Date: 30.11.2021

Manpower and Equipment


Manpower
3 Engineers 1 Supervisors
5 fitters & Technicians 16 Helpers
Equipment (Plant)
NA

1. Current Activities

- Continue cable pulling of MV and LV cables from substation no. [410] to Urea Plant.
- Official electrical Punch clearing for Overhead Crane no. [3121] in NA plant.
- Continue installation work of secondary cable tray & conduits in unit no [8310].
- Continue installation of lighting fixtures & Conduits above deck level & stairs of [Cooling tower] as agreed with NCIC (Eng. Ayman).
- Continue official inspection of lighting fixtures & conduit routes in unit no. [8352] [Postponed for tomorrow].
- Continue installation work of PVC conduit routes & LCS above deck level of [Cooling tower] unit no. [8300].
- Continue cable pulling & dressing in main/Secondary cable tray route of pipe rack no. [1501 &1040].
2. Upcoming Activities

- Continue Lighting installation & termination works in Utility area.


- Continue secondary cable trays installation works in Ammonia plant.
- Preparing to start cable pulling for unit no. [1020] in Compressors house.
- Preparation to start installation work of heat tracing system in all areas.
- Continue Earthing installation work activity in [Utility & Ammonia plant].
- Continue cable pulling activity in [utility & Ammonia plant].
- Continue installation work of PVC conduit routes & LCS above deck level of [Cooling tower] unit no. [8300].

3. Area of concern

- Missing terminal lugs different sizes for a lot of safety switches & motors [ supplied by Petrojet].