Professional Documents
Culture Documents
Daily Report 2021 - 12 - 05 Ahmed Samir
Daily Report 2021 - 12 - 05 Ahmed Samir
Daily Report 2021 - 12 - 05 Ahmed Samir
Date: 05.12.2021
1. Current Activities
- Continue cable pulling of MV and LV cables from substation no. [410] to Urea Plant.
- Continue installation work of secondary cable tray & conduits in unit no [1020].
- Continue installation of lighting fixtures & Conduits above deck level & stairs of [Cooling tower] as agreed with NCIC (Eng. Ayman).
- Continue cable pulling & dressing in main/Secondary cable tray route of pipe rack no. [1501 &1040].
- Start modification work of LCS & safety switches locations in unit no. [3130].
2. Upcoming Activities
3. Area of concern
- Missing terminal lugs different sizes for a lot of safety switches & motors [ supplied by Petrojet].