep-23
SPS 2 Wet well and screen raft concrete pouring 21-Sep-23 22-Sep-23
Sps 1 Dewatering operation 23-Aug-23 21-Nov-23
SPS 1 wet well raft steel fixing 2-Sep-23 4-Sep-23
SPS 1 Wet well raft form work 5-Sep-23 6-Sep-23
SPS 1 Wet well raft concrete pouring 7-Sep-23 9-Sep-23
SPS 1 Back filling till Screen bottom raft 10-Sep-23 15-Sep-23
SPS 1 Wet well and screen wall surface preparation 15-Sep-23 16-Sep-23
SPS 1 Wet well and screen termite 15-Sep-23 16-Sep-23
Page 6 of 7
Sept~2023
Project Name : Triple bay Primary Infrastructure Development AMAALA SA SU M TU W TH FR SA SU M TU W TH FR SA SU M TU W TH FR SA SU M TU W TH FR
C
el Report Type : 3 Weeks look ahead (Infra)

10-Sep-23
11-Sep-23
12-Sep-23
13-Sep-23
14-Sep-23
15-Sep-23
16-Sep-23
17-Sep-23
18-Sep-23
19-Sep-23
20-Sep-23
21-Sep-23
22-Sep-23
23-Sep-23
24-Sep-23
25-Sep-23
26-Sep-23
27-Sep-23
28-Sep-23
29-Sep-23
2-Sep-23
3-Sep-23
4-Sep-23
5-Sep-23
6-Sep-23
7-Sep-23
8-Sep-23
9-Sep-23
ls Data Date : 09-Sept-2023
I5
T
hi Activity Name D
Start Finish
A
SPS 1 Wet well and screen wall water proofing 17-Sep-23 19-Sep-23
SPS 1 Wet well and screen wall Lean concrete 20-Sep-23 22-Sep-23
SPS 1 Wet well and screen raft steel fixing 22-Sep-23 24-Sep-23