Initial Project Implementation Plan 11-09-22 (RPB Comments)
Initial Project Implementation Plan 11-09-22 (RPB Comments)
No. of From To
working days
Determine and collect needed 12 days 9/12 9/24 Needs cooperation of MAIF team
documents
Initial Desk review
Review documents and develop
summaries
Identify the tools needed for the 5 days 9/25 9/30 Need consult with int. team
assessment
Tools design and
Design tools & Identify officials to be
validation
interviewed
Analyze qualitative & quantitative 10 days 10/26 11/5 Translation is needed into English.
Data analysis data and produce & organize results Inputs needed from Int. team
Develop conclusions Conduct meetings with the team 5 days 11/6 11/11 Close collaboration between int. +
for the institutional
Page 2 of 4
Discuss results and Hold one day workshop with the 5 days 11/12 11/17 Splitting results into two parts is
conclusions with the leaders of agriculture sector needed for presentation purpose
MAIF and modify
Hold workshop with the leaders of
them based on their
fisheries sector
feedback
Write assessment Develop document. Clarify 12 days 11/18 11/30 EB team provides inputs while the
document (note: to outstanding issues as necessary in int. team will develop the final
proceed in parallel consultation with MAIF document
with developing the
capacity building
framework below)
Develop the Identify key issues and priorities for 12 days 11/18 11/30 EB team provides inputs while the
capacity building the capacity building framework int. team will develop the final
framework (note: to document
proceed in parallel
with writing the
assessment
document above)
Develop capacity Hold one day workshop with the 2 days 12/4 12/5 Consultations to be conducted with
building framework leaders of agriculture sector the MAIF team to get related views
and concerns
Hold workshop with the leaders of
fisheries sector
Page 4 of 4
Write CBF document Develop document 10 days 12/6 12/16 Translation is needed into English
after concluding documents.
Submit final Order and document all deliverables 5 days 12/17 12/22 To be made in full and close
deliverables cooperation, collaboration and
consultation with int. team
Project closing Write and submit the final project 14 days 12/23 1/5 Preferably through a final WS to be
report including all managerial, headed by the MAIF Minister
technical and financial activities.