ID Task Task Name Duration Start Finish Resource Names November 2021 December 2021 January 2022

Mode 02 07 12 17 22 27 02 07 12 17 22 27 01 06 11 16 21 26
0 MUNDRA INTERIOR PROJECT 61 days Wed 10-11-21 Sun 09-01-22
1 Glass door & partition installation work 13 days Wed 10-11-21 Mon 22-11-21 main
main entrance area Drawing pending and rate finalisation is entrance
working on area Drawing pending and rate finalisation is working on
2 Stone work 31 days Wed 10-11-21 Fri 10-12-21
3 Male & Female toilet tiles reparing work 2 days Wed 10-11-21 Thu 11-11-21
4 Male & Female toilet granite work on counter
3 days Fri 12-11-21 Sun 14-11-21
5 Granite work on courtyard 3 days Mon 15-11-21 Wed 17-11-21
6 Pantry tiles cladding work 2 days Thu 18-11-21 Fri 19-11-21 Tille finalization is pending Tille finalization is pending
7 Windows cill correction in pantry 2 days Sat 20-11-21 Sun 21-11-21
8 Tiles skirting work 2 days Mon 22-11-21 Tue 23-11-21
9 FF kitchen tiles 3 days Wed 24-11-21 Fri 26-11-21 GFC Drwawing is pending GFC Drwawing is pending
10 Servant and toilet tiles 3 days Sat 27-11-21 Mon 29-11-21 GFC Drwawing is pending GFC Drwawing is pending
11 Exterior Flooring work 8 days Fri 03-12-21 Fri 10-12-21 GFC Drwawing is pending GFC Drwawing is pending
12 Sanitary work 16 days Mon 15-11-21 Tue 30-11-21
13 GF toilets fittings 2 days Mon 15-11-21 Tue 16-11-21
14 FF toilets fittings 1 day Tue 30-11-21 Tue 30-11-21 Drawing is pending Drawing is pending
15 kitchen and pantary fitting 2 days Thu 25-11-21 Fri 26-11-21 pantry fitting
pantry fitting after installation of modular kitchen & FF kitchen drawing after installation of modular kitchen & FF kitchen drawing is pending
is pending
16 Exterior plumbing work 6 days Sat 27-11-21 Thu 02-12-21 Exterior plumbing GFc drawing is pending Exterior plumbing GFc drawing is pending
17 Carpentry work 34 days Wed 10-11-21 Mon 13-12-21
18 furnitures in pantry 4 days Sun 21-11-21 Wed 24-11-21 shop drawing is not approved shop drawing is not approved
19 wooden framing on AC area 2 days Wed 10-11-21 Thu 11-11-21
20 GF flush door installation 3 days Fri 12-11-21 Sun 14-11-21
21 FF flush door installation 3 days Mon 15-11-21 Wed 17-11-21 kitchen and Servant floor is pending kitchen and Servant floor is pending
22 Cupboard lock & handle work 3 days Thu 18-11-21 Sat 20-11-21 Handles not finalise Handles not finalise
23 Mian Entrance Door work 7 days Sun 21-11-21 Sat 27-11-21 GFC Drwawing is pending GFC Drwawing is pending
24 Bison fixing work on Façade 2 days Sun 21-11-21 Mon 22-11-21
25 Modular Furniture Installation 3 days Sat 11-12-21 Mon 13-12-21 GFC Drwawing is pending GFC Drwawing is pending
26 FF kitchen counter 12 days Sat 27-11-21 Wed 08-12-21 Drawing is pending Drawing is pending
27 Louvers work 4 days Tue 23-11-21 Fri 26-11-21
28 ceiling work 4 days Fri 12-11-21 Mon 15-11-21 main entrance area Drawing pending main entrance area Drawing pending
29 Elecrical work 9 days Thu 18-11-21 Fri 26-11-21
30 wiring in exterior area 2 days Thu 18-11-21 Fri 19-11-21 GFC Drwawing is pending GFC Drwawing is pending
31 FF wiring 2 days Sat 20-11-21 Sun 21-11-21 staircase lobby and tarrace elctrical drawing pending staircase lobby and tarrace elctrical drawing pending
32 DB installation 3 days Mon 22-11-21 Wed 24-11-21 DB location is not finalise DB location is not finalise
33 switch,soket and light fixing 2 days Thu 25-11-21 Fri 26-11-21 light fixture is not finalise light fixture is not finalise
34 Staircase railling work 2 days Mon 15-11-21 Tue 16-11-21 Details drawing is pending Details drawing is pending
35 pop work 4 days Wed 24-11-21 Sat 27-11-21
36 Pop Groove and repairing work 4 days Wed 24-11-21 Sat 27-11-21
37 Paint work 38 days Fri 03-12-21 Sun 09-01-22
38 first coat(internal) 10 days Sun 28-11-21 Tue 07-12-21 colour scheme pending colour scheme pending
39 second coat(internal) 10 days Fri 31-12-21 Sun 09-01-22 colour scheme pending colour scheme pending
40 external paint 12 days Sun 19-12-21 Thu 30-12-21 colour scheme pending colour scheme pending
41 Aluminium window 8 days Sat 11-12-21 Sat 18-12-21 window shop drawing approval is pending window shop drawing approval is pending
42 AC installation work 4 days Sun 19-12-21 Wed 22-12-21 AC modal is not finalise AC modal is not finalise
43 IT work 35 days Thu 11-11-21 Wed 15-12-21
44 CCTV camera(exterior) 3 days Thu 11-11-21 Sat 13-11-21 server room drawing is pending server room drawing is pending
45 CCTV camera(interior) 3 days Tue 16-11-21 Thu 18-11-21 server room drawing is pending server room drawing is pending
46 LAN/VOICE work 2 days Tue 14-12-21 Wed 15-12-21
Project: MUNDRA INTERIOR PROJ Task start Dependency Start
Date: Sat 29-07-23

Page 1